Pipe
Pipe
Pipe
S. C. Gupta*
SYNOPSIS
Pipe culverts are most commonly used conduits for cross drainage through
Railway/Highway embankments, in addition to carrying of liquid under pressure.
They are one of the most economical conduits because of circular structure.
Circular structures are governed by the directed stress instead of bending
stress, therefore, are economical. The article deals with basic design concept
of pipe culverts and a case study showing advantage so obtained in
upgrading the existing pipe culverts in embankments for higher grade of
loading by following basic concepts.
1.0 INTRODUCTION
There is a general thinking amongst the Rly. engineers that the existing hume
pipes provided for a lower standard of loading are not suitable for higher
standard of loading, therefore, decisions are taken to dismantle and replace the
existing pipe culverts with higher grade pipes without going into design details.
A similar and interesting case study is provided here.
A Rly. line from Cuttack to Paradeep (82.9 km) long was to be executed as a
doubling project. Since the entire line from Cuttack to Paradeep was planned
for carrying axle load of Heavy Mineral Loading Standard, therefore, it was
planned to upgrade the existing bridges from BGML to HMLS and to construct
all new bridges for HMLS. The existing line was having 109 Hume pipe bridges
of dia varying 0.6 m to 1.2 m.
The IS code provides thickness, amount and spacing of steel required for NP1,
NP2, NP3, NP4 type of pipes for different diameters ranging from 80 mm to
These designs provided irrespective of surcharge over the pipe. It was also
clarified vide amendment slip no.2 of April, 1991, that the designs provided in
IS-458-1988 are not suitable for Railway loadings. This aspect is discussed in
detail in the subsequent paras.
Due to this reason, separate pipes are designed for loadings and various
drawings are issued by RDSO from time to time for various types of loadings or
sometimes designs are done by the field units as per the requirements. But in
most of the cases RDSO drawings are religiously followed.
RDSO drg does not mention about at what load the pipes shall be tested. They
have defined that pipes are designed for wide trench, positive projection and
type ‘A’ beddings.
Table – I
Working Stress Load to Produce 0.25 Permissible Parameters for Parameters for
Method mm crack (Edge load (l/m) class NP4 RC Existing BGML NP4
Surcharge height (M)
Table – II
described in detail in various RCC design books for pressure and non-
pressure pipes by neglecting relief due to side earth pressure.
(b) Pipes are checked for 0.25m cracking loads for two conditions
(a) The above theory neglects the relief due to side earth pressure, which is
about 33%.
(ii) If checked with IS 783’s method then not only RDSO’s BGML and MBG
drawings are safe for HM loading but also NP4 type pipes of IS 458 are
safe with a surchage > 0.5 m. The design concept prescribed in IS 783 is
based on Spangler’s theory and is more appropriate as it directly checks
the 0.25mm cracking load and ultimate load, This procedure is well
established and proven reliable and safe over the years, not only in
India but all over the world in similar conditions (Ref.4,9,11)
(iii) It is also worth noting that even Spangler’s theory is on conservative side
as it does not take into account the full arching action of soil and IS-783
has further gone on more conservative side by neglecting cohesive
element of soil.
(i) Calculation of superimposed dead load (SIDL) and equivalent live load:
Pipes are subjected to SIDL due to ballast, sleepers and Rails in addition to
dynamic loads. Dynamic loads were calculated for HM Loading. They were
coming as
(i) To test pipes under field condition a plate 1.5 x 3.0 x 10mm x 4 nos were
provided on the bank coinciding with the underlying pipes centre line. The
above dimension were chosen on the basis that at ballast soil interface the
loading area over the 1.44m (external dia) pipe is approximately, 1.50 x
3.0m.
(iii) Remaining load was then applied with help of sand bags and loose sand.
The arrangements are shown in Sketch – 1 and photographs No. 1 on
page no. 12.
(iv) Such load was applied for a surcharge of 1.0m and 3.0m.
(i) One meter scale was fixed at the bottom bed of the pipes centre and
supported with a plate.
(ii) To measure deflection in hume pipe a scale was fixed on the inside top of
the hume pipe having a least count of 1.0mm.
(iii) Out side reference BM were fixed to measure relative settlement and
deflection of pipe.
The details of measurement arrangement are shown in sketch No. 2 and
photograph No. 2 on page no. 13.
Note: Readings were taken at an increment of 20-25 ton of load, but same are not
shown as there is no change in between readings.
The above load test indicates that the existing pipes are safe even HMLS
Loading with a factor of safety of more than 2.25 to 3.0, which is much more than the
codal requirement of 1.5.
Three pieces of 1.2m dia pipe, one piece each of 900mm dia and 600mm dia
pipes were taken to a factory about 100km away from the site at Bhubaneswar.
The pipes were tested by three edge bearing test as prescribed in IS
3597:1998. The results are given in the Table – IV below:
5.0. ECONOMICS
At this juncture it was decided not to dismantle about 9 No. of Hume pipe
bridges having higher (5-7m) cushion. The saving because of adoption of
existing pipes was about 42.9 lakhs (Refer table V) excluding saving of
disruption to traffic and inconvenience under traffic block.
Where as the saving could be unimaginable had there been clear and logical
guidelines on the subject. Such type of dismantling of Hume pipe bridges must
be continuing all over the Indian Railways, such in depth study and
reviewing certainly help in ease in construction apart from saving of
money and time.
Above saving includes only cost of extension portion of bridge for doubling, but
there is a plan to upgrade existing BGML bridge to HM loading standard in next
phase. Then the savings will almost be double. Entire savings for left over
bridges may amount to several crores.
6.0. CONCLUSION/RECOMMENDATIONS
II. For all new construction of HM/MBG loading standards, present NP4
pipes (given IS 458-1998) shall be used with a minimum cushion of
600 – 900 mm.
III. The study so conducted caused a immediate saving of Rs. 42.90 lakhs
for Rlys in addition to time saving, easier execution, avoiding of
suspension of running lines.
IV. It shall also be kept in mind that calculations and formulae developed by
Mortson and Spangler for pipes are itself on very much conservative
side, as they ignores the full arching benefits of soil. In addition to this
IS 783:1985 has further gone on safer side by ignoring cohesive element
of soil in calculating dead load factor.
V. Construction in field can be easily and shall be done as per para A-4 of
IS 783:1985 for imperfect ditch conditions than load factors will further
increase and requirement of pipe thickness and reinforcement will further
decrease.
VI. Special design Hume pipe with simple bending and shear stress
theory for HM loading with 85kg per meter spiral reinforcement
(1200mm internal dia, 120mm thickness, M-30 concrete) are also
casted and tested on three edge bearing load. The pipes shown
VII. There is no need for separate RDSO’s drawings for Hume pipes, rather
they shall only prescribe the requirement of test load for three edge
bearing test for present NP4 type of pipes. As this method is well
established, proven and tested all over the world as discussed by various
authors. The clause provided in IS – 458 i.e., NP4 pipes shall not be
used for Rly loadings shall not be mistaken as those calculations are
provided irrespective of minimum cushion.
ACKNOWLEDGEMENT:
1. I acknowledge my gratitude to Sri S.P. Sahu, CE/C/I/BBS, who inspired, helped
and encouraged in conducting load tests.
2. I acknowledge my thanks to Sri. I.B. Jha, Dy. CE/C/CTC and Sri. N.S. Uikey,
Dy. CE/C/D-IV/BBS for helping in making arrangements for necessary load
testing.
3. I acknowledge my thanks to Sri PK Patra, AXEN/C/Designs/BBS, Sri RC Sethi,
JE/I/Drg, Sri DK Choudhury, JE/I/W for helping in making calculations and
supervising load tests.
REFERENCES:
1. IS-783-1985 “Indian Standard Code of Practice For Laying of Concrete Pipes”,
(First Revision), Bureau of Indian Standard, New Delhi.
2. Is-458-1988 “Indian Standard Specification for Precast Concrete Pipes (With &
Without Reinforcement)”, (Third Revision), Bureau of Indian Standard,
New Delhi.
3. IS-3597-1998 “Concrete Pipes – Method of Tests”, Bureau of Indian Standard,
New Delhi.
4. A. Rico Rdgrighez, H.del Castrilo and G.F. Seweres “Soil Mechanics in
Highway Engineering”, Trans Tech Publication.
5. G.Annamalai, J Shammujesunderam & others “Earthfill Load on Burred Pipes”.
Journal of Insitute of Engineers, India
6. N.Krishna Raju “Advanced RCC Design”. Tata Machrawhill Publication.
7. O.P. Jain & Jai Krishna “Plain and Reinforced Concrete –Vol.II” Nem Chand
and Brothers, Roorkee
8. Merlin G.Spangler “Culverts and Conduits”.
9. Bernard E.Butler “Structural Design Practice of Pipe Culverts”, Highway
Research Record No.413/1972
10. A.Martson & A.O. Anderson “Theory of Loads on Pipes in Ditch”.
STANDARD DATA
*Bending moment due to side earth pressure are neglected, while considering critical
design moments
ARRANGEMENT FOR
HUME PIPE SETTLEMENT READING
NOT TO SCALE
SCALE 0.30M
SCALE 1.00M
INSTRUMENT NO. 1
H. P. 1.2MØ
REFERENCE
POINT
BY
Vardhman Jain*
D. S. Yadav**
P. K. Vyas***
1. Introduction :
The problem of leakage from roof of building is experienced by all the zonal railways.
Various methods / Techniques have been tried to arrest the leakages. Most of the time
the treatments adopted proves to be effective only for a short duration.
This report is covering the details of prevention of leakage through R.C.C. New/old or
flat slabs terrace by China mosaic treatment.
2. Provision of adequate openings for drainage of water pipe - spacing of Down take
pipes - not more than 6 meter (as per clause 5.3.2 of IS 2527 year 1984).
3. Proper detailing of junction at roof with parapet wall - (as per IS 3067 -1988).
In order to arrest leakage of water through RCC roofs. It is necessary that roofs are
provided with suitable water Proofing system.
The various methods adopted at various part of country are given below :
6. Water proofing by polymer cementitious slurry coating and then china mossaic
treatment.
In order to overcome the leakage problems the china mosaic treatment is very effective
to prevent leakage from slabs. And most widely used in W. Railway in BCT Division.
Surface Preparation :
2. The surface must be free from dust, dirt, coatings loose particle, fungus, oils,
greases etc.
3. Clean the surface by scrapping sand blasting, grinding to remove dust and loose
particles.
5. Oils, greases and mould release agents can be cleaned with solvents.
Provision of Slope :
Providing water proofing treatment with china mosaic on terrace slab as per under in
addition to specifications enclosed along with tender documents. Preparing the surface
for water proofing treatment by scrapping and brushing the surface so as to remove all
loose material after removing old tarfelt bitumen fiber glass tissues etc. and complete
washing to the surface with. Only dismantling of concrete if any will be paid separately
under SOR item. Providing cement concerete to proper slope as directed by the
Railway Engineer or his representative. However, cost of providing cement concrete
will be paid for separately under SOR items.
Applying one coat of polymer based water proofing compound of approved quality
mixed with cement (OPC). 1 kg of polymer based water proofing compounds and 2 kg
of cement (OPC) should cover an area of 2.80 sq. m.
Providing and laying broken China Mosaic (Broken pieces of China glazed tiles) of
approved colour set in 20 mm thick cement mortaral 1 : 3 mixed with water proofing
powder of approved quality at correct level and slope and joints finished by pouring
cement slurry and brooming them down. The tiles shall be closely packed such that
china mosaic covers atleast 90% of slab area.
The above treatment shall be provided on the parapets / any other wall upto 30 cm
above the floor level and the junction between the wall and parapet round offin the
shape of area of a curve.
Curing of the flooring continuously for 10 days so as to render the surface hard.
ADæÔ»¤ ædÚ <≤GD·Ò _™D¤· ß<Ë_™D Indian Railways Construction Bulletin
‹x|> ëë, _¥™. î, GDY· íêêí / Vol. 11, No. 4, March - 2002
17
Cleaning the China mosaic tiles of all dust and stains.
The rate shall also exclude cost of cement, which will be paid for separately, but shall
include disposal debris released from this work.
3. Allows trapped water vapours to escape and prevents blistering and adhension
failure.
7. It is non-flammable, non hazardous, does not evolve toxic gasses when exposed to
fire.
B) Master - Crete
(a) PH Value - 9 to 10
It can be used with all types of cement including the sulphate resistance type. It is
F) Xypex : Water proofing by crystallization when mixed with water and applied as a
cementitious coating, the active chemical in X Y P E X cause a catalytic reaction
with generates a non-soluble crystalline formation of dendristic fibers within the
pores and capillary track of concrete. Thus the concrete becomes permanently
sealed against the penetration of water or liquids from any direction.
Properties :
core replacement-10%
H) Roff Super Crete : Acrylic polymer based designed for use with cement
formulation.
50 kg cement + 125 kg zone II sand + 10 lit roff super create + 5 to 7 lit water.
9. Conclusion
2. Terrace give good out look appearances. Hence can be used for commercial
purpose.
3. The 90% area of top surface is covered by the Broken tiles which reduced
weathering effects.
4. The method reduce unnecessary dead load.
5. The minimum effective life is 5 years. However it is effective more than 12 years.
(i) The china clay tiles pieces give the impervious surface which do not allow to
penetrate the water through top surface.
(ii) If due to any cause water passes through the china clay top layer then the
dense M 15 layer of concrete with admixtures and in proper slope do not permit
the water to further penetrate the slab. The penetrated water flow outside the
slab due to gravitational flow. Hence, water is not sustain above the slab.
(iii) Even though, if water penetrates through the both surfaces, then the third
(i. e. bottom most) layer of polymers do not allow to penetrate the water through
the slab.
Hence, the china mosaic restrict the percolation of water in three stages thus
proving to be the most effective method of water proofing.
10. Suggestions :
Inspite of water proofing treatment of the leaky roofs, in some of the cases, water
again starts leaking from the roofs after passing one or two years, due to poor
workmanship or in adequate supervision, causing hardship to the occupants.
Therefore the water proofing treatment shall be guaranteed for a minimum period of
5 years from the date of completion of the work. For this purpose special condition
should be included in all tenders regarding water proofing treatment work. A
certain amount say about 5% of the cost of work shall be kept deposit from the
contractor which shall be released only after successful completion of 5 years. In
the meantime if leakage occurs the contractor should be bound to rectify the same.
Annexure - I
Following is the list of various I S codes which deals with water proofing of roofs.
(a) I S 1322 : 1993 specification for bitumen felts for water proofing and damp proofing
(Forth revision)
(b) I S 1346 : 1991 code of practice for water proofing of roofs with bitumen felt (Third
revision)
(c) I S 1580 : 1991 specification for bituminous compound for water proofing and
caulking proposes (First revision)
(d) I S 2115 : 1980 code of practice for flat roof finish mud phuska.
(e) I S 2527 : 1984 code of practice for fixing rain water gutters and down pipes for
drainage.
(f) I S 3036 : 1992 code of practice for laying lime concrete of a water proofing roof
finish (second revision)
(g) I S 3037 : 1986 specification of bitumen mastic for use in water proofing of roofs
(First revision)
(h) I S 3067 : 1988 code of practice for general design details and preparatory work for
damp proofing and water proofing of buildings (First revision)
(i) I S 3384 : 1986 specification for bitumen primer for use in water proofing and damp
proofing (first revision)
(j) I S 4365 : 1967 code of practice for application of bitumen mastic for water -
proofing of roofs.
(k) I S 4911 : 1968 glossary of terms relating to bituminous water proofing and damp
proofing buildings (first revision)
(G) I S 7193 : 1974 specification for glass fiber base - bitumen felt.
(m) I S 7290 : 1979 Recommendations for use of polyethylene film for water - proofing
of roofs (first revision)
(o) I S 13182 : 1991 Recommendations for water proofing of wet areas in building.
(p) I S 13826 ( P + 1) 1993 Bitumen based felts - method of test part 1 breaking
strength test,.
(q) I S 13826 (P + 2) Bitumen based felts method of : 1993 test part 2 pliability test
(r) I S 13826 Bitumen based felts - method of test (P + 3) : 1993 Part 3 storage
stocking test.
(s) I S 13826 Bitumen based felts - method of (p + 4) 1993 test part - 4 pressure head
test.,
(t) I S 13826 Bitumen based felts - method of test (P + 5) 1993 Part-5 head resistance
test.
(u) I S 13826 Bitumen based felts - method of test (P + 6), 1993 Part - 6 water
absorption test.
(v) I S 13826 Bitumen based felts - method of test (P + 7) 1993 Part-7 determination of
binder content.
___
The field engineers and other readers are requested to send articles
on various issues, which they feel important enough to be shared with
others through this common forum of Indian Railway Construction Bulletin.
The articles may be sent on diskette or through E-mail so that editing at our
end can be done quickly.
- EDITOR
<„ Q ¤ „ yÔÃ
C O N T E N T S
Page No.
1. Economic Designs of Hume Pipes for Railway Embankments and Upgrading (1)
of Existing Hume Pipes Designed for BGML Standard (Constructed in 1970)
to HM Loading Standard (A Case Study)
By
S. C. Gupta. Dy. CE/C/Designs, Bhubaneshwar
Ô_™≤»_™” ßdßÙ· _d™ Úd‹_™Dd* VDæD @¤⁄Ô <_™e ‘e <„YDæ Í<≤„D¤· L™ß Ùd ΩRæÙd≤ _d™ <„YDæ ≤´»* ´I $
The views expressed by the authors of Technical Papers are not
necessarily the views of IRICEN.
(i)
THIS IS YOUR BULLETIN, SHOULDN'T
YOU BE CONTRIBUTING TO IT?
Editor, Indian Railways Construction Bulletin
extends an invitation to all its readers to take active
part in the publication of the Bulletin.
Do send any articles, experiences, notes and
suggestions which you think would make interesting
and informative reading to other readers of our
Bulletin.
You could also give us some ideas on how
to improve the Bulletin, its contents and its
presentations.
Any reader can contribute articles, but they
should be about your work environment and
experiences on maintnance & construction of works
and Bridges.
Please send your articles to:
The executive Editor,
Indian Railways Construction Bulletin,
Director,
Indian Railways institute of Civil Engineering,
Pune 411 001.
Fax: (020) 6128677
e-mail : [email protected]
Website : www.iricen.gov.in
Edited Published By :
The Director
Indian Railways Institute Of Civil Engineering,
Pune - 411 001.