Management Accounting Exam Practice Kit
Management Accounting Exam Practice Kit
Tufal Choudhury
[email protected]
077 9090 4122
1|Page
P1 MANAGEMENT ACCOUNTING
Syllabus overview
P1 stresses the importance of costs and the drivers of costs in the production, analysis and
use of information for decision making in organisations. The time focus of P1 is the short
term. It covers budgeting as a means of short-term planning to execute the strategy of
organisations. In addition it provides competencies on how to analyse information on
costs, volumes and prices to take short-term decisions on products and services and to
develop an understanding on the impact of risk to these decisions. P1 provides the
foundation for cost management and the long-term decisions covered in P2.
2|Page
CONTENTS
3 Budgeting 43 215
3|Page
4|Page
Chapter 1 - Classification of costs and maths for budgets
1.1
The table below shows the output, total costs and the cost inflation index for a business in
two periods. Cost behaviour patterns were the same in both periods.
The variable cost per unit at an inflation index of 1.08 will be:
A $1.56
B $1.45
C $1.50
D $1.62
The following data are given for sub-questions 1.2 and 1.3 below
A company is estimating its costs based on past information. The total costs incurred by
the company at different levels of output were as follows:
The company uses the high-low method to separate total costs into their fixed and
variable elements. Ignore inflation.
1.2
A $2,870,000
B $3,050,000
C $3,064,211
D $3,080,857
5|Page
1.3
The company has now established that there is a stepped increase in fixed costs of
$30,000 when output reaches 180,000 units.
The estimate of total costs for an output of 175,000 units using the additional information
is:
A $2,645,000
B $2,275,000
C $2,615,000
D $2,630,000
1.4
The budgeted costs for a company at different levels of output are as follows:
The variable cost per unit will reduce by 5% for output levels above 40,000 units. The
reduced cost per unit will apply to all units. Fixed costs will increase by $30,000 for
output levels above 38,000 units.
Calculate the budgeted total costs for an output level of 45,000 units.
1.5
The following extract is taken from the production cost budget of L plc:
The budget cost allowance for an output of 4,000 units would be:
A £17,600
B £18,514
C £20,400
D £24,000
6|Page
1.6
XYZ Ltd is preparing the production budget for the next period. The total costs of
production are a semi-variable cost. The following cost information has been collected in
connection with production:
The estimated total production costs for a production volume of 5,750 units is nearest to
A £29,200
B £30,000
C £31,500
D £32,500
1.7
The budgeted total costs for two levels of output are as shown below:
Within this range of output it is known that the variable cost per unit is constant but fixed
costs rise by £10,000 when output exceeds 35,000 units.
7|Page
1.8
The data in the table below has been extracted from a company’s cost accounting records.
It shows the total costs and the inflation index for the periods in which the costs were
incurred. Cost behaviour patterns are the same in both periods.
The variable cost per unit, to the nearest $0.01, at an inflation index of 1.06 is:
A $1.45
B $1.59
C $1.53
D $1.50
1.9
A company has recorded the following activity levels and distribution costs for the
previous three quarters:
What will be the distribution costs in quarter 4 if the expected level of activity is 85,000
units? You should assume that the cost behaviour pattern in the previous three quarters
will continue in quarter 4.
A $252,500
B $255,000
C $254,303
D $253,963
8|Page
1.10
A £16,500
B £12,000
C £13.450
D £9,500
1.11
A Plc had the following average cost data for two activity levels:
A £31,000
B £32,775
C £24,000
D £10,000
1.12
Using the available data, predict what the cost would be of cleaning 70 bedrooms within
a hotel?
Bedrooms cleaned 20 35 55 75
A £150
B £160
C £165
D £170
9|Page
1.13
South Eastern Railway wants to develop a way of forecasting for the number of
passengers it handles on its railway system; it provides the following information
regarding total costs for two quarters of the year.
The total cost model for South Eastern Railway for the number of passengers in a quarter
of a year would be?
A TC = 1,200,000 + 1.2P
B TC = 1,100,000 + 2.1P
C TC = 1,000,000 + 1.2P
D TC = 1,800,000 + 2.1P
1.14
A £15.00
B £223.05
C £238.00
D £284.06
1.15
Which of the following would best categorise sales commission expenses for an
organisation?
A Fixed cost
B Variable cost
C Functional cost
D Stepped cost
10 | P a g e
1.16
Which of the following would be more likely not to be classified as an indirect labour
cost within an organisation?
1.17
A Plc had the following average cost data for two activity levels:
A £31,000
B £32,775
C £24,000
D £10,000
1.18
Which of the following is the most likely definition for a variable cost?
1.19
A hotel pays cleaners £5 an hour and estimates that it should take 30 minutes to clean a
room but expected idle time would be 20%. Given that 45 rooms were cleaned in a given
day, what would be the estimated cost?
A £112.50
B £135.00
C £140.63
D £160.00
11 | P a g e
1.20
A cost unit is
A A cost containing both fixed and variable components and thus partly affected by
a change in the level of activity
B Expenditure which cannot be economically identified with a specific saleable cost
unit
C Expenditure which can be economically identified with and specifically measured
in respect to a relevant cost object
D A unit of product or service in relation to which costs are ascertained
1.21
A prime cost is
1.22
Which one of the following would not be considered one of the roles of a financial
accountant?
1.23
12 | P a g e
1.24
1.25
Which one of the following would not be the role of a financial accountant?
1.26
Historical in nature
Forward looking
Show the profit or loss for the business
Used for decision making purposes
Prepared for external users
1.27
Historical in nature
Forward looking
Reports on variances against budget
Used for decision making purposes
Prepared for external users
13 | P a g e
1.28
Units Cost
500 $14,000
800 $16,400
1200 $19,600
The budget cost allowance for the production of 1,000 units would be?
1.29
Within a company one purchase ledger clerk needs to be recruited for every 50 supplier
accounts that need management and administration. Which one of the following types of
cost would this be?
A Fixed cost
B Step cost
C Variable cost
D Mixed cost
1.30
Which one of the following types of cost would be factory rent and rates?
1.31
Within a relevant range of output, the fixed cost per unit of a product will normally
14 | P a g e
1.32
1.33
The following information exists about a certain type of cost within a company;
A Fixed cost
B Step cost
C Variable cost
D Mixed cost
15 | P a g e
16 | P a g e
Chapter 2 - Advanced mathematics for budgets
2.1
A company is preparing its annual budget and is estimating the number of units of
Product A that it will sell in each quarter of Year 2. Past experience has shown that the
trend for sales of the product is represented by the following relationship:
y = a + bx where
y = number of sales units in the quarter
a = 10,000 units
b = 3,000 units
x = the quarter number where 1 = quarter 1 of Year 1
Actual sales of Product A in Year 1 were affected by seasonal variations and were as
follows:
Calculate the expected sales of Product A (in units) for each quarter of Year 2, after
adjusting for seasonal variations using the additive model.
2.2
A company provides three different levels of customer service support for one of its
software products.
Note: The total annual fixed costs are budgeted to be $1,000,000. None of these costs are
specific to any type of customer service support.
17 | P a g e
Assuming that the number of customer service support contracts sold are in the
proportion:
A $1,690,000
B $1,695,000
C $1,710,000
D $2,270,000
2.3
S plc produces and sells three products, X, Y and Z. It has contracts to supply products X
and Y, which will utilise all of the specific materials that are available to make these two
products during the next period. The revenue these contracts will generate and the
contribution to sales (c/s) ratios of products X and Y are as follows:
Product X Product Y
Revenue £10 million £20 million
C/S ratio 15% 10%
The total fixed costs of S plc are £5.5 million during the next period and management
have budgeted to earn a profit of £1 million.
Calculate the revenue that needs to be generated by Product Z for S plc to achieve the
budgeted profit.
2.4
A company makes and sells three products, R, S, and T. Extracts from the weekly profit
statements are as follows:
R S T Total
$ $ $ $
Sales 10,000 15,000 20,000 45,000
A would be higher.
B would be lower.
C would remain unchanged.
D cannot be determined without more information.
The following data are given for sub-questions 2.5 and 2.6 below
2.5
Calculate the average contribution to sales ratio of the company based on the sales mix
stated above.
2.6
Calculate the average contribution to sales ratio of the company if the total number of
monthly contracts sold remains the same, but equal numbers of each contract are sold.
2.7
A company provides a number of different services to its customers from a single office.
The fixed costs of the office, including staff costs, are absorbed into the company’s
service costs using an absorption rate of $25 per consulting hour based on a budgeted
activity level of 100,000 hours each period.
Fee income and variable costs are different depending on the services provided, but the
average contribution to sales ratio is 35%. The breakeven fee income each period is
closest to:
A $1,400,000
B $11,500,000
C $875,000
D $7,143,000
19 | P a g e
2.8
A company manufactures three products. Each of these products use the same type of
material but in different quantities. The unit selling prices, cost and profit details are as
follows:
Product X Y Z
$/unit $/unit $/unit
Selling price 23 26 28
Direct materials 6 8 6
Direct labour 8 6 8
Variable overhead 2 3 3
Fixed overhead 4 5 6
Profit 3 4 5
The direct material used on all three products costs $10 per kg. The material available is
expected to be limited to 600 kgs for the next accounting period. The maximum demand
for each of the products during the next accounting period is expected to be as follows:
Required:
Calculate the optimum product mix for the next accounting period.
2.9
A company has budgeted break-even sales revenue of £800,000 and fixed costs of
£320,000 for the next period.
The sales revenue needed to achieve a profit of £50,000 in the period would be
A £850,000
B £925,000
C £1,120,000
D £1,200,000
20 | P a g e
2.10
$000
Revenue 400
Variable costs 240
Fixed costs 100
Profit 60
Assuming that the sales mix does not change, the percentage increase in sales volume
that would be needed to increase the profit to $100,000 is
A 10%
B 15%
C 25%
D 40%
2.11
The overhead costs of RP Limited have been found to be accurately represented by the
formula
y = £10,000 + £0.25x
where y is the monthly cost and x represents the activity level measured as the number of
orders.
Monthly activity levels of orders may be estimated using a combined regression analysis
and time series model:
a = 100,000 + 30b
where a represents the de-seasonalised monthly activity level and b represents the month
number.
Calculate the overhead cost for RP Limited for month 240 to the nearest £1,000.
21 | P a g e
2.12
All three services use the same type of direct labour which is paid at $30 per hour. In a
period when the availability of the direct labour is limited, the most and least profitable
use of the direct labour are:
2.13
Z plc has found that it can estimate future sales using time-series analysis and regression
techniques. The following trend equation has been derived:
y = 25,000 + 6,500x
where:
y is the total sales units per quarter, and
x is the time period reference number.
Z has also derived the following set of seasonal variation index values for each quarter
using a multiplicative (proportional) model:
Quarter 1 70
Quarter 2 90
Quarter 3 150
Quarter 4 90
Using the above model, calculate the forecast for sales units for the third quarter of year
7, assuming that the first quarter of year 1 is time period reference number 1.
22 | P a g e
2.14
If the budgeted fixed costs increase, the gradient of the line plotted on the budgeted
Profit/Volume (P/V) chart will
A increase.
B decrease.
C not change.
D become curvi-linear.
2.15
A company uses time series and regression techniques to forecast future sales. It has
derived a seasonal variation index to use with the multiplicative (proportional) seasonal
variation model. The index values for the first three quarters are as follows:
A -270
B -269
C 110
D 130
2.16
The budgeted profit statement for a company, with all figures expressed as percentages of
revenue, is as follows:
%
Revenue 100
Variable costs 30
Fixed costs 22
Profit 48
After the formulation of the above budget it has now been realised that the sales volume
will only be 60% of that originally forecast. The revised profit, expressed as a percentage
of the revised revenue will be:
A 20%
B 33.3%
C 60%
D 80%
23 | P a g e
2.17
The following details relate to ready meals that are prepared by a food processing
company:
Ready meal K L M
$/meal $/meal $/meal
Selling price 5 3 4.40
Ingredients 2 1 1.30
Variable conversion costs 1.60 0.80 1.85
Fixed conversion costs 0.50 0.30 0.60
Profit 0.90 0.90 0.65
Each of the meals is prepared using a series of processes, one of which involves cooking
the ingredients in a large oven. The availability of cooking time in the oven is limited
and, because each of the meals requires cooking at a different oven temperature, it is not
possible to cook more than one of the meals in the oven at the same time. The fixed
conversion costs are general fixed costs that are not specific to any type of ready meal.
Rank in terms of the profitability of the manufacture of these meals.
2.18
A bakery produces three different sized fruit pies for sale in its shops. The pies all use the
same basic ingredients. Details of the selling prices and unit costs of each pie are as
follows:
Small Medium Large
$ per pie $ per pie $ per pie
Selling price 3.00 5.00 9.00
The fruit used in making the pies is imported and the bakery has been told that the
amount of fruit that they will be able to buy for next week is limited to 300 kgs. The
bakery has established its good name by baking its pies daily using fresh fruit, so it is not
possible to buy the fruit in advance. Determine the mix of pies to be made and sold in
order to maximise the bakery’s contribution for next week.
24 | P a g e
2.19
RF Ltd is about to launch a new product in June 2007. The company has commissioned
some market research to assist in sales forecasting. The resulting research and analysis
established the following equation:
Where:
Calculate the forecast sales volume for each of the months June, July and August 2007
and for that three month period in total.
2.20
A company will forecast its quarterly sales units for a new product by using a formula to
predict the base sales units and then adjusting the figure by a seasonal index.
Quarter 1 105%
Quarter 2 80%
Quarter 3 95%
Quarter 4 120%
A 25%
B 80 units
C 100 units
D 1,156 units
25 | P a g e
2.21
KL has determined from past experience that the following equation provides a reliable
estimate of its future sales volume:
y = 15,000 + 2,200x
KL has also derived the following set of seasonal variation index values for each quarter
using the multiplicative model:
Quarter 1 80
Quarter 2 110
Quarter 3 120
Quarter 4 90
Required:
Calculate the forecast sales units for the third quarter of year 6 using the above model and
assuming that the first quarter of year 1 is time period 1.
The following data are given for sub-questions 2.22 and 2.23
A company is estimating future sales using time-series analysis. The following trend
equation has been derived from actual sales data for Year 1:
y = 22,000 + 800x
The following set of seasonal variation index values has been derived using a
multiplicative model and based on Year 1 actual sales:
Quarter 1 70
Quarter 2 90
Quarter 3 130
Quarter 4 110
26 | P a g e
2.22
Using the above multiplicative time series model, sales for Year 2 Quarter 3 would be
estimated as:
A 35,880 units
B 40,040 units
C 27,600 units
D 27,730 units
2.23
Using an additive time series model, the amount of the seasonal variation for Quarter 2
would be:
A - 2,680
B - 2,360
C + 2,680
D + 2,360
2.24
X Plc sells three products. The budgeted contribution to sales ratio for each product and
the sales mix is as follows:
If the budgeted fixed cost for the period were £345,000, the breakeven sales revenue
would be nearest to
A £907,900
B £893,800
C £893,700
D £890,000
27 | P a g e
2.25
The lowest breakeven sales value, subject to meeting the above sales value constraints is
nearest to
A £1,366,700
B £1,356,700
C £1,456,800
D £1,556,800
2.26
X Ltd provides a single unit the ‘widget’ to its customers. Analysis for the year shows
that, when the budgeted level of activity was 6,000 units with a sales value of £250 a unit,
the margin of safety was 25%.
A £675,000
B £775,000
C £825,000
D £456,000
28 | P a g e
2.27
If the yearly fixed cost is £600,000, the yearly breakeven sales revenue, to the nearest £1,
will be
A £1,551,675
B £1,345,670
C £1,558,442
D Impossible to calculate without further information
2.28
ABC Plc manufactures three products from the same type of material, which is in short
supply. The following budget relates to these products:
Machine hours
per unit 1.0 0.5 3.0
The conversion costs include general fixed overhead that have been absorbed on the basis
of £4.00 per machine hour. The most and the least profitable use of the raw material for
the above products would be
29 | P a g e
2.29
If both the selling price and variable cost per unit of a product rises by 20%, the
breakeven point would
A Increase
B Decrease
C Remain constant
D Would be impossible to calculate without further information
2.30
S Ltd sells a single product for £50 a unit. Fixed cost is £450,000 and variable cost is
90% of the selling price. If fixed cost rises by £50,000 and the contribution to sales ratio
changes to 20%, but the sales price remains the same, the breakeven number of units
would decrease by
A 40,000 units
B 30,000 units
C 20,000 units
D 10,000 units
2.31
2.32
Where Y = Sales
X = the period
In accounting period 26, the seasonal variation will have an index of 90. The expected
sales for this period to the nearest units will be?
A 187
B 428
C 385
D 400
30 | P a g e
2.33
The regression equation Y = 20x + 560 has been found to be a reliable method of
calculating X Plc deseasonlised sales in units.
Where Y is the total sales units and X refers to the accountancy period. Quarterly
seasonal variations have been found to be:
Q1 Q2 Q3 Q4
A 1,560
B 560
C 1,260
D 1,071
2.34
The overhead cost of X Ltd has been found to accurately reflect the following formula
Y = £20,000 + £0.50X
Each month’s activity level, in labour hours, may be estimated using a combined
regression and time series model:
a = 50,000 + 40b
Where “a” is the deseasonalised month’s activity level and “b” the month number.
In month 250, when the seasonal index value was 123, the overhead cost (to the nearest
£1,000) would be
A £55,000
B £56,000
C £57,000
D £58,000
31 | P a g e
2.35
Pringle Plc makes a single product, which sells for £50 a unit and has a contribution to
sales ratio of 60%. Given that fixed overhead is £400,000, the break even volume (to the
nearest unit) would be?
A 13,333
B 8,000
C 20,000
D 11,667
2.36
Pringle Plc makes a single product, which sells for £50 a unit and has a contribution to
sales ratio of 60%. Given that fixed overhead is £400,000, the volume (to the nearest
unit) to achieve a target profit of £200,000 would be?
A 13,333
B 8,000
C 20,000
D 11,667
2.37
Pringle Plc makes a single product, which sells for £50 a unit and has a contribution to
sales ratio of 60%. Given that budgeted fixed overhead is £400,000 and the budgeted
sales units are 25,000, what would be the margin of safety?
A 13,333
B 8,000
C 20,000
D 11,667
32 | P a g e
2.38
XYZ Plc manufactures three products from the same type of labour, which is in short
supply. The following budget relates to these products:
Labour hours
per unit 2.5 5.0 2.5
The fixed cost represents indirect production overhead apportioned to each product. The
most and the least profitable use of the labour time for the above products would be?
2.39
Maryland Plc sells units of production for £100, incurring a variable cost per unit of £30
and total fixed cost of £700,000. If the variable cost was to rise by 50% and the fixed
overhead reduced by £100,000, what would be the change in the number of break even
units sold (to the nearest unit)?
33 | P a g e
2.40
XYZ Plc manufactures three products from the same type of machine, which is in short
supply. The following budget relates to these products:
Machine Hours
per unit 3.0 5.0 4.0
The fixed cost represents indirect production overhead apportioned to each product. The
most and the least profitable use of the machine time for the above products would be?
2.41
A Sales demand
B Principle or key budget factor
C Avoidable budget factor
D Unavoidable budget factor
2.42
The equation of a straight line is given by y = a +bx. The method which is NOT used for
estimating a straight line is:
A Linear regression
B The line of best fit
C Time series
D Interpolation
34 | P a g e
2.43
x
x x
x x x x
xx
x x
x
The above data is:
2.44
The correlation between variables “b” and “d” is 0.96. This means that:
2.45
A 0.993
B 0.938
C 0.867
D 0.834
35 | P a g e
2.46
A 0.3136
B 0.7483
C 0.44
D 0.21
2.47
x x
x
x
x
x
x x
2.48
36 | P a g e
2.49
If a regression equation (in £m) y = 10 + 2.9x links sales (y) to the level of marketing
costs (x), when £6,000 is spent on marketing, compared to £2,000 spent previously, the
extra sales are:
A £10,017,400
B £11,600
C £5,800
D £17,400
2.50
One of the component parts of a time series is cyclical variation. An example of this
would be:
A An economic recession
B A strike
C A long term increase in costs of 3% each year
D A decrease in sales over summer
2.51
Based on the last 6 periods, the underlying trend of train drivers turning up late for work
is y = 73 – 0.78x, where y = number of train drivers turning up late and x = period
number.
If the 7th period has a seasonal factor of 1.05, assuming a multiplicative model then the
forecast for period 7 is:
A 50.9
B 60.9
C 70.9
D 80.9
2.52
Mobile phone users in a town in the 3rd quarter of 2002 were 10,456. The underlying
trend at this point was 9,500 and the seasonal factor is +36.44. Using the additive model
for seasonal adjustment, the seasonally adjusted figure for the quarter is:
A 9,464
B 10,492
C 9,536
D 10.420
37 | P a g e
2.53
Over a 25 month period, the underlying linear trend for the number of teachers playing
truant is y = 26 + 5.3x, where y = number of truants and x = period number. If the 26th
period has seasonal factor of –46.52, assuming an additive model then the forecast for
period 26 is:
A 117
B 115
C 210
D 215
2.54
Quarters Q1 Q2 Q3 Q4
Seasonality +25% +35% -45% -65%
If the demand for Q1 was 145 units, then the forecasted demand for Q2 is (assume a
multiplicative model):
A 157 units
B 153 units
C 47 units
D 43 units
2.55
One of the component parts of a time series is seasonal variation. An example of this
would be:
A An economic recession
B A strike
C A long term increase in costs of 3% each year
D A decrease in sales over summer
2.56
38 | P a g e
2.57
A y = 73.2 + 41.56x
B y = 68.6 + 36.14x
C y = 62.6 + 18.63x
D y = 60.1 + 17.42x
2.58
Which one of the following is not true, for time series forecasts to be reliable?
2.59
Where “w” represents the year intended for forecast. The forecast for the year 2000 is
estimated at 1.23 times trend. The forecast for the year 2000 is:
A 2678 units
B 2515 units
C 2241 units
D 2789 units
2.60
39 | P a g e
2.61
A time series analysis was done using the multiplicative model. It was used to forecast
the sales for the next quarter which was worked out to be £265,000. The trend value for
sales for that period that was used was £375,000. The season variation value was
approximately?
A 1.145
B 1.123
C 0.701
D 0.863
2.62
The budgeted profit statement of a company, with all figures expressed as a percentage of
revenue is as follows:
Revenue 100%
Variable costs 40%
Fixed costs 20%
Profit 40%
If the sales volume turns out to be only 80% of that budgeted, the profit, expressed as a
percentage of the revised revenue will be?
2.63
Sales $20,000
Variable costs $16,000
Contribution $4,000
Fixed costs $2,000
Profit $2,000
40 | P a g e
2.64
Label this diagram with the following the words. Not all apply and some can be used
more than once.
Sales revenue, Production costs, Semi-variable costs, Break even point, Fixed costs,
Margin of safetly, Stepped fixed costs, Variable costs, Budgeted sales
Cost and
revenue £
Output (units)
0
2.65
A company has three products with the following contribution to sales ratios:
Product A: 40%
Product B: 50%
Product C: 54%
If the product mix in sales value is 40% Product A, 25% Product B and 35% Product C,
what is the overall contribution to sales ratio?
41 | P a g e
2.73
When a limiting factor exists for an organisation then profit will be maximised when?
A The organisation is producing products which earn the highest profit per unit
B The organisation is producing products which use the least of the limiting factor
C The organisation is producing products which earn the highest contribution per
unit
D The organisation is producing products which earn the highest contribution per
limiting factor
2.74
According to a profit volume (PV) chart, when fixed cost increases, the point at which
the profit line cuts the horizontal axis of the chart would?
42 | P a g e
Chapter 3 - Budgeting
3.1
AB is preparing its cash budget for the next quarter. Which of the following items should
NOT be included in the cash budget?
3.2
AB is preparing its cash budget for next year. The estimated accounts payable balance at
the beginning of next year is $540,000. The budgeted purchases for next year are
$6,800,000, occurring evenly throughout the year. It is estimated that 75% of purchases
will be on credit and the remainder will be for cash. The company pays for credit
purchases in the month following purchase. The budgeted cash payments to suppliers
next year are:
A $6,375,000
B $6,773,333
C $6,915,000
D $5,215,000
3.3
AB is preparing its purchases budget for raw material C for the forthcoming year. The
opening inventory of raw material C is expected to be 2,000kg and the price is expected
to be $8 per kg.
Raw material C is used only in the production of Product D. Each unit of Product D
requires two kg of material C. Budgeted sales of Product D for the forthcoming year and
for the following year are 36,000 units in each year. Sales will occur evenly throughout
each year. The opening inventory is expected to be 6,000 units.
AB will implement a new inventory policy from the first month of the forthcoming year.
The closing inventory that will be required at the end of the forthcoming year is as
follows:
43 | P a g e
3.4
The estimated receipts in September from cash and credit sales are:
A $195,552
B $196,400
C $198,000
D $201,600
3.5
The following details have been extracted from the accounts payable records of RS.
The pattern of payments is expected to continue in the future and has been used to
produce RS’s cash budget for October to December.
October $280,000
November $250,000
December $300,000
A $264,500
B $261,250
C $250,325
D $263,500
44 | P a g e
3.6
3.7
PJ has budgeted sales for the next two years of 144,000 units per annum spread evenly
throughout each year. The estimated closing inventory at the end of this year is 6,500
units. PJ wants to change its inventory policy so that it holds inventory equivalent to one
month’s sales. The change in inventory policy will take place at the beginning of next
year and will apply for the next two years.
Each unit produced requires 2 hours of direct labour. The budgeted direct labour rate per
hour is $15. It is anticipated that 80% of production will be paid at the budgeted rate and
the remainder will be paid at the overtime rate of time and a half. PJ treats overtime costs
as part of direct labour costs.
Calculate the direct labour cost budget for the next year.
3.8
JB has budgeted production for the next budget year of 36,000 units. Each unit of
production requires 4 labour hours and the budgeted labour rate is $12 per hour excluding
overtime.
Idle time is expected to be 10% of total hours available i.e. including idle time. Due to
labour shortages it is expected that 20% of the hours paid, including idle time, will be
paid at an overtime rate of time and a half.
45 | P a g e
3.9
(i) It is the measurement of differences between planned outputs and actual outputs.
(ii) It is the measurement of differences between planned outputs and forecast outputs.
(iii) Target costing is an example.
(iv) Variance analysis is an example.
3.10
A A standard set at an ideal level, which makes no allowance for normal losses,
waste and machine downtime.
3.11
GS has budgeted sales for the next two years of 24,000 units per annum spread evenly
throughout both years. The estimated opening inventory of finished goods at the start of
the next year is 500 units but GS now wants to maintain inventory of finished goods
equivalent to one month’s sales.
Each unit uses 2kg of material. The estimated opening raw material inventory at the start
of the next year is 300kg but GS now wants to hold sufficient raw material inventory at
the end of each month to cover the following month’s production.
The change in the policy for inventory holding for both raw materials and finished goods
will take effect in the first month of next year and will apply for the next two years.
46 | P a g e
3.12
A set prior to the control period and not subsequently changed in response to
changes in activity, costs or revenues
B continuously updated by adding a further accounting period when the earliest
accounting period has expired
C changed in response to changes in the level of activity
D changed in response to changes in costs
The following data are given for sub-questions 3.13 and 3.14
A company has budgeted to produce 5,000 units of Product B per month. The opening
and closing inventories of Product B for next month are budgeted to be 400 units and 900
units respectively. The budgeted selling price and variable production costs per unit for
Product B are as follows:
$ per unit
Selling price 20.00
Direct costs 6.00
Variable production overhead costs 3.50
The company absorbs fixed production overheads on the basis of the budgeted number of
units produced. The budgeted profit for Product B for next month, using absorption
costing, is $20,700.
3.13
Prepare a marginal costing statement which shows the budgeted profit for Product B for
next month.
3.14
Explain, using appropriate calculations, why there is a difference between the profit
figures for the month using marginal costing and using absorption costing.
47 | P a g e
The following data are given for sub-questions 3.15 and 3.16:
RT is preparing the production budget for Product R and the material purchases budget
for Material T for next year. Each unit of Product R requires 6 kg of Material T.
The estimated inventory at the beginning of next year for Product R is 6,000 units and the
company wants to decrease the inventory held by 10% by the end of next year.
The estimated inventory at the beginning of next year for Material T is 60,000 kg and due
to problems with the material supplier the closing inventory at the end of next year is to
be increased to 75,000 kg. The budgeted sales of Product R for next year are 80,000
units.
3.15
3.16
Calculate the material purchases budget for Material T for next year.
3.17
B A method of budgeting whereby all activities are re-evaluated each time a budget
is formulated.
48 | P a g e
3.18
(ii) Incremental budgeting can be defined as a system of budgetary planning and control
that measures the additional costs that are incurred when there are unplanned extra units
of activity.
(iii) Rolling budgets review and, if necessary, revise the budget for the next quarter to
ensure that budgets remain relevant for the remainder of the accounting period.
3.19
The CIMA definition of zero-based budgeting is set out below, with two blank sections.
Blank 1 Blank 2
49 | P a g e
3.20
H has a budgeted production for the next budget year of 12,000 units spread evenly over
the year. It expects the same production level to continue for the next two years. Each
unit uses 4kg of material.
The estimated opening raw material inventory at the start of the next budget year is
3,000kg. H’s future policy will be to hold sufficient raw material inventory at the end of
each month to cover 110% of the following month’s production.
The budgeted material cost is $8 per kg for purchases up to 49,000kg. The excess of
purchases over 49,000kg in a year will be at a cost of $7.50 per kg.
3.21
A Lead time between the preparation of the functional budgets and the approval
of the master budget by senior management
3.22
JK has budgeted sales for next year of 24,000 units and inventory levels are expected to
remain constant throughout the year. Each unit produced will require 3 labour hours and
the budgeted labour rate will be $15 per hour. It is estimated that 10% of units produced
will be wasted.
It is expected that 15% of the total hours worked will be paid at overtime rates. 10% of
the total hours will be paid at the basic rate plus an overtime premium of 50% of the basic
rate. 5% of the total hours will be paid at the basic rate plus an overtime premium of
100% of the basic rate. The labour cost budget for next year is:
A $1,350,000
B $1,306,800
C $1,188,000
D $1,320,000
50 | P a g e
3.23
An enterprise commenced business on 1 April 2002. Revenue in April 2002 was $20,000,
but this is expected to increase at 2% a month. Credit sales amount to 60% of total sales.
The credit period allowed is one month. Bad debts areexpected to be 3% of credit sales,
but other customers are expected to pay on time. Cash sales represent the other 40% of
revenue.
3.24
The following details have been taken from the debtor collection records of W plc:
Customers paying in the month after the sale are allowed a 10% discount. Invoices for
sales are issued on the last day of the month in which the sales are made.
The budgeted credit sales for the final five months of this year are:
Calculate the total amount budgeted to be received in December from credit sales.
3.25
D plc operates a retail business. Purchases are sold at cost plus 25%. The management
team are preparing the cash budget and have gathered the following data:
Month £000
July 100
August 90
September 125
October 140
2. It is management policy to hold inventory at the end of each month which is sufficient
to meet sales demand in the next half month. Sales are budgeted to occur evenly during
each month.
51 | P a g e
3. Creditors are paid one month after the purchase has been made.
Calculate the entries for “purchases” that will be shown in the cash budget for
(i) August
(ii) September
(iii) October
3.26
Month 1 £90,000
Month 2 £105,000
Month 3 £120,000
Month 4 £108,000
80% of sales are on credit and the remainder are paid in cash. Credit customers paying
within one month are given a discount of 1.5%. Credit customers normally pay within the
following time frame:
3.27
Which ONE of the following items should be left out of its calculations?
52 | P a g e
3.28
3.29
FJ commenced business on 1 April 2008. Sales in April 2008 were $60,000. This is
forecast to increase by 2% per month.
Credit sales accounted for 50% of sales. Credit sales customers are allowed one month to
pay; 75% of April credit customers paid on time. A further 20% are expected to pay after
more than one month, but before two months. The remaining 5% are not expected to pay.
All these percentages are expected to continue in the near future.
Calculate the total amount of cash FJ should forecast to be received in June 2008.
3.30
AB is preparing its cash budget for next year. The accounts receivable at the beginning of
next year are expected to be $460,000. The budgeted sales are $5,400,000 and will occur
evenly throughout the year. 80% of the budgeted sales will be on credit and the remainder
will be cash sales. Credit customers pay in the month following sale.
A $5,040,000
B $5,410,000
C $5,500,000
D $4,420,000
53 | P a g e
3.31
£
April 32,000
May 30,000
June 25,000
July 28,000
The recent experience in terms of how credit sales are collected is as follows:
A £19,200
B £29,200
C £22,300
D £27,400
3.32
The following details have been extracted from the debtor collection records of S Plc
Customers paying in the month after sale are entitled to receive a 15% discount. Credit
sales for January to April are budgeted as follows:
A £38,500
B £29,900
C £32,400
D £40,500
54 | P a g e
3.33
3.34
3.35
3.36
William has opening stock of £6,000 and purchases of £15,000. Cost of goods sold is
£8,000.
A £13,000
B £17,000
C £15,000
D £8,000
55 | P a g e
3.37
3.38
3.39
A company has opening stock of 400kg of material A. Planned production will be 1,000
units, requiring 3kg of material A, after wastage, for every unit manufactured. Given that
10% of material is normally wasted when it goes into production and the company
requires 500kg of material in stock at the end of the period, what would be the material
purchases (to the nearest unit) planned for this period?
A 1,100 units
B 1,433 units
C 3,100 units
D 3,433 units
56 | P a g e
3.40
A Depreciation
B Bad debts
C Discounts given to customers
D Payments to suppliers
3.41
A A flexible budget
B A rolling budget
C An activity based budget
D A zero based budget
3.42
A The comparison of actual results with planned outcomes and taking action to
correct differences in order to achieve the desired future results.
B The comparison of forecast results with planned outcomes and taking action to
avoid forecast differences.
C The forecasting of future events as a basis for a system of budgetary planning and
control.
57 | P a g e
3.43
What does responsibility accounting mean? Select all that apply if any.
To allow comparisons between the budge and actual results and then any
major differences can be investigated.
To allow a more efficient production of goods and services because they can
be linked with one another.
To allow targets to be created for managers that they will want to achieve.
To allow everyone to understand what resources are available and how they
are to be allocated to different budgets.
3.44
What is the behavioural side of budgets concerned about? Select all that apply if any.
3.45
Which of these relate to feedback control? Select all that apply if any.
58 | P a g e
3.46
Which of these relate to feedforward control? Select all that apply if any.
Forecasting ahead and doing something now before the event occurs
They are good for adaptive planning
Examples of feedforward control is variance analysis
Control action would be ‘closing the stable door before the horse bolts’
Part of the output of a system is measured and returned as input to regulate
the systems further output.
3.47
Fill in this diagram of an open loop control system using the words below:
59 | P a g e
3.48
Which of these if any describe a double feeback loop system? Select all that apply if any.
3.49
Which if these if any describe a single feedback loop system? Select all that apply if any.
3.50
Which of these defines the “High Level Controller” in an open control system?
3.51
60 | P a g e
3.52
Associate the correct word with the relevant example, not all words will apply.
Sales manager takes action over those sales reps that did not meet
their sales targets
3.53
Associate the correct word with the relevant example, not all words will apply.
The sales manager will review the level of sales and production and
in conjunction with the production manager and together agree on
appropriate action to increase or decrease raw materials levels to
ensure that a satisfactory level of production is reached to support
sales.
Comparisons are made between the actual level of sales and actual
level of production of finished goods.
61 | P a g e
3.54
3.55
3.56
Which of these, if any, are why budgetary planning and control might be inappropriate in
a rapidly changing business environment.
3.57
Variance analysis
Cash flow forecasting
Target costing
Budget setting process
62 | P a g e
3.58
A company has a production budget for the next 2 years of 36,000 units per annum to be
produced evenly throughout both years. Each unit uses 2 kg of material. The estimated
opening raw material inventory at the start of the next year is 2,000 kg but the company
then wants to hold sufficient raw material inventory at the end of each month to cover the
following month's production. The budget material cost is $12 per kg.
3.59
Market research anticipates an annual demand of 55,000 units if the unit selling price is
$18.
3.60
In the context of budgeting and control, the term 'goal congruence' refers to:
63 | P a g e
3.61
A budget that is set prior to the control period and not subsequently
changed in response to changes in activity, costs or revenues
64 | P a g e
Chapter 4 - Absorption, marginal and activity based costing
The following information is given for sub-questions 4.1 and 4.2 below :
Product R Product S
Budgeted production per annum (units) 80,000 60,000
Batch size (units) 100 50
Machine set-ups per batch 3 3
Processing time per unit (minutes) 3 5
4.1
A $0.20
B $0.51
C $0.60
D $0.45
4.2
A $150
B $1.80
C $1.50
D $30
65 | P a g e
The following data are given for questions 4.3 and 4.4:
LM operates a parcel delivery service. Last year its employees delivered 15,120 parcels
and travelled 120,960 kilometres. Total costs were $194,400.
LM has estimated that 70% of its total costs are variable with activity and that 60% of
these costs vary with the number of parcels and the remainder vary with the distance
travelled.
LM is preparing its budget for the forthcoming year using an incremental budgeting
approach and has produced the following estimates:
• All costs will be 3% higher than the previous year due to inflation
• Efficiency will remain unchanged
• A total of 18,360 parcels will be delivered and 128,800 kilometres will be travelled.
4.3
Calculate the total variable costs related to the number of parcels delivered.
4.4
The following data are given for questions 4.5, 4.6 and 4.7:
DRP Limited has recently introduced an Activity Based Costing system. It manufactures
three products, details of which are set out below:
Three cost pools have been identified. Their budgeted costs for the year ending 31
December 2004 are as follows:
66 | P a g e
4.5
(a) batches
(b) machine set-ups
4.6
4.7
Calculate the budgeted overhead unit cost for Product R for inclusion in the budget for
2004.
4.8
£000 Units
Sales revenue 820
Variable production costs 300
Variable selling costs 105
Fixed production costs 180
Fixed selling costs 110
Production in March 1,000
Opening inventory 0
Closing inventory 150
A £170,000
B £185,750
C £197,000
D £229,250
The following data are given for sub-questions 4.9 and 4.10:
The following data relate to a manufacturing company. At the beginning of August there
was no inventory. During August 2,000 units of product X were produced, but only 1,750
units were sold. The financial data for product X for August were as follow:
67 | P a g e
£
Materials 40,000
Labour 12,600
Variable production overheads 9,400
Fixed production overheads 22,500
Variable selling costs 6,000
Fixed selling costs 19,300
Total costs for X for August 109,800
4.9
A £6,575
B £7,750
C £8,500
D £10,562
4.10
A £5,000
B £6,175
C £6,575
D £13,725
4.11
A company has a budget to produce 5,000 units of product B in December. The budget
for December shows that for Product B the opening inventory will be 400 units and the
closing inventory will be 900 units. The monthly budgeted production cost data for
product B for December is as follows:
The company absorbs overheads on the basis of the budgeted number of units produced.
The budgeted profit for product B for December, using absorption costing, is
4.12
Calculate the budgeted unit cost of product Z for October assuming that a direct labour-
based absorption method was used for all overheads.
4.13
Calculate the budgeted unit cost of product Z for October using an activity-based costing
approach.
4.14
Explain in less than 50 words, why the costs absorbed by a product using an activity-
based costing approach could be higher than those absorbed if a traditional labour-based
absorption system were used, and identify two implications of this for management.
69 | P a g e
4.15
WTD Ltd produces a single product. The management currently uses marginal costing
but is considering using absorption costing in the future.
The budgeted fixed production overheads for the period are £500,000. The budgeted
output for the period is 2,000 units. There were 800 units of opening inventory at the
beginning of the period and 500 units of closing inventory at the end of the period.
If absorption costing principles were applied, the profit for the period compared to the
marginal costing profit would be
A £75,000 higher.
B £75,000 lower.
C £125,000 higher.
D £125,000 lower.
4.16
X Ltd has two production departments, Assembly and Finishing, and two service
departments, Stores and Maintenance.
Stores provides the following service to the production departments: 60% to Assembly
and 40% to Finishing.
Maintenance provides the following service to the production and service departments:
40% to Assembly, 45% to Finishing and 15% to Stores.
At the end of the year after apportioning the service department overheads, the total fixed
production overheads debited to the Assembly department’s fixed production overhead
control account were £180,000.
Calculate the under/over absorption of fixed production overheads for the Assembly
department.
70 | P a g e
4.17
CJD Ltd manufactures plastic components for the car industry. The following budgeted
information is available for three of their key plastic components:
W X Y
£ per unit £ per unit £ per unit
Selling price 200 183 175
Direct material 50 40 35
Direct labour 30 35 30
The total number of activities for each of the three products for the period is as follows:
Calculate the budgeted profit per unit for each of the three products using activity based
budgeting.
4.18
T Ltd uses a standard labour hour rate to charge its overheads to its clients’ work. During
the last annual reporting period production overheads were under-absorbed by £19,250.
The anticipated standard labour hours for the period were 38,000 hours while the
standard hours actually charged to clients were 38,500. The actual production overheads
incurred in the period were £481,250.
A £456,000
B £462,000
C £475,000
D None of the above.
71 | P a g e
4.19
RDE plc uses an activity based costing system to attribute overhead costs to its three
products. The following budgeted data relates to the year to 31 December 2008:
Product X Y Z
Production units (000) 15 25 20
Batch size (000 units) 2.5 5 4
Machine set up costs are caused by the number of batches of each product and have been
estimated to be £600,000 for the year.
Calculate the machine set up costs that would be attributed to each unit of product Y.
4.20
A company uses a standard absorption costing system. The fixed overhead absorption
rate is based on labour hours.
Extracts from the company’s records for last year were as follows:
Budget Actual
Fixed production overhead $450,000 $475,000
Output 50,000 units 60,000 units
Labour hours 900,000 930,000
The under- or over-absorbed fixed production overheads for the year were
A $10,000 under-absorbed
B $10,000 over-absorbed
C $15,000 over-absorbed
D $65,000 over-absorbed
4.21
4.23
4.24
4.25
73 | P a g e
4.26
For a hospital which of these does not seem like a sensible activity and cost driver?
4.27
4.28
Y Ltd operates an activity based costing system to allocate overhead to cost units.
In its budget for the year, the company expected to undertake a total number of quality
control inspections of 550 at a total cost of £5,775. During this period, a total number of
inspections of 468 were undertaken, which incurred an actual cost of £4,500. The over or
under recovery of these costs for the above period was
74 | P a g e
4.29
Product A Product B
Budgeted annual production (units) 50,000 30,000
Batch size (units) 1,000 300
Machine set ups per batch 7 5
Budgeted costs for the machine set up for the above period was £55,250.
The budgeted machine set up cost per unit for the above period was:
A £50
B £55
C £60
D £65
4.30
A plc operates an absorption costing system; details about budget and actual cost and
activity levels are as follows:
Budget Actual
Production (units) 12,000 12,300
Production overhead (£) 120,000 128,000
The under or over recovery of these costs for the above period was
4.31
75 | P a g e
4.32
The budgeted overhead absorption rate for variable production overhead in a department
was £4.50 per direct labour hour and for the fixed production overhead £2.50 per direct
labour hour. In the period actual direct labour hours worked were 1,000 less than budget.
If actual production overhead were as expected for variable and fixed overhead, the total
under-absorbed production overhead for the period would have been:
A £2,500
B £7,000
C £0
D £4,500
Budgeted production for the month was 10,000 units, but the company only produced
9,200 units, incurring fixed overhead costs of £56,750. Sales for the period were 9,000
units.
4.33
A £159,250
B £160,250
C £170,250
D £171,250
4.34
A £159,250
B £160,250
C £170,250
D £171,250
76 | P a g e
4.35
In a period a company had opening stock of 7,000 units and closing stock of 13,000 units.
Profits based on marginal costing were £567,000 and for absorption costing £627,000.
If budgeted fixed production overhead for the period was £100,000, the budgeted level of
activity in units was:
A 8,000 units
B 9,000 units
C 10,000 units
D 11,000 units
4.36
When the level of stock decreases during a period assuming the overhead absorption rate
remains unchanged:
A Absorption costing profits will be lower and closing stock valuation higher than
under marginal costing
B Absorption costing profits will be higher and closing stock valuation lower than
under marginal costing
C Absorption costing profits will be lower and closing stock valuation lower than
under marginal costing
D Absorption costing profits will be higher and closing stock valuation higher than
under marginal costing
4.37
77 | P a g e
4.38
For a job which has a cost estimated at £400, the company needs to ensure they have a
selling price, which is charged and will earn a profit of 20% of the selling price.
A £400
B £450
C £480
D £500
4.39
4.40
An accountancy practice recovers its fixed salaries of audit managers, by charging a fixed
amount to a client on the basis of the number of hours of consultation provided.
Budgeted salaries for the period were £300,000 and actual salaries and consulting hours
performed for the period were £320,000 and 16,000 hours respectively. There was an
over absorption of salary overhead for the period of £24,000.
The overhead absorption rate per consultancy hour would have been?
A £15.00
B £18.75
C £20.00
D £21.50
78 | P a g e
4.41
The accounting entry for an over absorption of production fixed overhead for a period,
within an integrated system of cost bookkeeping would be?
Debit Credit
A Work-in-progress account Production overhead control account
B Production overhead control account Profit and loss account
C Cost of sales account Production overhead control account
D Production overhead control account Finished goods control account
4.42
The double entry for the transfer of completed production for a company operating an
integrated cost ledger bookkeeping system would be?
Debit Credit
A Work-in-progress account Finished goods control account
B Cost of sales account Work-in-progress account
C Finished goods control account Work-in-progress account
D Cost of sales account Finished goods control account
4.43
The following information is relevant to handling customer enquires within a call centre.
The average cycle time for the call centre would be? minutes
79 | P a g e
4.44
A company has budgeted to produce 5000 units of chemical X for a period. The budget
includes 400 units of opening inventory and 1000 units of closing inventory. The
following budgeted information is also provided.
Chemical X
The budgeted profit of chemical X for the period, using absorption costing would be?
4.45
During a financial period there was no opening inventory. Sales were 1750 units and the
level of production 2000 units. The following information is also provided for the
financial period.
£
Direct material £30,000
Direct labour £20,000
Variable production overhead £10,000
Fixed production overhead £50,000
Variable selling and distribution expenses £15,000
Fixed selling and distribution expenses £20,000
The valuation of closing inventory using a marginal costing approach would be?
A £7,500
B £9,500
C £13,750
D £18,250
80 | P a g e
4.46
Which of the following are characteristics of batch costing?
A i only
B ii only
C ii and iii only
D All of the above
4.47
For a job which has a cost estimated of £400, a company needs to ensure they have a
selling price that will earn a profit of 20% of sales.
A £400
B £450
C £480
D £500
4.48
Assembly Packaging
Direct materials $1000 $400
Direct labour hours 20 hours 30 hours
Direct labour rate per hour $10 $7
Production overhead per direct labour hour $5 $5
Administration 20% of production cost
Profit margin 50% of selling price
81 | P a g e
4.49
The total production cost for one unit is £20. To achieve a profit margin of 40% of sales,
the selling price would be?
A £26.67
B £28.00
C £32.00
D £33.33
4.50
Activity based costing (ABC) is claimed to provide more accurate product costs than a
traditional absorption costing system.
A ABC uses cost drivers to allocate overhead costs to products by cost pool
B ABC will improve gives an exact understanding of how overheads were onsumed
C ABC assigns overheads to each major activity
D ABC uses volume based cost drivers
4.51
A company uses an activity based costing system. Three products are manufactured,
details of which are given below:
A B C
Annual production (units) 80,000 100,000 50,000
Batch size (uints) 100 50 25
Machine set-ups per batch 3 4 6
The machine set-up cost per unit of Product B (to the nearest $0.01) is:
A $0.46
B $0.65
C $6.70
D $0.54
82 | P a g e
4.52
A company produced 5,000 units of Product B last month. The opening and closing
inventory of Product B was 400 units and 900 units respectively. The selling price and
production costs for Product B were as follows:
What is the gross profit for Product B last month, using absorption costing?
4.53
Which if any of the following statements regarding marginal and absorption costing are
true in the context of pricing decisions?
Absorption costing when used for pricing decisions includes the 'total-cost'
of the product
Marginal costing ensures the recovery of all costs incurred in selling prices
Marginal costing is more appropriate than absorption costing for use in one-
off pricing decisions
Absorption costing is more appropriate than marginal costing for use in one-
off pricing decisions
83 | P a g e
4.54
Put the following stages of an activity based budgeting system in chronological order.
Take action to adjust the capacity of resources to match the projected supply
4.55
Cost Classification
Purchase order processing costs
84 | P a g e
4.56
A company uses an activity based costing system to attribute overhead costs to its three
products. The following budgeted data relates to this year:
Product X Y Z
Production (units) 50,000 25,000 20,000
Batch size 250 100 400
Material handling costs are determined by the number of batches of each product and
have been estimated to be $60,000 for the year. What is the cost driver rate for material
handling costs?
4.57
Which of the following if any is NOT used as the basis to absorb production overheads in
a traditional absorption costing system?
4.58
Fixed production overhead is more likely to be under absorbed when?
A The actual overhead incurred is lower than the amount of overhead absorbed
B The actual overhead incurred is higher than the amount of overhead absorbed
C Actual output is higher than budgeted output for a period
D Budgeted overhead is lower than the actual overhead absorbed
4.59
Which of the following would be best apportioned to cost centres on the basis of the
number of employees?
A Insurance of machinery
B Rent and rates of the factory
C Factory canteen
D Supervision salary overhead within the assembly department
85 | P a g e
4.60
The following budgeted and actual financial information exits for an assembly
department.
Budget Actual
The overhead absorption rate per direct labour hour would be?
4.61
$
Direct materials 4,000
Direct labour:
Budgeted labour time (100 hours) 2,000
Overtime incurred 900
Production overhead charged 5,000
Total 11,900
The budgeted direct labour hours for the period was 200000 hours and budgeted
production overhead $10 million, production overhead is currently absorbed on a direct
labour hour basis.
If production overhead had been charged based on the percentage of budgeted direct
labour cost, then the revised cost of the job would have been?
A $5,000
B $11,900
C $14,150
D $17,250
86 | P a g e
4.62
A company uses an absorption costing system and calculates its overhead absorption rate
based on machine hours.
Budgeted Actual
4.63
When operating a costing system, which one of the following would best explain the
process of overhead allocation?
4.64
When common costs are shared amongst cost centres, this process is known as?
A Overhead budgeting
B Overhead absorption
C Overhead allocation
D Overhead apportionment
4.65
Which one of the following about overhead absorption rates is true?
87 | P a g e
4.66
A company uses an absorption costing system using labour hours as its basis of charging
production overhead for the period. Actual labour hours for the financial period were
11,500 hours and this was 500 hours above budgeted labour hours for the period. Actual
production overhead for the period was £134,500 and there was an over absorption of
production overhead the period of £3,500.
4.67
Which ONE of the following is less likely to lead to an over absorption of fixed
production overhead for a period?
A The production activity was higher than budget and fixed production overhead
expenditure lower than budget.
B The production activity was lower than budget and fixed production overhead
expenditure higher than budget.
C The production activity was the same as the budget and fixed production overhead
expenditure lower than budget.
D The production activity was higher than budget and fixed production overhead
expenditure the same as the budget.
4.68
A company runs a job costing system. Direct material and labour of $2,700 and $1,200
have been budgeted and charged to job number 349 respectively. Budgeted production
overhead for the period was $650,000 and actual production overhead $625,000.
Budgeted direct labour hours were 50,000 at budgeted total cost of $300,000.
4.69
A company operates an absorption costing system whereby prices are charged based on
the full cost of a product made. Production overhead is absorbed using an overhead
absorption rate of £5 per machine hour. Product X uses 2 machine hours to make one unit
of product.
The direct cost of making product X is £25 per unit. The company adds 20% to total
production cost in order to cover non-production expenses. If the company needed to
earn a 25% sales margin from the sale of product X.
88 | P a g e
4.70
4.71
Division X target return on investment (ROI) is 12%. It also has fixed costs of £400,000
and a variable cost per unit of £5. The net assets of the division forecast for the following
period will be £1.5m and the number of units forecast to be sold is 30,000 units.
The price for each unit sold in the next period would be?
4.72
The following data relates to a manufacturing company. At the beginning of August there
was no inventory. During August 2,000 units of product X were produced, but only 1,750
units were sold. The financial data for product X for August were as follow:
£
Materials 40,000
Labour 12,600
Variable production overheads 9,400
Fixed production overheads 22,500
Total costs for X for August 84,500
89 | P a g e
4.73
The following data relates to a manufacturing company. At the beginning of August there
was no inventory. During August 2,000 units of product X were produced, but only 1,750
units were sold. The financial data for product X for August were as follow:
£
Materials 40,000
Labour 12,600
Variable production overheads 9,400
Fixed production overheads 22,500
Total costs for X for August 84,500
4.74
4.75
90 | P a g e
4.76
An accountancy practice recovers its fixed salaries of audit managers, by charging a fixed
amount to a client on the basis of the number of hours of consultation provided.
Budgeted salaries for the period were £300,000 and actual salaries and consulting hours
performed for the period were £320,000 and 16,000 hours respectively. There was an
over absorption of salary overhead for the period of £24,000.
The overhead absorption rate per consultancy hour would have been?
A £15.00
B £18.75
C £20.00
D £21.50
4.77
A college offers discounts of 10% to students who pay on enrolment and 50% of
customers pay on enrolment. The extra sales needed to increase cash receipts by £20,000
would be?
A £20,000
B £21,053
C £22,000
D £44,000
4.78
There are 400 beds in a hospital for in-patients, hospital wards are expected to be utilised
on average for 90% of the time. A hospital has budgeted a total overhead cost for in-
patient catering of £1.314 million within the next year.
Assuming a 365 day a year, what would be the overhead absorption rate for
catering cost per bed per overnight stay?
4.79
Which one of the following would be an appropriate composite cost unit for a road
transport business?
91 | P a g e
4.80
Number of:
Packs sold (000) 50 27 300
Sales visits to customers 24 12 200
Orders placed by customers 75 20 700
Normal deliveries to customers 45 15 240
Urgent deliveries to customers 5 0 30
4.81
B D Company
Number of:
Packs sold (000) 34 45 300
Sales visits to customers 30 12 200
Orders placed by customers 43 30 700
Normal deliveries to customers 70 45 240
Urgent deliveries to customers 25 4 30
92 | P a g e
Fill in the CPA statement below:
B D
Sales visits
Orders processing
Normal deliveries
Urgent deliveries
Total costs
4.82
The main difference (or differences) between how traditional costing and activity based
costing treat indirect manufacturing costs is (are) that
A Traditional costing uses only production volume based drivers while activity
based costing uses only non production volume based drivers.
B D amd E
C Traditional cost allocations are usually based on a plant wide overhead rate, while
ABC systems use departmental overhead rates.
D Traditional costing treats only unit level costs as variable, while ABC systems
treat unit level, batch level and product level costs as variable.
E A and C
93 | P a g e
4.83
In activity based costing, the manufacturing overhead cost per unit will
depend partially on the number of units in a batch.
4.84
Which would be the most favorable basis for allocating manufacturing overhead for a
factory with automated equipment and a significant variation of services by its indirect
labour?
4.85
The ABC cost allocation system excludes consideration of which of the following if any?
94 | P a g e
4.86
The activity based costing system will be less detailed than an absorption
costing system
4.87
4.88
A company has a budgeted level of fixed overheads of £385,000 and the overhead
recovery rate is £4.25 per machine hour, what is the number of machine hours we expect
to use?
A 4,250
B 385,000
C 90,600
D 1,636
95 | P a g e
4.89
Which would be the least favorable basis for allocating manufacturing overhead for a
factory with automated equipment and a significant variation of services by its indirect
labour?
96 | P a g e
Chaper 5 - Standard costing and variance analysis
The following information is given for sub-questions 5.1 and 5.2 below
It has now been decided that the standard price for the raw material should have been $5
per kg.
5.1
A $6,000 Adverse
B $30,000 Adverse
C $32,000 Adverse
D $33,000 Adverse
5.2
A $6,000 Favourable
B $30,000 Adverse
C $6,400 Favourable
D $32,000 Adverse
97 | P a g e
5.3
A the difference between the budgeted fixed production overhead cost and the
standard fixed production overhead cost absorbed by actual production.
B the difference between the standard fixed production overhead cost absorbed by
actual production and the actual fixed overhead cost incurred.
C the difference between the budgeted and actual fixed production overhead cost.
D the difference between the budgeted fixed production overhead cost and the
budgeted production at the actual absorption rate incurred.
The following data are given for sub-questions 5.4, 5.5 and 5.6 below
DB manufactures and sells e-readers. The standard labour cost per unit of the product is
$7. Each unit takes 0.5 hours to produce at a labour rate of $14 per hour. The budgeted
production for August was 20,000 units.
The Production Director subsequently reviewed the market conditions that had been
experienced during August and determined that market labour rates were $17.50 per
hour. The actual production was 22,000 units. Actual labour hours worked were 11,400
hours at $15.50 per hour.
5.4
5.5
5.6
98 | P a g e
The following data are given for sub-questions 5.7 and 5.8 below
A company operates a standard absorption costing system. Details of budgeted and actual
figures for February are given below:
Budget Actual
Production (units) 29,000 26,000
Direct labour hours per unit 3.0 2.8
Direct labour cost per hour $10.00 $10.40
5.7
A $34,800 A
B $34,800 F
C $29,120 A
D $31,200 A
5.8
A $58,000 F
B $60,320 F
C $52,000 F
D $54,080 F
The following data are given for questions 5.9 and 5.10
Trafalgar Limited budgets to produce 10,000 units of product D12, each requiring 45
minutes of labour. Labour is charged at £20 per hour, and variable overheads at £15 per
labour hour. During September 2003, 11,000 units were produced. 8,000 hours of labour
were paid at a total cost of £168,000. Variable overheads in September amounted to
£132,000.
5.9
A £5,000 Adverse
B £5,000 Favourable
C £5,250 Favourable
D £10,000 Adverse
99 | P a g e
5.10
What is the correct variable overhead expenditure variance for September 2003?
A £3,750 Favourable
B £4,125 Favourable
C £12,000 Adverse
D £12,000 Favourable
5.11
The following data have been extracted from the budget working papers of WR Limited:
In November 2003, the actual activity was 13,780 machine hours and the actual overhead
cost incurred was £14,521.
The following data are given for questions 5.12 and 5.13
SW plc manufactures a product known as the TRD100 by mixing two materials. The
standard material cost per unit of the TRD100 is as follows:
£
Material X 12 litres @ £2.50 30
In October 2003, the actual mix used was 984 litres of X and 1,230 litres of Y. The actual
output was 72 units of TRD100.
5.12
5.13
X40 is one of many items produced by the manufacturing division. Its standard cost is
based on estimated production of 10,000 units per month. The standard cost schedule for
one unit of X40 shows that 2 hours of direct labour are required at £15 per labour hour.
The variable overhead rate is £6 per direct labour hour. During April, 11,000 units were
produced; 24,000 direct labour hours were worked and charged; £336,000 was spent on
direct labour; and £180,000 was spent on variable overheads.
5.14
A £20,000 Favourable
B £22,000 Favourable
C £24,000 Adverse
D £24,000 Favourable
5.15
A £12,000 Adverse
B £12,000 Favourable
C £15,000 Adverse
D £15,000 Favourable
5.16
A the difference between the budgeted value of the fixed overheads and the standard
fixed overheads absorbed by actual production.
B the difference between the standard fixed overhead cost specified for the
production achieved, and the actual fixed overhead cost incurred.
D the difference between the standard fixed overhead cost specified in the original
budget and the same volume of fixed overheads, but at the actual prices incurred.
101 | P a g e
The following data are given for sub-questions 5.17 and 5.18:
D Limited manufactures and sells musical instruments, and uses a standard cost system.
The budget for production and sale of one particular drum for April was 600 units at a
selling price of £72 each. When the sales director reviewed the results for April in the
light of the market conditions that had been experienced during the month, she believed
that D Limited should have sold 600 units of this drum at a price of £82 each. The actual
sales achieved were 600 units at £86 per unit.
5.17
5.18
The following data are given for sub-questions 5.19 and 5.20
A company has a process in which the standard mix for producing 9 litres of output is as
follows:
$
4·0 litres of D at $9 per litre 36·00
3·5 litres of E at $5 per litre 17·50
2·5 litres of F at $2 per litre 5·00
58·50
A standard loss of 10% of inputs is expected to occur. The actual inputs for the latest
period were:
$
4,300 litres of D at $9.00 per litre 38,700
3,600 litres of E at $5.50 per litre 19,800
2,100 litres of F at $2.20 per litre 4,620
63,120
5.19
5.20
102 | P a g e
5.21
Y has set the current budget for operating costs for its delivery vehicles, using the
formula described below. Analysis has shown that the relationship between miles driven
and total monthly vehicle operating costs is described in the following formula:
y = £800 + £0.0002x²
where:
y is the total monthly operating cost of the vehicles, and
x is the number of miles driven each month
The budget for vehicle operating costs needs to be adjusted for expected inflation in
vehicle operating costs of 3%, which is not included in the relationship shown above.
The delivery mileage for September was 4,100 miles, and the total actual vehicle
operating costs for September were £5,000.
The total vehicle operating cost variance for September was closest to
A £713 Adverse
B £737 Adverse
C £777 Adverse
D £838 Adverse
5.22
The CIMA official definition of the “variable production overhead efficiency variance” is
set out below with two blank sections.
“Measures the difference between the variable overhead cost budget flexed on
_____________ and the variable overhead cost absorbed by _______________ .”
Blank 1 Blank 2
103 | P a g e
The following data are given for sub-questions 5.23 to 5.25:
The following data relate to Product Z and its raw material content for September.
Budget
Output 11,000 units of Z
Standard materials content 3 kg per unit at $4.00 per kg
Actual
Output 10,000 units of Z
Materials purchased and used 32,000 kg at $4•80 per kg
It has now been agreed that the standard price for the raw material purchased in
September should have been $5 per kg.
5.23
A $6,000 Adverse
B $30,000 Adverse
C $32,000 Adverse
D $33,000 Adverse
5.24
A $8,000 Adverse
B $9,600 Adverse
C $9,600 Favourable
D $10,000 Adverse
5.25
A $6,000 Adverse
B $6,400 Favourable
C $30,000 Adverse
D $32,000 Adverse
104 | P a g e
5.26
The standard cost of the goods produced during February was £128,500.
A £96,998
B £124,448
C £132,552
D £160,002
5.27
The following data are given for sub-questions 5.28 and 5.29:
A company has a process in which three inputs are mixed together to produce Product S.
The standard mix of inputs to produce 90 kg of Product S is shown below:
$
50 kg of ingredient P at $75 per kg 3,750
30 kg of ingredient Q at $100 per kg 3,000
20 kg of ingredient R at $125 per kg 2,500
9,250
105 | P a g e
During March 2,000 kg of ingredients were used to produce 1,910 kg of Product S.
Details of the inputs are as follows:
$
1,030 kg of ingredient P at $70 per kg 72,100
560 kg of ingredient Q at $106 per kg 59,360
410 kg of ingredient R at $135 per kg 55,350
186,810
5.28
5.29
Q plc uses standard costing. The details for April were as follows:
5.30
5.31
106 | P a g e
The following data are given for sub-questions 5.32 to 5.34:
A company uses standard absorption costing. The following information was recorded by
the company for October:
Budget Actual
Output and sales (units) 8,700 8,200
Selling price per unit £26 £31
Variable cost per unit £10 £10
Total fixed overheads £34,800 £37,000
5.32
A £38,500 favourable
B £41,000 favourable
C £41,000 adverse
D £65,600 adverse
5.33
A £6,000 adverse
B £6,000 favourable
C £8,000 adverse
D £8,000 favourable
5.34
A £2,000 adverse
B £2,200 adverse
C £2,200 favourable
D £4,200 adverse
107 | P a g e
5.35
RJD Ltd operates a standard absorption costing system. The following fixed production
overhead data is available for one month:
A 180,000 units.
B 240,000 units.
C 270,000 units.
D 280,000 units.
PP Ltd operates a standard absorption costing system. The following information has
been extracted from the standard cost card for one of its products:
It has subsequently been noted that due to a change in economic conditions the best price
that the material could have been purchased for was £4.50 per kg during the period.
5.36
5.37
108 | P a g e
5.38
SS Ltd operates a standard marginal costing system. An extract from the standard cost
card for the labour costs of one of its products is as follows:
Labour Cost
5 hours x £12 £60
The following data are given for sub-questions 5.39 and 5.40:
X Ltd operates a standard costing system and absorbs fixed overheads on the basis of
machine hours. Details of budgeted and actual figures are as follows:
Budget Actual
Fixed overheads £2,500,000 £2,010,000
Output 500,000 units 440,000 units
Machine hours 1,000,000 hours 900,000 hours
5.39
A £190,000 favourable
B £250,000 adverse
C £300,000 adverse
D £490,000 favourable
5.40
A £190,000 favourable
B £250,000 adverse
C £300,000 adverse
D £490,000 favourable
109 | P a g e
The following data are given for sub-questions 5.41 and 5.42:
Product XYZ is made by mixing three materials (X, Y and Z). There is an expected loss
of 20% of the total input. The budgeted and actual results for Period 1 are shown below.
There were no opening or closing inventories of any materials or of the finished product.
Budget Actual
Output of XYZ 800 kg 960 kg
Material
X 500 kg @ $5⋅ 00 per kg 600 kg @ $4⋅ 70 per kg
Y 300 kg @ $6⋅ 00 per kg 380 kg @ $6⋅ 50 per kg
Z 200 kg @ $7⋅ 00 per kg 300 kg @ $7⋅ 10 per kg
Total input 1,000 kg 1,280 kg
5.41
5.42
5.43
A 277,000 units
B 324,000 units
C 360,000 units
D 420,000 units
110 | P a g e
The following data are given for sub-questions 5.44 and 5.45:
PQR Ltd operates a standard absorption costing system. Details of budgeted and actual
figures are as follows:
Budget Actual
Sales volume (units) 100,000 110,000
Selling price per unit £10 £9.50
Variable cost per unit £5 £5.25
Total cost per unit £8 £8.30
5.44
5.45
5.46
Operation B, in a factory, has a standard time of 15 minutes. The standard rate of pay for
operatives is £10 per hour. The budget for a period was based on carrying out the
operation 350 times. It was subsequently realised that the standard time for Operation B
included in the budget did not incorporate expected time savings from the use of new
machinery from the start of the period. The standard time should have been reduced to 12
minutes.
Operation B was actually carried out 370 times in the period in a total of 80 hours. The
operatives were paid £850.
A £60 adverse
B £75 favourable
C £100 adverse
D £125 adverse
111 | P a g e
5.47
5.48
A the difference between the budgeted value of the fixed overheads and the standard
fixed overheads absorbed by actual production.
B the difference between the standard fixed overhead cost specified for the
production achieved, and the actual fixed overhead cost incurred.
D the difference between the standard fixed overhead cost specified in the original
budget and the same volume of fixed overheads, but at the actual prices incurred.
112 | P a g e
The following data are given for sub-questions 5.49 and 5.50:
The budgeted selling price of one of C’s range of chocolate bars was $6.00 per bar. At
the beginning of the budget period market prices of cocoa increased significantly and C
decided to increase the selling price of the chocolate bar by 10% for the whole period. C
also decided to increase the amount spent on marketing and as a result actual sales
volumes increased to 15,750 bars which was 5% above the budgeted volume. The
standard contribution per bar was $2.00 however a contribution of $2.25 per bar was
actually achieved.
5.49
A $9,450 A
B $9,450 F
C $9,000 A
D $9,000 F
5.50
A $1,500.00 F
B $3,937.50 F
C $3,750.00 F
D $1,687.50 F
5.51
If inventory levels have increased during the period, the profit calculated using marginal
costing when compared with that calculated using absorption costing will be
A Higher.
B Lower.
C Equal.
D Impossible to answer without further information.
113 | P a g e
5.52
Flexed budgets for the cost of medical supplies in a hospital, based on a percentage of
maximum bed occupancy, are shown below:
During the period, the actual bed occupancy was 87% and the total cost of the medical
supplies was $430,000.
A $5,000 adverse
B $12,000 adverse
C $5,000 favourable
D $12,000 favourable
5.53
The systematic comparison of key factors between sections or departments within the
same organisation is called
A Internal benchmarking
B Performance appraisal
C Environmental auditing
D Quality assessment
5.54
X Plc uses a standard absorption costing system. Details for the month were as follows
Budget Actual
The sales price and volume variance for the month was
Volume Price
A £2,600 (A) £5,424 (F)
B £2,600 (A) £5,424 (A)
C £2,600 (F) £4,480 (A)
D £2,600 (F) £4,480 (F)
114 | P a g e
The following data is to be used for 5.55 and 5.56:
Z Plc sells garden gnomes that it purchases from a local distributor. Its budget shows for
the four-week period that it plans to sell 800 gnomes at a unit price of £30, which would
give a contribution to sales ration of 40%
Actual sales were 770 gnomes at an average selling price of £27.50, the actual
contribution to sales ratio averaged 27%
5.55
A £2,000 (A)
B £1,925 (F)
C £1,925 (A)
D £2,000 (F)
5.56
A £360 (A)
B £360 (F)
C £223 (A)
D £223 (F)
Meat and Veg Ltd manufactures steak and kidney pies, the standard cost of a 1Kg pie
being as follows:
£
0.6kg Steak @ £5.60 per kg 3.36
0.6kg Kidney @ £1.40 per kg 0.84
4.20
115 | P a g e
5.57
The total material mix variance (to the nearest £) using the weighted average approach
for both ingredients would be?
A £145 (A)
B £145 (F)
C £290 (A)
D £290 (F)
5.58
A £1,134 (A)
B £1,134 (F)
C £777 (A)
D £648 (F)
5.59
The following data has been extracted from the budget of XL Plc:
10,000 £25,000
12,000 £29,000
18,000 £41,000
In May 2002, the actual activity was 12,750 machine hours and the actual overhead cost
incurred was £32,560.
A £2,060 (A)
B £2,060 (F)
C £1,748 (A)
D £1,748 (F)
116 | P a g e
5.60
The budgeted and actual number of units produced for this period was 4,000 and 4,260
units respectively, giving an adverse labour efficiency variance of £2,386 (A). The actual
labour hours worked for the period was?
A 17,466
B 16,614
C 16,426
D 15,574
5.61
ABC Ltd standard cost of material X which is used to assemble their final product is as
follows
3,000 units were produced for the period. This gave a material usage variance of £4,875
adverse, with material stock for the period rising by 800kg.
A 6,750kg
B 6,000kg
C 5,250kg
D 7,550kg
5.62
A budget has been prepared which includes the standard cost of material per unit of £50
(4kg of material P at £12.50 per kg). Budgeted production was 1,000 units. There was a
shortage of material P during this month and the price per kg fluctuated to £13.00 per kg.
During this period 950 units were manufactured at a material cost of £50,160 for 3,800kg
of material P. What was the material price operational and planning variance for this
period?
Operational Planning
A £760(A) £1,900(A)
B £760(A) £1,900(F)
C £760(F) £2,000(F)
D £760(A) £2,000(A)
117 | P a g e
The following information is to be used for 5.63 to 5.65:
£
0.5hrs @ £1.40 an hour (unskilled) 0.70
0.6hrs @ £7.50 an hour (skilled) 4.50
5.20
5.63
The labour yield variance for the above period (to the nearest £1) was?
A £9(A)
B £9(F)
C £6(A)
D £9(F)
5.64
It was found during the period that the labour rate per hour for skilled labour was
estimated as too high, it should have been £5.50 an hour rather than the £7.50 an hour
used within the standard cost.
What was the operational and planning variance for the labour rate variance for skilled
labour?
Operational Planning
A £50(A) £80(A)
B £50(F) £72(A)
C £50(A) £80(F)
D £50(F) £72(F)
118 | P a g e
5.65
Using the new revised standard of £5.50 an hour for skilled labour, what would be the
planning and operational efficiency variance for skilled labour if the budget was wrong
and it should have been 0.5 hours per unit rather than the 0.6 hours as planned above?
Operational Planning
A £55(A) £33(F)
B £55(F) £33(A)
C £55(A) £45(A)
D £55(F) £45(A)
119 | P a g e
120 | P a g e
Chapter 6 - Modern manufacturing methods
6.1
D A purchasing system which minimises the sum of inventory ordering costs and
inventory holding costs.
6.2
A company operates a throughput accounting system. The details per unit of Product C
are:
A $50.00
B $122.85
C $121.15
D $148.08
121 | P a g e
6.3
MN plc uses a Just-in-Time (JIT) system and backflush accounting. It does not use a raw
material stock control account. During April, 1,000 units were produced and sold. The
standard cost per unit is £100: this includes materials of £45. During April, conversion
costs of £60,000 were incurred.
What was the debit balance on the cost of goods sold account for April?
A £90,000
B £95,000
C £105,000
D £110,000
The following data are given for questions 6.4 and 6.5:
A company produces three products using three different machines. No other products
are made on these particular machines. The following data is available for December
2003.
Product A B C
Contribution per unit £36 £28 £18
Machine hours required per unit
Machine 1 5 2 1.5
Machine 2 5 5.5 1.5
Machine 3 2.5 1 0.5
Estimated sales demand (units) 50 50 60
6.4
(a) Calculate the machine utilisation rates for each machine for December 2003.
6.5
(a) State the recommended procedure given by Goldratt in his “Theory of Constraints”
for dealing with a bottleneck activity.
(b) Calculate the optimum allocation of the bottleneck machine hours to the three
products.
122 | P a g e
6.6
J K L M
£/unit £/unit £/unit £/unit
Selling price 2,000 1,500 1,500 1,750
Cost:
Direct materials 410 200 300 400
Labour 300 200 360 275
Variable overheads 250 200 300 175
Fixed overheads 360 300 210 330
Profit 680 600 330 570
Machine X – minutes per unit 120 100 70 110
Using a throughput accounting approach, how would you rank the products?
6.7
Which of the following pairs of terms correctly matches the definitions A and B above?
Definition A Definition B
123 | P a g e
6.8
(ii) Flexible manufacturing systems (FMS) are simple systems with low levels of
automation that offer great flexibility through a skilled workforce working in teams.
(iii) Electronic data interchange (EDI) is primarily designed to allow the operating units
in an organisation to communicate immediately and automatically with the sales and
purchasing functions within the organisation.
A (i) only
B (i) and (ii) only
C (i) and (iii) only
D (ii) and (iii) only
SM makes two products, Z1 and Z2. Its machines can only work on one product at a
time. The two products are worked on in two departments by differing grades of labour.
The labour requirements for the two products are as follow:
There is currently a shortage of labour and the maximum times available each day in
Departments 1 and 2 are 480 minutes and 840 minutes, respectively.
The current selling prices and costs for the two products are shown below:
Z1 Z2
£ per unit £ per unit
Selling price 50.00 65.00
Direct materials 10.00 15.00
Direct labour 10.40 6.20
Variable overheads 6.40 9.20
Fixed overheads 12.80 18.40
Profit per unit 10.40 16.20
As part of the budget-setting process, SM needs to know the optimum output levels. All
output is sold.
124 | P a g e
6.9
Calculate the maximum number of each product that could be produced each day, and
identify the limiting factor/bottleneck.
6.10
Using traditional contribution analysis, calculate the ‘profit-maximising’ output each day,
and the contribution at this level of output.
6.11
6.12
£
Conversion costs incurred 890,000
Finished goods produced 1,795,000
Finished goods sold 1,700,000
Conversion costs allocated 840,000
The two items debited to the cost of goods sold account in June would be
£ £
A 890,000 and 95,000
B 1,700,000 and 50,000
C 1,700,000 and 95,000
D 1,795,000 and 50,000
125 | P a g e
6.13
Definition 1: “A system that converts a production schedule into a listing of materials and
components required to meet the schedule so that items are available when needed.”
Definition 2: “An accounting system that focuses on ways by which the maximum return
per unit of bottleneck activity can be achieved.”
Which of the following pairs of terms correctly matches definitions 1 and 2 above?
Definition 1 Definition 2
6.14
(i) Enterprise Resource Planning (ERP) systems use complex computer systems, usually
comprehensive databases, to provide plans for every aspect of a business.
(ii) Flexible Manufacturing Systems (FMS) are simple systems with low levels of
automation that offer great flexibility through a skilled workforce working in teams.
(iii) Just-in-time (JIT) purchasing requires the purchasing of large quantities of inventory
items so that they are available immediately when they are needed in the production
process.
A (i) only
B (i) and (ii) only
C (i) and (iii) only
D (ii) and (iii) only
126 | P a g e
6.15
(i) Just-in-time (JIT) systems are designed to produce or procure products or components
as they are required for a customer or for use, rather than for inventory;
(iii) Material requirements planning (MRP) systems are computer based systems that
integrate all aspects of a business so that the planning and scheduling of production
ensures components are available when needed.
A (i) only
B (i) and (ii) only
C (i) and (iii) only
D (ii) and (iii) only
6.16
JJ Ltd manufactures three products: W, X and Y. The products use a series of different
machines but there is a common machine that is a bottleneck.
The standard selling price and standard cost per unit for each product for the forthcoming
period are as follows:
W X Y
£ £ £
Selling price 200 150 150
Cost
Direct materials 41 20 30
Labour 30 20 36
Overheads 60 40 50
Profit 69 70 34
Bottleneck machine
– minutes per unit 9 10 7
Using a throughput accounting approach, what would be the ranking of the products for
best use of the bottleneck?
127 | P a g e
6.17
S Ltd manufactures three products, A, B and C. The products use a series of different
machines but there is a common machine, P, that is a bottleneck. The selling price and
standard cost for each product for the forthcoming year is as follows:
A B C
$ $ $
Selling price 200 150 150
Direct materials 41 20 30
Conversion costs 55 40 66
Machine P – minutes 12 10 7
6.18
1. A system that converts a production schedule into a listing of the materials and
components required to meet that schedule so that adequate stock levels are maintained
and items are available when needed.
Definition 1 Definition 2
A Material requirements planning Enterprise resource planning
B Manufacturing resource planning Material requirements planning
C Material requirements planning Manufacturing resource planning
D Manufacturing resource planning Enterprise resource planning
128 | P a g e
The following data are given for sub-questions 6.19 and 6.20:
$
Direct materials 20,000
Direct labour 6,300
Variable production overhead 4,700
Fixed production overhead 19,750
Variable selling costs 4,500
Fixed distribution costs 16,800
Total costs incurred for Product X 72,050
During October 4,000 units of Product X were produced but only 3,600 units were sold.
At the beginning of October there was no inventory.
6.19
The value of the inventory of Product X at the end of October using marginal costing
was:
A $3,080
B $3,100
C $3,550
D $5,075
6.20
The value of the inventory of Product X at the end of October using throughput
accounting was:
A $630
B $1,080
C $1,100
D $2,000
6.21
A company can produce many types of product but is currently restricted by the number
of labour hours available on a particular machine. At present this limitation is set at
12,000 hours per annum. One type of product requires materials costing $5 which are
then converted to a final product which sells for $12. Each unit of this product takes 45
minutes to produce on the machine. The conversion costs for the factory are estimated to
be $144,000 per annum. Calculate the throughput accounting ratio for this product and
state the significance of the result.
129 | P a g e
6.22
$/unit
Selling price 45.00
Purchased components 14.00
Labour 10.00
Variable overhead 8.50
Fixed overhead 4.50
A $0.80
B $1.25
C $2.10
D $3.10
6.23
In the context of quality costs, customer compensation costs and test equipment running
costs would be classified as:
130 | P a g e
The following scenario is to be used for questions 6.24 and 6.25:
The standard selling price and standard cost per unit for each product for the next period
are as follows:
W X Y
£ £ £
Selling price 180 150 150
Cost:
Direct material 41 20 30
Direct labour 30 20 50
Variable production overheads 24 16 20
Fixed production overheads 36 24 30
Profit 49 70 20
Time (minutes) on bottleneck machine 7 10 7
6.24
Using a traditional limiting factor approach, the rank order (best first) of the products
would be
A W, X, Y
B W, Y, X
C X, W, Y
D Y, X, W
6.25
Using a throughput accounting approach, the rank order (best first) of the products would
be
A W, X, Y
B W, Y, X
C X, W, Y
D Y, X, W
131 | P a g e
6.26
(i) Enterprise Resource Planning (ERP) systems are accounting oriented information
systems which aid in identifying and planning the enterprise wide resources needed to
resource, make, account for and deliver customer orders.
The following data are given for sub-questions 6.27 and 6.28:
A company produces three products D, E and F. The statement below shows the selling
price and product costs per unit for each product, based on a traditional absorption
costing system.
Product D Product E Product F
$ $ $
Additional information:
Demand per period (units) 3,000 4,000 5,000
Time in Process A (minutes) 20 25 15
Each of the products is produced using Process A which has a maximum capacity of
2,500 hours per period.
132 | P a g e
6.27
A D, E, F
B E, D, F
C F, D, E
D D, F, E
6.28
A D, E, F
B E, D, F
C F, D, E
D D, F, E
6.29
6.30
133 | P a g e
6.31
6.32
Which ONE of the following statements about Kaizen would NOT be correct?
6.33
Which ONE of the following would NOT normally be a characteristic of lean production
methods?
6.34
Which ONE of the following would NOT be an example of an internal failure cost for an
organisation?
134 | P a g e
6.35
Which ONE of the following product processes tend to deal with deal with ‘high variety’
and ‘low volumes’?
A Continuous
B Job
C Project
D Mass
6.36
A Quality accreditation
B Continuous improvement
C Elimination of waste
D Service quality improvement
6.37
The following information is relevant to handling customer enquires within a call centre.
6.38
Which of the following are less likely to be forms of waste to eliminate when using lean
production methods?
Services
Waiting time
Movement
Quality
Over-production
Cost
Defects
Transport
135 | P a g e
6.39
Which ONE of the following would describe machine operators and assembly workers
which are trained to undertake routine servicing, fault diagnosis and maintenance of their
own operating machinery?
A Lean production
B Total productive maintenance
C Total quality management
D Lean synchronisation
6.40
Which ONE of the following would describe a car manufacturer which is organised into
smaller standalone factories with teams in each factory responsible for making a
complete product or small range of products?
6.41
Which ONE of the following means ‘the flow of products or services delivered exactly to
what customers require and with zero waste in this process?
A Lean synchronisation
B JIT systems
C Flexible manufacturing systems
D Sustainable operations
6.42
A removal of waste
B incremental change
C official accreditation
D continuous improvement
136 | P a g e
6.43
6.44
Small groups of employees that meet to identify work problems and their solution are
known as
A Quality circles
B Peer counsellors
C Cellular production teams
D Teleworkers
6.45
A Internal failure
B Appraisal
C Prevention
D Transaction
6.46
A Feedforward Control
B Feedback Control
C Continuous improvement
D Quality assurance procedures and systems
137 | P a g e
6.47
Rework of work-in-progress
Regular inspection and routine servicing of equipment
Supplier quality assurance schemes
Performance measures to monitor quality
Inspection of materials and components
Consumer acceptance testing
TQM culture of staff
6.48
Which of the following would be examples of external failure costs for quality?
Select THREE only.
6.49
Which ONE of the following processes is used commonly in car manuafacturing today?
A Job production
B Dedicated cell production
C Focus factory production
D Batch production
6.50
Information systems or software which can provide a list of parts and materials required
for the type and number of products entered thus allowing better inventory management,
would normally be called?
138 | P a g e
6.51
Collaborating with its suppliers may bring a company added value because it can
6.52
6.53
6.54
A Intangibility
B Immediate consumption
C Inventory management
D Involvement of the consumer
6.55
Loss of goodwill and the expense of product recalls are known as which ONE of the
following?
139 | P a g e
6.56
Quality failure costs incurred before the good or service has been transferred to the
customer would normally be described as?
A Prevention costs
B Appraisal costs
C Internal failure costs
D External failure costs
6.57
6.58
A Just-in-time
B Ad hoc
C Level capacity strategy
D Plan-do-check-act (PDCA) quality
6.59
140 | P a g e
Chapter 7 - Environmental cost accounting
7.1
7.2
Which of these if any will occur as a result of having an effective environmental costing
sytem?
7.3
Which of these are known as environmental costs? Select all that apply.
7.4
141 | P a g e
7.5
7.6
Landfill tax
Income tax
Court imposed fine on illegal dumping of waste
Road tax
7.7
A one off tax on company profits to pay for new recycle bins
Company fine for using toxic illegal chemcials in manufacture
Increased fuel duty
A tax on tobacco to fund additional hospitals in the UK
7.8
Increase productivity
Reduces pollution
Increases profits
Increases goodwill with customers
7.9
142 | P a g e
7.10
Complete the following sentances with the following words, not all words maybe used:
Energy and water consumption have proven to be both very __________ to businesses as
well as having significant impact on the ____________ through ____________ carbon
emissions. Businesses should look towards ways of _____________ the use of these
___________ as far as practicable. Energy and ____________ consumption are closely
linked as energy is needed to heat up water and so a _________ in water useage would
mean a reduction in _____________ useage as well.
7.11
7.12
143 | P a g e
7.13
7.14
Tracking systems for environmental wastes are needed in order to assign costs
It does not allows us to use cost data to develop superior strategies
Does not allow intangible and uncertain environmental factors to be brought
into the decision-making framework
Requires clear definition of environmental costs
7.15
7.16
Emissions trading
Transfer pricing
Clean development mechanism
Joint implementation
144 | P a g e
7.17
7.18
7.19
145 | P a g e
146 | P a g e
Chapter 8 - Decision theory
8.1
A company is considering the launch of a new product which it estimates has a 75%
chance of success if no marketing is undertaken. The company believes that if it
undertakes a marketing campaign costing $50,000 the probability of success of the
product will increase to 90%.
If successful, the product will make a profit of $300,000, before marketing costs.
However, if it is unsuccessful, the product will make a loss of $80,000 before marketing
costs.
Calculate whether it is worthwhile for the company to undertake the marketing campaign.
8.2
A company is planning to launch a new product. The price at which it will sell the
product will be determined by the level of competition in the market which is currently
uncertain. The possible selling prices and variable costs and their respective associated
probabilities are as follows:
Selling price and variable cost per unit are independent of each other.
Calculate the probability of the contribution per unit being equal to or greater than $40.
147 | P a g e
8.3
EF sells personal computers on which it gives a one year warranty. EF is estimating the
cost of warranty claims for next year.
If all products under warranty need minor repairs the total cost is estimated to be $2
million. If all products under warranty need major repairs it would cost $6 million. If all
products under warranty need to be replaced it would cost $10 million.
Based on past experience EF has estimated that 80% of products under warranty will
require no repairs, 15% will require minor repairs, 3% will require major repairs and 2%
will need to be replaced.
Calculate the expected value of the cost of warranty claims for next year.
The following information is given for sub-questions 8.4 and 8.5 below
A marketing manager is deciding which of four potential selling prices to charge for a
new product. The market for the product is uncertain and reaction from competitors may
be strong, medium or weak. The manager has prepared a payoff table showing the
forecast profit for each of the possible outcomes.
Identify the selling price that would be chosen if the manager applies the maximin
criterion to make the decision.
8.5
Identify, using a regret matrix, the selling price that would be chosen if the manager
applies the minimax regret criterion to make the decision.
148 | P a g e
8.6
A decision maker who makes decisions using the maximax decision criterion would be
described as:
A Pessimistic
B Optimistic
C A bad loser
D Cautious
The following information is given for sub-questions 8.7 and 8.8 below
The committee of a new golf club is setting the annual membership fee. The number of
members depends on the membership fee charged and economic conditions. The forecast
annual cash inflows from membership fees are shown below.
Membership level
Membership Fee Low Average High
$000 $000 $000
$600 360 480 540
$800 400 440 480
$900 360 405 495
$1,000 320 380 420
8.7
If the maximin criterion is applied the fee set by the committee would be:
A $600
B $800
C $900
D $1,000
8.8
If the minimax regret criterion is applied the fee set by the committee would be:
A $600
B $800
C $900
D $1,000
149 | P a g e
8.9
A decision maker who makes decisions using the expected value criterion would be
classified as:
A Risk averse
B Risk seeking
C Risk neutral
D Risk spreading
8.10
The table below details the annual contribution earned from each of the possible
outcomes. If PT applies the minimax regret criterion, the fee level it will choose is:
A Deluxe
B High
C Standard
D Low
150 | P a g e
8.11
PL currently earns an annual contribution of $2,880,000 from the sale of 90,000 units of
product B. Fixed costs are $800,000 per annum.
The management of PL is considering reducing the selling price per unit to $48. The
estimated levels of demand at the revised selling price and the probabilities of them
occurring are as follows:
The estimated variable costs per unit at either of the higher levels of demand and the
probabilities of them occurring are as follows:
The level of demand and the variable cost per unit are independent of each other.
Calculate the probability that the profit will increase from its current level if the selling
price is reduced to $48.
8.12
A marketing manager is trying to decide which of four potential selling prices to charge
for a new product. The state of the economy is uncertain and may show signs of
recession, growth or boom. The manager has prepared a regret matrix showing the regret
for each of the possible outcomes depending on the decision made.
Regret Matrix
State of the economy Selling price
$40 $45 $50 $55
Boom $10,000 $0 $20,000 $30,000
Growth $20,000 $10,000 $0 $20,000
Recession $0 $10,000 $20,000 $30,000
151 | P a g e
If the manager applies the minimax regret criterion to make decisions, which selling price
would be chosen?
A $40
B $45
C $50
D $55
8.13
A decision maker that makes decisions using the minimax regret criterion would be
classified as:
A Risk averse
B Risk seeking
C Risk neutral
D Risk spreading
8.14
FP can choose from three mutually exclusive projects. The net cash flows from the
projects will depend on market demand. All of the projects will last for only one year.
The forecast net cash flows and their associated probabilities are given below:
(i) Calculate the expected value of the net cash flows from each of the THREE projects.
(ii) Calculate the value of perfect information regarding market demand.
152 | P a g e
8.15
A company is deciding which of four potential selling prices it should charge for a new
product. Market conditions are uncertain and demand may be good, average or poor. The
company has calculated the contribution that would be earned for each of the possible
outcomes and has produced a regret matrix as follows.
Regret Matrix
State of the economy Selling price
$140 $160 $180 $200
Good $20,000 $60,000 $0 $10,000
Average $50,000 $0 $40,000 $20,000
Poor $0 $30,000 $20,000 $30,000
If the company applies the minimax regret criterion to make decisions, which selling
price would be chosen?
A $140
B $160
C $180
D $200
8.16
A company is deciding whether to launch a new product. The initial investment required
is $40,000. The estimated annual cash flows and their associated probabilities are shown
in the table below.
The company’s cost of capital is 10% per annum. You should assume that all cash flows
other than the initial investment occur at the end of the year. The expected present value
of the year 1 cash flows is
A $12,453
B $(27,547)
C $15,070
D $13,700
153 | P a g e
8.17
Nile Limited is preparing its sales budget for 2004. The sales manager estimates that
sales will be 120,000 units if the Summer is rainy, and 80,000 units if the Summer is dry.
The probability of a dry Summer is 0.4.
A 96,000 units
B 100,000 units
C 104,000 units
D 120,000 units
TX Ltd can choose from five mutually exclusive projects. The projects will each last for
one year only and their net cash inflows will be determined by the prevailing market
conditions. The forecast net cash inflows and their associated probabilities are shown
below.
8.18
Based on the expected value of the net cash inflows, which project should be undertaken?
8.19
Calculate the value of perfect information about the state of the market.
154 | P a g e
8.20
A company has estimated the selling prices and variable costs of one of its products as
follows:
Selling price per unit Variable cost per unit
$ Probability $ Probability
40 0.30 20 0.55
50 0.45 30 0.25
60 0.25 40 0.20
Given that the company will be able to supply 1,000 units of its product each week
irrespective of the selling price, and that selling price and variable cost per unit are
independent of each other, calculate the probability that the weekly contribution will
exceed $20,000.
The following data are to be used when answering questions 8.21 and 8.22:
A company expects to sell 1,000 units per month of a new product but there is
uncertainty as to both the unit selling price and the unit variable cost of the product. The
following estimates of selling price, variable costs and their related probabilities have
been made:
Selling Price Unit Variable Cost
£ per unit Probability £ per unit Probability
20 25% 8 20%
25 40% 10 50%
30 35% 12 30%
There are specific fixed costs of £5,000 per month expected for the new product.
8.21
A £5,890
B £10,300
C £10,890
D £15,300
8.22
The probability of monthly contribution from this new product exceeding £13,500 is
A 24.5%
B 30.5%
C 63.0%
D 92.5%
155 | P a g e
8.23
A baker is trying to decide the number of batches of a particular type of bread that he
should bake each day. Daily demand ranges from 10 batches to 12 batches. Each batch of
bread that is baked and sold yields a positive contribution of £50, but each batch of bread
baked that is not sold yields a negative contribution of £20.
Assuming the baker adopts the minimax regret decision rule; calculate the number of
batches of bread that he should bake each day. You must justify your answer.
8.24
A company has determined its activity level and is now predicting its costs for the quarter
ended 31 March 2008. It has made the following predictions:
Calculate the expected value of total cost and its standard deviation.
2
Σ(x – x)
Note: SD =
n
8.25
A company is considering its costs in respect of a new product. The following tables
show the predictions made by the company, together with their associated probabilities:
Fixed costs
$ Probability
100,000 0.35
130,000 0.45
160,000 0.20
Variable costs
$ Probability
70,000 0.40
90,000 0.35
110,000 0.25
156 | P a g e
8.26
The owner of a van selling hot take-away food has to decide how many burgers to
purchase for sale at a forthcoming outdoor concert. The number of burgers sold will
depend on the weather conditions and any unsold burgers will be thrown away at the end
of the day.
The table below details the profit that would be earned for each possible outcome:
(i) If the van owner applies the maximin rule how many burgers will he purchase?
(ii) If the van owner applies the minimax regret rule how many burgers will he purchase?
8.27
A company is considering investing in a new project. The following table shows the
project’s estimated cash inflows and cash outflows, together with their associated
probabilities. The cash inflows and cash outflows are totally independent.
8.28
A company has to choose between three mutually exclusive projects. Market research has
shown that customers could react to the projects in three different ways depending on
their preferences. There is a 30% chance that customers will exhibit preferences 1, a 20%
chance they will exhibit preferences 2 and a 50% chance they will exhibit preferences 3.
The company uses expected value to make this type of decision.
157 | P a g e
The net present value of each of the possible outcomes is as follows:
A market research company believes it can provide perfect information about the
preferences of customers in this market.
Calculate the maximum amount that should be paid for the information from the market
research company.
8.29
A marketing manager is deciding which of four potential selling prices to charge for a
new product. Market conditions are uncertain and demand may be good, average or poor.
The contribution that would be earned for each of the possible outcomes is shown in the
payoff table below:
If the manager applies the maximin criterion to make decisions, which selling price
would be chosen?
A $40
B $60
C $80
D $100
8.30
A company is considering whether to develop and market a new product. The cost of
developing the product is estimated to be $150,000. There is a 70% probability that the
development will succeed and a 30% probability that the development will be
unsuccessful.
158 | P a g e
If the development is successful the product will be marketed. There is a 50% chance that
the marketing will be very successful and the product will make a profit of $250,000.
There is a 30% chance that the marketing will be reasonably successful and the product
will make a profit of $150,000 and a 20% chance that the marketing will be unsuccessful
and the product will make a loss of $80,000. The profit and loss figures stated are after
taking account of the development costs of $150,000.
The expected value of the decision to develop and market the product is:
A $154,000
B $4,000
C $107,800
D $62,800
8.31
Calculate the expected value of the net present value of the project and its standard
deviation.
Note:
8.32
A decision maker who makes decisions using the maximin criterion would be classified
as:
A Risk averse
B Risk seeking
C Risk neutral
D Risk spreading
159 | P a g e
8.33
If the company applies the minimax regret criterion the venue chosen would be
A Ayefield
B Beefield
C Ceefield
D Deefield
The following data are given for questions 8.34 and 8.35 below:
XY can choose from four mutually exclusive projects. The projects will each last for one
year and their net cash inflows will be determined by market conditions. The forecast net
cash inflows for each of the possible outcomes are shown below.
If the company applies the maximin criterion the project chosen would be:
A Project A
B Project B
C Project C
D Project D
160 | P a g e
8.35
If the company applies the maximax criterion the project chosen would be:
A Project A
B Project B
C Project C
D Project D
8.36
The table below shows the possible outcomes, the probability of their occurrence and the
expected value of the net present value for Project A:
Calculate the standard deviation of the net present value for Project A.
Note:
A famous sports car company is considering whether or not to exhibit their cars at a
motor show in Birmingham, which is to held later in the year. The total cost of setting up
and holding the show would be £10,000. Sales will be dependent on the turn out of new
models by competitors, there is a 0.4 chance competition will be better in comparison and
a 0.6 chance that it will be worse.
If competition is better, the company expects to sell 4 cars at the exhibition. If the
competition is worse, they expect to sell 8 cars at the exhibition. The contribution per car
is on average £15,000.
If the company does not set up an exhibition at the show, they believe 4 of the above cars
would be sold anyway during the year.
161 | P a g e
8.37
The expected net gain from exhibiting the show would be?
A £26,000
B £86,000
C £96,000
D £109,000
8.38
The owner can pay for a specialist car marketing company that claims that 70% of the
time it can accurately predict whether or not the competition will be better or worse. The
maximum amount that would be paid to the firm of consultants, compared with not
purchasing it and not attending the exhibition would be?
A £89,600
B £59,800
C £29,200
D £19,800
8.39
K Plc is about to launch a new training centre in London the cost of doing so will be
£20,000. There is a 60% chance it will be successful and a 40% chance it will be
unsuccessful. If it is successful it is estimated that there is a 50% chance it will be very
successful and generate contribution of £60,000 and a 50% chance that it will be
moderately successful and generate contribution of £30,000. What is the expected value
of the new centre launch?
A £27,000
B £15,000
C £7,000
D £42,000
162 | P a g e
Chapter 9 - Linear programming
9.1
9.2
9.3
Product A and product B each need 17 mins of labour and 23 mins of labour respectively.
“a” = number of product A produced, “b” = number of product B produced. We have
1,956 labour hours at our disposal. The labour constrain would be written as:
9.4
In a final simplex tableau the cell which meets the row for variable r (this is product R)
and the column for slack variable j (material J) is -0.56 this means:
A Every extra unit of R made would use up 0.56 units more of material J
B Every extra unit of R made would use up 0.56 units less of material J
C Every extra unit of material J would produce 0.56 more of product R
D Every extra unit of material J would produce 0.56 less of product R
163 | P a g e
9.5
ABC Ltd manufactures three products from a single machine, which is in limited supply.
The planned production optimises the use of 8,100 machining hours that are available
within this period. However another company has been found which can outsource
another 2,000 machine hours to ABC Ltd.
What would be the maximum price that ABC Ltd should be prepared to pay for the
additional 2,000 machine hours?
A £6,050
B £6,250
C £6,450
D £6,850
9.6
W Plc has skilled labour available every week of 560 hours and unskilled labour of 860
hours every week. It produces two products, details of the required labour time per unit:
Product A Product B
Skilled labour 0.75 Hours 0.4 Hours
Unskilled labour 1.6 Hours 0.2 Hours
164 | P a g e
9.7
Using linear programming, the amount left unused for a product that is not a binding
constraint is called
9.8
In linear programming which of these if any would explain the area where the solution
is?
9.9
Dual price
Extra contribution earned
A scarce resource
A limiting factor
Slack variable
The feasible region
Maximum price
A unit of a constraint
165 | P a g e
9.10
A limiting factor
They identify the main objectives
Show the limits of resources available
Where the answer is always positive
Slack variable
The feasible region
Where the answer is always negative
9.11
A Dual price plus the orginal cost of the limiting factor to make one more unit
B Contribution plus fixed costs to make one more unit
C Shadow price plus the variable cost to make one more unit
D Shadow price plus the material cost to make one more unit
9.12
A company produces two products, Product F and Product G, using the same resources.
The company is determining the production plan for this month. It has been established
that there are two resources used by the company that are constraints on the amounts that
can be produced and sold. The contribution for each unit of F is $43 and the contribution
for each unit of G is $52, where F and G represent the units of each product that can be
produced.
Material C: 2F + 3G ≤ 10,800
Labour: 3F + 2G ≤ 10,000
166 | P a g e
9.13
D E F
Demand (units) 2,400 2,200 3,000
Contribution per unit £54 £72 £35
Skilled labour hrs per unit 1 1.5 0.5
A (2,200 x E) + (2,100 x D)
B (1,000 x E) + (2,400 x D) + (3,000 x F)
C (2,200 x E) + (600 x D) + (3,000 x F)
D (2,400 x D) + (2,200 X E) + (3,000 x F)
9.14
T
2,000
1,600
1,400
1,200
1,000
A
800
600
B C
400
200 E
D
167 | P a g e
9.15
Product L M
$ per unit $ per unit
Selling price 70 90
Direct labour ($7 per hour) (28) (14)
Direct material ($5 per kg) (10) (45)
Machine hours ($10 per hour) (10) (20)
Contribution 22 11
Demand for L and M is 400 units and 700 units respectively. Material is in short supply
and there is only 6,000 kg avaialble. What is the optimum contribution that can be
earned?
A $8,800
B $17,150
C $6,347
D $15,147
9.16
Product R T
$ per unit $ per unit
Selling price 130 160
Direct labour ($8 per hour) (24) (40)
Material A ($3 per kg) (15) (12)
Material B ($7 per litre) (14) (7)
Machine hours ($10 per hour) (30) (40)
Contribution 47 61
Demand for R and T is 750 ans 1,150 respectively. Labour hours is in short supply and
there is only 7,500 hrs available, however we must fulfil a commercial customer order
first of 250 R’s and 350 T’s before we can produce what we wish to make.
A R = 250, T = 350
B R = 300, T = 1,150
C R = 750, T = 1,050
D R = 500, T = 500
168 | P a g e
9.17
P4 P6 C3 C5
$ $ $ $
Selling price 125 175 75 95
169 | P a g e
170 | P a g e
Chapter 10 - Relevant costing
10.1
Future costs
Sunk costs
Incremental costs
Avoidable costs
Fixed costs
Common costs
Differential costs
10.2
Z Plc has 400kg of material in stock that had cost £1,750. The company no longer uses
the material and if sold for scrap would earn £1.75 a kg.
Z Plc however is considering taking on a special order from a customer, which would
require 500kg of this material. The current price of the material at present is £4.50 per kg.
10.3
A Variable costs
B Committed costs
C Product specific fixed costs
D Incremental costs
171 | P a g e
10.4
Which of these costs if any are not relevant in short term decision making?
10.5
10.6
10.7
A company has some material in stock and it has no further use for it. Which of these is
not a possible opportunity cost?
172 | P a g e
10.8
A Identify objectives, identify course of action, evaluate course of action, select best
option, compare actual v budget
B Identify course of action, evaluate course of action, identify objectives, select best
option, compare actual v budget
C Compare actual v budget, identify course of action, evaluate course of action,
identify objectives, select best option
D Identify course of action, identify objectives, evaluate course of action, select best
option, compare actual v budget
10.9
10.10
A company is considering the acceptance of a one-year contract, which requires the use
of two skilled employees. They would be recruited on a one-year contract at a cost of
£45,000 per employee. An existing manager earning £80,000 a year, approximately
taking up 20% of her time, would also supervise them.
Instead of this plan above the company could instead retrain there existing employees
who currently earn £35,000 a year. This would require training costs of £20,000 in total
and the current existing employees would need to be replaced at a cost to the company of
£60,000 in total. This would therefore not require any management time.
A £90,000
B £80,000
C £106,000
D £170,000
173 | P a g e
10.11
ZYP Ltd has a current customer order which requires the use of a machine which was
purchased two years ago and currently has a net book value of £9,000. ZYP Ltd could
sell the machine now for £8,500, but if the machine is used on the above contract it
would require a complete reconditioning if it is to be used again, hence ZYP Ltd will
have to pay someone £1,000 to dismantle it and it could not therefore be sold anymore.
The cost of operating the machine (variable cost) for the customer would be £4,500 for
the job. The minimum price ZYP Ltd should quote the customer should be?
A £5,500
B £6,000
C £7,500
D £14,000
10.12
A Infinite numbers
B Opinions
C Internal data
D Finite numbers
10.13
A by-product is:
10.14
The skilled labour is currently employed by your company and paid at a rate of $8.00 per
hour. If a new job were undertaken it would be necessary either to work 25 hours’
overtime, which would be paid at time plus one half, OR in order to carry out the work in
normal time, reduce production of another product that earns contribution of $13.00 per
hour.
Calculate the relvant cost of skilled labour for the new job.
174 | P a g e
10.15
Incremental costs
Committed costs
Sunk costs
Differential costs
Absorbed fixed costs
Opportunity costs
10.16
A company is preparing a quotation for a one-off job that would require 1,200 kg of
Material B. There are 900 kg of Material B in inventory that were bought at a cost of $3
per kg. The company does not foresee any other use for the material. The material held in
inventory could be sold for $3.50 per kg. The current purchase price of Material B is
$4.50 per kg.
A $4,050
B $4,500
C $4,200
D $5,400
10.17
175 | P a g e
10.18
Which of the following is NOT a valid reason why the costs used for decision making
may be different from the costs used for profit reporting?
Costs used for decision making include only costs that are affected by the
decision.
Costs used for decision making never include fixed costs.
Costs used for decision making do not include past costs.
Costs used for decision making include opportunity costs.
10.19
Which components should the company buy in order to minimise total costs?
A Components X and Z
B Component Y only
C None of the components
D All of the components
176 | P a g e
10.20
40% of the fixed overheads are specific to the individual Divisions. Each division incurs
the same level of specific fixed overheads.
10.21
When deciding whether to replace a non-current asset, which of the following if any is
NOT relevant?
10.22
A Incremental cost
B Committed
C Avoidable cost
D Differential cost
177 | P a g e
10.23
Which one of the following is a relevant cost when making a decision in the short-term?
A Sunk cost
B Historical cost
C Notional cost
D Differential cost
10.24
Which one of the following would not be a characteristic of a relevant cost or revenue?
A Cash
B Future
C Incremental
D Notional
10.25
Which of the following costs are more relevant for decision making?
A Historical costs
B Current costs
C Notional costs
D Future c osts
10.26
Alan Salt purchased some used mobile phones 6 motnhs ago and one of his regular
custoemrs wants to buy them off him but doesnot know what to quote him.
He originally bought them for £6,500 and if he put them on Ebay today he’d get £3,500.
He could also melt down the phones and use the metal and plastic to manufacture retro
computers for his fans. He would have to buy this material in normally for £1,000.
What is Alan’s relvant cost here if he were to sell the phones to his regular cusotmer?
A £6,500
B £3,500
C £1,000
D Not possible to say
178 | P a g e
10.27
The cost of a supervisor is based on a monthly salary of $3,500 multiplied by 10% as the
the project time estimate = $350. If the supervisor cannot complete this project work
within his normal hours he will work overtime but he is not paid for this.
A $3,500
B $350
C $0
D Not enough information to calculate this
10.28
It will be necessary to hire specialist machine for a project. In total the project will
require the machine for 5 days but it is difficult to predict exactly which five days the
machine will be required within the overall project time of one month.
One option is to hire the machine for the entire month at a cost of $5,000 and then sub-
hire the machine for $150 per day when it is not required. It is expected that we would be
able to sub-hire the machine for 20 days.
Alternatively we could hire the machine on the days we need it and its availability would
be guaranteed at a cost of $500 per day.
10.29
The overhead absorption rate in a company is £20 per hour and includes power costs
which are directly related to machine usage. If a job were undertaken, it is estimated that
the machine time required would be ten hours. The machines incur power costs of £0.75
per hour. There are no other overhead costs that can be specifically identified with this
job.
A £200
B £207.50
C £7.50
D £0
179 | P a g e
10.30
We need 500 square metres of steel for a project. The steel is regularly used, and has a
current stock value of $5.00 per square metre. There are currently 100 square metres in
stock. The steel is readily available at a price of $5.50 per square metre.
A $2,500
B $2,750
C $2,200
D $2,000
10.31
The skilled labour is currently employed by your company and paid at a rate of $18.00
per hour. If a new job were undertaken it would be necessary either to work 35 hours’
overtime, which would be paid at time plus one half, OR in order to carry out the work in
normal time, reduce production of another product that earns contribution of $24.00 per
hour.
10.32
The cost of the estimating time of $400 is that attributed to the four hours taken by a
manager to analyse information to determine the cost estimate given. It is company
policy to add 20% of $1,000 to the production cost as an allowance for administration
costs associated with the jobs accepted. The brass fittings would have to be bought
specifically for this job: a supplier has quoted the price of $20 for the fittings required.
The semi-skilled labour that is needed for the job is $460; currently the company has
sufficient paid idle time to be able to complete this work.
$20
$400
$1,080
$880
$460
$480
$0
180 | P a g e
10.33
10.34
Henry Ford owns a coach which cost him $12,000. The coach today is worth $8,000.
Enzo Ferrari has asked if he can borrow the coach. If Enzo borrowed the coach then it
would be out of use for Henry for eight days. At the same time Henry has a two day a
contract which has already been accepted which contains a significant financial penalty
clause. This contract earns a contribution of $250 per day. A replacement coach could be
hired for $180 per day.
10.35
Ronnie Biggs a bank robber needs a driver to drive the getaway car for a day. He already
has a driver who he pays $60,000 a month, but he is needed by his boss Tony Soprano on
a 5 day heist. If Tony uses the driver then Ronnie will need to replace him. The
replacement driver would be hired from a recruitment agency that charges $400 per day
for a suitably qualified driver.
What is the relevant cost to Ronnie if he has to give his driver to Tony?
10.36
General overheads of $2,000 are based upon the overhead absorption rate of $10 per unit
as set in the budget. The only general overhead cost that can be specifically identified
with the job is the time that has been spent in considering the costs of the job and
preparing the quotation. This amounted to $250.
181 | P a g e
10.37
Z can sell products R, S or T after this common process or they can be individually
further processed and sold as RZ, SZ and TZ respectively. The market prices for the
products at the intermediate stage and after further processing are:
$
R 3.00
S 5.00
T 3.50
RZ 6.00
SZ 5.75
TZ 6.75
10.38
DVDBusters Ltd is a national chain of film rental shops carrying the latest from the silver
screen. Recently they are finding it difficult financially to maintain all their shops and are
considering shutting down some of them. Which of the following should they consider if
they are basing their decision on relevant costing?
182 | P a g e
10.39
David Peckham is evaluating whether to purchase a BMW 320 or continue to use his
Rover 75. Both cars are identical in David’s opinion. The BMW costs $25,000 has an
estimated service life of ten years, has no scrap value, and will have maintenance costs of
$500 per year.
The Rover 75 was $12,000 when he bought it brand new and has an existing book value
of $6,500. It has an estimated remaining service life of ten years and has no scrap value at
the end of ten years. It has a current disposal value of $3,500 and will have maintenance
costs of $2,650 per year.
Ignoring present value and tax considerations, what should David do?
10.40
Usain wishes to discontinue his Broadband Division as he belives it is making losses. The
division has contribution margin of $10,000 and allocated overhead of $26,000 (of which
$7,000 cannot be eliminated). This shut down would:
10.41
Alan Sweet has 2,000 defective units of a product that cost $4 per unit to manufacture,
and can be sold for $2 per unit. These units can be reworked for $1 per unit and sold at
their full price of $6 each. If Alan reworked the defective units, how much extra benefit
will he obtain?
A $2,000
B $6,000
C ($6,000)
D $12,000
183 | P a g e
10.42
An additional cost that results from a particular course of action is known as a(an):
A Sunk cost
B Opportunity cost
C Incremental cost
D Net present cost
10.43
Stuart Brand 17,000 defective units of a product that cost $3 per unit to manufacture, and
can be sold for $1 per unit. These units can be reworked for $3 per unit and sold at their
full price of $5 each. Should Henny-Penny rework the defective units, how much
incremental net return will result?
A $85,000
B ($34,000)
C $0
D $17,000
10.44
What unit price would the company have to charge to make $2,000 on a sale of 500
additional units that would be shipped out of the normal market area?
A $7.40
B $7.80
C $8.90
D $7.00
184 | P a g e
Chapter 1 Solutions - Classification of costs and maths for budgets
1.1 Answer is D
The variable cost per unit = ($26,000 - $20,000) / (16,000 – 12,000) = $1.50
1.2 Answer is B
Fixed costs
= $2,840,000 – (190,000 x $14)
= $180,000
1.3 Answer is C
Variable cost per unit = ($392,000 - $304,000) / (35,000 – 24,000) = $8 per unit
At 45,000 units:
1.5 Answer is A
Tip: The high-low technique uses the highest and the lowest activity and associated
monetary values to predict a variable and fixed cost, by recognising cost behaviour.
This technique concentrates on splitting a semi-variable cost into its fixed and
variable categories in order to help predict cost.
The technique creates a linear relationship for cost forecasting, normally expressed as
Y= a + bX
Use either 3,500 or 2,000 units to work out the fixed cost as a balancing figure.
£16,200 = Fixed cost + (3500 x £2.80)
£16,200 = Fixed cost + (£9,800)
Fixed cost = £6,400
186 | P a g e
Therefore
a = £6,400
b = £2.80
The budget for 4,000 units
Y = £6,400 + (£2.80 x 4,000)
Y = £17,600
1.6 Answer is C
Tip: The high-low technique uses the highest and the lowest activity and associated
monetary values to predict a variable and fixed cost, by recognising cost behaviour.
This technique concentrates on splitting a semi-variable cost into its fixed and
variable categories in order to help predict cost.
The technique creates a linear relationship for cost forecasting, normally expressed as
Y= a + bX
Therefore
a = £20,000
b = £2
187 | P a g e
1.7
Part (i)
The variable cost element is the change in costs from one output level to another.
Therefore:
Output Cost
40,000 units £194,000
25,000 units £143,500
15,000 units £50,500
However there is a further £10,000 of fixed costs to deduct when output exceeds 35,000
units.
Part (ii)
To work out total fixed costs at 36,000 units we can take the total costs at any of the two
levels and deduct all variable costs; however don’t forget to include a further £10,000 of
fixed costs if using the lower output level of 25,000 units.
OR
£143,500 + £10,000 – (£2.70 variable cost per unit x 25,000 units) = £86,000
188 | P a g e
1.8 Answer is B
This is a question where you have to use the high-low method to solve, however in the
first instance we need to remove inflation from the figures to ensure that they are like for
like high.
Using high-low method, compare the change in activity to the change in cost.
Now to obtain the correct figure we must apply inflation index being 1.06:
1.9 Answer is A
Compare the change in activity to the change in cost. Use only the highest and lowest
activities given and ignore all other activities given as data.
Use either 100,000 or 64,000 units above to work out fixed cost as the balancing figure.
189 | P a g e
Total Cost = Fixed Cost + (Variable Cost per unit x units produced)
TC = FC + (VC per unit x units produced)
1.10 Answer is A
3,500 19,875
2,500 17,625
1,000 2,250
1.11 Answer is B
190 | P a g e
1.12 Answer is D
High-low technique
High 75 180
Low 20 70
55 110
1.13 Answer is C
1,118,000 £2,341,600
982,000 £2,178,500
136,000 £163,100
VC £163,100/136,000 = £1.20
1.14 Answer is A
1115 £316,725
1345 £320,175
230 £3,450
£3,450/230 = £15
191 | P a g e
1.15 Answer is B
1.16 Answer is B
1.17 Answer is A
3,500 19,875
2,500 17,625
1,000 2,250
1.18 Answer is B
1.19 Answer is A
1.20 Answer is C
1.21 Answer is D
1.22 Answer is B
1.24 Answer is C
1.25 Answer is A
1.26 Answer
Historical in nature
Show the profit or loss for the business
Prepared for external users
1.27 Answer
Forward looking
Reports on variances against budget
Used for decision making purposes
193 | P a g e
1.28 Answer
High-low technique
$8 per
Variable cost $5,600/700 = unit
1.29 Answer is B
1.30 Answer is B
1.31 Answer is B
High-low technique
1.33 Answer is A
194 | P a g e
Chapter 2 Solutions - Advanced mathematics for budgets
2.1
2.2 Answer is A
Breakeven (units) = Fixed costs / Contribution per unit = $1,000,000 / $370 = 2,703
Sales
Superior = 20% x 2,703 = 541
Standard = 30% x 2,703 = 811
Basic = 50% x 2,703 = 1,352
195 | P a g e
2.3
Revenue Contribution
£m £m
Product X (given) 10 1.5
Product Y (given) 20 2.0
30 3.5
Product Z (balance) 12 3.0
Budgeted contribution 6.5
Fixed overhead 5.5
Budgeted profit 1.0
2.4 Answer is B
Take the individual C/S ratios and then take their portions as in the new mix to find the
new average C/S ratio and then compare to the old C/S ratio.
The new average C/S ratio is lower than the old C/S ratio, and therefore the answer is B.
196 | P a g e
2.6 Answer is 49.1%
If equal numbers were sold then 500 contracts would be sold for each type.
2.7 Answer is D
2.8 Answer make 400 Z units, 240 X units and 270 Y units.
Product X Y Z
Contribution per unit $7 $9 $11
Materials per unit (kg) $6/$10 = 0.6 $8/£10 = 0.8 $6/$10 = 0.6
Contribution per kg $7 / 0.6 = $11.67 $9 / 0.8 = $11.25 $11 / 0.6 = $18.33
Rank 2 3 1
0.6kg x 400 units = 240kg of material would be used. We would now have 360kgs of
material left.
0.6kg x 240 units = 144kg of material would be used. We would now have 216kgs of
material left.
How many Y’s can be made: 216kgs / 0.8kg per unit = 270 units.
197 | P a g e
2.9 Answer is B
When we are at the break-even point this means that we make no profit and no loss,
therefore at this point fixed costs will be equal to contribution.
Therefore:
Revenue needed to achieve target profit = (Fixed costs + desired profit) / C/S ratio
Therefore:
2.10 Answer is C
We need to calculate the C/S ratio in order work out the increase in sales needed to have
a profit of £100,000.
Fixed costs will not change with sales and so the extra contribution will achieve the
desired profit.
Extra contribution needed is £40,000 and therefore using the C/S ratio we can calculate
the increase in sales needed.
Therefore:
198 | P a g e
2.11
Y = a + bX
Y = £10,000 + £0.25x
a = 100,000 + 30b
This is the forecast trend for orders e.g. the long-term movement of orders forecast
over time. This forecast represents ‘deseasonalised data’ and therefore must be
adjusted by a seasonalised index value of 108 (or 1.08) in order to predict accurately
the number of orders forecast.
Once the trend for the number of orders has been forecast and adjusted for the
seasonal variation, the value ‘X’ can be found and this will therefore enable you to
forecast the total cost.
3. X therefore equals 115,776. Include this now in your forecasting model for
cost
199 | P a g e
2.12
This is a simple limiting factor question. They have identified that direct labour cost is
our limiting factor and so we need to work contribution per $ of direct labour cost then
rank them in order of profitability.
Service J H N
SP $84 $122 $145
Ranking 3 1 2
2.13
Y = a + bX
Y = 25,000 + 6,500X
This represents the forecast trend for unit sales. The long-term movement of sales
units forecast over time which would be ‘deseasonalised data’ and therefore must be
adjusted by a seasonalised index value of 150 (or 1.5) in order to predict accurately
the number of sales units forecast. The index value of 150 would be used because we
are estimating sales for the third quarter of year 7.
200 | P a g e
1. Work out the forecast trend for sales units
Y = 25,000 + 6,500X
Y = 25,000 + 6,500 (27*)
Y = 25,000 + 175,500
Y = 200,500 units
2.14 Answer is C
2.15 Answer is D
Trend (T) or Y = a + bX
Seasonal variations are found by the process of dividing actual data (‘TS’ or time
series, also known as seasonalised data) by the trend (deseasonalised data). The
seasonal variations over a period (one year in this case) should cancel each other out.
Therefore the index of seasonal variations should come to 400 for this period (if using
a decimal for seasonal variations it should total 4.0 for the period).
201 | P a g e
2.16 Answer is B
Tip: Only sales and variable cost (and therefore contribution) will rise and fall with
sales volume, fixed cost will remain constant.
% %
Revenue 100 x 60% 60
Variable cost 30 x 60% 18
Contribution 70 x 60% 42
Fixed cost 22 (constant) 22
Profit 48 20
2.17
They have identified that cooking time is our limiting factor and so we need to work out
contribution per minute of cooking time and then rank them in order of profitability.
Meal K L M
SP $5 $3 $4.40
Ingredients ($2) ($1) ($1.30)
Variable conversion costs ($1.60) ($0.80) ($1.85)
Contribution $1.40 $1.20 $1.25
Cooking time per meal 10 4 8
Contribution per minute $1.40/10 = $0.14 $1.20/4 = $0.30 $1.25/8 = $0.16
Rank 3 1 2
This is a limiting factor question. They have identified that fruit is our limiting factor and
so we need to work out contribution per kg of fruit and then rank them in order of
profitability.
0.3kg x 500 pies = 150kg of fruit would be used. We would have 150kgs of fruit left.
How many pies can be made: 150kgs / 0.6kgs per pie = 250 pies.
2.19
Therefore units in the month of July 2007 = 2,274 – 1,500 = 774 units
Therefore units in the month of Aug 2007 = 2,900 – 2,274 = 626 units
203 | P a g e
2.20 Answer D
204 | P a g e
2.21 Answer is 78,720 units
If quarter 1 of year 1 is time period 1 for the value of “x”, and then quarter 2 of year 1
will be x = 2, then if we count all the way to quarter 3 year 6 then x must equal 23.
Therefore sales based on the trend equation is:
2.22 Answer is A
2.23 Answer is B
Trend sales for quarter 2 year 1 = 22,000 x 800 (2) = 23,600 units
2.24 Answer is B
(0.1 x 0.3) + (0.68 x 0.4) + (0.28 x 0.3) = average C/S ratio 0.386
205 | P a g e
2.25 Answer is A
Sales Contribution
Product X 100 x 0.3 30
Product Y 200 x 0.25 50
Product Z 300 x 0.4 120
200
To breakeven the fixed cost of £450,000 needs to be met. £200,000 contribution has
already been met using the minimum sales values, therefore an additional £250,000
contribution still needs to be raised. The most profitable sales in order to minimise sales
would be to produce the products with the highest C/S ratios. In order Z, X, Y.
Sales Contribution
Product X 100 x 0.3 30
Product Y 200 x 0.25 50
Product Z 300 x 0.4 120
Product Z (remaining sales 500 – 300) 200 x 0.4 80
Product X (Balance) 566.7 x 0.3 170
1,366.7 450
2.26 Answer is A
2.27 Answer is C
600,000/0.385 = £1,558,442
206 | P a g e
2.28 Answer is D
To produce a limiting factor analysis for each product you would need the calculation for
the contribution per unit first. The profit includes the deduction of general fixed
overhead therefore if this is added back it will give the contribution per unit.
2.29 Answer is B
If both sales price and variable cost rises by 20% then contribution would also rise by
20% therefore the breakeven point would decrease (fixed overhead shared amongst a
greater contribution per unit.
2.30 Answer is A
2.31 Answer is A
2.32 Answer is C
2.33 Answer is D
Y = 20 (35) + 560
Y = 1,260
207 | P a g e
2.34 Answer is C
a (or the trend T) = 50,000 + 40 (250) = 60,000 x 1.23 (SV) = forecast labour hours of
73,800
2.35 Answer is A
SP £50.00
VC -£20.00 £50 x 0.4
C per unit £30.00 £50 x 0.6
or
£400,000/0.6 = £666,667
2.36 Answer is C
SP £50.00
VC -£20.00 £50 x 0.4
C per unit £30.00 £50 x 0.6
or
208 | P a g e
2.37 Answer is D
SP £50.00
VC -£20.00 £50 x 0.4
C per unit £30.00 £50 x 0.6
or
11,667/25,000 47%
2.38 Answer is D
A B C
Contribution per unit £15.00 £18.00 £55.00
2.39 Answer is C
£600,000/(£100-£45) = 10909
£700,000/(£100-£30) = 10000
209 | P a g e
2.40 Answer is A
X Y Z
Contribution per unit £5.00 £35.00 £10.00
2.41 Answer is B
2.42 Answer is D
2.43 Answer is C
2.44 Answer is B
This is positively correlated - a change in the value of b would mean that d would also
change by 96% in the same positive direction.
2.45 Answer is A
r= 5(160560) – (128)(6040)
√ ((5(3408) – (128)2)( 5(7568800) – (6040)2))
r= 802800 – 773120
√ (656)(1362400)
r= 0.993
210 | P a g e
2.46 Answer is A
2.47 Answer is B
2.48 Answer is D
2.49 Answer is B
y = 10 + 2.9x
Therefore the extra sales generated through increased marketing costs are:
2.50 Answer is A
Cyclical variations are not always in equal intervals or similar patterns. Examples of
which are economic recessions or economic recovery.
2.51 Answer is C
y = 73 – 0.78x
Seasonality of 1.05:
211 | P a g e
2.52 Answer is D
2.53 Answer is A
y = 26 + 5.3x
Seasonality of -46.52:
2.54 Answer is A
2.55 Answer is D
Seasonal variations (SV) are the adjustment to the trend due to as an example weather
factors.
2.56 Answer is A
212 | P a g e
2.57 Answer is B
Y = a + bX
b = n∑XY – (∑X)(∑Y)
n∑X2 – (∑X)2
a = Y – bX
b = (14)(240345) – (167)(900)
(14)(8345) – (1672)
b = 3364830 – 150300
116830 – 27889
b = 3214530
88941
b = 36.14
a = 68.6
Y = 68.6 + 36.14x
2.58 Answer is D
Extrapolation should be reliable and accurate. This is not true as it may not be reliable
and accurate.
2.59 Answer is D
T = 2267.4
Seasonality is 1.23:
2.60 Answer is A
213 | P a g e
2.61 Answer is C
Multiplicative model is Time Series (TS) = Trend (T) x Seasonal variation (SV)
TS = £265,000
T = £375,000
Therefore SV = £265,000 / £375,000 = 0.701
If volume changes then variable costs will change but not fixed costs. Therfore the new
profit will be:
2.64 Answer
Cost and
revenue £
Sales revenue
Semi-variable costs
Variable costs
Fixed costs
Margin
of
safety
Break- Budgeted Output (units)
0 even
point sales
2.65 Answer is
3.1 Answer is B
3.2 Answer is C
Units
Opening inventory 6,000
Production (balance figure) 33,000
39,000
Sales (36,000)
Closing inventory 3,000
Kg
Opening inventory 2,000
Purchases (balance figure) 70,000
72,000
Useage (33,000 x 2kg) (66,000)
Closing inventory (3,000 x 2kg) 6,000
3.4 Answer is C
215 | P a g e
3.5 Answer is B
$
20% of October sales 56,000
65% of November sales 162,500
15% of December sales x 0.95 42,750
Total cash paid 261,250
3.6 Answer is D
Units
Opening inventory 6,500
Production (balance figure) 149,500
156,000
Sales (144,000)
Closing inventory 12,000
Idle time = 10% of total available hours, therefore total available hours need to be:
3.9 Answer is C
216 | P a g e
Feedback contrasted to feed-forward control is like closing the door after the horse has
already bolted, in other words there is little you can do about it now, except try and
rectify the situation to avoid it happening again. Feed-forward control is more prevention
than appraisal, controlling a system by making adjustments now to the system in advance
before any exceptions occur. It does this by trying to predict what will happen in the
future.
Feedback can be transformed into feed-forward control by being more proactive and
predictive as to what will happen in the future, rather than being reactive or backward
looking by historical reflection on the past.
Target costing
Desired profit XX
Used by Nissan, Sony and Toyota and many other Japanese companies, who sought not
what a product ‘does’ cost (which is what most UK companies used as the method of
pricing) but rather what it ‘should’ cost.
Traditional approaches were to develop a product, determine its cost, add mark up and
determine a price. This therefore ignored competition or demand.
Target costing combines the use of JIT, TQM, cost reduction, value analysis and
benchmarking. The idea is that a product price is determined by the market place, costs
are then reduced to enable the product to be sold at that price.
3.10 Answer is C
217 | P a g e
3.11 Answer is $656,400
Production budget
Units
Opening inventory 500
Production (balance) 25,500
26,000
Sales (24,000)
Closing inventory (W1) 2,000
Workings
W1 – Closing inventory
Closing inventory at the end of each month would be 1 months of sales.
Therefore: 24,000 units / 12 months = 2,000 units
3.12 Answer is C
Flexible budgets are amended or flexed if the actual level of activity turns out to be
different from the budgeted level of activity. A flexible budget is therefore flexed to
correspond to the actual activity level for a period. When a budget is flexed it would give
an appropriate level of revenue and cost as a yardstick to compare on a like for like basis
to actual results, meaningful variances or exceptions to the budget, can then be
highlighted for management attention.
218 | P a g e
3.13
Tip: The difference between the absorption and marginal costing approach is that the
marginal costing approach makes no attempt to ‘absorb’ fixed production overhead into a
standard cost unit or the income statement. It treats production overhead as a period cost
only and charges it entirely to the income statement for each period.
It is equally important to remember that marginal costing organisations would also value
inventory at variable production cost only never full production cost, when contrasted
with an absorption costing company.
Marginal costing $
Sales (4,500 units x $20) 90,000
Variable costs (4,500 units x $9.50) (42,750)
Contribution (4,500 units x $10.50) 47,250
Fixed production costs (29,500)
Net profit 17,750
3.14
The only reason why profits will differ under both methods of costing is due to the way
that each method values finished goods inventory. The marginal costing method values
inventory at variable production cost only never full production cost. The absorption
costing method values inventory at full production cost.
$
Absorption costing profit 20,700
Marginal costing profit 17,750
Difference 2,950
Inventory levels rise (closing inventory > opening inventory) therefore a greater amount
of fixed overhead under absorption costing is being carried forward to the following
period within the valuation of the closing inventory, therefore creating a higher profit
than marginal costing.
219 | P a g e
Increase in inventory = 900 – 400 = 500 units
Therefore the increase profit under absorption costing = 500 units x $5.90 = $2,950
3.15
Production budget
Units
Closing inventory (6,000 x 0.90) 5,400
Add: Sales 80,000
85,400
Less: Opening stock (6,000)
Production needed 79,400
3.16
Materials budget
Kg
Closing inventory 75,000
Add: Production (79,400 x 6 kg) 476,400
551,400
Less: opening inventory (60,000)
Purchases needed 491,400
3.17 Answer is B
A method of budgeting whereby all activities are re-evaluated each time a budget is
formulated.
3.18 Answer is D
3.19 Answer is C
220 | P a g e
3.20 Answer is $395,000
Kg
Opening inventory 3,000
Material purchases (balance) 49,400
52,400
Less material usage (W1) 48,000
Closing inventory (W2) 4,400
Value of purchases $
$8 per Kg x 49,000 Kg 392,000
$7.50 x 400 Kg 3,000
395,000
Workings
W1 - Material usage
Production 12,000 x 4 Kg = 48,000 Kg
W2 – Closing inventory
Closing inventory at the end of each month would be 110% of next month’s production.
Therefore:
12,000 units/12 x 4 Kg = 4,000 Kg.
4,000 Kg x 1.1 = 4,400 Kg.
3.21 Answer is D
Budgetary slack or padding is a term used to describe the difference between the
minimum necessary expenditure required and the actual estimate or forecast submitted.
221 | P a g e
3.22 Answer is D
April May
Revenue 20,000 20,400
Cash received (x 40%) 8,000 8,160
Credit sales cash for May (20,000x 60% x 97%) 11,640
Total cash received in May (8,160 + 11,640) 19,800
December
$
Invoices paid in the month after sale
November ($130,000 x 60% x 90%) 70,200
Invoices paid in the second month after sale
October ($120,000 x 20%) 24,000
Invoices paid in the third month after
sale
September ($100,000 x 15%) 15,000
109,200
222 | P a g e
3.25 Answer is (i) £76,000, (ii) £86,000, (iii) £106,000
Cost of sales
July £100,000 x 80% = 80,000
August £90,000 x 80% = 72,000
September £125,000 x 80% = 100,000
October £140,000 x 80% = 112,000
3.26
£
Cash sales £108,000 x 20% 21,600
Within 1 month £120,000 x 80% x 40% x 98.5% 37,824
Within 2 months £105,000 x 80% x 30% 25,200
Within 3 months £90,000 x 80% x 28% 20,160
Brought forward 6,000
Total receipts in month 4 110,784
223 | P a g e
3.27 Answer is A
The expected gain on the disposal of the land is an accounting calculation and not a cash
flow item. The sales proceeds from the disposal of the asset would be included in the
cash forecast.
All the other items are actual cash inflows or outflows.
3.28 Answer is D
3.30 Answer is C
$
Cash received from previous period 460,000
Sales for this budget period 5,400,000
5,860,000
Credit sales not paid until next period (360,000)
($5,400,000 x 80% x 1/12)
Total cash received 5,500,000
3.31 Answer is C
3.32 Answer is A
3.33 Answer is A
224 | P a g e
3.34 Answer is B
3.35 Answer is A
3.36 Answer is A
£
Opening stock 6,000
+ Purchases 15,000
- Closing stock (bal fig) (13,000)
COGS 8,000
3.37 Answer is C
3.38 Answer is A
3.39 Answer is D
Budget (Kg)
Opening Stock 400
3833
3.40 Answer is D
3.41 Answer is B
3.42 Answer is A
225 | P a g e
3.43 Answer
To allow comparisons between the budge and actual results and then any
major differences can be investigated.
To allow a more efficient production of goods and services because they can
be linked with one another.
To allow targets to be created for managers that they will want to achieve.
To allow everyone to understand what resources are available and how they
are to be allocated to different budgets.
3.44 Answer
3.45 Answer
226 | P a g e
3.46 Answer
Forecasting ahead and doing something now before the event occurs
They are good for adaptive planning
Examples of feedforward control is variance analysis
Control action would be ‘closing the stable door before the horse bolts’
Part of the output of a system is measured and returned as input to regulate
the systems further output.
3.47 Answer
High Level
Controller
(Human)
Effector Comparator
(Takes control (Compares
action) actual to
standard)
227 | P a g e
3.48 Answer
Which of these if any describe a double feeback loop system? Select all that apply if any.
3.49 Answer
Which if these if any describe a single feedback loop system? Select all that apply if any.
3.50 Answer is D
3.51 Answer is A
3.52 Answer
Comparator Comparisons are made between the target level of sales expected
by sales reps and the actual results
Effector Sales manager takes action over those sales reps that did not meet
their sales targets
228 | P a g e
3.53 Answer
Effector The sales manager will review the level of sales and production and
in conjunction with the production manager and together agree on
appropriate action to increase or decrease raw materials levels to
ensure that a satisfactory level of production is reached to support
sales.
Comparator Comparisons are made between the actual level of sales and actual
level of production of finished goods.
Output These are the products themselves which are sold customers.
3.54 Answer is B
3.55 Answer is C
3.56 Answer
3.57 Answer
Variance analysis
Cash flow forecasting
Target costing
Budget setting process
229 | P a g e
3.58 Answer is $12,000
If produce 36,000 units over 2 years then per month = 1,500 units
If it is 2kg per unit then to hold enough to make next month = 3,000kg
We will have opening raw materials of 2,000kg therefore only need to purchases 1,000kg
3.60 Answer is D
3.61 Answer
Fixed A budget that is set prior to the control period and not subsequently
changed in response to changes in activity, costs or revenues
Incremental A budget that is based on the previous budget or actual results for
changes in the activity and inflation
230 | P a g e
Chapter 4 Solutions - Absorption, marginal and activity based costing
4.1 Answer is C
4.2 Answer is B
Costs that varied with number of parcels = $194,400 x 70% x 60% = $81,648
Cost per parcel last year = $81,648 /15,120 = $5.40
Parcel related cost for next year = $5.40 x 1.03 x 18,360 = $102,118
Costs that vary with kilometres travelled = $194,400 x 70% x 40% = $54,432
Cost per km = $54,432 / 120,960 = $0.45
Distance related costs for next year = $0.45 x 1.03 x 128,800 = $59,699
231 | P a g e
4.5 and 4.6
232 | P a g e
4.8 Answer is A
£ £
Sales revenue 820,000
Less:
Variable production cost 300,000
Closing stock (W1) (45,000)
255,000
Variable selling cost 105,000
360,000
Contribution 460,000
233 | P a g e
4.9 Answer is B
The difference between the absorption and marginal costing approach, is that the
marginal costing approach makes no attempt to ‘absorb’ fixed production overhead
into a standard cost unit or the income statement. It treats production overhead as a
period cost only and charges it entirely to the income statement for each period.
£
Material 40,000
Labour 12,600
Variable overhead 9,400
62,000
4.10 Answer is A
Throughput contribution
= sales less material cost only ‘the only true variable cost’
234 | P a g e
4.11 Answer is B
Tip: The only reason why profits differ under both methods of costing is due to the
different way that each method values inventory. Marginal costing organisations
value inventory at variable production cost only never full production cost, when
contrasted with an absorption costing company.
Valuation of inventory
£
Variable direct cost per unit 6.00
Variable production overhead per unit 3.50
Total variable production cost per unit 9.50 MC valuation per unit
Fixed overhead absorbed per unit
£29,500 ÷ 5,000 units = 5.90
Total production cost per unit 15.40 AC valuation per unit
Under the absorption costing method, a greater amount of fixed overhead would be
carried forward to the next financial period, due to closing stock being higher than
opening stock (production > sales). (900 units – 400 units x £5.90) = £2,950. Therefore
using absorption costing, profit would be £2,950 greater than it would be using marginal
costing.
235 | P a g e
4.12
Fixed overhead absorbed per labour hour (£88,000 ÷ 8,000 hrs) = £11.00
4.13
Cost drivers
Set-up cost (£22,000 ÷ 88 set-ups) = £250 per set-up
Other overhead cost (£32,000 ÷ 8,000 labour hours) = £4 per labour hour
236 | P a g e
4.14
Tip: The ABC approach recognises the complexity and diversity of how different
products consume different resources and therefore fixed overhead. This gives a
better overall understanding of product costing when contrasted to the simple
absorption costing approach. Four implications for management of using ABC have
been provided below; however the question only requires two.
The ABC approach could lead to a higher cost absorbed, if a product consumes far more
resources and therefore shares a higher proportion of the cost drivers e.g. set-up, quality
testing etc. Rather than just how much labour time each product consumes when
contrasted to absorption costing.
4.15 Answer is B
Tip: A marginal costing system would value inventory at variable production cost
only not full production cost, when contrasted with to an absorption costing system.
The different methods of stock valuation explains why there would be profit
differences.
When production > sales
Stock levels rise (closing stock > opening stock) therefore a greater amount of fixed
overhead under absorption costing is being carried forward to the following period
within the valuation of the closing stock, therefore creating a higher profit than
marginal costing.
237 | P a g e
Fixed overhead absorption rate included in the value of stock for an absorption costing
system equals £250 per unit (£500,000 ÷ 2,000 units).
Under the absorption costing method, a lower amount of fixed overhead would be carried
forward to the next financial period, due to closing stock being lower than opening stock
(production < sales). (800 units – 500 units x £250 per unit) = £75,000. Therefore
using absorption costing, profit would be £75,000 lower than it would be if using
marginal costing.
4.16
Process of absorption
Step 1
Allocate (give directly to) or apportion (share/divide) budgeted fixed production
overhead between cost centres used by the organisation at the start of the financial
period.
Step 2
After the first process above reapportion the budgeted fixed production overhead
allocated or apportioned to service cost centres to production cost centres. This
eliminates any fixed overhead apportioned to service cost centres in Step 1.
Step 3
Absorb (charge) the budgeted fixed production overhead from production cost
centres directly to cost units, work-in-progress accounts or jobs undertaken during
the financial period by the organisation, using budgeted fixed overhead absorption
rates calculated for the different production cost centres.
There are three methods of reapportioning production overhead from service cost
centres to production cost centres.
Direct method
Any work that service cost centres do for other service cost centres is ignored
completely when reapportioning service cost centre overhead to production cost
centres.
238 | P a g e
Step method
Work that service cost centres do for other service cost centres would be recognised,
but only those service cost centres which are the most widely used or have the largest
overhead allocated or apportioned to them. The more immaterial service cost centres
would reapportion overhead to production cost centres only.
Note: if not clear in your exam, you would normally reapportion the service cost
centre with the largest overhead only to both production as well as service cost
centres.
During the financial period the actual fixed overhead incurred is recorded within the
production overhead control account
Debit Production overhead control account
Credit Creditor (or cash)
During the financial period fixed overhead is absorbed (charged) from the production
overhead control account to jobs or work-in-progress accounts (ultimately ending up
being charged as an expense in the income statement).
Debit Income statement (as a fixed overhead expense)
Credit Production overhead control account
At the end of the financial period the fixed overhead ‘absorbed’ is compared to the
actual production overhead recorded and incurred for the period.
Any shortfall in fixed overhead absorbed during the financial period to the income
statement would be an ‘under absorption’ of production overhead
Debit Income statement (as a fixed overhead expense)
Credit Production overhead control account
239 | P a g e
Any surplus in fixed overhead absorbed during the financial period to the income
statement would be an ‘over absorption’ of production overhead
240 | P a g e
4.17
W X Y
£ £ £
200.0
Selling price 0 183.00 175.00
Direct material 50.00 40.00 35.00
Direct Labour 30.00 35.00 30.00
120.0
Contribution 0 108.00 110.00
Overhead allocated using ABC
W1 Receiving/inspecting
W (1200 ÷ 10,000 units) x £280 33.60
X (1800 ÷ 15,000 units) x £280 33.60
Y (2000 ÷ 18,000 units) x £280 31.11
W2 Production/machine set up
W (240 ÷ 10,000 units) x £1,500 per set up 36.00
X (260 ÷ 15,000 units) x £1,500 per set up 26.00
Y (300 ÷ 18,000 units) x £1,500 per set up 25.00
Profit per unit 50.40 48.40 53.89
W1 Receiving/inspecting
£1,400,000 ÷ (1,200 + 1,800 + 2,000) = £280 per
requisition
W2 Production/machine set up
£1,200,000 ÷ (240 + 260 + 300) = £1,500 per set up
4.18 Answer is A
Under absorption means that more production overheads were actually needed than
expected based on actual output. Therefore “flexed” production overheads (budget cost
based on actual output) can be found by subtracting the under absorption from the actual
production overheads.
The overhead absorption rate (OAR) used can be calculated by dividing flexed
production overheads by actual standard hours.
Product X Y Z
Production units 15,000 25,000 20,000
Batch size 2,500 5,000 4,000
Number of set ups required 15,000 / 2,500 25,000 / 5,000 20,000 / 4,000
=6 =5 =5
4.20 Answer is D
Traditional absorption costing takes the total budgeted fixed overhead for a period and
divides by a budgeted (or normal) activity level e.g. units, in order to find the overhead
absorption rate. This is a simple method of charging fixed overhead and allows fixed
overhead to be allocated to products, jobs or work-in-progress
Standard labour hours per unit = 900,000 hours / 50,000 units = 18 hours per unit
Standard hours flexed for actual output = 18 hours x 60,000 units = 1,080,000 hours
Over absorption of fixed overheads for the period is $65,000.
242 | P a g e
4.21 Answer is A
Traditional absorption costing takes the total budgeted fixed overhead for a period and
divides by a budgeted (or normal) activity level e.g. units, in order to find the overhead
absorption rate. This is a simple method of charging fixed overhead and allows fixed
overhead to be allocated to products, jobs or work-in-progress
Over absorption
(£300,000 - £260,000) £40,000
4.22 Answer is C
4.23 Answer is D
Absorption costing is a method of costing that assigns fixed production overhead to cost
units, jobs or work-in progress accounts during a period, by using pre-determined
overhead absorption rates. Because overhead absorption rates are pre-determined at the
beginning of a financial period and fixed overhead is charged by the process of
absorption below, it is likely a difference or balance within the production overhead
control account will arise at the end of a financial period, this balance is referred to as an
under or over absorption.
243 | P a g e
Production overhead control account
Any deficit in fixed overhead absorbed during the financial period to the income
statement would be an ‘under absorption’ of production overhead
Debit Income statement (to reduce fixed overhead absorbed)
Credit Production overhead control account
4.24 Answer is B
An inventory management method that concentrates effort on the most important items.
4.25 Answer is D
4.26 Answer is D
4.27 Answer is A
4.28 Answer is A
244 | P a g e
4.29 Answer is D
4.30 Answer is D
4.31 Answer is C
4.32 Answer is A
If the activity were 1,000 hours lower then the variable overhead would also be (£4.50 x
1,000 = £4,500) lower as well, therefore no under recovery of variable overhead would
have occurred. However the under recovery of fixed production overhead would have
been £2.50 x 1,000 hours = £2,500 under absorbed.
4.33 Answer is A
4.34 Answer is B
245 | P a g e
Alternatively if the marginal costing profit was £159,250 production exceeds sales by
200 units therefore 200 x £5.00 = £1,000 fixed overhead carried forward to the next
period under absorption costing therefore the profit will be £1,000 more than marginal
costing.
4.35 Answer is C
Stock levels rose by 6,000 units and absorption costing profit is £60,000 higher.
Therefore fixed production overhead per unit included in stock was £60,000/6,000 units =
£10 per unit of stock.
4.36 Answer is A
4.37 Answer
4.38 Answer is D
4.39 Answer
4.41 Answer is B
4.42 Answer is C
Cycle time = throughput time (30000 minutes) ÷ WIP (1000 customer enquires)
= 30 minutes average cycle time.
4.44 Answer is A
Valuation of inventory
£
Direct cost per unit 5.00
Variable overhead per unit 3.00
Total variable production cost per unit 8.00 MC valuation per unit
Fixed overhead absorbed per unit
£30,000 ÷ 5000 units = 6.00
Total production cost per unit 14.00 AC valuation per unit
Under the absorption costing method, a greater amount of fixed overhead would be
carried forward to the next financial period, due to closing inventory being higher than
opening inventory (production > sales). (1000 units – 400 units x £6.00) = £3,600.
Therefore using absorption costing, profit would be £3,600 greater than it would be using
marginal costing.
247 | P a g e
4.45 Answer is A
£
Material 30,000
Labour 20,000
Variable production overhead 10,000
60,000
4.46 Answer is D
4.47 Answer is D
248 | P a g e
4.48 Answer is $4,944
$
Direct materials ($1,000 + $400) 1,400
Direct labour (20 x $10) + (30 x $7) = 410
Production overhead (20 x $5) + (30 x $5) = 250
2,060
Administration (2,060 x 20%) = 412
Total cost 2,472
Profit mark-up 100% (W1) 2,472
The selling price 4,944
The problem is that you are told sales margin (profit as a % of sales), but you need mark-
up (profit as a % of cost).
If selling price is 100 (assume) then profit is 50% of that much (50) therefore cost must
be the difference = 50 cost. Therefore mark-up 50 profit ÷ 50 cost = 100% mark-up on
cost.
4.49 Answer is D
If sales margin is 40/100 = 40%. Then mark-up (profit as a % of cost of sales) would be
40/60 = 66.67%. Therefore take £20 cost and add 66.67% mark-up to cost = (20 x
1.6667) = £33.33.
4.50 Answer is B
249 | P a g e
4.51 Answer is D
A B C
Total numbe of batches 80,000/100 100,000/50 50,000/25
=800 =2,000 =2,000
4.53 Answer
Absorption costing when used for pricing decisions includes the 'total-cost'
of the product.
Marginal costing ensures the recovery of all costs incurred in selling prices.
Marginal costing is more appropriate than absorption costing for use in one-
off pricing decisions.
Absorption costing is more appropriate than marginal costing for use in one-
off pricing decisions.
250 | P a g e
4.54 Answer
4th Take action to adjust the capacity of resources to match the projected supply
3rd Determine the resources that are required to perform organisational activities
1st Estimate the production and sales volume by individual products and
customers
4.55 Answer
Cost Classification
Purchase order processing costs Batch level activities
4.57 Answer
4.58 Answer is B
4.59 Answer is C
251 | P a g e
4.60 Answer is $6
4.61 Answer is B
Production overhead now charged on the percentage of budgeted direct labour cost?
Budgeted labour cost ($2,000/100 hours budgeted labour cost given) = $20 an hour.
Budgeted direct labour hours for the period was 200,000 hours, therefore budgeted total
labour cost = $20 an hour x 200,000 hours = $4 million.
Production overhead $10 million/$4 million x 100 = 250% of direct cost is how
production overhead would now be allocated to this job.
$
Direct materials 4,000
Direct labour:
Budgeted labour time (100 hours) 2,000
Overtime incurred 900
Production overhead 250% x $2,000 labour cost 5,000
Revised cost of the job 11,900
The answer would be no difference to the existing cost of this job. The overtime paid is
not direct cost and therefore would not be used to absorb production overhead.
252 | P a g e
4.62 Answer is B
Traditional absorption costing takes the total budgeted fixed overhead for a period and
divides by a budgeted (or normal) activity level e.g. units, in order to find the overhead
absorption rate. This is a simple method of charging fixed overhead and allows fixed
overhead to be allocated to products, jobs or work-in-progress
4.63 Answer is D
4.64 Answer is D
4.65 Answer is A
253 | P a g e
4.66 Answer is £132,000
Traditional absorption costing takes the total budgeted fixed overhead for a period and
divides by a budgeted (or normal) activity level e.g. hours, in order to find an overhead
absorption rate (OAR). This simple method allows fixed overhead to be absorbed (or
‘charged’) for a period, in this case it would have been £138,000 absorbed (see below).
The overhead absorption rate (OAR) would be £138,000 absorbed ÷ 11,500 actual hours
= £12 per hour OAR. Therefore if budgeted labour hours were 11,000 hours (500 below
actual labour hours), then budgeted production overhead for the period would have been
11,000 hours x £12 per hour OAR = £132,000.
4.67 Answer is B
Over absorption of fixed production overheads (DR Fixed Production Overhead Control
Account and CR Income Statement), leads to a direct reduction to overhead charged in
the income statement for the period.
Only one of two situations (or both) can cause an over absorption of fixed production
overheads, that is ‘budgeted production overhead is lower than expected’ or the
‘normal/budget level of activity is more than expected’, hence too much fixed overhead
would be charged for the period (ignoring any overspending which may have arisen).
254 | P a g e
4.68 Answer is £2600
* Overhead absorption rate per unit ($650,000 ÷ 50000 hours) = £13.00 per hour.
If labour $1,200 has been budgeted then divided by the hourly labour rate ($300,000 ÷
50,000 hours) = $6 an hour = 200 hours actually worked.
Therefore production overhead absorbed would be 200 hours actually worked x £13.00
per hour OAR = £2600.
W1
The total cost per unit is £42. Sales margin (profit as a percentage of sales) is 25%, but
given we have cost, then we need mark-up (profit as a percentage of cost) to establish a
selling price. Assume Sales = 100, then if sales margin is 25% then profit would be 25.
Therefore cost would be (balance) 100 – 25 = 75. Therefore mark-up would be 25/75 =
33.33% mark-up.
255 | P a g e
4.71 Answer is £24.33
ROI = Profit
Capital employed
£19.33 contribution per unit + £5 variable cost per unit = £24.33 price per unit sold.
Or £580,000 total contribution + (30,000 units x £5 variable cost per unit) = £730,000
sales revenue. £730,000 ÷ 30000 units = £24.33 price per unit sold.
256 | P a g e
4.73 Answer is £70.42
Full cost pricing cost pricing adds a mark-up to variable and fixed (total) production cost.
Materials 40,000
Labour 12,600
Variable production overheads 9,400
Fixed production overheads 22,500
Total costs for X for August 84,500
£84,500 ÷ 2000 units produced (not sold) = £42.25 full cost per unit + 66.67% mark-up
on cost = £42.25 x 1.6667 = £70.42.
4.74 Answer
£
Direct materials 35,000
Direct labour (3400 x £7.50 per hour) 25,500
Variable Overhead 4,500
Production overhead (3400 x £5) 17,000
82,000
Administration (82,000 x 20%) = 16,400
Total cost 98,400
Profit mark-up 100% on cost (W1) 98,400
The selling price 196,800
(W1) The problem is that you are told sales margin (profit as a % of sales), but you need
mark-up (profit as a % of cost). So if profit is 50% of selling price…
If selling price is 100 (assume) then profit is 50% of that much (50) therefore cost must
be the difference = 50 cost. Therefore mark-up 50 profit ÷ 50 cost = 100% mark-up on
cost.
4.75 Answer
257 | P a g e
4.76 Answer is D
4.77 Answer is B
10% discount is offered to students who pay on enrolment and 50% of customers pay on
enrolment; therefore 50% x 10% = 5% sales lost before you receive £20,000. Therefore
£20,000/0.95 = £21,053 or if £20,000 represents 95% then 100% of sales would be
(100%/95%) x £20,000 = £21,053.
PROOF: £21,053 x 50% get discount x 10% discount = £1,053 discounts given.
400 beds x 90% capacity x 365 days = composite cost units of 131400 bed overnight
stays. £1.314 million ÷ 131400 patient overnight stays = £10 per bed per overnight stay.
4.79 Answer is A
4.80 Answer
258 | P a g e
4.81 Answer
B D
4.82 Answer is D
4.83 Answer
True
In activity based costing, the For example, a setup cost of £900 is associated with
manufacturing overhead cost per the batch of items that will be processed. A large
unit will depend partially on the quantity of items processed will mean a low setup cost
number of units in a batch. per unit. A small quantity of items being processed
will mean a high setup cost per unit.
259 | P a g e
4.84 Answer is C
It is highly unlikely that machine hours will correlate with the indirect labor cost.
It is highly unlikely that direct labor hours will correlate with the indirect labor cost.
4.85 Answer
ABC cost allocation systems can be used to allocate either variable or fixed
manufacturing overhead, to allocate joint costs, or to reallocate service department costs
to outputs. Direct costs of materials and labour do not need to be allocated to specific cost
objects.
4.86 Answer
The activity based costing system will be less detailed than an absorption
costing system
260 | P a g e
4.87 Answer
True
4.88 Answer is C
4.89 Answer is A
Since the equipment is automated, direct labour hours would be the least favorable basis.
ABC is the most favorable basis for allocating a variety of services provided by indirect
labour.
261 | P a g e
262 | P a g e
Chapter 5 Solutions - Standard costing and variance analysis
5.1 Answer is B
5.2 Answer is C
5.3 Answer is A
5.7 Answer is C
5.8 Answer is C
263 | P a g e
5.9 Answer is B
Shorter method Labour efficiency variance (8,000 – 8250 x £20) = £5,000 (F)
Tip: This variance calculation always uses the actual hours worked never hours paid if
there is a difference between the two within a question.
5.10 Answer is C
Tip: The high-low technique uses the highest and the lowest activity and associated
monetary values to predict a variable and fixed cost, by recognising cost behaviour.
This technique concentrates on splitting a semi-variable cost into its fixed and
variable categories in order to help predict cost.
The technique creates a linear relationship for cost forecasting, normally expressed as
Y= a + bX
264 | P a g e
Work out variable cost
Therefore
a = £10,000
b = £0.34675
265 | P a g e
5.12 Answer is £49.20 (F)
Tip: A material usage variance can be subdivided into a mix and yield variance where
there exists two or more ingredients that can be substituted for one another. The sum
of the material mix and yield variances will total the sum of the material usage
variance. The material mix variance can be calculated by using two different methods
and in this case the examiner has not specified which one to use, so I would
recommend the individual valuation basis because it is the easiest to apply. Both
methods give the same answer as a total sum, but the individual values to arrive at this
total will be different.
Material X X x £x = £x (F)
Material X X x £x = £x (A)
X X £x (A)
If you use a quantity of material which is more than standard mix there would
be an adverse variance
If you use a quantity of material which is less than standard mix there would
be a favourable variance
266 | P a g e
5.13 Answer is £151.20 (A)
Yield variance
Units of TRD100
2214 litres of X and Y did yield 72.0
2214 litres of X and Y should yield (2214 ÷ 30 litres per unit) 73.8
Under produced 1.8
5.14 Answer is D
This variance calculation always uses the actual hours paid for never hours worked if
there is a difference between the two within a question.
267 | P a g e
5.15 Answer is A
This variance calculation always uses the actual hours worked never hours paid if there
is a difference between the two within a question; the proforma is similar to the labour
efficiency variance
5.16 Answer is A
268 | P a g e
5.17 and 5.18
Tip: Planning variances are caused by the original budget and standard at the
planning stage being wrong. The original budget and standard used would therefore
need revising to make operational variances more realistic. Planning variances are
sometimes referred to as revision variances.
1. Calculate the planning variance and adjust the original budget within the
operating statement for this before any operational variances are calculated.
2. Adjust the standard used in the original budget from ex ante to ex post
(revised) standard.
3. Now that the original budget and standard have been adjusted, the operational
variances can be calculated and are more realistic for control purposes.
1. The planning variance, beyond the control of staff e.g. due to planning errors.
2. The operational variance, more likely to be within the control of staff.
£
Original budget (600 x £72) = 43,200
Planning sales price variance (W1) 6,000 (F)
Revised budget (600 x £82) 49,200
Original sales price variance (W2) 2,400 (F)
Actual sales (600 x £86) 51,600
269 | P a g e
5.19 Answer is $2,400 (A)
Tip: A material usage variance can be subdivided into a mix and yield variance where
there exists two or more ingredients that can be substituted for one another. The sum
of the material mix and yield variances will total the sum of the material usage
variance. The material mix variance can be calculated by using two different methods
and in this case the examiner has not specified which one to use, so I would
recommend the individual valuation basis because it is the easiest to apply. Both
methods give the same answer as a total sum, but the individual values to arrive at this
total will be different.
Material A X X x £x = £x (F)
Material B X X x £x = £x (A)
X X £x (A)
If you use a quantity of material which is more than standard mix there would
be an adverse variance
If you use a quantity of material which is less than standard mix there would
be a favourable variance
270 | P a g e
5.20 Answer is $650 (F)
Yield variance
Litres of output
10000 litres input did yield 9,100
10000 litres input should yield (10,000 x 0.9) 9,000
Under produced 100
W1 The standard cost of 9 litres of output is $58.50 therefore the standard cost of one
litre of output is $58.50 ÷ 9 litres = $6.50.
5.21 Answer is A
Y = a + bX
a = fixed cost (cost incurred regardless of the activity level for mileage) £800
b = variable cost (the cost of each mile) £0.0002
x = the activity level (the number of miles) 4100 miles
Y = £800 + £0.0002x2
This represents the forecast trend for miles. Once the forecast trend has been found
this would then need inflating by 3% e.g. multiply your answer by 1.03.
271 | P a g e
1. Work out the forecast ‘budgeted’ trend for the number of miles given
Y = £800 + £0.0002 (4,1002)
Y = £800 + £0.0002 (16,810,000)
Y = £800 + £0.0002 (16,810,000)
Y = £800 + £3,362
Y = £4,162
2. Adjust this for inflation
£4,162 x 1.03 = £4,287 flexed budgeted cost for 4,100 miles
3. Compare to actual operating cost to calculate the variance
Did cost £5,000
Should cost £4,287
Variance £713 (A)
5.22 Answer is C
This variance calculation always uses the actual hours worked never hours paid if there
is a difference between the two within a question e.g. idle time; the proforma is similar
to the labour efficiency variance.
Measures the difference between the variable overhead cost budget flexed on actual
labour hours and the variable overhead cost absorbed by output produced. Actual
output drives standard hours and therefore the absorption of variable production
overhead.
272 | P a g e
5.23 Answer is B
5.24 Answer is D
5.25 Answer is B
Tip: Planning variances are caused by the original budget and standard at the planning
stage being wrong. The original budget and standard used would therefore need
revising to make operational variances more realistic. Planning variances are
sometimes referred to as revision variances. These will ensure staff are not assessed on
variances which are caused by poor planning rather than their own operational
efficiency. This will improve motivation and performance by the removal of
uncontrollable factors when assessing staff performance.
1. Calculate the planning variance and adjust the original budget within the
operating statement for this before any operational variances are calculated.
2. Adjust the standard used in the original budget from ex ante to ex post (revised)
standard.
3. Now that the original budget and standard have been adjusted, the operational
variances can be calculated and are more realistic for control purposes.
1. The planning variance, beyond the control of staff e.g. due to planning errors.
2. The operational variance, more likely to be within the control of staff.
$
Flexed budget (10,000 units x 3kg x $4) = 120,000
Planning material price variance (W1) 30,000 (A)
Revised budget (10,000 units x 3kg x $5) = 150,000
273 | P a g e
W1 Planning material price variance
274 | P a g e
5.26 Answer is B
Tip: Variances are transferred to the income statement as either a debit (expense
increase) or credit (expense decrease) for an adverse or favourable variance
respectively. These variances represent the difference between expenses being
recorded at actual cost on the debit side and transfers during the period from these
accounts at standard cost on the credit side.
The fact that all material purchased was used for the period of February, means it
would not be necessary to adjust the actual cost of goods produced for the closing
stock of material.
£
Standard cost of goods produced 128,500
Variances F A
Material price 2,400
Material usage 8,400
Labour rate 5,600
Labour efficiency 3,140
Variable production overhead 2,680
Fixed production overhead 3,192
14,732 10,680
4,052 (F)
Actual cost of goods produced 124,448
275 | P a g e
5.27 Answer is C
Absorption costing is a method of costing that assigns fixed production overhead to cost
units, jobs or work-in progress accounts during a period, by using pre-determined
overhead absorption rates. Because overhead absorption rates are pre-determined at the
beginning of a financial period and fixed overhead is charged by the process of
absorption below, it is likely a difference or balance within the production overhead
control account will arise at the end of a financial period, this balance is referred to as an
under or over absorption.
Any surplus in fixed overhead absorbed during the financial period to the income
statement would be an ‘over absorption’ of production overhead
Debit Production overhead control account
Credit Income statement (to reduce fixed overhead absorbed)
Absorbed production overhead
less
Over absorption
=
Actual production overhead expense for the period.
276 | P a g e
5.28 Answer is $500 (F)
Tip: A material usage variance can be subdivided into a mix and yield variance where
there exists two or more ingredients that can be substituted for one another. The sum
of the material mix and yield variances will total the sum of the material usage
variance. The material mix variance can be calculated by using two different methods
and in this case the examiner has not specified which one to use, so I would
recommend the individual valuation basis because it is the easiest to apply. Both
methods give the same answer as a total sum, but the individual values to arrive at this
total will be different.
Material A X X x £x = £x (F)
Material B X X x £x = £x (A)
X X £x (A)
If you use a quantity of material which is more than standard mix there would
be an adverse variance
If you use a quantity of material which is less than standard mix there would
be a favourable variance
277 | P a g e
5.29 Answer is $11,305 (F)
A word of caution favourable variances, especially when dealing with mix and yield
do not necessarily mean you have improved the organisation e.g. adding far more
water and less flavouring could improve both mix and yield when making soft drinks,
but would do little to improve the quality of the drink being made.
Yield variance
Kg of Product S
2,000 Kg of P, Q and R did yield 1,910
2,000 Kg of P, Q and R should yield (2000 Kg x 90%) 1,800
Under produced 110
278 | P a g e
5.30 Answer is £49,500 (A)
(61,500 hours – 56,000 hours) = 5,500 hours x £9 (W1) per hour = £49,500 (A).
Tip: This variance calculation always uses the actual hours worked never hours paid
if there is a difference between the two within a question. A labour efficiency
variance is the difference between how long your workforce did and should have
taken according to actual production volume, valued at standard rate.
Shorter method: Labour efficiency variance (56,000 – 58,600 x £9) = £23,400 (F).
5.32 Answer is B
279 | P a g e
5.33 Answer is A
5.34 Answer is A
Traditional absorption costing takes the total budgeted fixed overhead for a period and
divides by a budgeted (or normal) activity level e.g. units, in order to find the overhead
absorption rate. This is a simple method of charging fixed overhead and allows fixed
overhead to be allocated to products, jobs or work-in-progress
The sum of the fixed overhead expenditure and volume variance would be equal to the
under or over absorption. F/OH Expenditure variance (£34,800 - £37,000) = £2,200 (A)
+ F/OH Volume variance (see below) £2,000 (A) = Under absorption of fixed overhead
for the period £4,200 (A).
280 | P a g e
5.35 Answer is B
Traditional absorption costing takes the total budgeted fixed overhead for a period and
divides by a budgeted (or normal) activity level e.g. units, in order to find the overhead
absorption rate. This is a simple method of charging fixed overhead and allows fixed
overhead to be allocated to products, jobs or work-in-progress
The total fixed production overhead variance is £100,000 (A) this represents the under
absorption of fixed overhead for the period.
The sum of the fixed overhead expenditure and volume variance would be equal to the
under absorption £100,000 (A). F/OH Expenditure variance (£1.0m - £1.3m) = £300,000
(A) + F/OH Volume variance ((240,000 – 200,000 units) x £5 OAR) = £200,000 (F) =
Under absorption of fixed overhead for the period £100,000 (A).
281 | P a g e
5.37 Answer is £3,600 (A)
1. Calculate the planning variance and adjust the original budget within the
operating statement for this before any operational variances are calculated.
2. Adjust the standard used in the original budget to the new (revised) standard.
3. Now that the original budget and standard have been adjusted, the operational
variances can be calculated and are more realistic for control purposes.
1. The planning variance, beyond the control of staff e.g. due to planning errors.
2. The operational variance, more likely to be within the control of staff.
Note: All possible variances have been calculated below to allow further revision,
however you were only required in the exam to calculate the material price planning
variance and the operational material usage variance.
£
Original budget (1,500 units x 7kg x £4.10) = 43,050
Planning material price variance (W1) 4,200 (A)
Revised budget (1,500 units x 7kg x £4.50) = 47,250
282 | P a g e
W3 Operating material price variance
£
12,000 kg did cost (12,000 kg x £4.35) = 52,200
12,000 kg should cost (12,000 kg x £4.50) = 54,000
1,800 (F)
5.38
Hours
Actual production did take (balance) 60,000
Actual production should take
(11,500 units x 5 hours) (57,500)
2,500
x standard labour rate per hour x £12
Labour efficiency variance 30,000 (A)
Using the labour efficiency variance calculation we can work out actual hours paid (and
worked) during the period. 60,000 hours can now be used to work out the actual labour
cost for the period.
£
Did spend (60,000 hours paid x actual rate) Balance 765,000
Should spend (60,000 hours paid x £12) (720,000)
Labour rate variance 45,000 (A)
The actual rate paid per direct labour hour = £765,000 ÷ 60,000 hours paid = £12.75
5.39 Answer is D
Fixed
Actual fixed overhead expenditure X
overhead
Budgeted fixed overhead expenditure (X)
expenditure
Fixed overhead expenditure variance X
variance
283 | P a g e
5.40 Answer is C
units
Did produce (actual quantity produced) X
Should produce (budget quantity produced) (X)
Fixed
X
overhead
x overhead absorption rate (O.A.R)
volume
Fixed overhead volume variance X
variance
This variance calculation is only applicable if the organisation uses
absorption costing, never when marginal costing.
Tip: A material usage variance can be subdivided into a mix and yield variance where
there exists two or more ingredients that can be substituted for one another. The sum
of the material mix and yield variances will total the sum of the material usage
variance. The material mix variance can be calculated by using two different methods
and in this case the examiner has not specified which one to use, so I would
recommend the individual valuation basis because it is the easiest to apply. Both
methods give the same answer as a total sum, but the individual values to arrive at this
total will be different.
Material X X x $x = $x (F)
Material X X x $x = $x (A)
X X $x (A)
If you use a quantity of material which is more than standard mix there would
be an adverse variance
If you use a quantity of material which is less than standard mix there would
be a favourable variance
284 | P a g e
Individual valuation basis
Yield variance
Units
1,280 kgs of X, Y and Z did yield 960
1,280 kgs of X, Y and Z should yield (1,280 x 80%) 1,024
Under produced 64
Yield variance = under or over production x standard cost of one unit (W1)
= 64 units x $7.125
= $456 adverse
Workings
285 | P a g e
5.43 Answer is C
An adverse fixed production overhead total variance means that the overheads have been
under absorbed. This means that actual overheads were greater than budgeted overheads.
We need to find out how much of the fixed overheads have been absorbed into
production and then dividing this by the budget overhead absorption rate (OAR) we can
find out actual production level.
286 | P a g e
5.46 Answer is A
Tip: This variance calculation always uses the actual hours worked never hours paid
if there is a difference between the two within a question. A labour efficiency
variance is the difference between how long your workforce did and should have
taken according to actual production volume, valued at standard rate.
Shorter method: Labour efficiency variance (56,000 – 58,600 x £9) = £23,400 (F).
5.47 Answer is C
5.48 Answer is A
5.49 Answer is B
287 | P a g e
5.50 Answer is A
5.51 Answer is B
288 | P a g e
5.52 Answer is B
In order to work out the expenditure variance we need to compare the budgeted
expenditure at 87% bed occupancy to the actual expenditure. We will calculate the
variable cost for each 1% increase in bed occupancy by comparing the costs of the flexed
budgets given.
Machine hours Cost ($)
82% 410,000
94% 429,000
12% 19,200
5.53 Answer is A
Internal benchmarking
5.54 Answer is A
5.55 Answer is C
5.56 Answer is A
5.57 Answer is D
Weighted average standard price per kg (0.6/1.2 x £5.60) + (0.6/1.2 x £1.40) = £3.50
289 | P a g e
5.58 Answer is C
5.60 Answer is A
Should take 4hrs x 4,260 units = 17,040 hours therefore if adverse it took 426 hrs longer
than expected.
5.61 Answer is D
Closing stock rose by 800kg therefore must have purchased 6,750kg + 800kg = 7,550kg
290 | P a g e
5.62 Answer is A
5.63 Answer is A
5.64 Answer is C
Planning
60 x 0.6 (old standard) x £5.50 an hour £198
60 x 0.5 (new standard) x £5.50 an hour £165
£33(F)
Operational
60 units did take 40 hours
60 units should take (x 0.5) 30 hours
10 hours
x £5.50
£55(A)
291 | P a g e
292 | P a g e
Chapter 6 Solutions - Modern manufacturing methods
6.1 Answer is A
6.2 Answer is D
6.3 Answer is C
Cost of Sales
DR CR
£ £
1000 units x £100 100,000 Income statement 105,000
Conversion (W1) 5,000
105,000 105,000
W1 Standard cost per unit is £100 of which £45 is raw material. Therefore the standard
cost of conversion per unit is (£100 - £45 = £55). 1000 units x £55 = £55,000 conversion
charged to cost of sales, which means if £60,000 conversion was actually incurred
(£60,000 - £55,000) = £5,000 further charge to cost of sales for the period.
Conversion
DR CR
£ £
Bank 60,000 Cost of sales (£55 x 1000 units) 55,000
Variance to cost of sales 5,000
60,000 60,000
293 | P a g e
6.4
Part (a)
Product B 50 units x 2.0 hrs 100 50 units x 5.5 hrs 275 50 units x 1.0 hrs 50
Product C 60 units x 1.5 hrs 90 60 units x 1.5 hrs 90 60 units x 0.5 hrs 30
Part (b)
The bottleneck machine (or limiting factor) would be machine 2. It is the most binding
constraint on production e.g. the most restricting of all machines to meet the estimated
sales demand given. It has the highest utilisation rate of all three machines of 154%.
6.5
Part (a)
1) Identify a systems bottleneck or most limiting factor that restricts the flow of
throughput.
2) Focus attention on achieving higher throughput from the bottleneck e.g. exploit or
alleviate it.
3) Subordinate all other resources to this bottleneck e.g. operate the bottleneck
resource at 100% capacity, whilst running non-bottleneck resources at a speed
that matches this which may not be 100%.
4) Elevate the bottleneck e.g. try and increase throughput from it either by improving
its efficiency or procuring more of it if possible.
5) Repeat steps 1-4 as once the bottleneck is eliminated another will become
apparent and take its place.
294 | P a g e
Part (b)
Product A Product B Product C
J K L M
£ £ £ £
SP 2,000 1,500 1,500 1,750
Material cost (410) (200) (300) (400)
Throughput contribution 1,590 1,300 1,200 1,350
Ranking 2 3 1 4
6.7 Answer is D
295 | P a g e
6.8 Answer is A
.
Tip: Flexible manufacturing system (FMS) consists of several machines along with
part and tool handling devices such as robots, arranged so that it can handle any
family of products or parts for which the system has been designed and developed.
Such systems aim to achieve greater economies of scope for the manufacturer, the
capability of economic production of small batches of a variety of products or parts
with minimal set up time. These systems are computerised and highly integrated.
The idea of an FMS was proposed in England (1960s) under the name “System 24”, a
flexible machining system that could operate without human operators 24 hours a day
under computer control. From the beginning the emphasis was on automation rather than
the “reorganization of workflow”.
Early FMSs were large and very complex, consisting of dozens of Computer Numerical
Controlled machines (CNC) and sophisticate material handling systems. They were very
automated, very expensive and controlled by incredibly complex software. There were
only a limited number of industries that could afford investing in a traditional FMS as
described above.
Currently, the trend in FMS is toward small versions of the traditional FMS, called
flexible manufacturing cells (FMC).
Today two or more CNC machines are considered a flexible cell and two ore more cells
are considered a flexible manufacturing system.
296 | P a g e
6.9
Z1 Z2
Department 1 480 minutes ÷ 12 = 40.0 480 minutes ÷ 16 = 30.0
Department 2 840 minutes ÷ 20 = 42.0 840 minutes ÷ 15 = 56.0
6.10
Z1 Z2
Selling price 50.00 65.00
Less:
Direct material 10.00 15.00
Direct labour 10.40 6.20
Variable overhead 6.40 9.20
Contribution per unit (£) 23.20 34.60
Given there is no maximum sales demand for product Z2 the total of 480 minutes each
day for department 1 should be allocated to making this product. The maximum
contribution earned would therefore be 480 minutes x £2.16 contribution earned per
minute = £1,036.80 contribution per day. 480 minutes would make (480 minutes ÷ 16
minutes) 30 units of product Z2.
297 | P a g e
6.11
Throughput Contribution
=
sales less material cost only ‘the only true variable cost’
Z1 Z2
Selling price 50.00 65.00
Less:
Direct material 10.00 15.00
Throughput contribution per unit (£) 40.00 50.00
Given there is no maximum sales demand for product Z1 the total of 480 minutes each
day for department 1 should be allocated to making this product. The maximum
throughput contribution earned would therefore be 480 minutes x £3.33 throughput
contribution earned per minute = £1,598.40 throughput contribution per day. 480
minutes would make (480 minutes ÷ 12 minutes) 40 units of product Z1.
6.12 Answer is B
Cost of Sales
DR CR
£ £
Cost of finished goods sold 1,700,000 Income statement 1,750,000
Conversion (W1) 50,000
1,750,000 1,750,000
298 | P a g e
W1 £840,000 conversion was allocated (or charged) during the period to finished goods
produced. If £890,000 conversion was actually incurred then (£890,000 - £840,000) =
£50,000 further would need to be charged to cost of sales for the period e.g. a conversion
under absorption or variance.
Conversion
DR CR
£ £
Bank 890,000 Finished good produced 840,000
Under absorption to cost of sales 50,000
890,000 890,000
There would be (£1,795,000 - £1,700,000) = £95,000 closing inventory for the period,
included within finished goods produced.
6.13 Answer is B
6.14 Answer is A
6.15 Answer is B
Tip: The JIT philosophy requires that products should only be produced if there is an
internal or external customer waiting for them. Traditionally manufacturers
stockpiled. JIT aims ideally for zero stock e.g. raw materials delivered immediately
at the time they are needed, no build up of work-in-progress during production and
finished goods only produced if there is a customer waiting for them.
Tip: Flexible manufacturing system (FMS) consists of several machines along with
part and tool handling devices such as robots, arranged so that it can handle any
family of products or parts for which the system has been designed and developed.
Such systems aim to achieve greater economies of scope for the manufacturer, the
capability of economic production of small batches of a variety of products or parts
with minimal set up time. These systems are computerised and highly integrated.
299 | P a g e
Tip: Materials requirement planning (MRP I) is an information system which
provides an automated list of components and materials required for the type and
number of products entered. This allows better production planning and stock
management.
6.16
Throughput contribution
=
sales less material cost only ‘the only true variable cost’
W X Y
£ £ £
Selling price 200 150 150
Direct materials 41 20 30
Throughput contribution per unit 159 130 120
Bottleneck (minutes) 9 10 7
300 | P a g e
6.17
A B C
£ £ £
Selling price 200 150 150
Direct materials 41 20 30
Throughput contribution per unit 159 130 120
Bottleneck (minutes) 12 10 7
6.18 Answer is A
6.19 Answer is B
A marginal costing system would value inventory at variable production cost only not
full production cost.
301 | P a g e
Therefore:
6.20 Answer is D
The throughput accounting approach is essentially the same principle as marginal costing,
but values inventory at material cost only.
6.21
Return per factory hour is similar to the concept of contribution maximisation; you
should notice the following calculation is similar to the contribution per unit of a limiting
factor used in short-term decision-making
Throughput accounting (TA) ratio demonstrates how much benefit or contribution per
hour we are receiving compared to our costs per hour when we manufacture a product. A
ratio of less than 1 means that costs per hour is greater than contribution per hour. A ratio
of greater than 1 means that contribution per hour is greater than costs per hour.
6.22 Answer is D
6.23 Answer is C
Customer compensation costs are costs that have been incurred after the product has left
the company, and so therefore is an external failure cost.
Test equipment running costs are costs to do with the assessment of quality and so
therefore an appraisal cost.
6.24 Answer is A
W X Y
Selling price 180 150 150
Less:
Direct material 41 20 30
Direct labour 30 20 50
Variable production overheads 24 16 20
Contribution per unit (£) 85 94 50
6.25 Answer is B
W X Y
Selling price 180 150 150
Less:
Direct material 41 20 30
Throughput contribution per unit (£) 139 130 120
303 | P a g e
6.26 Answer is D
6.27 Answer is C
Time in Process A 20 25 15
(mins per unit)
6.28 Answer is D
Time in Process A 20 25 15
(mins per unit)
6.29 Answer is D
6.30 Answer is A
6.31 Answer is D
Economically producing small batches of a variety of products with the same machines
304 | P a g e
6.32 Answer is D
6.33 Answer is A
6.34 Answer is D
6.35 Answer is B
Job
6.36 Answer is C
Elimination of waste
Throughput time
= work-in-process (1,000 customer enquires) x cycle time (30 minutes average duration)
6.39 Answer is B
6.40 Answer is C
Focus factories
6.41 Answer is A
Lean synchronisation
6.42 Answer is A
Removal of waste
305 | P a g e
6.43 Answer is D
6.44 Answer is A
Quality circles
6.45 Answer is D
Transaction
6.46 Answer B
Feedback Control
6.48 Answer is customer complaint departments, poor brand reputation, cost of free
repairs under gurantee.
6.49 Answer is C
6.50 Answer is C
6.51 Answer is B
6.52 Answer is C
6.53 Answer is D
Removal of waste
6.54 Answer is C
Inventory management
306 | P a g e
6.55 Answer is A
6.56 Answer is C
6.57 Answer is D
6.58 Answer is A
Just-in-time (JIT)
6.59 Answer is C
307 | P a g e
308 | P a g e
Chapter 7 Solutions - Environmental cost accounting
7.1 Answer is A
7.2 Answer
7.3 Answer
7.4 Answer
7.5 Answer
309 | P a g e
7.6 Answer
Landfill tax
Income tax
Court imposed fine on illegal dumping of waste
Road tax
7.7 Answer
A one off tax on company profits to pay for new recycle bins
Company fine for using toxic illegal chemcials in manufacture
Increased fuel duty
A tax on tobacco to fund additional hospitals in the UK
7.8 Answer
Increase productivity
Reduces pollution
Increases profits
Increases goodwill with customers
7.9 Answer
7.10 Answer
Energy and water consumption have proven to be both very costly to businesses as well
as having significant impact on the environment through increased carbon emissions.
Businesses should look towards ways of conserving the use of these resources as far as
practicable. Energy and water consumption are closely linked as energy is needed to heat
up water and so a reduction in water useage would mean a reduction in energy useage as
well.
310 | P a g e
7.11 Answer
7.12 Answer
7.13 Answer
7.14 Answer
Tracking systems for environmental wastes are needed in order to assign costs
It does not allows us to use cost data to develop superior strategies
Does not allow intangible and uncertain environmental factors to be brought
into the decision-making framework
Requires clear definition of environmental costs
311 | P a g e
7.15 Answer
7.16 Answer
Emissions trading
Transfer pricing
Clean development mechanism
Joint implementation
7.17 Answer
7.18 Answer
7.19 Answer
312 | P a g e
Chapter 8 Solutions - Decision theory
It is therefore worthwhile for the company to undertake the marketing campaign as the
increase in the expected value of profit is $7,000
We need to work out the probability of earning more than or equal to a contribution of
$40. Therefore we need to select those outcomes which will yield this and select their
respective probabilities to multiply to make the combined probabilities.
313 | P a g e
8.4 Answer is $110
Therefore if the manager wants to maximise the minimum profit a selling price of $110
would be chosen.
Therefore if the manager wants to minimise the maximum regret a selling price of $100
would be chosen.
8.6 Answer is B
8.7 Answer is B
Therefore if the committee wants to maximise the minimum cash inflow it will set a fee
of $800.
314 | P a g e
8.8 Answer is A
Membership level
Membership Fee Low Average High
$000 $000 $000
$600 40 0 0
$800 0 40 60
$900 40 75 45
$1,000 80 100 120
Therefore if the manager wants to minimise the maximum regret a fee of $600 a selling
price of $100 would be set.
8.9 Answer is C
8.10 Answer is C
Deluxe is $35,000
High is $20,000
Standard is $7,500
Low is $20,000
The fixed costs will remain the same therefore the contribution has to exceed $2,880,000.
The outcomes that comply with this and the probability of them occurring are given
below:
The probability therefore that the contribution will exceed $2,880,000 is 90%.
8.12 Answer is B
$40 is $20,000
$45 is $10,000
$50 is $20,000
$55 is $30,000
Therefore if the manager wants to minimise the maximum regret, a selling price of $45
will be selected.
8.13 Answer is A
(i)
Expected values ($000)
Project A ($400 x 0.3) + ($500 x 0.5) + ($600 x 0.2) = $490
Project B ($300 x 0.3) + ($350 x 0.5) + ($400 x 0.2) = $345
Project C ($500 x 0.3) + ($450 x 0.5) + ($650 x 0.2) = $505
(ii)
Value of perfect information ($000)
If weak select Project C = ($500 x 0.3) = $150
If average select Project A = ($500 x 0.5) = $250
If good select Project C = ($650 x 0.2) = $130
Value of perfect information is ($530 – $505) = $25
316 | P a g e
8.15 Answer is D
$140 is $50,000
$160 is $60,000
$180 is $40,000
$200 is $30,000
Therefore if AP wants to minimise the maximum regret it will select a selling price of
$200
8.16 Answer is A
8.17 Answer is C
* The probability of being dry is 0.4 therefore the probability of being rainy is (1.0 – 0.4)
= 0.6. The sum of your probabilities must always come to 1.0.
Tip: An expected value works out a long-run average based upon a decision repeated
over and over again, based upon the values forecast and probability assigned to each
value.
Example
An ice cream sales van if it is hot will earn £10,000 a day in sales and if it is cold only
£2,000 a day in sales, the probability of the weather cycle all year round is 10% hot and
90% cold.
317 | P a g e
Solution
An expected value calculates a long-run average value assuming the decision is repeated
over and over again e.g. the ice cream van does not just go once but many times over and
over again.
8.18
Project EV
L (500 x 0.2) + (470 x 0.5) + (550 x 0.3) = $500,000
M (400 x 0.2) + (550 x 0.5) + (570 x 0.3) = $526,000
N (450 x 0.2) + (400 x 0.5) + (475 x 0.3) = $432,500
O (360 x 0.2) + (400 x 0.5) + (420 x 0.3) = $398,000
P (600 x 0.2) + (500 x 0.5) + (425 x 0.3) = $497,500
8.19
318 | P a g e
8.20
Answer is 45%
We need to work out the probability of earning more than a weekly contribution of
$20,000. Therefore we need to select those outcomes which will yield this and select their
respective probabilities.
We are producing 1,000 units per week so therefore contribution must be greater than
$20 per unit, in order for us to earn more than $20,000 per week.
8.21 Answer is D
To find the monthly expected value we must multiply the probabilities by their respective
unit sales values or unit variable cost values. This will give us our expected unit sales and
variable cost values.
Expected unit sales value = (£20 x 0.25) + (£25 x 0.40) + (£30 x 0.35) = £25.50
Expected unit variable cost value = (£8 x 0.20) + (£10 x 0.50) + (£12 x 0.30) = £10.20
Subtract the expected variable cost value from the sales value which would result in the
monthly unit contribution.
319 | P a g e
8.22 Answer is C
In order to achieve a monthly contribution of greater than £13,500 and we expect to sell
1,000 units then each unit must sell for more than £13.50. We should select the
combinations which offer us that and then add up their respective probabilities.
P(Monthly contribution exceeds £13,500) = 0.08 + 0.20 + 0.07 + 0.175 + 0.105 = 0.63
The key point to understand here is that you need to find the solution that will minimise
the maximum opportunity cost or if you like regret. We need to first find what
contributions can be earned by the different combinations.
Sold
Made 10 11 12
10 500 500 500
11 500 – 20 = 480 550 550
12 500 – 40 = 460 550 – 20 = 530 600
Now we work out how much contribution we would lose for those items we did not
make. Please note this is the £50 contribution per batch and the £20 negative contribution
per batch.
Sold
Made 10 11 12
10 0 50 100
11 20 0 50
12 40 20 0
Compare the best outcomes in the first table with the maximum opportunity cost or regret
in the second for each batch of bread made. Select the batch with the most amount of
contribution left.
320 | P a g e
10 batches = 500 – 100 = 400
11 batches = 550 – 50 = 500
12 batches = 600 – 40 = 540
Therefore the answer is to make 12 batches as this will minimise the opportunity cost or
regret.
Σp=1
_
Standard deviation or S.D. = √ Σ p(x - x)² / Σ p = √29,560,000,000 / 1= $171,930
321 | P a g e
Variable Probability Expected
costs ($) value ($)
70,000 0.40 28,000
90,000 0.35 31,500
110,000 0.25 27,500
Total EV 87,000
8.26
Part (i)
The maximin rule states that we should consider the worst consequence of each possible
course of action and choose the one that has the least bad consequence.
Therefore in the scenario the worst consequence is having bad weather and the least bad
consequence would be to purchase 1,000 burgers as this gives the most profit being
$1,000.
Part (ii)
The key point to understand here is that you need to find the solution that will minimise
the maximum opportunity cost or if you like regret.
We work out how much contribution we would lose for those burgers we did not sell. For
example if we have actual bad weather then we would sell 1,000 burgers and had we
purchased 1,000 burgers then the profit earned would be $1,000 (according to the table in
question) with no regret or cost of unsold burgers, net regret being $0.
If however the actual weather was bad then again we would sell 1,000 burgers but this
time we had purchased 2,000 burgers then the profit earned would be $0 but regret or
cost would $1,000, net regret being $1,000.
We can apply the same logic if we had purchased 3,000 or 4,000 burgers. See table
below:
No of burgers purchased
If actual weather is: 1,000 2,000 3,000 4,000
Bad $0 ($1,000) (£2,000) ($4,000)
Average ($4,000) ($1,000) $0 ($1,000)
Good ($9,000) ($6,000) ($3,000) $0
322 | P a g e
The maximum regret for:
1,000 burgers is $9,000
2,000 burgers is $6,000
3,000 burgers is $3,000
4,000 burgers is $4,000
We need to work out the probability of earning net cash flows $90,000 or more.
Therefore we need to select those outcomes which will yield this and select their
respective probabilities. The combinations which will comply are:
Project EV
A (400 x 0.3) + (500 x 0.2) + (700 x 0.5) = $570,000
B (800 x 0.3) + (300 x 0.2) + (200 x 0.5) = $400,000
C (500 x 0.3) + (600 x 0.2) + (400 x 0.5) = $470,000
323 | P a g e
8.29 Answer is B
Risk averse managers (maximin managers or “pessimist”) assume always the worse
outcome will arise, therefore aim to maximise the returns from the worst outcomes.
Therefore, the marketing manager would choose selling price of $60 as the worst case
scenario is $30,000 contribution being earned which is the best of all the worst case
scenarios.
8.30 Answer is D
If development is successful then the company will market the product and therefore we
need to work out the EV of marketing success.
This is a probability distribution and therefore the squared deviations (column 5 below)
have to be weighted by the probabilities. We cannot do the usual operation of dividing
the squared deviations by the number of data items (being 3 in this case) as the three
NPV’s do not have equal chance of occurrence and therefore must be reflected in the
calculation.
_ _ _ Weighted
NPV($) Probability EV or x ($) x-x (x – x)² Deviations
2,800 0.25 700 -1,175 1,380,625 345,156.25
3,900 0.40 1,560 -75 5,625 2,250
4,900 0.35 1,715 925 855,625 299,468.75
3,975 646,875
Risk averse managers (maximin managers or “pessimist”) assume always the worse
outcome will arise, therefore aim to maximise the returns from the worst outcomes.
Risk seeking managers (maximax managers or “optimist”) go for the best outcome
ignoring the probability of actually attaining it, when making decisions, therefore aim to
maximise the maximum or best return from a decision.
Risk neutral managers go for the most likely return and will use expected values in
order to make a decision.
The minimax regret criterion is to find the solution that will minimise the maximum
opportunity cost or regret of decisions made. The question gives us the regret or
opportunity cost we would suffer if we chose any of the venues. For each venue we need
to select the most regret that we would suffer, and then from this select the venue with the
lowest of these maximum regrets, i.e. minimise the maximum regrets.
Deefield should be picked as the venue to stage the event as it minimises the maximum
regrets.
8.34 Answer is A
The maximin rule states that we should consider the worst consequence of each possible
course of action and choose the one that has the least bad consequence. Therefore in the
scenario the worst consequence is having a poor market condition and the outcomes are:
Project A $440,000
Project B $400,000
Project C $360,000
Project D $320,000
325 | P a g e
8.35 Answer is B
The maximax rule states go for the best outcome ignoring the probability of actually
attaining it, when making decisions, therefore aim to maximise the maximum or best
return from a decision.
8.37 Answer is A
4 x £15k = 60k
0.4
A (10k)
£96k 0.6 8 x £15k = 120k
N
£86k 4 x £15k = £60k
A = Attend show
N = Not attend show
The decision to go to the show yields contribution after the £10,000 running cost of
£86,000, compared to the contribution of selling 4 cars without going to the show
generating £60,000 contribution. The expected net gain therefore would be £86,000 -
£60,000 = £26,000.
326 | P a g e
8.38 Answer is D
A = Attend show and pay for market research
N = Not attend show and do not pay for market research
4 x £15k = 60k
£90k Wrong
0.3 8 x £15k = 60k
£90k 0.6
Therefore the most you will pay for the market research with imperfect information
would be £90,000 – £60,000 = £30,000.
Other decision trees could have represented the decision differently e.g. could have
shown better or worse first and then right or wrong for the market research company last
on the decision tree
Evaluation:
The market research company is right (0.7) and the competition is going to be better (0.4)
you therefore do not go as you will sell 4 cars anyway.
The market research is right and the competition is worse (0.6) you therefore do go and
sell 8 cars but will have to incur 10k exhibition costs.
The market research is wrong (0.3) and the competition you find is better (0.4), you
would not have gone had you been told this, but you would go because they were wrong
so you would sell 4 cars and incurred 10k exhibition costs for doing so.
The market research is wrong (0.3) and the competition is worse (0.6), you would have
gone but seeing as they predicted the competition would be better, you would have stayed
away, sold 4 cars anyway, but incurred no exhibition costs.
327 | P a g e
In the above decision you would have always sold 4 cars any way so you could have
excluded the 4 cars sold at every stage of the decision process.
The decision tree is the same as above but ignores 4 cars sold (earning £60k contribution,
every stage of each decision. This would also allow you to calculate the answer quicker.
£0
£0
0.4
N
Right
0.7 £30k 0.6 £50k
A
£19.8 -£10k
0.4
£19.8 Wrong
0.3
-£4k 0.6
£0
Probability of attending the show and finding competition is worse than you
= 0.7 x 0.6 = 0.42.
Incremental contribution 8 cars – 4 cars sold anyway = £60k -£10k cost = £50k.
Probability of attending the show and finding the competition is better than you
= 0.3 x 0.4 = 0.12.
Incremental contribution 4 cars – 4 cars sold anyway = £0k –10k cost = -£10k.
328 | P a g e
8.39 Answer is C
£0
0.4
£60k
-20k
£27k 0.5
£7k 0.6
329 | P a g e
330 | P a g e
Chapter 9 Solutions - Linear programming
9.1 Answer is C
9.2 Answer is B
9.3 Answer is C
9.4 Answer is D
9.5 Answer is D
We currently produce already 1200 of product B and 2500 of product C, using up the
maximum of 8100 machine hours.
If a further 2000 machine hours were offered we could produce another 500 of product C
and 250 of product A (product C will use 500 units x 3hrs a unit = 1500, the balance of
500 hrs would use 2 hrs a unit for product A
The shadow price would be (500 units x £8.40) + (250 units x £5.00) = £5,450 also this
would be the contribution earned. However the contribution is arrived at after the
deduction of the normal cost of a machine hour so to get the maximum price we must add
the normal cost of 2000 machine hours (2000 x £0.70 = £1,400). Therefore the maximum
price will be £1,400 + £5,450 = £6,850
9.6 Answer is D
331 | P a g e
Subtract equation (1) from the above equation. Therefore:
9.7 Answer is D
9.8 Answer
9.9 Answer
Dual price
Extra contribution earned
A scarce resource
A limiting factor
Slack variable
The feasible region
Maximum price
A unit of a constraint
332 | P a g e
9.10 Answer
A limiting factor
They identify the main objectives
Show the limits of resources available
Where the answer is always positive
Slack variable
The feasible region
Where the answer is always negative
9.11 Answer is A
Whre the constraints intercept each other is our optimal solution. We will need to solve
using simultaneous equations.
2F + 3G = 10,800 (equation 1)
3F + 2G = 10,000 (equation 2)
4F + 6G = 21,600
9F + 6G = 30,000
4F + 6G = 21,600
9F + 6G = 30,000
-5F = -8,400
F = 1,680
2 (1,680) + 3G = 10,800
3,360 + 3G = 10,800
3G = 7,440
G = 2,480
333 | P a g e
9.13 Answer is B
D E F
Contribution per hour (£54 / 1) = £54 (£72 / 1.5) = £48 (£35 / 0.5) = £70
Rank 2 3 1
Therefore:
(1,000 x E) + (2,400 x D) + (3,000 x F)
9.14 Answer is B
9.15 Answer is D
Product L M
Material per unit 10/5 = 2 kg 45/5 = 9kg
Contribution per kg 22/2 = $11 11/9 = $1.22
Kg used
L 400 units x 2 kg 800
M 6,000 kg – 800 kg = 5,200 kg 5,200 kg / 9 kg = 577 units 5,193
5,993
Production
L 400
M 577
334 | P a g e
9.16 Answer is C
Product R T
Labour
hrs used
R 500 units x 3 hrs 1,500
T 5,000 hrs – 1,500 hrs = 3,500 hrs 3,500 hrs / 5 hrs = 700 units 3,500
5,000
P4 P6 C3 C5
$ $ $ $
Rank in order
4 1 2 3
of production
335 | P a g e
336 | P a g e
Chapter 10 Solutions - Relevant costing
10.1 Answer
Future costs
Sunk costs
Incremental costs
Avoidable costs
Fixed costs
Common costs
Differential costs
10.2 Answer is B
400kg in stock – if not used could be sold for (400 x £1.75) £700
100kg extra required – at current cost (£4.50 x 100) £450
£1,150
10.3 Answer is B
10.4 Answer
10.5 Answer is B
10.6 Answer is C
10.7 Answer is A
10.8 Answer is A
10.9 Answer is B
337 | P a g e
10.10 Answer is B
The lowest cost option would be to retrain the existing employees therefore the relevant
cost is £80,000
Salaries of existing staff and the manager’s apportioned salary cost is irrelevant when
decision-making.
10.11 Answer is D
The minimum price that ZYP Ltd should accept for the above contract , using relevant
costing would be:
The net book value is an ‘historical cost’ and therefore not relevant when decision
making
10.12 Answer is B
10.13 Answer is B
Skilled labour can either be obtained by asking staff to do overtime or stop production of
another product, because there is no skilled labour available.
Choose the cheapest option which would be paying staff overtime, therefore $300.
338 | P a g e
10.15 Answer
Incremental costs
Committed costs
Sunk costs
Differential costs
Absorbed fixed costs
Opportunity costs
10.16 Answer is B
10.17 Answer
10.18 Amswer
Costs used for decision making include only costs that are affected by the
decision.
Costs used for decision making never include fixed costs.
Costs used for decision making do not include past costs.
Costs used for decision making include opportunity costs.
10.19 Answer is B
Compare the company’s variable costs for each compnonet with supplier’s price to see
which is cheaper to buy in. Fixed costs are ignored as they are sunk.
339 | P a g e
10.20 Answer is B
40% of fixed overheads are relevant and need to be deducted to find the real contrbutions
earned. This is because they are specific costs that have to be spent by each divison if
they are to manufacture.
Each divison will get an equal share of $210, therefore $70 each. Now work out
contribution:
10.21 Answer
10.22 Answer is B
10.23 Answer is D
10.24 Answer is D
10.25 Answer is D
10.26 Answer is B
You take the higher of the scrap value and what you can save in material if you can use it
in another project or production.
10.27 Answer is C
340 | P a g e
10.28 Answer is $2,000
The machine hire cost is based on 5 days multiplied by a hire charge of $500 per day.
However, this is not the relevant cost because there is a lower cost option available.
If the machine is hired for an entire month at a cost of $5,000 and then sub hired for $150
per day for 20 days (total $3,000) the net cost of this option is $2,000. Therefore the
relevant cost is $2,000.
10.29 Answer is C
The overheads are fixed and therefore ignored, but the machine power costs will be
incurred as a result of this job, and so therefore we should include these costs. £0.75 x
10hrs = £7.50.
10.30 Answer is B
It is a direct material which is regularly used and therefore we would need to use the
replacement cost to value it for the quote. 500m² x $5.50 = $2,750
Skilled labour can either be obtained by asking staff to do overtime or stop production of
another product, because there is no skilled labour available.
Choose the cheapest option which would be paying staff overtime, therefore $945.
10.32 Answer
$20
$400
$1,080
$880
$460
$480
$0
341 | P a g e
10.33 Answer is M and N only
To work out the optimal processing plan we need to also consider the extra benefit
compared to the extra cost involved in processing M, N and P further.
The optimal processing plan is to make products M and N further as they yield further
profits, but not product P as it yields a further loss.
If we were to go ahead with this contract we would need to obtain a replacement coach to
cover existing obligations. If this is ignored then we lose contribution and incur
significant penalties on existing obligations.
Replacement coach costs = $180 x 2 days = $360 or if we don’t honour our current
obligations then we would lose contribution of $250 x 2 days = $500. It is cheaper to hire
replacement coach for $360.
Ronnie only needs his driver for a 1 day bank robbery. All the other days he is not
required. Therefore we need to hire a replacement driver for 1 day to cover the bank
robbery. Therefore $400 x 1 day = $400.
10.36 Answer is $0
342 | P a g e
10.37 Answer is make RZ, TZ and S
We need to work out the extra benefit of making RZ, SZ and TZ and then compare these
to the extra cost involved. We should make those which give a net extra benefit.
Product S should not be further processed to make product SZ as there is net cost of
$0.15 per kg every time an SZ is produced.
10.38 Answer is C
Shops that are making contribution losses should be shut down and overheads are sunk
and so therefore their apportionment is irrelevant.
10.39 Answer is C
10.40 Answer is B
This would be the $10,000 less the $19,000 of specific fixed overheads, therefore $9,000
loss which will now not be incurred if shut down.
(To get $19,000 remove the $7,000 from the $26,000 of overheads to be left with the
specific fixed overheads which is relevant).
343 | P a g e
10.41 Answer is B
10.42 Answer is C
The definition given applies to an incremental cost; an additional cost that will result
when a particular course of action is taken.
10.43 Answer is D
10.44 Answer is A
344 | P a g e
Mock Exam 1
M1.1
When output levels increase which one of the following is more likely considered true?
M1.2
Within a relevant range of output, as output increases which one of the following would
be correct about fixed cost?
M1.3
345 | P a g e
M1.4
The data below has been extracted from the cost accounting records of a company. The
data shows the total cost and the inflation index relevant to the period in which the costs
were incurred.
The best estimate of the variable cost per unit of output at an inflation index of 1.06, to
the nearest $0.01 is:
A $2.44
B $2.75
C $2.30
D $3.14
M1.5
The variable cost per unit will reduce by 5% for output levels above 45,000 units. The
reduced cost per unit will apply to all units.
If the high-low method is used to estimate costs, the budgeted total costs for an output
level of 50,000 units is:
A $522,800
B $427,500
C $525,500
D $480,000
346 | P a g e
M1.6
A A break-even chart
B A profit-volume chart
C A variable cost chart
D A semi-variable cost chart
M1.7
A company has a contribution to sales (C/S) ratio of 40%. Fixed cost estimated for the
period is $100,000.
For the company to earn a profit of $250,000, its sales revenue would be?
M1.8
X
What type of chart is best represented by the diagram above?
A A break-even chart
B A profit-volume chart
C A variable cost chart
D A semi-variable cost chart
347 | P a g e
M1.9
According to a profit volume (PV) chart, when selling price per unit increases, the point
at which the profit line cuts the horizontal axis of the chart would?
M1.10
According to a profit volume (PV) chart, when selling price per unit increases, the point
at which the profit line intersects the vertical axis of the chart would?
M1.11
According to a profit volume (PV) chart, when fixed cost decreases, the point at which
the profit line intersects the vertical axis of the chart would?
A Shift upwards
B Shift downwards
C Disappear off the chart
D Remain on the same point
348 | P a g e
M1.12
£ £
Less:
60,000
Less
90,000
What is the margin of safety (in units) if budgeted output for the period is 85,000
units?
M1.13
A college offers discounts of 10% to students who pay on enrolment and 50% of
customers pay on enrolment. The extra sales needed to increase cash receipts by £20,000
would be?
A £20,000
B £21,053
C £22,000
D £44,000
349 | P a g e
M1.14
A flexible budgeting system exists for an organisation and financial details for the budget
period are provided below.
40% 60%
What would be the total budgeted cost allowance for 70% level of activity?
M1.15
Which one of the following reasons is more likely to explain why budgeted production
and sales would be different?
M1.16
Forecast monthly sales will be £20,000 and this trend is expected to continue throughout
the year.
20% of customers will pay by cash and will be given a 10% discount. Of the remaining
80% credit sales, 60% will settle within one month after sale and 40% will settle 2
months after sale.
A £212,800
B £232,800
C £237,600
D £240,000
350 | P a g e
M1.17
M1.18
Which of the following sentences is the best representation of the behavioural aspects of
budgeting?
A If budget targets are unrealistic there may be a negative reaction from individuals
B It is seldom necessary to involve employees in the budgetary process
C Budgets will always improve motivation
D Budgets will always improve participation
351 | P a g e
M1.19
A Zero-base budgeting starts with the figures of the previous period and assumes a
zero rate of change
M1.20
Which of the following is not a broad cost classification category typically used in
activity based costing?
A Unit level
B Batch level
C Product sustaining level
D Operational level
M1.21
In an activity based costing system, direct labour used would typically be classified as a:
M1.22
A Dispatching
B Receiving and inspection
C Income tax
D Quality assurance
352 | P a g e
M1.23
M1.24
Tyson is developing a new range of vacuum cleaners that use turbine power technology.
The research costs for this technology are said to come from:
M1.25
Which of the statements if any are true regarding product sustaining activities?
M1.26
M1.27
The salaries of the finance department staff in a manufacturing company are from:
353 | P a g e
M1.28
Place the following costs in the correct coulumn for batch level activity and facility level
activity, select all that apply.
Shipping
Plant depreciation
Inspection
Quality assurance
Plant maintenance
Direct materials
Material handling
Property taxes
Insurance
Battersea tyres uses an activity based costing system to compute the cost of making
premium tyres and delivering the tyres to garages. Staff costs are £80,000 and make and
deliver the tyre. Other general overheads are £70,000.
354 | P a g e
M1.29
What is the staff costs and general overheads that would be charged to each tyre?
A £0.88
B £1.40
C £2.28
D Some other amount
M1.30
What is the staff costs and general overheads that would be charged to each delivery?
A £6.17
B £2.67
C £3.50
D Some other amount
M1.31
SRK combines all manufacturing overheads into one single cost pool and allocates this
overhead to products based on machine hours.
Activity based costing would show that with SRK’s current procedures:
M1.32
JJB is changing from a traditional costing system to an activity based system. Which of
the following costs would change from indirect to direct?
A Direct materials
B Factory supplies
C Production setup
D Production setup, finished-goods inspection, and product shipping
355 | P a g e
M1.33
M1.34
Determine the cost of unit level, batch level, product sustaining, and facility level
activities.
M1.35
A hotel pays cleaners £5 an hour and estimates that it should take 30 minutes to clean a
room but expected idle time would be 20%. Given that 45 rooms were cleaned in a given
day, what would be the estimated cost?
A £112.50
B £135.00
C £140.63
D £160.00
356 | P a g e
M1.36
The budget for the cost of medical supplies in a hospital, based on a percentage of
maximum bed occupancy is shown below:
During the period, the actual bed occupancy was 87% and the total cost of the medical
supplies was $430,000.
A $5,000 adverse
B $12,000 adverse
C $5,000 favourable
D $12,000 favourable
M1.37
A company's annual sales budget includes 1,500 units of a product at a selling price of
$400. Each unit has a budgeted contribution to sales ratio of 30%. Actual sales were
1,630 units at an average selling price of $390. The actual contribution to sales ratio was
28%.
A $16,300 A
B $15,000 A
C $16,200 A
D $17,604 A
M1.38
Which of the following are possible causes of an adverse direct material usage variance?
Output was higher than budgeted therefore more material was used
Labour was of a lower skill than standard
The standard material usage was set unrealistically high
Material was of a lower quality than standard
Output was higher than budgeted
Output was lower than budgeted
357 | P a g e
M1.39
A company's sales budget includes 800 units of a product at a selling price of $300. Each
unit has a budgeted contribution to sales ratio of 30%. Actual sales were 720 units at an
average selling price of $275. The actual contribution to sales ratio was 32%.
The sales volume contribution variance (to the nearest $1) is:
A $7,200 A
B $24,000 A
C $7,680 A
D $7,040 A
M1.40
BB mixes two materials R and S in proportions 2:1. The standard price is $4 kg for R and
$3kg for S. There is a 2% normal loss. Last week 40,400 kg of R at a cost of $121,200
and 19,000kg of S at a cost of $76,000 were input to produce 60,000 kg of output.
For the whole process for last week the material mix variance is $
M1.41
D Standard costing provides a basis for the prediction of future costs which can be
used for decision making and planning purposes.
M1.42
In the context of quality costs, free replacements to customers and training costs are
classified as:
The following company uses a backflush accounting system. During May, 2,500 units
were produced and sold, the standard cost per unit being £50 (of which includes material
of £30 per unit). During May, £52,500 conversion cost was incurred.
The debit balance on the cost of goods sold account for the above period was?
A £125,000
B £127,500
C £75,000
D £177,500
M1.44
Which of the following is not a likely example of a bottleneck when planning for
production capacity
A Resources available
B Physical space
C Lead time to organise expansion
D Sales demand
M1.45
Which ONE of the following would NOT be considered part of the lean philosophy
approach?
M1.46
Which of the following are NOT likely to be factors that can restrict productive capacity
of a firm? Select THREE only.
Physical space
JIT systems
Efficiency
Waste
Over-production
Outsourcing
Defects
Resource availability
359 | P a g e
M1.47
M1.48
B A system in which material purchases are contracted so that the receipt and usage
of material, to the maximum extent possible, coincide.
D A system that converts a production schedule into a listing of the materials and
components required to meet that schedule, so that adequate stock levels are
maintained and items are available when needed.
M1.49
360 | P a g e
M1.50
M1.51
A company is considering whether to develop and market a new product. The cost of
developing the product is estimated to be $200,000. There is a 60% probability that the
development will succeed and a 40% probability that the development will be
unsuccessful, and the development costs will be lost.
If the development is successful the product will be marketed. There is a 50% chance that
the marketing will be very successful and the product will make a profit of $250,000.
There is a 30% chance that the marketing will be reasonably successful and the product
will make a profit of $150,000 and a 20% chance that the marketing will be unsuccessful
and the product will make a loss of $80,000. The profit and loss figures stated are after
taking account of the development costs of $200,000.
The expected value of the decision to develop and market the product is:
A $154,000
B ($46,000)
C $92,400
D $12,400
361 | P a g e
M1.52
A company can choose from three mutually exclusive projects. The net cash flows from
the projects will depend on market demand. All of the projects will last only for one
year. The forecast net cash flows, their associated probabilities and the expected value of
the projects are given below:
The maximum amount that should be paid for perfect information regarding market
demand is $
M1.53
A Assume that risk can be ignored and will choose the outcome with the highest
expected value.
B Assume that he will regret not having chosen another alternative and will
therefore minimise the possible loss under this assumption.
C Assume that the worst outcome will always occur and will select the largest
payoff under this assumption.
D Assume that the best payoff will always occur and will therefore select the option
with the maximum payoff.
M1.54
If 2 products H and J use 13kg and 60kg of a material respectively to make a whole
product, and the amount of material avaible was 3,000kg, which of the follwoing is the
correct constraint?
362 | P a g e
M1.55
M1.56
M1.57
Which of the following costs is not relevant when considering the closure of a department
within a factory?
A Variable overheads
B Fixed overheads
C Direct materials
D Direct labour
M1.58
Which of the following may form the basis for the price a company (working at full
capacity) should charge for a one-off order?
A Variable costs
B Direct and indirect costs
C Opportunity costs plus marginal costs
D Direct labour plus materials costs
M1.59
In a make versus buy decision which of the following factors is not relevant?
A department makes a product whose contribution per unit is £1,000, and which takes 20
hours machine time. A component used in this product with a marginal cost of £300
(taking 5 hours of machine time) could be purchased from an external supplier. The
department is working at full capacity. What is the maximum price that the company may
pay to buy the component from an external supplier?
A £550
B £600
C £575
D £500
364 | P a g e
Mock Exam 1 - Answers
M1.1 Answer is B
M1.2 Answer is B
M1.3 Answer is D
M1.4 Answer is A
This is a question where you have to use the high-low method to solve, however in the
first instance we need to remove inflation from the figures to ensure that they are like for
like high.
Using high-low method, compare the change in activity to the change in cost.
Now to obtain the correct figure we must apply inflation index being 1.06:
M1.5 Answer is C
365 | P a g e
Therefore at 50,000 units:
M1.6 Answer is B
M1.7 Answer
M1.8 Answer is A
M1.9 Answer is B
M1.10 Answer is D
M1.11 Answer is A
M1.13 Answer is B
10% discount is offered to students who pay on enrolment and 50% of customers pay on
enrolment; therefore 50% x 10% = 5% sales lost before you receive £20,000. Therefore
£20,000/0.95 = £21,053 or if £20,000 represents 95% then 100% of sales would be
(100%/95%) x £20,000 = £21,053.
PROOF: £21,053 x 50% get discount x 10% discount = £1,053 discounts given.
366 | P a g e
M1.14 Answer is $275,500
40%
Direct materials ($) 67,500
Direct labour ($) 33,500
Production overhead ($) 45,000
146,000 x (70%/40%) = 255,500
Other fixed overhead ($) 20,000 Fixed = 20,000
Flexed budget at 70% activity level 275,500
M1.15 Answer is A
M1.16 Answer is B
In the year… try relating the answer to a calendar year to understand it better!
Opening trade receivables would all pay in Jan and Feb (in the year) 20,000
12 months sales x £20,000 (say Jan-Dec) = 240,000
However trade receivables still outstanding for Nov-Dec? (W1) -22,400
Cash discounts in the year (W2) -4,800
Cash and credit sales received Jan-Dec 232,800
W1
November monthly sales are £20,000 x 80% credit sales x 40% will settle 2
months after sale (not paying this year) = £6,400.
December monthly sales are £20,000 x 80% credit sales (not paying this year) =
£16,000.
Trade receivables outstanding at the end of the year £6,400 + £16,000 = £22,400.
W2
Cash discounts for the year £20,000 x 12 months x 20% of customers will pay by cash
and will be given a 10% discount, therefore cash discount = £4,800
367 | P a g e
M1.17 Answer
(i) The raw material usage (Kg) for the month would be 11600 kg
(ii) The value of budgeted material purchases (£) for the month would be 14600 kg x
£3.50 = £51,100.
WORKINGS:
Production Budget:
41000 units
16600 kg
M1.18 Answer is A
M1.19 Answer is B
M1.20 Answer is D
M1.21 Answer is C
M1.22 Answer is C
M1.23 Answer is D
M1.24 Answer is C
368 | P a g e
M1.25 Answer
M1.26 Answer is A
M1.27 Answer is D
M1.28 Answer
Direct materials is a unit level activity and therefore not included in the above.
M1.29 Answer is C
M1.30 Answer is A
M1.31 Answer is B
M1.32 Answer is D
M1.33 Answer is D
369 | P a g e
M1.34 Answer
M1.35 Answer is C
M1.36 Answer is B
In order to work out the expenditure variance we need to compare the budgeted
expenditure at 87% bed occupancy to the actual expenditure. We will calculate the
variable cost for each 1% increase in bed occupancy by comparing the costs of the flexed
budgets given.
Machine hours Cost ($)
82% 410,000
94% 429,000
12% 19,200
M1.37 Answer is A
370 | P a g e
M1.38 Answer
Output was higher than budgeted therefore more material was used
Labour was of a lower skill than standard
The standard material usage was set unrealistically high
Material was of a lower quality than standard
Output was higher than budgeted
Output was lower than budgeted
M1.39 Answer is A
M1.41 Answer is A
M1.42 Answer is B
M1.43 Answer is B
£50 x 2,500 units = £125,000 at standard cost + under absorption (£52,500 – ((£50-£30) x
2,500) = £2,500) = £127,500
M1.44 Answer is A
371 | P a g e
M1.45 Answer is A
M1.46 Answer
JIT systems
Over-production
Outsourcing
M1.47 Answer is D
M1.48 Answer is A
M1.49 Answer
M1.50 Answer
372 | P a g e
M1.51 Answer is D
50% $250,000
30%
60% $150,000
20%
$154,000
Spend
40% ($80,000)
$12,400
$12,400
($200,000)
$0
Not $0
spend
M1.53 Answer is C
M1.54 Answer is B
M1.55 Answer is C
M1.56 Answer is D
M1.57 Answer is B
M1.58 Answer is C
M1.59 Answer is D
373 | P a g e
M1.60 Answer is A
The maximum price is the material cost of buying in the material and the machine time
taken to process. This machine time will result in lost contribution of the the current
products being made as the company is at full capacity.
374 | P a g e
Mock Exam 2
M2.1
Within a relevant range of output, as output increases which one of the following would
be correct?
M2.2
The wages of an assembly worker within a car factory would be best classified as?
M2.3
When output levels increase which one of the following would be more likely considered
false?
M2.4
Assembly workers are paid an hourly wage and a bonus for each unit produced. What
type of cost would this be?
A Variable cost
B Fixed cost
C Semi-variable cost
D Stepped fixed cost
375 | P a g e
M2.5
Output Costs
(units) (£)
1,200 34,000
1,800 46,000
It is forecast that fixed cost will increase by 20% and the variable cost will decrease by
10% in the next year.
The forecast budgeted cost next year for an output of 1,500 units would be?
M2.6
M2.7
Which of the following are the only figures required to determine the total breakeven
sales value in a multi-product environment?
376 | P a g e
M2.8
An accountancy firm provides a number of different services to its clients. Fixed costs are
$50 per client hour based on a budgeted activity level of 100,000 hours each period.
M2.9
Given a selling price per unit of £5.00, the break even level of sales in units would be?
A 4,364 units
B 5,333 units
C 7,909 units
D 9,999 units
M2.10
The break even point can be identified where the sales line intersects the
fixed cost line
The break even point can be identified where the sales line intersects the
variable cost line
M2.11
A company had sales for a period of £189,780 and fixed costs for the period of £28,324
Its profit/volume ratio was 40%.
377 | P a g e
M2.12
A company has $5m in fixed cost, its selling price is budgeted to be $120 and its
budgeted total cost per unit is expected to be $50. If 25% of total cost represents
variable cost.
How many units to earn a profit of $1,000,000 (to the nearest unit)?
M2.13
If an entity regularly fails to pay its suppliers by the normal due dates, it may lead to a
number of problems:
Which TWO of the above could arise as a result of exceeding suppliers’ trade credit
terms?
M2.14
DY’s trade receivables balance at 1 April 2006 was $22,000. DY’s income statement
showed revenue from credit sales of $290,510 during the year ended 31 March 2007.
Assume DY’s sales occur evenly throughout the year and that all balances outstanding at
1 April 2006 have been received.
Also, it should be assumed all sales are on credit, there were no bad debts and no trade
discount was given.
How much cash did DY receive from its customers during the year to 31 March 2007?
A $268,510
B $273,510
C $312,510
D $351,510
378 | P a g e
M2.15
M2.16
Company Z pay their suppliers in the ratio of 60% paid one month after purchase and
40% paid two months after purchase. All invoices are received on the last day of each
month.
Those suppliers paid one month after purchase offer company Z a 5% discount and
those suppliers paid two months after purchase offer company Z a 1% discount.
January 35,000
February 40,000
March 15,000
A $15,000
B $27,880
C $36,660
D $38,000
M2.17
Cars
Opening finished goods 10,000
Closing finished goods 15,000
Sales 35,000
Each car requires 60 hours of assembly labour time, however idle time will be 20% of
total labour hours. Cars as part of quality control procedures are checked and normal
reject rates of 25% of assembled cars are normally returned.
The budgeted direct labour assembly hours per car would be?
379 | P a g e
M2.18
The amount received in April according to the information above would be?
M2.19
Finished goods
Opening inventory 6,000 units
Closing Inventory 6,300 units
Budgeted sales 26,700 units
Each unit produced takes 5 hours of labour time and 10% of units are rejected after
production. Production staff are paid $8 per hour.
The total direct labour cost budgeted for this period would be?
A $1,068,000
B $1,080,000
C $1,186,667
D $1,200,000
380 | P a g e
M2.20
A Activity based costing uses a number of activity cost pools, each of which is
allocated to products on the basis of direct labour hours
C Activity rates in activity based costing are computed by dividing costs from the
first-stage allocations by the activity measure for each activity cost pool
M2.21
M2.22
The estimated total cost and expected activity for a company's activity cost pools are as
follows.
The activity rate under the activity based costing system for this activity is closest to:
A £300
B £125
C £214
D £140
381 | P a g e
M2.23
A company uses activity-based costing to compute product costs. The company applies
overheads using a predetermined overhead rate for each activity cost pool.
Budgeted costs were £20,000 and budgted activity was 1,250. Actual activity for the
current year was 3,000. The amount of overhead applied for this activity during the year
was closest to:
A £42,000
B £26,780
C £48,000
D £34,190
M2.24
A Parts administration
B Advertising a product
C Testing a prototype of a new product
D Human resource management
M2.25
A company has two products, X and Y. The annual production and sales level of product
X is 17,000 units. The annual production and sales level of product Y is 13,000. The
company uses activity based costing and has prepared the following analysis showing the
estimated total cost and expected activity for each of its three activity cost pools.
Activity cost pool Budgeted overhead cost Hrs for Hrs for Total
Product X Product Y
Alpha $15,000 800 300 1,200
Beta $30,000 400 700 1,100
Gamma $45,000 100 2,300 2,400
A $29.32
B $19.57
C $18.75
D $17.66
382 | P a g e
M2.26
A company has two products, G and H. The annual production and sales level of product
G is 9,000 units. The annual production and sales level of product H is 20,000. The
company uses activity based costing and has prepared the following analysis showing the
estimated total cost and expected activity for each of its three activity cost pools.
Activity cost pool Budgeted overhead cost Hrs for Hrs for Total
Product G Product H
Alpha $24,000 800 300 1,200
Beta $88,000 400 700 1,100
Gamma $12,000 100 2,300 2,400
The overhead cost per unit of product G under activity based costing is:
A $5.39
B $3.56
C $10.45
D $7.56
M2.27
A company has three activity cost pools and applies overhead using predetermined
overhead rates for each activity cost pool. Estimated costs and activities for the current
year are presented below for the three activity cost pools:
The ABC overhead rates for G, H and I to the nearest whole number:
383 | P a g e
M2.28
When there are batch level or product level costs, in comparison to a traditional cost
system, an activity based costing system ordinarily will shift costs from:
M2.29
M2.30
Shah Rukh Khan’s production company writes songs for Indian films.
During a recent period, his company wrote 10,000 songs which cost £145,000. If 3,312 of
these songs were sad songs and the remainder were happy songs, what would be the costs
allocated to the happy songs?
A £96,976
B £48,024
C £145,000
D £10,000
M2.31
ABC systems:
384 | P a g e
M2.32
Manufacturers
Financial-services firms
Book publishers
Hotels
None of the above, as all are able to use this costing system
M2.33
M2.34
M2.35
Moogle Plc uses 3kg of raw material Alpha into the production process to produce one
unit of output, but have calculated that this would be after 25% wastage of the raw
material. The cost of 1kg of Alpha is £25.
What would be the standard usage of material Alpha, per unit of output, if Moogle Plc
wanted to include the level of wastage within this standard?
A 3 kg
B 4 kg
C 5 kg
D 6 kg
385 | P a g e
M2.36
F Ltd uses an absorption costing system in which labour hours are used as the basis of
recovering overhead costs. Its accounting year is divided into 13 four-week periods, with
fixed production overhead costs budgeted to be incurred at a constant rate of £300,000
per four-week period. Budgeted labour hours per four-week period were 40,000 hours.
In the accounting period of quarter 2, actual hours worked were 37,576 and the output
was 39,000 standard hours.
Given that actual fixed overhead expenditure was £315,000, what would have been the
fixed overhead expenditure and volume variance for the above period?
M2.37
Material
Average price £5.00 £5.60
Average usage per unit 3.5kg 3.3kg
Units produced 2,000 2,300
A £2,240 favourable
B £2,000 adverse
C £2,000 favourable
D £2,300 favourable
386 | P a g e
M2.38
Budget Actual
Material
Average price £7.00 £7.60
Units produced 2,000 2,300
Material purchased 6,500kg 6,700kg
A £3,900 adverse
B £4,020 adverse
C £7,590 adverse
D £9,300 adverse
M2.39
The budgeted and actual number of units produced for this period was 4,000 and 4,260
units respectively, to meet production for the period 32,450 hours were worked.
A £12,388 favourable
B £3,420 adverse
C £12,388 adverse
D £3,420 favourable
M2.40
Benchmarking to compare an internal function to that of the best in the world rather than
the industry the organisation operates within, would normally be described as
A Internal benchmarking
B Functional benchmarking
C Competitive benchmarking
D Strategic benchmarking
387 | P a g e
M2.41
M2.42
M2.43
M2.44
A bundle of machines that can reprogrammed to switch from one production run to
another is an example of:
M2.45
An information systems which provides a list of parts and materials required for the type
and number of products entered, allowing for better stock management is an example of:
A bottleneck is described as a:
A Limited resource
B Unlimited resource
C Expensive resource
D Inferior resource
M2.47
M2.48
M2.49
M2.50
Which of these if any are practices for reducing long term harm to the environment?
M2.52
Project M has possible results of £3, £10 or £25 with probabilities of 0.3, 0.3, 0.4
respectively. The expected profit is:
A £12.30
B £13.90
C £15.60
D £25
M2.53
Project A will earn £1.5m or £3m with probabilities of 0.4 and 0.6 respectively and
project B will earn £0.8m with probability of “g” or alternatively £3.2m. The value of “g”
if both projects are equally attractive under expected value is:
A 0.256
B 0.356
C 0.333
D 0.312
390 | P a g e
M2.54
T
2,000
1,600
1,400
A
1,200
1,000
E
800
D
600 B
400
C
200
M2.55
If 2 products A and B sell for £15 and £20 respectively, the variable costs are £4 and £6
repectively and the fixed costs are £1 and £3 respectively. Which of the following is the
correct objective function?
A 11A + 14B
B 10A + 11B
C 14A + 17B
D 4A + 6B
391 | P a g e
M2.56
The cost of a speciasl gas installation for an asset when looking at its purchase
The salary of a manager who will be transferred to the West Nottingham branch
after the closure of the East Nottingham branch
M2.57
M2.58
In the short-term decision-making which of the following if any would be a relevant cost?
The original cost of materials already in the store which will be used on the
project
Depreciation of existing fixed assets
Specific development costs incurred
General expenditure already incurred
Cost of specific materials which will be purchased
M2.59
392 | P a g e
M2.60
A Ccommitted costs
B Accounting costs
C Cash costs
D Historical costs
393 | P a g e
394 | P a g e
Mock Exam 2 - Answers
M2.1 Answer is B
M2.2 Answer is A
M2.3 Answer is B
M2.4 Answer is C
1,800 46,000
1,200 34,000
600 24,000
Average C/S Ratio = (30% of 25) + (50% of 20) + (20% of 30) = 23.5%
M2.7 Answer
395 | P a g e
M2.8 Answer is $14,285,714
M2.9 Answer is A
3,500 19,875
2,500 17,625
1,000 2,250
M2.10 Answer
The break even point can be identified where the sales line intersects the
fixed cost line
The break even point can be identified where the sales line intersects the
variable cost line
396 | P a g e
M2.12 Answer is 55,814 units
If 25% of total cost is variable cost then $50 x 25% = $12.50 variable cost per unit.
Contribution per unit = (selling price) $120 – (variable cost) $12.50 = $107.50
contribution per unit.
($5m fixed cost + $1m target profit) ÷ $107.50 contribution per unit = 55,814 units.
M2.13 Answer is C
The entity is failing to pay its suppliers by the normal due dates, this means they are
deliberately paying them late, they do have sufficient cash. If there are insufficient funds,
then the entity can’t help it, they can only pay when they have enough cash available.
Delaying payments will affect the entities credit ratings and therefore obtaining goods on
credit from new suppliers who will be reluctant to offer credit.
M2.14 Answer is B
Revision - trade receivable days (turnover)
Therefore year end trade receivables = Trade receivable days / 365 x credit sales
397 | P a g e
Trade receivables control account
$ $
Bal b/f 22,000 Bal c/f 39,000
Credit sales 290,510
Cash received (bal 273,510
fig)
M2.15 Answer is A
M2.16 Answer is C
March
January invoices $35,000 x 0.4 x 0.99 = $13,860
February invoices $40,000 x 0.6 x 0.95 = $22,800
Total payments to suppliers in March $36,660
Then you have to account for rejects, if 25% of cars are returned then 75 hours is 75% of
total hours required. Therefore 75 hours x (100%/75%) = 100 hours.
The information about sales and opening and closing finished goods are irrelevant since
the question asks for the budgeted direct labour assembly hours per car.
Bad debts do not form part of the % receipts for calculation, therefore can be ignored.
398 | P a g e
M2.19 Answer is D
Production budget
OS FGs 6,000
+ Production (balance) 27,000
33,000
- Sales 26,700
CS FGs 6,300
27,000 ‘good production’ x (100%/90%) = 30,000 units of total production before 10%
of units are rejected. 30,000 units x 5 hours of labour time x $8 = $1,200,000.
M2.20 Answer is C
Rather than using a single allocation base (such as direct labor hours), activity based
costing uses a number of allocation bases for assigning costs to products (thus statement
A is false).
Generally, an activity based costing system is harder (rather than easier) to implement
and maintain than a traditional costing system (thus statement B is false).
Rather than eliminating waste by allocating costs to products that waste resources,
activity based management is a management approach that focuses on managing
activities as a way of eliminating waste and reducing delays and defects (thus statement
D is false).
Statement C is true.
M2.21 Anwer is A
Batch level activities are activities that are performed each time a batch of goods is
handled or processed, regardless of how many units are in a batch. Further, the amount of
resources consumed depends on the number of batches run rather than on the number of
units in the batch.
Worker recreational facilities relate to the organization as a whole rather than to specific
batches and, as such, would not be considered a batch level activity. On the other hand,
purchase order processing, setting up equipment, and the clerical activities described are
activities that are performed each time a batch of goods is handled or processed, and, as
such, are batch level activities.
M2.22 Answer is B
399 | P a g e
M2.23 Answer is C
M2.24 Answer is D
Product level activities are activities that relate to specific products that must be carried
out regardless of how many units are produced and sold or batches run. Human resource
management activities relate to the organization as a whole rather than to specific
products and, as such, would not be considered a product level activity. On the other
hand, advertising, testing of prototypes and parts administration are activities that relate
to specific products, and, as such, are product level activities.
M2.25 Answer is C
M2.26 Answer is B
M2.27 Answer is D
G = £45,000 / 6 = £7,500
H = £10,000 / 70 = £143
I = £25,000 / 130 = £192
400 | P a g e
M2.28 Answer is B
Under traditional costing methods, overhead costs are allocated to products on the basis
of some measure of volume such as direct labour hours or machine hours. This results in
most of the overhead cost being allocated to high volume products. In contrast, under
activity based costing, some overhead costs are allocated on the basis of batch level or
product level activities. This change in allocation bases results in shifting overhead costs
from the high volume products to low volume products.
M2.29 Answer
M2.30 Answer is A
M2.31 Answer
M2.32 Answer
Manufacturers
Financial-services firms
Book publishers
Hotels
None of the above, as all are able to use this costing system
401 | P a g e
M2.33 Answer
M2.34 Answer is B
M2.35 Answer is B
M2.36 Answer is A
Standard hours would be the standard labour time per unit x the number of units actually
produced, therefore the company would have absorbed fixed overhead for the period of
39,000 x £7.50 = £292,500
402 | P a g e
M2.37 Answer is D
Did use
2,300 x 3.3 kg = 7,590
Should use
2,300 x 3.5 kg = 8,050
460
x
x Standard price £5.00
M2.38 Answer is B
Did purchase
6,700 kg x (£7.60 - £ 7.00) = £4,020 (A)
M2.39 Answer is A
M2.40 Answer is B
M2.41 Answer is C
M2.42 Answer is C
M2.43 Answer is B
M2.44 Answer is A
403 | P a g e
M2.45 Answer is A
M2.46 Answer is A
M2.47 Answer is A
M2.48 Answer is B
M2.49 Answer
M2.50 Answer
M2.51 Answer is D
M2.52 Answer is B
M2.53 Answer is C
Expected value of project B is the same as project A therefore the expected value of
Project B is:
M2.55 Answer is A
404 | P a g e
M2.56 Answer
The cost of a speciasl gas installation for an asset when looking at its purchase
The salary of a manager who will be transferred to the West Nottingham branch
after the closure of the East Nottingham branch
M2.57 Answer
M2.58 Answer
The original cost of materials already in the store which will be used on the
project
Depreciation of existing fixed assets
Specific development costs incurred
General expenditure already incurred
Cost of specific materials which will be purchased
M2.59 Answer is B
M2.60 Answer is C
405 | P a g e