0% found this document useful (0 votes)
17 views1 page

To: Polyethylene Plant Manager. Subject: Re-Locate Pressure Switch For Air Dryer Package 2844-D-30

The document discusses a request to relocate a pressure switch for an air dryer package to eliminate moisture in the instrument air stream. The plant engineering department approved relocating the pressure switch as long as safety relief valves are not affected. They will also work with operations to investigate excess moisture in the air stream to meet quality requirements.

Uploaded by

ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views1 page

To: Polyethylene Plant Manager. Subject: Re-Locate Pressure Switch For Air Dryer Package 2844-D-30

The document discusses a request to relocate a pressure switch for an air dryer package to eliminate moisture in the instrument air stream. The plant engineering department approved relocating the pressure switch as long as safety relief valves are not affected. They will also work with operations to investigate excess moisture in the air stream to meet quality requirements.

Uploaded by

ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

‫ ل‬. ‫ م‬.

‫شركة راس النوف لتصنيع النفط والغاز ش‬


RasLanuf Oil & Gas Processing Co . Inc

2323 ‫ بريد مصورطراـبلـــــس‬Fax ‫ الموقع اإللكتروني‬Web Site ‫البريد اإللكتروني‬


1971‫بــنغـازي‬3605174 021 ‫ـ‬ [email protected]
‫ ل‬. ‫ م‬. ‫ شركة راس النوف لتصنيع النفط والغاز ش‬.

Date: 07-07-2020 Ref No. IH.KS.ELZ.TS-27656

To: Polyethylene Plant Manager.

Subject: Re-Locate Pressure Switch for Air Dryer Package 2844-D-30

Refer to your request TSR No. PED/20/I/03 seeking approval for Instrument Air
dryer modification to eliminate or absorbing moisture present in the outlet
instrument air stream.
Therefore, the plant-engineering department has deeply studied your
proposal to solve the problem of dryer system failure, and conclude that, there is no
objection to re-locate the pressure switch to absorber A & B as long as the function
of safety relief valves PSV-2102 & PSV-2106 is not affected.

However, we still need to work closely with your operation staff to investigate
the excess of moisture present in the outlet of Air stream dryer to meet Instrument
.Air Quality requirements specified in RASCO design criteria GNS SP-2000-GG

This is hereby made for your information and kind consideration for further action.

Prepared by
Ahmed Elhoni
Chief Eng. Automation & Digital Solutions

Idris Hammad
Manager, Technical Service Dept.

Copy to: - Department File Tele phone: 25240