Test 1 SKAA 4113 Construction Project Management Semester I Session 2016/17
Test 1 SKAA 4113 Construction Project Management Semester I Session 2016/17
SKAA 4113
CONSTRUCTION PROJECT MANAGEMENT
SEMESTER I SESSION 2016/17
Table 1 shows a list of activities for a small project. The project starts on Thursday 1 October
2016. Assume five (5) working days a week except Saturday and Sunday.
Table 1
DURATION
ACTIVITY
(weeks)
0-1 3
1-2 4
1-3 5
1-4 6
2-5 7
2-6 8
3-5 9
4-6 2
4-7 9
5-8 8
6-8 1
6-9 6
7-9 4
8-10 3
9-10 2
1. Based on the information given in Table 1 develop a logical network diagram schedule
using Critical Path Method. Determine the critical path and total week of completion.
(2 marks)
Set A
After the project has been underway for 7 days, the instruction was given to the scheduler to
make update as per Table 2 by using Precedence Diagram Method:
Table 2
Node DURATION
ACTIVITY PREDECESSORS
(Weeks)
1 A 3 -
2 B 4 A(SS+4)
3 C 5 A
4 D 6 A
5 E 7 B; C(FF+2)
6 F 8 D; E(FS+2)
7 G 9 F(SS+3)
8 H 2 E; F(FF+2); G(SS-1)
9 I 9 G(FS+2)
10 J 8 H; I
2. Based on the information given in Table 2 develop a logical network diagram schedule
using Precedence Diagram Method. Provide ES, EF, LS, LF for each activity.
(3 marks)