Remedial Measures Incorporating Jet Grouting and Micropiles For The Construction of A New Back Ow Preventer
Remedial Measures Incorporating Jet Grouting and Micropiles For The Construction of A New Back Ow Preventer
Remedial Measures Incorporating Jet Grouting and Micropiles For The Construction of A New Back Ow Preventer
net/publication/345548076
CITATIONS READS
0 28
3 authors, including:
Naresh Gurpersaud
Keller Canada
28 PUBLICATIONS 52 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Naresh Gurpersaud on 09 November 2020.
ABSTRACT
A new back flow preventer (BFP) was constructed as part of Toronto’s West Don Lands (WDL) redevelopment in
preparation for the 2015 Pan Am Games. Movement of three adjacent existing bridge piers early during conventional
construction necessitated an embargo on dewatering, a change from conventional to innovative techniques as well as
remedial measures to construct the new backflow preventer. The site is located within the flood plain of the Don River
and is underlain by over 30 metres of weak organic deposits. Overlapping jet grouted columns were installed using the
double fluid process to create both a low permeability base plug and a vertical cut-off. Jet grouting parameters were
verified by conducting a full-scale pre-production test program. Rock-socketed micropiles were installed through the jet
grout base plug to support and tiedown the new chamber. Several challenges were encountered during remedial works,
namely revisions to the method and sequence required to mitigate further movement of the adjacent bridge piers.
Eventually additional micropiles were installed as part of a foundation retrofitting scheme to permanently transfer the
foundations of the three existing bridge piers to rock. Jet grouting was successfully applied to construct a base plug and
vertical cut-off to stabilize the ground and enable excavation works to be performed in the dry. Micropiles were
successfully applied to construct a foundation through the jet grout base plug as well as replacing the compromised
existing bridge pier foundations. Full scale pre-production test programs were conducted for both jet grouting and
micropiles. Details of the jet grouting, backflow preventer micropiles and bridge micropiles, including test programs and
challenges encountered during construction are outlined in this paper.
RÉSUMÉ
Un nouveau dispositif antirefoulement a été construit dans le cadre de West Don Lands (BNM) le réaménagement de
Toronto en préparation pour les Jeux panaméricains de 2015. Mouvement de trois adjacentes piles de pont premiers
cours de construction classique a nécessité un embargo sur la déshydratation, un changement du conventionnel à des
techniques novatrices ainsi que des mesures correctives pour construire le nouveau dispositif antirefoulement.Le site est
situé dans la plaine d'inondation de la rivière Don et est sous-tendue par plus de 30 mètres de dépôts organiques
faibles. Jet injecté colonnes se chevauchent ont été installés à l'aide du processus à double fluide pour créer à la fois un
bouchon de base à faible perméabilité et un vertical coupure. paramètres d'injection de Jet ont été vérifiées par la
réalisation d'un programme de test de pré-production à grande échelle. micropieux Rock-socketed ont été installés à
travers le bouchon de base de coulis de jet de soutenir et d'arrimage de la nouvelle chambre. Plusieurs défis ont été
rencontrés lors de travaux de réparation, à savoir la révision de la méthode et la séquence nécessaire pour atténuer
davantage le mouvement des piles de pont adjacentes. Finalement micropieux supplémentaires ont été installés dans le
cadre d'un régime fondation de modernisation de transférer définitivement les fondations des trois piles de pont au rock.
Jet grouting a été appliquée avec succès à construire un bouchon de base et verticale coupure pour stabiliser le sol et
permettre des travaux d'excavation à effectuer sur le sec. Micropieux ont été appliquées avec succès pour construire
une fondation à travers le bouchon de base jet de coulis ainsi que le remplacement des fondations de pile de pont
existantes compromis. Programmes d'essais de pré-production à pleine échelle ont été menées à la fois pour jet
grouting et micropieux. Détails du jet grouting, micropieux reflux préventifs et micropieux de pont, y compris les
programmes et les défis rencontrés lors de la construction essai sont décrites dans le présent document.
2 GEOLOGICAL SETTING silt, clayey silt till and highly weathered shale of the
Georgian Bay formation at 28 m below grade.
The site is located in the area where the Don River used Approximately 3 m of weathered shale is present before
to flow before being straightened out at the start of the sound rock is encountered. A dense, wet, sand layer
20th century. The soil profile consists of clayey silt and exists at locations closer to the Don River at depths
organic fill from 0-5 m below existing grade. Weak organic around 20-25 m. Figure 2 shows the subsurface profile at
silt with SPT ‘N’ values between 0 and 7 then make up the the location of the backflow preventer.
profile from 5 m to approximately 13 m below existing
grade. The remainder of the profile is made up of sandy
Figure 2: Subsurface profile at work location
Description Designed Average Throughout the jet grouting operations, numerous quality
control measures were implemented to continuously
Column dia. (m) 1.8 2.2 monitor the jet grouting parameters (i.e. lift, flow, rotation,
pressure, air flow, etc.). All DAQ reports from each
installed column were reviewed to ensure consistency
In-situ permeability (cm/s) 1 x 10-5 1.69 x 10-5 with the site specific parameters. A typical plot obtained
during the jet grouting of a column is shown in Figure 5.
Unconfined compressive Samples of grouting spoils being expelled from the collar
1 3.2
strength after 28 days(MPa) of the hole were captured at regular intervals and
measured for specific gravity. Spoils samples were also
Specific Energy (MJ/m) 50 50 cast into grout cube moulds and sent to an accredited
independent testing laboratory for unconfined
compressive strength (UCS) testing. Every jet grout
column was surveyed and the SAA data was reviewed
3.5 JET GROUTING METHODOLOGY and plotted in a timely manner to identify potential gaps in
the cut-off and base plug. The SAA (Shape Accel Array)
A dynamic process was implemented for establishing the tool is a reel mounted unit with 3 MEMS (micro
layout of the jet grout columns considering the existing electromechanical systems) in every segment, spaced at
sewer, steel bracing, sheet piles and restricted access. In 0.5 m intervals. This unit is able to provide real time data
advance of jet grout installation, all as-built information of the inclination and orientation with a single shot
was incorporated to establish a preliminary scheme to measurement. A 3-D grouting profile was developed and
create adequate overlap of the jet grout columns despite updated on a daily basis due to the obstructions and
the several interferences at various depths throughout the complexity in achieving the desired column overlap.
treatment profile. Jet grouting was performed using a
specially configured drill rig with on-board data acquisition
(DAQ) and control system to perform jet grout installations
in a fully automated mode. Grout slurry was batched using
Figure 5: A typical plot obtained from the DAQ system during jet grouting of a column
3.5.2 POST CONSTRUCTION VERIFICATION Table 2.0: Summary of results from the post-production
falling head tests
Upon completion of the jet grout columns, two P-size
cored holes were advanced 11 m below surface to Hole Location Permeability (cm/s)
penetrate into the 3 m deep jet grout base plug and falling CH-1 2.34 x 10-6
head permeability tests were performed. The installation
procedure of the cored holes was modified from the CH-2 2.75 x 10-7
process used to conduct testing on the pre-production jet
grout columns. A P-size casing was advanced 0.5 m into
the jet grout base plug and a tremie plug was installed to 4 CHAMBER MICROPILES
seal the casing in place. Coring of the 1 m long test
section was performed 24 hours after installation of the P- When the project first encountered crisis and the decision
size casing was set in place. The results obtained from was reached to change the construction approach to
the falling head tests performed in the two cored holes are incorporate jet grouting, the project designers had a new
provided in Table 2.0. problem to tackle in the form of the deep foundation for
the cast-in-place concrete BFP chamber. The original
scheme of founding the chamber on H-piles driven to rock
was no longer feasible given the extreme sensitivity of the
bridge piers. The driven H-piles were replaced with twelve
rock-socketed micropiles designed to resist both
compression and uplift forces, installed from existing
grade after jet grouting but prior to chamber excavation.
ACKNOWLEDGEMENTS