CRE Sample Test #2.: P X K e K K
CRE Sample Test #2.: P X K e K K
1. Which answer is the expected value of the Poisson distribution shown below ?
e - μμ k
P( x = k) = k = 0, 1, 2, 3,....
k!
A. μ B. μe - μ C. e-μ D. μ2
2. FMECA is :
A. A professional engineering organization.
B. A formal technique for review of failure potentials during design.
C. A technique to assure that design performance guidelines are fulfilled.
D. A technique useful for space-government project.
6. For human factors testing, the reliability engineer should understand and consider which of the following
?
. Sight capabilities.
. Touch capabilities.
. Audio capabilities.
. Thermal capabilities.
. Vibration capabilities.
A. , , B. , , ,
C. , , , D. , , , ,
7. What is the minimum number of failure free trips that one must make in their car to be at least 95%
confident it is 95% reliable ?
A. 22 B. 45 C. 58 D. 102
11. Looking at systems in terms of (1) a series-parallel functional configuration, (2) using a truth table
approach, or (3) performing a Monte-Carlo simulation are techniques for :
A. Trade-off studies. B. Sneak circuit analysis.
C. Modeling systems. D. Fault tree analysis.
13. When reliability deterioration of a system can be associated with independent and small multiplicative
effects of its components, the applicable time-to-failure distribution is :
A. Lognormal. B. Extreme value. C. Exponential. D. Weibull.
14. Typical statistical distributions or confidence limits can be determined for accelerated tests. In the case
of a step-stress test, the proper estimated distribution would be which of the following ?
A. Exponential. B. Weibull.
C. Lognormal. D. None, not meaningful.
15. What is the difference between an active parallel system and a shared load parallel system ?
A. There is no significant difference.
B. In the shared load parallel system, the load is equally shared between the two parallel components.
C. The shared load parallel system is a type of active parallel system.
D. The failure rate of the remnant component increases in the shared load parallel system on first
component failure.
16. Which of the following techniques is MOST effective for incorporating desired attributes into the
earliest stages of product design ?
A. FTA B. FRACAS C. QFD D. FMEA
17. Total productive maintenance seeks to eliminate the "six big losses". Which of the following are
included in that category ?
. Process defects.
. Environmental losses.
. Setup losses.
. Equipment failures.
19. If a company monitors field reliability using both three month and yearly MTBF moving averages, a
comparison of the averages will generally show that the yearly moving averages :
A. Are greater than the 3 month values. B. Are less than the 3 month values.
C. Vary more than the 3 month values. D. Vary less than the 3 month values.
20. Reliability testing plans may encompass :
. Fixed length tests.
. Probability ratio sequence tests.
. Longevity tests.
23. Failure occur on a system at 75, 79, 83, 85 hours. Assuming normality, one sided and unbiased the
lower tolerance limit for 95% reliability with 90% confidence for this sample is :
A. 96 hours. B. 60 hours. C. 100 hours. D. 63 hours.
A. , , B. , C. , , D. , ,
26. In a design team environment, the reliability function can influence product reliability principally by :
A. Integrating the reliability requirements into product design.
B. Developing reliability tests and procedures.
C. Conducting internal and external failure analyses.
D. Providing repair and maintenance service information.
27. An item was removed from testing after 25 hours without failing. This unit was :
. Right censored.
. Suspended.
. Truncated.
28. A good practice in selection of components is to select standard parts. The valid reasons include :
. Standard parts are generally proven and at a cost advantage.
. Use of standard parts sometimes reduces the number of different parts.
. Standard parts are usually more technically innovative.
. Standard parts might prevent inventory expansion.
. Standard parts usually are free from schedule concerns.
A. , , B. , , ,
C. , , , D. All of the above.
29. The failure data collection, analysis, and corrective action system :
. Should include failures due to equipment failure and those due to human error in
designing, manufacturing, and operating the equipment.
. Should include elapsed operating time (or cycles) prior to failure.
. Should include all failures from initial development through acceptance testing.
30. If the elements in the following logic diagram are independent, reliability is :
31. Balancing a reliability requirement against other design parameters, such as performance, cost, or
schedule, and then analyzing the consequences of placing special emphasis on one of these factors is
called
A. Reliability allocation. B. Trade-off decisions.
C. Reliability predictions. D. System modeling.
32. Which of the following tests are always performed on production items ?
. Demonstration Tests.
. Qualification Tests.
. Screening Tests.
35. A reliability test was terminated after 171 hours based upon a pre-established plan. An estimate of
mean-time-to-failure of 57 hours was obtained. The lower 95 percent confidence bound on the true
population mean-time-to-failure is :
A. 125 hours. B. 22 hours. C. 27 hours. D. 11 hours.
37. For equal length missions an increase in the MTBF will yield :
. An increase in availability.
. An increase in reliability.
. A decrease in reliability.
. A decrease in availability.
A. B. and C. D. and
38. The predicted reliability is higher than the long term realized probability. Which of the following is the
most likely cause of this difference ?
A. Deterioration of the manufacturing processes and procedures.
B. Lack of adequate employees training and process audits.
C. The accumulation of random process variations.
D. A poor initial estimation of reliability.
39. In the classification of defectives, such as DOD-STD-2101, if an item will produce a significant
degradation in performance, the classification would be :
A. Incidental. B. Minor. C. Critical. D. Major.
41. Large power generating stations frequently have auxiliary turbine generators operating at speed. They
do not produce power but act as back-ups. This type of redundancy is known as :
A. Active parallel system. B. Stand-by parallel system.
C. Shared load parallel system. D. Bayes' theorem application.
44. Given a reliability growth test in progress having accumulated 4 failures during 5000 test hours.
Assume a growth rate of 0.3, what is the expected MTBF at 25,000 hours ?
A. 1250 hrs. B. 1895 hrs. C. 1950 hrs. D. 2026 hrs.
46. An engineer must design a product with a probability of success 99%. Assume that both the strength
and stress are normally distributed and that the standard deviations are the same. If the stress is known
to be 3000 lbs with a standard deviation of 100 lbs, what must be the approximate designed strength ?
A. 4020 lbs. B. 3730 lbs. C. 3330 lbs. D. 3100 lbs.
47. Which test would potentially take longer than expected to complete ?
. Time terminated tests.
. Failure terminated tests.
. Sequential tests (PRST)
53. The main reason for the use of Quality Function Deployment (QFD) is which of the following ?
A. To implement the voice of the customer.
B. To ensure concurrent engineering.
C. To assign responsibilities for product designs.
D. To provide a structured product design approach.
54. Which of the following are the MOST desirable basic skills required of a reliability engineer assigned
to a cross-functional product team ?
A. Reliability trouble shooting, data collection and analysis.
B. Experience with FMECA and FTA.
C. Reliability planning, testing and measurement.
D. Communication, co-operation, and technical knowledge.
55. Design review should be a process to ensure and/or develop more reliable design. Which of the
following person(s), if any, should work with the designer during the design process ?
A. Reliability engineer. B. Designer only.
C. Management team. D. Design supervisor.
56. A Pareto analysis of field failure data indicates that several significant failure categories are
approximately equal in size. The BEST next course of action to take in selecting a category for
improvement would be which of the following ?
A. Take additional data until a more significant category is evident.
B. Select the category that offers the most overall cost saving.
C. Select the category that is easiest to fix.
D. Select the category that requires the least expense to fix.
57. The linear graphs which accompany Taguchi designs have as their objectives :
. Providing a compact design layout.
. Providing a visualization of the design options.
. Depicting where main factors can be assigned.
. Depicting where interactions may be evaluated.
58. A substantial fraction of the usual design effort need NOT be devoted to a reliability program. :
A. When the equipment is complex. B. When time is limited.
C. When high reliability is specified. D. When high reliability is not specified.
59. The means of large samples from a population tend to be normally distributed around the population
mean. This statement is TRUE according to which of the following theorems ?
A. Central limit. B. Camp-Meidel.
C. Tchebysheff's D. Least squares.
60. For a steady state large system reliability prediction which of the following distribution is normally used
?
A. Poisson. B. Exponential. C. Normal. D. Weibull.
61. For a high compression aircraft air conditioning system, the MTBF is 100 hours. This mean life is
allocated for four serial units comprising the total system. The unit failure rates are then weighted as
follows :
w1 = 0.1250 w3 = 0.1875
w2 = 0.2500 w4 = 0.4375
Based upon the above data, indicate which of the following is the correct calculation for one of the units.
A. λ 3 = 0.0018750 B. λ 4 = 0.0435700
C. λ 1 = 0.0125000 D. λ 2 = 0.0025100
62. Given mean-time-to-failure for three components as M 1 = 100 hours, M 2 = 500 hours M 3 = 1000
hours ; what is the mean-time-to-failure of the system if the three components are in series ?
A. 160 hours. B. 100 hours. C. 77 hours. D. 13 hours.
63. A person takes their car to the repair shop and it stops doing what it was previously doing. This is
an example of :
A. Catastrophic failure. B. Degradation failure.
C. Intermittent failure. D. Drift failure.
66. To conduct accelerated life tests, which of the following assumptions must be made ?
. The severity of the stress levels does not change the life distribution.
. The Arrhenius model is normally followed.
. The relationship between the stress level and the life distribution is known and valid.
. The testing is conducted at a stress level equivalent to or near failure conditions.
67. Parts in use during the "wear out" portion of the part life cycle curve will exhibit :
A. A constant failure rate. B. A low failure rate.
C. A decreasing failure rate. D. An increasing failure rate.
68. When testing is establish failure rate data and reliability predictions, which of the following is NOT
normally a feasible acceleration factor with respect to rated conditions ?
A. Longer time. B. Greater humidity.
C. Higher temperature. D. Higher voltage.
69. Maintenance repair tasks in a large scale system with constant repair rates follow which of the
following distributions ?
A. Normal. B. Exponential. C. Lognomal. D. Geometric.
70. The purpose of a failure reporting, analysis and corrective action system(FRACAS) includes which two
of the following ?
. Provide a closed loop failure reporting system.
. Provide initial robust product designs.
. Provide management with derating methods and principles.
. Provide a failure analysis and corrective action vehicle.
A. , B. , C. , D. ,
75. Which one of the following would NOT be necessary in a corrective action status report ?
A. Due date. B. Failure cost.
C. Responsible function (department). D. Failure identification.
76. Which of the following actions would usually be performed FIRST after receiving a product failure from
the field ?
A. Verification of failure. B. Estimate possible causes.
C. Assignment of investigative actions. D. Determine possible mode of failure.
78. Which one of the following quantitative methods does NOT apply to the assessment of actual
system/component reliability ?
A. Statistical analysis of field test data.
B. Statistical allocation of reliability goals.
C. Evaluation of laboratory and acceptance test data.
D. Analysis of result for reliability demonstration test.
79. The prediction technique has obviously not always been effective quantitatively. There is often a wide
difference between actual reliability and predicted reliability. Nevertheless, the reliability prediction technique
permits :
A. Separating out "the vital few" from the "trivial many".
B. Spotlighting what has gone wrong with the program.
C. Indicating which department is to blame.
D. Estimating how good the product really is.
81. When performing trade-offs in evaluating parts for reliability, which of the following is LEAST important ?
A. Technical comparison of new part with standard part type.
B. Search of data part history to established reliability potential.
C. Process and materials compatibility.
D. Initial parts costs.
84. The design function which assigns probability of failures between components or subsystems is called :
A. Confidence. B. Significance. C. Apportionment. D. Qualification.
85. A component fails on the average of once every 4 years with 75% of the failures observed to occur
during stormy weather. If there are 12 hours of stormy whether to every 240 hours of good weather, what
are the failure rates for stormy and good weather respectively ?
A. λ (stormy) = 3.938, λ (good) = 0.0656 failures/yr
B. λ (stormy) = 4.202, λ (good) = 0.0525 failures/yr
C. λ (stormy) = 6.594, λ (good) = 0.0458 failures/yr
D. λ (stormy) = 4.000, λ (good) = 0.0655 failures/yr
86. Root cause failure analysis is necessary to identify and correct basis problems. Usually a priority of
failure mode is established. This classic or traditional approach to improvement results in which of the
following ?
A. Zero defects. B. Defect reduction.
C. Catastrophic problem reduction. D. Special cause reduction.
87. What is the Z value needed to conduct a two tail test in a statistical inference problem, specifying
90% level of confidence ?
A. 1.96 B. 1.28 C. 1.65 D. 2.24
88. The probability of survival (or, reliability), using an exponential distribution can be defined by which of
the equations on the left ?
Where
Rs = system reliability = probability of survival.
m = mean time between failures.
t = time of test.
λ = failure rate.
.
. . .
89. A random sample of 100 bars of aluminum shows a tensile strength mean of 30,000 psi and a
standard deviation of 3,000 psi. On the basis of this sample, what is the 95 percent confidence interval
for the average tensile strength ?
A. 30,000 ± 528 psi B. 30,000 ± 600 psi
C. 30,000 ± 588 psi D. 30,000 ± 768 psi
90. A reliability test of 12 pumps is terminated at 1000 hours. There were 5 failures as follows, what is
the median rank % for the 4th failure ?
91. In 4 flips of a coin the probability of two heads and two tails (in any order) is:
A. 9/16 B. 7/16 C. 1/2 D. 3/8
92. The hazard function is :
. The probability of failure during a very small time interval, assuming a failure occurs before that
time.
. A function of constant failure rate only.
. A function of increasing failure rate only.
. The ratio of the probability density function to the reliability function.
94. Which mathematical method provides a solution, has a time dimension and is solved numerically ?
A. Strength and stress model. B. Simulation model.
C. Analytic solution. D. None of the above.
95. The distribution which has a mean equal to the variance is the :
A. Poisson. B. Exponential. C. Weibull. D. Rayleigh.
96. Preventive maintenance is usually performed in the plant to ensure smooth transformation of raw
materials to finished goods. A prime assumption for preventive maintenance action is :
A. Cost of failures are more than scheduled maintenance costs.
B. The part is in an increasing hazard rate period.
C. A constant hazard rate would result in no preventive maintenance.
D. The minimum point for total costs.
97. The basic maintainability requirements for a system or component is BEST determined via :
A. Analysis of customer requirements.
B. Analysis of test data.
C. Analysis of field (actual) data.
D. The compatibility of design engineering and maintainability engineering.
98. Given a system requirement of maintainability (MTTR) of 4.7 hours. There are 5 devices in series with
the following individual failure rates and MTTR.
102. If the average repair time for a system is 3 hours and the MTBMA is 122 hours, what is the
operational availability ?
A. 0.975 B. 0.976 C. 0.982 D. 0.997
103. An appropriate preventive maintenance program can greatly increase the overall availability of a
system because of :
. An increase in observed reliability.
. An improvement in product or system safety.
. A reduction in spare parts inventory.
A. I and II only B. I, II and IV only C. II, III and IV only D. I, II, III and IV
105. The use of plug-in devices improves all of the following EXCEPT :
A. Mean time to repair. B. Design reliability.
C. Interchangeability. D. Fault isolation time.
106. Availability of a system is roughly the :
A. Product of the individual subsystem availabilities.
B. Sum of the individual system availabilities.
C. The difference of the individual subsystem.
D. The quotient of the individual subsystem availability.
A. I, II and III only B. II and IV only C. I, II and IV only D. I, II, III and IV only
110. Feedback channels for the planning, management and assessment of product safety should include :
. Both official and unofficial sources.
. Phone, fax, mail and questionnaire sources.
. Captured company process information.
A. I and II only B.I and III only C. II and IV only D. I and IV only
112. A go/no-go device is tested until it fails. If X is the number of tests to first failure with no wear out
present, and the probability of success on each test is .99, then the probability that X is greater than 5 is
:
A. 0.9510 B. 0.9410 C. 0.9310 D. 0.9610
115. A system has components connected in active parallel. At least n - 1 of the components must
operate for the system to function properly. Suppose the time to failure of each component has an
exponential distribution with the same failure rate λ. The mean time to failure of this system is :
A. (2n - 1)/n(n - 1) λ. B. 1/(n - 1) λ
2
C. 2/(n - 1) λ D. (n - 1)/n λ
116. In order to attain a high order of series reliability :
A. The number of parts must be kept to a minimum.
B. The number of parts must be increased.
C. The number of parts must have a low failure variance.
D. The number of parts is insignificant if each part has a reliability of 99 percent of more.
117. For equipment consisting of three components connected in series whose respective reliabilities are
0.95, 0.94, 0.96, which could be used to calculate total probability ?
A. Exponential failure law. B. Addition law. C. Product rule. D. Bayes Theorem.
118. What is the failure rate of a system composed of three components, each of which can cause a
system failure, and which have the following information ?
119. The probability of an accident for the head event "H" given below is :
A. 0.0700.
B. 0.1125.
C. 0.0689.
D. 0.1100.
120. Which of the following FTA statements is NOT true ?
A. It provides corrective actions for component failures.
B. It includes common mode failure effects.
C. It indicates the critical path from system failure to component failure.
D. It illustrates the overall system behavior.
121. The reliability engineer's ultimate goal in most organizations may be BEST expressed as :
A. The reduction of warranty returns and improvement of test yields.
B. The minimization of product failure rate during the constant failure rate period.
C. The analysis and optimization of full life cycle cost impact.
D. The identification and elimination of all failure modes.
124. Total system effectiveness can be predicted during the conceptual or development design by
considering three main elements of reliability. Which of the four elements does NOT apply ?
A. Inherent reliability. B. Manufacturing reliability.
C. Test reliability. D. Use reliability.
125. The first phase in the operation life history of a population of product units is typically called :
A. Debugging phase. B. Wear out phase.
C. Transition phase. D. Chance failure phase.
126. It is reliability's job to see that all the tasks outlined in the reliability program are :
A. Carried out by reliability engineers.
B. Carried out by the department having the primary responsibility.
C. Making sure that quality control does its job.
D. Doing those jobs that the primary responsible departments are incapable of doing.
127. With respect to calculating a mission reliability, the time of the operating mission is :
A. Always an important consideration.
B. More important than the failure rate.
C. Important only when discussing outer space exploration projects.
D. Important only when assuming a constant failure rate.
129. All of the following activities would be appropriate during the design and development stage of a
product' life cycle EXCEPT :
A. Formalizing reliability requirements. B. Measuring production reliability.
C. Initiating the reliability growth testing. D. Performing reliability analysis.
130. Successful reliability programs should address which of the following elements ?
. Defining of the program and developing reliability goals and requirements.
. Designing for reliability and manufacturing feasibility.
. Assessing and measuring of reliability progress and ensuring reliable performance.
. Providing for sequential and qualification testing plans in usage stage.
132. What is the probability of performing a repair within 10 hours, if the MTTR is 10 hours ?
A. 0.368 B. 1.00 C. 0.632 D. 0.500
133. What type of failure is usually reduced by periodic overhaul and replacement of component parts ?
A. Early life. B. Wear out. C. Random. D. Catastrophic.
134. The margin of safety in a design is BEST described by which of the following statements ?
A. The ratio of the variance of the stress to the strength.
B. The ratio of the mean load to the mean strength.
C. The ratio of the difference between the mean strength and the mean load.
D. The mean load variance divided by the mean strength variance times 100.
135. In the House of Quality, the principal matrix shows the relationship between :
A. Specifications and Results. B. Quality Requirements and Quality Inspection.
C. Wants and Hows. D. Reliability Results and Time.
138. Calculate the worst case minimum using the root-sum squared analysis for a 1000 μF capacitor
using the following information.
Bias (%)
Parameters: Capacitance Random (%)
Neg. Pos.
Initial Tolerance at 25 - - - - 10
Low Temp (-20 ) 20 - - - -
High Temp (+80 ) - - 25 - -
Other-Envt's (Hard Vacuum) 15 - - - -
13 2
Radiation (10KR, 10 N/cm ) - - 5 - -
Aging - - - - 15
140. Which of the following should be avoided in parts selection to enhance the design reliability ?
A. Selection of standard parts. B. Selection of exotic technology parts.
C. Selection of redundant parts. D. Selection of high reliability parts.
143. For complex electronics systems, the major contributor to repair time is generally:
A. Final checkout. B. Disassembly/reassembly.
C. Remove/replace. D. Diagnosis.
144. Failure modes and effects analysis involves what activity ?
A. The determination of the probability of failure in a specified period of time.
B. The expected number of failures in a given time interval.
C. The study of the physics of failure to determine exactly how a product fails and what causes the
failure.
D. A study of the probability of success in a given time period.
A. The limits for an X Bar control chart. B. The limits for a Range chart.
C. The process capability adjusted for centering. D. The probability of meeting specification.
147. The designer has certain tools for reliable design at his/her disposal. He/She can :
. Simplify the design and minimize the number of parts without degrading performance.
. Perform design reliability review by means of reliability analysis.
. Apply component derating techniques.
. Reduce the elevated operating temperature of components.
A. I and III only B. II and IV only C. I, II and III only D. I, II, III and IV
148. Of the following, which is the MOST important reliability principle ?
A. Use only proven designs.
B. Specify only high reliability components.
C. Consider reliability early in the design phase.
D. Use redundancy throughout the design.
150. The department having the authority to sign all deviations pertaining to the design of the product is
normally :
A. Inspection. B. Manufacturing engineering.
C. Design engineering. D. Contractual.
Solutions :
1 A 16 C 31 B 46 C 61 A 76 A 91 D 106 A 121 C 136 D
2 B 17 B 32 C 47 B 62 C 77 D 92 D 107 D 122 C 137 D
3 A 18 A 33 B 48 A 63 C 78 B 93 C 108 C 123 D 138 A
4 D 19 D 34 D 49 D 64 D 79 A 94 B 109 D 124 C 139 D
5 A 20 D 35 B 50 A 65 A 80 D 95 A 110 D 125 A 140 B
6 D 21 C 36 C 51 C 66 B 81 D 96 A 111 D 126 B 141 D
7 C 22 C 37 B 52 B 67 D 82 B 97 A 112 A 127 A 142 A
8 B 23 D 38 A 53 A 68 A 83 A 98 B 113 A 128 D 143 D
9 C 24 A 39 D 54 D 69 B 84 C 99 D 114 A 129 A 144 C
10 B 25 B 40 C 55 A 70 C 85 A 100 D 115 A 130 C 145 C
11 C 26 A 41 B 56 B 71 B 86 B 101 C 116 A 131 B 146 A
12 A 27 A 42 D 57 C 72 C 87 C 102 B 117 C 132 C 147 D
13 A 28 B 43 D 58 D 73 D 88 C 103 A 118 B 133 B 148 C
14 D 29 D 44 D 59 A 74 C 89 C 104 B 119 C 134 C 149 C
15 D 30 B 45 B 60 B 75 B 90 B 105 B 120 A 135 C 150 C