SPM Unit 1
SPM Unit 1
4.Which of the following is/are main parameters that you should use when
computing the costs of a software development project?
travel and training costs
hardware and software costs
effort costs (the costs of paying software engineers and managers)
all of the mentioned
10. Which is the difference between the present value of cash inflows and
the present value of cash outflows over a period of time
ROI
Payback period
NPV
None of the above
13.What is ROI for average annual benefit 10000 and total investment 100000?
10%
1%
0%
100%
15. What assess the risk and your plans for risk mitigation and revise these when
you learn more about the risk?
Risk monitoring
Risk planning
Risk analysis
Risk identification
18. Identify and allocate resources ,2 Revise plan and estimates to take account of
resource constraints under which step of STEPWISE PROJECT PLANNING
Analyze project characteristics
Estimate effort for each activity
Identify activity risks
Allocate resources
20. Which one of the following models is not suitable for accommodating any
change?
Build & Fix Model
Prototyping Model
RAD Model
Waterfall Model
26.Agile methods seem to work best when team members have a relatively high
skill level.
a) True
b) False
27.Expansion of XP
a) Extreme Programming
b)External Project
c)External Programming
d)None
28. The COCOMO model takes into account different approaches to software
development, reuse, etc.
a) True
b) False
29.Which model is used during early stages of the system design after the
requirements have been established?
a) An application-composition model
b) A post-architecture model
c) A reuse model
d) An early design model
34. Which four framework activities are found in the Extreme Programming(XP) ?
a) analysis, design, coding, testing
b) planning, analysis, design, coding
c) planning, design, coding, testing
d) planning, analysis, coding, testing
35.Which model is used to compute the effort required to integrate reusable
components or program code that is automatically generated by design or program
translation tools?
a) An application-composition model
b) A post-architecture model
c) A reuse model
d) An early design model
36.Calculate staff –month required for organic mode of COCOMO when KLOC is
200
a)626
b)1133
c) 2077
d)None
38.DSDM
a) Dynamic Software Design Method
b) Dynamic Software Development Method
c)Dynamic System Design Method
d) Dynamic System Development Method
Part – B(6*2=12)
1. Write short notes on Management Principles.
2. List various categorization of software Projects
3. Why Net Present Value is required?
4. Brief about two ways of setting objectives.
5. What is Software Project Planning?
6. What are the three modes of COCOMO-I?
7. Write short notes on SCRUM.
8. Mention the drawbacks of Waterfall Model.
9. Write the advantages of V-Model.
10.Write any three differences between agile model and Non-Agile models.
SPM Final Question Paper
1. In which approach brainstorming involves
The activity based approach
The product based approach
The hybrid approach
Work breakdown structure approach
5.An easy to use approach that is well adapted to evaluating the risk in certain
situation is known as
Integerate Simulation
Monte Corlo Simulation
Modulated Simulation
Vague Simulation
6. Expansion of PERT
Project Evaluation Review Techniques
Program Estimation Review Techniques
Program Evaluation Resource Techniques
Program Evaluation Review Techniques
7. Which of the following is not a Software Configuration Management Activity?
Configuration item identification
Risk management
Release management
Branch management
10.According to the time estimates made by the PERT planners, the maximum
time that would be needed to complete an activity is called as __________
The most likely time estimate
Optimistic time estimate
Pessimistic time estimate
Expected time estimate
16. The ______has overall the responsibility for setting, monitoring and modifying
objectives of the project.
Project steering committee
Team manager
Team member
Project manager
17. A _____ is likely to have very high priority for close monitoring.
Critical path activity
Activity
Activity with free float
Activity with float
18. In a project team, the ________is a good team player who is willing to
undertake less attractive tasks if they were needed for team success.
Company Worker
Monitor-evaluator
Team worker
Complete finisher
22 From the above Table in Q no (21) calculate in the backward pass and identify
the value for earliest start and latest start for activity G.
15,15
11, 14
13, 15
12, 14
23. From the above Table in Q no (21) find the total float for the activity C
1
2
3
0
24.A project depended on a data centric vulnerable with flood. It might be
estimated that if a floor occurred a new computer configuration could be
established for Rs. 2,00,000 . It might also be estimated that ehere the computer is
located there is 1 in 100 chance of flood actually happening. Find the resk
explosure?
200
2000
20000
200000
25. Calculate expected time if a=2 ,b=2 and m=2
3
2
3.5
2.5
26. Calculate SPI for EV(₹ 17,50,000) and PV (₹ 17,10,000)
1.0233918
0.0233918
2.0233918
3.0233918
27. Find the risk reduction leverage if the risk evaluation before is 1% of the total
cost Rs, 2,00,000 and risk evaluation after is 0.5% of the total cost if fire accident
happens. And the total cost to fit the fire alarm is Rs. 1000.
1
2
4
8
28. The PERT activity time estimates is given below
time
A ---- 9 7 8
B ---- 8 4 3
C A 7 3 2
D B 6 4 5
E B 5 3 4
F --- 10 8 15
G E,F 5 3 4
H C,D 4 2 3
8.Expansion of PERT
10.Expansion of RRL
13.Expansion EVA
A) Earned Verify Analysis B) Estimated Value Analysis C) Earned Value Analysis D) Efficient Value
Analysis
14. The following costs are not part of the total effort cost______
A. Costs of lunch time food
B. Costs of providing heating
C. Costs of networking
D. Costs of support
15. _________ standards should be in place to ensure that changes to requirements are
implemented in a safe and orderly way.
A. Change control and configuration management
B. Time control and configuration management
C. Access control and configuration management
D. Quality control and configuration management
16. The relationship between program design and program specification can be portrayed in
_________.
A. Data Flow Diagram
B. Product Flow Diagram
C. Network Diagram
D. Data Flow Diagram
17. _________ is the amount of work that needs to be done for every activity.
A. Strength.
B. Energy.
C. Capacity.
D. Effort.
18. _______ is an activity bar chart indicating scheduled activity dates and durations frequently
augmented with activity floats.
A. Bar chart.
B. Ball chart.
C. Slip Chart.
D. Gantt chart.
19. _______ is the method of recording and displaying the way in which targets have changed
throughout the duration of the project.
A. Gantt chart.
B. Bar chart.
C. Timeline.
D. Schedule.
20. The total value credited to a project at any point is known as _______ value.
A. earned.
B. ROI Value
C. money.
D. recurred.
Part b(15*2=30)
1.________ = risk likelihood X risk impact.
A. Risk estimate.
B. Risk expenditure.
C. Risk identification
D. Risk exposure
2.Calculate SPI for EV(₹ 17,50,000) and PV (₹ 17,10,000)
a) 1.0233918 b) 0.0233918 c) 2.0233918 d) 3.0233918
4. List three approaches to identifying the activities or tasks that make up a project
a)Activity-based approach,The product-based approach and Hybrid approach
b) Actual-based approach,The product-based approach and Hybrid approach
c) a)Activity-based approach,The project-based approach and Hybrid approach
d) a)Activity-based approach,The product-based approach and Hierarchical approach
5. __Essentially an activity bar chart indicating the scheduled activity dates and duration with
activity floats,___ Provides a more striking visual induction of the activities and ________A
method of recording and displaying the way in which targets have changed throughout the
duration of the project
7. Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish times for the three
activities are 12, 15, and 10, then the earliest start time for Y will be
A) 10
B) 15
C) 12
D) Cannot be determined
8. Which is a software configuration management concept that helps us to
control change without seriously impeding justifiable change?
a) Baselines
b) Source code
c) Data model
d) None of the mentioned
10.According to the time estimates made by the PERT planners, the maximum
time that would be needed to complete an activity is called as __________
a) The most likely time estimate
b) Optimistic time estimate
c) Pessimistic time estimate
d) Expected time estimate
11. a)The difference between the maximum time available and the actual time
needed to perform an activity is known as _________and , b)In a network, a critical
path is the time-wise shortest path.
a) Free float,false
b) Independent float,false
c) Total float,false
d) Half float,false
3. In product-driven projects, the objectives of the project are defined in terms of ___________.
Functional Requirements Only.
Resource And Non-Functional Requirements.
Functional And Quality Requirements.
Resource Requirements Only.
4. __________ is record of how much the organization is willing to spend on the system.
Resource Requirements
Functional Requirements
Security Requirements
Non Functional Requirements
5. Projects are __________ by definition and therefore more uncertain than normal undertakings.
Routine
Non-Routine
Specific
Controllable
7. _________ is the amount of work that needs to be done for every activity.
Strength.
Energy.
Capacity.
Effort.
9. An Elaboration of Waterfall which stresses the necessity for validation activities is known as
__________.
Extended Waterfall.
Iterative Model.
V-Process Model.
Spiral Model.
10. _______ is a working model of one or more aspects of the projected system.
Evolutionary model.
V-process model.
Spiral model.
Software Prototyping.
17. Which of the following activity is not the part of project planning?
Project Estimation
Project Scheduling
Project Monitoring
Risk Management
22.Expansion of CPM
Cost Path Method
Critical Path Method
Critical Project Method
None Of The Above
23.Expansion of PERT
Project Evaluation Review Techniques
Program Estimation Review Techniques
Program Evaluation Resource Techniques
Program Evaluation Review Techniques
24.The ------------ is carried out to calculate the earliest dates on which each activity may be
started and completed. Where an actual start date is known, the calculations may be carried out
using actual dates.
Forward Pass
Backword Pass
CPM
PERT
25.Expansion of RRL
Risk Reduction Leverage
Return Reduction Leverage
Risk Rejection Leverage
Risk Reduction Level
26. Software Configuration Management can be administered in several ways. These include
A single software configuration management team for the whole organization
A separate configuration management team for each project
Software Configuration Management distributed among the project members
All of the mentioned
28.Expansion EVA
Earned Verify Analysis
Estimated Value Analysis
Earned Value Analysis
Efficient Value Analysis
29. The following costs are not part of the total effort cost______
Costs of lunch time food
Costs of providing heating
Costs of networking
Costs of support
30. _________ standards should be in place to ensure that changes to requirements are
implemented in a safe and orderly way.
Change control and configuration management
Time control and configuration management
Access control and configuration management
Quality control and configuration management
31. The relationship between program design and program specification can be portrayed in
_________.
Data Flow Diagram
Product Flow Diagram
Network Diagram
Data Flow Diagram
32. _________ is the amount of work that needs to be done for every activity.
Strength.
Energy.
Capacity.
Effort.
34. The poor quality of selection will mean extra cost on _______ and supervision.
Training
Recruitment
Work quality
None of the above
35. Which of these is the most important external factor governing recruitments?
Sons of soil
Labor market
Unemployment rate
Supply and demand
36. Which of the following act deals with recruitment and selection?
Child labor act
The apprentices act
Mines act
All of the above
III, II, I, V, IV
III, V, I, IV, II
IV, V, III, I, II
II, I, IV, V, III
38. ___________ express the relationship of applicant inputs to outputs at various decision
points.
Number of contacts
Yield Ratios
Type of contacts
Technological sophistication
39. Which of the following are the decisions to be made while devising the strategies to hire?
Geographic distribution of labour markets comprising job seekers
Make or buy employees
Sequencing the activities in the recruitment process
All of the above
40. What is the natural perception of people on the process of recruitment and selection?
Positive
Negative
Both positive and negative
None of the above
PART B (30X2=60)
1.The activities involved in the management which is suggested by the Open University
Software Project Management module are__________.
.Planning.
Representing.
Monitoring.
A, B, And C.
2. The problems experienced in the survey of managers published by Thayer, Pyster and Wood
include_________.
Poor Estimates And Plans.
Poor Role Definition.
Poor Quality Control.
Both A And B.
3. ________ is needed to ensure that the project remains under control and that it continues to
meet its business justification.
Yellow tape.
White tape.
Red tape.
Black tape.
4. Which form of software development model is most suited to a system where all the
requirements are known at the start of a project and remain stable throughout the project?
Waterfall model.
Incremental model.
Evolutionary model.
Spiral model.
6.Which type of risk factor is most likely to cause problems for a software project developing
commercial software?
Inadequate user documentation.
Litigation expense.
Low productivity.
Cancellation of project.
7. _______ is a collection of projects that all contribute to the same overall organizational goals.
Software.
Task
Programme.
Activity
9.Effort = __________.
System Size X Productivity Rate.
System Size X KLOC.
Person In Months / SLOC.
Person In Months X Productivity Rate.
10. The statement "If a system does not have to reliable, it can meet any other objective" is from
__________.
Brooks Law.
Peters Law.
Parkinson's first Law.
Weinberg's Zeroth Law.
13. The calculation of __________ is a project evaluation technique that takes into account the
profitability of a project and the timing of cash flows that are produced.
NPV.
TPV.
SPV.
LPV.
14. The costs that include the salaries and other employment costs of the staff involved in the
project development and all associated costs are called____________.
Operational Cost.
Development Cost.
Setup Cost.
Direct Cost.
15. One of your team members has asked for some time on the meeting agenda to seek the help
and cooperation of other team members on his/her assignment. During the ensuring team
discussion, you feel that:
Every team member is hiding their real motives and feelings
The majority of the team members are hiding their needs, expectations, and goals
Some team members are posturing to advance their hidden agendas
All team members are open about their real motives and feelings; we communicate
honestly
16. The team leader has just made an impassioned plea to improve the level of cooperation that
exists within the group. As the discussion develops you note:
All team members really seem concerned with helping each other, and working as a team
The majority of the team members are in favor of improving teamwork
The team members are split-half are in favor of improving teamwork; half would rather operate
independently
The majority of the team members want to continue to operate independently
17.Which of the following statements best describes the level of risk taking, innovation,
imagination, and initiative by members of the group:
Beware, we shoot the messenger
Nothing ventured, nothing gained-go for it
Don’t rock the boat, if it’s not broke don’t fix it
Some team members seem more comfortable with risk-taking and change than others
22. List three approaches to identifying the activities or tasks that make up a project
Activity-based approach,The product-based approach and Hybrid approach
Actual-based approach,The product-based approach and Hybrid approach
Activity-based approach,The project-based approach and Hybrid approach
Activity-based approach,The product-based approach and Hierarchical approach
23. __Essentially an activity bar chart indicating the scheduled activity dates and duration with
activity floats,___ Provides a more striking visual induction of the activities and ________A
method of recording and displaying the way in which targets have changed throughout the
duration of the project
Gantt chart , slip chart and Timeline
Slip chart , Gantt chart and Timeline
Timeline ,Slip chart and Gantt chart
None of the above
25. Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish
times for the three activities are 12, 15, and 10, then the earliest start time for Y will be
10
15
12
Cannot be determined
26. Which is a software configuration management concept that helps us to control change
without seriously impeding justifiable change?
Baselines
Source code
Data model
None of the mentioned
27. What complements the formal technical review by assessing a configuration object for
characteristics that are generally not considered during review?
Software configuration audit
Software configuration management
Baseline
None of the mentioned
28.According to the time estimates made by the PERT planners, the maximum time that would
be needed to complete an activity is called as __________
The most likely time estimate
Optimistic time estimate
Pessimistic time estimate
Expected time estimate
29. a)The difference between the maximum time available and the actual time needed to perform
an activity is known as _________and , b)In a network, a critical path is the time-wise shortest
path.
Free float,false
Independent float,false
Total float,false
Half float,false
2. The problems experienced in the survey of managers published by Thayer, Pyster and Wood
include_________.
A. poor estimates and plans.
B. poor role definition.
C. poor quality control.
D. both a and b.
3. ________ is needed to ensure that the project remains under control and that it continues to
meet its business justification.
A. Yellow tape.
B. White tape.
C. Red tape.
D. Black tape.
4. Which form of software development model is most suited to a system where all the
requirements are known at the start of a project and remain stable throughout the project?
A. Waterfall model.
B. Incremental model.
C. Evolutionary model.
D. Spiral model.
6.Which type of risk factor is most likely to cause problems for a software project developing
commercial software?
A. Inadequate user documentation.
B. Litigation expense.
C. Low productivity.
D. Cancellation of project.
9.Effort = __________.
A. system size X productivity rate.
B. system size X KLOC.
C. person in months / SLOC.
D. person in months X productivity rate.
10. The statement "If a system does not have to reliable, it can meet any other objective" is from
__________.
A. Brooks Law.
B. Peters Law.
C. Parkinson's first Law.
D. Weinberg's Zeroth Law.
13. The calculation of __________ is a project evaluation technique that takes into account the
profitability of a project and the timing of cash flows that are produced.
A. NPV.
B. TPV.
C. SPV.
D. LPV.
14. The costs that include the salaries and other employment costs of the staff involved in the
project development and all associated costs are called____________.
A. operational cost.
B. development cost.
C. setup cost.
D. direct cost.
15. One of your team members has asked for some time on the meeting agenda to seek the
help and cooperation of other team members on his/her assignment. During the ensuring
team discussion, you feel that:
A. Every team member is hiding their real motives and feelings
B. The majority of the team members are hiding their needs, expectations, and goals
C. Some team members are posturing to advance their hidden agendas
D. All team members are open about their real motives and feelings; we communicate
honestly
16. The team leader has just made an impassioned plea to improve the level of cooperation
that exists within the group. As the discussion develops you note:
A. All team members really seem concerned with helping each other, and working as a
team
B. The majority of the team members are in favor of improving teamwork
C. The team members are split-half are in favor of improving teamwork; half would rather
operate independently
D. The majority of the team members want to continue to operate independently
17.Which of the following statements best describes the level of risk taking, innovation,
imagination, and initiative by members of the group:
A. Beware, we shoot the messenger
B. Nothing ventured, nothing gained-go for it
C. Don’t rock the boat, if it’s not broke don’t fix it
D. Some team members seem more comfortable with risk-taking and change than others
22. List three approaches to identifying the activities or tasks that make up a project
a)Activity-based approach,The product-based approach and Hybrid approach
b) Actual-based approach,The product-based approach and Hybrid approach
c) a)Activity-based approach,The project-based approach and Hybrid approach
d) a)Activity-based approach,The product-based approach and Hierarchical approach
23. __Essentially an activity bar chart indicating the scheduled activity dates and duration with
activity floats,___ Provides a more striking visual induction of the activities and ________A
method of recording and displaying the way in which targets have changed throughout the
duration of the project
a) Gantt chart , slip chart and Timeline
b) Slip chart , Gantt chart and Timeline
b) Timeline ,Slip chart and Gantt chart
d) None of the above
25. Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish
times for the three activities are 12, 15, and 10, then the earliest start time for Y will be
A) 10
B) 15
C) 12
D) Cannot be determined
26. Which is a software configuration management concept that helps us to control change
without seriously impeding justifiable change?
a) Baselines
b) Source code
c) Data model
d) None of the mentioned
27. What complements the formal technical review by assessing a configuration object for
characteristics that are generally not considered during review?
a) Software configuration audit
b) Software configuration management
c) Baseline
d) None of the mentioned
28.According to the time estimates made by the PERT planners, the maximum time that would
be needed to complete an activity is called as __________
a) The most likely time estimate
b) Optimistic time estimate
c) Pessimistic time estimate
d) Expected time estimate
29. a)The difference between the maximum time available and the actual time needed to perform
an activity is known as _________and , b)In a network, a critical path is the time-wise shortest
path.
a) Free float,false
b) Independent float,false
c) Total float,false
d) Half float,false
3.The process each manager follows during the life of a project is known as
(a) Project Management
(b) Manager life cycle
(c) Project Management Life Cycle
(d) All of the mentioned
Answer: c
5.The objective of _______________________ is to determine a specific value based on a predetermined discount rate.
(a)PERT
(b)ROI
(c) cost benefit analysis
(d) net present value
Answer: d
6. A unique, planned, scheduled activity with one or more objectives referred as
(a) Project
(b) Job
(c) Process
(d) Task
Answer: a
10. Projects may be distinguished by whether their aim is to produce a or meet certain
.
(a) product, objective
(b) product, tasks
(c) tasks, objective
(d)t
a
s
k
s
A
N
S
W
E
R
:
A
UNIT-2
1. Which of the following is/are main parameters that you should use when computing the costs of
a software development project?
(a) travel and training costs
(b) hardware and software costs
(c) effort costs (the costs of paying software engineers and managers)
(d) all of the mentioned
Answer: d
2. Many software projects digress from the original scope because of the nature of the software
product or technology used, it’s happened in ________
(a) Product scope changed toward the end of the project life cycle
(b) Research-oriented software development
(c) Defined scope
(d) Fuzzy users
Answer: b
3.When you build a product or system, it’s important to go through a series of predictable steps , the
process which you follow to develop it is known as________
(a)Software design
(b)Software process
(c)Software schedule
(d)Framework
Answer: b
4.Project has uncertainties on some functionalities at the beginning which will improve over time.
Which software development model is suitable?
(a) Waterfall
(b) Iterative
(c) Incremental
(d) None of the above
Answer: b
8. prototypes are used and discarded when the true development of the operational
system is commenced.
a.Evolutionary.
b.Throw away.
c.Operational.
d
.
R
e
a
l
.
A
N
S
W
E
R
:
B
UNIT-3
1.What should be done by the project manager to ensure that all work in the project is included?
(a) Create a contingency plan
(b) Create a risk management plan
(c) Create a WBS
(d) Create a scope statement
Answer: c
2. What should a project manager do or follow to ensure clear boundaries for project completion?
(a) Scope verification
(b) Completing a scope statement
(c) scope definition
(d) Risk management plan
Answer: b
3.An organization is certified to a stringent environmental standard and uses that as the key
differentiator with its competitors. Alternative method is available but involves lot of risk. What
should the project team do?
(a) Drop the alternative approach
(b) Work out a mitigation plan
(c) Procure an insurance against the risk
(d) Plan all precautions to avoid the risk
Answer: a
UNIT-4
1.Version control combines ______ to manage different versions of configuration objects that are
created during software product development.
(a) Procedure
(b) Tools
(c) Procedure and Tools
(d) None of given
Answer: c
2. Most software project manager’s practice a lot of management techniques that are of
doubtful authenticity are called
(a)Project management tools
(b)Project management myths
(c)Project management thumb rules
(d) Project management fundamentals
Answer: b
3.Which of the following is incorrect activity for the configuration management of a software
system?
(a)System Management
(b)Internship Management
(c ) Version Management
(d)Change Management
Answer:b
4.What is the common metrics for correctness of software?
(a)Error
(b)Good documentation
(c) Defect
(d) LOC
Answer: c
6.To define all project tasks, build a network that depicts their
A. Interdependencies B. Arrangement
C. Position D. Work
Answer:A
8.What complements the formal technical review by assessing a configuration object for characteristics that
are generally not considered during review?
c) Baseline
Answer:A
9.Which of the following is the process of assembling program components, data, and libraries, and
then compiling and linking these to create an executable system?
a) System building
b) Release management
c) Change management
d) Version management
Answer:A
Answer:D
UNIT-5
1.Which technique is applicable when other projects in the same analogy application domain have
been completed?
(a) Algorithmic cost modelling
(b) Parkinson’s Law
(c ) Estimation by analogy
(d)Expert Judgement
Answer: c
3.Who delivers the technical skills that are necessary to engineer a product or an application?
(a) practitioners
(b) senior managers
(c ) project managers
(d) None
Answer: a
5.Requirements are refined and analysed to assess the clarity , completeness and --------------
(a)concurrency
(b)consistency
(c ) correctness
(d)None of the above
Answer: b
6.Algorithmic cost estimation in different organisations may be different for the same
application development, because
Answer:E
7.Work that continues throughout the project and does not relate to any specific phase of software
development is termed a(n)
a) Milestone
b) Project function
c) Activity
d) Task
e) Baseline.
Answer:B
8.In the classical chief programmer team approach, the team member responsible for maintaining the
detailed design and coding is
Answer:D
9. The organization as part of its monitoring and control policy may have a programme in place which dictates that certain statistics have to be collected at
various stages of a project.
a.measurement.
b.system.
c.software.
d.testing.
ANSWER:A
10. If the measurement taken by the two people are same refers to the terms as
E. Reliability
F. Validity
G. Calibration
H. Ease of use and simplicity
ANSWER: A
Dr.G.R.Damodaran College of Science
(Autonomous, affiliated to the Bharathiar University, recognized by the UGC)Re-accredited at the 'A' Grade Level by the NAAC and ISO
9001:2008 Certified
CRISL rated 'A' (TN) for MBA and MIB Programmes
1. A unique, planned, scheduled activity with one or more objectives referred as___
A. Project
B. Job
C. Process
D. Task
ANSWER: A
6. Projects may be distinguished by whether their aim is to produce a ________ or meet certain _______.
A. product, objective
B. product, tasks
C. tasks, objective
D. tasks and null objects
ANSWER: A
7. The first stage of the software project is a ________which results in a recommended course of action.
A. system driven project
B. software driven project
C. hardware driven project
D. objectives driven project
ANSWER: D
9. In case of product-driven projects, the objectives of the project are defined in terms of ___________.
A. functional requirements only
B. resource and non-functional requirements
C. functional and quality requirements
D. resource requirements only
ANSWER: C
10. ________ defines what the end product of the project is to do.
A. product perspective.
B. Non-functional requirements.
C. Quality requirements.
D. Functional requirements.
ANSWER: D
11. ________ is a system analysis and design method designed primarily to provide functional requirements.
A. SSTD.
B. SADT.
C. SGTH.
D. STDH.
ANSWER: B
13. _______ is record of how much the organization is willing to spend to the system
A. Resource requirements.
B. Functional requirements.
C. Security requirements.
D. Non-functional requirements.
ANSWER: A
14. Projects are by definition __________ and therefore more uncertain than normal undertakings.
A. routine
B. non-routine
C. specific
D. controllable
ANSWER: B
18. The organization as part of its monitoring and control policy may have a ________ programme in place which dictates that certain statistics have to be collected at
various stages of a project.
A. measurement.
B. system.
C. software.
D. testing.
ANSWER: A
19. The products handed over to the clients at the end of projects are called as __________.
A. software
B. application program
C. deliverables
D. intermediate products
ANSWER: C
22. The relationship between program design and program specification can be portrayed in _________.
A. PFD.
B. DFD.
C. PDF.
D. DDF.
ANSWER: A
23. Which one of the following is NOT an agile method?
A. SCRUM
B. Extreme Programming (XP)
C. DSDM
D. Waterfall
ANSWER: D
24. Same generic fragment relates to more than _________ instance of the particular type of the product.
A. one.
B. two.
C. three
D. four
ANSWER: A
27. In order to carry out a successful strategic assessment of a potential project there should be strategic plan clearly defining the organization's _________.
A. objectives.
B. rules.
C. conditions.
D. ideas.
ANSWER: A
28. The standard way of evaluating the economic benefits of any projects is to carry out a ________ analysis.
A. price-benefit.
B. cost-benefit.
C. cash flow.
D. fund flow.
ANSWER: B
29. The costs that include the salaries and other employment costs of the staff involved in the development project and all associated costs are____________.
A. operational cost.
B. development cost.
C. setup cost
D. direct cost.
ANSWER: B
30. Long term or benefits that are considered very difficult to quantify is called _______.
A. direct benefits.
B. assessable benefits.
C. indirect benefits.
D. intangible benefits.
ANSWER: D
31. _________ will indicate when expenditure and income will take place.
A. Cash flow forecast.
B. Cost analysis.
C. Fund flow.
D. Technical forecast.
ANSWER: A
32. _________ is the time taken to break even or pay back the initial investment.
A. Back period.
B. Payback period.
C. Cash back period.
D. Rate of Return.
ANSWER: B
42. ________prototypes are used and discarded when the true development of the operational system is commenced.
A. Evolutionary.
B. Throw away.
C. Operational.
D. Real.
ANSWER: B
43. ______ is as when copies of input screens are shown to the users on a workstation, but the screens cannot actually be used.
A. Simulation.
B. Annealing.
C. Mock-ups.
D. RAD system.
ANSWER: C
45. The scope of the deliverables for an increment is rigidly constrained by an agreed deadline called as ____________.
A. sand boxing.
B. time boxing.
C. time delaying.
D. local delaying.
ANSWER: B
46. ______ would mean the change can be implemented without software development.
A. One cost.
B. Total cost.
C. Zero cost.
D. No cost.
ANSWER: C
47. SSADM means ___________.
A. Straight Systems Analysis Design Method.
B. Structured Systems Analysis Design Method.
C. Software Systems Analysis Design Method.
D. Solutions Systems Analysis Design Method.
ANSWER: B
54. The statement "If a system does not have to reliable, it can meet any other objective" is from __________.
A. Brooks Law.
B. Peters Law.
C. Parkinson's first Law.
D. Weinberg's Zeroth Law.
ANSWER: D
63. ________ the degree to which there is a large dispersed team as opposed to there being a small tightly knit team.
A. Small cohesion.
B. Team cohesion.
C. Process maturity.
D. Team maturity.
ANSWER: B
69. The activities have zero duration but are assumed to start at the same time as the first and the end at the same time as the last one is called__________.
A. hijacked activity.
B. heuristic activity.
C. hammocked activity.
D. hole activity.
ANSWER: C
70. ____ is carried out to calculate the earliest dates on which each activity may be started and completed.
A. Backward pass.
B. Forward pass.
C. No pass.
D. Increasing pass.
ANSWER: B
71. The time by which an activity may be delayed without affecting any subsequent activity is called _________.
A. action float.
B. terminal float.
C. free float
D. null float
ANSWER: C
72. The objective of ________ is to avoid or minimize the adverse effects of unforeseen events is called
A. risk management.
B. risk maintenance.
C. risk taking.
D. risky job.
ANSWER: A
73. A _________ is an event that might occur and if it occurs, create a problem for the successful completion of the project.
A. planning.
B. hazard.
C. safety.
D. start.
ANSWER: B
78. The shortest time in which we could expect to complete the activity, barring outright miracles called ________.
A. Optimistic Time
B. Pessimistic Time
C. Most Likely Time
D. Shortest Time
ANSWER: A
79. PERT combines three estimates of time and obtains a single expected duration is ____________.
A. te
B. tp
C. tm
D. ts
ANSWER: A
80. _________ is proportional to the difference between the optimistic and pessimistic estimates.
A. Activity Regression
B. Activity mean
C. Activity Standard Deviation
D. Activity Variance
ANSWER: C
81. The________ value in PERT is calculated for each node that has a target date.
A. x value.
B. y value.
C. t value.
D. z value.
ANSWER: D
84. A ________ is any item or person required for the execution of the project.
A. risk.
B. allocation.
C. activity.
D. resource.
ANSWER: D
85. According to Bob Hughes and Mike Cotterell, resources fall into _______ categories.
A. five.
B. four.
C. seven.
D. two.
ANSWER: C
87. "Each activity has been scheduled to start at its earliest start date" is called as_________.
A. likelihood.
B. activity schedule.
C. probability.
D. planning.
ANSWER: A
88. In _________ activities are allocated resources in ascending order of total float.
A. total free priority.
B. total float priority.
C. technical float priority.
D. top float priority
ANSWER: B
89. ______ is the selection of individuals in which the final shape of the project team is taken into account
A. Independent building.
B. Construction building.
C. Team building.
D. Recruitment.
ANSWER: B
90. To know whether a particular individual is available when required is known as _____.
A. reliability.
B. consistency.
C. availability.
D. portability.
ANSWER: C
92. _________ represents expenditure that an organization incurs, which cannot be directly related.
A. Under head
B. Over head.
C. Top head.
D. Miscellaneous expenses
ANSWER: B
96. _______ is an activity bar chart indicating scheduled activity dates and durations frequently augmented with activity floats. .
A. Bar chart.
B. Ball chart.
C. Slip Chart.
D. Gantt chart
ANSWER: D
97. Gantt charts, Slip chars and Ball charts are under ___________ process.
A. monitoring.
B. verification.
C. control.
D. visualization.
ANSWER: D
98. _______ is the method of recording and displaying the way in which targets have changed throughout the duration of the project.
A. Gantt chart.
B. Bar chart.
C. Timeline.
D. Schedule.
ANSWER: C
99. The total value credited to a project at any point is known as _______.
A. earned value.
B. moral value.
C. money value.
D. recurred value
ANSWER: A
100. The priorities we might apply in deciding levels in monitoring is called as ______.
A. deciding monitoring.
B. monitoring.
C. tracking.
D. prioritized monitoring.
ANSWER: D
101. Risk management will occur in the step ____________ of step wise planning.
A. 7
B. 8
C. 6
D. 4
ANSWER: C
102. __________ relates to the physical resources used when the software is executed.
A. Functionality.
B. Maintainability.
C. Reliability.
D. Efficiency.
ANSWER: D
104. A _________ is a container-like element for organizing other elements into groups.
A. classes.
B. adornments.
C. packages.
D. activities.
ANSWER: C
109. An ______ is a named property of a class that describes the object being modeled.
A. method.
B. constant.
C. message.
D. attribute.
ANSWER: B
111. _______ is a description of a set of objects that share the same attributes,operations, relationships, and semantics.
A. Object.
B. Class.
C. Process.
D. Instance
ANSWER: B
112. _______ will divide the domain of the task hierarchy in activity diagrams.
A. Swim lane.
B. Activity.
C. Interface.
D. Split.
ANSWER: A
113. _______ is the task/process which describes the way in which the actor interact the system.
A. Class.
B. Flow.
C. Object.
D. Use case.
ANSWER: D
115. A metric used to measure the characteristic of documentation and code called as
A. Process metric
B. Product Metric
C. Test metrics
D. None of the above
ANSWER: B
118. Software testing which is done without planning and Documentation is known as
A. adHoc Testing
B. Unit Testing
C. Regression testing
D. Functional testing.
ANSWER: A
119. This type of testing method attempts to find incorrect or missing functions, errors in data structures or external database access, interface errors, Performance errors
and initialization and Termination errors. It is called as
A. White Box Testing
B. Grey Box Testing
C. Black Box Testing
D. Open Box Testing
ANSWER: C
120. Retesting of a single program or component after a change has been made?
A. Full Regression Testing
B. Unit Regression
C. Regional Regression
D. Retesting
ANSWER: B
121. Defects are less costly if detected in which of the following phases
A. Coding
B. Design
C. Requirements Gathering
D. Implementation
ANSWER: C
133. You are told to prepare a report on the most commonly occurring product defects. You review the software defect reports, which categories the defects of coding
errors, requirement errors, documentation errors, etc. The best tool to report this information is
A. A histogram
B. A pareto diagram
C. A cause and effect diagram
D. A scatter plot
ANSWER: A
134. A statistical technique to assess, monitor and maintain the stability of a process is
A. Pareto chart
B. Control chart
C. Run chart
D. Histogram
ANSWER: B
136. If the measurement taken by the two people are same refers to the terms as
A. Reliability
B. Validity
C. Calibration
D. Ease of use and simplicity
ANSWER: A
139. You are performing a test to see that it complies with the user requirement that a certain field be populated by using a drop down box containing a list of values.
What kind of testing are you doing?
A. White box testing
B. Black box testing
C. Load testing
D. Regression testing
ANSWER: B
141. The approach/document used to make sure all the requirements are covered when writing test cases
A. Test Matrix
B. Checklist
C. Test bed
D. Traceablity Matrix
ANSWER: D
142. Executing the same test case by giving the number of inputs on same build called as
A. Regression Testing
B. ReTesting
C. Ad hoc Testing
D. Sanity Testing
ANSWER: B
143. To check whether we are developing the right product according to the customer requirements are not. It is a static process
A. Validation
B. Verification
C. Quality Assurance
D. Quality Control
ANSWER: B
144. To check whether we have developed the product according to the customer requirements r not. It is a Dynamic process.
A. Validation
B. Verification
C. Quality Assurance
D. Quality Control
ANSWER: A
146. A Non-Functional Software testing done to check if the user interface is easy to use and understand
A. Usability Testing
B. Security Testing
C. Unit testing
D. Block Box Testing
ANSWER: A
147. It measures the quality of processes used to create a quality product. It is a system of management activities, It is a preventive process, It applies for entire life cycle
& Deals with Process.
A. Validation
B. Verification
C. Quality Assurance
D. Quality Control
ANSWER: C
150. Name the events that will be analyzed, Count the named incidents, Rank the count by frequency using a bar chart & Validate reasonableness of the analysis is called
as
A. Pareto Analysis
B. Cause and Effect Diagram
C. SWOT Analysis
D. Pie Charts
ANSWER: A
Staff Name
Sujatha S .
MG6088 Software Project Management Department of IT/CSE 2019- 2020
2. Project managers have to assess the risks that may affect a project.
a) True
b) False
4. The process each manager follows during the life of a project is known as
a) Project Management
b) Manager life cycle
c) Project Management Life Cycle
d) All of the mentioned
6. Which of the following is/are main parameters that you should use when computing the
costs of a software development project?
a) travel and training costs
b) hardware and software costs
c) effort costs (the costs of paying software engineers and managers)
d) all of the above
c) customers
d) project manager
8. Which of the following is incorrect activity for the configuration management of a
software system?
a) Internship management
b) Change management
c) Version management
d) System management
10. An independent relationship must exist between the attribute that can be measured and
the external quality attribute.
a) True
b) False
11. In designing a system it is found that the cost of the system was Rs 1,50,000 and the
benefit is Rs 10,000 per month. The interest is 1% per month; the payback period using
the present value method is
a) 14 months
b) 17 months
c) 15 months
d) 20 months
b) i and iv
c) ii and iii
d) i and ii
15. A unique, planned, scheduled activity with one or more objectives referred as
a) Project
b) Job
c) Process
d) Task
16. The first stage of the software project is a which results in a recommended
course of action.
a) system driven project
b) software driven project
c) hardware driven project
d) objectives driven project
19. Which of the following risks are derived from the organizational environment where
the software is being developed?
a) People risks
b) Technology risks
c) Estimation risks
d) Organizational risks
20. Which of the following strategies means that the impact of the risk will be reduced?
a) Avoidance strategies
b) Minimization strategies
c) Contingency plans
d) All of the mentioned
21. Which of the following term is best defined by the statement: ―There will be a change
of organizational management with different priorities.‖?
a) Staff turnover
b) Technology change
c) Management change
d) Product competition
22. What assess the risk and your plans for risk mitigation and revise these when you learn
more about the risk?
a) Risk monitoring
b) Risk planning
c) Risk analysis
d) Risk identification
25. Positive motivation makes people willing to do their work in the best way they can and
improve their.
a) Productivity
b) Personality
c) Performance
d) All of the above
26. Return on investment(ROI) is calculated by
a) (Average Annual Profit*total investment)/100
b) (Average annual profit*100)/total investment
27. In the abbrevation of SMART what does the letter M stands for
a) Marketing
b) Measurable
c) Milestone
d) Management
29. The process each manager follows during the life of a project is known as
a) Project Management
b) Manager life cycle
c) Project Management Life Cycle
d) All of the mentioned
30. Which of the following is incorrect activity for the configuration management of a
software system?
a) Internship management
b) Change management
c) Version management
d) System management
35. Which of the following traits need to exist among the members of an agile software team?
a) Competence
b) Decision-making ability
c) Mutual trust and respect
d) All of the above
38. The formal methods model of software development makes use of mathematical methods
to
a) Define the specification for computer-based systems.
b) Develop defect free computer-based systems.
c) Verify the correctness of computer-based systems.
d) All of the above.
40. Agile modeling (AM) provides guidance to practitioner during which of these software
tasks?
a) Analysis and Design
b) Design and Coding
c) Coding and Testing
d) Testing and Maintenance
41. Which of the following is not necessary to apply agility to a software process?
a) Eliminate the use of project planning and testing
b) Only essential work products are produced
c) Process allows team to streamline tasks
d) Uses incremental product delivery strategy
42. What are the four framework activities found in the Extremen Programming (XP) process
model?
a) Analysis, design, coding, testing
b) Planning, analysis, design, coding
c) Planning, analysis, coding, testing
d) Planning, design, coding, testing
43. Which is not one of the key questions that is answered by each member at each daily
Scrum meeting?
a) What did you do since the last meeting?
b) What obstacles are you creating?
c) What is the cause of the problem you are encountering?
d) What do you plan to accomplish be the next team meeting?
c) Software functions
d) Software functions and process activities
56. Which of the following is/ are main parameters that you should use when computing the
costs of a software development project?
a) Travel and training costs
b) Hardware and software costs
c) Effort costs
d) All of the above
62. Which of the following is not an approach to identify the activities that make up a project
a) The activity-based approach,
b) The product-based approach
c) The non- hybrid approach.
d) The process-based approach
64. Which of the option is not a notable challenge while scheduling a project?
a) Deadlines exist.
b) Independent activities.
c) Too many workers may be required.
d) Costly delay
68. Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish
times for the three activities are 12, 15, and 10, then the earliest start time for Y will be
a) 10
b) 15
c) 12
d) Cannot be determined
69. Activities P, Q and R instantly follow activity M, and their current start times are 12, 19,
and 10. Therefore, the latest finish time for activity M is
a) 11
b) 10
c) 18
d) Cannot be determined
72. A process of specifying the time for when each activity should take place
a) Scheduling
b) Sequencing
c) Activity Plan
d) Project Plan
c) Activity Model
d) Pie Chart
76. The difference between the earliest date and latest date for an event is
a) Free Float
b) Total Float
c) Slack
d) Float
79. An event that might occur and will create a problem for the successful completion of the
project, if it does occur.
a) Risks
b) Project Failure
c) Hazards
d) Threat
c) Stock Holding
d) Stock Maintenance
d) Close Activity
89. Using feasibility analysis it is necessary to examine several alternative solutions because
(i) a comparison of alternatives will lead to a cost-effective solution
(ii) a pre-conceived single solution may turn out to be unimplementable
(iii)it is always good to examine alternatives
(iv) management normally looks at alternatives
a) i and iii
b) i and iv
c) i and ii
d) ii and iv
91. Resource requirement in project becomes constant while the project is in its
progress stage.
a) 40 to 55%
b) 55 to 70%
c) 70 to 80%
d) 80 to 95%
92. Project managers have to assess the risks that may affect a project.
a) True
b) False
93. Which of the following is/are main parameters that you should use when computing the
costs of a software development project?
a) travel and training costs
b) hardware and software costs
c) effort costs (the costs of paying software engineers and managers)
d) All of the mentioned
94. Which of the following is incorrect activity for the configuration management of a
software system?
a) Internship management
b) Change management
c) Version management
d) System management
c) De-processification
d) Process distribution
96. An independent relationship must exist between the attribute that can be measured and
the external quality attribute.
a) True
b) False
104. Which of the following is not considered one of the four important elements that should
exist when a configuration management system is developed?
a) Component elements
b) human elements
c) process elements
d) Validation elements
105. Which configuration objects would not typically be found in the project database?
a) design specification
b) marketing data
c) Organizational structure Description
d) test plans
e) b and c
107. Which of the following task is not part of software configuration management?
a) Change control
b) reporting
c) Statistical quality control
d) Version control
108. Change management for web and mobile Apps is best handled in agile manner.
a) True
b) False
109. Content management establishes a process which web content is rendered on the user’s
display screen
a) True
b) False
112. Change control is not necessary if a development group is making use of an automated
project database tool
a) True
b) False
113. The following costs are not part of the total effort cost
a) Costs of lunch time food
b) Costs of providing heating
c) Costs of networking
d) Costs of support
114. A is developed using historical cost information that relates some software
metric to the project cost.
a) Estimation by analogy
b) Parkinson’s Law
c) Algorithmic cost modeling
d) Expert judgement
117. If Task A to complete,it takes 10 days of human effort.It started 5 days earlier to the
scheduled date and completed on 35th day.Then,the float value
a) A.20
b) B.25
c) C.10
d) D.15
122. Which of the following is not included in Hackman and Oldham’s job characteristics model
of work motivation?
a) Variety of skill
b) Significance of the task
c) Quality of job life
d) Autonomy
124. The field of organisational behaviour examines such questions as the nature of leadership,
effective team development, and
a) Interpersonal conflict resolution; motivation of individuals
b) Organisational control; conflict management
c) Motivation of individuals; planning
d) Planning; development
126. The study of organisation behaviour has certain basic assumptions. They are
a) An industrial enterprise is an organization of people.
b) These people must be motivated to work effectively.
c) The goals of the employee and the employer may not necessarily coincide.
d) All of the above.
128. Which of the following is not correct for the organisational behaviour?
a) Organisational behaviour is an integral part of management
b) Organisational behaviour is a disciplinary approach
c) Organisational behaviour helps in analysis of behavior
d) Organisational behaviour is goal-oriented
130. Now a days a lot of stress is being put on the of the employee in the
organization
a) Character
b) improvement
c) Behaviour
d) Rewards
133. theory emphasis that, Unsatisfied need can influence the behaviour
satisfied one will not act as a motivator.
a) Maslow Theory
b) Herzberg’s Theory
c) Expectancy theory
d) Alderfer’s ERG theory
134. Among the following which is not a problem in changing the attitude of the employee
a) Insufficient Information
b) Resistant by employee
c) Cognitive Dissonance
d) Cognitive Dissonance
138. In which stage of the team development process does hostility and infighting occur?
a) storming
b) forming
c) norming
d) performing
140. Which of the following best defines the type of rewards that are distributed toindividuals
for their unique contribution to the team?
a) functional team rewards
b) competitive team rewards
c) cooperative team rewards
d) non-competitive team rewards
142. What is the ideal size of a team in order for it to be productive and successful?
a) 2 to 4
b) 9 to 12
c) 5 to 8
d) 8 to 11
143. Which of the following best defines an organization where decision making authority is at
the top of the organization and employees have little freedom to make their own decisions?
a) decentralized organization
b) centralized organization
c) virtual organization
d) functional organization
145. Which of the following best describes functions that are advisory and supportive in nature;
designed to contribute to the efficiency and maintenance of theorganization?
a) line functions
b) organizational functions
c) matrix functions
d) staff functions
149. On her work team Michelle develops detailed tasks lists and work flow charts to help her
team members understand the steps involved in each project. She also maintains the project
calendar and receives periodic updates from each team member to ensure that projects are
progressing on schedule. Which role does Michelle most likely fill on her team?
a) assessor
b) organizer
c) maintainer
d) creator
Topic
1
MG6088 Software Project Management
MULTIPLE CHOICE QUESTIONS
UNIT 1
1. Project managers have to assess the risks that may affect a project.
a) True
b) False
3. The process each manager follows during the life of a project is known as
a) Project Management
b) Manager life cycle
c) Project Management Life Cycle
d) All of the mentioned
5. Which of the following is/are main parameters that you should use when computing
the costs of a software development project?
a) travel and training costs
b) hardware and software costs
c) effort costs (the costs of paying software engineers and managers)
d) all of the above
2
MG6088 Software Project
Management
c) customers
d) project manager
7. Which of the following is incorrect activity for the configuration management of
a software system?
a) Internship management
b) Change management
c) Version management
d) System management
9. An independent relationship must exist between the attribute that can be measured
and the external quality attribute.
a) True
b) False
10. In designing a system it is found that the cost of the system was Rs 1,50,000 and the
benefit is Rs 10,000 per month. The interest is 1% per month; the payback period
using the present value method is
a) 14 months
b) 17 months
c) 15 months
d) 20 months
3
MG6088 Software Project
Management
a) iii and iv
b) i and iv
c) ii and iii
d) i and ii
14. A unique, planned, scheduled activity with one or more objectives referred as
a) Project
b) Job
c) Process
d) Task
5
MG6088 Software Project
Management
29. Which of the following are Project Management processes?
a) Planning and develop processes
b) Analyzing and evaluate processes
c) Planning and executing processes
d) None of them
30. Your project statement tells you what must be done, how it must be
done.
a) assumption B. resource
C. scope D. constraint and objectives or specifications to be met
UNIT II
1) ___________ is a method of splitting of software development work into distinct phases (or
stages) containing activities with the intent of better planning and management.
a) software development methodology
b) artifacts
c) process
d) phase
2) The software development methodology may include the predefinition of _____ and ____ that
are created.
a)model, process
b)deliverables,artifacts
c)planning,management
3) ______, ______ and ______ are the three basic approaches applied to software development
methodology frameworks.
a) Framework, process,planning
b) Prototyping,waterfall,spiral
c) Methodology, framework,management
4) Each of the methodology frameworks are best suited to specific kinds of projects, based on
technical, organizational, project and team considerations.
a) Process,cost,benefit
b) Selecting,implementing,monitoring
c) Technical,organizational,project
5) Software development organizations implement --------- to ease the process of development.
a) Cost-benefit analysis
b) Process methodologies
c) Framework planning
6) The international standard for describing the method of selecting, implementing and monitoring
the life cycle for software is ---------------.
a) ISO/IEC 12207
b) ISO/IEC 12307
c) ISO/IEC 12107
6
MG6088 Software Project
Management
7) Large numbers of software projects do not meet their expectations in terms of ------, -------, or -----
-- schedule.
a) functionality, cost, delivery
b) cost,benefit,planning
c) framework, management, methodology
8) Organizations may create a _________, which is the focal point for process improvement.
a) Software Engineering Process Group (SEPG)
b) Plan
c) Model
9) A major part of the _________ will be the choosing of the development methods to be used and
the slotting of these into an overall process model.
a) Planning
b) Framework
c) Model
10) --------------- is a general term used to refer to alternatives to the conventional waterfall model of
software development.
a) Rapid application development (RAD)
b) Waterfall model
c) Framework model
11) RAD approaches to software development put less emphasis on ………… and more emphasis on
…………..
a) Planning, process.
b) Process,planning
c) Framework,model
12) RAD approaches emphasize ________ in response to knowledge gained as the project progresses.
a) adaptability
b) scalability
c) reliability
13) Graphical user interface builders are often called __________ tools.
a) rapid application development
b) process development
c) framework development
14) The James Martin approach to RAD divides the process into four distinct phases such as _____,
_____,_____ and _____
a) Requirements planning, User design, Construction, Cutover
b) Process,planning,framework,model
c) Cost,benefit,planning,analysis
15) _______ phasecombines elements of the system planning and systems analysis phases of the
Systems Development Life Cycle (SDLC).
a) Requirements planning
b) User design
c) Construction
d) Cutover
7
MG6088 Software Project
Management
16) The RAD groups or subgroups typically use a combination of _____ techniques and ______ to
translate user needs into working models.
a) Joint Application Development, CASE tools
b) Cost,benefit
c) Process,model
d) Framework,process
17) ________ is a continuous interactive process that allows users to understand, modify, and
eventually approve a working model of the system that meets their needs.
a) User Design
b) Adaptability
c) Feasibility
d) Scalability
18) ________ phase focuses on program and application development task similar to the SDLC.
a) Construction
b) User Design
c) Requirement
d) Analysis
19) ______ is an advantage of RAD model
a) Risk control
b) Adaptability
c) Scalability
d) Feasibility
20) The _______ model emphasizes on the fact that entire team should be a tightly integrated unit.
a) Agile
b) Process
c) Project
d) Framework
21) Deliveries are short-term and these are usually a delivery cycle ranges from one week to four
weeks. These are commonly known as _____
a) Sprints
b) Frameworks
c) Processes
d) Models
22) Agile Project Management does not _____
a) Enhance the tool and practices used in the development process
b) Facilitate and encourage effective and open communication within the team.
c) hold agile meetings that discusses the short-term plans and plans to overcome obstacles.
d) involve in technical decision making or deriving the product strategy.
23) _____________is a software development methodology which is intended to improve software
quality and responsiveness to changing customer requirements.
a) Extreme programming (XP)
b) Waterfall model
c) Spiral model
8
MG6088 Software Project
Management
24) _________ are the elements of extreme programming
a) extensive code review
b) unit testing of all code
c) flat management structure
d) all of these
25) _____ is the process of finding an estimate, or approximation, which is a value that can be used
for some purpose even if input data may be incomplete, uncertain, or unstable.
a) Estimation
b) Planning
c) Framework
d) Programming
26) Estimation is based on
a) Past Data/Past Experience
b) Available Documents/Knowledge
c) Assumptions
d) All of these
27) The Project Estimation Approach that is widely used is_________
a) Decomposition Technique
b) Waterfall model
c) Spiral model
28) Important factors that affect the accuracy of estimates are_________
a) input data
b) estimate calculation
c) predictability
d) all of these
29) Guidelines in estimating a project include _________
a) Include management time in any estimate.
b) Always build in contingency for problem solving
c) Allow enough time to do a proper project estimate.
d) All of these
30) _________, __________ and ____________ are the three function point counts.
a) Development, Application, Enhancement
b) Waterfall,spiral,process
c) Framework,planning,cost
31) _________ and ______ are the types of data function
a) Internal Logical File, External Interface File
b) Process, Data
c) Framework, Model
32) ______________ is an Elementary Process that sends data or control information outside the
application’s boundary.
a) External Output (EO)
b) Dataflow
c) Process Framework
9
MG6088 Software Project
Management
33) The ___________ method is an internationally standardized software sizing method.
a) COSMIC
b) Waterfall
c) Spiral
34) ______, _________ and __________ are performed in a stepwise manner by breaking down a
Project into major Functions or related Software Engineering Activities.
a) Size, Effort ,Cost estimation
b) Framework, process,planning
c) Cost,benefit,process analysis
35) _________ can provide a historical perspective and valuable input for generation of quantitative
estimates.
a) Analysis
b) Requirement
c) Project metrics
UNIT III
1. A combination of interrelated activities and events depicted with arcs and nodes is known as
a) Listing
b) Node sorting
c) Team management
d) Network
2. Networks usually indicate activity precedence constructed from
a) Left to right
b) Right to left
c) Bottom to up
d) Up to bottom
5. The amount of resources of each kind that are to be assigned to a specific activity in a certain time
period is
a) Resource leveling
b) Resource prioritizing
c) Resource loading
d) Resource generation
10
MG6088 Software Project
Management
6. Deciding how to approach and plan the risk management activities for a project is known as
a) Risk identification
b) Risk analysis
c) Risk management planning
d) Risk response
8. Which of the following risk is the failure of a purchased component to perform as expected?
a) Product risk
b) Project risk
c) Business risk
d) Programming risk
9. Which of the following strategies means that the impact of the risk will be reduced?
a) Avoidance strategies
b) Minimization strategies
c) Contingency plans
d) All of the mentioned
10. Risk management is now recognized as one of the most important project management tasks.
a) True
b) False
11. Which of the following is not one of the guiding principles of software project scheduling
a) Compartmentalization
b) Market assessment
c) Time allocation
d) Effort validation
12. The software equation can be used to show that by extending the project deadline slightly
a) Fewer people are required
b) You are guaranteed to meet the deadline
c) More lines of code can be produced
d) None of the above
13. The 40-20-40 rule suggests that the least of amount of development effort be spent on
a) Estimation and planning
b) Analysis and design
c) Coding
d) Testing
11
MG6088 Software Project
Management
14. A task is a collection of
a) Engineering work tasks,milestones,deliverables
b) Task assignments,cost estimates, metrics
c) Milestones, deliverables, metrics
d) Responsibilities , milestones ,documents
15. Tasks that lie on the critical path in a task network may be completed in any order as long as the
project is on the schedule
a) True
b) False
16. Two tools for computing critical path and project completion times from activity networks are
a) CPM,DRE
b) CPM,PERT
c) CPM,FP
d) FP,PERT
17. Which of the following is the reason that software is delivered late?
a) Changing customer requirements that are not reflected in schedule changes
b) Technical difficulties that could not have been foreseen in advance
c) Human difficulties that could not have been foreseen in advance
d) All of the mentioned
18. Which of the following is an activity that distributes estimated effort across the planned project
duration by allocating the effort to specific software engineering tasks?
a) Software Macroscopic schedule
b) Software Project scheduling
c) Software Detailed schedule
d) None of the mentioned
19. What is a collection of software engineering work tasks, milestones, and deliverables that must be
accomplished to complete a particular project?
a) Task set
b) Degree of milestone
c) Adaptation criteria
d) All of the mentioned
20. Ensuring that no more than the allocated number of people are allocated at any given time in
Software Scheduling is known as
a) Time Allocation
b) Effort Validation
c) Defined Milestone
d) Effort Distribution
21. What is used to determine the recommended degree of rigor with which the software process should
be applied on a project?
a) Degree of Rigor
b) Adaptation criteria
12
MG6088 Software Project
Management
c) Task Set
d) Both degree of Rigor and adaptation criteria
22. What evaluates the risk associated with the technology to be implemented as part of project scope?
a) Concept scoping
b) Preliminary concept planning
c) Technology risk assessment
d) Customer reaction to the concept
23. Which of the following is a project scheduling method that can be applied to software development?
a) PERT
b) CPM
c) CMM
d) Both PERT and CPM
26. What assess the risk and your plans for risk mitigation and revise these when you learn more about
the risk?
a) Risk monitoring
b) Risk planning
c) Risk analysis
d) Risk identification
27. Which of the following risks are derived from the organizational environment where the software is
being developed?
a) People risks
b) Technology risks
c) Estimation risks
d) Organizational risks
28. Which of the option is not a notable challenge while scheduling a project?
A) Deadlines exist.
B) Independent activities.
C) Too many workers may be required.
D) Costly delay
13
MG6088 Software Project
Management
34. The project manager meets with the project team to review lessons learned from previous projects. In
what activity is the team involved?
A) Performance management
B) Scope identification
C) Risk identification
D) Project team status meeting
35. All of the following are ALWAYS inputs to the risk management process EXCEPT:
14
MG6088 Software Project
Management
A) Historical information
B) Lessons learned
C)Work breakdown structure
D)Project status reports
37. During which risk management process is a determination to transfer a risk made?
a) Identify Risks
b) Perform Quantitative Risk Analysis
c) Plan Risk Response
d) Monitor and Control Risks
38. If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five
months, what is the probability that the risk event will occur during the fourth month of the project?
40. Which of the following is/are main parameters that you should use when computing the costs of a
software development project?
a) travel and training costs
b) hardware and software costs
c) effort costs (the costs of paying software engineers and managers)
d) All of the mentioned
15
MG6088 Software Project
Management
UNIT IV
1.Which of the following is example of multi-variable cost estimation model?
A.COCOMO
B.intermediate COCOMO
C.both
D.None
2.Which of the following technique overcomes the drawbacks of expert judgement technique?
A.Heuristic technique
B.Delphi cost esttimation
C.Basis COCOMO
D.only a & b
5.This technique decompose a given task set recursively into small activities?
A.Sotware Configuration Management
B.Configuration indentification
C.Work breakdown Structure
D.both a & c
7. Which of the following activity is undertaken immediately after feasibility study and before the
requirement analysis and specification phase?
A.Project Planning
B.Project Monitoring
C.Project Control
D.Project Scheduling
8.In the project planning, which of the following is considered as the most basic parameter based
on which all other estimates are made?
A.project size
B.project effort
16
MG6088 Software Project
Management
C.project duration
D.project schedule
9. To define all project tasks, build a network that depicts their ________________
A. Interdependencies B. Arrangement
C. Position D. Work
10. Software project scheduling is an activity that distributes ________________ across the
planned project duration.
A. Resource B. Time
C. Estimated effort D. Money
12. A task network, also called an activity network, is a _________________ of the task flow for a
project.
A. Slide Presentation B. Video
C. graphic representation D. Drawing
16. ________ combines procedures and tools to manage different versions of configuration
objects that are created during the software process.
a. Configuration status reporting.
b. Change control
c. Version control
d. None of the above
18. What is the name of process which will ensure that different versions of system and its
components are recorded and maintained?
a. workspace
b. code control
c. versions
d. Configuration Control
19. Which of the following tasks is not part of Software Configuration Management (SCM)?
a. Change control
b. Version control
c. Configuration status reporting
d. None of the above
20. To pass an Exam, a candidate has to score minimum of 50 marks in order to clear the exam.
The maximum that he can score is 100 marks. Identify the Valid Equivalence values if the student
passes the exam.
a. 50, 58, 75
b. 49, 50, 51
c. 52, 60, 99
d. 0, 15, 50
21. Which of the following values for age are in the same Equivalence Partition?
- If you are less than 18, you are too young to be registered for program.
- Between 18 and 50 inclusive, you will receive a 20% discount.
- Anyone over 50 is not eligible for a discount.
a. 17, 18, 19
b. 51, 52, 53
c. 18, 49, 50
d. 17, 49, 51
22. Which of the following is / are the output of the Software Process?
a. Computer programs
b. Documents that describe the computer programs.
c. Data (contained within the program or external to it).
d. All of the above
a. Decreases
b. Increases
c. No effect
d. None of the above
26. _______ combines procedures and tools to manage different versions of configuration
objects that are created during the software process.
a. Baseline
b. Procedure
c. Audit
d. None of the above
28. What is the name of process which will ensure that different versions of system and its
components are recorded and maintained?
a. workspace
b. code control
c. versions
d. Configuration Control
29. Which of the following tasks is not part of Software Configuration Management (SCM)?
a. Change control
b. Version control
c. Configuration status reporting
d. None of the above
19
MG6088 Software Project
Management
30. If the Earned Value is equal to Actual Cost, it means
32. Which of the following types of Organizational Charts can be BEST used to track project
costs:
a. Hierarchical type Organizational Chart
b. Organizational Breakdown Structure
c. Resource Breakdown Structure
d. Responsibility Assignment Matrix
33. What kind of quality cost is incurred when an error is detected in a product prior to shipment?
a. Internal Failure
b. Prevention
c. Appraisal
d. External Failure
34. Ensuring that no more than the allocated number of people are allocated at any given time in
Software Scheduling is known as
a. Time Allocation
b. Defined Milestone
c. Effort Validation
d. Effort Distribution
35. Which of the following is not an effective software project management focus?
a. popularity
b. process
c. product
d. people
20
MG6088 Software Project
Management
37. David’s project metrics says that his project has SPI of .83 and CPI of 1.3. How can David’s
Project status BEST described?
a. Project is behind schedule and over budget
b. Project is behind schedule and under budget
c. Project is ahead of schedule and over budget
d. Project is ahead of schedule and under budget
38. A new project manager in your company is asked to make a report for a project where the
work is performed at the budgeted rate. He asks for your help and provide these values to you
BAC = $ 35,000, Earned value (EV) = $25,000, planned value (PV) = $24,000 and actual cost
(AC) = $ 28,000. What is the value of Estimate At Completion (EAC) ?
a. $ 38,000
b. $ 24,000
c. $ 37,000
d. $ 36,000
39. Which of the following is incorrect activity for the configuration management?
a. Version management
b. Change management
c. Internship management
d. System management
40. If the budget at completion is £19,000 and CPI is 1.86 what is Estimate at Completion EAC
a. £13500
b. £12,400
c. £13000
d. £10,215
UNIT V
3 intrinsic motivation refers to
(a)interest or enjoyment in the task itself
(b)Create a jobholderprofile
(c)ExamineCVsInterviews
(d)Valence Expectancy
21
MG6088 Software Project
Management
6 What are the factors that made the job meaningful?
(a) Intrinsic motivation
(b) Extrinsic motivation
(c) Skill Variety and Task Identity
(d)hygiene
7 Define Stress.
(a)psychological demands on a person such that an unusual
(b) out-of-the-ordinary response occurs.
(c) The circumstance – the stressor- can be a final exam, a financial problem, or a difficult
boss.
(d) all of the above
11.Define leadership.
(a)Leadership is the ability to influence others
(b)Leadership is the ability not to influence other
(c )Leadership is the ability to order other
(d)Leadership is the ability not to order other
22
MG6088 Software Project
Management
(b)worker’s collar stressors.
(c )blue-collar stressors
(d)black-collar stressors
20.Define Acceptance.
(a)to demonstrate that the expected quality has not achieved.
(b)to demonstrate that the expected quality has not been achieved.
23
MG6088 Software Project
Management
( c)to demonstrate that the expected quantity has been achieved.
( d)to demonstrate that the expected quantity has been not achieved.
27.In the work goal context the psychological factors stimulating the people’s behaviour can be
-
(a)desire formoney
(b)success
24
MG6088 Software Project
Management
(c) recognition
(d)All of the above
31.what are the measures to reduce the disadvantage of group Decision making?
(a)The cooperation of a number of experts
(b) The problem is presented to the experts.
(c) The experts record their recommendations.
(d)All of the above
26
MG6088 Software Project
Management
32. Which of the following risks are derived from the organizational environment
where the software is being developed?
a) People risks
b) Technology risks
c) Estimation risks
d) Organizational risks
33. Which of the following strategies means that the impact of the risk will be reduced?
a) Avoidance strategies
b) Minimization strategies
c) Contingency plans
d) All of the mentioned
34. Which of the following term is best defined by the statement: ―There will be a
change of organizational management with different priorities.‖?
a) Staff turnover
b) Technology change
c) Management change
d) Product competition
35. What assess the risk and your plans for risk mitigation and revise these when you
learn more about the risk?
a) Risk monitoring
b) Risk planning
c) Risk analysis
d) Risk identification
27
MG6088 Software Project
Management
b) organising, leading, planning, controlling
c) planning, organising, leading, controlling
d) planning, organising, controlling, leading
38. Positive motivation makes people willing to do their work in the best way they can
and improve their.
a) Productivity
b) Personality
c) Performance
d) All of the above
39. Return on investment(ROI) is calculated by
a) (Average Annual Profit*total investment)/100
b) (Average annual profit*100)/total investment
c) (100*Total investment)/Average annual profit
d) (1000*Total investment)/Average annual profit
40. In the abbrevation of SMART what does the letter M stands for
a) Marketing
b) Measurable
c) Milestone
d) Management
42. The process each manager follows during the life of a project is known as
a) Project Management
b) Manager life cycle
c) Project Management Life Cycle
d) All of the mentioned
28
MG6088 Software Project
Management
43. Which of the following is incorrect activity for the configuration management of
a software system?
a) Internship management
b) Change management
c) Version management
d) System management
48. Which of the following traits need to exist among the members of an agile software team?
a) Competence
b) Decision-making ability
c) Mutual trust and respect
d) All of the above
51. The formal methods model of software development makes use of mathematical
methods to
a) Define the specification for computer-based systems.
b) Develop defect free computer-based systems.
c) Verify the correctness of computer-based systems.
d) All of the above.
53. Agile modeling (AM) provides guidance to practitioner during which of these
software tasks?
a) Analysis and Design
b) Design and Coding
c) Coding and Testing
d) Testing and Maintenance
54. Which of the following is not necessary to apply agility to a software process?
a) Eliminate the use of project planning and testing
b) Only essential work products are produced
c) Process allows team to streamline tasks
d) Uses incremental product delivery strategy
55. What are the four framework activities found in the Extremen Programming (XP)
process model?
a) Analysis, design, coding, testing
b) Planning, analysis, design, coding
c) Planning, analysis, coding, testing
d) Planning, design, coding, testing
56. Which is not one of the key questions that is answered by each member at each
daily Scrum meeting?
a) What did you do since the last meeting?
b) What obstacles are you creating?
30
MG6088 Software Project
Management
c) What is the cause of the problem you are encountering?
d) What do you plan to accomplish be the next team meeting?
69. Which of the following is/ are main parameters that you should use when computing
the costs of a software development project?
a) Travel and training costs
b) Hardware and software costs
c) Effort costs
d) All of the above
32
MG6088 Software Project
Management
71. COCOMO was developed initially by
a) B.Beizer
b) Rajiv Gupta
c) B.W.Bohem
d) Gregg Rothermal
75. Which of the following is not an approach to identify the activities that make up a project
a) The activity-based approach,
b) The product-based approach
c) The non- hybrid approach.
d) The process-based approach
77. Which of the option is not a notable challenge while scheduling a project?
a) Deadlines exist.
b) Independent activities.
c) Too many workers may be required.
d) Costly delay
33
MG6088 Software Project
Management
b) Event
c) Activity
d) Contract.
81. Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish
times for the three activities are 12, 15, and 10, then the earliest start time for Y will be
a) 10
b) 15
c) 12
d) Cannot be determined
82. Activities P, Q and R instantly follow activity M, and their current start times are 12, 19,
and 10. Therefore, the latest finish time for activity M is
a) 11
b) 10
c) 18
d) Cannot be determined
85. A process of specifying the time for when each activity should take place
a) Scheduling
34
MG6088 Software Project
Management
b) Sequencing
c) Activity Plan
d) Project Plan
89. The difference between the earliest date and latest date for an event is
a) Free Float
b) Total Float
c) Slack
d) Float
92. An event that might occur and will create a problem for the successful completion of
the project, if it does occur.
a) Risks
b) Project Failure
35
MG6088 Software Project
Management c) Hazards
d) Threat
102. Using feasibility analysis it is necessary to examine several alternative solutions because
(i) a comparison of alternatives will lead to a cost-effective solution
(ii) a pre-conceived single solution may turn out to be unimplementable
(iii)it is always good to examine alternatives
(iv) management normally looks at alternatives
a) i and iii
b) i and iv
c) i and ii
d) ii and iv
105. Project managers have to assess the risks that may affect a project.
a) True
b) False
106. Which of the following is/are main parameters that you should use when
computing the costs of a software development project?
a) travel and training costs
b) hardware and software costs
c) effort costs (the costs of paying software engineers and managers)
d) All of the mentioned
37
MG6088 Software Project
Management
107. Which of the following is incorrect activity for the configuration
management of a software system?
a) Internship management
b) Change management
c) Version management
d) System management
109. An independent relationship must exist between the attribute that can be
measured and the external quality attribute.
a) True
b) False
117. Which of the following is not considered one of the four important elements that
should exist when a configuration management system is developed?
a) Component elements
b) human elements
c) process elements
d) Validation elements
118. Which configuration objects would not typically be found in the project database?
a) design specification
b) marketing data
c) Organizational structure Description
d) test plans
e) b and c
120. Which of the following task is not part of software configuration management?
a) Change control
b) reporting
c) Statistical quality control
d) Version control
121. Change management for web and mobile Apps is best handled in agile manner.
a) True
b) False
39
MG6088 Software Project
Management
122. Content management establishes a process which web content is rendered on the
user’s display screen
a) True
b) False
126. The following costs are not part of the total effort cost
a) Costs of lunch time food
b) Costs of providing heating
c) Costs of networking
d) Costs of support
40
MG6088 Software Project
Management
d) D.Floating Point
130. If Task A to complete,it takes 10 days of human effort.It started 5 days earlier to
the scheduled date and completed on 35th day.Then,the float value
a) A.20
b) B.25
c) C.10
d) D.15
131. Earned value Formula
a) percentage Pending*Total cost
b) Percentage Completed*Budget
c) Percentage Completed*Initial investment
d) Percentage Pending*Initial investment
135. Which of the following is not included in Hackman and Oldham’s job characteristics model
of work motivation?
a) Variety of skill
b) Significance of the task
c) Quality of job life
d) Autonomy
139. The study of organisation behaviour has certain basic assumptions. They are
a) An industrial enterprise is an organization of people.
b) These people must be motivated to work effectively.
c) The goals of the employee and the employer may not necessarily coincide.
d) All of the above.
141. Which of the following is not correct for the organisational behaviour?
a) Organisational behaviour is an integral part of management
b) Organisational behaviour is a disciplinary approach
c) Organisational behaviour helps in analysis of behavior
d) Organisational behaviour is goal-oriented
42
MG6088 Software Project
Management
143. Now a days a lot of stress is being put on the of the employee in
the organization
a) Character
b) improvement
c) Behaviour
d) Rewards
144. The purpose of job enrichment is to
a) expand the number of tasks an individual can do
b) increase job efficiency
c) increase job effectiveness
d) increase job satisfaction of middle management
147. Among the following which is not a problem in changing the attitude of the employee
a) Insufficient Information
b) Resistant by employee
c) Cognitive Dissonance
d) Cognitive Dissonance
153. Which of the following best defines the type of rewards that are distributed
toindividuals for their unique contribution to the team?
a) functional team rewards
b) competitive team rewards
c) cooperative team rewards
d) non-competitive team rewards
155. What is the ideal size of a team in order for it to be productive and successful?
a) 2 to 4
b) 9 to 12
c) 5 to 8
d) 8 to 11
156. Which of the following best defines an organization where decision making authority is
at the top of the organization and employees have little freedom to make their own
decisions?
a) decentralized organization
b) centralized organization
c) virtual organization
d) functional organization
162. On her work team Michelle develops detailed tasks lists and work flow charts to help
her team members understand the steps involved in each project. She also maintains
the project calendar and receives periodic updates from each team member to ensure
that projects are progressing on schedule. Which role does Michelle most likely fill on
her team?
a) assessor
b) organizer
c) maintainer
d) creator
45
www.rejinpaul.com
UNIT – I
8. The old control technique(s) which was (were) used through years is (are)
(A) unity of policies
(B) break-even analysis
(C) budgetary control
(D) All of the above
11. Costliness of the ________ is the overriding factor determining the extent of decentralization.
(A) Decision
(B) Staffing
(C) Both (A) and (B)
(D) None of the above
15. Derivation of principles of management is a matter of I)--------- and their application is a matter of -----
-----------ii)
16. Which of the following technique of scientific management has the objective to determine the number
of employed. Frame suitable incentive schemes and determine labour cost.
(A) Fatigue study
(B) Time Study
(C) Functional foremanship
(D) Simplification of work
17. --------------- involve a series of steps to be taken to accomplish desired goals. Principles are
guidelines to take decisions of actions while practicing
(A) Values
(B) Techniques
(C) Programmes
(D) Actions
20. Direction is a ________ function performed by all the managers at all levels of the organization.
(A) Managerial
(B) Organizational
(C) Both (A) and (B)
(D) None of the above
23. which of the following technique of scientific management is violation of unity of command.
(A) Motion study
(B) fatigue study
(C) functional foremanship
(D) Simplification of work
24. Fayol’s principle of division of work can be applied to following kind of work
(A) Technical
(B) Managerial
(C) Both
(D) None of these
28. Which Management spent more time on organizational and directional functions
(A) Top
(B) Middle
(C) Lower
(D) All the Above
29. Henry Fayol and F.W.Taylor belongs to which of the following school of management
(A) Classical
(B) Modern
(C) Early perspective
(D) None of the Above
30. ---------------- among the following was the first to identify four functions of management.
31. Authority is undermined, discipline is in jeopardy, order disturbed, and stability threatened?
(A) Unity of direction
(B) Discipline
(C) Unity of Command
(D) Stability of Personnel
33. Positive motivation makes people willing to do their work in the best way they can and improve their
________.
(A) Productivity
(B) Personality
(C) Performance
(D) All of the above
37.Management should find the best way to perform one task. Which technique of management is suitable
---------- to perform the task.
(A) Method Study
(B) Time Study
(C) Motion Study
(D) Fatigue study
39.Same battery can be used different mobile phones of a particular brand. This is an example of which of
the following techniques of Scientific Management?
(A) Standardisation
(B) simplification
(C) Method study
(D) Functional foremanship
41.Principle of division of work is applicable to a government office where there is a diary/dispatch clerk
whose job is to receive and send mail, a data entry operator whose task is to input data on the computer.
Division of work is also applicable to limited company where there are separate departments like
productions, finance , research and development etc
1. General Guidelines
2. Universal applicability
3. Flexible
4. Contigent
42. Employees deserve fair and just remuneration but what is just, and fair is determined by multiple factor.
They include contribution of the employee, paying capacity of the employer and prevailing wage rate for
the occupation under consideration.
1. General Guidelines
2. Universal applicability
3. Flexible
4. Contigent
43. Management principles increase managerial efficiency as manager leave routine decision making to
his subordinates and deal with exceptional situations which require his expertise by following the principle
of delegation
44. Even a small production activity like loading pigs of iron into boxcars can be scientifically planned and
managed.This can result in tremendous saving of human energy as well as wastage of time and materials
45. Principles of management do not provide readymade solution to any problem but in dealing with a
situation of conflict between two department, a manager may emphasize the primacy of the organization
goal.
Which quality of Pom is highlighted above?
1. General Guidelines
2. Universal applicability
3. Flexible
4. Contigent
UNIT – II
1.Planning involves............
(a) review of past performance
(b) setting objectives and determining course of action for achieving them
(c) analysis of policies
(d) All of these
3.Which of the planning is based on organization’s mission and is often carried out by top
management?
(a) Strategic planning
(b) Operational planning
(c) Tactical planning
(d) None of the above
5. Which plan is made once and retain their value over a period of years while undergoing periodic
revisions and updates?
(a) Operational plans
(b) Strategic plans
(c) Standing plans
(d) Single-use plans
6.According to knootz, which term is used to indicate end point of management programme?
(a) planning
(b) Strategy
(c) Policies
(d) Objective
13. ............... are goals established to guide the efforts of the company and each of its components
(a) objectives
(b) strategy
(c) policies
(d) procedure
18.Which strategy helps in identifying the internal and external factors for achieving the objective?
(a) BCG Matrix
(b) Porter’s Five force model
(c) Gap Analysis
(d) SWOT analysis
20.Which strategy is frequently used to identify an industry's structure to determine corporate strategy?
(a) Gap Analysis
(b) Porter’s Five force model
(c) Balance score card
(d) BCG Matrix
21.Among the porter’s five forces ,which one is involved in how much of profit the competitors are earning?
(a) Power of suppliers
(b) Power of customers
(c) Threat of substitute products
(d) Potential of new entrants into the industry
25.Which of the following is a planning techniques used for strategic management ………..
(a) Poster,s 5 Forces Competitive model
(b) Gap Analysis
(c) Balanced Score Card
(d) All the above
UNIT-III
3. Organizing destroys:
(a) individual relationships,
(b) plans,
(c) simplicity in the organization,
(d) environment.
7. The degree to which an organization relies on rules and procedures to direct the behaviour of
employees is:
(a) complexity,
(b) formalization,
(c) centralization,
(d) motivation.
9. Delegation is:
(a) a continuous process,
(b) unfolding talents,
(c) granting the right to command.
[Hint: Delegation is the act of granting of conferring something and the term authority means right to command.]
12. Indicate which of the following is NOT among the six main types of organization structure–
(a) Line organization
(b) Functional structure
(c) Committees
(d) Department
13. Organisattion structure is primarily concerned with and of tasks and authority.
(a) Allocation and Delegation
(b) Allocation and apportionment
(c) Reporting and delegating
(d) Setting standards and delegation
16. Organizational structure is made up of key elements. Which of the following is not one of these
elements?
(a) Centralisation
(b) Coordination
(c) Decentralisation
(d) Span of control
17. Staffing refers to:
(a) measuring performance,
(b) managing the positions,
(c) management in action,
(d) making strategic plans.
[Hint: Staffing refers to appointing the right person for the right job.]
25. Which of the following is not a function normally performed by the HR department?
(a) Recruitment and selection.
(b) Accounting.
(c) Training and development.
(d) Pay and reward.
31. Which of the following is not a type of remuneration system under Time Rate System?
(a) High wage plan
(b) Measured day work
(c) Taylor System
(d) Differential time rate.
32. Which of the following functions or activities requires recruiting and placing qualified
personnel needed for the organization so that it may achieve its objectives and goals?
(a) Planning
(b) Staffing
(c) Organizing
(d) Controlling.
36. As per Cartwright which of the following characteristics of a group is a means for overcoming
resistance to change
(a) Incentives
(b) Coercion
(c) Education
(d) Strong sense of belonging.
37. Organization structure deliberately created by the management for achieving the objectives
of the enterprise is called
(a) Product organization
(b) Functional organization
(c) Formal organization
(d) Informal organization
UNIT – IV
2. Marry Follett pointed that reform was possible provided the following consideration were taken into
account:
(a) building up new attitudes,
(b) planning
(c) negative attitudes,
(d) None of the above.
4. Direction is a:
(a) discrete process,
(b) continuous process,
(c) circular process,
(d) supervisory process
7. Communication is a:
(a) two-way process,
(b) one-way process,
(c) discrete process,
(d) circular process
[Hint: Communication is a transfer of information from one person to another and getting the feedback to check the
efficiency of the message communicated.]
18. Which of the three components are part of the human communication process?
(a) Message, noise, feedback
(b) Feedback, message, critiquing
(c) Noise, feedback, jargon
(d) Message, recording, feedback
23. When a subordinate or a lower level manager passes information or offers suggestions to the
higher level management, they are using which level of communication?
(a) Upward communication
(b) Downward communication
(c) Lateral communication
(d) Diagonal communication.
26. Leadership has a lot of characteristics and a leader must not maintain this trait in his
behaviour:
(a) coexistence,
(b) taking responsibility,
(c) avoiding responsibility,
(d) All of the above.
29. Another contingency model of leadership is the path-goal theory. This suggests that subordinates
will see leadership behaviour as a motivating influence if:
(a) path-goal relationships are clarified.
(b) their effective performance will satisfy their needs.
(c) the necessary direction, guidance, training and support is provided.
(d) all the above.
30. When determining the most appropriate form of leadership, which of the following should be
considered?
(a) The manager.
(b) The work environment.
(c) The group.
(d) All the above.
34. Which of the following statements is false about the behavioral theories of leadership?
(a) Consideration is a people-oriented dimension of leadership behavior
(b) Production-centered leader behavior focuses on tasks and has little concern for people
(c) Leaders high in initiating structure do not set deadlines or make individual task assignments
(d) Employee-centered leader behavior focuses on people and the quality of the social system.
36. Maslow suggests that human needs are arranged in a series of levels, a hierarchy of importance.
Which of the following statements are relevant to Maslow's hierarchy of needs theory?
(a) The hierarchy is not necessarily in a fixed order.
(b) A satisfied need is no longer a motivator.
(c) A need is not necessarily fully satisfied before a subsequent need arises.
(d) All of the above.
37. According to Herzberg, which of the following may be regarded as hygiene/maintenance factors?
(a) Sense of achievement.
(b) Recognition.
(c) Personal growth and advancement.
(d) None of the above.
38. Which of the following statements is true about the goal theory of motivation?
(a) People with easier goals will perform better than people with difficult goals.
(b) A person's level of commitment to a goal will not regulate the level of effort expended.
(c) People with difficult goals will perform better than people with easier goals.
(d) Research has shown that there is little support for the goal theory and its effects on motivation with
regard to the relationship between goal-setting and performance.
39. Douglas McGregor's view that suggests that employees will exercise self-direction and self-control
when they are committed to the objectives of the work is called:
(a) Theory B
(b) Theory X
(c) Theory Y
(d) Theory A
40. Which step in Maslow's Hierarchy of Needs Theory deals with achieving one's potential?
(a) Esteem
(b) Physiological
(c) Self-actualization
(d) Social
42. Who proposed that achievement, affiliation and power are three important needs that help explain
motivation in workplace situations?
(a) McClelland
(b) Herzberg
(c) Alderfer
(d) Maslow
43. Company policy, administration, supervision, interpersonal relations, working conditions, and
salary are characterized as:
(a) Achievement factors
(b) Growth factors
(c) Motivating factors
(d) Hygiene factors
44. An employee's experiences in a situation or position outside his or her current organization is a
referent comparison called:
(a) Self-outside
(b) Other-inside
(c) Other-outside
(d) Self-inside
social needs.
(a) Kurt Lewin’s
(b) Douglas McGregor’s.
(c) Elton Mayo’s
(d) Chris Argyris’s
49. proposed by Douglas McGregors has a positive, dynamic, flexible and optimistic
view of employees.
(a) Theory W
(b) Theory X
(c) Theory Y
(d) Theory Z
UNIT – V
1. What is the management function that involves monitoring activities to ensure that they’re being
accomplished as planned and correcting any significant deviations.
(a) Control
(b) Planning
(c) Organising
(d) Directing
4. By starting the budget of each package from base zero, budgeters calculate costs afresh for each
budget period is called as ………………………..
(a) Cash Budget
(b) Variable Budget
(c) Captial Expenditure Budget
(d) Zero Based Budget
7. Expand MIS?
a) Management Interactive session
b) Management Information system
c) Message Information system
d) Managers Information system
17. _________ refers to the technical process of gathering, examining, and analyzing the project
(e) Cost control
(f) Maintenance control
(g) Quality control
(h) Functional control
19. What should be made and the cost of reporting should commensurate with the expenditure
involved?
(e) Cost benefit analysis
(f) Flexibility
(g) Controllability
(h) Principle of exception
3. A stage in which individual components are integrated and ensured that they are error-free to
meet customer requirements.
a) Coding
b) Testing
c) Design
d) Implementation
5. The customer requirements are broken down into logical modules for ease of
_______________
a) inheritance
b) design
c) editing
d) implementation
6. What do you call a technical person who is capable of understanding the basic requirements?
a) team leader
b) analyst
c) engineer
d) stakeholder
7. A step in waterfall model that involves a meeting with the customer to understand the
requirements.
a) Requirement Gathering
b) SRS
c) Implementation
d) Customer review
10. A planned program if work that requires a definitive amount of time, effort and planning to
complete.
a) Problem
b) Project
c) Process
d) Program
MCQ Questions
1. Motivation
2. Resource allocation
3. Plan to mitigate
4. Feasibility assessment
5. Delivery on time
a. 1,2,3,4,5
b. 1,2,4
c. 1,2,4,5
d. 3,4,5
a. Maximum time
c. Acceptable cost
d. impose constrains
3. The following are the steps in creating a project schedule, arrange them in
order
b. an requires resources
7. The different levels used in work break down structure is given arrange
according their levels in order.
a. activity
b. project
c. schedule
d. sequencing
d. does not represent the possible start and possible end activities
b. does not represent the possible start and completion of the activity
11. what are the rules for constructing the precedence networks.
a. should have multiple start node
2. it will not start at the same time and will not end at the same time
a. 1,3,4
b. 2,4
c. 1,2,3,4
d. 3,4
13. The project specification with estimated activity durations and precedence
requirements are given below
C Install hardware 5 A
D Data migration 9 B
a. 11, 14
b. 7,10
c. 12, 14,
d. 8,10
14. From the above Table in Q no (13) calculate the forward pass and identify
the value for earliest finish and latest finish for activity H.
a. 17,19
b. 19,19
c. 15,15
d. 11,14
15. From the above Table in Q no (13) calculate in the backward pass and
identify the value for earliest start and latest start for activity G.
a. 15,15
b. 11, 14
c, 13, 15
d. 12, 14
16. From the above Table in Q no (13) calculate in the backward pass and
identify the value for earliest start and latest start for activity D.
a. 6,9
b, 6,5
c. 6,6
d. 8,10
16. From the above Table in Q no (13) find the critical path
a. F-G
b. B,D,H
C. B, E, G
A,C,H
17. From the above Table in Q no (13) find the total float for the activity H.
a.1
b.2
c.3
d. 0
18. From the above Table in Q no (13) find the total float for the activity C
a.1
b.2
c.3
d. 0
19. From the above Table in Q no (13) find the total float for the activity E
a.1
b.2
c.3
d. 0
b. difference between the earliest completion date and earliest start date for
succeeding activity.
c. difference between the earliest completion date and earliest start date for
preceding activity.
d. difference between the latest completion date and latest start date for
preceding activity.
a. 1,2,3
b. 2,3,4
c. 1,3,4
d. 1,2,3,4
1. Structure
2. Tasks
3. Checklist
4. Brain storming
a. 1,2
b. 1,3
c. 2,4
d. 3,4
2. Team building
4. Protyping
a. 1,2
b. 2,3
c. 1,2,3,4
d. 2,3,4
24. The risk due to developing the wrong user interface consist of
1.task analysis
2. Design to cost
a. 1,3
b. 2,4
c. 3,4
d. 1,4
a. 200
b. 2000
c. 20000
d. 200000
27. what is the range value for the qualitative descriptors of risk probability with
moderate.
a. > 50 %
b. 30-50%
c. 10-29%
d. <10%
28. what is the associated range value for the qualitative descriptors of impact
on cost for significant impact level.
a. > 30 %
b. 20-29%
c. 10-19%
d. <10%
a. risk avoidance, risk reduction and mitigation, risk transfer, risk acceptance
b. risk reduction and mitigation, risk transfer, risk acceptance, risk avoidance
c. risk transfer, risk acceptance, risk avoidance, risk reduction and mitigation,
d. risk acceptance, risk avoidance, risk reduction and mitigation, risk transfer
30. What are the four commercial off-the-shelf software acquisition risks.
d. Risk acceptance, activities may be prone, reduce the risk probability, risk
transfer.
31. Find the risk reduction leverage if the risk evaluation before is 1% of the
total cost Rs, 2,00,000 and risk evaluation after is 0.5% of the total cost if fire
accident happens. And the total cost to fit the fire alarm is Rs. 1000.
a. 1
b. 2
c. 4
d. 8
time
A ---- 9 7 8
B ---- 8 4 3
C A 7 3 2
D B 6 4 5
E B 5 3 4
F --- 10 8 15
G E,F 5 3 4
H C,D 4 2 3
a. 4
b. 5
c. 6
d. 7
34. From question number 33 , calculate the Standard deviation for activity E
and H
a. 1/3 , 2/3
b. 1/3, 4/3
c. 1/3, 1/3
d. 2/3, 2/3
35. from question number , calculate the Standard deviation for activity A and B
a. 1/3 , 2/3
b. 1/3, 4/3
c. 2/3, 1/3
d. 2/3, 2/3
a. A,C,H
b. B,D,H
c. F,G
d. B,E,G
a. 1/3
b. 2/3
c. 4/3
d. 5/3
38. Why we go for Monte carlo simulation
a. 1,2,3
b, 1, 4
c. 2, 3, 4
d, 2,3
39.The steps of Monte carlo simulation are given arrange them in order.
b. generate the random inputs, Evaluate the project completion time, analyse the
result, Express the project completion time.
c. Evaluate the project completion time, analyse the result, Express the project
completion time, generate the random inputs,
d. Analyse the result, Express the project completion time, generate the random
inputs, Evaluate the project completion time,
Function
3. ------------are used to measure effectiveness of the project. Check point Review point None of the above 3
Point
Change
Which is provided an efficient way of storing Configuration Management Open source
10. Control None of the above 3
versions that minimize the amount of occupied disk space? Process configuration tool
Board
What are the different types of contract based on payment?
a. Fixed Price Contracts
11. a b c All of the above 4
b. Time and Materials Contracts
c. Fixed Price per Delivered Unit
Supplier will increase price to meet contingencies is a Fixed Price Per
12. Time and Material Fixed Price None of the above 2
disadvantages of ----------------------- contracts. Delivered unit
Size and
13. What are the two factors used to progress of project? Size and Degree of the Risk
Accuracy
Size and Time None of the above 1
14.
What is/are the ways used to reporting? Oral and Written
Formal and
Regular and Adhoc All of the above 4
Informal
A------------- is a unit of measurement to express the
Review
15. amount of business functionality an information system Check Points
Points functional point None of the above 3
provides to a user
The ______has overall the responsibility for setting, project steering team
16. team member project manager 3
monitoring and modifying objectives of the project. committee manager
The ______ covers the planning stages of a project and not PRINCE project ISO 9001 project
17. Stepwise project planning PRINCE2 1
monitoring and control. planning planning
A _____ is likely to have very high priority for close activity with free
18. critical path activity activity activity with float 1
monitoring. float
In a project team, the ________are skilled at creating a monitor-
19. chair sharper team worker 4
good working environment. evaluator
In a project team, the ________is a good team player who
monitor-
20. is willing to undertake less attractive tasks if they were Company Worker Team worker Complete finisher 1
evaluator
needed for team success.
The ______ chart need to be redrawn each time when
21. Ball Slip Timeline Pie 1
target dates are revised.
In Gantt chart, ______ provides an immediate visual
22. indication of which activities are ahead or behind the Cursor Indicator Today cursor pointer 3
schedule.
Risk
23. Traffic light method is used for _______. Risk reporting
mitigation
Risk contingency Risk transfer 1
Control
The organization as part of its monitoring and control
policy may have a ________ programme in place which
27. measurement system software testing
dictates that certain statistics have to be collected at
various stages of a project.
A -------- is a unit of measurement to express the amount of
28. business functionality an information system provides to a functional point Control point Review point None of the above 1
user
Reflect
scope Review,
changes evaluates,
in and approve/di
Change management systems are designed to Track all changes that baseline
29. accomplish all of the following except: sapprove
are to be implemented and All of the above 4
proposed
performan changes
ce formally
measures