Drainage Systems
Drainage Systems
1. INTRODUCTION
1.1 Background.
Drainage system is a process of removing & controlling excess surface
water with in right of way. Drainage is an important feature in determining the
ability of given pavement to withstand the effects of traffic and environment.
(Adequate drainage is very essential in the design of highways since it affects the
highway's serviceability and usable life. If bonding on the traveled way occurs,
hydroplaning becomes an important safety concern. Drainage design involves
providing facilities that collect, transport and remove storm water from the
highway (O'Flaherty, C.A. (2002).
As the water can cause a serious impact on both the road access and its strength,
an efficient drainage system is the most important part of road construction and
maintenance works.
Ensuring good drainage begins when selecting the road alignment. A Centre line
that avoids poorly drained areas, large runoffs and unnecessary stream crossings
will greatly reduce the drainage problems. Provision of sufficient drainage is an
important factor in the location and geometric design of highways. Drainage
facilities on any highway or street should adequately provide for the flow of water
away from the surface of the pavement to properly designed channels. In
addition, traffic may be slowed by accumulated water on the pavement, and
accidents may occur as a result of hydroplaning and loss of visibility from squish
and sprig. The importance of enough drainage is recognized in the amount of
highway construction dollars allocated to drainage facilities. About 25 percent of
1
highway construction dollars are spent for erosion control and drainage structures,
such as culverts, bridges, channels, and ditches (Wyatt et al, (2000).
Roads will affect the natural surface and subsurface drainage pattern of a
watershed or individual hill slope. Road drainage design has as its basic objective
the reduction and/or elimination of energy generated by flowing water. Therefore,
water must not be allowed to develop sufficient volume or velocity so as to cause
excessive wear along ditches, below culverts, or along exposed running surfaces,
cuts, or fills. Provision for adequate drainage is of paramount importance in road
design and cannot be overemphasized. The presence of excess water or moisture
within the roadway will adversely affect the engineering properties of the
materials with which it was constructed. Cut or fill failures, road surface erosion,
and weakened sub grades followed by a mass failure are all products of
inadequate or poorly designed drainage. As has been stated previously, many
drainage problems can be avoided in the location and design of the road:
Drainage design is most appropriately included in alignment and gradient
planning (Larson, C. L. June 1949).
2
1.2 Statement of problems
1. The design peak discharge calculated and the review peak discharge calculated
of the return period is not equal. From this the road around this is damaged by
over flooding of the water on the road because the calculated peak discharge for
the design were less than the calculated peak discharge for the review at station,
0+30, 0+400 and 0+85 .Therefore before the culverts are constructing the design
and the review data must be checked always when its design the road it must be
the design peak discharge is greater than the review peak discharge to control the
floods that over follow on the road.
4. The inadequacy of drainage system during the rainy season to pass the flood,
poor quality construction and improper maintenance of some drainage systems
with respect to the road alignment.
This is the main reason why this study wants to analyze the factors
contributing to the drainage and come up with corresponding recommended
remedial measure.
3
The study is expected to propose appropriate solutions to the drainage systems
whose implementation would contribute to the sustainability of the case study
road.
What are the major causes of drainage system that affect the road segment?
1.5 Objectives
The main Objectives of the research study are as follows:
To identify the major cause of the road damages which was affected by
drainage problem.
To evaluate the hydrological condition of the existing road drainage system
in the study area.
4
1.7 Structure of the Research
The structure of research is as follow:
CHAPTER ONE content to: INTRODUCTION (Background ، Statement of
the problems ، Significance of the study ، Research questions ، Objectives and
Scope and Limitation of the Study.
CHAPTER TWO: content LITERATURE REVIEW (Introduction ، Road
Surface Drainage، Shoulders ،Cross slope ، longitudinal drainage ،Subsurface
drainage systems (culverts،Alignment of Drainage System، Description and
Function of Road Drainage System ، Description of Road Drainage Systems ،
Functions of Road Drainage Systems ، Failures of Road Drainage System ،
Effects of Drainage on Roads، Culverts ، Components of a road and pavement
drainage system ،Necessities to Construct Drainage System ،The Criteria for
Roadside Channels ، Design Flood for Road Drainage System ، Flow Velocity in
Road Drainage System ، Hydrological Analysis and Hydrological Equations for
Determining Peak Flood.
CHAPTER THREE: content to METHODOLOGY (Research Methodologies
، Study Area ، Study period،Research design ، Study population ، Sample size and
sampling procedures ،Study variables،Data collection process ، Data processing
and analysis ، Ethical considerations ، Data quality assurance ، Limitations of the
study and Rational Method
CHAPTER FOUR: content to RESULT AND DISCUSSION (Results from
analysis، Causes and effects of drainage system on asphalt road that response
from the Engineers ،Results from observation and photography
، Investigations of Design and Construction Performs on the study area، Results
from Hydrological Analysis and Peak Discharge Computation
CHAPTER FIVE: content to CONCLUSION AND RECOMMENDATION
(Conclusion and Recommendation)
5
CHAPTER TWO
2. LITERATURE REVIEW
Any damage or failure of this highway drainage system can cause the risk of the
lives of road users as well as create serious influence to the entire country
economic development.
The two main types of water flows that can be considered are the flows
that usually crossing the area that could be diverted by the presence of the road,
and the flows generated by the runoff of the rainwater falling on the carriageway
and its surroundings. The basic design techniques in roadway drainage system
should be developed for economic design of surface drainage system including
ditches, culverts and bridges (ERA manual, 2002). A hydraulic investigation and
analysis of both the upstream and downstream reaches of the watercourse is
necessary to determine the best location, size, and elevation of the proposed
crossroad structure, whether a culvert. The investigation should ensure that any
roadway system or roadway embankment that encroaches on or crosses the flood
plain of a watercourse would not cause significant adverse effect to the flood
plain and would be capable of withstanding the flood flow with minimal damage.
It is significant to provide attention during design of the magnitude, frequency
and appropriate water surface elevations for the design flood, the 100-year flood,
and the overtopping or 500-year flood for all structures (ADOT, 2007).
A drainage system includes the pavement and the water handling system. They
must be properly designed, built, and maintained. The water handling system
6
includes: road surface, shoulders, drains and culverts; curb, gutter and storm
sewer. When a road fails, whether it's concrete, asphalt or gravel, inadequate
drainage often is a major factor. Design can direct water back into the road or
keep it from draining away.
2.2.1 Shoulders
Shoulders help provide lateral support for the pavement, carry water
from the pavement to ditches, and give vehicles a place to go if they lose control
or need to stop in an emergency show figure 2.1. For drainage they need to be
slightly steeper than the pavement and should be able to withstand occasional
traffic. Erosion and washing of shoulders is a major problem and should be
addressed by using less erosive material on the surface.
7
2.2.2 Cross slope
Cross slope is provided to provide a drainage gradient so that water would
run off the surface to a drainage system such as a street gutter or ditch. Water
would flow faster on a paved surface. Therefore the slope of a road surface does
not need to be steep. The cross slope should not be too steep. If it is, the water
running off the side would start eroding the shoulder and sides of the road.
8
stream stability, to construction and maintenance costs, and to the safety &
integrity of the roadway. Proper alignment is also particular importance to
prevent outlet scour or excessive sediment build up in the road According to ERA
geometric design manual (ERA, 2011).
A surface drainage system collects and diverts storm water from the
road surface and adjoining areas to avoid flooding. It decreases the possibility of
water infiltration into the road and retains the road bearing capacity. Appropriate
design of the surface drainage system is an essential part of road design (GDD
2011). Sub-surface drainage systems drain water that has infiltrated through the
pavement and the inner slope but also ground water.
9
Township paved road. Due to inadequate capacity of the drainage. If the failure is
sudden and catastrophic, it can result in injury or loss of life and property.
10
2.8 By drainage effects of water on road
Softening and reducing the load carrying ability of sub grades and
shoulders; increasing the disintegration of pavements and gravel surfaces;
2.9 Culverts
Culverts are shallow passages that are fitted under roads that allow
water to pass beneath them. They can be made of either steel, plastic or concrete.
A culvert helps move water under a road or driveway to a stream, lake or
detention basin. The purpose of culverts is to safely convey water from one side
of the road way to the other show figure 2.3. The water may be from natural
streams or runoff surface water from the road structure or areas close to the road.
A culvert must be durable and have sufficient hydraulic capacity to carry a
predetermined quantity of water for a given time (NAAS, 1986). Generally,
drainage structures designed to prevent road damage during the most usual floods
such as annual, 10-year, 25-year 50-year or 100-year flood, depending on the
importance of the road and the type of structures (ERA, 2002) and to minimize
the modifications in the hydrology of the area. Culverts conveying cross drainage
flow from outside should be located on the natural drainage path of the flow.
When the natural drainage path of the flow is a wide overland flow area, the
designer should evaluate the need for multiple culverts in order to prevent
concentrated flow at a single location. The proposed cross culvert must be aligned
with upstream and downstream channels. Culverts are the most common cross
drainage structures used on roads. They are built using a variety of materials, in
different shapes and sizes, depending on the preferred design and construction
practices. Culverts are required in order to (i) allow natural streams to cross the
road, and (ii) discharge surface water from drains and the areas adjacent to the
road. Culverts form an essential part of the drainage system on most roads.
Culverts are constructed using different materials. The most common practice of
culverts is based on the use of pre-cast concrete pipes, in-situ concrete boxes and
corrugated steel pipes culverts. The box culvert is generally built with 1 to 3 cells
of width 1m to 3m and the pipe culvert is built with 1 to 3 rows of pipes with
diameters commonly ranging from 0.6m to 1m. Wing walls and aprons of
concrete or stone pitching are used to protect the culverts from water flow erosion
and scouring at upstream side. Culverts should slope enough so water will flow
(NCHRP, (1997)).
11
Culvert drainage structures shall be adequate to avoid hazardous flooding and
failures of road or embankment structures. Poorly designed culverts are also more
appropriate to become blocked with sediment and debris during medium to large-
scale rain events.
This can cause the road to fail, often introducing a large amount of fine
sediment that can clog other structures downstream and also damage crops and
property. Hard bank armoring and a proper sized structure can help to alleviate
this pressure.
Providing scour protections are important at both inlet and outlet for all
culverts to protect the structure from damage. Providing rock armor is significant
protection measure of scour for inlets and outlets of culverts. Moreover,
headwalls and end walls utilized to control erosion and scour, to anchor the
culvert against lateral pressures, and to ensure bank stability. Constructing all
headwalls from reinforced concrete material is significant and may be straight and
parallel to the channel, however, flared or warped, with or without aprons is
possible when the site and hydraulic conditions permit.
To prevent the possible piping failure, cement stabilized fill can be used to form
the culvert invert bedding for a suitable length. These measures found to perform
well in clayey/silt/sandy soils (ERA manual 2002).
12
2.10 Components of a road and pavement drainage system.
Drainage system on a given road and pavement is made up of various
components, which are supposed to conduct the water to appropriate discharge
points. It is important that components of a drainage system work well together.
If one component of the drainage system breaks down, it will not only
compromise drainage in that specific location, but may lead to overloading other
drainage components which in turn may lead to more damage of roads due to
flooding. Less effective components will show signs of its shortcomings through
excessive scoring, accumulation of silt or entire washouts.
2.10.1 Ditches
Ditches carry water away from the roadway and into streams or other
natural waterways. To do this, ditches must be properly shaped for safety,
maintenance, water flow, and erosion control. The ditch should be at least one
foot below the bottom of the gravel base in order to drain the pavement. Ditches
should extend to shoulders with smooth transition to fore slope show figure 2.4.
A well maintained, smooth flowing ditch will be free of heavy vegetation (tall
grass) and standing water, with enough grades to ensure self-cleaning and
continuous flow.
13
2.11 Necessities to Construct Drainage System
A complete drainage system design includes consideration of both major
and minor drainage systems. The minor system, sometimes referred to as the
"Convenience" system, consists of the components that historically considered as
part of the "storm drainage system". These components include curbs, gutters,
ditches, inlets, access holes, pipes and other conduits, open channels, detention
basins, and water quality control facilities (Achleitner S. (2006). According to
HEC (Hydrologic Engineering Centre) No. 22(10), the minor system normally
designed to carry runoff from 10-year frequency storm events (FHWA (Federal
Highway Administration), 2001).
14
the design storm event. Minor culverts designed for a 10-year storm and checked
for adequate performance with a 25-year interval storm event.
15
Therefore, I used the rainfall intensity from the ID curve for the corresponding
return period (from Ethiopian national methodology).
16
Characteristics of the Rational Method that generally limit its use to 0.5km2
include:
(1) The rate of runoff resulting from any rainfall intensity is a maximum when the
rainfall intensity lasts as long as or longer than the time of concentration. That is,
the entire catchment area does not contribute to the peak discharge until the time
of concentration has elapsed.
(2) The frequency of peak discharges is the same as that of the rainfall intensity
for the given time of concentration. Frequencies of peak discharges depend on
rainfall frequencies, antecedent moisture conditions in the catchment area, and the
response characteristics of the drainage system. For small and largely impervious
areas, rainfall frequency is the dominant factor.
(3) The fraction of rainfall that becomes runoff (C) is independent of rainfall
intensity or volume.
This assumption is only reasonable for impervious areas, such as streets, rooftops,
and parking lots. For pervious areas, the fraction of runoff does vary with rainfall
intensity and the accumulated volume of rainfall.
(4) The peak rate of runoff is sufficient information for the design. Modern
drainage practice includes detention of urban storm runoff to reduce the peak rate
of runoff downstream. Using only the peak rate of runoff, the Rational Method
severely limits the evaluation of design alternatives available in urban and in
some instances, rural drainage design.
Equation: The rational formula estimates the peak rate of runoff at any location
in a catchment area as a function of the catchment area, runoff coefficient and
means rainfall intensity for duration equal to the time of concentration (the time
required for water to flow from the most remote point of the basin to the location
being analyzed). The rational formula is expressed as:
Q = 0.00278CIA (2.1)
Where:
17
The basic assumptions in rational method to determine peak flood are:
1. The peak rate of runoff at any point is a direct function of the average rainfall
intensity for the time of concentration to that point.
2. The recurrence interval of the peak discharge is the same as the recurrence
interval of the average rainfall intensity.
3. The time of concentration is the time required for the runoff established and
flow from the most distant point of the drainage area to the point of discharge.
The main reason that is required to limit the use of rational method for small
watersheds pertains to the assumption that rainfall is constant throughout the
entire watershed. Severe storms, say a 10-year return period, generally cover a
very small area. Applying the high intensity corresponding to a 10-year storm to
the entire watershed could produce greatly exaggerated flows, as only a fraction
of the area may be experiencing such intensity at any given time.
The variability of the runoff coefficient also favors the application of the rational
method to small and developed watersheds.
i. Drainage area
iv. Distance from the farthest point of the drainage area to the point of discharge
v. Difference in elevation from the farthest point of the drainage area to the point
of discharge
2. Determine the time of concentration for the selected recurrence interval with
duration equal to the time of concentration
18
2.16.1.1 Runoff Coefficient
The runoff coefficient (C) is the variable of the Rational Method least
susceptible to precise determination and requires judgment and understanding on
the part of the designer. A typical coefficient represents the integrated effects of
many drainage basin parameters.
C1, C2, --------Cn= coefficient of runoff for parts of the drainage area.
A1, A2, ------, An= parts of drainage areas with different runoff coefficients.
19
precipitation intensity for a given storm duration. Furthermore, as storm duration
increases average precipitation intensity decreases.
The relation between storm duration, storm intensity, and storm return interval, is
represented by a family of curves called the intensity-duration-frequency curves,
or IDF) curves. Quantification of rainfall is generally carried out using is pluvial
(Return Period) maps and intensity-duration-frequency (IDF) curves (Chow et al.,
1988). Various rainfall contour maps developed to provide the design rain depths
for various return periods and durations (Hersh field, 1961). The IDF relationship
is a mathematical relationship between the rainfall intensity, the duration, and the
return period for this research, ERA regionalized IDF curves are used to quantify
rainfall.
The velocity of flow depends on the catchment characteristics and slope of the
watercourse. It is estimated from appendix A on Figure 7, according to ERA
drainage design manual 2011 for LVRs. The design return periods are taken from
Appendix B in Table 7.
To determine time of concentration for over land flow there are many formula.
Among these the Kerby and Kirpich formula are presented and for defined flow
(Channel flow), U.S. SCS formula is presented.
20
Tc = 0.604[RL/S0.5] 0.467 (2.3) Kerby Formula
S – Slope in m/m
R – Roughness coefficient
Where:
S – Slope in m/m
(m=1 for bare earth, m=2 for grass and m=0.4 for asphalt).
21
2.16.2.1 Catchment Area
Catchment area regression equations shall be used for all routine designs
at sites where applicable; In general, the catchment area can be determined from
topographic maps and field surveys. However, for large catchment areas, it is
necessary to divide the area into sub-catchment areas to account for major land
use changes. Locate storm water drainage structures and assess their effects on
the flood flows. A field inspection of existing or proposed drainage systems shall
be made to determine if the natural drainage divides have been altered. These
alterations could make significant changes in the size and slope of the sub
catchment areas.
For P>0.2S
Q =0 for P≤0.2S
22
Where:
Q = accumulated direct runoff, mm.
S=25.4*((1000/CN)-10) (2.6b)
S is millimeter
S is in inches
Ia = 50.8((100/CN)-1) (2.7b)
A. Sheet flow,
23
The type that occurs is a function of the conveyance system and is determined by
field inspection. It is often a combination of these flows so that the total travel
time is the sum of the time taken for the water to pass through all of the segments
of the catchment. Travel time is the ratio of flow length to flow velocity:
T = L/ (3600V) (2.9)
Where:
T = travel time, hr
L = flow length, m
Tc=((.87L^2)/1000Sav)^.385 (2.10)
Where:
L – Hydraulic length of catchment along the flow path from the catchment
boundary to the place where the flood needs to be determined (km).
Travel time is the time it takes water to travel from one location to another in a
catchment area.
Tc=Tt1+Tt2+----+Ttm (2.11)
1. Sheet Flow
In sheet flow, travel time is determined by Manning's kinematic solution. The
Tt=[0.091(nL)^0.8/(P2)^0.5*S^0.4] (2.12)
Where:
Tt=travel time, hr
24
n= Manning's roughness coefficient
L=flow length, m
According to ERA DDM 2002, the Manning's kinematic solution is based on the
following criteria:
According to ERA DDM 2002 these two formulae are based on the solution of
Manning's equation with different assumptions for n (Manning's roughness
coefficient) and R (hydraulic radius, meter). According to the ERA DDM 2002
for unpaved areas, the value of n is 0.05 and R is 0.12; for paved areas, the value
of n is 0.025 and R is 0.06.
After determining average velocity, equation (3.9) is used to estimate travel time
for the shallow concentrated flow segment.
25
(1:50,000). Average velocity is usually determined for bank-full elevation.
Manning's equation or water profile information used to estimate average flow
velocity. When the channel section and roughness coefficient are available, then
the average velocity can be calculated by using Manning's equation. For this
thesis, topographic map of the study area was used that was produced in 1:50,000
scale.
V = (R^2/3S^1/2)/n (2.14)
R = A/P
After average velocity is calculated, Tt is calculated by using equation (2.9)
Tc=Tt1+Tt2+Tt3 (2.15)
Where,
Tt1=travel time for sheet flow
Using the calculated time of concentration, unit peak discharge is obtained from
Appendix A on Figure 5. After unit peak discharge is obtained, design peak
discharge is determined using the formula:
Where,
Q = Direct Runoff, mm
26
2.16.2.4 Runoff and Curve Numbers
The physical catchment area characteristics affecting the relationship
between rainfall and runoff (i.e. the CN values) are land use, land treatment, soil
types, and land slope. Land use is the catchment area cover and it includes
agricultural characteristics, type of vegetation, water surfaces, roads and roofs.
Land treatment applies mainly to agricultural land use, and it includes mechanical
practices such as contouring or terracing and management practices such as
rotation of crops. The SCS method uses a combination of soil conditions and
land-use to assign a runoff factor (curve number) to an area. These runoff factors
or curve numbers (CN), indicate the runoff potential of an area. The higher the
CN, the higher is the runoff potential.
F/S=Q/P-Ia (2.17)
Where,
After runoff has started, all additional rainfall becomes either runoff or actual
retention (i.e. the actual retention is the difference between rainfall minus initial
abstraction and runoff).
F=P-Ia-Q (2.18)
27
maximum retention (S = ∞), which is an infinitely abstracting watershed. As the
potential maximum retention (S) can theoretically vary between zero and infinity
(2.18) shows that the Curve Number, CN, can range from one hundred to zero.
For highly permeable, flat-lying soils, S will go to infinity and CN will be zero;
all rainfall will infiltrate and there will be no runoff. In drainage basins, the reality
will be somewhere in between. Therefore, equation (2.7b) and (2.8) will be
defined.
The curve number method was developed with daily rainfall data measured with
non-recording gauges. The relationship therefore excludes time as an explicit
variable (i.e. rainfall intensity is not included in the estimate of runoff depth)
soils.
Group B Soils having moderate infiltration rates when thoroughly wetted. These
consist chiefly of moderately deep to deep, moderately well to well drained soils
with moderately fine to moderately coarse textures. These soils have a moderate
rate of water transmission (0.15 to 0.30 in/hr). (NRCS, 2007).
Group C Soils having low infiltration rates when thoroughly wetted. These
consist chiefly of soils with a layer that impedes downward movement of water or
soils with moderately fine to fine texture. These soils have a slow rate of water
transmission (0.05 to 0.15 in/hr.). (NRCS, 2007).
Group D Soils having high runoff potential. They have very low infiltration rates
when thoroughly wetted (high runoff potential). These consist chiefly of clay
soils with a high swelling potential, soils with a permanent high water table, soils
with a clay pan or clay layer at or near the surface, and shallow soils over nearly
impervious material. These soils have a very low rate of water transmission (0 to
0.05 in/hr.). (NRCS, 2007).
The type of soil on the study area is Nitisols (FAO, 1998) that covers almost
100% of the total soil coverage. In Nitisols about 70% of the soil is silt loam of
hydrologic soil group B and the remaining 30% is clay (FAO, 1998) of
hydrologic soil group C.
28
CHAPTER THREE
3. RESEARCH METHODOLOGY
As part of the Upper Atbara & Setit Dam Complex, a township is currently
being constructed to provide residence for the dam operation team as well
as the first class, fully serviced and local events.
29
3.3 Study period
The time allocated for this study from April 2013 up to May 2017.
30
3.6 Sample size and sampling procedures
Sampling procedures are using Random sampling includes choosing subjects
from a population through unpredictable means. In its simplest form, subjects all
have an equal chance of being selected out of the population being researched
(Chambers, 2003). Once the population frame is randomized, the next step is to
decide on the sampling interval. The confidence level set in determining the
sample size is 95% confidence level of the target population while the response is
taken to be within positive or negative 5% (+ or -5%) of the population. Then the
existing condition of the drainage system and their causes and effects on the roads
are prepared as questionnaires to get information from engineer, road users and
residents. The sample size for the population was calculated using the formula
below:
n=Z^2 pqN/(e^2(N-1)+Z^2 pq)
Where:
N – Size of the population
P – Sample proportion
n – Size of the sample
q – 1-P
e – Accepted error (e = 0.05, this is because estimate should be within 5% of the
true value)
Z – The value of the standard deviation at a given confidence level.
by used equation above and used random value for (N=600,330,230,40
respectively):
Total sample population n = 65
Road users n = 36
Residents n = 25
Engineers n= 4
31
physical observation checklist, which was filled through observations and a
digital camera was used to take photographs of the current state of the road and
the drainage system, Field survey measuring the data by using tape and GPS.
Questionnaire is a research instrument consisting of a series of questions and
other prompts for the purpose of gathering information from respondents. Was
asking the contractors and people living around the study area and interviews
means Oral questions were asked to get more information and to clarify the
ambiguous response. The study area information that was gathered from the
residences and road user.
3.9Ethical considerations
This study is conducted in a manner that is consistent with ethical issues
that need to be considered in conducting a Thesis. Accordingly, letter from the
Jimma University Institute of technology department of civil engineering is
written for the concerned bodies. Hence, most individuals, the researcher visited
for interview, accepted and cooperated with the researcher thesis. Moreover, a
prior consent of the participants is requested before conducting the interview.
32
3.10 Data quality assurance
Before data collection all the source populations availability has checked
and respondents daily work schedule has respected. All the questions that are put
in simple and clear ways, willingness of the respondents to answer the questions
and collaborates with the study is test out, all necessary schedule are worked out
needed to administrate the observations group interviews and to measurements.
3.13 Equation:
The rational formula estimates the peak rate of runoff at any location in a
catchment area as a function of the catchment area, runoff coefficient and means
rainfall intensity for duration equal to the time of concentration (the time required
for water to flow from the most remote point of the basin to the location being
analyzed). The rational formula is expressed as:
Q = 0.00278CIA (3.1)
Where,
Q = Peak flow in cubic meter per second (m3/sec)
C= Dimensionless weighted runoff coefficient
I= Rainfall intensity in millimeters per hour (mm/hr.)
A= Drainage area in hectares (ha)
33
CHAPTER FOUR
A response rate of 50% is acceptable for data analysis and reporting, 60% is good
and above 70% is very good (Mugenda, 1999). There was a response rate of
69.23% for this study and therefore good enough for the analysis of the data show
table above.
The improper and no well-maintained of the drainage system are causes the
failure of road pavement and it's reduce their life span. This bad condition of the
side drain and its structures remains the same throughout the rain season causing
the runoff water to flow on the surface of the road and unable to run off through
the path far from the failed drain. The resultant effect of this critical situation
causes serious distresses and damages on pavement. The road edges suffered
from detachment of asphalt layer due to continuous contact of water leading to
stripping of asphalt from aggregates resulting in severe pavement distresses of
cracking, potholes and failure of edges of the road.
34
The impact of drainage condition on road pavement is very adverse. It
causes pavement distresses and deterioration which affect the safety and riding
quality on the pavement. The study investigated cases of pavement failures and
damages due to drainage experienced during the rainy season.
According to get the information from the engineers and DDM of ERA when
design and construction of the road drainage structure it must be consider more
on the topography of around the study area based on the location of settlements of
road that useful for road user and residents in the way which to control the causes
and effects of poor drainage on the road. And also consider the cost of
construction and state of the road. It was important to know the critical factors
considered when designing a road drainage system. This is because they helped to
understand the reasons behind the design of every road show figure 4.1.
35
Table 4.2 Problems, Causes, effects and actions of the drainage on the road
It was important to know the critical factors considered when designing a road
drainage system. This is because they helped to understand the reasons behind the
design of every road and in this case, Upper Atbara and Setit Dam Complex
Township and people who use the road show Table 4.2.
36
4.2.3 Appropriateness of the drainage system
The engineers‟ and consultant indicated that the drainage system provided
for Upper Atbara and Setit Dam Complex Township and people who use the road.
Drainage was poor and inappropriate. The magnitude of the water from the
surrounding the area in which the road is situated was overlooked during design.
They also indicated that studies that were carried out before designing the road
were not sufficient to satisfactorily ascertain the amount of water that would cross
the road at a point in time and therefore the design lacked capacity to adequately
drain the runoffs during the rains. However, poor workmanship by the contractor
during construction and poor maintenance also contributed to the drainage
problems on road. As part of understanding the background of the poor drainage
system provisions in the Upper Atbara and Setit Dam Complex Township and
people who use the road. That lack drainage.
37
4.2.4 State of the drainage services
The engineers‟ and consultant have carried out a study on the effects of poor
drainage system on the surrounding environment. They both agreed that though
there was need for redesigning and reconstruction of the drainage system, there
was also need to carry out maintenance on the existing drainage facilities to
increase their efficiency and effectiveness. They reported that redesigns and
reconstruction have been implemented in the future.
From figure 4.3 A significant proportion of the respondents either use the road
every day or twice a week. The data collected shows that 80% of the respondents
use the road often. This was important to this study as it showed that the
respondents could be relied on to give authentic information to achieve the
studies objectives.
The road users were concerned about their safety and the convenience of going
through Upper Atbara and Setit Dam Complex Township road during the rains.
The state of the drainage system compromised their safety as they travelled. Only
20% think the drainage system provided in Upper Atbara and Setit Dam Complex
Township road is good, whereas, there was none of the respondents who thought
the drainage system was very poor that causes the damage of the road eroded,
cracking, wash away by over flooding of the water and deposited waste materials
on the road.
38
Figure 4.4 Effects of drainage system on the asphalt pavement road.
From figure 4.4 Road users were in consensus when it came to the effects of the
poor drainage system on the road. Majority reported that the causes and effects of
poor drainage on the road are water leaves debris on the road surface during the
rains there by hindering free movements of vehicles on the road. It also washed
away the asphalts during the rainy season, therefore totally making it impossible
the passage of the road. A significant proportion reported that runoffs on the road
block and cracking the through the road and leave debris on the road after the
rains; this debris would then hinder movement along the road and therefore
inconvenience travelers. The travelers would then become late in their businesses
or other engagements.
The causes of flooding are complex. A combination of factors can have an
impact on causing flooding and consequences in road drainage systems.
According to the clogging of drainage pipes, culverts and ditches by debris flow
and fine-grade soil is one of the most import maintenance issues in current
drainage systems. Some of the respondents stated that cleaning of drainage pipes,
culverts and ditches is not specified at a certain time and is therefore only done
when needed. This suggests that it is important to perform operations such as
maintenance and cleaning regularly to prevent over flooding of the water on the
road.
39
Figure 4.5 Level of road user satisfaction.
4.3.2Causes and effects of drainage system on asphalt road that response from
the residents
A good percentage from within 100 meters from the road. According to
the data collected 30% come from within a hundred meters from the road and
outside the 50 meters mark. This was important because it showed that they could
respond to all the issues raised in this study so as to achieve the objectives.
On drainage across the road having inadequate drainage systems,
deterioration often begins with the origin of cracks or potholes on the road
pavements either at the edges along the drive way which differs by their shapes,
configuration, amplitude of loading, movement of traffic and rate of deformation.
Figure 4.6 below shows how the residents feel they were affected by the poor
drainage in the area. Majority of the respondents reported that runoff had had
adverse effects on their road and land. They stated that runoff eroded their land
the water that comes from the road there by making the land less productive and
affecting the good road satisfactions of the area.
40
Figure 4.7 Improvement activities.
The data shows in figure4.7 that there have been ongoing activities geared
towards the improvement of the drainage system. A greater percentage of the
respondents have not observed improvement activities on the road, however,
there is also a significant percentage that have observed these activities being
carried out. This shows that though there are efforts to improve the drainage
system, enough has not yet been done yet. There is therefore need to improve the
facilities to an acceptable standard.
41
Figure 4.8 Accumulation of soils on the road and Edge of the road erosion
Figure 4.9 the side drain was blocked with soil, debris, vegetation, wheel and
solid waste.
The existing drain is located on both side of the road. It is open and earth
ditch with 1m width and 0.5 to 1 depth. The condition of this drain is very bad. It
was full with soil accumulation and refuse dumps. The side drain was blocked
with soil, debris, vegetation, wheel and solid waste as shown in above figure.
Therefore from these problems the remedies suggests that it is important to
perform operations such as maintenance and cleaning regularly to prevent the
over flooding of water on the road.
4.5 Investigations of Design and Construction Performs on the study
area.
Road drainage system should be designed by analyzing hydrologic parameters of
the catchment area. Adequate hydrologic analysis design is significant for road
drainage system to pass peak discharge without distraction, destruction the
drainage system and property adjoining the road crossing. Moreover, after
acceptable hydrologic analysis design proper construction is very important for
the road drainage construction to function properly for the proposed purpose.
42
In general, most of the side drains provided to roads in Upper Atbara and Setit
Dam Complex Township are earth drains or ditches. Some drains built from
bricks, stones or concrete materials are open drains without covers. Others built
drains are covered with concrete slab or blocks. Failures of built drains like
collapse of bed, side walls and/or covers caused by improper design and
construction, settlement or heave may lead to the development of cracks and
subsequent failure.
This leads to a situation where preliminary studies that would help the design and
construction decisions are not done.
43
structure sustainable after In order to serve a road properly for the road users,
drainage system should be constructed by considering where the location of the
crossing in the watershed is required and how can water, sediment, and wood be
transported at that location and how is the catchment configured. The proper
construction practice is important after proper design for drainage system to
function properly for the road users as intended. Only proper design by itself does
not make the drainage structure to serve properly up to its design life but also
proper construction practice must be carried out by appropriate personnel
according to the design.
Figure 4.11 initially constructed one Rows of Pipe Culvert at Station 0+400
The main cause for the pavement erosion was the lack of detail flood information
during rainy season and poor drainage design. The construction of the culvert was
carried out without some rational and scs calculation of the expected flow. The
hydrologic analysis is required to estimate peak discharge that is a major
component of the overall design effort. In general, drainage crossings must be
designed to pass the appropriate storm flows and debris or to survive overtopping.
44
Proper design and construction of drainage structures are dynamic components
for road structure to function without traffic disturbance. Appropriate
hydrological analysis of the catchment area where the drainage system would be
constructed and appropriate drainage parameters should be determined.
45
Figure 4.12 initially constructed one Rows of Pipe Culvert at Station 0+85
Review is the appraisal of the design and the check list is a very imperative. It's
hoped that this road design review would be use full to those engaged upon the
design review for the road projects it is the necessary to emphasize the current
evaluation of the documents and provided comment at any time to improve can be
made in the future. Also the main purpose of review is to check and to ensure the
design deliverables consists of the drawing. After sizing a drainage facility using
a flood (and the hydrograph) corresponding to the design frequency, it is
necessary to review this proposed facility with a base discharge. This is done to
insure that there are no unexpected flood hazards inherent in the proposed facility.
The review (check) flood shall be at least the 50-100-year event, or as provided.
46
4.6 Results analysis
Station Area(ha)
2 0+400(road 2) 902
0+85(road38) 723
3
After the watershed areas and properties were described, the land use coverage,
soil type and curve number were computed. From the Soils Map and field survey
approximately about 70% of the catchment is covered by grass, and the remaining
30% is covered by small trees, and scarcely distributed trees. As presented in
Appendix B on Table 16, the runoff curve number for pasture, Fair condition and
covered land, without conservation treatment average hydrologic soil group B is
47
75 and hydrologic soil group C is 83.5 Therefore, average runoff curve number
is:
(0.70x75) + (0.30x83.5)
= 77.55 but the nearest CN value is 80.
Since the drainage system at station 0+30 is culvert that has diameter greater than
2-meter as shown on the 24-hour rainfall depth for years 25 and 50 are 118mm
for design and 132mm for checking (See Appendix B in Table 13).
48
Table 4.4 summary of the watershed properties calculations at station 0+30
(road 3)
1 Curve number(CN) 91wet
2 Precipitation(p) of 25 118mm
years
3 Precipitation(p) of 50 132mm
years
v. Time of concentration
A. sheet flow
The sheet flow occurs up to 100 meters. Sheet flow, natural range, slope of 0.02
m/m, and length of 150m and from Appendix B, Table 2, Manning‟s roughness
coefficient is 0.13. The 2-year, 24-hour rainfall depth is determined from
Appendix A in Figure 3 or Appendix B in Table 13 to be 65mm. Hence, from
Equation (2.12), travel time for sheet flow is determined as:
Tt = [0.091(nL) ^ 0.8/ (P2) ^0.5S^0.4]
= [0.091(0.13*150) ^0.8 / (65^0.5*0.02^0.4)
= 0.979/1.686
=0.58hr
49
c. Channel Flow
For channel flow, natural stream channel, curving with hoes and ponds, slope is
0.01m/m, and length is 1100m. By direct measuring the average bottom width of
the stream channel is 2.75m, side slopes are 1V:1.6H, 25-year storm depth is
observed from flood mark and measured to be 1.25m. From Appendix B in Table
2, Manning's roughness coefficient for fallow (no residue) channels is 0.050.
Cross-sectional flow area (A) = by+zx^2
Where b= width, z= depth, y vertical slope and x is horizontal slope
= (2.75 x 1) + 1.25(1.6) ^2
= 5.95m2
Wetted perimeter (Pw) = b+2x (1+z^2) ^0.5
= 2.75+2x1.6 (1+1.25^2)^0.5
= 7.87m
50
Table 4.5 summary of time concentration at station 0+30 (road 3).
length 150m
Manning roughness
coefficients(n) 0.13
1 sheet flow
Slope 0.02
Precipitation of 2 year(p2) 65mm
Travel time 0.58hr
length 1000m
shallow concentrated Slope 0.02
2
flow unpaved watershed 0.70m/sec
Travel time 0.39hr
length 1100
Slope 0.01
width of the stream channel(b) 2.75m
Depth of the stream channel(z) 1.25m
side slope 1V:1.6H
Manning roughness
3 channel flow
coefficients(n) 0.05
Cross section area 5.95m^2
Wetted perimeter 7.87m
Hydraulic radius® 0.756m
Velocity 1.658M^3
Travel time 0.18hr
4 Total of time concentration 1.15hr
Using the time concentration and the year to find intensity (I) from appendix A
figure 1 and Runoff Coefficient (c) based on the soil group find from appendix B
table 12
Unit peak discharge (Qu25) = 0.00278*C*I*A= 0.00278*0.13*60*8.89 = 0.193
51
4.6.2.2 Catchment Characteristic at Station0+400(road 2) Drainage
System
After the watershed areas description, watershed properties like the land use
coverage, soil type and curve number are computed. From the Soils Map of
Ethiopia and from the field survey approximately about 70% of the catchment is
cultivated, and the remaining 30% is covered by small trees, shrubs, and scarcely
distributed trees. From Appendix B on Table 16, the runoff curve number for
pasture, Fair condition and cultivated land, without conservation treatment
average hydrologic soil group B is 75 and hydrologic soil group C is 83.5.
Therefore, average runoff curve number is:
(0.70x75) + (0.30x83.5)
= 77.55 but the nearest CN value is 80.
i. Runoff Curve Number
As per Appendix B in Table 11, hydrological characteristics of soil groups, the
region is a wet antecedent moisture condition (AMC) region. From Appendix B
in Table 1,
CN80avg = CN91wet.
ii. 24-hour rainfall depth
Since the drainage system at station 24+200 is culvert that has diameter greater
than 2-meter as shown on 24-hour rainfall depth for years 10 and 25 are 98mm
for design and 118mm for checking (See Appendix B in Table 13).
iii. Direct runoff depth
Direct runoff (Q) is determined from Appendix A on Figure 2, by using rainfall
depth of 98mm for design, 132mm for checking and CN of 91. Therefore,
S = 25.4((1000/91)-10) = 25.12mm
Ia = 0.2s =0.2*25.12 = 5.02mm
52
Table 4.6 Summaries of the watershed properties calculated at station
0+400(road 2)
V. Time of concentration
A. sheet flow
The sheet flow occurs up to 50meters. Sheet flow, natural range, slope of 0.02
m/m, and length of 100m and from Appendix B, Table 2, Manning's roughness
coefficient is 0.13. The 2-year, 24-hour rainfall depth is determined from
Appendix A in Figure 3 or Appendix B in Table 13 to be 65mm. Hence, from
Equation (3.12), travel time for sheet flow is determined as:
Tt = [0.091(nL)0.8/ (P2)0.5S0.4]
= [0.091(0.13*100)0.8 / (650.5*0.020.4)
= 0.708/1.686
0.42hr.
B. Shallow Concentrated Flow
For shallow concentrated flow, unpaved watershed slope is approximated
0.02m/m and length from topography map is 900m. From equation (3.12), V=
4.9178(S) 0.5 for unpaved watershed. V=4.9178(0.02)0.5 =0.70m/sec. From
equation (3.9), travel-time is determined as:
Tt = L/ (3600V)
= 900/ (3600X0.70)
= 0.36hr.
C. Channel Flow
For channel flow, natural stream channel, curving with hoes and ponds, slope is
0.01m/m, and length is 1000m. By direct measuring the average bottom width of
53
the stream channel is 2.5m, side slopes are 1V:1.5H, 25-year storm depth is
observed from flood mark and measured to be 1.5m. From Appendix B in Table
2, Manning's roughness coefficient for fallow (no residue) channels is 0.050.
Cross-sectional flow area (A) = by+zx^2
Where b= width, z= depth, y vertical slope and x is horizontal slope
= (2.5 x 1) + 1.5(1.52)
= 5.875m2
Wetted perimeter (Pw) = b+2x (1+z2)^0.5
= 2.5+2x1.5 (1+1.52)^0.5
= 7.91m
Hydraulic radius (R) = A/P
= 5.875/7.91
= 0.743m
From Equation (3.14), V = (R2/3S1/2)/n
V = (0.743)2/3*(0.01)1/2/0.05 = 1.64m/sec.
From equation (3.9), Tt = L/ (3600V)
= 1000/ (3600*1.64) = 0.17hr.
From equation (3.15)
Total Time of Concentration (Tc) is (0.42 + 0.36+ 0.17) = 0.95 hr.
Table 4.7Summary of time concentration at station 0+400(road 2)
1
2
3
4
54
Using the time concentration and the year to find intensity from appendix A
figure1 and Runoff Coefficient(c) based on the soil group to find the from
appendix B table 12
Unit peak discharge (Qu10) = 0.00278*C*I*A= 0.00278*0.13*58*9.02 = 0.189
(Qu25) = 0.00278*C*I*A= 0.00278*0.13*70*9.02 = 0.228
Peak discharge (Qp10) = Qu*Q*A → Qp10 = 0.189*73*9.02 = 124.500
(Qp25) = Qu*Q*A → Qp25 = 0.261 *92*9.02 = 189.359
By the same procedures, catchment parameters of the rest stations are
determined.
After the watershed areas description, watershed properties like the land use
coverage, soil type and curve number are computed. From the Soils Map of
Ethiopia and from the field survey approximately about 70% of the catchment is
cultivated, and the remaining 30% is covered by small trees, shrubs, and scarcely
distributed trees. From Appendix B on Table 16, the runoff curve number for
pasture, Fair condition and cultivated land, without conservation treatment
average hydrologic soil group B is 75 and hydrologic soil group C is 83.5.
Therefore, average runoff curve number is:
(0.70x75) + (0.30x83.5)
= 77.55 but the nearest CN value is 80.
i. Runoff Curve Number
As per Appendix B in Table 11, hydrological characteristics of soil groups, the
region is a wet antecedent moisture condition (AMC) region. From Appendix B
in Table 1,
CN80avg = CN91wet.
ii. 24-hour rainfall depth
Since the drainage system at station 0+85(road38) is culvert that has diameter
greater than 2-meter as shown on 24-hour rainfall depth for years 10 and 25 are
98mm for design and 118mm for checking (See Appendix B in Table 13).
iii. Direct runoff depth
Direct runoff (Q) is determined from Appendix A on Figure 2, by using rainfall
depth of 98mm for design, 132mm for checking and CN of 91. Therefore,
S = 25.4((1000/91)-10) = 25.12mm
Ia = 0.2s =0.2*25.12 = 5.02mm
55
iv. Slope of the watershed
56
Hydraulic radius (R) = A/P
= 5.95/7.87
= 0.756m
From Equation (2.14), V = (R2/3S1/2)/n
V = (0.756)2/3*(0.01)1/2/0.05 = (0.829*0.1)/0.05
= 1.658m/sec.
From equation (2.9), Tt = L/ (3600V)
= 1100/ (3600*1.658)
= 0.18hr
From equation (2.15)
Total Time of Concentration (Tc) is (0.25 + 0.39+ 0.18) = 0.82 hr.
Using the time concentration and the year to find intensity from appendix A
figure1 and Runoff Coefficient(c) based on the soil group to find the from
appendix B table 12
Unit peak discharge (Qu10) = 0.00278*C*I*A= 0.00278*0.13*58*9.02 = 0.209
(Qu25) = 0.00278*C*I*A= 0.00278*0.13*70*9.02 = 0.235
Peak discharge (Qp10) = Qu*Q*A → Qp10 = 0.189*73*9.02 = 135.996
(Qp25) = Qu*Q*A → Qp25 = 0.261 *92*9.02 = 178.359
4.8 Existing culvert design:
general characteristic for culverts design show in the tables below:
Table 4.8: Catchment Parameters for Design and Check (Station 0+30(road3)
57
Table 4.9: Catchment Characteristics for Design and Check (Station
0+400(road2)
Parameters of Design data Review data
Design and Review
Return Periods 10 25
(years)
Time of 0.95 0.95
Concentration (hours
Curve Number (CN) 91 91
Potential Maximum 25.12 25.12
Retention (mm)
Initial Abstraction Ia 5.02 5.02
(mm)
Design Storm (24-hr 98 118
maximum rainfall)
Ia/P 0.051 0.043
Direct Runoff (mm) 73 92
Unit Peak Discharge 0.189 0.228
(m3/s/km2/mm)
Peak Discharge 124.500 189.359
(m3/sec)
Table 4.10: Catchment Characteristics for Design and Check at Station
0+85(road38)
58
Direct Runoff (mm) 90 105
Unit Peak Discharge 0.209 0.235
(m3/s/km2/mm
Peak Discharge 135.996 178.400
(m3/sec)
On the above tables the design peak discharge calculated and the review
peak discharge calculated of the return period is not equal. From this the road
around this is damaged by over flooding of the water on the road because the
calculated peak discharge for the design was less than the calculated peak
discharge for the review at station, 0+30(road3), 0+85(road38) and
0+400(road2)the difference between them are: 48.03 , 64.859 and 42.404 values.
Therefore before the culverts are constructing the design and the review data must
be checked. Because based on these values the more volume of runoff is very
high on the culvert stations. Initially, one rows of pipe culvert was constructed.
The one rows of pipe culvert could not accommodate the peak discharge during
the rainy season after constructed because the active channel width is greater than
the span of the culvert. In order to mitigate the overtopping problem two row pipe
that has one-meter internal diameter on the left side and the right side was
important additionally to mitigate the overtopping problem of the peak flood
during the rainy season. Always when its design the road it must be follow the
drainage design manual. A flood event larger than the specified review flood
might be used for analysis to ensure the safety of the drainage structure and
downstream development.
The analysis of the peak rate of runoff, volume of runoff, and time distribution of
flow is fundamental to the design of drainage structures. Errors in the estimates
would result in a structure that is either undersized and causes more drainage
problems or oversized road at station 0+30(road3), 0+85(road38) and
0+400(road2), the surface of the road on the downstream side was eroded by
overtopping flood. Therefore when construct the road drainage it consider
hydraulic analysis. Also maintenance and cleaning of the block drainage system
are important.
59
4.10 comparison between new culverts and old culverts:
They are many different between culverts as show in the table below:
from design:
Q = 0.189 m^3/sec
S = 0.02
n =0.03
Q =( (1/n)*A*(R)^2/3*(S)^1/2)
R = A/P
A = π r^2
P = 2π r
r = 0.23 m
V =((1/n)*(R^2/3)*(S^1/2))
P = 2π*.23 =1.45 m
R = 0.166/1.45 = 0.11 m
V = ((1/0.03)*(0.11^2/3)*(0.02^1/2))
60
V = 1.2 m/sec
Q = 0.193 m^3/sec
S = 0.02
n =0.03
Q =( (1/n)*A*(R)^2/3*(S)^1/2)
R = A/P
A = π r^2
P = 2π r
r = 0.23 m
V =((1/n)*(R^2/3)*(S^1/2))
P = 2π*.23 =1.45 m
R = 0.166/1.45 = 0.11 m
V = ((1/0.03)*(0.11^2/3)*(0.02^1/2))
V = 1.2 m/sec
61
4.11.2.2 review data :
Q = 0.218 m^3/sec
S = 0.02
n =0.03
Q =( (1/n)*A*(R)^2/3*(S)^1/2)
R = A/P
A = π r^2
P = 2π r
r = 0.24 m
V =((1/n)*(R^2/3)*(S^1/2))
P = 2π*.24 =1.51 m
R = 0.181/1.51 = 0.12 m
V = ((1/0.03)*(0.12^2/3)*(0.02^1/2))
V = 1.3 m/sec
Qd < Qr
62
4.11.3 Station 0+85
4.11.3.1 design data :
Q = 0.209 m^3/sec
S = 0.02
n =0.03
Q =( (1/n)*A*(R)^2/3*(S)^1/2)
R = A/P
A = π r^2
P = 2π r
r = 0.239 m
V =((1/n)*(R^2/3)*(S^1/2))
P = 2π*.239 =1. 5 m
R = 0.179/1. 5 = 0.12 m
V = ((1/0.03)*(0.12^2/3)*(0.02^1/2))
V = 1.3 m/sec
63
4.11.3.2 review data :
Q = 0.235 m^3/sec
S = 0.02
n =0.03
Q =( (1/n)*A*(R)^2/3*(S)^1/2)
R = A/P
A = π r^2
P = 2π r
r = 0.27 m
V =((1/n)*(R^2/3)*(S^1/2))
P = 2π*.24 =1.70 m
R = 0.229/1.70 = 0.135 m
V = ((1/0.03)*(0.135^2/3)*(0.02^1/2))
V = 1.4 m/sec
Qd < Qr
64
CHAPTER FIVE
5.1 Conclusions
1. The design peak discharge calculated and the review peak discharge calculated
of the return period is not equal. From this the road around this is damaged by
over flooding of the water on the road because the calculated peak discharge for
the design were less than the calculated peak discharge for the review at station,
0+30(road3), 0+85(road38) and 0+400(road2)the difference between them are:
48.03 , 64.859 and 42.404 values. Therefore before the culverts are constructing
the design and the review data must be checked always when its design the road,
it must be the design peak discharge is greater than the review peak discharge to
control the floods that over follow on the road.
2. The most common causes of road drainage problem were found related to
improper road geometry, insufficient capacity of drainage structures, poor
construction, and lack of proper maintenance. There was a general feeling that the
type of drainage system is not adequate .Also the drain suffered from low
capacity, soil accumulation, absence of inlets, lack of proper maintenance and
disposal of solid waste into the drain and the crossing culverts. For these
problems remedies suggests that it is important to perform operations such as
when its design and construct the road drainage it must be follow the drainage
design manual. Maintenance and cleaning regularly the drainage structures and
waste solids remove to prevent these problems.
65
5.2 Recommendations
66
REFERENCES
67
REFERENCES
68
States for durations from research recording 1519,TRB National Research
Council ,Washington, D.C.1996,pp110.
[16] Highway Drainage Guidelines, American Association of State Highway and
Transportation Officials, 2003.
[17] Hydrologic Engineering Centre (HEC), (2000), “HEC-RAS User‟s Manual”,
Internet, http://www.wrc.hec.usace.army.mil/software-distib/hec-
ras/hecrasprogram.html.
[18] IRC: SP 42-1994, “Guidelines on Road Drainage”, Special Publication,
Indian Roads Congress, New Delhi 1994.
[19] Larson, C. L. and Straub, L. G. Grate inlets for surface drainage of streets
and highways, univ. of Minnesota, st. Anthony falls hydr. Lab, bull. no.2, (June
1949).
[20] L.M. Nyuyo, Maintenance of drainage systems in nairobi‟s Bahati estate,
B.A Land Ecomics, University of Nairobi, 1993.
[21] Mina, H.L., Sethi, N.K. (2007) “Road Maintenance of Drainage, Shoulders
and Slopes “Journal of Indian Highways, 37(6), 35-38.L.
[22] Mutual C.K (2005), A Study On Participatory Maintenance and Its Impacts
on Performance of Ground Storm Water Drainage Systems in Residential Areas
[23] Mwangi, (2013), A Study on the Maintenance of Drainage Systems on
Public Roads and Pavements, a Case Study of Nairobi‟s Industrial Area,
Bachelor of Quantity Surveying, University of Nairobi.
[24] NAASRA (National Association of Australian State Road Authorities),
(1986), Guide to the Design of Road Surface Drainage, Sydney.
[25] NCHRP Synthesis 237, (1997).pavement subsurface drainage systems, TRB
National Research Council, Washington, D.C.
[26] O'Flaherty, C.A. (2002). Chapter 7 - Surface drainage for roads. Highways
(Fourth Edition), C. A. O‟Flaherty, ed., Butterworth- Heinemann, Oxford, 185-
209.
69
Engineering Circular No. 22, Second Edition “Urban Drainage Design Manual,”
FHWA- NHI-01-021.
[31] U.S. Natural Resources Conservation Service (2004), National Engineering
Handbook “Estimation of Direct Runoff from Storm Rainfall”.
[32] Wyatt et al, (2000); effectiveness of subsurface drainage features based on
design adequacy, of transportation research recording 1709,TRB National
Research Council ,Washington, D.C.2000,pp69-76.
[33] Zumrawi, M.(2013),“Pavement design for roads on expansive clay
subgrades,”University of
Khartoum Engineering Journal (UOFKEJ), Vol.3 Issue 1, pp.52-58.
70
Appendix: A, B and C
71
Appendix: A
72
Appendix A: Time of Flow, Unit Peak Discharge, Velocity of flow and SCS CN
Charts.
73
Figure 2: the relation between direct run off, curve number and
precipitation (ERA 2002 and 2011)
74
Figure 3 - 24 Hour Depth – Frequency curves
75
Figure 5: Unit Peak Discharge, Type II rainfall
76
Figure 6: Overland Time of Flow (ERA 2002 and 2011)
77
Figure 7: Velocities for Upland Method of Estimating Time of Concentration
78
APPENDEX B
79
APPENDEX B: Roughness and Runoff Coefficient Values and Parameters for
the Design of Drainage Structures.
Dry Wet
95 87 98
90 78 96
85 70 94
80 63 91
75 57 88
70 51 85
65 45 82
60 40 78
55 35 74
50 31 70
45 26 65
40 22 60
35 18 55
30 15 50
25 12 43
15 6 30
5 2 13
80
Table 2: Roughness Coefficients (Manning’s n) For Sheet Flow
Table 4: Ia Value for runoff curve numbers (ERA DDM 2002)
Table 4: Ia Value for runoff curve numbers (ERA DDM 2002) Table 4: Ia Value for runoff curve
numbers (ERA DDM 2002)
81
Table 3: values of roughness coefficient n (uniform flow) (ERA DDM 2002)
82
Table 4: Ia Value for runoff curve numbers (ERA DDM 2002)
83
Table 6: values of roughness coefficient n (uniform flow) (ERA DDM 2002)
84
85
Table 7: Storm Design Return Period –years (ERA DDM, 2011)
Table 8: Runoff Coefficient: Humid Catchment (ERA Drainage Design Manual, 2011)
86
Table 10: Hydrological Characteristics of Soil Groups (ERA DDM, 2011)
Table 11: Antecedent Moisture Conditions (ERA DDM, 2011 for LVRs)
87
Table 13: 24 hour depth (mm) versus frequency (yrs).
88
Table 16: Runoff curve numbers (ERA DDM 2002)
89
Appendix: C
90
Appendix C: Questionnaire Type One
Causes and Effects of Poor Drainage System on the Flexible Pavement Layers: a
Case Study in Upper Atbara & Setit Dam Complex, a township Road.
This questionnaire is being administered for the collection of data to investigate
in the study of the Causes and Effects of Poor Drainage System on the Upper
Atbara & Setit Dam Complex, a township Road. The information collected is
confidential and will strictly be used for related data with the study.
Sector: Practical Perspective.
Practical Aspect
1 What is your academic background or field of training?
A Engineer
B Any other (specify)
………………………………………………………………………………
2 What are some of the considerations that are made when coming up with road
design and appropriate drainage facility in Upper Atbara & Setit Dam Complex, a
township road?
A. State of road
B. Cost of construction
C. Class of the road
D. Period of construction
E .Topography
4 Do you think the contractor observed due diligence in the construction of the
road drainage systems?
A Yes
B No
If your answer above is yes, why do you think so?
…………………………………………
5 If your answer is no, in your opinion what percentage of roads in Ethiopia are
not provided with adequate drainage system?
A 0 – 20%
B 20 – 40%
C 40 – 60%
D 60 – 80%
91
E 80 – 100%
6 From your engineering experience and practice, how can you rate the state of
the drainage system in Upper Atbara & Setit Dam Complex, a township road?
A Excellent
B Very good
C Good
D Poor
E Any other (specify) …………………………………………………………….
7 How often do you carry out inspection to ascertain the state of the drainage
system in Upper Atbara & Setit Dam Complex, a township road?
A Monthly
B Every three months
C Every six months
D Once a year
E Any other (specify) ………………………………………………………….
8 Have you carried out a research on the effects of the poor drainage system on
the surrounding environment?
A Yes
B No
9 What did you find the causes and effects of poor drainage system on flexible
road and their solution?
A …………………………
B …………………………
C …………………………
D …………………………
10 What do you think is the remedy to the solution state of the drainage system in
Upper Atbara & Setit Dam Complex, a township road?
Maintenance
B Redesigning
C Reconstruction
D Any other (specify)
……………………………………………………………………
11 Why do you think has hindered the above mentioned measures from being
implemented?
A Lack of resources
B Lack of awareness
92
C Poor planning
D Lack of commitment by the government
Causes and Effects of Poor Drainage System on the Flexible Pavement Layers: a
Case Study in Upper Atbara & Setit Dam Complex, a township Road. This
questionnaire is being administered for the collection of data to investigate in the
study of the Causes and Effects of Poor Drainage System on the Upper Atbara &
Setit Dam Complex, a township Road. The information collected is confidential
and will strictly be used for related data.
Sector: General Perspective.
1) How often do you use Upper Atbara & Setit Dam Complex, a township road?
A Every day
B Twice a week
C One's a week
93
A Runoff on the road block the road
B Runoff washes away the asphalt
C Cracking of road surface
D Water leaves debris on the road surface
E Any other (specify) -----------------------------------------------------------------------
-----------------
4) What are the main challenges faced by solving over flooding hazards in Upper
Atbara & Setit Dam Complex, a township road?
A …………………
B …………………
C …………………
D ………………
5) How does poor drainage of the road affect you as the resident?
A Runoff erodes the land
B Runoff create valleys on your land
d) No responsibility
94
10) In your opinion, which of the following problem is the most serious that
needs immediate Solution?
A). Lack of good drainage systems
B). high traffic accidents due to drainage
C). high soil erosions
D). Other (If any) ----------------------------------------------------------------------------
11) How do you perform the assessment taken to solve the drainage problems?
95