Test 1 SKAA 4113 Construction Project Management Semester I Session 2016/17

This document provides information about a construction project management test, including two tables of activities with durations. Table 1 lists activities for the original project plan, and asks to draw a critical path network diagram and determine the critical path and completion time. Table 2 then provides an updated plan after 7 days and asks to draw a precedence diagram network, and calculate early/late start/finish dates, critical path, total float for activity F, free float for activity G, and project completion date.

Uploaded by

Erik Aiden
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
91 views2 pages

Test 1 SKAA 4113 Construction Project Management Semester I Session 2016/17

This document provides information about a construction project management test, including two tables of activities with durations. Table 1 lists activities for the original project plan, and asks to draw a critical path network diagram and determine the critical path and completion time. Table 2 then provides an updated plan after 7 days and asks to draw a precedence diagram network, and calculate early/late start/finish dates, critical path, total float for activity F, free float for activity G, and project completion date.

Uploaded by

Erik Aiden
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

TEST 1

SKAA 4113
CONSTRUCTION PROJECT MANAGEMENT
SEMESTER I SESSION 2016/17

Table 1 shows a list of activities for a small project. The project starts on Thursday 1 October
2016. Assume five (5) working days a week except Saturday and Sunday.

Table 1

DURATION
ACTIVITY
(weeks)
0-1 3
1-2 4
1-3 5
1-4 6
2-5 7
2-6 8
3-5 9
4-6 2
4-7 9
5-8 8
6-8 1
6-9 6
7-9 4
8-10 3
9-10 2

1. Based on the information given in Table 1 develop a logical network diagram schedule
using Critical Path Method. Determine the critical path and total week of completion.
(2 marks)

Set A
After the project has been underway for 7 days, the instruction was given to the scheduler to
make update as per Table 2 by using Precedence Diagram Method:

Table 2
Node DURATION
ACTIVITY PREDECESSORS
(Weeks)
1 A 3 -
2 B 4 A(SS+4)
3 C 5 A
4 D 6 A
5 E 7 B; C(FF+2)
6 F 8 D; E(FS+2)
7 G 9 F(SS+3)
8 H 2 E; F(FF+2); G(SS-1)
9 I 9 G(FS+2)
10 J 8 H; I

2. Based on the information given in Table 2 develop a logical network diagram schedule
using Precedence Diagram Method. Provide ES, EF, LS, LF for each activity.
(3 marks)

3. Determine the critical path of the schedule


(1marks)

4. Determine the Total Float for Activity F


(1marks)

5. Determine the Free Float for Activity G


(1marks)

6. Determine the completion date of this project.


(2marks)

Set A