FIDIC and The Standard Form Contracts
FIDIC and The Standard Form Contracts
” FIDIC”
Mohammed Said Fatha
Consultant Engineer
M C I Arb-London
Member of the Arabic translation Task Group
of FIDIC Contracts
Member of the Arab Center Of Arbitration Cairo.
Contents of this presentation.
Fédération Internationale des Ingénieurs-Conseils
1- What is FIDIC?
2-Types of standard
forms of contracts
Issued by FIDIC &
their main features.
HISTORY OF FIDIC
Fédération Internationale des Ingénieurs-Conseils
To be the Founded in
Fédération Internationale des Ingénieurs-Conseils
To promote the
business interests of
suppliers of
technology-based
intellectual services for
the built and natural
environment
Fédération Internationale des Ingénieurs-Conseils – World Trade Center 2 –
CH-1215 Genève 15 – www.FIDIC.org
Fédération Internationale des Ingénieurs-Conseils
Strategic Objectives
Training Modules
Fédération Internationale des Ingénieurs-Conseils
Integrated Programme
Fédération Internationale des Ingénieurs-Conseils
Conferences
- Formal presentations
- Flexible programme
- Many topics
Seminars
- Formal presentations
- Flexible programme
- Several topics
Workshops
- Flexible programme
- One topic
- Break-out discussion
Courses
- Highly structured
- One topic
History of FIDIC
Fédération Internationale des Ingénieurs-Conseils
Conditions of Contract
Hereafter are
some Standard
form of contracts
issued By FIDIC.
The White Book.
Fédération Internationale des Ingénieurs-Conseils
Updated 2009
Quality Based Selection (QBS)
Guidelines (2011) brochure
Fédération Internationale des Ingénieurs-Conseils
• This is a guidelines
Brochure for the
Quality Based
Selection (QBS).
Business Integrity Management
Fédération Internationale des Ingénieurs-Conseils
industry.
The FIDIC Quality Management
Guide has been developed as a
living document, subject to
periodic review and update in
order to provide Consulting
Engineers with a comprehensive
document on Quality Management.
The document sets out reasons
why Consulting Engineers must
apply Quality Management in all
their work, and provides an
introduction to initiating this
Quality Management process in a
firm.
The Red Book.
Fédération Internationale des Ingénieurs-Conseils
Design-Build and
Turnkey
(Orange Book) Guide .
Insurance of large
civil engineering projects.
Fédération Internationale des Ingénieurs-Conseils
Guide
published
2001
CONTRACT CONTINUITY
Fédération Internationale des Ingénieurs-Conseils
Employer /
consultant
design
Contractor
design
STRAIGHTFORWARD yes
no EMPLOYER
PROJECT
yes DESIGN
no
CONTRACTOR DESIGN
Fixed price - lump sum Plant and/or high
no
Little employer involvement unforeseen risks
No major unforeseen risks
no yes Maintenance
DISCUSS IN DETAIL
Employer’s
requirements with the
Contractor, and
negotiate a modified
FIDIC contract
Fédération Internationale des Ingénieurs-Conseils
Contract for Dredging and Reclamation Works.
Fédération Internationale des Ingénieurs-Conseils
A best-practice approach to
help solve a worldwide lack
of Quality of Construction.
Contents:
1. Introduction
2. FIDIC Quality of Construction
Survey
3. Policy and strategy
4. Approach to Quality
5. Recommended actions
6. Appendices
Work in Progress
Fédération Internationale des Ingénieurs-Conseils
Business Practice
- Quality Based Selection guide (update)
- Risk Management guide (update)
- Definitions of Scope guidelines (new)
- Design for Safety guidelines (new)
FIDIC Contracts
Fédération Internationale des Ingénieurs-Conseils
Engineer
Contractor Employer
Powers of Engineer
Contractual Relations
61
FIDIC Contracts
Fédération Internationale des Ingénieurs-Conseils
62
FIDIC Contracts
Fédération Internationale des Ingénieurs-Conseils
63
FIDIC Contracts
Fédération Internationale des Ingénieurs-Conseils
• Understanding FIDIC
Liquidated damages
v. penalties
Legal background Common law
Substantial completion
v. acceptation
Implied Definitions Reasonable/Shall
Defects Notification
Definitions
Period
Way
of
working Check
Identify Check Check
Legal
term definitions context
background
64
FIDIC Contracts
Fédération Internationale des Ingénieurs-Conseils
White Book
• Contract Administration
Consultant
shall perform
Services
Contract
Instruction
administration
Determination
Certification
Valuation
65
FIDIC Contracts
Fédération Internationale des Ingénieurs-Conseils
White Book
• Contract Administration
Contract
authorises
Consultant/Engineer
to act
Contract
Instruction
administration
Determination
Certification
Valuation
66
FIDIC Contracts
Fédération Internationale des Ingénieurs-Conseils
Legal
Procurement
risk Good faith
law
allocation
Risk of No duty to
Posession? Relevance?
interpretation make survey
To the extent
which was … shall be deemed to have obtained
practicable
67
FIDIC Contracts and Dispute Resolution
Fédération Internationale des Ingénieurs-Conseils
Instruction Request
Variation
Presumption
Amendment
EOT
Legal Risk Damages Rescission Adjustment
68
FIDIC Contracts and Dispute Resolution
• Claims
Fédération Internationale des Ingénieurs-Conseils
Input
Legal Advice
Application for
Statement
Action
Calculation
Engineering
Representative
69
FIDIC Contracts and Dispute
Resolution
Chart: Contractor´s Claims
Fédération Internationale des Ingénieurs-Conseils
70
FIDIC Contracts and Dispute Resolution
Fédération Internationale des Ingénieurs-Conseils
71
FIDIC Contracts and Dispute
Resolution
Fédération Internationale des Ingénieurs-Conseils
Approval
Check Taking-Over Cl. 10
Certificate
Consent
Determination Variations Cl. 13
Disapproval
Examination
Inspection
Instruction Cost Management White Book
Notice Cl. 13.2
Proposal
Request
Time Management Cl. 8.3, 8.6, 8.1
Suspension
Test
Valuation
Claim Determination Cl. 2.5, 3.5
72
FIDIC Contracts and Dispute Resolution
• All the claims should be setteled by Binding agreement or by disipute
Fédération Internationale des Ingénieurs-Conseils
resolution decision.
• Every solved Claim should be included in the contractual price
– Ajustement or deduction
Balance
Contractor
Claim Claim
Amount due Balance
Notice Procedure
Claim Claim
Amount due Balance
Notice Procedure
Retention of
Employer uncertified Payment
amounts Payment
Certificate
2.5 excluded
73
FIDIC Contracts and Dispute Resolution
Fédération Internationale des Ingénieurs-Conseils
• Commencement Date
Engineer Contractor
21 days
Commencement Programme
Date
7 days
Letter of
Acceptance
or Performance
Contract Security
Agreement 28 days
74
FIDIC CONTRACTS
Fédération Internationale des Ingénieurs-Conseils
CONSTRUCTION
EPC/TURNKEY PROJECTS
BALANCED
fair apportioning of risks, rights and obligations between the parties
WELL
TRIED
long case history for earlier contracts
ACCEPTED
SUPPORTED
recommended or required by development banks, ISPA, etc.
EFFECTIVE
Employer designs.
Bill of Quantities.
Contractor designs.
No certification of payments.
Key points: SHORT FORM
Fédération Internationale des Ingénieurs-Conseils
Simple projects.
No certification of payments.
Key points: CLIENT/CONSULTANT
Fédération Internationale des Ingénieurs-Conseils
Decide early.
Draft by professionals.
Buy originals.
PRINCIPLES OF PROCUREMENT
Fédération Internationale des Ingénieurs-Conseils
Effectiveness.
Economy.
Efficiency.
Accountability.
Transparency / confidentiality.
Strong competition.
Publicity, wide participation.
Fair and equal conditions.
Standard procedures.
Standard documentation.
PROCUREMENT CATEGORIES
Fédération Internationale des Ingénieurs-Conseils
Goods.
Works.
Consultant services.
Other services.
TENDERING PROCEDURES
Fédération Internationale des Ingénieurs-Conseils
Shopping.
Single source.
Preparation.
Publication.
Pre-qualification / short-listing.
Invitation.
(Submission).
Evaluation.
Award, contracting.
Supervision, contract administration.
Lessons learned.
PREPARATION OF PROCUREMENT
Fédération Internationale des Ingénieurs-Conseils
Supervision.
Enforcement.
Quality and quantity.
Invoice verification.
Payments.
Extensions, variation orders, amendments.
Termination.
Disputes and their resolution.
RISKS IN PROCUREMENT
Fédération Internationale des Ingénieurs-Conseils
Fraud.
Corruption.
Construction General Conditions Contents.
Fédération Internationale des Ingénieurs-Conseils
Tender Stage
– Clause 13.7 – Adjustment for
Changes in Legislation
Base Date – Clause 13.8 – Adjustment for
Changes in Cost
Floating Tender
the Tender Submission
Fédération Internationale des Ingénieurs-Conseils Major steps under FIDIC Explaining the timeline
Project Execution
42d Max. Time for Completion
Issuance of Commencement Extra
LOA Date – 8.1 Cost
Typical Sequence of Payment
Events Envisaged in Clause 14
Fédération Internationale des Ingénieurs-Conseils
95
Major steps under FIDIC Explaining the timeline
Contract
Employer to Termination
42d
pay after 14 days
Payment notice – 16.2
Application
Major steps under FIDIC Explaining the timeline
Statement at Completion
Fédération Internationale des Ingénieurs-Conseils
Contract
42d Termination
TOC Employer to after 14 days
S@C pay notice – 16.2
Major steps under FIDIC Explaining the timeline
Engineer to
Contractor to Certify FC pay
submit FS
Engineer Verify, <28d <56d
Contractor support
<56d Agree
<56d
Dispute
Disagree <28d 20.4
PC
Draft Engineer to Employer to
FS Certify IPC pay
Fédération Internationale des Ingénieurs-Conseils Major steps under FIDIC Explaining the timeline
TOC
FIDIC Contracts and Disiputes resolution
Fédération Internationale des Ingénieurs-Conseils
101
• DAB :How This procedure work?
Fédération Internationale des Ingénieurs-Conseils
28 days
Notice of intention to
Appointment of DAB
refer a dispute to DAB
112 days
84 days
Submission of Access to
Experts
additional information the site, etc.
See Procedural
Hearing
Rules
102
Chart: FIDIC système of Disiputes resolution
.
Fédération Internationale des Ingénieurs-Conseils
Dispute
Referral to DAB
Arbitration Enforcement
103
Typical Sequence of Dispute
Events Envisaged in Clause 20
Fédération Internationale des Ingénieurs-Conseils
74
Major steps under FIDIC Explaining the timeline
Event
Fédération Internationale des Ingénieurs-Conseils
Dispute <28d
– No EoT N Notification of Y Claim
– No additional payment Claim <42d Particulars
<42d
DAB Decision N
<84d DAB Engineer to
20.4 respond
N Y
Y
Notification N Parties
N Parties
20.4 <28d Accepted Y Accepted
Amicable Succeeded Y
Settlement 20.5 56d
Dispute
Arbitration Y Resolved
20.6 N
• FIDIC Books recommande the ICC
procedure of Arbitration (Clause 20.6).
Fédération Internationale des Ingénieurs-Conseils
106
FIDIC Contracts and Dispute Resolution
Fédération Internationale des Ingénieurs-Conseils
stage 1
Engineer
Permanent
DAB
Nomination
Determination Rejection DAB
if necessary
Stage 2
Stage 3
DAB Decision Arbitration Decision
Procédure au fond
• Red Book
– General Conditions, Cl. 20.6:
• The arbitrator(s) shall have full power to „open up, review and revise any certificate,
determination, instruction, opinion or valuation of the Engineer, and any decision of the
DAB, relevant to the dispute“.
• Neither Party shal be limited in the proceedings … to the evidence or arguments
previously put before the DAB …
107
Fédération Internationale des Ingénieurs-Conseils
Thanks