Site Visit Procedure Stat-X
Site Visit Procedure Stat-X
Site Visit Procedure Stat-X
1. Upon arrival coordinate to person in charge about site checking for STAT-X
fire suppression system design requirements(total flood or local
application).
2. Checks the site status room or equipment is ready for visual inspection, if
yes proceed to number 3 procedures.
3. Check the following requirements for design.
- Type of room to be protected.
- Dimension of room or equipment.
Note:
1. Length, Width and Height, also check if there’s a raised floor or
ceiling void to protect.
2. Check also the possible leakage of chemical (louver or exhaust fan
windows), measure the possible leakage.
-
4. Proposed possible location of the following components
o Control Panel – Wall must be concrete and check also the
concrete wall if there’s a pipe embedded installed, And Clear for
any obstruction for maintenance purposes, and visible for daily
maintenance checking.
Note:
1. Source of power supply for control panel not exceed 3 meters.
2. For Interfacing to FDAS, aircon shut down and damper switch
shut off we will provide only a contact not the installation and
termination.
o Manual release station – Wall must be concrete, and clear for any
obstruction, visible in case of fire, proposed location outside
room.
o Abort Station – Wall must be concrete, and clear for any
obstruction, visible in case of fire for checking if true fire.
Proposed location outside room.
o Alarm Bell – proposed location outside or inside room.
o Horn/Strobe - proposed location outside or inside room.
o STAT-X Aerosol – Install stat-x aerosol 15-30 degree Celsius aim to
the flooring not to protected equipment.
- Piping Installation concerns to be discuss to the client
o Exposed piping if fixed ceiling.
5. Safety protocols.
- PPE’s requirements
- Workers documents needed NBI Clearance, Police Clearance etc….if
necessary.
- Electrical equipment shut down if needed, safety assistance will be
provided by the client.
6. Work Permit including tools gate pass form
- Working Hours (must be minimum of 8 working hours)
- Site availability for installation MORNING OR EVENING
- Who/when will provide permit.
5. Discuss for work permit, gate pass and pull out form get a copy if
possible.