2021 MWT Annual Sector Performance Report Final 2019-2020
2021 MWT Annual Sector Performance Report Final 2019-2020
2021 MWT Annual Sector Performance Report Final 2019-2020
MINISTRY OF WORKS
AND TRANSPORT
ANNUAL SECTOR
PERFORMANCE REPORT
FY2019/20
FOREWORD
I hereby present the Annual Performance Report (ASPR) for the Department for the Works
and Transport Sector for Financial Year 2019/20. The report highlights both the financial
and physical performance as well as challenges faced by the Sector during the financial year
2019/20. The report provides an opportunity to stakeholders to reflect on performance of the
Sector and to learn from what has not been done well and what may need to be addressed so
as to achieve the set targets in the future.
During the Financial Year, the sector registered improved performances in the different
subsectors. For example, under the road subsector, national road network in fair to good
condition was 84% for paved roads and 77% for unpaved roads against the NDPII target of
82% and 66% respectively.
The Air subsector was the most affected by the COVID-19 Pandemic. However, prior to the
closure of the airports due to COVID-19 Pandemic, passenger transits and revenue collections
from Uganda Airlines Company Limited were steadily increasing. The number of passengers
had reached 77,355 while the revenue collected from the passengers had reached UG.Shs
26.668Bn between August 19th 2019 and 20th March 2020. The airline acquired the last batch
(2 No.) of the CRJ900 aircrafts. The overall progress on the expansion and modernization of
Entebbe International Airport was at 73% while construction works for the development of
Kabaale International Airport in Hoima district was at 42.7% against a target of 50%.
Overall, the sector attained at least 80% on more than half of the Sector performance targets
as measured against the Sector Golden indicators. The performance was generally affected
by the lock down occasioned by the COVID-19 Pandemic and lack of an adequate budget to
implement the planned outputs.
Lastly, on the behalf of the Government of Uganda, I express gratitude to the Development
Partners, Civil Society Organizations and the Private Sector for the support extended to the
Sector during the previous Financial Year. I thank all the staff for the work done during the
Financial Year 2019/20.
EXECUTIVE SUMMARY
Introdution
This Annual Sector Performance Report (ASPR) provides a record of the overall Works
&Transport Sector performance for the financial year 2019/20. It gives a management record
of the sector progress towards achieving the Ministerial Policy statement for the FY 2019/20.
It also highlights the key sector indicator measurement and analysis for FY 2019/20 and the
performance trend of key sector indicators over the last six years. It further enumerates
the key challenges affecting performance in the sector. The key indicators measured include
the Golden Indicators which were agreed within the sector for results-based management,
the Government Annual Performance Report (GAPR) Indicators and the implementation
progress on 15th Joint Transport Sector Action Matrix.
Financial Performance
In the Financial Year 2019/20, the approved budget for the sector was UGX 6,126.668 Bn
representing 14.61% of the national Budget. UGX 622.97 Bn (10.17%) was for recurrent
expenditure and UGX 5503.684 Bn (89.83%) was for development expenditure. The Government
of Uganda contribution was UGX 3294.327bn representing 55.77%. The Development
partners contributed UGX 2,832.341 Bn representing 46.23%. Budget performance release
was UGX 4528.592Bn (73.92%). The big drop in the release was in the external financing
which was 48.5% for Ministry of Works and Transport and 37.28% for UNRA respectively.
This was due the low performance level for external financing under Multinational Lake
Victoria Maritime Communication and Transport, Development of new Kampala Port in
Bukasa and Development of Kabaale Airport under Ministry of Works and Transport due
to the lengthy procurement process for the boats, RAP implementation challenges and the
Covid 19 pandemic that affected project progress respectively. While for UNRA it was due
to MoFPED’s delay in finalizing the financing (loan) negotiations with China Exim Bank and
subsequent approval by Parliament. Therefore, UGX 717.5Bn which had been appropriated
to the Critical Oil roads was not made available to UNRA by the end of the year and UGX 325
billion which was allocated by MoFPED and appropriated to Kampala-Jinja Expressway was
not released because the project was still under preparation.
Road Transport
The road network in Uganda comprise of the National Roads, District Roads, Urban Roads
and Community Access
Access Roads.
Roads.As In per
the June
financial
2020year 2019/20,
the total UNRA
national roadcompleted studies
network was and
…..Kms
designs of 46 projects.
of which……Kms wereFY 2019/20,
National rehabilitation
Roads,…….Kms of 313 roads,
District Km of …….Kms
the national roads
Urban continued
roads and ……
on
Kmsseven (7) road projects
are Community andRoads.
Access a totalOf
of 167.1 Km-Equivalent
the total was achieved
national roads,….Kms (..%)out
are of the targeted
paved AS PER
200
june Km-Equivalent thisinrepresents
2020. The increase a performance
the stock of paved nationallevel
roadofnetwork
83.6% compared
in the last to 66% inyear
financial the
FY
was2018/19.
427.5 Kms.At the end of the FY 2019/20, four (4) road rehabilitation projects totaling 146
Km were substantially completed. There are currently 24 road upgrading projects (new
In the financial year 2019/20, UNRA completed studies and designs of 46 projects. FY
construction and upgrading to paved bituminous standards) covering a total length of 1,692
2019/20, rehabilitation of 313 Km of the national roads continued on seven (7) road projects
Km. Six projects were substantially completed by the end of the FY, adding 427.5 Km to
and a total of 167.1 Km-Equivalent was achieved out of the targeted 200 Km-Equivalent
this represents a performance level of 83.6% compared to 66% in the FY 2018/19. At the end
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
5
v
the paved
of the road network.
FY 2019/20, four (4)UNRA carried out maintenance
road rehabilitation activities
projects totaling 146 Km on were
the road network
substantially
and achieved
completed. theare
There following
currently against theupgrading
24 road targets. Routine
projects maintenance
(new constructionof the
and paved roads
upgrading
5,117.8km was achieved
to paved bituminous against acovering
standards) target of a4,791Km representing
total length of 1,692aKm.performance
Six projectsof 107%,
were
routine maintenance
substantially completedof un
bypaved roads27,886kms
the end was 427.5
of the FY, adding achieved
Kmagainst a targetroad
to the paved of 21,275kms
network.
representing
UNRA carried a performance
out maintenance of 131%. Sevenon
activities (07)
thebridges were substantially
road network and achieved completed.
the following
against the targets. Routine maintenance of the paved roads 5,117.8km was achieved against
The Ministry was able to gravel 281.98km out of a target of 669.8km due to limited funding
a target of 4,791Km representing a performance of 107%, routine maintenance of un paved
and not being able to council out of a target of 16 kms. The Ministry was also able to work
roads27,886kms was achieved against a target of 21,275kms representing a performance of
on 14 bridges and five bridges were substantially completed. 687.4km rehabilitation works
131%. Seven (07) bridges were substantially completed.
of Inter-connectivity roads were achieved out of a target of 1050 km in the selected districts.
This was due to
The Ministry waslimited funding.
able to gravel 281.98km out of a target of 669.8km due to limited funding
and not being able to council out of a target of 16 kms. The Ministry was also able to work
Kampala city comprise of 2,110km of which 626.05km (29.7%) are paved and 1483.95 km are
on 14 bridges and five bridges were substantially completed. 687.4km rehabilitation works
unpaved. In Fy 2019/20 KCCA was able to complete paving 10.05km using GOU funding.
of Inter-connectivity roads were achieved out of a target of 1050 km in the selected districts.
The KCCA paved road network in good to fair condition was 63% against a target of 62%
This was due to limited funding.
while the unpaved network in good to fair condition was at 74% against a target of 75%.
Kampala city comprise of 2,110km of which 626.05km (29.7%) are paved and 1483.95 km are
The fatality rate in Uganda has been high and is one of the highest in the sub- Sahara Africa.
unpaved. In Fy 2019/20 KCCA was able to complete paving 10.05km using GOU funding.
The fatalities in the financial year were 3,881 as compared to 3,194 in the financial year
The KCCA paved road network in good to fair condition was 63% against a target of 62%
2019/20. This means on average 10 people die daily in road accident
while the unpaved network in good to fair condition was at 74% against a target of 75%.
The fatality rate in Uganda has been high and is one of the highest in the sub- Sahara Africa.
Air
The Transport
fatalities in the financial year were 3,881 as compared to 3,194 in the financial year
2019/20. This means on average 10 people die daily in road accident
The Government under took major development projects in air transport. The two key proj-
ects are the expansion of Entebbe International Airport which was at 73% level overall prog-
ress at the end of the FY 2019/20 as compared to 67.5% in the FY2018/19. The Kabala Airport
Air Transport
in Hoima was at 42.7% level of progress against a target of 50% due to the effects of COVID
TheOther
19. Government
projectsunder tookunder
were also majortaken
development projects
at different in airairports.
regional transport. Thefinancial
In the two key proj-
year
ectscraft
air are the
andexpansion
passengerofmovement,
Entebbe International
domestic andAirport which was
International at 73% level
passengers overalldue
declined prog-
to
ressclosure
the at the end of the
of the FY 2019/20
Entebbe as compared
International to 67.5%
airport in theof
as a result FY2018/19.
COVID 19.The TheKabala Airport
international
in Hoima was
passenger at 42.7%
movement level offrom
declined progress against
1,728,779 a target ofin50%
passengers due to the
FY2018/19 to 1,effects
355,772of passen-
COVID
19. Other
gers projects were also under taken at different regional airports. In the financial year
in FY2019/20.
air craft and passenger movement, domestic and International passengers declined due to
the closure of the Entebbe International airport as a result of COVID 19. The international
Railway transportdeclined from 1,728,779 passengers in FY2018/19 to 1, 355,772 passen-
passenger movement
gers in FY2019/20.
Railway Transport sector recorded an improvement in operations compared to the passengers
carried hit a number of 488,951 despite the closure due to Covid 19, the freight carried
improved from 3.735 million-tonne-km Line the FY2018/19 to 40.172 million-tonne-km in FY
Railway transport
2019/20. The Government of Uganda acquired a loan from European Union in addition to the
Railway Transport
co-funding of GoU sector recorded
to repair an improvement
the meter Guage railway infrom
operations
Tororocompared to the passengers
to Gulu which is expected
carried
to hit afurther
improve number its of 488,951 despite
performance. the closure of
Implementation due
thetopre-construction
Covid 19, the freight carried
activities e.g.
improved from
acquisition 3.735
of the million-tonne-km
Right Line continued
of Way for the SGR the FY2018/19
duringto 40.172
the FY,million-tonne-km in FY
albeit at a slow pace.
2019/20. The Government of Uganda acquired a loan from European Union in addition to the
co-funding of GoU to repair the meter Guage railway from Tororo to Gulu which is expected
In Land Water
to improve furtherTransport
its performance. Implementation of the pre-construction activities e.g.
acquisition of the Right of Way for the SGR continued during the FY, albeit at a slow pace.
Achievements under development of new Kampala Port in Bukasa where; the Environmental
and Social Impact Assessment (ESIA) and the Resettlement Action Plan for Project Affected
Persons (PAPs) were completed. 1,149 PAP’s of the project had been compensated by the end
6
vi ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
of the FY2019/20. Under Maritime, the inception report of the Maritime search and Rescue
Policy had been development and submitted. Registering and licensing of water vessels and
In Land Water Transport
the establishment of the marine training institute where also done.
Achievements under development of new Kampala Port in Bukasa where; the Environmental
and Social Impact Assessment (ESIA) and the Resettlement Action Plan for Project Affected
Conclusion
Persons (PAPs) were completed. 1,149 PAP’s of the project had been compensated by the end
of the FY2019/20. Under Maritime, the inception report of the Maritime search and Rescue
Most of the key sector indicator targets were met or nearly met despite the challenges of the
Policy had been development and submitted. Registering and licensing of water vessels and
impact of the COVID 19 pandemic and limited funding.
the establishment of the marine training institute where also done.
Conclusion
Most of the key sector indicator targets were met or nearly met despite the challenges of the
impact of the COVID 19 pandemic and limited funding.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
vii
Table of Contents
LIST OF FIGURES
Figure 2: Condition of Paved National Road Network over the years ........................................ 46
Figure 3: Condition of the Unpaved National Road Network over the years ........................... 46
Figure 5: Showing the Annual increment in stock of paved national road network ............. 49
Figure 6:Funding requirement vis-a vis amount provided for road maintenance...................55
FIGURE 13: GRAPH SHOWING THE FINANCIAL PERFORMANCE OF AGENCIES ......... 109
LIST OF TABLES
Table 1: Ministry of Works and Transport, institutions, Agencies and their mandates .......... 9
Table 7 : Overview of Vote016 (Ministry of Works and Transport Expenditures (UShs Bil-
lion) .................................................................................................................................................................... 31
Table 12: Condition of the National Road Network (June 2020) ................................................... 46
Table 13: Substantially Completed Upgrading Road Projects (as at 30th June 2020) ............. 49
Table 14: Annual Increment in Stock Paved National Road Network. ........................................ 50
Table 15: Road Construction and Rehabilitation Cost (UGX Bn) ....................................................53
Table 16: Average cost of road construction over the years (UGX Bn) .........................................54
Table 19: Funding requirement vis-à-vis amount provided for road maintenance over the
years (UGX Bn) ...............................................................................................................................................56
Table 21: proportion of expenditure on road maintenance, relative to the overall budget
from FY 2014/15 to FY 2019/20 ...............................................................................................................57
Table 25: Road projects were Green Right of Way was done ......................................................... 60
Table 29: Bridges substantially completed in the past three Financial Years FY 2017/18 – FY
2019/20 ............................................................................................................................................................63
Table 30: Ferry crossing along the national road network ............................................................. 64
Table 33: Completed Studies and Designs for Road Projects ...........................................................66
Table 44: Progress of CAA Major Projects at Entebbe International Airport By June 2020 76
Table 45: Progress Other Projects at Entebbe International Airport as at the End of
June2020 .........................................................................................................................................................77
Table 46: Status of Progress of UCAA Projects at Upcountry Airport as at the end of June,
2020 ..................................................................................................................................................................77
Table 58: Road Maintenance Unit Costs in the period FY 2018/19 – FY 2019/20 ................. 100
TABLE 66: SUMMARY OF FUNDS INFLOW TO VOTE 118, FY 2019/20 ............................... 106
TABLE 67: PERFORMANCE ON KPIS FOR FUNDS INFLOW, FY 2019/20 ........................... 106
TABLE 70: PROGRESS OF URF ON THE 15TH JTSR ACTION PLAN MATRIX ....................... 111
TABLE 71: Global allocation of funds, fy 2020/2021 ...................................................................... 112
Table 74: showing the physical performance of the RTI projects in FY 2019/20 ................... 117
Table 76: Road improvement works under ongoing contracts in the reporting period FY
2019/2020 .....................................................................................................................................................122
Table 82: Showing Monthly Passenger Numbers and Number of flights .................................133
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
xv
LIST OF ABBREVIATIONS
Isimba Bridge
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
1
1.0 INTRODUCTION
It is an institutional requirement for the Sector to compile its Annual Sector Performance
Report (ASPR) highlighting progress achieved, challenges, lessons learnt and proposals
of moving the Sector forward in relation to the National Development Plan (NDP)II, the
National Transport Master Plan including the Transport Master Plan for Greater Kampala
Metropolitan Area (2008 -2023), Agreed Action Matrix of the JTSR for the FY 2019/2020
and the Works and Transport Sector Development Plan (WTSDP) 2015/16 -2019/20. The FY
2019/20 report is the tenth ASPR produced by the Works and Transport Sector since the
Sector adopted a new M&E framework in 2011 and also the fifth annual report within the
framework of the WTSDP. The Report primarily focuses on the progress in implementation
of the annual work plans of the Ministry of Works & Transport and its Agencies against
output targets set for the FY 2019/20 across the Sector; as well as progress made in the
implementation of key actions agreed upon during the previous Sector performance retreat.
The Report aims at providing stakeholders with an account of the performance in the delivery
of Sector programmes and projects. It provides information on financial and the physical
performance measured against agreed upon performance indicators. The information
provided in this report shall inform policy and programmatic decisions; and hold the Works
and Transport Sector accountable for utilization of resources. The report will also guide
the decision-making process on resource allocations for the coming FY. The Department
of Policy and Planning in the Ministry of Works and Transport led the preparations of the
FY 2019/20 ASPR with participation from affiliated agencies viz UNRA, UCAA, URC, URF,
KCCA and UACL
The Report comprises twelve chapters. The first four chapters include an introduction
about the Report; an overview of the Sector; legal and guiding policy framework of the
sector through which the Sector implements its mandate and Performance on policies and
strategies. The next eight chapters detail the performance of the sector (MoWT, UNRA,
UCAA, URC, URF, KCCA, UACL and Vote 500-Local Government)
2 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
2.1 PREAMBLE
The Sector exists to promote the cost effective, efficient, safe and environmentally friendly
transport services to support increased agricultural and industrial production, trade, tourism
and social and administrative services. The Sector plays a critical role in the development of
an integrated and self-sustaining economy, poverty eradication and the economic integration
of the country as a whole.
The Sector being a propeller for socio-economic development of any country with its
significant positive effects on other Sectors of the economy; particularly the development
of the private Sector as an engine of growth. To achieve the goals, systems must operate
efficiently so that activities, operations and movements are conducted in a timely manner.
2.2.1 VISION
2.2.2 MISSION
To promote adequate, safe and well-maintained Works and Transport Infrastructure and
Services for Social Economic Development of Uganda.
2.2.3 MANDATE
i. Plan, develop and maintain an economic, efficient and effective transport infrastruc-
ture;
ii. Plan, develop and maintain economic, efficient and effective transport services by road,
rail, water and air;
iii. Manage public works including government structures and;
iv. Promote good standards in the construction industry
These are:
The Ministry of Works and Transport is the head of the Sector which also comprises affiliated
institutions established by Acts of Parliament and statutes including: Uganda National Roads
Authority (UNRA), Uganda Railways Corporation (URC), Uganda Road Fund (URF); and
Uganda Civil Aviation Authority (UCAA). Other affiliated institutions of the Sector include
the East African Civil Aviation Academy (EACAA), Mount Elgon Labour based Technology
(MELTEC), Ministry of Local Government (MoLG), Engineers Registration Board (ERB),
Kampala Capital City Authority (KCCA), National Building Review Board (NBRB) and Uganda
National Airlines Company Ltd (UNACoL). See table 1
The mandates of the Ministry of Works and Transport, and its affiliated institutions is
shown in Table 1.
Table 1: Ministry of Works and Transport, institutions, Agencies and their mandates
No Institution Responsibility
Uganda National Plan, Develop and Maintain the National Roads network; and
2
Roads Authority axle load control.
Uganda Civil Plan, Develop and maintain airports and regulate the air
3
Aviation Authority transport sub-Sector.
Uganda Railways Plan, Develop and Manage Rail and Marine transport, and
4
Corporation regulate the rail transport sub-Sector.
Road transport is the most dominant mode carrying 96.5 % and 95 % of freight cargo and
passenger traffic respectively. As at 2019, the Country has a total road network of 159,364
km which comprise of 20,854 km of National Roads; 38,603 km of District Roads; 19,959km
of Urban Roads and 79,947 km of Community Access Roads. Overall, only 6,107km (3.83%) is
paved and for district roads only 106.5 km (0.28%) is paved while for urban roads, 1229.7 km
(6.16%) is paved.
The cheapest form of land transport worldwide is railway transport and in Uganda, currently
325km of the MGR are operational out of the 1,266km representing 25.6% of the rail network.
The rest of the rail network is closed largely because of dilapidation. The railway network is
as indicated in the Table 3 and the operational lines are as indicated in Table 4.
The SGR is intended to comprise of 1,724km of railway network which will be developed in
a phased manner starting with the Eastern route: Malabe-Kampala 273km, Nothern route:
Tororo-Gulu-Nimule/Gulu-Pakwach-Vula 751km (South Su dan and Democratic Republic
of Congo). The western route which covers Kampala-Bihanga/Mirama Hills/Bihanga-
Kasese-Mpondwe 662Km (Rwanda and Democratic Republic of Congo). Currently it’s in
the preliminary stages of development i.e land acquisition, capacity building and resource
mobilization
2.7.1 AIRPORTS
Ministry of Works and Transport operates the East African Civil Aviation Academy (EACAA)
for pilot training and aircraft maintenance engineers. There are also private pilot training
facilities such as Vine Air Academy at Jinja Airport.
The Uganda Airlines Company Ltd was founded on 30th January 2019. The aim of the
company is to enhance the countries competitiveness by reducing the cost of air transport
and easing connectivity to and fro Uganda, Support faster harnessing opportunities in the
economy, e.g. Oil and gas, agriculture, tourism, etc. Its headquarters are located in Entebbe,
Wakiso district. As of January, 2020 it was going to nine cities (Bujumbura, Mombasa,
Nairobi, Mogadishu, Juba, Dar es Salaam, Kilimanjaro, Zanzibar and Entebbe) all around the
East African Community.
Uganda’s surface area consists of about 18% lakes, rivers or swamps. The water transport
system is still dominated by the “informal Sector” characterised by of small motorized and
non-motorized boats transporting goods and passengers. The principal lake and river system
includes Lake Victoria, Lake Kyoga, Lake Albert and Lake George, together with River Kagera,
the Victoria Nile and the Albert Nile. Transport on Uganda’s water comprises mainly: wagon
ferry services on Lake Victoria; Short distance road vehicle ferries acting as ‘road bridges’;
and Informal Sector operations by individual canoes.
URC manages and operates wagon ferries on the water ways which primarily carry cargo;
MoWT manages MV Kalangala which it leases out to private operators and UNRA managing
and operating about 10 ferries at Kiyindi, Mbulamuti, Masindi Port, Laropi, Obongi, Kyoga 1,
Kyoga 2, Nakiwogo and Bisina. Uganda Wildlife Authority also manages and operates vessels
on Lake Kyoga, Lake Albert & the River Nile.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
7
Kibembe footbridge
8 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
The legal framework under which the sector took interventions comprises the following
laws;
The sector planning framework is guided by the follow plans the Uganda Vision 2040;
the National Development Plan II (2015/16 -2019/20); the National Transport Master Plan
including the Transport Master Plan for Greater Kampala Metropolitan Area (2008 -2023)
and the Works and Transport Sector Development Plan (2015/16 -2019/20).
Uganda Vision 2040 provides the development paths and strategies to operationalize
Uganda’s Vision statement which is “A Transformed Ugandan Society from a Peasant to a
Modern and Prosperous Country within 30 years” as approved by Cabinet in 2007. It aims at
transforming Uganda from a predominantly peasant and low income country to a competitive
upper middle income country
The National Development Plan (NDPII) is the development planning framework for the
GoU for the period 2015/16–2019/20. It highlights the strategic agenda for development and
further details priority interventions in all sectors of the economy. The overall goal of NDP
II is to attain lower middle income status by 2020. It will be realized through strengthening
the country’s competitiveness for sustainable wealth creation, employment and inclusive
growth.
3.2.4 National Transport Master Plan / Transport Master Plan for GKMA (2008–2023)
The National Transport Master Plan Including a Transport Master Plan for Greater Kampala
Metropolitan Area (NTMP/GKMA) sets out a framework for development of the transport
sector over the next 15 years, 2008-23. Since transport is the “blood” circulation system of
any economy, this Plan constitutes an essential element for overall planning of the medium-
term economic and social development of Uganda. A new National Transport Master Plan is
under development. The NTMP/GKMA key strategic objectives include;
a) To provide a long-term comprehensive framework multi-modal transport within
which consistent plans for individual modes can be developed;
b) To serve as a key input to regional transport planning at East African Community,
COMESA and African Union levels;
c) To create a framework within which well-informed investment decisions can be made
by both public and private sectors;
The National M&E policy that is spearheaded by the Office of the Prime Minister (OPM) provides
a clear framework for strengthening the coverage, quality and utility of the assessment
of public policies and investments intended to achieve socio-economic development. In FY
2012/13, the Ministry of Works and Transport developed a comprehensive Monitoring and
Evaluation framework to enhance monitoring in the Transport Sector.
10 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Golden Indicators
The main indicators, shown in green in figure 1 are Golden Indicators and GAPR Indicators.
The Golden Indicators were agreed upon by the Transport Sector Working Group to assess
its own performance. Some of the Golden indicators double as GAPR indicators. The principal
purpose of the Golden Indicators is the demonstration of Sector-wide performance aimed
at overall strategic management, including the review of related policy issues. The Golden
Indicators were adopted by the Sector in 2011. The Golden Indicators are related to the
mandates and functions of the Ministry and its Agencies and the objectives of the National
Development Plan (NDPIII). The MoWT progress towards the golden indicators is discussed
further in this report. The Government Annual Performance Report (GAPR) is used by
the Office of the Prime Minister to monitor and evaluate performance of all Government
Sectors, including transport. The GAPR uses indicators which report on outcomes; it also
has output indicators to be compared with budgets, releases and expenditure of government
programmes. Performance of the Sector against GAPR indicators is as detailed.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
11
Uganda is a member of regional blocs such as EAC, COMESA and AU. The major objective of
these regional blocs is regional integration to reduce non-tariff barriers and enable a seam-
less movement of goods, persons and services across states.
The Vision 2050 focuses on initiatives that will create gainful employment to the economically
active population. It focuses on the development of pillars and enablers that would create
jobs to absorb the expected expansion of workforce in the next decades of the Vision 2050.
Infrastructure and transport network that is easy, fast and cheap for people and goods
creating regional competitiveness are identified as one of the pillars and enablers of economic
transformation.
The overall Goal of the EAC Development Strategy (2016/17 - 2020/21) is: “to build a firm
foundation for transforming the East African Community into a stable, competitive and
sustainable lower middle income region by 2021”, while its overarching theme is: “accelerating
a people-centred and market driven integration”.
Specifically, the EAC Development Strategy aims at investing in enhancement of the stock
and quality of multi-dimensional strategic infrastructure and related services, to support and
accelerate sustainable regional integration and competitiveness.
The Master Plan on Logistics in the Northern Economic Corridor (NEC) is a multi-modal plan
consisting of road, rail, pipeline and inland water ways transport to link Uganda to countries
like Kenya through Mombasa port, Rwanda, Burundi, the Democratic Republic of Congo and
Southern Sudan.
The Master plan addresses transport and logistics gaps by proposing a shift to the following:
The EAC Northern Corridor Infrastructure Master Plan specifically to the transport sector
aims at:
In the area of regional transport cooperation, the principal treaties ratified by Uganda are:
i) The “Treaty for the Establishment of the East African Community (EAC)”.
Among other provisions, this treaty proposes a customs union in which internal tariffs
are abolished and non-tariff barriers are eliminated. In the transport sector it provides
for the elimination of non-physical barriers to road transport and the non-discrimination
between carriers of member states. The EAC agreed also on tariff setting, schedules and
safety issues for the water cargo transport on Lake Victoria.
ii) The “Treaty for the Establishment of the Common Market for Eastern and Southern Africa
(COMESA)”.
Under this treaty, member states are required to develop coordinated transport and
communications policies. In addition, it provides for the measures to ensure common
procedures for the harmonization of road transit charges, similar treatment to the carriers
of all member states and the promotion of cost-effectiveness through competition.
Uganda is an active member of COMESA and has supported all the initiatives aimed at
strengthening integration in the region.
iii) The “Northern Corridor Transit Agreement” between Burundi, the Democratic Republic
of Congo, Kenya, Rwanda, and Uganda.
The provisions of this agreement are mainly concerned with facilitating the transit of
goods traffic and the similar treatment of carriers of all member states.
The United Nations (UN) is the universal platform for global normative debate and consensus-
building on global policy issues, including the economic, social and environmental dimensions
of sustainable development. UN adopted a global Post-2015 Development Agenda, which
includes a comprehensive set of 17 universal Sustainable Development Goals (SDGs), together
with 169 specific development targets.
The SDGs provide comprehensive global policy guidance for all United Nations Member
States. Transport provides essential means to stimulate socio-economic activities and to
promote development including the eventual achievement of the SDGs. The efficient, reliable,
affordable, safe, accessible, and environmentally friendly transport of passengers and goods
is indeed key to the implementation of the Post-2015 Development Agenda.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
13
The Sector undertakes a number of activities which impact on the achievement of the 2030
Sustainable Development Agenda of the United Nations (UN). More specifically targets 3.f,
9.a&f and 11.b below:
i) Target 3.f: By 2020, halve the number of global deaths and injuries from road traffic
accidents 3.7
ii) Target 9.a: To develop quality, reliable, sustainable and resilient infrastructure, including
regional and trans-boundary infrastructure to support economic development and
human well-being, with a focus on affordable and equitable access for all.
iii) Target 9.f: Facilitate sustainable and resilient infrastructure development in developing
countries through enhanced financial, technological and technical support to African
countries, least developed countries, landlocked developing countries and Small Island
developing States.
iv) Target 11.b: By 2030, provide access to safe, affordable, accessible and sustainable
transport systems for all, improving road safety, notably by expanding public transport,
with special attention to the needs of those in vulnerable situations, women, children,
persons with disabilities and older persons
The list of more instruments, conventions, protocols and agreements to guide Sector
institutions while executing their mandates is provided below;
i. The Yamoussoukro Decision spearheaded by the African Union (AU), the East
African Community Air Transport Liberalization Programme under the East
African Community (EAC);
ii. Common Market for Eastern and Southern Africa (COMESA) Legal Notice No. 2 on
Liberalization of Air Transport; and
iii. The Communication, Navigation, Surveillance/Air Traffic Management (CNS/ATM)
Master Plan.
iv. The United Nations Decade of Action on Road Safety
v. The LAke Victoria Transport Act 2007
vi. The United Nations Convetion for the Law of the Sea (UNCLOS)
vii. The Convention for suppression of Unlawful Acts at Sea (SUA 88’)
viii. The African Maritime Transport Charter
ix. Applicable Conventions of the International Maritime Organization (IMO)
x. Port Management Association for East and Southern Africa Protocol’s (PMAESA)
xi. Northern Corridor Transit and Transport Coordination Agreement
xii. Central Corridor Transit Transport Coordination Protocol
xiii. International Convention on the International Civil Aviation Organization
(ICAO) 1944
xiv. ICAO Standards and Recommended Practices (SAPS)
xv. East African Community Treaty and Protocols
xvi. Standard Gauge Railway Protocol
xvii. Agreement on the Intergovernmental Standing Committee on Shipping (ISCOS)
14 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
The 15th Joint Transport Sector Review (JTSR) of September 2019 discussed and raised key
Policy and Strategy issues. These issues were consolidated into an agreed Action Plan Matrix.
Progress on the Actions is detailed in Annex I of this report.
Roads
1 Road network in fair
to good condition (%)
FY2019/20
1 This is based on provisional estimates from Uganda Police for Calendar year 2019
2 This is based on provisional estimates from Uganda Police for Calendar year 2019.
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
Fatalities per 10,000 26 26 26 26 19
vehicles
Total registered ve- 1,102,021 1,222,964 1,355,090 2,000,000
hicles
4 Road Service Level-
Travel Time (min-
utes/km)
On National Roads 1.15 1.143 1.13 N/A N/A 1.13 1.13 100
On District Roads N/A N/A N/A N/A N/A 2.5 N/A N/A
In GKMA 2.5 2.9 2.7 4.2 4.1 3.5 4.1 100
5 Road Construction/
Maintenance Cost
a Paved Roads (1000
USD/km)
National Roads – N/A N/A N/A N/A N/A N/A N/A N/A
New-Construction
National Roads – up- 650-1,100 650-1,100 1,800,000- 1,800,000- 576,610- 600,000- 2,259,000- N/A
grading from gravel 2,000,0004 2,000,0004 1,380,6176 1,500,000 4,651,000
to tarmac
National Roads – 896-984 896-984 1,800,000- 1,800,000- 576,610- 600,000- 1,776,000- N/A
Re-Construction 2,000,000 2,000,000 1,380,6176 1,500,000 2,929,000
National Roads – Re- 400-791 400-791 280,000- 280,000- 454,087- 400,087- 1,776,000- N/A
habilitation 497,500 497,500 504,541 540,000 2,929,000
National Roads – Pe- 100-300 100-300 8,400- 8,400- 8,400-17,500 8,400-17,500
riodic maintenance 17,500 17,500
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
3
19
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
20
b Unpaved Roads
(1000 USD/km)
National Roads – Pe- 13.4-15 13.4-15 13.4-15 13.4-15 7.2-13.9 13.5-14.0
riodic Maintenance
National roads – 3.5-5.5 3.5-5.5 3.5-5.5 3.5-5.5 3.8-4.8 4.0-5.0
Mechanised routine
maintenance
District roads – Reha- NOT AV NOT AV NOT AV NOT AV NOT AV N/A N/A
bilitation
District – Periodic 4.5 4.7 4.9 5.1 5.3 5.5 5.4
Maintenance
District roads - Rou- 0.3-1.2 0.4-1.3 0.4-1.4 0.6-1.5 0.7-1.6 0.8-1.7 0.8 - 1.8
tine Maintenance
Urban roads – Reha- 3-19 6.4 – 13.1 6.4-13.1 6.9-13.6 7.2-13.9 7.3-14.0 7.4 – 14.2
bilitation
Community Access NOT AV NOT AV NOT AV NOT AV NOT AV NOT AV NOT AV
Roads - Routine
maintenance
6 Rural Accessibility
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
Rural population liv- 83% 85%5 85 N/A 60 53 88.3
ing within 2 km of an
all-weather road
Population with ac- 38 38 38 N/A 40 N/A N/A
cess to Taxi / Matatu
service (% of total)
All year motorable 77186 19,4827 N/A N/A 20,000 N/A N/A
Community Access
Road network (km)
7 Road Maintenance
Needs Met
a Maintenance
budget relative to
requirement
a.1 Maintenance
Financed by URF
National Roads – 34.8 25.6 22 45 52.4 50 47.3 94.6
budget to require-
ment (%)
District Roads 51.6 37.3 27 24 27 30 15.0 50
– budget to
requirement (%)
Urban Roads includ- 50.7 46.4 47 22 26 30 15.0 50
ing KCCA – Budget to
requirement (%)
a.2 Backlog –
Rehabilitation Needs
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
Budget for all roads 145.2 118.8 166.1 172.7 179.2 200 186.2 93.1
(USD million)
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
22
Unfunded backlog 802.4 1047 1244 1,403 1,520 1,400 1,154.3 82.45
for all roads (USD
million)
FY2019/20
b Maintenance
Expenditure relative
to Release (%)
National Roads 98.6 76.9 67.5 99.9 101 100 98.9 98.9
DUCAR Roads 90.3 76.0 76.4 59.1 62 100 64 64
8 Compliance with
Axle Load Regulation
ANNUAL SECTOR PERFORMANCE REPORT
Number of Vehicles 215,067 654,369 575,211 1,247,931 1,364,562 1,400,000 1,220,753 87.20
weighed
Number of Overload- 107,533 14,029 21,282 47,421 42,301 45,000 46,389 103.09
ed vehicles
Overloaded Vehicles 50 2.1 3.7 3.8 3.1 2.5 3.8 152
(% of total controlled)
Rail
9 Rail Freight Volume
Total freight carried 171.1 165.7 118.9 7.54 3.735 7.5 40.172 535.7
(million-tonne-km)
10 Rail Modal share at
Malaba, Busia and
Port Bell Border
Points
Total Freight crossing 8,325 5,162.7 5107.1 179 180 145.02 80.6
the three borders
(1000 tonnes)
Freight that crosses 6 8.3 6.5 3.5 - 5 7.26 145
the three borders by
rail (% of total)
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
11 Rail Modal Share on
Lake Victoria Ferries
Freight transported on 16.1 N/A 7 0.002 35 40 34.3 85.6
ferries by rail, regis-
tered at Port Bell border
post (% of total).
12 Rail Efficiency
Locomotive produc- 147 69 78 148 251 150 74 49.3
tivity (km/loco/day)
13 Wagon Utilization
Wagon Transit time 8 13 12 7 31 12 25 208
(days)
Wagon Turn-round 28 25 34 28 31 28 76 271.4
time (days)
Air
14 International
Aircraft Movements
(tones)
Exported 31,867 34693 46,777 39,594 41339 42,579 37,829 88.8
Imported 20,747 21490 20,317 22,499 20788 21,412 21,985 102.7
Water Transport
16 Freight Traffic on
Lake Victoria
ANNUAL SECTOR PERFORMANCE REPORT
b Number of EIAs Accepted by NEMA against Total Number of EIAs Required (%)
2.Major injury 0 0 30
3.Fatal accidents 0 0 33
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
Golden indicators are the principal demonstration of sector-wide performance aimed at overall strategic management. The Golden Indicators
25
were adopted by the Works and Transport Sector in 2011. These indicators give an insight into the current state of the National Road Network.
They are related to the mandate and functions of UNRA.
26 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
27
For the Financial year 2019/20, the approved budget for Vote 016 was UGX 1,655.864 Bn.
The total amount released by the end of June 2020 was UGX 1,159.158 Bn representing 70%
of the approved annual budget. The low release was due no releases in quarter four because
of the Corona Virus pandemic.
The total GoU release performed at 84.1% of the approved budget while the External
financing performed at 48.5% of the approved budget. The low performance level for external
financing was under Multinational Lake Victoria Maritime Communication and Transport,
Development of new Kampala Port in Bukasa and Development of Kabaale Airport due to the
lengthy procurement process for the boats, RAP implementation challenges and the Covid
pandemic breakdown that affected project progress respectively. Table 7 shows the budget
breakdown in terms of the release and expenditure for the financial year 2019/20
Table 7 : Overview of Vote016 (Ministry of Works and Transport Expenditures (UShs Bil-
lion)
Budget Absorption: By the end of June 2020; 100% of the released fund under GoU component
had been spent while only 44.5% of the external financing had been spent. The low budget
absorption under external financing was due to low performance level under Multinational
Lake Victoria Maritime Communication and Transport, Development of the new Kampala
Port in Bukasa and Development of Kabaale Airport due to the lengthy procurement process
for the boats, RAP implementation challenges and the Covid pandemic breakdown that
affected project progress respectively. Overall, 84.8% of the funds released had been spent by
the end of June 2020.
28 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
This section covers the assessment of the performance based on the Programme Outcome
indicators, the performance of the Directorate of Transport and the performance of the
Directorate of Engineering and Works.
1) Formulate transport policies, laws and regulations in conjunction with the department of policy
and planning.
2) Monitor and evaluate the effectiveness of transport policies, laws and regulation.
3) Develop and set standards for transport services in all modes.
4) Provide technical advice on transport matters.
5) Oversee performance of Uganda Civil Aviation Authority (UCAA), Uganda Railways Corporation
(URC), Transport Licensing Board (TLB) and National Rod Safety Council (NRSC).
The performance of the directorate in the financial year 2019/20 is as indicated in table 9:
On the development of the boat standards ;only Delays were caused by SoPs set by
Bidding documents for the Boatbuilding standards Government during Lock-down
were prepared due to COVID-19 outbreak.
On the construction and equipping of the 9 Search Awaiting Bank No Objection to
and Rescue centres; Contract for design of 9 Search submit draft Contract to Solicitor
and Rescue Centres was signed. General Office.
258. Flag and Port State Control Inspections were Inspections were affected by
conducted out of the targeted 500 inspection. limitations to travel caused by
In land COVID-19
water
inspection/ 252 in land water vessels were registered and Inspections were affected by
licensing licensed out of the targeted 300 in land water limitations to travel caused by
vessels. COVID-19.
Two( 02) out of three (03) public awareness . COVID-19 Pandemic lockdown
campaign on inspection, registration and licensing affected achieving target
were conducted
Road
Contract for Remodeling of URC block and URA On target.
Inspection / warehouse to house the Uganda Computerized
Licensing Driving Permit Facilities for the digital archiving of
motor vehicle manual registration records signed and
remodeling Works at 100% as had been planed
55. Driving schools were inspected to ensure COVID-19 Pandemic lockdown
compliance with regulatory Standards out of the 75 affected achieving target.
driving schools targeted.
1,156 Drivers’ Badges were processed COVID-19 Pandemic lockdown
affected achieving target.
and issued out of the 1,500 targeted.
32,660 PSV were licensed out of the target of 22,000 Stepped up enforcement and
PSVs vehicles. requirement for route charts for
taxi operation.
42. Driving Schools were license out of the 75 schools COVID-19 Pandemic lockdown
planned. affected achieving target.
Carried out joint road safety inspections for black COVID-19 Pandemic lockdown
spots in Western Uganda and Eastern Uganda along affected achieving target.
the National Corridor routes only instead of all the
four regions (North, East, west and central).
Only One (01) Road Safety awareness campaign out COVID-19Pandemic lockdown
of the four planned was conducted during URA Tax affected achieving target.
Appreciation Week. Road Safety Awareness were
carried out during Tweddeko Caravan along Kampala
-Luwero Road.
(vii) Participated one instead of two East African COVID-19 Pandemic lockdown
Consultative Meetings on Facilitation of Air affected achieving target.
Transport in the 46th by-annual East African
Consultative meeting on Facilitation of Air Transport
(EAC FAL) in Dar el Salaam-Tanzania.
The directorate of engineering and works comprises of the departments of Roads and Bridges,
Public structures, Mechanical Engineering Services, and Construction Standards and Quality
Assurance.
T h e m a t i c Performance Remarks
Area
District, Of the targeted 132.8 km to be rehabilitated in Tororo, The underperformance was
Urban and Namutumba, Serere, Busia, Butaleja, Budaka and Buke- due to low funding.
communi- dea; 93.5 km were just opened; 77.1 kms were opened
ty Access and graded while 69Km were opened, graded and grav-
roads. elled by the Eastern Unit under Force Account (Details
in Annex 7 ).
64.7kms were fully gravelled out of a target of 131.1kms Limited funding affected
in the financial year by the central force account road performance.
unit in the districts of Buikwe, Gomba, Kasanda, Kayun-
ga, Kikuube, Luwero, Lwengo , Mukono and Nakaseke (
Details in Annex 4)
135.2 kms of district roads had been targeted to be re- The underperformance was
habilitated in Kitgum,Nwoya,Moroto,Albetong,Omoro, due to low funding
Lira and Apac but only 69.8 kms were opened,67.5 kms
were opened and graded while only 58.5 kms were
opened,graded and gravelled by the Northern Unit
under Force Account.(Details in Annex 9)
Of the targeted 140.60km to be rehabilitated in Kamuli, Limited funding affected
Buyende, Jinja West, and Bugiri. 93.8 km were just performance
opened; 140.6 kms were opened and graded while only
41.18Km were opened, graded and gravelled by the Jinja
Unit under Force Account (Details in Annex table 6).
97.3Km were opened, 54.8 kms were opened and graded Work Progress was affected
while, and 46.6 km were fully gravelled out of a target when No funds were
of 130.1km by the western force account unit.(Details in released for quarter four.
Annex 8 ) Execution was also affected
by COVID -19 lockdown
15 km urban roads were sealed under force account out Work Progress was affected
of the target of 16km (Details in Annex 10 ) when No funds were
released for quarter four.
Execution was also affected
by COVID -19 lockdown
14 bridges are under construction (Details in Annex- Details on progress of each
table 2 ) bridge is in table on bridges
attached.
Detailed designs for Kagera Bridge, Ongino Tisai Bridge On target
and NakadidirLukolwe-Namuganga swamp, Nyahuka-
Mirambi Bridge, Komorotot bridge, Mutti-Gwa Kirevu
and Rwammable swamp crossing, Karujumba Bridge,
Bugibuni-Bunadasa Bridge and Rwammabaale Swamp
Crossing were conducted and completed in the financial
year.
Only 10 retained Road camps in South Western and Lack of enough funds to car-
North Western surveyed out of the 207 road camps ry out the works.
planned.
38 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
T h e m a t i c Performance Remarks
Area
District, 33 out 33 targeted projects of UNRA were monitored On target
Urban and and evaluated on progress and reports Prepared.
communi- Kiruku - Bukiiyi gravel road Constructed to completion On target
ty Access as part of training in LBT; The road measuring 4.3Km
roads. long was completed in Q1 and is ready for handover to
Sironko district.
456Trees were Planted along Kiruku -Bukiiyi LBT mod- COVID19 affected achieving
el road reserves out of 500 trees targeted. the target.
LCS trial(9km) contracts are 100%completed in districts On target.
of
T h e m a t i c Performance Remarks
Area
42km of District roads for Low Cost Sealing were de- On target
signed as had been planned
42km of District Roads were sealed using Low Cost On target
SealingTechnology on Nyaruzigati-Kyapa-Kitabu, Kyer-
ima-Nakaseeta-Lukonda, Bufulubi-Kyanda-Buyemba
and Kisozi-Kifampa as had been planned.
58.75% average availability for Ministry vehicles was There were no funds availed
attained against a target of 70%. to facilitate maintenance/
Mechanical
repair of the vehicles.
services
37.5% average availability for MV Kalangala was at- Services of MVKalangala
tained instead of the 95% targeted. were suspended to allow the
ferry undergo mandatory
survey and maintenance.
100% average availability for Lake Bisina ferry was On target
attained against a target of 95%.
67.5% instead of 65% targeted average availability tar- Repairs on some of the pro-
geted for the Government protocol fleet was attained. tocol vehicles that were
on-going since Q3 were able
to be completed.
88.5% average availability for equipment acquired from Monitoring ensured proper
Japan attained against a target of 80%. management by District
Local Governments
Emergency repair works for Nakiwogo and Lutoboka The piers at Nakiwogo (En-
piers were just initiated. The target was to have them tebbe Mainland) and Lutobo-
completed and in a good condition ka (Kalangala Island) landing
sites were submerged due
to the rise in water levels of
Lake
Victoria.
47% average availability for equipment acquired from Inadequate funds to rehabil-
China was attained instead of the 60% targeted. itate or carry out major re-
pairs for the road equipment
acquired from China.
255 equipment operators from District Local Govern- The training program for
ments trained against a target of 480 operators. equipment operators, ar-
tisans and technicians
was suspended due to the
COVID-19 pandemic.
Only 2 bailey bridges on rivers Cheptui(in Magonja, Bi- There was no inspection and
honge Bulambuli district)and Unyama (in Atiak Amuru monitoring of bailey bridges
district) were inspected and their condition monitored conducted because of lack of
against a target of 8 bailey bridges. funds
40 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
T h e m a t i c Performance Remarks
Area
310 against a target of the 280 materials testing, quality This is demand driven and
control and research on construction material reports all requests were handled
Construc-
were produced and reports produced.
tion stan-
500 assorted laboratory equipment for CML-Kireka and on target
dards and
Regional laboratories procured (bitumen, Soil, Concrete
quality
and Rock testing equipment).
Assurance.
16 out of the planned 10 geotechnical investigation This is a demand driven ac-
were conducted on the Kayunga – Nabuganyi road. tivity.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
41
T h e m a t i c Performance Remarks
Area
Contracts for Supervision of Consultants and Contrac- On target
tors were monitored and supervised (Mpondwe and
Public
Bunagana OSBP, Goli and Ntoroko OSBP, UgIFT Project
structure
-MoH and MoE&S), Lukaya Market, Kyabazinga Palace
and Tito Okello House and Others.
22 venues for National functions were prepared. Others could not be prepared
due to COVID 19 lockdown.
30 out of 40 planned Technical Support services were Others could not be rendered
rendered to MDAs (Office of President ;Ministry of due to COVID 19 lockdown.
Finance; Parliament of Uganda; Ministries of Tourism,
Internal Affairs, Foreign Affairs, Defence and Veteran
Affairs; Ministry of Health(UgFT), Ministry of Educa-
tion and Sports(UgFT), Uganda Police Force;Trademark
EA, URA, IGG, UTC-Lira and others).
ERB, UIPE, UNABCEC and NEMA activities were sup- On target
ported as had been planned.
National Building Review Board supported and over 8 On target
Board Meetings held with 2 via Zoom due to Covid 19.
All Six( 06) Investigations of Construction, Building and On target. The investiga-
Fire related Accidents were conducted in Jinja, Kansan- tions are demand driven.
ga, Makerere, Kampala City and Makindye and reports
were produced.
85 District technical audits were conducted on various Others could not be under-
district local governments out of a target of 90. taken due to limitation on
movements as a result of
restrictions imposed during
the covid-19 outbreak.
30% of Central Materials Laboratory was rehabilitated Issues related to availability
the target was 50%. of funds hampered the final
stages of the procurement.
Four (04) instead of 08 Buildings were assessed for Others could not be assessed
Structural Integrity; Palm Courts Office Block for due to COVID 19 lockdown.
NITA-U report submitted on 25/11/2019, Plastic Bottle
Construction Technology
T h e m a t i c Performance Remarks
Area
Cross 90 Environment and Social Safeguards Technical audits The output is demand
cutting in MDA were undertaken as demanded. driven and the target was
issues achieved.
600 Model road workers and communities sensitized on The staff from other districts
gender and equity mainstreaming and HIV/AIDS Man- could not be trained due to
agement in Buhalya and Lusaka Low Cost Seal road sites inadequate funds and inter-
and Butalejja District. ruption by country wide lock
down as a result of corona
virus threats.
38 Non Engineering staff from 6 District LGs & 6 Urban Few were trained due to lim-
LGs in CCIs were trained in Environmental and Social ited funds.
Safeguards Management.
Sensitization of communities was done on the impor- On target
tance and need to plant trees along the model roads;
Meeting tookplace on Kiruku - Bukiiyi LBT model road.
456 Trees Planted along Kiruku -Bukiiyi LBT model On target
road reserves.
3 instead of 4 Quarterly HIV/AIDS Technical Commit- The fourth meeting could
tee meeting held and activities undertaken. not be held due to the out-
break of COVID-19.
Four (04) Gender and Equity audits were conducted on There was limitation on
MDAs. movements due to the
restrictions imposed during
the covid-19 outbreak. No
technical audits were could
be done in the
last quarter.
The support services departments and divisions include the department of Policy and
Planning, the Division of Procurement, Human resource Management and the department
of Finance and administration.
The department of Policy and Planning was able to achieve the following Key outputs in the
FY 2019/20:
(a) Held a validation workshop for the National Transport and Logistics Policy and Strategy
as had been planned.
(b) Did verification of survey location points for the preparation of the National Transport
Master Plan in western Uganda as had been planned.
(c) The draft Regulatory Impact Assessment (RIA) for the National Transport and Logistic
Policy was prepared.
(d) Regulatory Impact Assessment (RIA) for the Inland and Water Transport Bill was finalised
as had been planned.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
43
(e) Situation analysis and Interim reports for the development of the 2nd National Transport
Master Plan (2021 - 2040) was prepared.
(f) The draft National Railway Policy and Draft Marine Search and Rescue Policy were
prepared.
(g) Compendium of service delivery standards for the sector was produced as had been
planned.
(h) On the development of HIV AIDS work place Policy, only Terms of reference for HIV/
AIDS workplace policy were reviewed. Development of HIV AIDS work place policy was
deferred to FY 2020/21 due to the COVID 19 lock down.
The division of human resource was able to achieve the following key outputs in the FY
2019/20:
(a) Ninety six (96) staff members were trained in short courses. Only three (03) staff were
trained in long term courses out of the total target of 221.The targeted could not be met
due to limited funds..
(b) Only 32 staff members were recruited out of the 110 planned to be recruited. Of the
recruited thirteen (13) were new entrants and 19 were promoted. The underperformance
was due to delay in the recruitment process, insufficient wage and the outbreak of Covid19
which halted government business for five months.
The department of finance and administration was able to achieve the following key outputs
besides the routine out puts:
(a) The ministry communication strategy was implemented through short documentaries,
field visits with the media, talk shows, media briefings and newspaper supplements.
(b) All projects and programmes were audited and reports made in the first, second and third
quarter. Projects and programmes were not audited in Q4 due to the Covid 19 lock down.
5.3 CHALLENGES
a) Inadequate budget for projects and activities (e.g undertaking the development of the
inland water master plan, Census of government buildings, some force Account road
rehabilitation projects like Nambweke - Bushabala – Buhunya (7.9km) road in Busia,
Angola - Pukurotho – Katerema(7.0km) in Tororo, Budaka - Iki-Iki(12.3 km) in Busia
, Opiko – Kalapata (6.0km) in Bukedea, Mbonjera-Mbulambuturo-Gatare-Foto Kigezi
(12.km) in Kisoro, Katatenga-Rwidoga (2.5km) in Rakai etc)
b) Licensing and registration of water vessels was affected by limitations to travel caused
by Covid 19.
c) Interruption by country wide lockdown as a result of corona virus which affected
achieving the planned targets e.g in force account projects, trainings for crew and
pilots that are done out of Uganda, Road Crash data base activities planned for Q4 etc.
d) Land related issues that attracted compensation affected rehabilitation of roads under
force account e.g Ibanda-Kisara-Mukabara road(8.8km) in Kikube etc
e) Delays in procurement of the contractor to undertake dredging, Piling and Swamp
surcharging works at Bukesa port.
44 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Kampala Northern
bypass works
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
45
UNRA is appropriated a budget for its recurrent and development activities from Government
of Uganda (GoU) with the support of the Development Partners under Vote 113. The
development budget is mainly utilised for the planning, design, rehabilitation, improvement
and upgrading of the national road network. The recurrent budget is utilised for wages to
staff and the organisational operational or administration costs. In addition, UNRA receives
funds from the Uganda Road Fund specifically for the maintenance and operation of the
National Road Network. The total approved budget for FY 2019/20 was UGX 4.289 trillion
compared to UGX 3.4429 trillion in FY 2018/19. Table 11 shows a summary of the funds
received last FY and the performance on the overall budget.
ITEM
Q1+Q2+Q3+Q3+Q4
Warrant (UGX BN)
% BUDGET SPENT
FUNDS UNSPENT
PAYMENTS (UGX
BUDGET FOR FY
UN-RELEASED
% BUDGET RE-
CUMULATIVE
% RELEASES
APPROVED
RELEASED
(UGX BN)
(UGX BN)
(UGX BN)
BUDGET
2019/20.
LEASED
SPENT
BN)
RECURRENT
WAGE 71.105 71.105 - 71.105 - 100.00% 100.00% 100.00%
NON-WAGE 27.347 22.768 4.579 22.764 0.004 83.26% 83.24% 99.98%
SUB TOTAL 98.452 93.873 4.579 93.869 0.004 95.35% 95.34% 100.00%
DEVELOPMENT
GOU 1,744.55 1,727.45 17.10 1,727.23 0.22 99.02% 99.01% 99.99%
EXT. FINANCING 2,176.06 811.29 1,364.77 440.67 370.62 37.28% 19.99% 54.32%
TOTAL Dev’t 3,920.62 2,538.74 1,381.88 2,167.90 370.84 64.75% 55.15% 85.17%
MAINTENANCE 270.00 282.17 -12.17 281.78 0.39 104.51% 104.36% 99.86%
– URF
GRAND TOTAL 4,289.07 2,914.78 1,374.29 2,543.55 371.23 67.96% 59.17% 87.27%
By the end of FY19/20; 100% of the approved wage bill amounting to UGX 71.11Bn was re-
leased. Out of the UGX 71.11Bn wage released, UGX 71.11Bn was spent by close of the FY
2019/20 representing 100% of budget released spent.
6.1.3 DEVELOPMENT
UNRA receives funding for road development through two sources that is; GoU and External
Financing.
For the FY19/20, a total of 1,744.55 Bn was approved for the Development GoU budget, out of
which UGX 1,727.45 Bn (99.02%) was released. Out of the cumulative release of UGX 1,727.45
Bn, UNRA spent UGX 1,727.23 Bn by end of the FY representing 99.99% of the releases spent.
A total of UGX 2,176.06Bn was appropriated for external financing under FY 2019/20 of
which UGX 811.29 Bn was cumulatively released by end of FY representing 37.28% of the
appropriation released. The budget included appropriations of UGX 1.1 trillion (50%) which
could not be spent within the year:
o UGX 717.5 billion was appropriated to the Critical Oil roads, yet MoFPED was still
finalising the negotiations with China Exim and approval by Parliament. The funds
were not made available to UNRA by the end of the year;
This means that UNRA’s externally financed budget, excluding the two above misappropria-
tions, was UGX 1 trillion, of which 43% was absorbed. Other reasons for the low absorption
of the external financing component include:
o UGX 150 billion was allocated to projects under procurement, whose contracts were
signed after the close of the FY;
o A few projects suffered slow progress due to the extended heavy rains and the
lockdown due to COVID-19 pandemic while NERAMP did not disburse (UGX 123
billion) due to the suspension of works to allow the contractor rectify the safeguards
management on the project.
The measurement of the road condition is by the International Roughness Index (IRI). Rough-
ness is a good indicator of the condition of the road because it affects the level of service in
terms of the riding quality, speed and cost of vehicle operation and maintenance. The con-
dition of the roads is a Key Performance Indicator that is used internationally for the roads
system. It refers to the structure, roughness and unevenness of the road. Golden Indicator 1
is: “% of the roads network in fair-to-good condition”.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
47
The trends in the improvements in the condition of the national paved roads are as shown
in the Figure 2. Figure 2 depicts that paved roads in good condition have increased over the
past 6 years however in comparisons to this FY there was a reduction. In the FY 2019/20
the national roads network in fair to good condition was 84% for paved roads and 77% for
unpaved roads.
4 As of June 2020, only 50% of paved roads had been surveyed and 90% of unpaved roads.
48 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Figure 3: Condition of the Unpaved National Road Network over the years
The paved roads refer to roads having an all-weather bituminous surface. The stock is
measured by computing the number of completed kilometres of gravel roads upgraded
to bitumen standard or new roads constructed to bitumen standard. Currently 24 road
upgrading projects (new construction and upgrading from paved bituminous standards)
covering a total length of 1,692 Km. At the beginning of the year, these were at various
stages of construction or physical progress. The annual increase in physical progress for all
the projects was assessed to be equivalent to 310 Km as the total construction output within
the FY 2019/20.
Table 13: % Performance and Km-Equivalent Achieved on upgrading projects (June 2020)
% PROGRESS JUNE
% PROGRESS JUNE
% ANNUAL PER-
FORMANCE
2020
2018
2019
(Km)
18. Masindi Park Junction and Tangi 159 0 11 47.1 36.1 56.84
Junction - Para - Bulisa
19. Kapchorwa - Suam 73 0 5 17.3 12.3 9.04
From the Table 13, 6 projects performed between 81% -100%, 5 projects performed between
41%-60% and between 0%-20% while 4 projects performed between 61%-80%. This is
cumulative progress of the project.
Table 14: Substantially Completed Upgrading Road Projects (as at 30th June 2020)
Table 14 shows the projects that were substantially completed by the end of the FY, adding
427.5 Km to the paved road network. This brings the total paved stock to 5,370 Km, which is
25.5% of the national road network.
50 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
This indicator assesses the per Km costs of the different road development and maintenance
interventions undertaken on the National Road Network. These interventions have been
categorised as follows:
(ii) Rehabilitation and Reconstruction of paved roads that have outlived their design
life. Works involve removal or reuse of base layers, improvement of alignment,
earthworks, and compaction and new surface bitumen layers. Rehabilitation of
paved roads that are in poor condition which involves removal or reuse of base
layers, re-compaction and new surface bitumen layers.
(iii) Under periodic maintenance for paved roads, the sections of the network are re-
resealed or over layed to prolong the lifespan of the road. There are no major
improvements to the base layers. For unpaved roads, periodic maintenance
consists of road re-grading and re-gravelling covering a lifecycle of 2-3 years.
Mechanised routine maintenance, on the other hand, involves spot re-gravelling
and grading of the bad sections/spots
Project Name
Supervision Cost
Wearing Course
Land Acquired
Unit cost/ KM
Construction
Length (Km)
Approved
(hectare)
Funder
Cost
RECONSTRUCTION/REHABILITATION PROJECTS
Fort Portal - Kyenjojo 50 GoU Asphalt 118.000 2.033 2.401
Dressing
The average construction cost for upgrading roads to paved standard with bituminous surface
treatment during the FY 2019/20 was UGX 3.41 Bn per kilometre as compared to UGX 3.1 Bn
per kilometre in FY 2018/19 and UGX 2.36 Bn per kilometre in FY 2017/18. This cost excludes
the cost of land acquisition, which is shown in the Table 15. This is because the value of land
is dependent on many factors which may not be easily benchmarked among projects or even
road sections in different geographical locations.
The average cost of reconstruction/rehabilitation of the paved roads was UGX 2.16 Bn per
kilometre as compared to UGX 1.8 Bn per kilometre for FY 2018/19 and UGX 1.96 Bn per
kilometre in FY 2017/18. During the reconstruction, the entity uses the opportunity to
improve the geometry and structure of the existing roads, which makes the cost higher than
it, would have been for only reinstating their serviceability. Table 16 shows the cost/Km for
construction and rehabilitation project
Table 16: Average cost of road construction over the years (UGX Bn)
Road Reconstruction/Rehabilitation
FY 2019/20, rehabilitation of 313 Km of the national roads continued on seven (7) road projects
and a total of 167.1 Km-Equivalent was achieved out of the targeted 200 Km-Equivalent this
represents a performance level of 83.6% compared to 66% in the FY 2018/19.
52 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Length
Performance 2020
Performance 2019
% Progress June
% Progress June
% Progress June
Km-Equivalent
Km-Equivalent
added 2020
added 2019
Annual
Annual
2020
(KM)
2018
2019
1. Nyenga - Njeru 10.0 0 5 100 0 95 0 10.00
2. Hima - Katunguru 29.0 2.7 65 100 62.3 35 37.3 20.30
Phase 1
3. Nakawa - Seeta 9.0 0 0 100 0 100 0 9.00
4. Fort Portal - 50.0 43.8 93 99.8 49.2 6.8 25.5 3.43
Kyenjojo
5. Ishaka - Katunguru 58.0 3.1 20 96.4 16.9 76.4 10.15 44.07
6. Fort Portal – Hima 55.0 0 11 85.6 11 74.6 8 40.78
7. Nakalama - Tirinyi 102.0 4.8 46 85.5 41.2 39.5 43.54 39.52
- Mbale
TOTAL 313.0 167.10
Hima - Katunguru Phase 1: this road was originally 58km but into two phases. Phase I is
29km and Phase II 29km
At the end of the FY 2019/20, four (4) road rehabilitation projects totalling 146 Km were
substantially completed. Table 18 shows the road rehabilitation projects substantially
completed by June 2020.
This indicator measures the maintenance budget relative to road maintenance requirements/
needs and it considers the percentage of annual road maintenance needs for funding. The
road maintenance needs for the FY 2019/20 totalled to UGX 596 Bn similar to that of FY
2018/19. A total of UGX 270 Bn was appropriated however, UGX 282.17 Bn was released. The
release represented 47.3% of the annual maintenance needs funded compared to the 52.4%
in the FY 2018/19.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
53
Releases for Maintenance-URF were higher than the appropriated budget due to additional
funding for the emergency works undertaken to address network cut-offs by the heavy
rains during the year. Underfunding of road maintenance is partly responsible for the road
maintenance backlog because the maintenance regime is not being followed. Table 19 show
the funding requirement vis-à-vis amount provide for road maintenance.
Table 19: Funding requirement vis-à-vis amount provided for road maintenance over the
years (UGX Bn)
Figure 4: Funding requirement vis-a vis amount provided for road maintenance
UNRA carried out maintenance activities on the road network and achieved the following
against the targets. The following were the key outputs and intermediate outcomes from the
road maintenance interventions.
54 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
S/N Indicator
Achievement (Km)
Achievement (Km)
Achievement
FY 2018/19
Target (Km)
Target (Km)
FY 2019/20
FY 2019/20
FY 2018/19
(%)
1 Routine: Km of Paved Roads 5,286 4,811 4,791 5,117.8 107%
Maintained
2 Routine: Km of Unpaved Roads 10,185 27,380 21,275 27,886 131%
Maintained
3 Periodic: Km of Paved Roads 655 786 7.5 4.5 60%
Maintained
4 Periodic: Km of Unpaved Roads 4,896 5,644 225 15 7%
Maintained
5 No. of Bridges maintained 324 46 324 0 0%
-Routine
No. of Bridges maintained
-Periodic
The overall budget allocated to UNRA for FY 2019/20 was UGX 4,289.07 Bn, out of which UGX
270 Bn was allocated to the Road Maintenance Programme. Road development still takes the
biggest share of the budget, at 91.4% compared to 88% in FY 2018/19 while road maintenance
takes a meagre 6.3% of the total budget compared to 9% in FY 2018/19. This imbalance is
resulting in unsustainable development of the network while the backlog maintenance is
growing and will result in higher replacement costs of the road asset in future.
Table 21: proportion of expenditure on road maintenance, relative to the overall budget
from FY 2014/15 to FY 2019/20
Figure 5: A line graph showing the relationship between road development and road
maintenance
This indicator measures progress in compliance with axle load limits on the national roads
network. The indicators are:
The total number of vehicles weighed was 1,220,753 compared to 1,364,562 to last FY 2018/19
and 1,247,931 in FY 2017/18. The percentage of weighed vehicles that were overloaded
increased from 3.1% in FY 2018/19, to 3.8% in the FY 2019/20. The performance of axle load
control over the past 8 years is shown in the Table 22.
At the end of the FY 2019/20, 08 weigh stations were operational with an average availability
of 97.16%, compared to 98.03% registered in the previous FY 2018/19.
The table 24 details the progress of works on the weighbridge operations projects.
2 Paving Mbarara Weigh Station Parking yard • Concrete for the single axle-weighing lane
completed, Earthwork for the approaches and the
parking yard at 90%. Mix design done.
3 3 High Speed Weigh In Motion Systems for • The contact for installation of the three systems
Magamaga, Luwero and Mbarara Weigh was signed towards the end of the 4th quarter. The
Stations. project expected to commence immediately with the
construction of the slip lanes.
4 Boarder post Weigh Stations at Mutukula, • The parking yards for the two stations were
Elegu and Malaba improved to the 2nd layer of gravel, Elegu station
started operations on 05 March 2019 while Mutukula
and Malaba still await calibration by UNBS
5 Centralized and Integrated Weighbridge Oper- • Three (3) indicators (Legal for trade type) that allow
ation and Monitoring System integration have been procured.
A prototype system is being developed and tests have
been carried out using the new indicators.
6 Procurement of three (03) enforcement vans Bidding notice was sent out in preparation for the
bidding exercise, which is due in July.
7 Procurement of Handheld GPS Trackers The evaluation report was submitted to Contracts
Committee for review.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
57
I. Bridge Development
In the Last 5 Years, UNRA has constructed a total of 26 Bridges including six (6) and one
culvert box which were substantially completed during FY 2019/20, as shown in the table 29.
Table 25: Bridges substantially completed in the past three Financial Years FY 2017/18 – FY
2019/20
NO. OF
S/N PROJECT LOCATION DISTRICT
BRIDGES
Ferry Operations
The ten (10) ferries at Kiyindi, Mbulamuti, Masindi Port, Laropi, Obongi, Kyoga 1, Kyoga 2,
Nakiwogo and Bisina were operational and registered 95% adherence to scheduled trips. Ferry
utilization fell from 99% in the FY 2018/19 to 82 % in the FY 2019/20 due to the COVID-19
lockdown that put restrictions on private transport.
MV Sigulu Ferry that will connect Namayingo district to the Islands of Lolwe & Sigulu will
provide safe means of transport to the communities of Namayingo, Lolwe and Sigulu Islands.
Ferry construction was completed and handed over to UNRA. However, high water levels
submerged the temporary landing sites hence delay in actual operation
% Availability
FY2018/19
% Utilization
FY2018/19
% Availability
FY2019/20
% Utilization
FY2019/20
1 Masindi - Kungu Kiryandongo and 99 109 94 82 214,694 246,921
Apac
2 Bisina - Agule Katakwi and Kumi 100 101 100 84 334,578 226,615
and Sigulu
Total 97 99 95 82 4,113,372 2,875,040
59
60 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
UNRA endeavours to identify and evaluate environmental and social risks, and impacts of
road/bridge and ferry projects in accordance with national laws and development partners’
requirements. Appropriate safeguards mechanisms are put in place to ensure that adverse
effects resulting from the project activities are eliminated or minimised.
The Green Right of Way (GROW) tree planting project was launched in March 2017 on the
Northern Bypass as part of the environmental restoration activities on all road reserves.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
63
Table 30: Road projects were Green Right of Way was done
In FY 2019/20, 10,300 trees were planted along various road corridors including; Nakalama
- Tirinyi - Mbale Road, Soroti - Katakwi - Akisim, Fort Portal -Bundibugyo, Fort Portal
- Mubende, Jinja – Kamuli, Kabale - Katuna among others. With 23 nurseries across the
country, UNRA intends to plant over 10 million trees on the national network over the next
2 years. In addition, treebanks have been established in 19 UNRA Stations with 139,058 trees.
In FY 2019/20, Contracts worth UGX 306.530 Bn were awarded to local or resident providers
in accordance with the PPDA Guidelines for Reservation schemes for promoting local content.
This represents 25% by value of the contracts signed in the FY, down from 28% in FY 2018/19
but higher than the 24% in the FY 2017/18. However, the entire 25% was only for reservation
by threshold and there was no service provided under the subcontracting component. There
was a reduction in the total amount awarded under the reservation scheme from 737 Bn to
306.5 Bn in FY 2018/19 however, this was also seen in the overall amount of signed contracts
from 2.2 Tr to 1.2 Tr.
This breakdown of the contracts signed and includes reservation by threshold and sub-
contracting is shown in the Table 31:
Providers
Contracts
Awarded
Contract
Signed
contracting
The end of FY 2019/20 saw a number of fully registered Engineers increase from 75 to 88
representing a 17.3% increase. Nineteen (19) engineers are currently at corporate membership
stage while thirty (30) are preparing for corporate membership while sixty-seven (67)
graduates are eligible for registration with ERB but are not yet registered.
i) The Covid-19 pandemic greatly affected UNRA’s ability to achieve the set targets. Several
of UNRA’s activities such as road construction were affected by the lockdown and
partial lockdown. Activities like land acquisition were halted while projects continued
to be implemented under very strict Standard Operating Procedures (SoPs). The result
of this has been a delay in progress with some contractors giving the notice to claim for
extension of time or cost.
ii) The heavy and long rainy season resulted in:
o the slow progress of the construction projects;
o Several cut-offs which required emergency interventions to reinstate the road
sections;
o The rapid deterioration of the condition of the roads, reducing the service level and
increasing the urgent need for periodic maintenance and rehabilitation of some
road sections;
iii) The financing for the road development programme remains constrained and not in
harmony with the five-year plan. This distorted effort to prepare and implement the
NDPII as was envisaged.
iv) A rigid Public Finance Management Act which does not allow flexibility in utilisation of
funds to drive the development programme.
v) The road maintenance budget remains lower than the required, which makes providing
the desired level of service and response to emergencies which result in network cut-offs
a challenge and reduced ferry services.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
65
vi) UNRA’s operational budget has remained inadequate and the same over the years, despite
the increase in the development and maintenance programme, the increase in operation
and administrative costs and the increase in staff numbers. This has constrained the
ability of the organisation to effectively supervise its programmes.
vii) Procurement delays occasioned on the programme by the external stakeholders.
During FY 2020/21, UNRA will construct 400 Km-equivalent for road upgrading projects
and substantially complete twelve road projects adding 383 Km to the stock of the national
road network.
UNRA will also commence upgrading of 19 road projects with a total length of 963.4 Km. Ta-
ble 35 shows the upgrading of road projects to commence in 2020/21.
During the 20/21 fiscal year, UNRA shall construct 252.5 KM-Equiv of road rehabilitation
projects and substantially complete three (3) road rehabilitation projects totalling 166 km.
Three road rehabilitation projects totalling to 134.7 Km will commence in 2020/21.
66 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Bridges Development
UNRA will continue construction on 56 bridges and structures of which, 15 will be completed
in FY 2020/21.
Road Maintenance
UNRA will ensure that the national roads network in fair to good condition will be kept at
above 85 % for paved roads and 70% for unpaved roads by implementing the following main-
tenance interventions.
Air traffic performance was promising to beat the target as up to the month of February
2020. All this was brought to near zero when the airport was shut down by government as a
way to contain the spread of Covid 19. Consequently, the performance of air passenger traffic
was below target averaging just above 70% of the projected levels. The drop in international
passenger traffic can be seen as of March 2020. Import cargo however, performed above
projection because cargo planes remained operational despite lockdown. Tables 41 show the
traffic performance at Entebbe International Airport as well as UCAA managed regional
airports.
70 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
YEAR 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20
JUL 87299 100068 107083 114101 122060 115282 124902 135253 145020 158508 166980
AUG 88340 100582 97476 109194 120316 123545 130628 136344 140743 153325 163344
SEP 77459 81777 89772 107533 113905 105248 113664 119658 128215 148382 155664
OCT 87319 92298 99558 108856 112864 108821 110935 117015 122065 138873 148028
NOV 75788 87878 95034 101924 112439 114863 118936 116803 121116 135841 152296
DEC 84306 92997 103779 110900 122685 117951 124528 136615 147590 157382 179323
JAN 82086 86657 107929 113347 114595 112465 115655 125833 135975 147346 158615
FEB 70932 69904 89415 97711 101757 99195 89170 107174 120155 128624 144334
MAR 76967 79098 97203 103708 104770 112460 106063 115277 130104 138461 83163
APR 72640 83452 95838 100882 101596 102431 104499 117551 127969 136334 987
MAY 82405 83379 93189 109478 108169 109138 112072 120153 129596 140108 1146
JUN 82807 90417 102452 114568 115902 115862 112432 120500 134122 145595 1892
TOTAL 968348 1048507 1178728 1292202 1351058 1337261 1363484 1468176 1582670 1728779 1355772
S
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
71
AIRPORT 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
ARUA 1845 1380 1601 2226 2305 1336 1464 1804 2298 1994
GULU 301 235 297 210 398 428 390 226 476 313
KASESE 51 75 94 442 544 520 692 800 1445 1412
PAKUBA 141 155 200 1202 464 210 266 298 440 356
SOROTI 380 404 497 3883 768 4804 410 752 268 200
MOROTO 64 94 111 364 336 366 400 422 512 491
MBARARA 4 3 2 160 80 182 150 102 98 122
MASINDI 190 183 168 12 14 2 0 0 0 0
JINJA 250 397 378 187 202 138 168 294 844 625
LIRA 62 456 708 114 128 58 42 100 86 100
KISORO 0 12 31 488 566 488 634 774 1082 1192
KIDEPO 221 206 238 365 444 314 330 260 465 390
TORORO 204 246 291 90 56 44 102 170 105 74
TOTAL 3713 3846 4616 9743 6305 8890 5048 6002 8119 7269
(a) Progress of CAA Major Projects at Entebbe International Airport By June 2020
Table 42: Progress of CAA Major Projects at Entebbe International Airport By June 2020
Table 43: Progress Other Projects at Entebbe International Airport as at the End of
June2020
(c) Status of Progress of UCAA Projects at Upcountry Airport as at the end of June, 2020
Table 44: Status of Progress of UCAA Pr ojects at Upcountry Airport as at the end of June,
2020
09 Construction of staff Arua and 645,378.0 CC approved meth- Bids evaluated and
quarters at Arua and Moroto ods of procurement. progress affected by the
Moroto COVID-19 lockdown
10 Repairs of the runways Kisoro 4,880,000 Forwarded to Con- Procurement initiated but
at KISORO Airfield tracts Committee for slowed down due to inad-
approval of methods equate funding.
of procurement.
The Uganda Civil Aviation Authority was also able to achieve the following:
• The infrastructure is inadequate to cope with the current COVID-19 pandemic port
health requirements
• Inadequate funding for development of infrastructure in order to position EIA and
other priority airports to attract more regional and international airlines into the
country.
• Land requirements for future developments
• Lack of funding to commence the plan for operationalization of Hoima International
Airport, activities such as recruitment and training of technical staff and technical
studies-ETOD need have commenced.
• The process of promulgating of Regulations takes longer time that is not in
synchronization with the latest amendments of ICAO Standards i.e. ICAO standards
are amended annually
• Implementation of the established independent Aircraft Accident
Investigation (AIG) Unit at Ministry of Works and Transport, is taking
long
• Lack of an Appeals Tribunal for Civil Aviation negatively impacts on the resolution
of aviation safety concerns
• Lack of a Policy for Attraction and Retention of Aviation Inspectors
• Training of Inspectors is highly specialized and costly. COVID-19 has
affected the fast-tracking of training of inspectors
• Essential Tools and office space for Inspectors
• Slow responsiveness of the Industry on Certification and Surveillance
Requirements
76 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
The total approved budget for 2019/2020 was Ugx.84.9Billion, out of which Ugx.9 Billion was
expected from the Government and Ugx.75.9 Billion was to be generated internally. However,
due to the low achievement of the budget for the FY 2018/19, the Board of Directors of the
Corporation undertook to revise the budget and was approved by the Ministry of Works and
Transport. The revised budget was Ugx.77.4Bn, out of which Ugx.8.5Bn was expected from
the Government and Ugx 42.3Bn was to be generated internally.
Table 45: URC Financial performance for the FY2019/2020
78
Total Income 2.14 1.5 2.12 2.13 2.74 29% 8.50 8.50 0%
ANNUAL SECTOR PERFORMANCE REPORT
GoU approved 2.14 1.5 2.12 2.13 2.74 29% 8.50 8.50 0% GoU indicated low re-
release source envelop of GoU
Total expenditure 4.15 1.34 1.08 3.08 2.59 16% 9.46 9.15 -3%
Wage -
Non-wage 0.23 0.21 0.21 0.21 0% 0.96 0.65 -32% Funds from prior year
balances
Development 3.92 1.34 0.87 2.88 2.38 17% 8.50 8.50 0%
The Corporation continued to raise revenue from various sources including freight, rent and
charges. Income from freight operations was Ugx.12.83bn a 1% drop from that of the last FY
(which was Ugx.12.96bn). COVID-19 very much affected this performance as there was little
or no economic activity in the last quarter of the year under review. Other sources included;
Assets hire contributing 0.23bn, Rent 3.39bn, Passenger services 0.54bn among others. See
figure 7.
Funding of URC
Exceptional income included debtors’ balances brought forward from the previous FY, cash at
hand and cash at bank. Also, revenue was generated from other fees which included cranage,
handling, port and docking fees, gate fees and hire of the dry dock. Further, there was income
generated from sale of mechanical and other scrap assets in the year which constituted the
miscellaneous receipts.
(Bn)UGX
Income 2017/18 2018/19 2019/20
Cargo Freight Income 5.24 12.96 12.83
Passenger Freight Income 0.40 0.54 0.544
Other Income 4.81 1.96 14.87
Total EBITDA -4.13 6.36 1.07
GoU funding 21.07 9.78 8.5
EBITDA- Earnings Before Interest Tax, Depreciation & Amortization. Other income includes
Asset hire, other fees, rent, miscellaneous receipts and exceptional income.
Northern route continued to generate more revenue followed by the southern route and
then local haulage. Revenues from the southern route dropped significantly towards the end
of the third quarter and the rest of the fourth quarter because both ships (Kaawa and Umoja)
were on dry dock.
URC contributes to five golden indicators, i.e. Rail Freight Volume, Rail Modal share at
Malaba, Busia and Port Bell Border Points, Rail Modal Share on Lake Victoria Ferries, Rail
Efficiency and Wagon Utilization. The performance of the Corporation against the golden
indicators are shown in Table 8.2
Table 47: The Golden Indicators for URC
82
Victoria Ferries
Freight transported on ferries by rail, registered at
Port Bell border post (% of total).
12 Rail Efficiency
Locomotive productivity(km/loco/day) 74 150 49.33
13 Wagon Utilization
Wagon Transit time (days) 25 12 208
8 13 12 7 19
Wagon Turn-round time (days) Wagon Turn- 76 28 271.4
round time (days)
28 25 34 28 31
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
83
In FY2019/20, the corporation railed a total of 169,255.09 tones. This tonnage railed consisted
of 68% as imports, 18% as exports and 14% as local haulage. Compared to last financial
year, there was a 14.19% decrease in performance and this was attributed to the COVID-19
pandemic effects and the wash aways in Kenya that affected trains movement.
A total of 2,263 trains were run during the financial year 2019/2020. During the financial
year, a total of one hundred twenty-nine (129) incidents for both mainline plus yards and
sidings were recorded. Out of the 129 only nineteen (19) were mainline accidents and one
hundred ten (110) were other incidents. Of the mainline accidents, three (3) were capsizements,
ten (10) derailments and six (6) level crossing accidents. These accidents cost the corporation
clearance times and resulted in delayed cargo delivery causing customer frustrations and
loss of business to other means of transport, mainly road.
During the financial year 2019/2020 Net Ton kilometre (NTK) achieved was 40,172,632.84
whereas Gross Ton kilometre (GTK) was 77,539,394. This represented a 52% pay load
performance, an improvement from 45% registered in the previous financial year.
The Corporation insured its assets against loss or damage and both the client’s cargo and its
own assets. The required operational licences for the ship (MV Kaawa) were also acquired
during the year. These included the Seaworthiness Certificate, Class Certificate and the
Manning Certificate.
NOTE:
1. For gross tonne kilometre, net tone kilometre, metric tonnes, passengers carried, Number
of trains and trains speed, higher figures indicate a good performance.
2. For delivery days, wagon Turn around, and accidents, a smaller figure indicates a good
performance.
6 Passenger Services Expan- Contract amount: 300,000 Still ongoing – 99% complete
sion Euros
Report submitted and currently
under review.
URC to engage government and
development partners.
1 Improve permanent
way to support
business
7.85 6.56 0.546
• Install 1,088 No pillars installed Activity
reinforced rescheduled to
concrete the new FY
pillars
3.26
• Routine 2.38
mainte- 250km of track
routinely maintained; Maintenance
nance of works
250km of weeding, packing,
realignment and continue to be
railway trac carried out on
opening drains -
Ugx.0.23M the track
2.6 km of track
partially renewed (re-
sleepered) Ugx.456M.
Very bad sections of More sections
the line between Jinja to be renewed
and Busembatia and
between Kawolo and
Jinja were fitted with
new sleepers.
A number of challenges were experienced by the corporation during the year, some of
which are outlined in the Table 51;
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
89
Unavailability of MV Kaawa was docked for its The works on MV Kaawa was expedited and it
MV Umoja and scheduled maintenance and was undocked in the last month of the FY.
the delay of MV repairs rendering the vessel non-
Kaawa repairs operational for 5 months (February Engagements with TRC are ongoing so as to
(Both ships were to June). In May, MV Umoja was speed up the repairs of Umoja.
on the dry dock) also docked in Mwanza. With
both vessels unoperational, this
meant that URC couldn’t carry
Central (Southern) corridor cargo,
which mainly comprised WFP.
The Corporation further lost an
estimated 20,000MT from GSM,
about 7000Mts of cargo that had
already been confirmed by clients
for haulage.
Continued use of These wagons do not to serve the The Corporation negotiated a charge to the
URC wagons for Transit purpose which affected TRC management and meetings were held to
internal haulage cargo movement on the central discuss the same.
within Tanzania corridor.
Further, TRC has been asked to return these
wagons so that they can be used on the
northern corridor.
90 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Continuous lack There is no visibility on cargo There are plans to procure a joint system with
of a cargo tracking beyond PortBell keeping all TRC.
system on the stakeholders in the dark about the
Central route location of wagons/cargo. Operations team have a daily online meeting
with TRC representatives where they share po-
sitions of transit cargo in their network.
Poor state of loco- The Corporation operated with Continued maintenance of the available
motives only one mainline locomotive locomotives through procurement of the
whose average availability was at required spares.
16% in the year, due to lack of funds
for its adequate maintenance. Lease of locomotives from Tanzania to
temporarily improve on our capacity.
This meant that for delivery of car-
go, use of other weak locomotives Procurement of new mainline locomotives.
had to be engaged, delaying cargo Process are completed pending delivery of
delivery and causing accidents. locos.
Poor state of real The real estate property was Rehabilitation and renovation of these proper-
estate property grossly affected by the period ty to increase their value.
of the concession during which
period many assets - especially
real estate- (those not considered
core to the business) were left
idle /abandoned, following which
many deteriorated.
Encroachment / Because many assets were left idle On the property management portfolio, URC
theft or unused for too long, some were management will follow-up with the line
occupied by squatters. Minister to intervene in the matter of the
Encroachers have put up struc- ownership claims of the Nalukolongo land and
tures, cultivated and put up many have the ministry of lands issue Special Titles
businesses. to URC.
Theft of track Rampant vandalism of track Beefing up police patrols and facilitating the
Materials (Van- materials especially sleepers and track with motorcycles was planned (shortage
dalism) pandrol clips of funds).
Strategy Status
Setting a national Transport The overall policy aims & framework that govern
Strategy how railways and other modes of transport will be
developed & operated
Project proposals geared towards improving the railway operations will continue to be
written for the GoU’s consideration and funding either using own resources or those of
international funders.
In the long term, URC’s strategy is to run both Meter Gauge and Standard Gauge Railway
under the reviewed railway policy. It is anticipated that URC will be able to operate profitably
after fully implementing most of the projects geared towards improving the efficiency
of its operations. The areas of priority and business focus will include:
In a bid to catch up with the deferred maintenance, URC has a plan to design and implement
a rehabilitation programme with spot improvement of the main line (Kampala-Malaba) by
re- laying 30,000 sleepers with new materials and ballasting. Expansion of the Portbell and
Bukasa Port are also planned to handle marine operations.
(1) Locomotives:
The current capacity of the rolling stock is very low due to long periods of deferred
maintenance of the assets. The Corporation had 5 mainline locomotives out of which 2
were active during the FY 2019/20, with an average availability of about 12%. URC plans to
salvage the current 16 locomotives by carrying out a complete overhaul, projected to cost
92 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
There are also plans to buy 10 high capacity locomotives, 4 in the next FY2020/21 and 6
in the following FY and install IT Infrastructure and tracking equipment on board. URC
tendered out procurement of 4 main Line locos expected to be delivered early next year
2021, two (02) reach stackers (container cranes) expected to be delivered before end of 2020.
(2) Wagons
URC currently has 1,351wagons available on the network, out of which 569 were active by
the end of June 2020. There are also plans to purchase 200 wagons within the stipulated
five years’ period, (of the investment plan) and to rehabilitate 150 Wagons.
(3) Human Resource Personnel:
URC carried out an evaluation of its current staff for competences and experiences
required for operations especially in operations and mechanical engineering skills. Plans
are underway to send various staff in the rolling stock sections for training, in partnership
with Kenya Railways Corporation (KRC), at the railways training school in Kenya. In order
to improve productivity, employee retention, efficiency and effectiveness of human capital
at URC, select staff training is planned.
This service was originally initiated as a Passenger service with the GoU subsidy. However,
URC is running this service fully, which has strained its resources. The current operational
costs of this service at Ugx.80M per month. For operational continuity therefore, URC
plans to source for GoU support.
With a limited sitting /standing capacity of 120-150 persons per coach, URC intends to
rehabilitate 10 more coaches and to acquire five sets of Diesel Multiple engines so as to
increase capacity and expand the passenger services across Greater Kampala Metropolitan
Area. The expansion is planned to cover Kampala station to Port Bell on the southern line,
and from Nalukolongo station to Bujjuko on the western line.
Commuter ridership has continued to grow over the past months which is a reflection of
the high demand for this service in the city. In spite of this, the service was operating at a
loss throughout the year, due to the high costs involved in running the service (Ugx,80M
pm). There is need to invest in infrastructure to increase the number of coaches, construct
platforms and halts and park and ride facilities. To make full utilisation of the passenger
service, the following will be done:
• request the GoU for more funding to expand the service, and also for the GoU to
continuously support this service financially as a fulfilment of the NRM objective of
improving connectivity within the GKMA through provision of light railways etc.
• extend the service to cover the Greater Kampala Metropolitan Area to 3 routes
namely, Kampala – Namanve; Kampala - Port Bell; and Kampala - Kyengera.
• rehabilitate and increase the number of coaches to 10 and above for each route,
procurement or rehabilitation of two additional locomotives.
• the Ministry of Works and Transport is in advance stages of presenting a com-
prehensive cabinet memorandum to cabinet for inventions to decongest the Greater
Kampala Metropolitan Area.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
93
URC currently operates only one wagon ferry MV Kaawa which is inadequate for the
anticipated volumes on the Southern route. There are plans to rehabilitate MV Pamba and
acquire a new wagon ferry.
8.5.7 URC plans t o exploit the opportunities below to improve its income generation
capacity;
• Develop capacity to enable negotiations for access rights for both Kenya and
Tanzania to solve problems in foreign networks currently affecting service
delivery.
• Plan to procure Reach stackers for container terminals.
• Hire agencies to manage URC interests in KRC and TRC networks.
• Start moving fuel from Eldoret to Kampala as soon as tanks are calibrated.
• Renovation of the big fuel tank at Kampala depot to facilitate fuel supply
management.
• Push for closure of negotiations with VIVO Energy, Equator shipping and
Kampala salt, push for an increase in imports from Spedag and DAMCO to match
their export needs and also drive for sugar exports along Central Corridor from
Madhvani and SCOUL.
• Through direct marketing, the commercial department is to conduct weekly client
visits and include visit engagements.
• More coordination planning and communication to be pushed for especially among
the sister networks especially on the central corridor.
• Push for civil department to develop necessary infrastructure for clients that
requested for sidings.
• Harmonization of rates with our sister partner networks against the ongoing
competitor rates so as to remain competitive throughout the network.
• URC is considering offering first and last mile solutions for their clients. This could
be through establishing sidings to all major and prospective client premises. Clients
like Steel, tube and petroleum product. Tasco Industries have expressed need for a
siding at their factory on a cost sharing basis.
• Up-selling other services like clearing services together with having reliable
partners in the other networks like clearing firms should be considered to improve
the services.
• Attain exports business from Madhvani and SCOUL on the southern route.
• Schedule weekly Client visits: Provide client engagement reports and follow ups
focusing on COVID19 SOPs
• Operationalization of Mukono ICD bond
94 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Earthmoving equipment in
Amuria District
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
95
In FY 2019/20 URF received a sum of UGX 443.282bn from the Treasury, in quarterly
tranches, which constituted 99.1% of the approved annual budget for road maintenance.
Table 53 shows the performance of the receipts from MoFPED during FY 2019/20.
Key indicators to note in Table 53 are: the budget releases performed at 99.1% of the approved
budget estimates, and on average took 16.75 calendar days from the start of each quarter.
Table 54 shows performance of the KPIs for funds inflow against target.
It can be seen from Table 54 that the performance target for Efficiency was achieved with
99.1% of the targeted minimum potential revenue collected. The performance target for
Timeliness was not achieved. The KPI for efficiency in revenue inflows performed well at
1.1% above the target, and, the KPI for timeliness of revenue under performed at 101.2% of
the maximum allowable time.
96 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
The costs were derived from aggregation and averaging of unit costs from annual work
plans of DUCAR agencies. The work plans conformed to the prevailing policy on use of force
account on road maintenance works in local government agencies. The data of maintenance
costs on national roads is measured and reported directly by UNRA and was therefore not
taken into account. Table 55 shows the data for district and urban roads for the period FY
2018/19 and FY 2019/20.
Table 55: Road Maintenance Unit Costs in the period FY 2018/19 – FY 2019/20
1.6 Urban Roads – Periodic Maintenance, Unpaved 7.2 – 13.9 7.4 – 14.2 4
1.7 Urban Roads – Routine Maintenance, Unpaved 0.7 – 2.4 0.8 – 2.6 5
Notes
1. Lower end of range for manual works; higher end for mechanized
2. Lower end of range for town councils; higher end for municipal councils
3. Lower end of range for low traffic; higher end for high traffic urban roads (KCCA and GKMA
MCs).
4. Lower end of range for town councils; higher end for municipal councils
5. Lower end of range for manual works; higher end for mechanized
It can be observed from Table 55 that there was a general increase in the unit cost of
road maintenance in FY 2019/20 compared to FY 2018/19. This is attributed to general
inflationary pressures that pushed up the cost of road maintenance inputs like fuel, gravel,
equipment repairs and maintenance, equipment hire, and labour rates. Observably, the
increase was more pronounced in urban local governments which were not beneficiaries of
newly acquired equipment from Japan and as such spent more on equipment hire.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
97
The budget relative to requirement indicators decreased from FY 2018/19 to FY 2019/20 for
all road categories following decreased budget for road maintenance from UGX 542.517bn
in FY 2018/19 to UGX 448.833bn in FY 2019/20. The road maintenance backlog decreased
as shown in Table 56 due to increased allocation for rehabilitation particularly under the
USMID Programme, but also due to a rebasing of the computation of maintenance needs on
the Community Access Roads during the year.
The indicators for maintenance expenditure relative to releases were derived as a percentage
of URF releases expended by the designated agencies within the FY. Absorption of funds
under rehabilitation programmes in UNRA and DUCAR agencies was not considered in line
with the approved indicator definition. Table 57 shows the absorption of road maintenance
funds on national roads, KCCA roads and the DUCAR network.
It can be seen from Table 57 that whilst UNRA and KCCA had essentially expended all the
funds released to them at close of FY 2019/20, the expenditure of DUCAR Agencies in Q1-3
FY 2019/20 stood at 64% of the annual funds availed them.
98 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Prior to the establishment of URF, the Treasury, within the framework of annual budgetary
appropriations, directly disbursed road maintenance funding to agencies. However, the
approach did not prioritise road network maintenance needs against the backdrop of
competing demands. Consequently, and owing to the funding shortfall, the national roads
network for instance, accumulated a maintenance backlog of 3,500Km (equivalent 33% of
its 11,000Km network at the time) between 1997/98 and 2007/08. Over the same period, the
district roads network in poor to very poor condition also escalated from 30% to 55%. Part
of the reason for establishment of the Road Fund in 2008 was to address these condition
declines.
A road fund in essence is an institutional setup through which a selected stream of revenues
is put at the disposal of a government roads department or agency without being subjected to
general procedures associated with the Consolidated Fund. An enabled road fund offers best
opportunity to ensure adequate level and predictability of road maintenance funding. URF
has not yet attained this status owing to legal impediments constraining its independent
realization of revenues from road user charges. As such the current method of financing
road maintenance through quarterly releases from the Treasury is not fully responsive to
the road condition and road network needs as to adequately check maintenance backlog
growth.
FY UGX, Bn
Needs Available1 Un-met Needs
M’tce Backlog Total M’tce Others 2
Total Amount %tage
2010/11 632 451.5 1,083.5 273.1 119.5 392.6 690.9 63.8%
2011/12 672.8 579.6 1,252.4 273.1 170.9 444 808.4 64.5%
2012/13 958.5 656.2 1,614.7 273.1 359.3 632.4 982.3 60.8%
2013/14 836.4 584.2 1,420.6 345.6 377.5 723.1 697.5 49.1%
2014/15 1,083.40 769.5 1,852.9 420.9 410.7 831.6 1,021.3 55.1%
2015/16 1,273.30 822.4 2,095.7 410.9 441.6 852.5 1,243.2 59.3%
2016/17 1,732.80 1,235.80 2,968.6 399.4 583.5 982.9 1,985.7 66.9%
2017/18 1,756.70 1,243.50 3,000.2 399.4 335.4 734.8 2,265.4 75.5%
2018/19 1,807.20 1,258.00 3,065.2 512.24 337.1 849.34 2,215.9 72.3%
2019/20 1,867.40 1,280.60 3,148.0 419.106 348.9 768.0 2,380.0 75.6%
2020/21 1,939.90 1,306.30 3,246.2 427.1 350.2 777.3 2,468.9 76.1%
1
MTEF Projections in National Budget Estim1ates, FY 2019/20
Include others for rehabilitation such as PRDP, RRP, KIIDP, USMID and others but excluding
2
Figure 10 shows the trend of road maintenance needs, road maintenance financing and the
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
99
un-met needs (including funding under USMID, RRP, KIIDP and PRDP), since FY 2010/11 and
as projected to FY 2020/21.
As shown in Figure 10, the total funds availed for road maintenance and rehabilitation has
been growing in nominal terms from UGX 393 billion in FY 2010/11 to UGX 768 billion in FY
2019/20 and is projected to further increase to UGX 777.3 billion in FY 2020/21. However,
the total maintenance needs (maintenance and rehabilitation) of the public road network is
increasing steadily at a faster rate than the increment in available funds. This is expected
since the funding for road maintenance and rehabilitation is not yet linked to road usage
represented by both traffic loading (cargo freight) and traffic volumes (number of vehicles).
Therefore, the total available funds need to be increased and sustained at a critical level to
force a steady decrease of the total maintenance needs. Funding of road maintenance also
needs to be linked to road usage through introduction of road user charges envisaged in the
URF Act.
A sum of UGX 448.833bn was allocated to URF for road maintenance in FY 2019/20, by
Parliamentary appropriations. This was UGX 93.7bn (17.3% decrement) less than the UGX
542.517bn in FY 2018/19. The funds were allocated to various expenditure heads by category
and by allowed uses as shown in sections 3.2 and 3.3.
100 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Comparatively, the allocation to national roads maintenance was decreased by UGX 42.6bn
(13.6%), the allocation to DUCAR network was decreased by UGX 44.4bn (24.1%), the allocation
to KCCA network was decreased by UGX 8.2bn (26.7%), while that for the URF Secretariat
was maintained at UGX 8.35bn.
The funds appropriated to URF in FY 2019/20 were applied for various categories of works,
goods and services in line with section 22 of the URF Act, as detailed in Table 60 - UNRA,
Table 61 - KCCA, and Table 62 - DUCAR.
It can be observed from Table 60 that not all the planned quantities of works on the national
roads network were funded in FY 2019/20. This is because some funds were reallocated to
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
101
emergency works and outstanding payments for contractors and suppliers. Implementation
of planned activities for both routine and periodic maintenance performed well as all funded
targets were achieved.
It can be observed from Table 61 that all the planned quantities of works on the city roads
network were funded in FY 2019/20. Actually, more works were funded than were planned
for in the FY. The extra funding was to cater for emergencies including dilapidated roads
and other facilities on Kampala City Roads. On average, the achievements were 100% of the
financed quantities when measured at the end of FY 2019/20.
Routine
Maintenance
Manual (km) 29,725 29,725 23,576 28,567 21,538 19,765 91.8%
Mechanised (km) 15,951 15,951 9,568 14,957 83.2%
11,344 9,437
Periodic
Maintenance
Paved (km) 5,308 5,308 1,988 4,962 3,912 2,985 76.3%
Unpaved (km)
Bridges
Routine (No) 40 40 20 35 27 21 77.8%
Periodic (No)
Culvert Installation 7,429 7,429 5,248 629 473 396 83.7%
(Lines)
Table 62 shows the physical performance of DUCAR agencies based on analysis of 94.3% of
the agencies (125 DLGs and 40 MCs) that had submitted Q3 FY2019/20 accountability reports
at the time of compilation of this report. The agencies constitute 96% of the funds released for
102 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
It can be observed from Table 7 that the planned quantities of works on the DUCAR network
were under funded in FY 2019/20. This was due to COVID-19 outbreak that distorted normal
operations across the country and thus affected release and disbursement of funds to LGs in
Q4 FY 2019/20. It can also be observed that the physical performance was in the range 76.3%
- 91.8% but on average 82.6% of the financed quantities across the various works categories
when measured at the end of Q3 FY 2019/20.
In FY 2019/20 URF received a sum of UGX 443.282bn from the Treasury, in quarterly
tranches, which constituted 99.1% of the approved annual budget for road maintenance.
Table 63 shows the performance of the receipts from MoFPED during FY 2019/20.
Key indicators to note in Table 63 are: the budget releases performed at 99.1% of the approved
budget estimates, and on average took 16.75 calendar days from the start of each quarter.
Table 64 shows performance of the KPIs for funds inflow against target.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
103
It can be seen from Table 64 that the performance target for Efficiency was achieved with
99.1% of the targeted minimum potential revenue collected. The performance target for
Timeliness was not achieved. The KPI for efficiency in revenue inflows performed well at
1.1% above the target, and, the KPI for timeliness of revenue under performed at 101.2% of
the maximum allowable time.
Budget Budget
FY Disbursed
2019/20
1 URF
Disbursements
UNRA 66.503 68.399 67.164 80.125 282.191 270.000 104.5%
KCCA 5.748 4.357 6.201 15.496 31.801 22.387 142.1%
Districts 14.484 10.980 15.626 - 41.089 56.414 72.8%
Municipalities 7.019 5.321 7.572 - 19.911 27.338 72.8%
Town Councils 6.159 4.669 6.644 - 17.472 23.989 72.8%
CARs - 12.996 - - 12.996 12.996 100.0%
Special Funds 7.124 1.610 5.122 11.829 25.686 19.009 135.1%
URF Sec. 3.117 1.703 1.486 2.043 8.350 8.350 100.0%
Recurrent
URF Sec. Dev’t 0.813 1.463 0.524 - 2.799 6.620 42.3%
Total 110.966 111.498 110.338 109.493 442.294 447.103 98.9%
104 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
It can be seen from Table 65 that disbursements to Local Governments and the URF de-
velopment project were significantly below 100%. This was occasioned by the COVID-19
pandemic that led to change in MoFPED’s funding priorities. Figure 1 shows the percentage
disbursements to the different categories of DAs and sub-agencies made by URF during FY
2019/20.
It can be seen from Figure 11 that the biggest portion of the disbursements went to UNRA
(63.8%) for maintenance on the national road network while the rest was shared between
maintenance of the DUCAR network and KCCA roads, with the residual going to the URF
Secretariat. Figure 12 shows a disaggregation of the disbursements as percentages of the
respective approved annual budgets in FY 2019/20 across the various expenditure heads.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
105
It can be seen from Figure 12 that Local Governments and the URF development project
received significantly less than 100% of their approved Indicative Planning Figures
(IPFs)
Table 66 shows the summary of performance of expenditures against available funds for FY
2019/20.
Funds Total
Annual Actual Unspent % of avail-
rolled Releas- Funds
Bud- Expendi- balanc- able funds
Agency over es FY avail-
get FY ture FY es FY absorbed
from FY 2019/20 able FY
2019/20 2019/20 2019/20 FY 2019/20
2018/19 2019/20
It can be observed from Table 66 that when measured at the end of Q4 FY 2019/20: UNRA,
KCCA and the URF Secretariat had absorbed all the funds that were availed to them during
the FY; while as at the end of Q3 FY 2019/20, DUCAR agencies had not yet absorbed 36% of
the annual funds availed to them. Total absorption of road maintenance funds was at 89.8%
of releases, however it was expected to rise in excess of 98% upon consideration of the Q4
absorption by DUCAR agencies.
106 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Figure 13 shows a graphical representation of the financial performance of the various main
expenditure lines in FY 2019/20.
It can be observed from Figure 13 that while UNRA, KCCA, and the URF Secretariat had good
absorption of the funds availed to them in FY 2019/20, the absorption of DUCAR agencies
was out of sync with time progress by about 11% as at the end of Q3.
9.2.3 PERFORMANCE AGAINST THE 14TH JTSR ACTION PLAN MATRIX AND
PROGRESS
The key action points for URF in the 15th JTSR action plan matrix and the respective achieve-
ments are provided in Table 67.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
107
TABLE 67: PROGRESS OF URF ON THE 15TH JTSR ACTION PLAN MATRIX
The budget estimate for road maintenance under vote 118 in FY 2020/21 is UGX 512.175bn.
This represents an increment of UGX 63.343bn which is 14.1% of the FY 2019/20 approved
budget. Table 68 shows the broad allocation of the funds across the various road network
categories.
Based on expressed needs of Agencies in the amount of UGX 1.2 Trillion in FY 2020/21, there
will be a shortfall in funding of UGX 653Bn made up as follows: National roads UGX 398bn;
and UGX 255Bn for the DUCAR network including KCCA. The effect of the shortfall will be
reduced level of periodic maintenance especially on the DUCAR network, which will conse-
quently increase the maintenance backlog.
Table 69 shows a summary of the key road maintenance activities planned to be funded in FY
2020/21 as compared to FY 2019/20.
It can be seen from Table 69 that, on both national roads and DUCAR network, there was a
general increase in the quantities planned to be funded under all works categories due to a
12.6% increase in the budget for maintenance of national roads and DUCAR network.
In the medium term, FY 2020/21 – 2022/23, URF plans to adopt the strategies in Table 70 to
improve operations of the Fund and road maintenance financing.
110 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
1 Promote use of • Revamping the use of road FY 2020/21 This is expected to support
road management maintenance management – 2021/22 planning and programming
tools/software systems of road maintenance works in
DUCAR agencies.
2 Establish regional • Zone LGs into 4 regions FY 2020/21 TSUs will support LGs in
Technical Support • Progress the Roll out and implementation of their road
Units (TSUs) for strengthening the TSUs maintenance programmes
LGs including preparation of good
quality work plans, works
implementation, preparation
of good quality reports and in
a timely manner.
1) Inadequate funding for road maintenance which has fundamentally reduced periodic
maintenance and driven backlog build-up. The approved road maintenance budget for
FY 2019/20 (UGX 448.833bn) constituted 0.36% of Uganda’s GDP (UGX 126,258bn), well
below the minimum recommended of 0.85%.
2) Failure to commercialise roads management to entrench market principles all through the
management cycle to save and protect asset value and ensure significant gains for road
users. This is occasioned by parliamentary appropriations based on normal budgetary
allocations which are not related to road usage and condition as envisaged in the URF
founding Act.
3) Lack of precise real-time knowledge on size and state of the road asset which clouds
planning and budgeting, more seriously dampening ability of URF to accurately evaluate
the programmes of DAs.
In mitigation, URF is incrementally rolling out TSUs and it will continue to work with
other government entities in addressing the various forms of capacity gaps in DUCAR
agencies.
District equipment at
Ngora District yard
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
113
The rural Transport Infrastructures (RTI) is implemented by the Ministry of Works and
Transport. It is a continuation of 15 years of Danish support to Uganda Road Sector Programme
(RSPS) and Rural ROAD Programme (RRP).
The districts in which projects were undertaken in the financial 2019/20 were 24 namely;
Katakwi, Kumi, Lira, Soroti, Amuria, Oyam, Dokolo, Bukedea, kole, Kwania, Kapelebyong,
Alebtong, Serere, Ngora, Kitgum, Apac, Kaberamaido, Nwoya, Pader, Amolatar, Lamwo, Am-
uru, Kalaki, Otuke, Omoro, Agago and Gulu.
Table 71: showing the physical performance of the RTI projects in FY 2019/20
Fareway junction
116 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Table 1.1 shows the financial performance of KCCA under the Directorate of Engineering and
Technical Services (DETS) for FY 2019/20 for Transport Sector projects and programmes. The
budget release for FY 2019/20 was 100 % of the approved budget.
The total GOU released funds as at June 2020 was UGX 96.8bn against a budget of UGX
96.8bn, which is 100% of the budgeted funds released. Of the UGX 96.8bn released a total of
UGX 48.1bn was specifically for roads construction.
The total URF released funds as at June 2020 were UGX 31.9bn against a budget of UGX
31.9bn which is 100% of the budgeted funds.
Table 72: KCCA Financial Performance for FY 2019/2020
DIRECTORATE OF ENGINEERING AND TECHNICAL SERVICES BUDGET ABSORPTION REPORT JULY- JUNE FOR FY 2019/20
DESCRIPTION OF EXPENDITURE ITEM BUDGET TOTAL WARRANTS TOTAL EXPENDITURE BALANCE ON Budget Vs Releases Vs
WARRANT Releases Expenditure
Q1,Q2,Q3,Q4 Q1,Q2,Q3,Q4
DETS-Operations Mechanical
DETS-MV Repairs and Maintenance- 1,500,000,000 1,500,000,000 1,494,076,463 5,923,537 100% 100%
Road Equipment
Maintenance and Repairs of Street 900,000,000 900,000,000 900,000,000 5,923,537 100% 100%
Lights and traffic lights
Sub-Total 2,400,000,000 2,400,000,000 2,394,076,463 11,847,074 100% 100%
DETS- Casuals 300,000,000 300,000,000 300,000,000 - 100% 100%
roads
DESCRIPTION OF EXPENDITURE ITEM BUDGET TOTAL WARRANTS TOTAL EXPENDITURE BALANCE ON Budget Vs Releases Vs
WARRANT Releases Expenditure
118
Maintenance of street lights and traffic 1,000,000,000 1,000,000,000 985,392,760 14,607,240 100% 99%
junctions
Road marking and Road Furniture-Road safety & Traffic management works 1,298,400,001 1,599,999 100%
1,300,000,000 100%
1,300,000,000
Purchase of new light equipment 734,000,000 734,000,000 734,000,000 - 100% 100%
Asphalt -concrete Stone- base- Road 11,063,160,749 11,063,160,749 11,090,031,010 (26,870,261) 100% 100%
aggregate-Hardcore-Quarry dust
Cement Safety signs & protective wear
Extra Funding for the Kyanja yard-
Murram-Tack Coat K160-Emulsion
Primer-Sand-Bitumen -Periodic
Maintenance
KCCA contributes towards the performance of mainly two golden indicators i.e. Paved roads
and travel time within GKMA.
Kampala City comprises 2,110km of roads of which 623km is paved and 1487km is unpaved.
These figures were derived from a study commissioned by KCCA in 2013 to undertake a roads
inventory and conditions assessment, which established an accurate database/inventory of
all road infrastructure within KCCA area of jurisdiction and its condition.
i) In the period June 2019 to June 2020 only 10.05km of roads was completed under GOU
funding. These included NMT Pilot Corridor (Namirembe-Luwum-1.5Km), Munaku
Road-0.8Km, Sebatendera-0.6Km Nsambya-Katwe-0.9Km, Kevina-1.2Km, Jjuko-
1.3Km, Kirombe Road-1.2Km, Queensway-1.6Km, Kalema Road-0.4Km, Lakedrive-
1.8Km, Naguru Hill Rise- 0.5Km
The travel time in Kampala is 4.1 minutes /km. which translates to 14.6Km/hr compared to
4.2minutes/km in FY 2017/18.
In the FY2019/20 KCCA did not sign any new contracts for new road upgrading/reconstruction
works. This is because there were ongoing multiyear contracts that were signed at the end of
FY2016/2017 and these have been running over last three financial years under GOU funding
and have now been completed. These contracts involved upgrading and reconstruction of
selected city roads totaling 44.85Km.
Road improvement works under ongoing contracts in the reporting period FY 2019/2020
had the following roads and have now been completed:
Table 73: Road improvement works under ongoing contracts in the reporting period FY
2019/2020
The road works under these contracts are all completed. The progress on the various ongoing
roads contracts is summarized in Table 74;
Table 74: Status of Ongoing Road Projects
120
Item Total Contractor and Commencement Duration Completion Progress as at June Progress to date
No. Length Contract Sum Date (Months) Date 2019 and Remarks
Contract Name
Km)
Roads Contracts (GOU Funding)
FY2019/20
1 Lot-1; Design update and construction of 5.4 M/s. Stirling 16th June 2016 36 Months 28th Febru- All roads were All roads
roads in the City-; Reconstruction and/or Civil Engineer- ary 2020 completed except completed and
Upgrading of roads in Central Division. ing Ltd Namirembe-Luwum works under
Street Defects Liability
a) NMT pilot corridor Namirembe-Lu- Period
wuum-1.5km,
b) Archer-0.75km,
c) Mengo hill-0.75km, Overall progress was
d) Nakivubo channel-0.5km, at 89%.
ANNUAL SECTOR PERFORMANCE REPORT
e) Mpabaana-0.75km,
Contract Sum
f) Luzige-0.3km ,
g) Mutebi-0.45km, UGX
Semugooma-0.4km
29,965,137,084
2 Lot-2; Design update and construction of 16.10 M/s. Energo 17th June 2016 36 Months 17th Decem- Works had been sub- All roads
roads in the City; Reconstruction and/or Projekt Nisko- ber 2019 stantially completed completed and
Upgrading of roads in Lubaga and Kawempe gradnja A.D on all roads except works under
Division Munaku Road Defects Liability
Period
a) Jakaana -0.65km,
b) Nsooba-0.75km,
c) Kafeero-0.8km, Overall progress was
d) Lumasi-0.55km, at 86%.
e) Muganzi-Awongera-1.6km,
Contract Sum
f) Waligo- 4.2km
g) Lungujja road-1.6km, UGX
h) Nakibinge-Bawalakata-2.9km,
i) Mackay-1.6km
j) Sembera-1.5km, 65,510,289,035
k) Concrete Box Culvert at Nalukolongo
Channel
l) Munaku Road-0.8Km
m) Sebatendera Road 0.6Km
3 Lot-3; Design update and construction of 7.35 M/s. Abubak- 13th June 2016 36 Months 20th June Works were complete Works are
roads in the City; Reconstruction and/or er Technical 2020 on Kulekana and Kev- ongoing on Ns-
Upgrading of roads in Makindye division Services and ina Road. ambya –Katwe
General Sup- road, Appas
a) Kulekana-2.1km, plies Ltd road and Juuko
b) Nsambya-Katwe-0.95km, Road.
c) Jjuko-1.3km, Contract Sum: Works were ongoing
d) Kevina-1.2km, on
e) Appas-1.3km UGX
f) Kirombe Road-2.1km Nsambya –Katwe Overall, physi-
road, Appas road cal progress is at
38,463,800,967 64%.
and Juuko Road.
4 Lot-4; Design update and construction of 12.15 M/s. Stirling Wednesday 8th 16th Decem- Works had been sub- All roads com-
roads in the City; Reconstruction and/or Civil Engineer- June 2016 ber 2019 stantially pleted and
Upgrading of roads in Nakawa Division ing Ltd works under
complete on all Defects Liability
a) Magambo-0.9km, Period
b) Dembe-Kilowoza-3.0km, roads.
c) Kiziri-0.75km, Contract Sum:
d) Kigoowa-1.9km,
e) Kimera-1.4km, UGX
Overall physical prog-
f) Kisalita-0.7km,
ress was at 96%
g) Kisosonkole-1.0km, and
34,784,061,713
h) Robert Mugabe-1.8km
5 Extended periodic maintenance of Park lane 0.5 Kiru General 16th April 2020 4Months Works are ongo-
road-0.5km, in Central Division Services ing and overall
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
Signalization of Ben Works involved traffic Signalisation of the Works were completed
Kiwanuka/Luwum street Ben Kiwanuka/Luwum street junction as by 20th July 2020.
junction GoU part of the Non-Motorised transport Project
KCCA projects under the Kampala Institutional Infrastructure Development Project (KIIDP)
with funding from the World Bank. The Government of the Republic of Uganda received a
Credit from the International Development Association (IDA) -Cr. 4367-UG, to implement the
Kampala Institutional and Development Infrastructure Development Programme Phase-2
(KIIDP2) through KCCA. In this period, KCCA continued with implementation of signed
contracts for execution of the following road works under KIIDP. A tender for reconstruction
and upgrading of several roads in the city using funds from the World Bank was awarded
which has a component of installation of traffic signals at thirteen (13) locations and works
commenced in May 2019.
The Batch-2 roads subproject is divided into three lots. The details of the respective contracts
signed for the civil works are as highlighted in Table 76 below.
ii) Lot 2: Upgrading to paved standard of Kabuusu – Bunamwaya - Lweza Road (8.06Km)
- Awarded to Contractor M/S China State Construction Engineering Corporation
Limited,
iii) Lot 3: Recycling and Overlay of Lukuli Road (7.71Km) including signalisation of Lukuli/
Namasoole/Kayembe junction- awarded to: M/s Stirling -Sobetra Joint Venture.
Table 76: Details of the Batch 2 Civil Works Contracts
Under
review.
Contractor
M/S China State
Upgrading to Paved Stan- has
Construction
dard of Kabusu – Bu- 28th March 15 16th August requested
Lot 2 Engineering 17th May 2019 458 N/A 410 89.5
namwaya - Lweza Road 2019 months 2020 for
Corporation Ltd.
(8.06km) extension
(CSCEC)
up to 31st
December
2020
5 EoT approved by CC during their 432th sitting on 12th June 2020 and was submitted to the Bank and now waiting for their No Objection
124 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
KCCA also engaged and signed contracts with M/s C. Lotti & Associati Società Di Ingegneria
SpA of Italy in association with UB Consulting Engineers Ltd of Uganda) to provide the
following services:
Lot 2&3 Consultancy Services for Design 28th March 17th December 30 months 16th August
Review and Construction 2019 2018 including DLP 2021
Supervision for Upgrading to
Paved Standards of 8.5 Km of
Kabuusu - Kitebi - Bunamwaya
Link under Lot 2 and Recycle
and Overlay of 7.8 Km, including
signalization of 1 Junction
of Lukuli Road in Makindye
Division
In addition, KCCA and JICA are in advanced stages of commencing a project for signalization
of thirty (30) more junctions in the city and construction of a traffic control center. This
project is expected to start in December 2020.
In the FY2019/20 a total of UGX 1.9 billion was allocated for maintenance and repair of street
and traffic lighting. As at end of June 2020, UGX 1.9 billion had been released and UGX
1.89Bn was spent on the maintenance and repairs for street and traffic lights. The streets
where lights were installed are in the Table 78:
i. Disruption of works due to the government restrictions imposed following the out-
break of the COVID-19 pandemic, as the Contractors had to suspend works for some
period after the partial lockdown directed by the President of Uganda. They subse-
quently declared a force majeure event as a result.
ii. Dilapidated Road Network. Most of the roads need overhaul as they have outlived
their existence and the road repairs tend to be too costly and serve little or no value
as new potholes continue to develop.
iii. Limited capacity of Road Network: The road network in Kampala has limited capacity
and was not built for the high volume traffic of recent years that has contributed to
severe congestion.
iv. Lack of adequate road reserves: Most roads are unplanned and lack adequate rights
of way for improvement. This makes road improvements very costly as the required
geometrical designs cannot be achieved without significant resettlement and acquisi-
tion of rights of way.
v. Lack of safe NMT facilities: Although most trips are pedestrian, there is a lack of pe-
destrian facilities on most roads. In many cases pedestrians are forced to share car-
riageways with vehicles exposing themselves to accidents. Provision of walkways and
cycle paths is hampered by lack or right of way and limited funding.
vi. Lack of an integrated and affordable public transport system: The public transport
system is fragmented and dominated by low capacity minibuses and boda bodas. A
mass transit system is needed to serve as the back bone of the transport system in
Kampala.
vii. Under Funding: The combined funds available to road construction from Govern-
ment allocations and KCCA’s own resources are insufficient to finance needed infra-
structure improvements that address the continuous growth of traffic in Kampala,
notwithstanding the current traffic problems in the city.
126 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
Government of Uganda through MoWT appropriated UGX 558.32 billion to the Uganda
National Airline project, UGX 525.49 billion was received (94.1%) and spend by the end of the
financial year. USD 53.6784 million approximately UGX 199.41 billion was to complete the
pre-delivery payments on the two Airbus A330-800neos, USD 41.5 million approximately
UGX 154.01 billion to Bombardier to pay for the last batch of the two CRJ-900 aircraft, USD
20 million approximately UGX 74.3 billion as refund to the operational funds that were used
to pay the initial Airbus prep-delivery payments and UGX 19.7 billion as part of the GOU
funds to capitalize the Airline.
In addition to the above, the Government has committed to release a total amount of UGX
112.5 billion in batches of UGX 28.125 billion as subvention expenditures towards the compa-
ny’s capitalization.
All pre-delivery payments to Airbus were made, the final payments to Bombardier were
made and the two CRJ -900 Aircraft were delivered in October 2019.
As at end of the financial year UGX 32.825 billion relating to Airline’s capitalization had not
been received.
Prior to the two aircraft delivered in October 2019 making the total fleet of four Aircraft, the
first batch of two CRJ900 Aircraft had been delivered in April 2018 and payments were fully
made
Eight regional routes have been opened and finished in Somalia, Juba, Nairobi, Dar es Salaam,
Bujumbura, Kilimanjaro, Mombasa and Zanzibar. Staff were recruited and currently they are
operational.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
129
The airline has been realizing the increasing trends of passengers and revenues before
Covid-19. From January 2020 till closure of commercial operations in Mach 2020, the Airline
was realizing reduction in passenger numbers and as a result of Covid-19.
Government through Ministry of Works and Transport also made all agreed pre delivery
payment for two Airbuses for the National Airline which are expected to be delivered in
December 2020 and January 2021 respectively
130 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
• Implement the Airlines core systems; that is the Enterprise Resource Planning system
and the Passenger Service System.
• Take delivery of the two A330-800 Neo Aircraft and launch long haul operations into
China, London, and Dubai.
• Set up a unit for self-handling of the Aircraft at Entebbe International Airport
• Conclude plans to register a local Approved Maintenance Organisation and start
self-maintenance
• Conclude negotiations for slots in all destinations planned for expansion
The plan also includes the identification of opportunities for joint-venture investment in non-
core airline related businesses business class lounges, on-board self-catering, and customer
services at Entebbe airport.
(a) The COVID 19 affected the operation of the airline which forced the government
shut down of the airport for passengers leaving only the operations of the cargo.
The Airline has not developed its cargo business yet and as such missed out on this
opportunity to carry cargo in and out of the country.
(b) Slow process of designation process of the Airline in the different countries and
destinations of choice that has delayed the launch of other regional routes that are on
the Airline’s plan.
(c) Non-disbursement of the of the Government Budgetary Support as committed and
scheduled that has an impact on the operationalization of the planned activities of
the Airline.
(d) Delayed implementation of approved airline incentives by government especially
those relating to waivers of taxes, charges, the grant of premises for the airline head
office, business class lounge and the grant of land for building hangars, catering units
and other complimentary services.
(e) Delayed activation of the Airline in the Global Distribution systems which makes the
Airline not visible by the Global Travel agents hence missed possible sales. This also
makes the indirect access the Company goes through using its Interline Partner APG
for it to be visible costly as this comes with an additional cost of Euro 30 per ticket sold
through this channel.
(f) High operating costs through third party service providers of inflight catering,
handling services at Entebbe and Aircraft maintenance services which make the
operation costly.
(g) Inability to activate code share and full interline partnerships with legacy Airlines
because the Airline is not yet IOSA certified. This limits the additional revenues that
could come from such partnerships.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
131
Annexs
1
Annex 1
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
133
2
134 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
3
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
135
4
136 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
5
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
137
6
138 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
7
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
139
8
140 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
9
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
141
10
142 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
11
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
143
12
144 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
13
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
145
14
146 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
15
Annex 2
Annex 3
The progress on the Bridges under procurement, Handed over to contractor and feasibility
/study/designs
9 Kagera Designed
11 NakadidirLukolwe- Designed
Namuganga swamp crossing
12 NyahukaMirambi Designed
13 Komorotot Designed
16 Karujumba Designed
17 Bugibuni-Bunadasa Designed
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
149
Annex 4
Performance of Roads Rehabilitation in FY 2019-2020 by the District Road Units in the
Central
*** Ibanda-Kisara-Mukabara road; Works on this road will not go as planned due to land
related issues that are attracting compensation.
* Wobulenzi-Woluleta was done under the training program
## 2nd Street Road – These were emergency works requested by OPM Corona Virus Taskforce.
Annex 5
PERFORMANCE OF INTERCONECTIVITY PROJECTS IN THE FINANCIAL YEAR 2019/20
150
001 Kayolo - Kijwala - Kivumbula - Sanje - Manjeri Road Rakai - 11.0 98% 100% 2% Works completed
(11.0km) in Kooki Consticuency, Rakai District Kooki
002 Buyojwa - Lyakisana Road (2.1km), Katoogo - Kamuraba - Rakai 11.5 75% 100% 25% Works completed
Kayunga Road (2.3km), Bwenyege - Runoni Road (4.2km) -Buyamba
and Nsimbo - Kyabalemela Road (2.9km) in Buyamba Con-
sticuency in Rakai District; (Total Length =11.5km)
003 Kyankanda - Bwooga - Kibirya Road (15.0km) in Buhweju Buhweju 15.0 48.0% 100% 52% Works completed
ANNUAL SECTOR PERFORMANCE REPORT
District
004 Nfasha - Kigunguzo - Rwabahondame Road (8.0km) and Rubanda 11.5 50% 95% 45% Works substantially
Kitagata - Mushanje Road (3.5km); Total Length = 11.5km complete
005 Rwesande - Kisoda - Kabatunda - Kitoha - Butswa Road Kasese 13.5 100% 100% 0% Works completed
(7.0km) and Kikonzo - Kinyabwamba - Kihyo - Kithoma
market road (6.5km) in Busongora North Constituency
(Total Length = 13.5km)
006 Kizungu Rise in Nyamwamba division (0.6km), Mariseri Kasese Mu- 8.1 90% 100% 10% Works completed
road in Nyamwamba division (0.5km), Mumbuzi-Basecamp nicipality
road (1.5km), Nyamwamba west road (0.5km), Mumbuzi 2
(0.1km), Nyakasanga Upper (1.0km), Mutanywana road in
Central division (1.8km), Kidodo road (1.2km) and Land fill
road (0.9km) (Total Length =8.1 km)
007 Butungama - Budiba (6.3km) and Makondo - Kanyamukura Ntoroko 12.3 92% 98% 5% Works substantially
(6km); Total Length = 12.3km complete
008 Nagweny Road (4.58km), Nawango Kifayunjwa Road Kamuli 20.28 95% 100% 5% Works completed
(1.2km), Bufasaga Buwoya Butasaga Road (1.9km) and Bu-
nandolo - Buyanda Busuubo - Namaira Buyero - Budaudhi
(4.3km) in Bugabula South and Kisakye - Kazinga - Nan-
sololo - Kisaikye Road (8.3km) in Bugabula North; Total
Length = 20.28km
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
009 Namanda - Manyanwe - Bubalya Road (3.0km), Muhuyu Butalleja 13.5 95% 100% 5% Works completed
- Binda - Malagha road (3.0km), Busolwe - Busaba road
(4.5km) and Busaba - Budira - Bugumu - Busolwe road
(3.0km); Total length = 13.5km
010 Otimong Road (2.6km), Kongoto Amukaru Road (2.1km), Serere 16.63 98% 100% 2% Works completed
Okulukulun Kagwara Road (1.9km), Olwa Kanungu - Ogan-
gai - Opeduru Road (7.40km) and Nakabira - Atiragato Road
(2.63km); Total Length =16.63km
011 Chebinyiy Kaptum Sundit Road (11.6km) Kween 11.6 35% 95% 60% Works completed.
Challenges with rock
blasting.
012 Akura Health Centre II – Agoro- Atiriglwo- Okwalo Moko Alebtong 9.0 80% 100% 20% Works completed
Market Road (6.9km), J B Odwee Road (1.1km) and Okello
Field Marshall Road (1.0km); Total length = 9.0km
013 Ocen - Olekata - Matailong Road (5.0km) and Nyada Road Amuria 10.0 100% 100% 0% Works completed
(5.0km); Total length = 10.0km
014 Atabu – Alenga Road (8.8km) Dokolo 8.8 95% 100% 5% Works completed
015 Iiri Iri - Nabwal Road (10.0km) Napak 10.0 90% 100% 10% Works completed
016 Bunaseke - Bugiboni Road (2.2km), Buyobo - Logotani - Sironko 10.8 76% 100% 24% Works completed
Soroti (4.0km), Nangooli -Butandiga Road (2.6km) and
Nakayindira Road (2.0km); Total km = 10.8km
017 Kabole - Chebeser Road Section (4.0km), Sirimityo - Amukol Kapchorwa 13.8 70.0% 98.0% 28% Works substantially
- Kapsayik TC (7,1km), Kayeywa - Loch Road (2.7km); Total complete.
length = 13.8km
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
018 Asuret - Magalo Road (6.9km) and Asuret - Atiira Road Soroti 10.3 100% 100% 0% Works completed
(3.4km); Total km=10.3km
151
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
152
019 Bong Cao-Corner Boroboro Road (7.1km), Awiirao Prima- Lira South 20.0 80% 100.0% 20% Works completed
ry School - Otai Village Banya Parish Road Section (3km)
includes Swamp Filling, Abongo Rwot Corner Pajero Road
(4.0Km) including Swamp Raising and Barjwinya - Barobo-
FY2019/20
020 Anai P/S-Wigweny Road (5.4km), Barpwo - Ongicab Road Lira North 19.6 80% 97.5% 18% Works substantially
Section (4.2km), Aromo T.C - Bapii - Aromo P/S Via Aleka completed. In DLP
Swamp (5.0km), Aromo TC - Bapii - Aromo P/S - including
Aleka swamp crossing (5.0km); Total length = 19.6km
021 Kinyara - Mukangala - Maguniya - Kandaha (4.2km), Mukono 16.8 95% 97.5% 3% Works substantially
Namaziba - Kitovu - Buyizi (2.9km) and Mbogo Road (2.7km) and Buikwe completed. In DLP
ANNUAL SECTOR PERFORMANCE REPORT
022 Busabala - Kibila - Salama Road (2.1km), Kibila - Kabuuma Wakiso 7.1 80% 90% 10% Works substantially
- Gangu (2.8km), Kibutika II (1.2km), Ndejje - Zaana (1.0km); complete. Had chal-
Total length = 7.1km in Makindye Ssabagabo Municipality lenges with relocation
of service lines.
023 Butanza - Ngabo - Lutembe (4.0km), Lukiizi - Kibaaga - Luwero 26.2 85% 95% 10% Works substantially
Nanywa (6.4km), Kawula - Nalulya (2km), in Katikamu complete
County North and Bugalama - Buyondo - Kamwano - Kan-
juki (4.8km), Bukembya - Buwakibila - Bakijulula (3.2km)
and Kibiike - Gangu - Kiryambidde - Kungu (5.4km); Total
length = 26.2km
024 Buwungilo - Kawuku (4.9km), Buyobe HCII - Bulyankuyege Kayunga 20.3 90% 100% 10% Works completed
(2km), Bulyankuyege - Busolo - Kiyagi (3.6km), Katikamu -
Busaale (1.5km), Katikamu - Namatogonya (1.3km), Bubajjwe
- Nalumuli - Nakaiba - Nakatovu (4.3km), Bwetyaba Kafuge
- Ntooke (2.7km) in Ntenjeru North, Kayunga District; Total
length = 20.3km
025 Rehabilitation of Kawongo - Kitwe - Kalenge - Misozi Road Kayunga 20.5 100% 100% 0% Works completed
(5.4Km), Baale - Kyasande - Kyantala Road (5.0Km), Bu- Baale
lawula - Nawankonge Road (5.1Km), Nsamba Close (0.6km),
Wankya Road (3.1km) and Kavule 2 Road (1.3km) in Baale
Consticuency, Kayunga District; Total length = 20.5km
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
026 Nsobiiri A Shopping centre to Kalamba Gombolola via Kis- Mpigi 4.9 100% 100% 0% Works completed
unwinu and Kalagala road (4.9km)
027 Ojigo Pakwinyo Emin Pasha Road (5.9 km), Ajibu Thendir Pakwach 11.3 92% 100% 8% Works substantially
Landing Site Road (2.53 km) and Palam Community Road complete.
(2.9 km); Total length = 11.3km
028 Wabusana Lugogo Road (2.83km) and Lugogo Lwenyana Nakason- 10.13 95% 95% 0% Works substantially
Road ( 7.3km); Total length = 10.1km gola complete
029 Streets in Pakele Town (Perina - 0.8km, Drani - 0.7km, Olal - Adjumani 15.23 90% 100% 10% Works completed
0.4km, Rasigala - 0.4km, Alakai - 0.15km, Adikesi - 0.15km, - Adjumani
Koli - 0.15km, Husen - 0.9km, Ingi - 0.4km, Eture - 0.65km, East
Lazaro - 0.65km, Duka - 0.8km, Ereme - 0.3km, Mondia -
0.4km, UNHCR - 0.4km) roads, Army road - 1.6km and Olia
- Tilorio - 5.1km; Total length = 15.23km
030 Tindibakira Road (0.7km), Banyagyi Road (0.95km) and Ntungamo 3.05 95% 95% 0% Works substantially
Kajyinya road (1.4km); Total length = 3.05km complete
031 Olua - Katirina road (5.5km), Cilio road (5.1km), Onai - Arua 20.25 62% 95% 33% Works Substantially
Oluodri road (2.5km), Ozufe road (4.5km) and Liria Ajiraku complete
Road (2.65km); Total length = 20.25km
032 Kyabagyenyi – Kyanda Road (10.8km) in Nyabushozi Kiruhura 23.1 50% 100% 50% Works completed
County and Rwozi I – Banywana Farm – Kabambaija Bright
Heart School (4.0km) and Nyaburunga I Coffee Factory –
Rwemamba TC (8.3km) in Kashonji County; Total length
=23.1km
033 Buyenja – Kashuro – Kyakatugunda TC (10.9km) Mbarara 10.9 98% 100% 2% Works completed
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
034 Kati – Bitereko – Rutokye Road (18.1km) Mitooma 18.1 55% 70% 15% Works ongoing
035 Kinyamashe – R. Kiruruma - Kanyambeho - Katafari Kanungu 12.0 80% 98% 18% Works ongoing
153
036 Rwambu - Rwenkuba - Burambira - Kayanja - Rusoro - Ibanda 20.1 50% 97.5% 48% Works substantially
Rwanyakabogo - Kamwiri - Rwenkobwa Road (20.1km) complete
037 Busweka - Naluntuntu Road (5Km) and Kabudubutu - Mubende 10 100% 100% 0% Works completed
Bbinikira Road (5km); Total length = 10.0km
FY2019/20
038 Nyakinombe - Kyewanura - Buyanja road (9.5km) and Off- Lyantonde 9.62 98% 100% 2% Works completed
set road - Lwengo boarder (0.12km); Total length = 9.62km
039 Ruyanga - Kibuba - Kabatangare (13.2km) Isingiro 13.2 95% 100% 5% Works completed
040 Bweza - Busimo - Nvunjwa (4.80km), Minoni - Nawankole Mayuge 20.7 65% 97.5% 33% Works substantially
- Kasokwe (2.90km) and Kyikubo - Ivugunhu Road (1.4km) complete. In DLP
in Bunya East Constituency and Bulubudde - Corner bar -
ANNUAL SECTOR PERFORMANCE REPORT
041 Nabiina - Buwabe - Nsozi ibiiri (12.0km) and Kiwanyi - Iganga 35.5 75% 90% 15% Works ongoing
Namusiisi - Bugambo - Bunyokano - Bugongo - Nawandala
(23.30Km) in Iganga District; Total length = 35.5km
042 Kitaleesa - Mwaro - Mukabingo - Nkakwa - Kiterede Road Kyegegwa 11.5 80% 100% 20% Works completed
(11.5Km)
043 Runga - Waaki - Butiaba (19.2km) Hoima 19.2 90% 100% 10% Works completed
044 Katungo - Kyantamba - Muyenje Road (8.0km) in Kiboga Kiboga and 23.9 80% 100% 20% Works completed
District and Lubiri - Cardinal Nsubuga - Kasejere Road Kyankwan-
(10.5km) and Kasejere - Nakakabara P/S (5.41km) in Kyank- zi
wanzi District; Total length = 23.9km
045 Kakumiro - Kinena - Mpanga (7.7km), Kyabashija CoU - Kakumiro 24.7 78% 100% 22% Works completed
Mukasagazi - Bendikito including Kitanda - Irwaniro Road
branch (8.5km) and Kisiita Market - Kyakajoro - Kadandali
(8.5km); Total length = 24.7km
046 Kachuru P/S - Kongoidi Road (1.1km), Kachuru - Komolo Bukedea 21.4 50% 100% 50% Works completed
Road (5.4km) and Amus Sapir - Amus Kireka Road (4.7km) and Kumi
in Bukedea District and Apuda - Isaiah Oonyu road (0.8km),
Atutur - Kalomongole (3.5km), Kakomongole - Bukedea road
(0.8km) and Olupe - Ongerei (5.1km) in Kumi District; Total
length = 21.4km
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
047 Buluganya - Buhokadala - Bulago Road (10.2km) Bulambuli 10.2 85% 98% 13% Works substantially
- Elgon complete
County
048 Tabagonyi - Logi - Atari Road (9.8Km) Bulambuli 9.8 55.0% 90.0% 35% Works ongoing.
-1 Heavy rains delayed
progress and some in-
stalled culverts were
washed away
049 Gadumire - Nsamule Road (9.2km) in Kaliro District and Kaliro and 22.2 97.5% 97.5% 0% Works substantially
Nawansagwa - Bugobi - Kyabakaire (13.0km) in Namutum- Namutum- complete. In DLP
ba District ba
050 Senda - Mwenge Road (starts Opp Senda P/S) (7.7km), Pas- Tororo 11.8 55% 100% 45% Works completed
aulo - Morikiswa - Namwaya road via Rukuli road (2.0km)
and Atapara - sengo road (2.1Km); Total length=11.80km
051 Mile 9 Off Tarmarc of Mbale Highway - Kamonkoli S/C Budaka 14.8 95% 100% 5% Works completed
Headquarter (4.3km), Namirembe TC - Late Balachi Kiirya
Farm - Hajji Yusuf Road Section (4.9km) and Nabugabo
TC - Kameruka PS terminating into Ikiki Kanghima road
(5.6Km); Total length = 14.8km
052 Bulucheke - Muchomu - Nyende Road (8.4km) Bududa 8.4 50% 50% 0% Works suspended.
Works delayed due
to heavy rains and
the need for blasting
rocks in the road
corridor.
053 Pagirinya - Latodo Road (11.7km) Adjumani 11.7 90% 95% 5% Works substantially
complete. In DLP
054 Ikulwe - Buyemba - Bukatube - Lwanika Landing Site Road Mayuge, 33.3 60% 100% 40% Works completed
(13.3km) and Baitambogwe - Mbilizi - Magunga - Mbaale Luuka and
Road (9.0km) in Mayuge District and Wainya - Bulanga - Jinja
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
055 Rehabilitation of Elema - Kalamuka - Mgbili Road Section Adjumani 14.4 0% 48% 48% Progress was slowed
(8.4km), and Eciya - Boroli Central Village (6.0km) in Adju- down by Covid 19 and
mani district; Total Length= 14.4km bad weather
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
156
056 Rehabilitation of Ogini Junction – Awiepek Center Road Alebtong 14.4 0% 68% 68% Works ongoing (grav-
(6.9km), St Monica sign post - Apunga – Ateno (3.5km) and elling, filling & culvert
Anara P/S - Te Oriang (4.0km) in Alebtong district; Total km installation)
FY2019/20
= 14.4km
057 Rehabilitation of Okoboi - Akulony - Acinga Road (9.7km) Amuria 15.3 0% 90% 90% Works ongoing. In-
and Olekat - Matailong Road (5.6km) in Amuria district; stallation of culverts
Total length = 15.3km & end structures in
progress
058 Rehabilitation of Itia -Ogboa Road (10.0km) in Arua district Arua 10 0% 90% 90% Completion expected
within the Contract
Period
ANNUAL SECTOR PERFORMANCE REPORT
059 Rehabilitation of Naboa Kakoli - Kabyonga Road (6.2km), Iki Budaka 16 0% 90% 90% Works substantially
Iki - Petete - Kadenge Road (5.5km), Puwatah - Nyire Road completed. Contractor
(2km) and Asadi - Hamudan (2.3km) in Budaka district; issued with a snag list
Total km = 16.0km to rectify before is-
suance of completion
cert. Cert 1 paid.
060 Rehabilitation of Natoolo - Kikholo - Sakusaku (5.6km) and Bududa 11.1 0% 48% 48% Opened the two
Mabale - Wakamala (5.5km) in Bududa district; Total length roads; gravelling and
= 11.1km drainage works in
progress
061 Rehabilitation of Itoolo Bulidha - Busano - Busakira - Mako- Bugiri 14.7 0% 70% 70% Works ongoing.
ma I Road (14.7km) in Bugiri district Change order adding
another road issued
062 Rehabilitation of Karokogoto - Ahamudara - Kamukaki Buhweju 15 0% 60% 60% Works ongoing.
(5.0km), Bwooga - Kibate (2.0km), Kikondera - Kidandari - Shaping and common
Kanunka (6.0km) and Kidandari - Itorero (2.0km) in Buhwe- excavation in progress
ju district; Total Length = 15.0km
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
063 Rehabilitation of Mpummude Kiyunga (konko parish) Buikwe 23.38 0% 45% 45% Works ongoing.
Wakisi Division Road (1.95km), Matovu Kidaga (Wakisi Hindered by Covid 19
ward Division) Road (1.2 km), Wankwale Bugoba Health pandemic
Centre II (Kabizi ward) - Nyenga Division Road (5.7km),
Owuma Kaibirwamu Gandege (Nyenga ward Division) Road
(1.2 km), Kaggwa Rd (1.65km), Kafeero Rd (0.6km), Nakawu-
ma Kokoola Road (4.1km), Tukulu Nkompe Katete Road
( 3.65km) and Bulamazi Zinga Road (3.33km) in Buikwe
district; Total length = 23.38km
064 Rehabilitation of Kachaboi - Kawo Swamp Crosisng Road Bukedea 10.6 0% 50% 50% Works ongoing
(2.6km) and Kongatuny - Acabule - Amee - Komelekes
Swamp Crossing (8km) in Bukedea district; Total km =
10.6km
065 Rehabilitation of Bufumbula - Muyembe Road (4.6km), Bulambuli 14.1 0% 65% 65% Works ongoing.
Bukewa - Kidutu Moses Road (6.0km), Shilimi - Joseph Gravelling and drain-
Bukhali Road (3.5km) in Bulambuli district; Total length = age works ongoing.
14.1km Cert 1 being refined
066 Rehabilitation of Kyeizooba - Bugongi (6.1km), Kitagata - Bushenyi 16.5 0% 50% 50% Cert 1 pending
Kabaale (2.1km), Kanyinemuyanga - Mwengura - Rwenye- payment. Culvert
na - Kabuba (5.3km), and Rwentuha P/S - Kyamuzoora P/S installation ongoing.
- Nyamirima P/S (3.0km) in Bushenyi district; Total km = Cluster 3 delayed by
16.5km land challenges.
067 Rehabilitation of Mugunu P/S - Bubalya Road (3.4km), Butaleja 15.1 0% 75% 75% Most of the work has
Namunyagwe Catholic Church - Ali Hasalya - Bunghanga been executed. Cert 1
Road (3km), Busabi P/S - Buwobowo - Habiga (4.5km) and being processed
Mwiha - Kasuleta road (4.2km) in Butaleja district; Total
length = 15.1km
068 Rehabilitation of Masagala - Bunyenye Loop Road (4.3km) Butambala 6.2 0% 80% 80% Gravelling complete.
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
and Buligi Village Road (1.9km) in Butambala district; Total Drainage works ongo-
length = 6.2km ing. Cert 1 paid.
157
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
158
069 Rehabilitation of Gombe – Kinoni – Kwezi – Kabalamba – Butambala, 10 0% 80% 80% Gravelling complete.
Mayombwe – Kalenge (10.0km) in Butambala district Butambala Drainage works
County ongoing. Cert 1 paid.
FY2019/20
070 Rehabilitation of Mushunga - Kayembe - Kashozi (3.8km), Ibanda 14 0% 36% 36% Cert 1 pending
Katengeto - Rushambya Nyabigoye (6.1km) and Bururuma payment
Bridge - Nyabigoye - Kakyere Road (4.1km) in Ibanda dis-
trict; Total length = 14.0km
071 Rehabilitation of Namungalwe - Bulanga - Namukanga Iganga 17.9 0% 85% 85% Works ongoing.
- Nabukone (11.9km), Namusisi P/S - Buganza (2.3km), Addendum 1 worth
ANNUAL SECTOR PERFORMANCE REPORT
Buganza Road - Kiringa Road (1.7km), Buganza Road 126m signed for
(1.0km) and Namusisi CoU - Busabi - Buyonga Road (1.1km) additional works
in Iganga district; Total Length = 17.9km
072 Rehabilitation of Rwenkumba - Mukonomura - Buhara Kabarole 15 0% 75% 75% Cert 1 pending
(5.7km), Mukonomura - Kasindikwa (2.0km), Kasindikwa payment. Gravelling
- Lake Saaka Acess (1.3km), Kyamukube - Hamuzigiti- and culvert
Busoma - Hamabale - Karago (3.0km), and Hakigere - installation ongoing
Kalyango - Canon Apollo (3.0km) in Kabarole district; Total
Length = 15.0km
073 Rehabilitation of Kanyabebe - Kinyarwanda - Bweranyangi Kagadi 12.4 0% 75% 75% Progress hampered
- Rugashari Road (12.4km) in Kagadi district by financial con-
straints. Cert 1 pend-
ing payment
074 Rehabilitation of Kyabazinga - Butongole - Bugodo - Kyani Kaliro 23.9 0% 78% 78% Works ongoing
Road (12.2km), Gadumire - Nasere Road (4.0km), Kisinda - (gravelling and filling
Namuntu Road (4.0km), and Kanabugo - Kabiri Kalalu Road in progress). Cert 1
(3.7km) in Kaliro district; Total length = 23.9km pending payment
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
075 Rehabilitation of Mailo T/C via Buyugu - Kibuye - Kitega Kaliro 21.3 0% 86% 86% Works on going.
(6.4km), Kitega - Namawa (1.4km), Lwanda - Beeda Naka- - Bulam- Variation I for addi-
longo road (5.5km), Budi - Nantamuli Swamp (3km), Bulike oji North tional works being
T/C - Budeba - Nswamire road (3km), and Nzirakahindi - County processed. Cert 1 paid.
Nswamme Swamp (2km) in Bulamoji North County, Kaliro Cert 2 being pro-
District; Total km = 21.3km cessed
076 Rehabilitation of Nakiwulo - Kitayundwa Road (7.8km), Kamuli Mu- 19.6 0% 50% 50% Works being slowed
Wakalumba - Wako - Buwaiswa Road (3.5km), Buwudha - nicipality down due to financial
Busutwa - Kayabya - Busanga P/s - Bukose - Budhumbula constraints. Cert 1
(4.8km), Kaima - Kirondo - Busubo Zone (3.5km) in Kamuli pending payment
Municipality; Total length = 19.6km
077 Rehabilitation of Nawanyago - Wankole Road (8.40km) Kamuli - 14.6 0% 56% 56% Works ongoing. Cert
including 1.65km swamp raising and Kidali - Bukagena - Buzaaya 1 pending payment
Bugabudyeri (6.2km) in Buzaaya county, Kamuli district; county
Total length = 14.6km
078 Rehabilitation of Kafewo - Kafule - Bulundo P/S - Kyama- Kamuli - 15 0% 50% 50% Works ongoing. Cert
tende Ring Road (15km) in Bugabula North County, Kamuli Bugabula 1 pending payment
district North
079 Rehabilitation of Ragon Road (off Mbale Highway)(3.0Km), Kapchorwa 12.7 0% 62% 62% Works on going
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
refined
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
160
080 Rehabilitation of Katoke - Kirongo - Ndughuth West - Mu- Kasese - 20 0% 65% 65% Works ongoing
hambo - Kihindi (10.0km) and Kihyo - Kitoma - Minana - Busongora (gravelling & culvert
Kasaka - Nyanorongo (10.0km) in Busongora North, Kasese North installation). Change
FY2019/20
081 Rehabilitation of Mbabu Road (1.5km), Kanyageya (3.5km), Kasese 14.95 0% 80% 80% Gravelling and
Kyondo (2.3km), Lugoki Road (1.05km), Nsenyi - Mughende culvert installation in
- Kajwenge (4.0km), Kisinga - Mughende (2.1km) and Ngole- progress
randi spur (0.5km) in Kasese district; Total length = 14.95km
082 Rehabilitation of Migongo - Palabul - Kasokwe (9.3km) and Kayun- 17.5 0% 40% 40% Works ongoing.
ANNUAL SECTOR PERFORMANCE REPORT
083 Rehabilitation of Kayonjo - Nanyuki (3.77km), Kiwangula - Kayunga 23.63 0% 98% 98% Works substantially
Nalumuli - Wajjanzi (3.1km), Ssekajja Muslim P/S - Kitered- - Ntenjeru complete. Change
de (1.6km), Ssekajja Atama Saafi (1.1km), Ssekajja Kagoye County order I issued. Cert 1
(1.45km), Kanjuki Wabusonko (7.85km), Ndeeba Mukasa is pending paymentd
Kyampisi (1.2km), Najjemba Kyampisi Namulanda (0.8 km),
Nabunya Namulanda (0.65 km), Tamale Kagoma Bbaali
(0.55km), Mayanja Nsejere Kalungi (0.6km) and Lugema
Ndeeba C/U P/S (0.96km) in Ntenjeru County, Kayunga
district; Total length = 23.63km
084 Rehabilitation of Nyamiringa - Budimbo Road (11.8km) in Kiboga 11.8 0% 91% 91% Works almost com-
Kiboga district plete. Cert 1 paid. Cert
2 being processed
085 Rehabilitation of Byanamira - Lwozi (5.0km), Muganda Kiruhura 20.6 0% 62% 62% Works ongoing with
Farm - Kashonji P/S (4.3km) and Byazo - Keitanturegye gravelling. Advance
(11.3km) in Kiruhura district; Total length = 20.6km and Cert 1 being pro-
cessed
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
086 Rehabilitation of Atulinga - Mudi - Ija - Anyau Road Section Koboko 10 0% 81% 81% Works ongoing.
(10.0km) in Koboko district
087 Rehabilitation of Rikitae - Moroto Road (10.6km) in Kotido Kotido 10.6 0% 100% 100% Completion cert is-
district sued. Change Order I
issued. Cert 1 pending
payment.
088 Rehabilitation of Kalungar - Bukedea Road (2.8km), Apapai Kumi 11.4 0% 40% 40% Works ongoing.
- Oswapai Road (2.2km) and Ceele - Oseera - Aduka Road Advance and Cert 1
(6.4km) in Kumi district; Total length = 11.4km being processed
089 Rehabilitation of Kitwala - Namutokwa - Mwangi Road Kyankwan- 11.5 0% 41% 41% Works ongoing
(11.5km) in Kyankwanzi district zi
090 Rehabilitation of Kidindimya P/S – Kayembe – Nyabuliko Kyegegwa 14.4 0% 55% 55% Works ongoing. Cert
– Isemitwe – Kikoboza – Visionary P/S Road (14.4km) in 1 being processed
Kyegegwa district
091 Rehabilitation of Wiodyek - Ayito Road (4.0km), Ayito-Wig- Lira 24.8 0% 80% 80% Works ongoing. End
weng (10.0km), Kulu Omati - Awita - Akolodong Road structures in progress.
(6.0km) and Acanadiro - Adyelowango - Alyanga Road Change order 1 being
(4.8km) in Lira district; Total km = 24.8km processed
092 Rehabilitation of Busanda - Budhuba - Buwutu - Ikumbya Luuka 10 0% 35% 35% Works ongoing. Cert
Road (10.0km) in Luuka district 1 pending payment.
Noted slow Progress
of works due to Covid.
093 Rehabilitation of Kiiya - Kasaala - Bukusu - Ngogolo Luwero 14.9 0% 60% 60% Gravelling in prog-
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
094 Rehabilitation of Byangiri - Luti - Nanywa T/C Road (7.2km) Lwengo 7.2 0% 45% 45% Works ongoing. Cert
in Lwengo district 1 pending payment
FY2019/20
095 Rehabilitation of Kinuuka - Kyenshama - Kasagama Road Lyantonde 21.4 0% 50% 50% Works ongoing.
(21.4km) in Lyantonde district Contractor expects to
finish works in Q1 if
Cert 1 is paid
096 Rehabilitation of Buwangani - Sikunga Road (4km), Buwan- Manafwa 12.8 0% 45% 45% Two roads have been
gani - Butooto Road (3.0km), and Masaka - Magodes (5.8km) opened; opening of
in Manafwa district; Total length = 12.8km the 3rd road is in
ANNUAL SECTOR PERFORMANCE REPORT
progress
097 Rehabilitation of Wandegeya - Kikandwa - Kayanja Road Mayuge 9.8 0% 40% 40% NFA stopped works
(9.8km) in Mayuge district waiting for environ-
mental clearance.
Need for EoT
098 Rehabilitation of Bulanga - Wainha - Nabalongo Road Mayuge, 30.9 0% 92% 92% Cert 1 pending pay-
(6.9km), Buwerere - Mbirabira - Bufuta - Luubu - Buka- Mayuge ment. Works ongo-
sero - Buseera Road (11.0km), Mukuta-Wagona-Buba- West ing. End structures
bwe-Namusenyu Road (6.5km) and Kyankuzi - Nalwesam- ongoing
bula A - Nalwesambula B - Mukuta Road (6.5km) in Mayuge
district; Total length = 30.9km
099 Rehabilitation of Zigoti T/C – Ssali – Namalele – Nkwale Mityana 9.3 0% 65% 65% Works ongoing. Cert
Road (4.3km) and Nkwale - Namungo Road (5.0km) in Mi- 1 pending payment.
tyana district; Total km = 9.3km
100 Rehabilitation of Loyaraboth - Natgumkale Road (7.5km) in Moroto 7.5 0% 90% 90% Works substantial-
Mororo district ly complete. Cert 1
paid. Cert 2 being
processed. Variation 1
being processed
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
101 Rehabilitation of Kawongo - Magonga - Kiwafu (5.9km), Mukono 44.4 0% 50% 50% Works ongoing. Cert
Kawuku- kiwafu (2.9km), Kasala - Kasinyinyinya - Lun- 1 pending payment
ya - Masiko (7.5km), Nakayi - Mamese manji - Kawoomya
(2.7km), Nenyodde -Namyooya C/U (2.9km) and Namyoya -
Nabalanga (4.5km), Wabusolo-Kalagala (2.5km) and Kala-
gala-Namugongo(1.6km) Kyambogo - Namuganga(6.9km),
Kyanika - Kyewanise (2.3km), and Kiyagi - Buteyongera
- Kitwe - Kakira (4.7km) in Mukono district; Total length =
44.4km
102 Rehabilitation of Kanana - Kiyaga - Kasana - Kayini P/S Mukono 17.4 0% 80% 80% Gravelling works
(5.5km), Kayini T/C - Kasala - Ndiba - Kiyagi - Ndese T/C completed, end
(6.2km) and Kabimbiri - Nasejobi - Kakukukulu - Kibamba structures being
(5.7km) in Mukono district; Total length = 17.4km constructed.
103 Rehabilitation of Timuna - Lugogo Road (8.0km) and Ki- Nakaseke 9.8 0% 70% 70% Cert 1 pending pay-
kamulo - Kibaale Road (1.8km) in Nakaseke district; Total ment. Cert 2 being
length = 9.8km processed
104 Rehabilitation of Nakitoma - Nabiswera Road (10.4km) in Nakason- 10.4 0% 35% 35% Grading and culvert
Nakasongora district gola installation complete.
Gravelling to
commence
105 Rehabilitation of Nyakasenyi - Masaka Road (9.2km) in Ntoroko 9.2 0% 75% 75% Work on filling and
Ntoroko district culvert installation in
progress
106 Rehabilitation of Masaka - Kyebukungulu Road (7.4km) in Ntoroko, 7.4 0% 85% 85% Gravelling & end
Ntoroko district Ntoroko structures in progress
County
107 Rehabilitation of Majeri - Kivumbula Road (9.1Km), Kamate Rakai - 16.8 0% 30% 30% Works ongoing. 2 out
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
Road (5.0Km) and Kaluluza - kaseese Road (2.7km) in Kooki Kooki of 3 roads fully bush
County, Rakai district; Total length = 16.8km cleared, shaped and
compacted.
163
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
164
109 Rehabilitation of Rubona - Kiraaro - Kacwekano Road Rubanda 9.62 0% 10% 10% Works ongoing
(9.62km) in Rubanda district
110 Rehabilitation of Karo - Katobo - Nyabihuku Road (3.95km), Rukungiri 6.59 0% 35% 35% Works ongoing.
ANNUAL SECTOR PERFORMANCE REPORT
111 Rehabilitation of Kashekure – Kikonkoma – Omukashabo – Rwampara 10.5 0% 56% 56% Shaping and instal-
Kashwojera TC Road (10.5km) in Rwampara district lation of culverts
complete
112 Rehabilitation of Otirono - Ajuba (2.6km), Makai Coners Serere 16.4 0% 43% 43% Works ongoing. De-
- Otekat Road (3.0km), Apapai - Agule (6.2km) and Kabes - layed by Covid
Nyanera (4.6km) in Serere district; Total km = 16.4km
113 Rehabilitation of Walawenji - Mukwana TC Road (2.0km), Tororo 15.5 0% 84% 84% Works ongoing. Cert
Mukwana P/S - Son - Ogwang (2.8km), Mukera - Matindi 1 paid. Cert 2 being
T/C (5.0km), Puwele Lwiza - Kainja (2.2km) and Poyo - Sugu- processed
da (3.5km) in Tororo district; Total length = 15.5km
114 Rehabilitation of Ssempala Kigozi Road (2.1km), Greenlight Wakiso – 13.2 0% 35% 35% Works ongoing
- Ssebowa (0.8km), Philly Bongole Lutaaya Road (1.7km), Makindye though slowed down
Kiziba - Gangu (3.3km), Kanaaba - Ziranumbu (2.1km), Ssabagabo by Covid 19 pandemic
Banalya Road (0.8km), Naume - Mukiibe Road (1.0km) and
Leticia Road (1.4km) in Makindye Ssabagabo, Wakiso dis-
trict; Total km = 13.2km
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
115 Rehabilitation of Kiwamirembe Road (4.5km) in Wakiso Wakiso 4.5 0% 35% 35% Works hindered by
district land challenges
ROAD CULVERTS
SN DISTRICT ROAD NAME OPENED GRADED GRAVELLED REMARKS
LENGTH INSTALLED
FY2019/20
Lambala- Nawangoma-Busand-
1 Kamuli ha-Bulopa-Namwendwa-Nda- 58.22 48.60 56.00 - -
like-Buyende Dist. H/Q
4 Kamuli Additional 10 No. roads 30.70 30.20 22.90 0.35 - Swamps raised, gravelled
Not graveled due to lack
5 Buyende 1. Namulikya-Nabitula-Gwase 11.00 0.00 11.00 - -
of equipment
6 Buyende 2. Ngandho-Buyamba-Iraapa 9.4 0.00 9.40 - -ditto-
0.6mm 9 culverts,
7 Jinja West 1. Kimaka by-pass 3.09 - 1.60
0.9mm 12 culverts
Graveling, headwalls,
8 Jinja West 2. Kabalega road 0.38 - 0.38
stone-pitching. 100%
9 Jinja West 3. Wanje road 0.73 - 0.60 0.6mm 8 culverts complete
1 Alupe-Abunget Tororo 6.0 0.0 0.0 6.0 1 line of 1.8m, 4 lines of 0.9m and Handed over
5lines of 0.6m culverts installed
2 Buyembe Tororo 5.0 4.1 4.1 4.1 1lines of 1.8m , 1 line of 0.9m, and Substantially completed.
-Kasipodo 5 lines of 0.6m culvert installed However, construction of
culvert end structures in
progress.
4 Magada Namutumba 11.6 13.4 13.4 13.4 1 line of 1.5m, 1 line of 1.2m,8 Handed over.
- Nabikabala – lines of 0.9m and 15 lines of 0.9m
Buwidi - Mulama culverts installed
- Kimenyulo
5 Usuk - Ngongoja Katakwi 14.0 15.0 15.0 15.0 17 lines of 0.9 and 22 lines of Substantially completed.
0.6m culverts installed. However, construction of
culvert end structures in
progress.
6 Apapai – Agule . Serere 6.3 6.0 6.0 6.0 7 lines of 0.6m culvert installed Handed over
8 Busia - Tira- Busia 12.5 12.5 12.5 12.5 11 lines of 0.6m and 3lines of Handed over, but minor
Busitema 0.9m culverts installed corrections in progress.
167
S/No. Road Name District Targeted Opened Graded Graveled Drainage works Remarks
Length (km) (km) (km)
168
(Km)
2020/2021.
10 Busia - Mikiya PS Tororo 7.7 7.7 3.5 0.0 - Forming of road in
progress.Road to be
completed in FY
2020/2021
11 Kachonga - Butaleja 6.5 5.3 5.3 5.3 1 line of 1.2m, 1 line of 0.9m and Substantially completed
ANNUAL SECTOR PERFORMANCE REPORT
1 Rwabukwitsi Ntungamo 2.0 0 2.0 2.0 8 line of 1.2m, 18 lines of 100% Completed and handed
0.9m and 30lines of 0.6m over to the district.
culverts installed.
2 Mukungu Ntungamo 1.7 0 0 1.7 29 lines of 0.9m and 36lines 100% Completed and handed
of 0.6m culverts installed over to the district.
and
5 Rwebisen- Ntoroko 8.0 8.0 8.0 0.0 16 line of 1.2m, 16 lines of 63% Progress affected by
go-Budiba 0.9m and 57lines of 0.6m lockdown due to Covid-19
culverts installed. Pandemic
6 Itojo-Kakindo Ntoroko 4.0 4.0 4.0 4.0 15 lines of 0.9m and 15lines 86% Works in progress
of 0.6m culverts installed.
9 Kinaba- Ba- Kanungu 7.0 10.0 1.0 0 9 line of 1.2m, 32 lines of 75% Progress was hampered
kundeine 0.9m and 64lines of 0.6m by the lockdown due to
culverts installed. Covid-19 spread
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
10 Omukyiyan- Kanungu 8.0 0 0 10 80 lines of 0.9m and 24 72% Work scope increased
169
(Km)
11 Rutoto-Ki- Rubirizi 15.0 15.0 10.0 15.0 39 line of 1.5m,58 line of Casting of reinforced
noko-Bitooma 1.2m, 154 lines of 0.9m and concrete culverts in
235 lines of 0.6m culverts 85% progress. Progress was
FY2019/20
Performance of Rehabilitation of District Roads Under force Account in the FY 2019-20 By the Northern Unit
Annex 9
S/N Road Name District Targeted Opened Graded Graveled Drainage works % of Physical Remarks
Length (Km) (km) (km) (km) Progress
1 Bajere-Alune Kitgum 19.5 19.5 19.5 19.5 14 lines installed 100% Completed and handed over to the
District
2 Patira-Anaka Nwoya 19.0 19.0 19.0 19.0 32 lines installed 95% Substantially completed. Construction
of culvert end structures commenced
3 Moroto Municipality Moroto 15.6 14.6 13.8 12.6 11 lines installed 70% Awaiting approval of extra budget to
Roads Complete remaining works.
4 Tecwao-Onir-Oloo Alebtong 7.8 7.8 7.8 0.0 4 lines installed 45% Works suspended due to flooding of
the swamp. To re-commence during
dry season
5 AbongodyangA- Alebtong 8.4 7.4 7.4 7.4 7 lines installed 95% Substantially completed. Construction
tingtwo-Teowello of culvert end structures to commence
soon
6 Abia Centre-Anwata PS Alebtong 10.5 0.0 0.0 0.0 - - No funds received. Rolled over tonext
FY2020-21
7 Kororom-Pece -Labora Omoro 8.0 0.0 0.0 0.0 - - No funds received. Rolled over to next
FY2020-21
8 Kangai-Adekinino Dokolo 6.8 0.0 0.0 0.0 - - No funds received. Rolled over to next
FY2020-21
9 Tee-Okole-AlirSwampA- Lira 22.0 0.0 0.0 0.0 - - No funds received. Rolled over to next
nyom Orem-Nngetta FY2020-21
Mission-KitgumRd/Kole
District Boarder
10 Ibuje-Abongokoko-Cor- Apac 12.6 0.0 0.0 0.0 - - No funds received. Rolled over to next
ner Agwen FY2020-21
11 Desilting of Lalikan Dam Kitgum - - - - - 80% Excavation works ongoing.
12 Spot Improvement of Nwoya 5.0 1.5 0.0 0.0 4 lines installed - Culvert Installation at the first
Lungulu-LebngecArana majorcrossing completed
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
Annex 10
SN Road Name Length Physical Remarks
progress by
(km) end of June
,2020
1 Upgrading to bitumen standard of 2.91 60% Contract Progress was affected
Bulindo – Nakwero road section in when No funds were released
Kira M.C for quarter four.
Total 16
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
173
Plot 57 -59 Jinja Road
P.o.Box 7174 Kampala Uganda
Telephone: +256 259 137 / 322
Fax: +256 414 231 369
Email: [email protected] Website: www.works.go.ug