Lecture Notes ON Project Management: Emad Elbeltagi, PH.D., P.Eng., Professor of Construction Management
Lecture Notes ON Project Management: Emad Elbeltagi, PH.D., P.Eng., Professor of Construction Management
Lecture Notes ON Project Management: Emad Elbeltagi, PH.D., P.Eng., Professor of Construction Management
ON
PROJECT MANAGEMENT
Copyright © 2016 by the author. All rights reserved. No part of this book may be
reproduced or distributed in any form or by any means, or stored in a data base or
retrieval system, without the prior written permissions of the author.
PREFACE
All praise is due to ALLAH and blessings and peace be upon His messenger and servant,
Muhammad, and upon his family and companions and whoever follows his guidance
until the Day of Resurrection.
Project management is a relatively young field. However, its impact has been quite
remarkable. It has become an important practice for improving the efficiency of different
operations around the world. This book deals with some topics and tools of the large field
of project management.
Finally, May ALLAH accepts this humble work and I hope it will be beneficial to its
readers.
i
TABLE OF CONTENTS
CHAPTER 1: INTRODUCTION
1.1 The Need for Project Management 1
1.2 The Project 4
1.3 The Project Scope and Goals 5
1.4 The Project Life-Cycle 9
1.4.1 Pre-execution phase 11
1.4.2 Procurement phase (Bidding and award phase) 12
1.4.3 Execution Phase 13
1.4.4 Closeout Phase 13
1.5 Major Types of Construction Projects 14
1.5.1 Residential Housing Construction 14
1.5.2 Institutional and Commercial Building Construction 15
1.5.3 Specialized Industrial Construction 15
1.5.4 Infrastructure and Heavy Construction 16
1.6 Construction Projects Participants 16
1.6.1 The Owner (Client) 16
1.6.2 The Design Professionals 17
1.6.3 The Construction Professionals 18
1.6.4 The Project Manager 18
1.7 Projects Stakeholders 20
1.8 Case Study 21
1.8 Exercises 22
ii
CHAPTER 2: CONTRACT STRATEGY
2.1 What is a Contract 24
2.2 Selection of Contract Type 25
2.2.1 Project Objectives 26
2.2.2 Project Constraints 27
2.3 Project Delivery Methods 28
2.3.1 Traditional Approach 28
2.3.2 Direct Labor 29
2.3.3 Design-Build 29
2.3.4 Build-Operate-Transfer (BOT) 30
2.3.5 Professional Construction Management (PCM) 30
2.3.6 Contractual Relationships 31
2.4 Types of Contracts 31
2.4.1 Lump-sum Contract 33
2.4.2 Admeasurement Contract 34
2.4.3 Cost-reimbursable Contract (cost-plus contract) 35
2.4.4 Target Cost Contract 35
2.4.5 Time and Material (T&M) Contract 36
2.5 Contract Administration 36
2.5.1 Contract Documents 37
2.5.2 Conditions of Contract 38
2.5.3 The Standard (general) Forms of Conditions of Contract 39
2.5.4 Special Conditions of Contract 41
2.5.5 Construction claims Contract 42
2.6 Selecting the Contractor 43
2.7 Sub-Contracting 43
2.8 Exercises 44
iii
CHAPTER 3: HUMAN RESOURCES MANAGEMENT
3.1 What is Human Resources Management (HRM)? 47
3.2 Organizational Structures 48
3.2.1 Functional Organization Structure 48
3.2.2 Project Organization Structure 50
3.2.3 Matrix Organization Structure 51
3.3 Human Resources Management Plan 54
3.3.1 Develop HR Plan 54
3.3.2 Acquire Project Team 54
3.3.3 Develop Project Team 55
3.3.4 Manage Project Team 57
3.4 Exercises 63
iv
CHAPTER 5: LEARNING THEORY
5.1 Introduction 67
5.2 Productivity 68
5.3 Learning Models Assumption` 70
5.4 Factors Affecting Learning Rates 71
5.5 Variability of Learning Curve 72
5.6 Learning Models 73
5.6.1 Straight-Line Model 76
5.6.2 Stanford "B" Model 76
5.6.3 Cubic Model 77
5.6.4 Piecewise (or Stepwise) Model 78
5.6.5 Exponential Model 78
5.7 Models Data Representation in Learning Curve Theory 79
5.8 Example 82
5.9 Comparison between Data Representing Methods 84
5.10 Using Learning Curves to Predict Future Performance 84
5.11 Forgetting Phenomenon 84
5.12 Exercises 86
CHAPTER 6: COST ESTIMATING
6.1 Purpose of Estimating 88
6.2 Types of Cost Estimating 89
6.3 Conceptual Cost Estimating Basics 93
6.4 Broad Scope of Conceptual Estimates 95
6.5 Conceptual Estimate Adjustment 96
6.5.1 Adjustment for time 96
6.5.2 Adjustment for location 98
6.5.3 Adjustment for Size 98
6.5.4 Combined Adjustment 99
6.5.2 Unit Cost Adjustment 99
6.6 Conceptual Estimating Techniques 101
6.6.1 Interpolation 101
v
6.6.2 Unit Method 102
6.6.3 Superficial Method 103
6.7 Detailed Estimate of Direct Costs 104
6.7.1 Unit Rate Estimating 105
6.7.2 Operational Estimating 105
6.8 Estimating Indirect Cost 107
6.8.1 Site Overheads 107
6.8.2 General Overheads 108
6.8.3 Contingences 110
6.8.4 Contractor/Subcontractor profits 111
6.9 Finalizing a Tender Price 112
6.9.1 Balanced bid (straight forward method) 112
6.9.2 Unbalanced bid (loading of rates) 113
6.10 Exercises 115
REFERENCES 144
vi
CHAPTER 1
INTRODUCTION
Triple constraints
In general, the construction industry is more challenging than other industries due to: its
unique nature; every project is one-of a kind; many conflicting parties are involved;
projects are constrained by time, money and quality; and high risk.
Project Success
A project is said to be successful when the following requirements are satisfied:
- Completed within allocated time frame.
- Customer Requirements satisfied/exceeded.
- Completed within allocated budget.
- Accepted by the customer.
Projects begin with a stated goal established by the owner and accomplished by the
project team. As the team begins to design, estimate, and plan out the project, the
members learn more about the project than was known when the goal was first
established. This often leads to a redefinition of the stated project goals.
The goal of construction project is to build something. What differentiate the construction
industry from other industries is that its projects are large, built on-site, and generally
unique. Time, money, labor, equipment, and, materials are all examples of the kinds of
resources that are consumed by the project.
How, exactly, do you go about determining your goal? First, go back to the person who
asked you to take on the project and grill him or her about what’s expected of this project.
Should the training have a measurable impact on job performance, customer satisfaction,
employee retention, or cost of delivery? The answer you get might be that the project
should do all of these things. But think about whether that’s realistic and whether one of
these goals should be paramount in guiding you and your project team. If overall training
program cost reduction is the biggest goal factor, for example, employee productivity
might have to take a back seat when you’re making choices along the way. If customer
satisfaction is the real goal, training costs might have to be adjusted accordingly.
Project scope
When you understand your goal, you can begin to define the specific parameters of the
project. This is often referred to as a project’s scope. It is necessary to know that a scope
is not a goal. Take a look again at this goal statement from the previous section: The goal
of the project is to upgrade the shopping cart feature Web site to be easier to use to
increase online sales by 25 percent. A scope statement for this project might read: This
project will involve all the steps to design and implement a new shopping cart feature
(but does not include maintaining or refining it once launched). The cost of the project
will not exceed $25,000 and implementation must be completed before October 1 to
accommodate holiday sales traffic. The new shopping cart feature should help to increase
sales by allowing customers more options to review their orders, give them more frequent
opportunities to shop for more items after they have added a product to the cart, and
allow them to save their cart contents and come back to complete the sale at a future date.
The new feature must function on our existing Web technology infrastructure.
From the perspective of an owner, the project life cycle for a constructed facility may be
illustrated schematically in Figure 1.2. A project is expected to meet market demands or
needs in a timely fashion. Various possibilities may be considered in the conceptual
planning stage, and the technological and economic feasibility of each alternative will be
assessed and compared in order to select the best possible project. The financing schemes
for the proposed alternatives must also be examined, and the project will be programmed
with respect to the timing for its completion and for available cash flows. After the scope
of the project is clearly defined, detailed engineering design will provide the blueprint for
construction, and the definitive cost estimate will serve as the baseline for cost control. In
the procurement and construction stage, the delivery of materials and the erection of the
project on site must be carefully planned and controlled. After the construction is
completed, there is usually a brief period of start-up of the constructed facility when it is
first occupied. Finally, the management of the facility is turned over to the owner for full
occupancy until the facility lives out its useful life and is designated for demolition or
conversion.
Of course, the stages of development in Figure 1.2 may not be strictly sequential. Some
of the stages require iteration, and others may be carried out in parallel or with
overlapping time frames, depending on the nature, size and urgency of the project.
Furthermore, an owner may have in-house capacities to handle the work in every stage of
the entire process. By examining the project life cycle from an owner's perspective we
can focus on the proper roles of various activities and participants in all stages regardless
of the contractual arrangements for different types of work.
The preconstruction phase of a project can be broken into conceptual planning, schematic
design, design development, and contract documents.
Conceptual design:
- Very important for the owner.
- During this stage the owner hires key consultants including the designer and
project manager, selects the project site, and establish a conceptual estimate,
schedule, and program.
Schematic design:
- During this phase, the project team investigates alternate design solutions,
materials and systems.
- Completion of this stage represents about 30% of the design completion for
the project.
Design development:
- Designing the main systems and components of the project.
- Good communication between owner, designer, and construction manager is
critical during this stage because selections during this design stage affect
project appearance, construction and cost.
- This stage takes the project from 30% design to 60% design.
Contract documents:
- Final preparation of the documents necessary for the bid package such as the
drawings, specifications, general conditions, and bill of quantities.
- All documents need to be closely reviewed by the construction manager and
appropriate owner personnel to decrease conflicts, and changes.
- With the contract documents are almost complete; a detailed and complete
cost estimate for the project can be done.
- Transition from design and construction to the actual use of the constructed
facility.
- In this stage, the management team must provide documentation, as-built
drawings, and operation manuals to the owner organization.
- The as-built drawings are the original contract drawings adjusted to reflect all
the changes that occurred.
- Assessment of the project team’s performance is crucial in this stage for
avoiding mistakes in the future.
- Actual activity costs and durations should be recorded and compared with that
was planned. This updated costs and durations will serve as the basis for the
estimating and scheduling of future projects.
Figure 1.3 shows the increasing cumulative cost as the projects progresses while the
influence in the project cost and scope decreases.
Residential housing construction includes houses and high-rise apartments. During the
development and construction of such projects, the developers usually serve as surrogate
owners and take charge, making necessary contractual agreements for design and
construction, and arranging the financing and sale of the completed structures.
Residential housing designs are usually performed by architects and engineers, and the
construction executed by builders who hire subcontractors for the structural, mechanical,
electrical and other specialty work.
Institutional and commercial building encompasses a great variety of project types and
sizes, such as schools and universities, medical centers and hospitals, sports facilities,
shopping centers, warehouses and light manufacturing plants, and skyscrapers for offices
and hotels. The owners of such buildings may or may not be familiar with construction
industry practices, but they usually are able to select competent professional consultants
and arrange the financing of the constructed facilities themselves. Specialty architects and
engineers are often engaged for designing a specific type of building, while the builders
or general contractors undertaking such projects may also be specialized in only that type
of building.
Because of the higher costs and greater sophistication of institutional and commercial
buildings in comparison with residential housing, this market segment is shared by fewer
competitors. Since the construction of some of these buildings is a long process which
once started will take some time to proceed until completion, the demand is less sensitive
to general economic conditions than that for housing construction.
Specialized industrial construction usually involves very large scale projects with a high
degree of technological complexity, such as oil refineries, steel mills, chemical
processing plants and coal-fired or nuclear power plants. The owners usually are deeply
involved in the development of a project, and prefer to work with designers-builders such
that the total time for the completion of the project can be shortened. They also want to
Although the initiation of such projects is also affected by the state of the economy, long
range demand forecasting is the most important factor since such projects are capital
intensive and require considerable amount of planning and construction time.
Governmental regulation such as environmental protection can also influence decisions
on these projects.
The engineers and builders engaged in infrastructure construction are usually highly
specialized since each segment of the market requires different types of skills. However,
demands for different segments of infrastructure and heavy construction may shift with
saturation in some segments. For example, as the available highway construction projects
are declining, some heavy construction contractors quickly move their work force and
equipment into the field of mining where jobs are available.
The owner is the individual or organization for whom a project is to be built under a
contract. The owner owns and finances the project. Depending on the owners’
capabilities, they may handle all or portions of planning, project management, design,
engineering, procurement, and construction. The owner engages architects, engineering
firms, and contractors as necessary to accomplish the desired work.
In order to achieve success on a project, owners need to define accurately the projects
objectives. They need to establish a reasonable and balanced scope, budget, and schedule.
They need to select qualified designers, consultants, and contractors.
Examples of design professionals are architects, engineers, and design consultants. The
major role of the design professional is to interpret or assist the owner in developing the
project’s scope, budget, and schedule and to prepare construction documents. Depending
on the size and sophistication of the owner, the design professional can be part of the
owner’s group or an independent, hired for the project. In some cases design professional
and construction contractor together form a design-build company.
Architect: An architect is an individual who plans and design buildings and their
associated landscaping. Architects mostly rely on consulting engineers for structural,
electrical, and mechanical work.
Engineer: The term engineer usually refers to an individual or a firm engaged in the
design or other work associated with the design or construction. Design engineers are
usually classified as civil, electrical, mechanical depending upon their specialty. There
are also scheduling, estimating, cost, and construction engineers.
Engineering-Construction Firm: An engineering-construction firm is a type of
organization the combines both architect/engineering and construction contracting. This
type of company has the ability of executing a complete design-build sequence.
The constructions Professional are the parties that responsible for constructing the
project. In traditional management where the owner, design professional, and contractors
are separate companies, the contractor would be termed a prime contractor. The prime
contractor is responsible for delivering a complete project in accordance with the contract
documents. In most cases, the prime contractor divides the work among many specialty
contractors called subcontractors as shown in Figure 1.4.
Owner
Contract
Prime contractor
First sub-
contractor Contract
The project manager is the individual charged with the overall coordination of the entire
construction program for the owner. These include planning, design, procurement, and
construction. Among his/her duties:
The Project Manager (PM) is solely accountable for stakeholder satisfaction and the
overall performance of a capital project. The PM ensures that a capital project meets its
goals in technical scope, schedule, and cost from start to finish. The PM is the
“responsible in charge” for all projects assigned to him. The Project Manager runs each
capital project like a business, performing relatively few technical activities. The PM
delegates most technical work to others and relies greatly on their experience and
judgment. The PM oversees and coordinates this technical work through the Project
Engineer (PE), the Resident Engineer (RE), and other resources who are assigned to the
capital project. The Project Manager administers all contracts with consultants and
contractors, which includes the change review process. The Project Manager maintains
an open dialogue with all Agency stakeholders and ensures that all communications are
both timely and effective.
The PM provides routine feedback on the performance of individual team members to the
team member, the team member’s supervisor, and the Agency Project Management
Office (APMO) Manager. The PM uses guidelines and templates for planning, executing,
controlling, and reporting the performance of each capital project. There are discussions
of the templates and forms that the Project Manager can use throughout this manual.
Typical Stakeholders:
- Funding Body.
- Customers.
- Suppliers.
- End Users.
- Shareholders.
- Lobbies.
- Government Agencies.
- Neighbors.
- Community.
1.9 Exercises