2021 MWT Annual Sector Performance Report Final 2019-2020

Download as pdf or txt
Download as pdf or txt
You are on page 1of 195

THE REPUBLIC OF UGANDA

MINISTRY OF WORKS
AND TRANSPORT

ANNUAL SECTOR PERFORMANCE


REPORT FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
i

ANNUAL SECTOR
PERFORMANCE REPORT
FY2019/20

Wanseko Panyimur Ferry


Albert Nile 1
ii ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
iii

FOREWORD

I hereby present the Annual Performance Report (ASPR) for the Department for the Works
and Transport Sector for Financial Year 2019/20. The report highlights both the financial
and physical performance as well as challenges faced by the Sector during the financial year
2019/20. The report provides an opportunity to stakeholders to reflect on performance of the
Sector and to learn from what has not been done well and what may need to be addressed so
as to achieve the set targets in the future.

During the Financial Year, the sector registered improved performances in the different
subsectors. For example, under the road subsector, national road network in fair to good
condition was 84% for paved roads and 77% for unpaved roads against the NDPII target of
82% and 66% respectively.

The Air subsector was the most affected by the COVID-19 Pandemic. However, prior to the
closure of the airports due to COVID-19 Pandemic, passenger transits and revenue collections
from Uganda Airlines Company Limited were steadily increasing. The number of passengers
had reached 77,355 while the revenue collected from the passengers had reached UG.Shs
26.668Bn between August 19th 2019 and 20th March 2020. The airline acquired the last batch
(2 No.) of the CRJ900 aircrafts. The overall progress on the expansion and modernization of
Entebbe International Airport was at 73% while construction works for the development of
Kabaale International Airport in Hoima district was at 42.7% against a target of 50%.

Overall, the sector attained at least 80% on more than half of the Sector performance targets
as measured against the Sector Golden indicators. The performance was generally affected
by the lock down occasioned by the COVID-19 Pandemic and lack of an adequate budget to
implement the planned outputs.

Lastly, on the behalf of the Government of Uganda, I express gratitude to the Development
Partners, Civil Society Organizations and the Private Sector for the support extended to the
Sector during the previous Financial Year. I thank all the staff for the work done during the
Financial Year 2019/20.

For God and My Country

Hon. Gen. Katumba Wamala

MINISTER OF WORKS AND TRANSPORT


4
iv ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

EXECUTIVE SUMMARY

Introdution
This Annual Sector Performance Report (ASPR) provides a record of the overall Works
&Transport Sector performance for the financial year 2019/20. It gives a management record
of the sector progress towards achieving the Ministerial Policy statement for the FY 2019/20.
It also highlights the key sector indicator measurement and analysis for FY 2019/20 and the
performance trend of key sector indicators over the last six years. It further enumerates
the key challenges affecting performance in the sector. The key indicators measured include
the Golden Indicators which were agreed within the sector for results-based management,
the Government Annual Performance Report (GAPR) Indicators and the implementation
progress on 15th Joint Transport Sector Action Matrix.

Financial Performance
In the Financial Year 2019/20, the approved budget for the sector was UGX 6,126.668 Bn
representing 14.61% of the national Budget. UGX 622.97 Bn (10.17%) was for recurrent
expenditure and UGX 5503.684 Bn (89.83%) was for development expenditure. The Government
of Uganda contribution was UGX 3294.327bn representing 55.77%. The Development
partners contributed UGX 2,832.341 Bn representing 46.23%. Budget performance release
was UGX 4528.592Bn (73.92%). The big drop in the release was in the external financing
which was 48.5% for Ministry of Works and Transport and 37.28% for UNRA respectively.
This was due the low performance level for external financing under Multinational Lake
Victoria Maritime Communication and Transport, Development of new Kampala Port in
Bukasa and Development of Kabaale Airport under Ministry of Works and Transport due
to the lengthy procurement process for the boats, RAP implementation challenges and the
Covid 19 pandemic that affected project progress respectively. While for UNRA it was due
to MoFPED’s delay in finalizing the financing (loan) negotiations with China Exim Bank and
subsequent approval by Parliament. Therefore, UGX 717.5Bn which had been appropriated
to the Critical Oil roads was not made available to UNRA by the end of the year and UGX 325
billion which was allocated by MoFPED and appropriated to Kampala-Jinja Expressway was
not released because the project was still under preparation.

Road Transport
The road network in Uganda comprise of the National Roads, District Roads, Urban Roads
and Community Access
Access Roads.
Roads.As In per
the June
financial
2020year 2019/20,
the total UNRA
national roadcompleted studies
network was and
…..Kms
designs of 46 projects.
of which……Kms wereFY 2019/20,
National rehabilitation
Roads,…….Kms of 313 roads,
District Km of …….Kms
the national roads
Urban continued
roads and ……
on
Kmsseven (7) road projects
are Community andRoads.
Access a totalOf
of 167.1 Km-Equivalent
the total was achieved
national roads,….Kms (..%)out
are of the targeted
paved AS PER
200
june Km-Equivalent thisinrepresents
2020. The increase a performance
the stock of paved nationallevel
roadofnetwork
83.6% compared
in the last to 66% inyear
financial the
FY
was2018/19.
427.5 Kms.At the end of the FY 2019/20, four (4) road rehabilitation projects totaling 146
Km were substantially completed. There are currently 24 road upgrading projects (new
In the financial year 2019/20, UNRA completed studies and designs of 46 projects. FY
construction and upgrading to paved bituminous standards) covering a total length of 1,692
2019/20, rehabilitation of 313 Km of the national roads continued on seven (7) road projects
Km. Six projects were substantially completed by the end of the FY, adding 427.5 Km to
and a total of 167.1 Km-Equivalent was achieved out of the targeted 200 Km-Equivalent
this represents a performance level of 83.6% compared to 66% in the FY 2018/19. At the end
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
5
v

the paved
of the road network.
FY 2019/20, four (4)UNRA carried out maintenance
road rehabilitation activities
projects totaling 146 Km on were
the road network
substantially
and achieved
completed. theare
There following
currently against theupgrading
24 road targets. Routine
projects maintenance
(new constructionof the
and paved roads
upgrading
5,117.8km was achieved
to paved bituminous against acovering
standards) target of a4,791Km representing
total length of 1,692aKm.performance
Six projectsof 107%,
were
routine maintenance
substantially completedof un
bypaved roads27,886kms
the end was 427.5
of the FY, adding achieved
Kmagainst a targetroad
to the paved of 21,275kms
network.
representing
UNRA carried a performance
out maintenance of 131%. Sevenon
activities (07)
thebridges were substantially
road network and achieved completed.
the following
against the targets. Routine maintenance of the paved roads 5,117.8km was achieved against
The Ministry was able to gravel 281.98km out of a target of 669.8km due to limited funding
a target of 4,791Km representing a performance of 107%, routine maintenance of un paved
and not being able to council out of a target of 16 kms. The Ministry was also able to work
roads27,886kms was achieved against a target of 21,275kms representing a performance of
on 14 bridges and five bridges were substantially completed. 687.4km rehabilitation works
131%. Seven (07) bridges were substantially completed.
of Inter-connectivity roads were achieved out of a target of 1050 km in the selected districts.
This was due to
The Ministry waslimited funding.
able to gravel 281.98km out of a target of 669.8km due to limited funding
and not being able to council out of a target of 16 kms. The Ministry was also able to work
Kampala city comprise of 2,110km of which 626.05km (29.7%) are paved and 1483.95 km are
on 14 bridges and five bridges were substantially completed. 687.4km rehabilitation works
unpaved. In Fy 2019/20 KCCA was able to complete paving 10.05km using GOU funding.
of Inter-connectivity roads were achieved out of a target of 1050 km in the selected districts.
The KCCA paved road network in good to fair condition was 63% against a target of 62%
This was due to limited funding.
while the unpaved network in good to fair condition was at 74% against a target of 75%.
Kampala city comprise of 2,110km of which 626.05km (29.7%) are paved and 1483.95 km are
The fatality rate in Uganda has been high and is one of the highest in the sub- Sahara Africa.
unpaved. In Fy 2019/20 KCCA was able to complete paving 10.05km using GOU funding.
The fatalities in the financial year were 3,881 as compared to 3,194 in the financial year
The KCCA paved road network in good to fair condition was 63% against a target of 62%
2019/20. This means on average 10 people die daily in road accident
while the unpaved network in good to fair condition was at 74% against a target of 75%.

The fatality rate in Uganda has been high and is one of the highest in the sub- Sahara Africa.
Air
The Transport
fatalities in the financial year were 3,881 as compared to 3,194 in the financial year
2019/20. This means on average 10 people die daily in road accident
The Government under took major development projects in air transport. The two key proj-
ects are the expansion of Entebbe International Airport which was at 73% level overall prog-
ress at the end of the FY 2019/20 as compared to 67.5% in the FY2018/19. The Kabala Airport
Air Transport
in Hoima was at 42.7% level of progress against a target of 50% due to the effects of COVID
TheOther
19. Government
projectsunder tookunder
were also majortaken
development projects
at different in airairports.
regional transport. Thefinancial
In the two key proj-
year
ectscraft
air are the
andexpansion
passengerofmovement,
Entebbe International
domestic andAirport which was
International at 73% level
passengers overalldue
declined prog-
to
ressclosure
the at the end of the
of the FY 2019/20
Entebbe as compared
International to 67.5%
airport in theof
as a result FY2018/19.
COVID 19.The TheKabala Airport
international
in Hoima was
passenger at 42.7%
movement level offrom
declined progress against
1,728,779 a target ofin50%
passengers due to the
FY2018/19 to 1,effects
355,772of passen-
COVID
19. Other
gers projects were also under taken at different regional airports. In the financial year
in FY2019/20.
air craft and passenger movement, domestic and International passengers declined due to
the closure of the Entebbe International airport as a result of COVID 19. The international
Railway transportdeclined from 1,728,779 passengers in FY2018/19 to 1, 355,772 passen-
passenger movement
gers in FY2019/20.
Railway Transport sector recorded an improvement in operations compared to the passengers
carried hit a number of 488,951 despite the closure due to Covid 19, the freight carried
improved from 3.735 million-tonne-km Line the FY2018/19 to 40.172 million-tonne-km in FY
Railway transport
2019/20. The Government of Uganda acquired a loan from European Union in addition to the
Railway Transport
co-funding of GoU sector recorded
to repair an improvement
the meter Guage railway infrom
operations
Tororocompared to the passengers
to Gulu which is expected
carried
to hit afurther
improve number its of 488,951 despite
performance. the closure of
Implementation due
thetopre-construction
Covid 19, the freight carried
activities e.g.
improved from
acquisition 3.735
of the million-tonne-km
Right Line continued
of Way for the SGR the FY2018/19
duringto 40.172
the FY,million-tonne-km in FY
albeit at a slow pace.
2019/20. The Government of Uganda acquired a loan from European Union in addition to the
co-funding of GoU to repair the meter Guage railway from Tororo to Gulu which is expected
In Land Water
to improve furtherTransport
its performance. Implementation of the pre-construction activities e.g.
acquisition of the Right of Way for the SGR continued during the FY, albeit at a slow pace.
Achievements under development of new Kampala Port in Bukasa where; the Environmental
and Social Impact Assessment (ESIA) and the Resettlement Action Plan for Project Affected
Persons (PAPs) were completed. 1,149 PAP’s of the project had been compensated by the end
6
vi ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

of the FY2019/20. Under Maritime, the inception report of the Maritime search and Rescue
Policy had been development and submitted. Registering and licensing of water vessels and
In Land Water Transport
the establishment of the marine training institute where also done.
Achievements under development of new Kampala Port in Bukasa where; the Environmental
and Social Impact Assessment (ESIA) and the Resettlement Action Plan for Project Affected
Conclusion
Persons (PAPs) were completed. 1,149 PAP’s of the project had been compensated by the end
of the FY2019/20. Under Maritime, the inception report of the Maritime search and Rescue
Most of the key sector indicator targets were met or nearly met despite the challenges of the
Policy had been development and submitted. Registering and licensing of water vessels and
impact of the COVID 19 pandemic and limited funding.
the establishment of the marine training institute where also done.

Conclusion
Most of the key sector indicator targets were met or nearly met despite the challenges of the
impact of the COVID 19 pandemic and limited funding.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
vii

Table of Contents

List of Figures .................................................................................................................................................. xi


List of Tables .................................................................................................................................................. xii
List Abbreviations ........................................................................................................................................ xv
1.0 Introduction ......................................................................................................................................... 1
1.1 About this Report...................................................................................................................................... 1
2.0 Overview Of The Works And Transport Sector ............................................................................ 2
2.1 Preamble ...................................................................................................................................................... 2
2.2 Vision, Mission And Mandate Of The Sector .................................................................................. 2
2.2.1 Vision .................................................................................................................................................... 2
2.2.2 Mission ................................................................................................................................................. 2
2.2.3 Mandate............................................................................................................................................... 2
2.3 Strategic Objectives Of The Sector ...................................................................................................... 2
2.4 Execution Of The Sector Mandate By Agency ............................................................................... 3
2.5 Road Transport .........................................................................................................................................4
2.5.1 Road Density ......................................................................................................................................4
2.6 Railway Transport ................................................................................................................................... 4
2.6.1 Existing Meter Gauge Railway (Mgr) .......................................................................................... 4
2.6.2 Standard Gauge Railway ................................................................................................................ 5
2.7 Air Transport ............................................................................................................................................. 5
2.7.1 Airports ................................................................................................................................................ 5
2.7.2 Aviation Training ............................................................................................................................. 6
2.7.3 Uganda Airline Company Ltd ....................................................................................................... 6
2.8 Water Transport....................................................................................................................................... 6
3.0 Legal And Guiding Policy Framework For The Sector ................................................................. 8
3.1 Legal Framework ...................................................................................................................................... 8
3.1.1 National Laws ..................................................................................................................................... 8
3.2.1 National Context ............................................................................................................................... 8
3.2.2 Uganda Vision 2040 ........................................................................................................................ 8
3.2.3 National Development Plan II ...................................................................................................... 9
3.2.4 National Transport Master Plan / Transport Master Plan for GKMA (2008–2023) ... 9
3.2.5 Sector Policies..................................................................................................................................... 9
3.4 Regional and International Commitments..................................................................................... 11
3.4.1 EAC Vision 2050 ............................................................................................................................. 11
3.4.2 EAC Development Strategy......................................................................................................... 11
viii ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

3.4.3 Master Plan on Logistics in the Northern Economic Corridor ........................................ 11


3.4.4 Northern Corridor Infrastructure Master Plan (2011 – 2030) ......................................... 11
3.5 International Treaties and Co operations ....................................................................................... 12
3.6 Other Regional and International legal and Policy instruments............................................. 13
PART B: PERFORMANCE OF THE SECTOR AND SUB-SECTORS .............................................14
4.1 PERFORMANCE ON POLICIES AND STRATEGIES ............................................................14
4.1.4 Action Plan Matrix......................................................................................................................... 14
4.1.5 Policy, Laws, regulations, Guidelines and Standards ...........................................................14
4.2 ANALYSIS OF THE PERFORMANCE MEASURED AGAINST GOLDEN INDICATORS
..............................................................................................................................................................................17
5.0 MINISTRY OF WORKS AND TRANSPORT (VOTE 016).....................................................27
5.1 INTRODUCTION ...............................................................................................................................27
5.2 FINANCIAL PERFORMANCE ......................................................................................................28
5.3 PHYSICAL PERFORMANCE ........................................................................................................28
5.3.1 PERFORMANCE BASED ON PROGRAMME OUTCOME INDICATORS ..............28
5.3.2 PERFORMANCE OF THE DIRECTORATE OF TRANSPORT...................................29
5.3.3 PERFORMANCE OF THE DIRECTORATE OF ENGINEERING AND WORKS ..36
5.4 GOOD PRACTICES AND CHALLENGES ................................................................................ 43
5.4.1 GOOD PRACTICES ................................................................................................................ 43
5.4.2 IMPLEMENTATION CHALLENGES ................................................................................ 43
6.0 PERFORMANCE OF UGANDA NATIONAL ROADS AUTHORITY: VOTE 113 ...............45
6.1 INTRODUCTION ....................................................................................................................................45
6.2 FINANCIAL PERFORMANCE ...........................................................................................................45
6.2.1 RECURRENT: WAGE .....................................................................................................................45
6.2.2 RECURRENT: NON-WAGE .........................................................................................................45
6.2.3 DEVELOPMENT ............................................................................................................................ 46
6.2.3.1 GOU FINANCED .................................................................................................................... 46
6.2.3.2 EXTERNALLY FINANCED ................................................................................................. 46
6.3 PHYSICAL PERFORMANCE ............................................................................................................. 46
6.3.1 PERFORMANCE AGAINST THE SECTOR INDICATORS ................................................ 46
6.3.1.1 Golden Indicator 1: Condition of The Road Network ................................................. 46
6.3.1.2 Golden Indicator 2: Paved Roads Stock ............................................................................ 48
6.3.1.3 Golden Indicator 3: Road Construction/Maintenance Cost ...................................... 50
6.3.1.4 Golden Indicator 4: Road Maintenance Needs Met .....................................................52
6.3.1.5 Golden Indicator 5: Expenditure On National Road Maintenance Relative to
Overall Budget .......................................................................................................................................54
6.3.1.6 Golden Indicator 6: Compliance with Axle Load Regulations ................................... 55
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
ix

6.3.1.7 Cross cutting issues................................................................................................................. 56


6.3.2 Other Achievements ..................................................................................................................... 57
6.4 CHALLENGES FACED DURING THE FY 2019/20 .................................................................... 64
6.5 FUTURE PLANS ..................................................................................................................................... 65
7.0 PERFORMANCE OF UGANDA CIVIL AVIATION AUTHORITY...........................................69
7.1 INTRODUCTION ....................................................................................................................................69
7.2 FINANCIAL PERFORMANCE FOR THE FY2018/19 .................................................................69
7.3 PHYSICAL PERFORMANCE ..............................................................................................................69
7.3.1 TEN YEAR TRAFFIC PERFORMANCE AT ENTEBBE INTERNATIONAL AIRPORT...
.........................................................................................................................................................................70
7.3.2 TEN YEAR PASSENGER TRAFFIC PERFORMANCE AT UPCOUNTRY AIRPORTS71
7.3.3 PROGRESS OF MAJOR UCAA PROJECTS.............................................................................72
7.3.3 Other Achievements .................................................................................................................... 74
7.4 CHALLENGES / CONSTRAINTS AND MEASURES ...................................................................75
8.0 PERFORMANCE OF UGANDA RAILWAY CORPORATION ...................................................77
8.1 INTRODUCTION ....................................................................................................................................77
8.2. FINANCIAL PERFORMANCE ..........................................................................................................77
8.3 PHYSICAL PERFORMANCE .............................................................................................................. 81
8.2.1 Performance of the Golden Indicators ..................................................................................... 81
8.2.2 Performance on projects ............................................................................................................. 84
8.4 CHALLENGES AND PROPOSED MITIGATION MEASURES .................................................88
8.5 STRATEGIES FOR THE FUTURE ..................................................................................................... 90
8 . 5 . 1 Rally GoU support for Railway ............................................................................................. 90
8.5.2 Rehabilitate Infrastructure: ..................................................................................................... 91
8.5.3 Rehabilitate Rolling stock .......................................................................................................... 91
8.5.4 Passenger service operations: ..................................................................................................92
8.5.5 Wagon ferries: ................................................................................................................................93
8.5.6 Property Development...............................................................................................................93
8.5.7 URC plans t o expl oit the opportunities below to improve its income generation
capacity; .......................................................................................................................................................93
9.0 PERFORMANCE OF UGANDA ROAD FUND VOTE 118 ...................................................95
9.1 FINANCIAL PERFORMANCE............................................................................................................95
9.1.1 Performance of Funds Inflow in FY 2019/20 ......................................................................... 95
9.2 PHYSICAL PERFORMANCE ..............................................................................................................96
9.2.1 PERFORMANCE ON GOLDEN INDICATORS MONITORED BY URF ..........................96
9.2.1.1 Road Maintenance Costs .......................................................................................................96
9.2.1.2 Maintenance Budget Relative to Requirements ............................................................97
x ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

9.2.1.3 Maintenance Expenditure Relative to Releases ............................................................97


9.2.2 PERFORMANCE OF ROAD MAINTENANCE FINANCING IN FY 2019/20 ..............98
9.2.2.1 Trend of Road Maintenance Financing ...........................................................................98
9.2.2.2 Allocation of funds .................................................................................................................99
9.2.2.3 Allocation by category of expenditure heads.............................................................. 100
9.2.2.4 Allocation by Allowed Uses .............................................................................................. 100
9.2.2.5 Performance of Funds Inflow in FY 2019/20.............................................................. 102
9.2.2.6 Performance of Funds Disbursements in FY 2019/20 ............................................. 103
9.2.2.7 Performance of Funds Expenditure in FY 2019/20 .................................................. 105
9.2.3 PERFORMANCE AGAINST THE 14TH JTSR ACTION PLAN MATRIX AND PROG-
RESS ........................................................................................................................................................... 106
9.3 FUTURE PLANS – 3 YEARS ...................................................................................................... 108
9.3.1 GLOBAL ALLOCATION FOR FY 2019/20 ........................................................................... 108
9.3.2 PLANNED ROAD MAINTENANCE ACTIVITIES IN FY 2019/20 ............................... 109
9.3.3 PLANS FOR THE MEDIUM TERM ........................................................................................ 109
9.4 CHALLENGES AND PROPOSED MITIGATION MEASURES ......................................... 111
10.0 PERFORMANCE OF LOCAL GOVERNMENTS – VOTE 500 .............................................. 113
10.1 Introduction ......................................................................................................................................... 113
10.2 Rural Transport Infrastructure Projects ..................................................................................... 113
10.3 Location of Projects undertaken in the Financial Year 2019/20 ........................................ 113
10.4 Financial Performance ..................................................................................................................... 113
10.5 Physical Performance of Rural Transport Infrastructure Projects in FY 2019/20 ....... 113
11.0 PERFORMANCE OF KAMPALA CAPITAL CITY AUTHORITY ......................................... 116
11.1 INTRODUCTION ................................................................................................................................. 116
11.2 FINANCIAL PERFORMANCE........................................................................................................ 116
11.3 PHYSICAL PERFORMANCE .......................................................................................................... 118
11.3.1 PERFORMANCE ON THE GOLDEN INDICATORS ......................................................... 119
11.3.2 ROADS IMPROVEMENT ......................................................................................................... 119
11.3.3 STREET LIGHTS ......................................................................................................................... 124
11.4 CHALLENGES AND MITIGATIONS ............................................................................................ 125
12.0 PERFORMANCE OF UGANDA NATIONAL AIRLINES COMPANY ................................127
12.1 INTRODUCTION ................................................................................................................................127
12.2 FINANCIAL PERFORMANCE .......................................................................................................127
12.3 PHYSICAL PERFORMANCE ..........................................................................................................127
12.4 FUTURE PLANS ................................................................................................................................ 130
12.5 CHALLENGES AND MITIGATIONS ........................................................................................... 130
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
xi

LIST OF FIGURES

Figure 1:Transport Sector M&E framework ......................................................................................... 15

Figure 2: Condition of Paved National Road Network over the years ........................................ 46

Figure 3: Condition of the Unpaved National Road Network over the years ........................... 46

Figure 4: % Performance and Km-Equivalent Achieved on upgrading projects (June 2020)47

Figure 5: Showing the Annual increment in stock of paved national road network ............. 49

Figure 6:Funding requirement vis-a vis amount provided for road maintenance...................55

Figure 7: URC internal income sources ..................................................................................................82

Figure 8: Summary of URC financial performance over years .......................................................83

Figure 9: Trend in income performance ................................................................................................83

Figure 10: TREND OF ROAD MAINTENANCE FINANCING, FY 2010/11 – 2020/21......... 102

FIGURE 11: DISBURSEMENTS BY CATEGORY OF AGENCIES – FY 2019/20 ...................... 107

FIGURE 12: DISBURSED FUNDS AGAINST IPFS OF DAS AND SUB-AGENCIES, FY


2019/20 ......................................................................................................................................................... 107

FIGURE 13: GRAPH SHOWING THE FINANCIAL PERFORMANCE OF AGENCIES ......... 109

Figure 14: Analysing Monthly Passenger Numbers ........................................................................133


xii ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

LIST OF TABLES

Table 1: Ministry of Works and Transport, institutions, Agencies and their mandates .......... 9

Table 2:The Changes in Road Density between 2008-2019 ............................................................10

Table 3: Uganda Railway Network (MGR) ............................................................................................. 11

Table 4: Rail Infrastructure operational lines....................................................................................... 11

Table 5: Sector Policies, Laws and Regulations under Implementation ....................................... 21

Table 6: Performance of the Golden Indicators .................................................................................. 24

Table 7 : Overview of Vote016 (Ministry of Works and Transport Expenditures (UShs Bil-
lion) .................................................................................................................................................................... 31

Table 8: Performance Based On Programme Outcome Indicators...............................................32

Table 9: Physical Performance of the Directorate of Transport .....................................................33

Table 10: Physical Performance of Directorate of Engineering and Works ...............................37

Table 11: Summary of UNRA’s Budget Performance ........................................................................ 44

Table 12: Condition of the National Road Network (June 2020) ................................................... 46

Table 13: Substantially Completed Upgrading Road Projects (as at 30th June 2020) ............. 49

Table 14: Annual Increment in Stock Paved National Road Network. ........................................ 50

Table 15: Road Construction and Rehabilitation Cost (UGX Bn) ....................................................53

Table 16: Average cost of road construction over the years (UGX Bn) .........................................54

Table 17: Performance of the Road Rehabilitation Programme...................................................... 55

Table 18:Road Rehabilitation projects completed in FY 2019/20 ................................................... 55

Table 19: Funding requirement vis-à-vis amount provided for road maintenance over the
years (UGX Bn) ...............................................................................................................................................56

Table 20 : Performance of Road Maintenance Interventions .........................................................57

Table 21: proportion of expenditure on road maintenance, relative to the overall budget
from FY 2014/15 to FY 2019/20 ...............................................................................................................57

Table 22: Performance of Axle Load Control .......................................................................................58

Table 23:Location and Operational Status of Weighbridges ............................................................59

Table 24: Progress of Weighbridge Operation Projects ..................................................................... 59

Table 25: Road projects were Green Right of Way was done ......................................................... 60

Table 26: Breakdown of contracts signed in FY 2019/20 (Bn UGX) .............................................. 61


ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
xiii

Table 27: Status of Registration of Engineers .......................................................................................62

Table 28: Trend of Registration of Surveyors and Valuers ..............................................................62

Table 29: Bridges substantially completed in the past three Financial Years FY 2017/18 – FY
2019/20 ............................................................................................................................................................63

Table 30: Ferry crossing along the national road network ............................................................. 64

Table 31: Performance of UNRA Ferry Services .................................................................................65

Table 32: Status of on-going Ferry Services Projects..........................................................................66

Table 33: Completed Studies and Designs for Road Projects ...........................................................66

Table 34: Upgrading projects to be substantially completed in FY 2020/21 ...............................69

Table 35: Upgrading projects to commence in 2020/21.................................................................... 70

Table 36: Rehabilitation projects to be completed in 2020/21 ........................................................ 70

Table 37: Rehabilitation projects to commence in 2020/21 ............................................................. 71


Table 38: Bridge development projects to commence in FY 2020/21 ........................................... 71

Table 39: Planned road maintenance interventions for FY 2020/21............................................72

Table 40: Financial Performance for The FY2019/20 ...................................................................... 74

Table 41: Traffic performance at Entebbe International Airport ...................................................75

Table 42: Traffic Performance at Entebbe International Airport ..................................................75


Table 43: Passenger traffic performance at Upcountry airports ....................................................76

Table 44: Progress of CAA Major Projects at Entebbe International Airport By June 2020 76

Table 45: Progress Other Projects at Entebbe International Airport as at the End of
June2020 .........................................................................................................................................................77

Table 46: Status of Progress of UCAA Projects at Upcountry Airport as at the end of June,
2020 ..................................................................................................................................................................77

Table 47: URC Financial performance for the FY2019/2020 .......................................................... 81

Table 48: Funding of URC over the years ..............................................................................................83

Table 49:Summary of financial performance .......................................................................................83

Table 50: The Golden Indicators for URC ..............................................................................................85

Table 51: Performance against targets ....................................................................................................86

Table 52: Ongoing projects and respective status................................................................................87

Table 53: Performance against set objectives for the FY ..................................................................89

Table 54: Challenges and proposed mitigations measures ...............................................................92

Table 55: How the Government can support railway ........................................................................ 95

Table 56: Summary of Funds Inflow to Vote 118, FY 2019/20 ........................................................99


xiv ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Table 57: Performance on KPIs for Funds Inflow, FY 2019/20 .......................................................99

Table 58: Road Maintenance Unit Costs in the period FY 2018/19 – FY 2019/20 ................. 100

Table 59: Maintenance Budget in FY 2019/20 Relative to Requirements .................................101

Table 60: Maintenance Expenditure Relative to Releases .............................................................101

Table 61: Road Maintenance Funding Fy2010/11 – Fy2020/21 .................................................. 102

TABLE 62: ALLOCATION OF FUNDS, 2019/20 ............................................................................... 104

Table 63: Physical Performance of the National Roads Maintenance Programme in FY


2019/20 ......................................................................................................................................................... 104

TABLE 64: PHYSICAL PERFORMANCE OF THE CITY ROADS MAINTENANCE


PROGRAMME IN FY 2019/20 ............................................................................................................... 105

TABLE 65: PHYSICAL PERFORMANCE OF THE DUCAR MAINTENANCE PROGRAMME


IN FY 2019/20 ............................................................................................................................................. 105

TABLE 66: SUMMARY OF FUNDS INFLOW TO VOTE 118, FY 2019/20 ............................... 106

TABLE 67: PERFORMANCE ON KPIS FOR FUNDS INFLOW, FY 2019/20 ........................... 106

TABLE 68: SUMMARY OF FUNDS DISBURSEMENTS–FY 2019/20 ....................................... 107

TABLE 69: SUMMARY OF EXPENDITURES AGAINST AVAILABLE FUNDS, FY 2019/20109

TABLE 70: PROGRESS OF URF ON THE 15TH JTSR ACTION PLAN MATRIX ....................... 111
TABLE 71: Global allocation of funds, fy 2020/2021 ...................................................................... 112

TABLE 72:Summary of road maintenance activities planned to be funded in fy 2020/21 . 113

TABLE 73: Strategies to improve road maintenance financing .................................................... 113

Table 74: showing the physical performance of the RTI projects in FY 2019/20 ................... 117

Table 75: KCCA Financial Performance for FY 2019/2020 .......................................................... 120

Table 76: Road improvement works under ongoing contracts in the reporting period FY
2019/2020 .....................................................................................................................................................122

Table 77: Status of Ongoing Road Projects ......................................................................................... 124

Table 78: Transport Planning Projects..................................................................................................126

Table 79: Details of the Batch 2 Civil Works Contracts ..................................................................127

Table 80: Details of the Batch 2 Service Contracts ...........................................................................128

Table 81: New Street Lights Installations for FY 2019/20 ..............................................................128

Table 82: Showing Monthly Passenger Numbers and Number of flights .................................133
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
xv

LIST OF ABBREVIATIONS

AfDB African Development Bank


ASPR Annual Sector Performance Report
BADEA Arab Bank for Economic Development in Africa
CAA Civil Aviation Authority
CAR Community Access Road
CBD Central Business District
DANIDA Denmark Development Assistance
DAS Designated Agencies
DUCAR District, Urban and Community Access Roads
EAC East African Community
EACAA East African Civil Aviation Academy
EBB Entebbe International Airport
EIA Environmental Impact Assessment
ERB Engineers’ Registration Board
EU European Union
EXIM Export Import Bank of China
FY Financial Year
GAPR Government Annual Performance Report
GDP Gross Domestic Product
GoU Government of Uganda
Ha Hectare
ICAO International Civil Aviation Organisation
IDA International Development Association of the World Bank
IFC International Finance Corporation of the World Bank
ILS Instrument Landing System
IMO International Maritime Organisation
IPFs Indicative Planning Figures
IRI International Roughness Index
IWT Inland Water Transport
JICA Japan International Cooperation Agency
JTSR Joint Transport Sector Review
KCCA Kampala Capital City Authority
KIIDP Kampala Institutional and Infrastructural Development Project
Km Kilometre
KPI Key Performance Indicators
LCs Local Councils
xvi ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

M&E Monitoring and Evaluation


MV Merchant Vessel
MAAIF Ministry of Agriculture, Animal Industry and Fisheries
MDA Ministry, Department and Agency
MELTC Mount Elgon Labour Based Training Centre
MoFPED Ministry of Finance Planning and Economic Development
MoLG Ministry of Local Government
MoPS Ministry of Public Service
MoU Memorandum of Understanding
MoWT Ministry of Works and Transport
MTEF Medium Term Expenditure Framework
MTRA Multi-Sectoral Transport Regulatory Authority
NAVAID Navigation Aid
NEMA National Environmental Management Authority
NMT Non-Motorised Transport
NTPS National Transport Policy and Strategy
NRM National Resistance Movement Organisation
OYRMP One Year Road Maintenance Plan
PPDA Public Procurement and Disposal of Public Assets Authority
PPP Private Public Partnership
PRDP Peace, Recovery and Development Plan
PS Permanent Secretary
PSV Public Service Vehicle
PU Privatisation Unit
RFP Request for proposals
RRP Rural Roads Rehabilitation Programme
RUC Road User Charge
RVR Rift Valley Railways
SG Solicitor General
SGR Standard Gauge Railway
SIP Strategic Implementation Plan
SwaP Sector Wide Approach
SWG Sector Working Group
TA Technical Assistance
TMEA Trade Mark East Africa
TMT Top Management Team
UBOS Uganda Bureau of Statistics
UGX Uganda Shillings
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
xvii

UNRA Uganda National Roads Authority


URA Uganda Revenue Authority
URC Uganda Railways Corporation
URF Uganda Road Fund
USD United States Dollars
VCT Voluntary Counselling and Testing
WB World Bank
xviii ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Isimba Bridge
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
1

1.0 INTRODUCTION

1.1 ABOUT THIS REPORT

It is an institutional requirement for the Sector to compile its Annual Sector Performance
Report (ASPR) highlighting progress achieved, challenges, lessons learnt and proposals
of moving the Sector forward in relation to the National Development Plan (NDP)II, the
National Transport Master Plan including the Transport Master Plan for Greater Kampala
Metropolitan Area (2008 -2023), Agreed Action Matrix of the JTSR for the FY 2019/2020
and the Works and Transport Sector Development Plan (WTSDP) 2015/16 -2019/20. The FY
2019/20 report is the tenth ASPR produced by the Works and Transport Sector since the
Sector adopted a new M&E framework in 2011 and also the fifth annual report within the
framework of the WTSDP. The Report primarily focuses on the progress in implementation
of the annual work plans of the Ministry of Works & Transport and its Agencies against
output targets set for the FY 2019/20 across the Sector; as well as progress made in the
implementation of key actions agreed upon during the previous Sector performance retreat.

The Report aims at providing stakeholders with an account of the performance in the delivery
of Sector programmes and projects. It provides information on financial and the physical
performance measured against agreed upon performance indicators.  The information
provided in this report shall inform policy and programmatic decisions; and hold the Works
and Transport Sector accountable for utilization of resources. The report will also guide
the decision-making process on resource allocations for the coming FY. The Department
of Policy and Planning in the Ministry of Works and Transport led the preparations of the
FY 2019/20 ASPR with participation from affiliated agencies viz UNRA, UCAA, URC, URF,
KCCA and UACL

1.2 OBJECTIVES OF THE ASPR


The ASPR has the following objectives:

i. To provide adequate feedback on the performance of Sector programs and projects,


goals and objectives as well as progress attained on key performance indicators of the
Sector;
ii. To serve as a basis for the annual Joint Transport Sector Review in which the Sector
agrees on key recommendations to be implemented in the coming FY;
iii. To document and review lessons and challenges faced by Sector MDAs in the
implementation of their mandate;

1.3 STRUCTURE OF THE REPORT

The Report comprises twelve chapters. The first four chapters include an introduction
about the Report; an overview of the Sector; legal and guiding policy framework of the
sector through which the Sector implements its mandate and Performance on policies and
strategies. The next eight chapters detail the performance of the sector (MoWT, UNRA,
UCAA, URC, URF, KCCA, UACL and Vote 500-Local Government)
2 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

2.0 OVERVIEW OF THE WORKS AND TRANSPORT SECTOR AS AT


JUNE 2020

2.1 PREAMBLE

The Sector exists to promote the cost effective, efficient, safe and environmentally friendly
transport services to support increased agricultural and industrial production, trade, tourism
and social and administrative services. The Sector plays a critical role in the development of
an integrated and self-sustaining economy, poverty eradication and the economic integration
of the country as a whole.

The Sector being a propeller for socio-economic development of any country with its
significant positive effects on other Sectors of the economy; particularly the development
of the private Sector as an engine of growth. To achieve the goals, systems must operate
efficiently so that activities, operations and movements are conducted in a timely manner.

2.2 VISION, MISSION AND MANDATE OF THE SECTOR

2.2.1 VISION

Provide reliable and safe works, transport infrastructure and services.

2.2.2 MISSION

To promote adequate, safe and well-maintained Works and Transport Infrastructure and
Services for Social Economic Development of Uganda.

2.2.3 MANDATE

i. Plan, develop and maintain an economic, efficient and effective transport infrastruc-
ture;
ii. Plan, develop and maintain economic, efficient and effective transport services by road,
rail, water and air;
iii. Manage public works including government structures and;
iv. Promote good standards in the construction industry

2.3 STRATEGIC OBJECTIVES OF THE SECTOR

These are:

i. Develop adequate, reliable and efficient multimodal transport network in the


Country
ii. Improve the human resource and institutional capacity of the Sector to efficiently
execute the planned interventions
iii. Improve the National Construction Industry
iv. Increase the safety of transport services
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
3

2.4 EXECUTION OF THE SECTOR MANDATE

The Ministry of Works and Transport is the head of the Sector which also comprises affiliated
institutions established by Acts of Parliament and statutes including: Uganda National Roads
Authority (UNRA), Uganda Railways Corporation (URC), Uganda Road Fund (URF); and
Uganda Civil Aviation Authority (UCAA). Other affiliated institutions of the Sector include
the East African Civil Aviation Academy (EACAA), Mount Elgon Labour based Technology
(MELTEC), Ministry of Local Government (MoLG), Engineers Registration Board (ERB),
Kampala Capital City Authority (KCCA), National Building Review Board (NBRB) and Uganda
National Airlines Company Ltd (UNACoL). See table 1

The mandates of the Ministry of Works and Transport, and its affiliated institutions is
shown in Table 1.

Table 1: Ministry of Works and Transport, institutions, Agencies and their mandates

No Institution Responsibility

Policy formulation, legislation, regulation, standard setting,


Ministry of Works
1 strategic multi-modal transport planning, monitoring and
and Transport
evaluation, and general oversight of the Sector.

Uganda National Plan, Develop and Maintain the National Roads network; and
2
Roads Authority axle load control.

Uganda Civil Plan, Develop and maintain airports and regulate the air
3
Aviation Authority transport sub-Sector.

Uganda Railways Plan, Develop and Manage Rail and Marine transport, and
4
Corporation regulate the rail transport sub-Sector.

Collect road user charges (RUCs) and manage the funds to


5 Uganda Road Fund
finance road maintenance programmes.

Regulate and control Engineers and their activities within


Engineers
6 Uganda and advise the Government in relation to the
Registration Board
engineering profession.

Kampala Capital Plan, Develop and maintain Kampala city transport


7
City Authority infrastructure and traffic management.

Plan, Develop and maintain transport networks under their


8 Local Governments
areas of jurisdiction.

Training aircraft pilots, air flight operation officers, flight


9 EACAA
instructors and air craft engineers

To provide an air transport service that ranks amongst the best


10 UNACoL
in terms of safety, cost-effectiveness, punctuality, and comfort

11 NBRB Monitor building developments


4 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

2.5 ROAD TRANSPORT

2.5.1 ROAD DENSITY

Road transport is the most dominant mode carrying 96.5 % and 95 % of freight cargo and
passenger traffic respectively. As at 2019, the Country has a total road network of 159,364
km which comprise of 20,854 km of National Roads; 38,603 km of District Roads; 19,959km
of Urban Roads and 79,947 km of Community Access Roads. Overall, only 6,107km (3.83%) is
paved and for district roads only 106.5 km (0.28%) is paved while for urban roads, 1229.7 km
(6.16%) is paved.

Table 2 Road length

Length of road in 2019(km) % of the total

National 20,854 13.1


District 38,603 24.2
Urban 19,959 12.5
Community 79,948 50.2
Total 159,364

2.6 RAILWAY TRANSPORT

2.6.1 METER GAUGE RAILWAY (MGR)

The cheapest form of land transport worldwide is railway transport and in Uganda, currently
325km of the MGR are operational out of the 1,266km representing 25.6% of the rail network.
The rest of the rail network is closed largely because of dilapidation. The railway network is
as indicated in the Table 3 and the operational lines are as indicated in Table 4.

Table 3: Uganda Railway Network (MGR)

No Section Km Rail Weight (lb/yd) Status


1 Malaba – Jinja 159 75 & 80 Main line
2 Jinja-Kampala 92 80 Main line
3 Jinja - Jinja Pier 4 50 Branch line
4 Kampala - Port Bell 9 80 Branch line
5 Kampala – Nalukolongo 5 80 Branch line
Sub-total Core Network
6 Tororo – Soroti 161 50 & 60 Branch line
7 Soroti – Pakwach 346 40 & 45 Branch line
8 Nalukolongo – Kasese 330 50 Branch line
9 Branch to Kilembe mines 4 50 Branch line
10 Branch to Hima Cement 11 Branch line
11 Busoga loop 145 Branch line
Sub-total other lines
  Total Network 1,266
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
5

Table 4: Rail Infrastructure Operational Lines

No Section Km Rail Weight (lb/yd) Status


1 Malaba – Jinja 159 75 & 80 Main line
2 Jinja Kampala 92 80 Main line
3 Jinja - Jinja Pier 4 50 Branch line
4 Tororo – Mbale 55 50 & 60 Branch line
5 Kampala – Nalukolongo 5 80 Branch line
6 Kampala-Port Bell 10 Branch line
Total Operational Network 325

2.6.2 STANDARD GAUGE RAILWAY

The SGR is intended to comprise of 1,724km of railway network which will be developed in
a phased manner starting with the Eastern route: Malabe-Kampala 273km, Nothern route:
Tororo-Gulu-Nimule/Gulu-Pakwach-Vula 751km (South Su dan and Democratic Republic
of Congo). The western route which covers Kampala-Bihanga/Mirama Hills/Bihanga-
Kasese-Mpondwe 662Km (Rwanda and Democratic Republic of Congo). Currently it’s in
the preliminary stages of development i.e land acquisition, capacity building and resource
mobilization

2.7 AIR TRANSPORT

The sector focuses on airports management and civil aviation training.

2.7.1 AIRPORTS

I. Entebbe International Airport


Entebbe International Airport is currently undergoing expansion in order to cater for
the increasing passenger traffic and cargo freight. As of June 2020,it was at 73% level
of progress.

II. Kabaale Airport


The Ministry of Works and Transport is developing the Kabaale International Airport
at Kabaale in Hoima. This Airport is designed to serve the oil industry and is expected
to be operation in 2023. It is expected to have a 3500 m paved runway in length, 45m
width with shoulders of 15m on each side, a cargo terminal, taxiway, run way, apron,
air traffic control tower, navigation aids, airport maintenance vehicle, rescue and
firefighting, fuel firm, cargo and passenger terminals and other facilities. it’s planned
to sit on 174.2 acres. The airport will also be capable of acting as an alternative air field
should EIA not be available.

III. Regional and Domestic Aerodromes


There are thirteen regional aerodromes managed by UCAA. These include; Arua,
Gulu, Soroti, Kasese, Kisoro, Jinja, Kidepo, Lira, Pakuba, Tororo, Masindi, Mbarara
and Moroto. However, Government designated five of those airports as entry/exit
(international) points to promote trade and tourism. These are; Arua, Gulu, Pakuba,
Kidepo and Kasese.
6 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

2.7.2 AVIATION TRAINING

Ministry of Works and Transport operates the East African Civil Aviation Academy (EACAA)
for pilot training and aircraft maintenance engineers. There are also private pilot training
facilities such as Vine Air Academy at Jinja Airport.

2.7.3 UGANDA AIRLINE COMPANY LTD

The Uganda Airlines Company Ltd was founded on 30th January 2019. The aim of the
company is to enhance the countries competitiveness by reducing the cost of air transport
and easing connectivity to and fro Uganda, Support faster harnessing opportunities in the
economy, e.g. Oil and gas, agriculture, tourism, etc. Its headquarters are located in Entebbe,
Wakiso district. As of January, 2020 it was going to nine cities (Bujumbura, Mombasa,
Nairobi, Mogadishu, Juba, Dar es Salaam, Kilimanjaro, Zanzibar and Entebbe) all around the
East African Community.

2.8 WATER TRANSPORT

Uganda’s surface area consists of about 18% lakes, rivers or swamps. The water transport
system is still dominated by the “informal Sector” characterised by of small motorized and
non-motorized boats transporting goods and passengers. The principal lake and river system
includes Lake Victoria, Lake Kyoga, Lake Albert and Lake George, together with River Kagera,
the Victoria Nile and the Albert Nile. Transport on Uganda’s water comprises mainly: wagon
ferry services on Lake Victoria; Short distance road vehicle ferries acting as ‘road bridges’;
and Informal Sector operations by individual canoes.

URC manages and operates wagon ferries on the water ways which primarily carry cargo;
MoWT manages MV Kalangala which it leases out to private operators and UNRA managing
and operating about 10 ferries at Kiyindi, Mbulamuti, Masindi Port, Laropi, Obongi, Kyoga 1,
Kyoga 2, Nakiwogo and Bisina. Uganda Wildlife Authority also manages and operates vessels
on Lake Kyoga, Lake Albert & the River Nile.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
7

Kibembe footbridge
8 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

3.0 LEGAL AND GUIDING POLICY FRAMEWORK FOR THE SECTOR

3.1 LEGAL FRAMEWORK

The legal framework under which the sector took interventions comprises the following
laws;

3.1.1 National Laws

i. Uganda National Roads Authority Act, 2006


ii. Uganda Road Fund Act, 2008
iii. Civil Aviation Authority (Amendment) Act, 2019
iv. The Traffic and Road Safety (Amended) Act, 2020
v. The Ferries Act, 1905 and the Rivers Act 1907;
vi. The Uganda Railways Corporation Act 1992;
vii. Lake Victoria Transport Act 2007
viii. Building Control Act, 2013
ix. The East African Community Vehicle Load Control Act,2016
x. The Engineers registration (Amendment) Act, 2015
xi. The Roads Act, 2019
xii. The 1995 constitution of Uganda

3.2 GUIDING POLICY FRAMEWORK

3.2.1 National Context

The sector planning framework is guided by the follow plans the Uganda Vision 2040;
the National Development Plan II (2015/16 -2019/20); the National Transport Master Plan
including the Transport Master Plan for Greater Kampala Metropolitan Area (2008 -2023)
and the Works and Transport Sector Development Plan (2015/16 -2019/20).

3.2.2 Uganda Vision 2040

Uganda Vision 2040 provides the development paths and strategies to operationalize
Uganda’s Vision statement which is “A Transformed Ugandan Society from a Peasant to a
Modern and Prosperous Country within 30 years” as approved by Cabinet in 2007. It aims at
transforming Uganda from a predominantly peasant and low income country to a competitive
upper middle income country

The vision targets investments in infrastructure including;

a) Five regional cities (Gulu, Mbale, Kampala, Mbarara, and Arua)


b) Five strategic cities (Hoima, Nakasongola, Fort Portal, Moroto, and Jinja);
c) Four international airports;
d) A standard gauge railway network with high speed trains; and
e) Multi-lane paved national road network linking major towns, cities and other strategic
locations.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
9

3.2.3 National Development Plan II

The National Development Plan (NDPII) is the development planning framework for the
GoU for the period 2015/16–2019/20. It highlights the strategic agenda for development and
further details priority interventions in all sectors of the economy. The overall goal of NDP
II is to attain lower middle income status by 2020. It will be realized through strengthening
the country’s competitiveness for sustainable wealth creation, employment and inclusive
growth.

3.2.4 National Transport Master Plan / Transport Master Plan for GKMA (2008–2023)

The National Transport Master Plan Including a Transport Master Plan for Greater Kampala
Metropolitan Area (NTMP/GKMA) sets out a framework for development of the transport
sector over the next 15 years, 2008-23. Since transport is the “blood” circulation system of
any economy, this Plan constitutes an essential element for overall planning of the medium-
term economic and social development of Uganda. A new National Transport Master Plan is
under development. The NTMP/GKMA key strategic objectives include;
a) To provide a long-term comprehensive framework multi-modal transport within
which consistent plans for individual modes can be developed;
b) To serve as a key input to regional transport planning at East African Community,
COMESA and African Union levels;
c) To create a framework within which well-informed investment decisions can be made
by both public and private sectors;

3.2.5 Sector Policies

The sector is governed by sector specific policies which include;

i. The National Construction Industry (NCI) Policy, 2010,


ii. Non-Motorized Transport Policy 2012;

iii. National Road Safety Policy, 2014

iv. National Road Tolling Policy, 2018

v. Works and Transport Sector Monitoring and Evaluation Policy, 2014

The National M&E policy that is spearheaded by the Office of the Prime Minister (OPM) provides
a clear framework for strengthening the coverage, quality and utility of the assessment
of public policies and investments intended to achieve socio-economic development. In FY
2012/13, the Ministry of Works and Transport developed a comprehensive Monitoring and
Evaluation framework to enhance monitoring in the Transport Sector.
10 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Office of the Prime Minister (sets M&E Policy)

National Stakeholders Ministry of Finance,


Planning (including Planning and
Authority (NAP) Development Economic
Partners) Development

National Development Plan Joint Transport Government Annual


(NDP) Sector Review (JTSR) Performance Report (GAPR)

Transport M&E Framework Annual Sector


(defining Golden indicators) Performance (ASPR) GAPR Indicators

Golden Indicators

Action Plan Matrix

Figure 1:Transport Sector M&E framework

The main indicators, shown in green in figure 1 are Golden Indicators and GAPR Indicators.
The Golden Indicators were agreed upon by the Transport Sector Working Group to assess
its own performance. Some of the Golden indicators double as GAPR indicators. The principal
purpose of the Golden Indicators is the demonstration of Sector-wide performance aimed
at overall strategic management, including the review of related policy issues. The Golden
Indicators were adopted by the Sector in 2011. The Golden Indicators are related to the
mandates and functions of the Ministry and its Agencies and the objectives of the National
Development Plan (NDPIII). The MoWT progress towards the golden indicators is discussed
further in this report. The Government Annual Performance Report (GAPR) is used by
the Office of the Prime Minister to monitor and evaluate performance of all Government
Sectors, including transport. The GAPR uses indicators which report on outcomes; it also
has output indicators to be compared with budgets, releases and expenditure of government
programmes. Performance of the Sector against GAPR indicators is as detailed.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
11

3.4 Regional and International Commitments

Uganda is a member of regional blocs such as EAC, COMESA and AU. The major objective of
these regional blocs is regional integration to reduce non-tariff barriers and enable a seam-
less movement of goods, persons and services across states.

3.4.1 EAC Vision 2050

The Vision 2050 focuses on initiatives that will create gainful employment to the economically
active population. It focuses on the development of pillars and enablers that would create
jobs to absorb the expected expansion of workforce in the next decades of the Vision 2050.
Infrastructure and transport network that is easy, fast and cheap for people and goods
creating regional competitiveness are identified as one of the pillars and enablers of economic
transformation.

3.4.2 EAC Development Strategy

The overall Goal of the EAC Development Strategy (2016/17 - 2020/21) is: “to build a firm
foundation for transforming the East African Community into a stable, competitive and
sustainable lower middle income region by 2021”, while its overarching theme is: “accelerating
a people-centred and market driven integration”.

Specifically, the EAC Development Strategy aims at investing in enhancement of the stock
and quality of multi-dimensional strategic infrastructure and related services, to support and
accelerate sustainable regional integration and competitiveness.

3.4.3 Master Plan on Logistics in the Northern Economic Corridor

The Master Plan on Logistics in the Northern Economic Corridor (NEC) is a multi-modal plan
consisting of road, rail, pipeline and inland water ways transport to link Uganda to countries
like Kenya through Mombasa port, Rwanda, Burundi, the Democratic Republic of Congo and
Southern Sudan.

The Master plan addresses transport and logistics gaps by proposing a shift to the following:

a) Modal shift function among rail, truck, and inland waterway;


b) Container depot function to reduce export cost; and
c) Logistic service including warehouse, distribution centre, and one stop shop.

3.4.4 Northern Corridor Infrastructure Master Plan (2011 – 2030)

The EAC Northern Corridor Infrastructure Master Plan specifically to the transport sector
aims at:

a) Defining transport infrastructure development needs in the Northern Corridor area


through 2030;
b) Determining the requirements for missing links in order to cover the (Northern Cor-
ridor Transit Agreement (NCTA) member countries, including extending the Corridor
to the Atlantic Ocean;
c) Improving the efficiency of the facilities along the Corridor;
12 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

3.5 International Treaties and Co operations

In the area of regional transport cooperation, the principal treaties ratified by Uganda are:

i) The “Treaty for the Establishment of the East African Community (EAC)”.

Among other provisions, this treaty proposes a customs union in which internal tariffs
are abolished and non-tariff barriers are eliminated. In the transport sector it provides
for the elimination of non-physical barriers to road transport and the non-discrimination
between carriers of member states. The EAC agreed also on tariff setting, schedules and
safety issues for the water cargo transport on Lake Victoria.

ii) The “Treaty for the Establishment of the Common Market for Eastern and Southern Africa
(COMESA)”.

Under this treaty, member states are required to develop coordinated transport and
communications policies. In addition, it provides for the measures to ensure common
procedures for the harmonization of road transit charges, similar treatment to the carriers
of all member states and the promotion of cost-effectiveness through competition.
Uganda is an active member of COMESA and has supported all the initiatives aimed at
strengthening integration in the region.

iii) The “Northern Corridor Transit Agreement” between Burundi, the Democratic Republic
of Congo, Kenya, Rwanda, and Uganda.

The provisions of this agreement are mainly concerned with facilitating the transit of
goods traffic and the similar treatment of carriers of all member states.

iv) Sustainable Development Goals

The United Nations (UN) is the universal platform for global normative debate and consensus-
building on global policy issues, including the economic, social and environmental dimensions
of sustainable development. UN adopted a global Post-2015 Development Agenda, which
includes a comprehensive set of 17 universal Sustainable Development Goals (SDGs), together
with 169 specific development targets. 

The SDGs provide comprehensive global policy guidance for all United Nations Member
States. Transport provides essential means to stimulate socio-economic activities and to
promote development including the eventual achievement of the SDGs. The efficient, reliable,
affordable, safe, accessible, and environmentally friendly transport of passengers and goods
is indeed key to the implementation of the Post-2015 Development Agenda. 
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
13

The Sector undertakes a number of activities which impact on the achievement of the 2030
Sustainable Development Agenda of the United Nations (UN). More specifically targets 3.f,
9.a&f and 11.b below: 
i) Target 3.f: By 2020, halve the number of global deaths and injuries from road traffic
accidents 3.7 
ii) Target 9.a: To develop quality, reliable, sustainable and resilient infrastructure, including
regional and trans-boundary infrastructure to support economic development and
human well-being, with a focus on affordable and equitable access for all. 
iii) Target 9.f: Facilitate sustainable and resilient infrastructure development in developing
countries through enhanced financial, technological and technical support to African
countries, least developed countries, landlocked developing countries and Small Island
developing States. 
iv) Target 11.b: By 2030, provide access to safe, affordable, accessible and sustainable
transport systems for all, improving road safety, notably by expanding public transport,
with special attention to the needs of those in vulnerable situations, women, children,
persons with disabilities and older persons 

3.6 Other Regional and International legal and Policy instruments

The list of more instruments, conventions, protocols and agreements to guide Sector
institutions while executing their mandates is provided below;

i. The Yamoussoukro Decision spearheaded by the African Union (AU), the East
African Community Air Transport Liberalization Programme under the East
African Community (EAC);
ii. Common Market for Eastern and Southern Africa (COMESA) Legal Notice No. 2 on
Liberalization of Air Transport; and
iii. The Communication, Navigation, Surveillance/Air Traffic Management (CNS/ATM)
Master Plan.
iv. The United Nations Decade of Action on Road Safety
v. The LAke Victoria Transport Act 2007
vi. The United Nations Convetion for the Law of the Sea (UNCLOS)
vii. The Convention for suppression of Unlawful Acts at Sea (SUA 88’)
viii. The African Maritime Transport Charter
ix. Applicable Conventions of the International Maritime Organization (IMO)
x. Port Management Association for East and Southern Africa Protocol’s (PMAESA)
xi. Northern Corridor Transit and Transport Coordination Agreement
xii. Central Corridor Transit Transport Coordination Protocol
xiii. International Convention on the International Civil Aviation Organization
(ICAO) 1944
xiv. ICAO Standards and Recommended Practices (SAPS)
xv. East African Community Treaty and Protocols
xvi. Standard Gauge Railway Protocol
xvii. Agreement on the Intergovernmental Standing Committee on Shipping (ISCOS)
14 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

PART B: PERFORMANCE OF THE SECTOR AND SUB-SECTORS

4.1 PERFORMANCE ON POLICIES AND STRATEGIES

4.1.4 Action Plan Matrix

The 15th Joint Transport Sector Review (JTSR) of September 2019 discussed and raised key
Policy and Strategy issues. These issues were consolidated into an agreed Action Plan Matrix.
Progress on the Actions is detailed in Annex I of this report.

4.1.5 Policy, Laws, regulations, Guidelines and Standards

Table 5: Progress on development of Sector Policies, Laws, Regulations and guidelines

SN Policy/law Objective(s) Status


1. National The overall objective of • The Draft NTLPS integrates the
Transport and this Policy is to improve Axle Load Control Policy; The
Logistics Policy the efficiency and safety National Aviation Policy, the
of transport in order National Railway Policy, the
to facilitate economic Maritime Search and Rescue
and social development, Policy and the Maritime Transport
through creation and Policy that were previously under
maintenance of an formulation independently.
Integrated and Sustainable
• Draft Policy was validated by
Transport System for
Uganda. Stakeholders and their final input
is being incorporated.
• The Draft Policy was approved
by both the Ministry’s Senior
Management Team, and Sector
Working Group and is to be
presented to the Ministry’s
Top Leadership Team for final
endorsement.
• The Regulatory Impact
Assessment was finalized.
• To draft Cabinet Memo for
submission of the finalized draft
Policy to Cabinet for approval.

2. Non-Motorised Policy was approved • The Policy was disseminated


Transport Policy in 2010 and now across all regions of the Country
(NMT) under implementation: • The Policy is being piloted in
Policy is designed to KCCA.
raise the profile of • Procured Consultant to develop
NMT elements within the NMT Design Manuals; work is
planning, designing, and in progress. Guidelines component
construction of road
infrastructure in Uganda.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
15

• SECTION B: LAWS |& REGULATIONS


1. The Roads Act, The Bill re-aligned and • The Roads Bill was presented to
2020 merged the Roads Act, Parliament and passed on 17th
Cap 358, Vol 13 and May,2019
the Access to Roads • Bill was passed on to H.E, the
Act Cap 350, Vol 13 President in July 2019 to sign it
to: address broader into law.
aspects of planning, • Signed into Law on September 4th
design, development and 2019
maintenance of road
infrastructure
2. Civil Aviation Harmonise the Act with • The Bill was passed by Parliament
(Amendment) the Chicago Convention in December 2018 and was
Act, 2019 and its Annexes in order assented to by H.E. the President
to comply with the in February, 2019
international standards • To disseminate the Act in the 2nd
and practices; and and 3rd Quarters of FY 2019/2020
enhance safety and
security of Civil Aviation
operations in Uganda.
3. Building Control To consolidate, harmo- • This Act commenced on 2nd April,
Act, 2013 nise and amend the law 2018
relating to the erection of • National Building Code was
buildings; to provide for established by the Hon. Minister
building standards; on 2nd October 2018
• Ministry cleared payment for
UPPC for gazetting, publishing
and printing but some editing
is still underway by Solicitor
General’s office.
• The National Building Review
Board was appointed and inaugu-
rated on 2nd October, 2018
• Board established a Secretariat,
with an Interim Executive
Secretary housed at Rumee
Building, along Lumumba Avenue.
• The Board considered and passed
the draft Building Regulations
with comments and are currently
before the First Parliamentary
Counsel (FPC) for updating.
• Hon Minister to issue statutory in-
strument on Building Regulations,
which is under preparation by the
Solicitor General, by September
2019.
4. Engineers Strengthening the regu- • The Bill is under review by the
Registration latory framework for the Solicitor General’s office.
(Amendment) practice of engineering • Awaiting issuance of Certificate of
Act 1969, in Uganda that enhances Legal Clearance
Cap.271 professional responsibility,
traceability, and account-
ability under appropriate
code of conduct
16 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

5. Ratification of Bilateral air services • Solicitor General cleared 7No.


Bilateral Air agreements remain the BASAs (Tanzania, South Sudan,
Service Agree- primary vehicles for Rwanda Turkey, United Arab
ments (BASAs) liberalizing international Emirates, USA and DRC).
and ICAO Con- air transport services for • Cabinet Memo cleared by Cabinet
ventions and most States Secretariat for submission of the
Protocols BASAs to Cabinet for ratification.
• 9No. of ICAO Conventions and
Protocols were ratified and depos-
ited to International Civil Aviation
Organization (ICAO)
• The Ministry has drafted a
standard BASA Instrument for use
in the subsequent BASA reviews
and negotiations.
• Instrument has been submitted to
MoFPED for clearance of financial
provisions.
7. Traffic and Road The objectives of • Cabinet approved the Bill in
Safety (Amend- the amendment are December 2018.
ment) Bill, 2018. to: Strengthen the • The Traffic and Road Safety
management of road (Amendment) Bill, 2018 had its
transport services and 1st reading in Parliament and is
road safety in Uganda currently before the Physical
Infrastructure Committee for
consideration.
8. Ratification of The 1968 convention • Stakeholders’ Consultation
the UN conven- provides rules on all Workshop was conducted on 13th
tions on Road aspects of international September 2018.
Safety road traffic and safety, • Incorporating comments made by
and serves as a reference stakeholders into the draft Cabinet
for national legislation to Memo
promote safe road user • The draft Cabinet Memo to be
behaviour. presented to the TMT.
9. Inland Water The overall objective • First Parliamentary Counsel (FPC)
Transport Bill, of the proposed law is Submitted Final IWT Bill 2019 on
2019 Provide a legislative 18/04/2019 to MoWT
framework to improve • Bill cleared of both Financial
Inland Water Transport implications and Legal Compliance
and to encourage Private • The Bill was approved by Cabinet
Sector investment in order • Bill has been published in the
to promote Safety, security Gazette
and prevention of marine • Scheduled for its 1st reading in
pollution to save lives and Parliament
reduce injuries.
10. Ratification/Ac- International Maritime • Entry into Force (3rd July 2019)
ceding to IMO Organization (IMO) in- and Implementation of (7) IMO
conventions struments that guide the conventions acceded to
regulatory development • Depositary Instrument for Load
of its member states to Line convention to be submitted
improve safety of water to IMO.
bodies; facilitate trade
among seafaring states
and protect the marine
environment.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
17

11. The UNRA To operationalize the • Effective 24th July 2018


Regulations, UNRA Act of 2006 by • To work with UNRA on plans to
2017 providing a clear and disseminate the Regulations.
transparent framework
for the use of national
roads, road reserves and
ferry landing sites.
These include:
(i) UNRA General
Regulations, 2017
(ii) UNRA Vehicle
Dimensions and Load
Control Regulations,
2017
(iii) UNRA Ferry
Management

4.2 PHYSICAL PERFORMANCE

The following section presents the physical performance of the sector.

4.2.1 ANALYSIS OF THE PERFORMANCE MEASURED AGAINST GOLDEN INDICA-


TORS

Table 6: Performance of the Golden Indicators


No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
18

Roads
1 Road network in fair
to good condition (%)
FY2019/20

National Roads 80 78.5 80 97 93 90 84 93.3


(paved) – fair to good
National Roads (un- 70 71 70 84 75 75 77 102.7
paved) – fair to good

District Roads (un- 57.8 59.1 60.5 61 66 70 67 95.7


paved) – fair to good
ANNUAL SECTOR PERFORMANCE REPORT

Urban Roads (paved) 58 67 72 78 78 80 78 97.5


– fair to good
Urban Roads (un- 49.7 51.5 56 60 64 55 85.9
paved) – fair to good
47
KCCA Roads (paved) 49 49 51 55 62 62 63 101.6
– fair to good
KCCA Roads (un- 61 61 70 70 73 75 74 98.7
paved) – fair to good
2 Paved Road Network
(km)
National Roads
Urban Roads 745 570 570 596 658.69 685 673.69 98.35
KCCA 498 500 578 595 616 640 626. 05 97.82
3 Road Safety
Total fatalities (Road 2,845 32241 3503 35002 3,194 3,350 3,880 115.82
deaths)

1 This is based on provisional estimates from Uganda Police for Calendar year 2019
2 This is based on provisional estimates from Uganda Police for Calendar year 2019.
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
Fatalities per 10,000 26 26 26 26 19
vehicles
Total registered ve- 1,102,021 1,222,964 1,355,090 2,000,000
hicles
4 Road Service Level-
Travel Time (min-
utes/km)
On National Roads 1.15 1.143 1.13 N/A N/A 1.13 1.13 100
On District Roads N/A N/A N/A N/A N/A 2.5 N/A N/A
In GKMA 2.5 2.9 2.7 4.2 4.1 3.5 4.1 100
5 Road Construction/
Maintenance Cost
a Paved Roads (1000
USD/km)
National Roads – N/A N/A N/A N/A N/A N/A N/A N/A
New-Construction
National Roads – up- 650-1,100 650-1,100 1,800,000- 1,800,000- 576,610- 600,000- 2,259,000- N/A
grading from gravel 2,000,0004 2,000,0004 1,380,6176 1,500,000 4,651,000
to tarmac
National Roads – 896-984 896-984 1,800,000- 1,800,000- 576,610- 600,000- 1,776,000- N/A
Re-Construction 2,000,000 2,000,000 1,380,6176 1,500,000 2,929,000

National Roads – Re- 400-791 400-791 280,000- 280,000- 454,087- 400,087- 1,776,000- N/A
habilitation 497,500 497,500 504,541 540,000 2,929,000
National Roads – Pe- 100-300 100-300 8,400- 8,400- 8,400-17,500 8,400-17,500
riodic maintenance 17,500 17,500
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

3
19
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
20

National Roads – 8.4-17.5 8.4-17.5 8.4-17.5 8.4-17.5 8.4-17.5


Mechanized routine
maintenance
FY2019/20

Urban Roads – Reha- 212-400 212-400 850 945-1160 950-1,200


bilitation
Urban Roads - Peri- 11.0 12.9 13.5 13.9 14.0
odic Maintenance
Kampala Roads- Up- 720-850 720-850 720-850 720-850 740-1,000 750-1,000 750-1000 100
grading from gravel
to tarmac
ANNUAL SECTOR PERFORMANCE REPORT

b Unpaved Roads
(1000 USD/km)
National Roads – Pe- 13.4-15 13.4-15 13.4-15 13.4-15 7.2-13.9 13.5-14.0
riodic Maintenance
National roads – 3.5-5.5 3.5-5.5 3.5-5.5 3.5-5.5 3.8-4.8 4.0-5.0
Mechanised routine
maintenance
District roads – Reha- NOT AV NOT AV NOT AV NOT AV NOT AV N/A N/A
bilitation
District – Periodic 4.5 4.7 4.9 5.1 5.3 5.5 5.4
Maintenance
District roads - Rou- 0.3-1.2 0.4-1.3 0.4-1.4 0.6-1.5 0.7-1.6 0.8-1.7 0.8 - 1.8
tine Maintenance
Urban roads – Reha- 3-19 6.4 – 13.1 6.4-13.1 6.9-13.6 7.2-13.9 7.3-14.0 7.4 – 14.2
bilitation
Community Access NOT AV NOT AV NOT AV NOT AV NOT AV NOT AV NOT AV
Roads - Routine
maintenance
6 Rural Accessibility
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
Rural population liv- 83% 85%5 85 N/A 60 53 88.3
ing within 2 km of an
all-weather road
Population with ac- 38 38 38 N/A 40 N/A N/A
cess to Taxi / Matatu
service (% of total)
All year motorable 77186 19,4827 N/A N/A 20,000 N/A N/A
Community Access
Road network (km)
7 Road Maintenance
Needs Met
a Maintenance
budget relative to
requirement
a.1 Maintenance
Financed by URF
National Roads – 34.8 25.6 22 45 52.4 50 47.3 94.6
budget to require-
ment (%)
District Roads 51.6 37.3 27 24 27 30 15.0 50
– budget to
requirement (%)
Urban Roads includ- 50.7 46.4 47 22 26 30 15.0 50
ing KCCA – Budget to
requirement (%)
a.2 Backlog –
Rehabilitation Needs
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

for Roads in Poor


Condition
21

Budget for all roads 145.2 118.8 166.1 172.7 179.2 200 186.2 93.1
(USD million)
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
22

Unfunded backlog 802.4 1047 1244 1,403 1,520 1,400 1,154.3 82.45
for all roads (USD
million)
FY2019/20

b Maintenance
Expenditure relative
to Release (%)
National Roads 98.6 76.9 67.5 99.9 101 100 98.9 98.9
DUCAR Roads 90.3 76.0 76.4 59.1 62 100 64 64
8 Compliance with
Axle Load Regulation
ANNUAL SECTOR PERFORMANCE REPORT

Number of Vehicles 215,067 654,369 575,211 1,247,931 1,364,562 1,400,000 1,220,753 87.20
weighed
Number of Overload- 107,533 14,029 21,282 47,421 42,301 45,000 46,389 103.09
ed vehicles
Overloaded Vehicles 50 2.1 3.7 3.8 3.1 2.5 3.8 152
(% of total controlled)
Rail
9 Rail Freight Volume
Total freight carried 171.1 165.7 118.9 7.54 3.735 7.5 40.172 535.7
(million-tonne-km)
10 Rail Modal share at  
Malaba, Busia and
Port Bell Border
Points
Total Freight crossing 8,325 5,162.7 5107.1 179 180 145.02 80.6
the three borders
(1000 tonnes)
Freight that crosses 6 8.3 6.5 3.5 -  5 7.26 145
the three borders by
rail (% of total)
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
11 Rail Modal Share on  
Lake Victoria Ferries
Freight transported on 16.1 N/A 7 0.002 35  40 34.3 85.6
ferries by rail, regis-
tered at Port Bell border
post (% of total).
12 Rail Efficiency
Locomotive produc- 147 69 78 148 251  150 74 49.3
tivity (km/loco/day)
13 Wagon Utilization
Wagon Transit time 8 13 12 7  31 12 25 208
(days)
Wagon Turn-round 28 25 34 28  31 28 76 271.4
time (days)
Air
14 International
Aircraft Movements

Commercial 22,265 28,073 29,159 29,785 32735 33,717 28,327 84.0


Non commercial 14,105 12,636 14,283 10,031 8310 8,559 6,996 81.7
15 Volume of Passenger
and Freight carried by
Air Transport
a Air Passenger
Traffic - International
Embarking 668,079 687,850 737,162 793,208 885449 951,857 699,859 73.0
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

Disembarking 669,182 675,627 731,000 785,082 843330 906,580 655,913 73.5


Transit 107,016 140,678 123,498 122,334 192894 207,361 133,659 64.5
23

b Air Passenger Traf-


fic-Domestic
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
24

Embarking 8,315 6872 7,765 10,932 13235 13,897 9,339 67.2


Disembarking 9,161 7314 8,203 11,300 14365 15,083 10,942 72.5
Freight Cargo Traffic
FY2019/20

(tones)
Exported 31,867 34693 46,777 39,594 41339 42,579 37,829 88.8
Imported 20,747 21490 20,317 22,499 20788 21,412 21,985 102.7
Water Transport
16 Freight Traffic on
Lake Victoria
ANNUAL SECTOR PERFORMANCE REPORT

Total freight on fer- 58,899 31,826 27,665 40,689.42 50,110 29,074.74 58


ries as registered at
Port Bell border post
(tonnes)
17 Passenger Traffic on
Lake Victoria
Entebbe – Kalangala 20,179 51,430 41,938 45,338 54,695 55,400 33,163 59.86
Through Port Bell N/A N/A N/A N/A
Through Jinja N/A N/A N/A N/A
18 Cross-Cutting Issues
18.1 Environment
a Emissions (Air Pol-
lution)
Ppm for CO2 / CO/ N/A N/A N/A N/A N/A 3,835.622Gg 3,835.622Gg 100%
SO2/ NOx

b Number of EIAs Accepted by NEMA against Total Number of EIAs Required (%)

Overall percentage 100 958 95 100 100% 100% 100%


for UNRA, MoWT,
URC, CAA, URF
No Description June 2015 June 2016 June 2017 June 2018 June 2019 Target June Actual June % performance
2020 2020 against target
18.2 Gender
a Availability of Gen- 5 5 6 5 5 5 100%
der Focal Person
b)Number in place of women in employment
% at top management 30% 15% 50%
% management level 30% 25% 83.3%
% at lower level 40% 34% 855
Overall percentage 26 25 n/a 30% 24.7% 82.3%
18.3 HIV/AIDS Interventions (Number)
Total No. of HIV Sen- 35 N/A n/a 1 - 248 190 45%
sitization

Total No. of Condoms 1,000 5,000 3,754,000 695,105 44%


distributed
Total No. of IEC ma- - - - - - 11,576 16,459 142%
terials made(UNRA)

Total No. of Coordi- - - - 1 2 4 1 25%


nation meetings held

18.4 Occupational Health and Safety-Accidents at the Work Place(No.)


1.Minor injury 0 0 10

2.Major injury 0 0 30

3.Fatal accidents 0 0 33
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

Total Number N/A N/A 292 386 0 73

Golden indicators are the principal demonstration of sector-wide performance aimed at overall strategic management. The Golden Indicators
25

were adopted by the Works and Transport Sector in 2011. These indicators give an insight into the current state of the National Road Network.
They are related to the mandate and functions of UNRA.
26 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
27

5.0 MINISTRY OF WORKS AND TRANSPORT (VOTE 016)

5.1 FINANCIAL PERFORMANCE

For the Financial year 2019/20, the approved budget for Vote 016 was UGX 1,655.864 Bn.
The total amount released by the end of June 2020 was UGX 1,159.158 Bn representing 70%
of the approved annual budget. The low release was due no releases in quarter four because
of the Corona Virus pandemic.

The total GoU release performed at 84.1% of the approved budget while the External
financing performed at 48.5% of the approved budget. The low performance level for external
financing was under Multinational Lake Victoria Maritime Communication and Transport,
Development of new Kampala Port in Bukasa and Development of Kabaale Airport due to the
lengthy procurement process for the boats, RAP implementation challenges and the Covid
pandemic breakdown that affected project progress respectively. Table 7 shows the budget
breakdown in terms of the release and expenditure for the financial year 2019/20

Table 7 : Overview of Vote016 (Ministry of Works and Transport Expenditures (UShs Bil-
lion)

Approved Released Spent by % Budget % Budget % Releases


by End
Budget Q4 End Q4 Released Spent Spent
Recurrent Wage 11.866 11.866 11.860 100% 100% 100%
Non- 72.182 62.418 62.011 86.5% 85.9% 99.3%
wage
Development GoU 917.269 767.494 767.485 83.7% 83.7% 100.0%
Ext Fin. 654.547 317.380 141.093 48.5% 21.6% 44.5%
GoU Total 1,001.317 841.778 841.357 84.1% 84.0% 99.9%
Total GoU+Ext Fin(MTEF) 1,655.864 1,159.158 982.449 70.0% 59.3% 84.8%
Arrears 0.463 0.463 0.453 100.0% 97.9% 97.9%
Total budget 1,656.327 1,159.621 982.902 70.0% 59.3% 84.8%
A.I.A Total 0.000 0.000 0.000 0.0% 0.0% 0.0%
Grand Total 1,656.327 1,159.621 982.902 70.0% 59.3% 84.8%
Total Vote Budget 1,655.864 1,159.158 982.449 70.0% 59.3% 84.8%
Excluding
Arrears

Budget Absorption: By the end of June 2020; 100% of the released fund under GoU component
had been spent while only 44.5% of the external financing had been spent. The low budget
absorption under external financing was due to low performance level under Multinational
Lake Victoria Maritime Communication and Transport, Development of the new Kampala
Port in Bukasa and Development of Kabaale Airport due to the lengthy procurement process
for the boats, RAP implementation challenges and the Covid pandemic breakdown that
affected project progress respectively. Overall, 84.8% of the funds released had been spent by
the end of June 2020.
28 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

5.2 PHYSICAL PERFORMANCE

This section covers the assessment of the performance based on the Programme Outcome
indicators, the performance of the Directorate of Transport and the performance of the
Directorate of Engineering and Works.

5.2.1 PERFORMANCE BASED ON PROGRAMME OUTCOME INDICATORS

Table 8: Performance Based On Programme Outcome Indicators

Programme Sector Programme indicator Achieved Targeted Actual Remark


Outcome Outcome Outcome measure 2018/2019 2019/20
contributed Indicator 2019/20
to by the
Programme
Outcome
Relevant Improved % of Driv- % 50% 55% 40% The private
policy and safety of ing Schools owners lack
regulatory transport meeting the capital to
frame work services required invest and
for safety of standards meet the
Transport required
services standards
Increased Improved Proportion % 23% 25% 23% Limited
efficiency and transport of functional funds thus
effectiveness system rail limiting
of transport rehabilita-
services tion of the
dilapidated
lines.
Strengthened Vibrant and Proportion of % 30% 30% 14.92% Low capacity
National operational construction of the local
construction national works (value) contractors.
Industry construc- executed by They there-
tion indus- local fore cannot
try take up large
firms projects
Improved Improved Percentage % 65% 68% 67% Heavy rains
urban and transport of District and low ab-
community system roads in fair sorptions of
access roads to good con- Local Gov-
dition ernments
affected
hitting the
target.
Functional Improved % of district % 96.13% 90% 88.5% Limited
government transport equipment in funds to
vehicles ,road system good work- undertake
equipment ing condi- repairs.
and ferry tion.
services
improved co- Enhanced Level of com- % 71.3% 75% 71.3% Limited
ordination of sector pliance of the funding and
sector priori- imple- Ministerial the impact
ties, policies, mentation Policy State- of COVID 19
strategies capacity ment affected the
institutions performance
and budgets (MPS) to
Gender and
Equity bud-
geting.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
29

5.2.2 PERFORMANCE OF THE DIRECTORATE OF TRANSPORT

The Directorate of Transport comprises of three departments; Maritime Administration department,


Transport services and Infrastructure department, and Transport regulation and Safety department.
The key functions of the directorate are to:

1) Formulate transport policies, laws and regulations in conjunction with the department of policy
and planning.
2) Monitor and evaluate the effectiveness of transport policies, laws and regulation.
3) Develop and set standards for transport services in all modes.
4) Provide technical advice on transport matters.
5) Oversee performance of Uganda Civil Aviation Authority (UCAA), Uganda Railways Corporation
(URC), Transport Licensing Board (TLB) and National Rod Safety Council (NRSC).

The performance of the directorate in the financial year 2019/20 is as indicated in table 9:

Table 9: Physical Performance of the Directorate of Transport


30 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Thematic Performance Remark


Area
40 % of L. Victoria covered by a GSM signal against a Covid 19 affected achieving the
target of 50% target.
Maritime
transport Inception report of the Maritime
Search and Rescue Policy was prepared and
submitted.
On having Ratification of the revised African Still on going
Maritime Transport Charter (AMTC) 2010
completed; the performance achieved was Legal
clearance from Solicitor General on the Cabinet
memo for ratification of AMTC was secured

Draft terms of reference for developing Draft terms of reference for


developing Search and Rescue
Search and Rescue Manuals were developed and Manuals were not reviewed due to
are awaiting review and adoption. The target was to failure to convene meetings of
have the search and rescue manuels.
stakeholders to review due to
COVID 19 lockdown

Cabinet memo for the Inland Water On target


Transport Bill was submitted to Cabinet Secretariat
and was approved for gazetting.
Two (02) out of four (04) Public awareness and Public awareness campaign on L.
advocacy campaign on safety of water transport Kyoga could not be conducted due
were conducted on Lake Victoria and Lake Albert. to COVID 19 restrictions on public
meetings.
Six (06) Aids to Navigations out of the targeted 11 Limited funds
were inspected for functionality (PortBell, Nakiwogo,
Kyanvubu, Waterfront
Beach).
On the supporting the establishment of the On target
Maritime training institute at Busitema University;
Consultations on the draft MoU between MoWT and
Busitema University finalized

On the development of the boat standards ;only Delays were caused by SoPs set by
Bidding documents for the Boatbuilding standards Government during Lock-down
were prepared due to COVID-19 outbreak.
On the construction and equipping of the 9 Search Awaiting Bank No Objection to
and Rescue centres; Contract for design of 9 Search submit draft Contract to Solicitor
and Rescue Centres was signed. General Office.

On the extension of Maritime Communication


Network (MCN) on Lake Victoria; Firms to develop
Maritime SMS and Voice system to activate Short
Code were shortlisted
Five (5) Officers out of the 06 targeted were trained Travel restrictions during
in Search and Rescue. COVID-19 lock-down limited the
training
One (01) Search and Rescue awareness campaign was COVID-19 Pandemic lockdown
held instead of the four planned. affected achieving target
One (01) Search and Rescue awareness campaign was COVID-19 Pandemic lockdown
held instead of the four planned. affected achieving target
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
31

Thematic Performance Remark


Area
Maritime On the procuring assorted equipment for Search
transport and Rescue Centres and a Maritime Rescue
Communication Center on Lakes Victoria, Kyoga and
Albert; Start up equipment, furniture and Life Saving
Appliances were delivered.

Annual contributions to International On target


Maritime organization (IMO) was paid for 2019.
Development of new Kampala Port in Bukasa
i) Environmental and Social Impact Assessment
(ESIA) for Development of Bukasa Port was
completed.
ii) Resettlement Action Plan for Project Affected
Persons (PAPs) for Development of Bukasa Port was
completed.
iii) 1,149 Project Affected Persons in Bukasa Area
were compensated.

258. Flag and Port State Control Inspections were Inspections were affected by
conducted out of the targeted 500 inspection. limitations to travel caused by
In land COVID-19
water
inspection/ 252 in land water vessels were registered and Inspections were affected by
licensing licensed out of the targeted 300 in land water limitations to travel caused by
vessels. COVID-19.

Two( 02) out of three (03) public awareness . COVID-19 Pandemic lockdown
campaign on inspection, registration and licensing affected achieving target
were conducted

85% of Construction Works of Kinawataka-Bukasa On target


Road was completed.

Procurement of Maritime publications and official log on target


books for vessels was completed and awarded.
Three (03 ) ports were Inspected for Compliance to On target
SOLAS requirements CAP11/1 against a target of two
ports.
Only six (06). landing sites (Nakiwogo and Kasenyi, 19 landing sites could not be
Kiyindi, Masese,Bwondha and Bugoto) out of inspected due to COVID-19 lock
the targeted 25 landing sites were inspected for down
compliance to safety, security and environmental
requirements

Road Consultations carried out through a benchmarking On target


Transport exercise on Statement of Requirements for the
services motor vehicle registration system, Operations and
Business Process Flow Manual for implementation of
motor vehicle registration and Legal framework for
implementation of motor vehicles registration.
32 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Thematic Performance Remark


Area
21,209 Public Service Vehicles were inspected out of COVID-19 Pandemic lockdown
the targeted 50,000 vehicles. affected achieving target.

Road
Contract for Remodeling of URC block and URA On target.
Inspection / warehouse to house the Uganda Computerized
Licensing Driving Permit Facilities for the digital archiving of
motor vehicle manual registration records signed and
remodeling Works at 100% as had been planed
55. Driving schools were inspected to ensure COVID-19 Pandemic lockdown
compliance with regulatory Standards out of the 75 affected achieving target.
driving schools targeted.
1,156 Drivers’ Badges were processed COVID-19 Pandemic lockdown
affected achieving target.
and issued out of the 1,500 targeted.
32,660 PSV were licensed out of the target of 22,000 Stepped up enforcement and
PSVs vehicles. requirement for route charts for
taxi operation.
42. Driving Schools were license out of the 75 schools COVID-19 Pandemic lockdown
planned. affected achieving target.

Road safety Internal Consultations and literature review on rules on target


of the road regulations were carried out.

Materials were procured and delivered for the on target


Annual Road Safety Week.

Carried out joint road safety inspections for black COVID-19 Pandemic lockdown
spots in Western Uganda and Eastern Uganda along affected achieving target.
the National Corridor routes only instead of all the
four regions (North, East, west and central).

Only One (01) Road Safety awareness campaign out COVID-19Pandemic lockdown
of the four planned was conducted during URA Tax affected achieving target.
Appreciation Week. Road Safety Awareness were
carried out during Tweddeko Caravan along Kampala
-Luwero Road.

11 Motor Rally routes were inspected and safety COVID-19Pandemic lockdown


measures recommended. affected achieving target.

Two (2) Road accidents investigations were carried COVID-19Pandemic lockdown


out and reports made. affected achieving target.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
33

Thematic Performance Remark


Area
Air Three(03) out of the four (04) inspections of Entebbe The achievement of the target
transport International Airport were conducted was affected by lock down due to
Covid 19
Seven (07) out 12 targeted upcountry aerodromes COVID-19 Pandemic lockdown
were inspected in Mbarara, Kasese, Jinja, Tororo, affected achieving target
Soroti;
Kabale Airport(Hoima) COVID-19 Pandemic lockdown
affected achieving target.
i) Biodiversity studies for the mitigation
Implementation plan was prepared.
ii) Baseline report for the air and noise emissions
and dispersion model for the Operation phase was
prepared.
iii) 42.7% cumulative physical works for the
development of Kabaale airport (Phase I) was
completed against at target of 50% .
All thirteen Upcountry aerodromes at Arua, on target
Gulu, Pakuba, Lira, Moroto, Kidepo, Soroti, Tororo,
Jinja, Kasese, Mbarara, Masindi and Kisoro were
maintained as planned
Apron reconstruction (rehabilitation of taxiway and on target
apron) at Kisoro aerodrome completed (100%);
Cadestral survey and titling of the aerodrome land on target
(Anai , Soroti and Kisoro Sites) were conducted
40% of Earthworks for Improvement of taxiway link on target
at soroti airport was Completed.
EACAA-Soroti
i) Nine (9). Aircraft were maintained.
ii) 8 technical staff were trained as planned.
Others:
(i)Two( 2) ICAO and Regional Programmes were
coordinated (Single African Airspace summit in
Kigali Rwanda and Designation of Uganda Airlines
in Kenya, Tanzania Burundi, South Sudan and
Somalia).

(ii)Participated in the International Civil Organization On target


Negotiation Meeting(ICAN) in Jordan in December
2019 where Uganda concluded three Bilateral Air
Services Agreements(BASAs) with Austria, Italy and
Germany.

(iii) Designations for Uganda Airlines to commence On target


commercial flights to Nairobi, Juba, Mombasa,
Dar el Salaam, Mogadishu, Bujumbura, Zanzibar,
Kilimanjaro were concluded.

(iv) Coordinated the designation of Uganda Airlines On target


to DR Congo, Zambia and Zimbabwe.

(v)Initiated BASA negotiations with Congo COVID-19 Pandemic lockdown


Brazzaville. affected achieving target.
34 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Thematic Performance Remark


Area
(vi) Commenced the process of reviewing the BASA COVID-19 Pandemic lockdown
between Belgium and Uganda, affected achieving target.
Uganda and Zambia.

(vii) Participated one instead of two East African COVID-19 Pandemic lockdown
Consultative Meetings on Facilitation of Air affected achieving target.
Transport in the 46th by-annual East African
Consultative meeting on Facilitation of Air Transport
(EAC FAL) in Dar el Salaam-Tanzania.

Three (03) Inspections instead of 04 of Entebbe COVID-19 Pandemic lockdown


International Airport were conducted. affected achieving target.

Organization structure for aircraft accident This is still on going. It was


investigation unit was developed pending approval partially affected by the lockdown
by the Ministry’s Top Management Team (TMT). due to Covid 19.
Partial procurement of aircraft accident Investigation
kit initiated. Bidding documents prepared, approved
and issued out. The target was establishment of
Aircraft accident and incident investigation unit .
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
35

Thematic Performance Remark


Area
Railway Safety inspection on railway lines was on target
Transport
conducted along Kampala- Tororo-
Malaba Railway line.
Two (2) rail transports Safety sensitization were COVID-19 Pandemic lockdown
carried out along the Eastern line out of a target of affected achieving target.
four(04).
Two (2) out of four (04) targeted Rail Accident reports Only two accidents occurred.
reviewed and
occurrences investigated.

Standard Guage railway Still on going


i) Field inspection visits of rivers and Lakeshores
were carried out.
ii) NFA valuation report for the ROW in 11 Central
Forest Reserves was reviewed.
iii) 30.001 Acres of the SGR corridor was
acquiredagainst a target of 28.748 acres.
iv) 100 PAPs were compensated.
v) 4.8Kms of the corridor was cleared in Namutumba
district. Boundary trees Planted to demarcate the
corridor. Periodic surveillance of the acquired
Corridor continues.
Metre Guage Railway
i) Civil works for the rehabilitation of Tororo-Gulu
railway line commenced.
ii) 1,000 PAPs for Tororo-Gulu railway line were
disclosed, verified and are awaiting compensation.
iii) Routine maintenance was carried out on 280kms
(weed control, packing, & opening of drains)
iv) Minor spot repairs were done on the track and a
total of 5.8kms of track was maintained.

Routine maintenance of 745wagons against a target


of 500wagons was undertaken.

One Stop i)Monitoring and Supervision of Construction works


Border for One Stop Border Posts at Katuna (Phase 1), Elegu
Posts (OSBP) (Phase2) and Malaba (Phase 2) was undertaken and
reports prepared.
ii) Bilateral meeting with Kenya was held on12 March
2020 to fast-track the construction of outstanding
works at Malaba OSBP.
iii) Contracts for construction of Goli OSBP and
Ntoroko Lake port signed.
iv) Construction of Katuna OSBP (PhaseI) was
completed and facilities handed over for use.
v) Construction of exit road (2.15km) at Malaba OSBP
was completed (technical handover of the exit road to
URA was done on 13 Feb 2020).
36 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

5.2.3 PERFORMANCE OF THE DIRECTORATE OF ENGINEERING AND WORKS

The directorate of engineering and works comprises of the departments of Roads and Bridges,
Public structures, Mechanical Engineering Services, and Construction Standards and Quality
Assurance.

The physical performance of the directorate of Engineering and Works is table 1

Table 10: Physical Performance of Directorate of Engineering and Works


ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
37

T h e m a t i c Performance Remarks
Area
District, Of the targeted 132.8 km to be rehabilitated in Tororo, The underperformance was
Urban and Namutumba, Serere, Busia, Butaleja, Budaka and Buke- due to low funding.
communi- dea; 93.5 km were just opened; 77.1 kms were opened
ty Access and graded while 69Km were opened, graded and grav-
roads. elled by the Eastern Unit under Force Account (Details
in Annex 7 ).
64.7kms were fully gravelled out of a target of 131.1kms Limited funding affected
in the financial year by the central force account road performance.
unit in the districts of Buikwe, Gomba, Kasanda, Kayun-
ga, Kikuube, Luwero, Lwengo , Mukono and Nakaseke (
Details in Annex 4)
135.2 kms of district roads had been targeted to be re- The underperformance was
habilitated in Kitgum,Nwoya,Moroto,Albetong,Omoro, due to low funding
Lira and Apac but only 69.8 kms were opened,67.5 kms
were opened and graded while only 58.5 kms were
opened,graded and gravelled by the Northern Unit
under Force Account.(Details in Annex 9)
Of the targeted 140.60km to be rehabilitated in Kamuli, Limited funding affected
Buyende, Jinja West, and Bugiri. 93.8 km were just performance
opened; 140.6 kms were opened and graded while only
41.18Km were opened, graded and gravelled by the Jinja
Unit under Force Account (Details in Annex table 6).
97.3Km were opened, 54.8 kms were opened and graded Work Progress was affected
while, and 46.6 km were fully gravelled out of a target when No funds were
of 130.1km by the western force account unit.(Details in released for quarter four.
Annex 8 ) Execution was also affected
by COVID -19 lockdown
15 km urban roads were sealed under force account out Work Progress was affected
of the target of 16km (Details in Annex 10 ) when No funds were
released for quarter four.
Execution was also affected
by COVID -19 lockdown
14 bridges are under construction (Details in Annex- Details on progress of each
table 2 ) bridge is in table on bridges
attached.
Detailed designs for Kagera Bridge, Ongino Tisai Bridge On target
and NakadidirLukolwe-Namuganga swamp, Nyahuka-
Mirambi Bridge, Komorotot bridge, Mutti-Gwa Kirevu
and Rwammable swamp crossing, Karujumba Bridge,
Bugibuni-Bunadasa Bridge and Rwammabaale Swamp
Crossing were conducted and completed in the financial
year.
Only 10 retained Road camps in South Western and Lack of enough funds to car-
North Western surveyed out of the 207 road camps ry out the works.
planned.
38 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

T h e m a t i c Performance Remarks
Area
District, 33 out 33 targeted projects of UNRA were monitored On target
Urban and and evaluated on progress and reports Prepared.
communi- Kiruku - Bukiiyi gravel road Constructed to completion On target
ty Access as part of training in LBT; The road measuring 4.3Km
roads. long was completed in Q1 and is ready for handover to
Sironko district.
456Trees were Planted along Kiruku -Bukiiyi LBT mod- COVID19 affected achieving
el road reserves out of 500 trees targeted. the target.
LCS trial(9km) contracts are 100%completed in districts On target.
of

Luweero, Masaka, Busia, Tororo and Sironko. Cumu-


lative progress for LCS trial contract roads in Mbale,
Paliisa, Namutumba and Nakasongola districts stands at
94% todate with seal works in progress.
126 Gang leaders from 12 DLGs of Kotido, Kabong, Mo- On target.
roto, Amudat,Nakapiripirit, Zombo, Nebbi, Arua,

Maracha and Napak trained in Routine Road mainte-


nance; and Training Needs Assessment was carried out

in 9 DLGs for selection of Trainable road gangs in West


Nile and Central regions; Districts include; Zombo, Neb-
bi,Arua, Maracha, Yumbe, Adjumani, Moyo and Pak-
wach.
Road works in 30 urban councils instead of the 40 Funds for monitoring works
planned for were monitored. in urban councils were not
released in Q4.
687.4km rehabilitation works of Inter-connectivity 1. Non release of funds by
roads were achieved out of a target of 1050 km in the MoFED in Q4 .
selected districts (Details in Annex 5 )
2. 382km under 57 lots were
procured but Contracts not
signed due to non-release of
funds.

3. Covid-19 pandemic related


restrictions led to slow prog-
ress of the ongoing works.
Some sites had to temporar-
ily close
25km of the 25 km of Kayunga-Nabuganyi, 90% Earthworks of Kayunga
(20.2Km) Nansana-Kireka-Bira, (4.8 -Nabuganyi and Nansana -
Km) in Kayunga and Wakiso Districts Kireka- Bira probase roads
repectively were constructed using Probase carried out. Still on going.
technology
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
39

T h e m a t i c Performance Remarks
Area
42km of District roads for Low Cost Sealing were de- On target
signed as had been planned
42km of District Roads were sealed using Low Cost On target
SealingTechnology on Nyaruzigati-Kyapa-Kitabu, Kyer-
ima-Nakaseeta-Lukonda, Bufulubi-Kyanda-Buyemba
and Kisozi-Kifampa as had been planned.
58.75% average availability for Ministry vehicles was There were no funds availed
attained against a target of 70%. to facilitate maintenance/
Mechanical
repair of the vehicles.
services
37.5% average availability for MV Kalangala was at- Services of MVKalangala
tained instead of the 95% targeted. were suspended to allow the
ferry undergo mandatory
survey and maintenance.
100% average availability for Lake Bisina ferry was On target
attained against a target of 95%.
67.5% instead of 65% targeted average availability tar- Repairs on some of the pro-
geted for the Government protocol fleet was attained. tocol vehicles that were
on-going since Q3 were able
to be completed.
88.5% average availability for equipment acquired from Monitoring ensured proper
Japan attained against a target of 80%. management by District
Local Governments
Emergency repair works for Nakiwogo and Lutoboka The piers at Nakiwogo (En-
piers were just initiated. The target was to have them tebbe Mainland) and Lutobo-
completed and in a good condition ka (Kalangala Island) landing
sites were submerged due
to the rise in water levels of
Lake

Victoria.
47% average availability for equipment acquired from Inadequate funds to rehabil-
China was attained instead of the 60% targeted. itate or carry out major re-
pairs for the road equipment
acquired from China.
255 equipment operators from District Local Govern- The training program for
ments trained against a target of 480 operators. equipment operators, ar-
tisans and technicians
was suspended due to the
COVID-19 pandemic.
Only 2 bailey bridges on rivers Cheptui(in Magonja, Bi- There was no inspection and
honge Bulambuli district)and Unyama (in Atiak Amuru monitoring of bailey bridges
district) were inspected and their condition monitored conducted because of lack of
against a target of 8 bailey bridges. funds
40 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

T h e m a t i c Performance Remarks
Area
310 against a target of the 280 materials testing, quality This is demand driven and
control and research on construction material reports all requests were handled
Construc-
were produced and reports produced.
tion stan-
500 assorted laboratory equipment for CML-Kireka and on target
dards and
Regional laboratories procured (bitumen, Soil, Concrete
quality
and Rock testing equipment).
Assurance.
16 out of the planned 10 geotechnical investigation This is a demand driven ac-
were conducted on the Kayunga – Nabuganyi road. tivity.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
41

T h e m a t i c Performance Remarks
Area
Contracts for Supervision of Consultants and Contrac- On target
tors were monitored and supervised (Mpondwe and
Public
Bunagana OSBP, Goli and Ntoroko OSBP, UgIFT Project
structure
-MoH and MoE&S), Lukaya Market, Kyabazinga Palace
and Tito Okello House and Others.
22 venues for National functions were prepared. Others could not be prepared
due to COVID 19 lockdown.
30 out of 40 planned Technical Support services were Others could not be rendered
rendered to MDAs (Office of President ;Ministry of due to COVID 19 lockdown.
Finance; Parliament of Uganda; Ministries of Tourism,
Internal Affairs, Foreign Affairs, Defence and Veteran
Affairs; Ministry of Health(UgFT), Ministry of Educa-
tion and Sports(UgFT), Uganda Police Force;Trademark
EA, URA, IGG, UTC-Lira and others).
ERB, UIPE, UNABCEC and NEMA activities were sup- On target
ported as had been planned.
National Building Review Board supported and over 8 On target
Board Meetings held with 2 via Zoom due to Covid 19.
All Six( 06) Investigations of Construction, Building and On target. The investiga-
Fire related Accidents were conducted in Jinja, Kansan- tions are demand driven.
ga, Makerere, Kampala City and Makindye and reports
were produced.
85 District technical audits were conducted on various Others could not be under-
district local governments out of a target of 90. taken due to limitation on
movements as a result of
restrictions imposed during
the covid-19 outbreak.
30% of Central Materials Laboratory was rehabilitated Issues related to availability
the target was 50%. of funds hampered the final
stages of the procurement.
Four (04) instead of 08 Buildings were assessed for Others could not be assessed
Structural Integrity; Palm Courts Office Block for due to COVID 19 lockdown.
NITA-U report submitted on 25/11/2019, Plastic Bottle
Construction Technology

by Upcycle Africa Ltd report submitted on 13/12/2019,


and Chancery Chambers in Mogadishu-Somalia; and
Site adjacent

Residence of IGG in Kololo.


42 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

T h e m a t i c Performance Remarks
Area
Cross 90 Environment and Social Safeguards Technical audits The output is demand
cutting in MDA were undertaken as demanded. driven and the target was
issues achieved.
600 Model road workers and communities sensitized on The staff from other districts
gender and equity mainstreaming and HIV/AIDS Man- could not be trained due to
agement in Buhalya and Lusaka Low Cost Seal road sites inadequate funds and inter-
and Butalejja District. ruption by country wide lock
down as a result of corona
virus threats.
38 Non Engineering staff from 6 District LGs & 6 Urban Few were trained due to lim-
LGs in CCIs were trained in Environmental and Social ited funds.
Safeguards Management.
Sensitization of communities was done on the impor- On target
tance and need to plant trees along the model roads;
Meeting tookplace on Kiruku - Bukiiyi LBT model road.
456 Trees Planted along Kiruku -Bukiiyi LBT model On target
road reserves.
3 instead of 4 Quarterly HIV/AIDS Technical Commit- The fourth meeting could
tee meeting held and activities undertaken. not be held due to the out-
break of COVID-19.
Four (04) Gender and Equity audits were conducted on There was limitation on
MDAs. movements due to the
restrictions imposed during
the covid-19 outbreak. No
technical audits were could
be done in the

last quarter.

5.2.4 PERFORMANCE OF THE POLICY, PLANNING AND SUPPORT SERVICES DEPART-


MENTS

The support services departments and divisions include the department of Policy and
Planning, the Division of Procurement, Human resource Management and the department
of Finance and administration.

The department of Policy and Planning was able to achieve the following Key outputs in the
FY 2019/20:

(a) Held a validation workshop for the National Transport and Logistics Policy and Strategy
as had been planned.
(b) Did verification of survey location points for the preparation of the National Transport
Master Plan in western Uganda as had been planned.
(c) The draft Regulatory Impact Assessment (RIA) for the National Transport and Logistic
Policy was prepared.
(d) Regulatory Impact Assessment (RIA) for the Inland and Water Transport Bill was finalised
as had been planned.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
43

(e) Situation analysis and Interim reports for the development of the 2nd National Transport
Master Plan (2021 - 2040) was prepared.
(f) The draft National Railway Policy and Draft Marine Search and Rescue Policy were
prepared.
(g) Compendium of service delivery standards for the sector was produced as had been
planned.
(h) On the development of HIV AIDS work place Policy, only Terms of reference for HIV/
AIDS workplace policy were reviewed. Development of HIV AIDS work place policy was
deferred to FY 2020/21 due to the COVID 19 lock down.

The division of human resource was able to achieve the following key outputs in the FY
2019/20:

(a) Ninety six (96) staff members were trained in short courses. Only three (03) staff were
trained in long term courses out of the total target of 221.The targeted could not be met
due to limited funds..
(b) Only 32 staff members were recruited out of the 110 planned to be recruited. Of the
recruited thirteen (13) were new entrants and 19 were promoted. The underperformance
was due to delay in the recruitment process, insufficient wage and the outbreak of Covid19
which halted government business for five months.

The department of finance and administration was able to achieve the following key outputs
besides the routine out puts:

(a) The ministry communication strategy was implemented through short documentaries,
field visits with the media, talk shows, media briefings and newspaper supplements.
(b) All projects and programmes were audited and reports made in the first, second and third
quarter. Projects and programmes were not audited in Q4 due to the Covid 19 lock down.

5.3 CHALLENGES

The following challenges were experienced during the FY

a) Inadequate budget for projects and activities (e.g undertaking the development of the
inland water master plan, Census of government buildings, some force Account road
rehabilitation projects like Nambweke - Bushabala – Buhunya (7.9km) road in Busia,
Angola - Pukurotho – Katerema(7.0km) in Tororo, Budaka - Iki-Iki(12.3 km) in Busia
, Opiko – Kalapata (6.0km) in Bukedea, Mbonjera-Mbulambuturo-Gatare-Foto Kigezi
(12.km) in Kisoro, Katatenga-Rwidoga (2.5km) in Rakai etc)
b) Licensing and registration of water vessels was affected by limitations to travel caused
by Covid 19.
c) Interruption by country wide lockdown as a result of corona virus which affected
achieving the planned targets e.g in force account projects, trainings for crew and
pilots that are done out of Uganda, Road Crash data base activities planned for Q4 etc.
d) Land related issues that attracted compensation affected rehabilitation of roads under
force account e.g Ibanda-Kisara-Mukabara road(8.8km) in Kikube etc
e) Delays in procurement of the contractor to undertake dredging, Piling and Swamp
surcharging works at Bukesa port.
44 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Kampala Northern
bypass works
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
45

6.0 PERFORMANCE OF UGANDA NATIONAL ROADS AUTHORITY:


VOTE 113

6.1 FINANCIAL PERFORMANCE

UNRA is appropriated a budget for its recurrent and development activities from Government
of Uganda (GoU) with the support of the Development Partners under Vote 113. The
development budget is mainly utilised for the planning, design, rehabilitation, improvement
and upgrading of the national road network. The recurrent budget is utilised for wages to
staff and the organisational operational or administration costs. In addition, UNRA receives
funds from the Uganda Road Fund specifically for the maintenance and operation of the
National Road Network. The total approved budget for FY 2019/20 was UGX 4.289 trillion
compared to UGX 3.4429 trillion in FY 2018/19. Table 11 shows a summary of the funds
received last FY and the performance on the overall budget.

Table 11: Summary of UNRA’s Budget Performance

ITEM
Q1+Q2+Q3+Q3+Q4
Warrant (UGX BN)

% BUDGET SPENT
FUNDS UNSPENT
PAYMENTS (UGX
BUDGET FOR FY

UN-RELEASED

% BUDGET RE-
CUMULATIVE

% RELEASES
APPROVED

RELEASED
(UGX BN)

(UGX BN)

(UGX BN)
BUDGET
2019/20.

LEASED

SPENT
BN)

RECURRENT                
WAGE 71.105 71.105  - 71.105  - 100.00% 100.00% 100.00%
NON-WAGE 27.347 22.768 4.579 22.764 0.004 83.26% 83.24% 99.98%
SUB TOTAL 98.452 93.873 4.579 93.869 0.004 95.35% 95.34% 100.00%
DEVELOPMENT                
GOU 1,744.55 1,727.45 17.10 1,727.23 0.22 99.02% 99.01% 99.99%
EXT. FINANCING 2,176.06 811.29 1,364.77 440.67 370.62 37.28% 19.99% 54.32%
TOTAL Dev’t 3,920.62 2,538.74 1,381.88 2,167.90 370.84 64.75% 55.15% 85.17%
MAINTENANCE 270.00 282.17 -12.17 281.78 0.39 104.51% 104.36% 99.86%
– URF
GRAND TOTAL 4,289.07 2,914.78 1,374.29 2,543.55 371.23 67.96% 59.17% 87.27%

6.1.1 RECURRENT: WAGE

By the end of FY19/20; 100% of the approved wage bill amounting to UGX 71.11Bn was re-
leased. Out of the UGX 71.11Bn wage released, UGX 71.11Bn was spent by close of the FY
2019/20 representing 100% of budget released spent.

6.1.2 RECURRENT: NON-WAGE


Out of the approved budget amounting to UGX 27.347Bn, UGX 22.768Bn was released by
end of the FY 19/20 representing 83.26% of the appropriated budget. Out of the cumulative
release amounting to UGX 22.768Bn, UGX 22.764Bn was spent by the end of the FY 2019/20
representing 99.98% of the releases spent.
46 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

6.1.3 DEVELOPMENT

UNRA receives funding for road development through two sources that is; GoU and External
Financing.

6.1.3.1 GOU FINANCED

For the FY19/20, a total of 1,744.55 Bn was approved for the Development GoU budget, out of
which UGX 1,727.45 Bn (99.02%) was released. Out of the cumulative release of UGX 1,727.45
Bn, UNRA spent UGX 1,727.23 Bn by end of the FY representing 99.99% of the releases spent.

6.1.3.2 EXTERNALLY FINANCED

A total of UGX 2,176.06Bn was appropriated for external financing under FY 2019/20 of
which UGX 811.29 Bn was cumulatively released by end of FY representing 37.28% of the
appropriation released. The budget included appropriations of UGX 1.1 trillion (50%) which
could not be spent within the year:

o UGX 717.5 billion was appropriated to the Critical Oil roads, yet MoFPED was still
finalising the negotiations with China Exim and approval by Parliament. The funds
were not made available to UNRA by the end of the year;

o UGX 325 billion was allocated by MoFPED and appropriated to Kampala-Jinja


Expressway, a project which is still under preparation.

This means that UNRA’s externally financed budget, excluding the two above misappropria-
tions, was UGX 1 trillion, of which 43% was absorbed. Other reasons for the low absorption
of the external financing component include:

o UGX 150 billion was allocated to projects under procurement, whose contracts were
signed after the close of the FY;

o A few projects suffered slow progress due to the extended heavy rains and the
lockdown due to COVID-19 pandemic while NERAMP did not disburse (UGX 123
billion) due to the suspension of works to allow the contractor rectify the safeguards
management on the project.

6.2 PHYSICAL PERFORMANCE

6.2.1 PERFORMANCE AGAINST THE SECTOR INDICATORS

6.2.1.1 Golden Indicator 1: Condition of The Road Network

The measurement of the road condition is by the International Roughness Index (IRI). Rough-
ness is a good indicator of the condition of the road because it affects the level of service in
terms of the riding quality, speed and cost of vehicle operation and maintenance. The con-
dition of the roads is a Key Performance Indicator that is used internationally for the roads
system. It refers to the structure, roughness and unevenness of the road. Golden Indicator 1
is: “% of the roads network in fair-to-good condition”.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
47

Table 12: Condition of the National Road Network (June 2020)

Year Paved Roads Condition (Km) Paved Roads Condition (%)


Good Fair Poor Total Good Fair Poor
2013/14 2505 531 759 3795 66% 14% 20%
2014/15 2,707 478 796 3,981 68% 12% 20%
2015/16 2,040 913 1204 4,157 61% 27% 12%
2016/17 2,924 979 354 4,257 69% 23% 8%
2017/18 3,413 1,001 136 4,551 75% 22% 3%
2018/19 3,862 802 351 5,015 77% 16% 7%
2019/20 4
1,463 903 451 2,817 52% 32% 16%
Unpaved Roads Condition (Km) Unpaved Roads Condition (%)
Good Fair Poor Total Good Fair Poor
2013/14 5,678 5,850 5,677 17,205 33% 34% 33%
2014/15 6,297 5,616 5,106 17,019 37% 33% 30%
2015/16 3,004 9,868 3,515 16,387 18% 60% 21%
2016/17 5,212 7,003 4,072 16,287 32% 43% 25%
2017/18 3,678 9,755 2,558 15,993 23% 61% 16%
2018/19 3,802 8,079 3,960 15,841 24% 51% 25%
2019/20 3,945 4,215 2,426 10,586 37% 40% 23%

The trends in the improvements in the condition of the national paved roads are as shown
in the Figure 2. Figure 2 depicts that paved roads in good condition have increased over the
past 6 years however in comparisons to this FY there was a reduction. In the FY 2019/20
the national roads network in fair to good condition was 84% for paved roads and 77% for
unpaved roads.

Figure 2: Condition of Paved National Road Network over the years

4 As of June 2020, only 50% of paved roads had been surveyed and 90% of unpaved roads.
48 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Figure 3: Condition of the Unpaved National Road Network over the years

6.2.1.2 Golden Indicator 2: Paved Roads Stock

Road Development – Upgrading to Paved Bituminous

The paved roads refer to roads having an all-weather bituminous surface. The stock is
measured by computing the number of completed kilometres of gravel roads upgraded
to bitumen standard or new roads constructed to bitumen standard. Currently 24 road
upgrading projects (new construction and upgrading from paved bituminous standards)
covering a total length of 1,692 Km. At the beginning of the year, these were at various
stages of construction or physical progress. The annual increase in physical progress for all
the projects was assessed to be equivalent to 310 Km as the total construction output within
the FY 2019/20.

Table 13: % Performance and Km-Equivalent Achieved on upgrading projects (June 2020)

S/N PROJECT NAME LENGTH


KM EQUIVALENTS
% PROGRESS JUNE

% PROGRESS JUNE

% PROGRESS JUNE

% ANNUAL PER-
FORMANCE
2020
2018

2019

(Km)

4.      Musita - Lumino / Busia - Majanji 104 51 98 100 47 3.12

5.      Akisim – Moroto 50.3 54.7 98 100 2 0.83


6.      Bulima - Kabwoya 66 72 81.4 91.8 10.4 6.87
7.      Soroti – Katakwi - Akisim 100 54.7 78 96.8 8.3 18.33
8.      Mubende – Kakumiro - Kagadi 107 35.7 68.5 91.4 22.9 24.43
9.      Kyenjojo - Kabwoya 100 41.9 66 77 11 11.49
10.   Kampala Northern Bypass -Phase 2 17 42 61 72.9 11.9 2.04
11.   Bumbobi - Lwakhakha 44.5 9 55.5 83.9 28.4 12.61

12.   Hoima – Butiaba - Wanseko Road 111 0 28 57 29 32.1


ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
49

13.   Pallisa - Kamonkoli 44 0 25 65.8 40.8 21.26

14.   Kigumba – Bulima 69 0 24 51.3 27.3 18.84

15.   Kitala - Gerenge 10 0 23 43.8 20.8 1.68

16.   Tirinyi –Pallisa - Kumi 67 0 17.5 75.6 40.8 38.85

17.   Buhimba – Nalweyo - Bulamagi & 93 0 14.5 40.1 25.6 23.81


Bulamagi - Igayaza - Kakumiro

18.   Masindi Park Junction and Tangi 159 0 11 47.1 36.1 56.84
Junction - Para - Bulisa
19.   Kapchorwa - Suam 73 0 5 17.3 12.3 9.04

20.   Masaka - Bukakata 41 0 1 30.8 29.8 12.53

21.   Rukungiri – Kihihi - Ishasha/Kanungu 78.5 0 1 19.2 18.2 14.42

22.   Busega - Mpigi Expressway 23.7 0 0 0.4 0.4 0

23.   Muyembe – Nakapiripirit 92 0 0 0 0 0

24.   Atiak – Laropi 66 0 0 0 0 0


TOTAL 309.75

From the Table 13, 6 projects performed between 81% -100%, 5 projects performed between
41%-60% and between 0%-20% while 4 projects performed between 61%-80%. This is
cumulative progress of the project.

Table 14: Substantially Completed Upgrading Road Projects (as at 30th June 2020)

S/N Project Name Length (Km) Funder Amount UGX (Bn)

Bulima - Kabwoya 66 GOU 167.189

Mubende – Kakumiro - Kagadi 107 GOU 484.887

Soroti – Katakwi - Akisim 100 GoU 398.884

Nyenga – Njeru 10 GoU 29.546

Bumbobi - Lwakhakha 44.5 AfDB & GOU 153.105

Kyenjojo - Kabwoya 100 IDA & GoU 214.564

Total 427.5 1,448.175

Table 14 shows the projects that were substantially completed by the end of the FY, adding
427.5 Km to the paved road network. This brings the total paved stock to 5,370 Km, which is
25.5% of the national road network.
50 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

6.2.1.3 Golden Indicator 3: Road Construction/Maintenance Cost

This indicator assesses the per Km costs of the different road development and maintenance
interventions undertaken on the National Road Network. These interventions have been
categorised as follows:

(i) Upgrading gravel roads to bitumen standards (tarmac).

(ii) Rehabilitation and Reconstruction of paved roads that have outlived their design
life. Works involve removal or reuse of base layers, improvement of alignment,
earthworks, and compaction and new surface bitumen layers. Rehabilitation of
paved roads that are in poor condition which involves removal or reuse of base
layers, re-compaction and new surface bitumen layers.

(iii) Under periodic maintenance for paved roads, the sections of the network are re-
resealed or over layed to prolong the lifespan of the road. There are no major
improvements to the base layers. For unpaved roads, periodic maintenance
consists of road re-grading and re-gravelling covering a lifecycle of 2-3 years.
Mechanised routine maintenance, on the other hand, involves spot re-gravelling
and grading of the bad sections/spots

(iv) Routine maintenance activities comprise of recurrent maintenance activities for


both paved and unpaved roads intended to keep the road clean, safe and protected
from damage of aggressive weather, environment, vandalism and loading.
This involves pothole patching, crack sealing, edge repairs using mechanised
compaction, drainage cleaning etc.

Table 15: Road Construction and Rehabilitation Cost (UGX Bn)

Project Name
Supervision Cost
Wearing Course

Land Acquired
Unit cost/ KM
Construction
Length (Km)

Approved

(hectare)
Funder

Cost

Bulima - Kabwoya 66 GOU DBST 167.189 6.375 2.63 13.05

Mubende – Kakumiro 107 GOU Asphalt 484.887 12.789 4.651 53.38


- Kagadi Dressing (AC)
Soroti - Katakwi – 100 GoU Surface 398.884 14.418 4.133 34.67
Akisim Dressing
Nyenga - Njeru 10 GoU Surface 29.546 1.688 3.123 0.0 
Dressing
Bumbobi - Lwakhakha 44.5 AfDB DBST 153.105 10.365 3.673 34.85

Kyenjojo - Kabwoya 100 IDA DBST 214.564 11.338 2.259 24.6

Total 427.5     1,448.175 56.973  3.412  160.55 


ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
51

RECONSTRUCTION/REHABILITATION PROJECTS
Fort Portal - Kyenjojo 50 GoU Asphalt 118.000 2.033 2.401  
Dressing

Ishaka-Katunguru 58 GoU Asphalt 103.000 0.0 1.776


Dressing

Hima-Katunguru 9 GoU Asphalt 83.258 1.680 2.929


Dressing

Nakawa-Seeta 9 GoU 13.953 0.0 1.550

Total 126      318.211  3.713  2.164  

The average construction cost for upgrading roads to paved standard with bituminous surface
treatment during the FY 2019/20 was UGX 3.41 Bn per kilometre as compared to UGX 3.1 Bn
per kilometre in FY 2018/19 and UGX 2.36 Bn per kilometre in FY 2017/18. This cost excludes
the cost of land acquisition, which is shown in the Table 15. This is because the value of land
is dependent on many factors which may not be easily benchmarked among projects or even
road sections in different geographical locations.

The average cost of reconstruction/rehabilitation of the paved roads was UGX 2.16 Bn per
kilometre as compared to UGX 1.8 Bn per kilometre for FY 2018/19 and UGX 1.96 Bn per
kilometre in FY 2017/18. During the reconstruction, the entity uses the opportunity to
improve the geometry and structure of the existing roads, which makes the cost higher than
it, would have been for only reinstating their serviceability. Table 16 shows the cost/Km for
construction and rehabilitation project

Table 16: Average cost of road construction over the years (UGX Bn)

Cost/KM of Upgrading Cost/KM of Rehabilitation


FY
projects projects
2015/16 3.70 2.7
2016/17 2.12  1.12
2017/18 2.36 1.96
2018/19 3.10 1.8
2019/20 3.41 2.16

Road Reconstruction/Rehabilitation

FY 2019/20, rehabilitation of 313 Km of the national roads continued on seven (7) road projects
and a total of 167.1 Km-Equivalent was achieved out of the targeted 200 Km-Equivalent this
represents a performance level of 83.6% compared to 66% in the FY 2018/19.
52 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Table 17: Performance of the Road Rehabilitation Programme

S/N Project Name

Length

Performance 2020
Performance 2019
% Progress June

% Progress June

% Progress June

Km-Equivalent

Km-Equivalent
added 2020
added 2019
Annual

Annual
2020
(KM)

2018

2019
1. Nyenga - Njeru 10.0 0 5 100  0 95 0 10.00
2. Hima - Katunguru 29.0 2.7 65 100 62.3 35 37.3 20.30
Phase 1
3. Nakawa - Seeta 9.0 0 0 100 0 100 0 9.00
4. Fort Portal - 50.0 43.8 93 99.8 49.2 6.8 25.5 3.43
Kyenjojo
5. Ishaka - Katunguru 58.0 3.1 20 96.4 16.9 76.4 10.15 44.07
6. Fort Portal – Hima 55.0 0 11 85.6 11 74.6 8 40.78
7. Nakalama - Tirinyi 102.0 4.8 46 85.5 41.2 39.5 43.54 39.52
- Mbale
TOTAL 313.0             167.10

Hima - Katunguru Phase 1: this road was originally 58km but into two phases. Phase I is
29km and Phase II 29km

At the end of the FY 2019/20, four (4) road rehabilitation projects totalling 146 Km were
substantially completed. Table 18 shows the road rehabilitation projects substantially
completed by June 2020.

Table 18:Road Rehabilitation projects completed in FY 2019/20

No. Project Name Length (KM) Cost (BN)


1 Fort Portal - Kyenjojo 50 118
2 Ishaka - Katunguru 58 103
3 Hima - Katunguru 29 30
4 Nakawa - Seeta 9 14
Total 146 265

6.2.1.4 Golden Indicator 4: Road Maintenance Needs Met

This indicator measures the maintenance budget relative to road maintenance requirements/
needs and it considers the percentage of annual road maintenance needs for funding. The
road maintenance needs for the FY 2019/20 totalled to UGX 596 Bn similar to that of FY
2018/19. A total of UGX 270 Bn was appropriated however, UGX 282.17 Bn was released. The
release represented 47.3% of the annual maintenance needs funded compared to the 52.4%
in the FY 2018/19.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
53

Releases for Maintenance-URF were higher than the appropriated budget due to additional
funding for the emergency works undertaken to address network cut-offs by the heavy
rains during the year. Underfunding of road maintenance is partly responsible for the road
maintenance backlog because the maintenance regime is not being followed. Table 19 show
the funding requirement vis-à-vis amount provide for road maintenance.

Table 19: Funding requirement vis-à-vis amount provided for road maintenance over the
years (UGX Bn)

FY Budget required Amount provided % amount provided


2015/16 582 261 44.85
2016/17 400 217 54.25
2017/18 596 267.8 44.93
2018/19 596 312.56 52.44
2019/20 596 282.17 47.34

Figure 4: Funding requirement vis-a vis amount provided for road maintenance

Road Maintenance Interventions

UNRA carried out maintenance activities on the road network and achieved the following
against the targets. The following were the key outputs and intermediate outcomes from the
road maintenance interventions.
54 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Table 20 : Performance of Road Maintenance Interventions

S/N Indicator

Achievement (Km)

Achievement (Km)

Achievement
FY 2018/19
Target (Km)

Target (Km)

FY 2019/20

FY 2019/20
FY 2018/19

(%)
1 Routine: Km of Paved Roads 5,286 4,811 4,791 5,117.8 107%
Maintained
2 Routine: Km of Unpaved Roads 10,185 27,380 21,275 27,886 131%
Maintained
3 Periodic: Km of Paved Roads 655 786 7.5 4.5 60%
Maintained
4 Periodic: Km of Unpaved Roads 4,896 5,644 225 15 7%
Maintained
5 No. of Bridges maintained 324 46 324 0 0%
-Routine
No. of Bridges maintained
-Periodic

6.2.1.5 Golden Indicator 5: Expenditure On National Road Maintenance Relative to Overall


Budget

The overall budget allocated to UNRA for FY 2019/20 was UGX 4,289.07 Bn, out of which UGX
270 Bn was allocated to the Road Maintenance Programme. Road development still takes the
biggest share of the budget, at 91.4% compared to 88% in FY 2018/19 while road maintenance
takes a meagre 6.3% of the total budget compared to 9% in FY 2018/19. This imbalance is
resulting in unsustainable development of the network while the backlog maintenance is
growing and will result in higher replacement costs of the road asset in future.

Table 21: proportion of expenditure on road maintenance, relative to the overall budget
from FY 2014/15 to FY 2019/20

S/N FY Total Budget Road Development Road Recurrent


Maintenance
UGX (BN) UGX (BN) % UGX (BN) % UGX %
(BN)
1 2014/15 2,096.60 1,781.90 85 274.4 13 40.2 2
2 2015/16 2,083.10 1,732.60 83 267.9 13 82.5 4
3 2016/17 3,300.50 2,930.30 89 267.9 8 102.3 3
4 2017/18 3,903.80 3,504.30 90 267.9 7 131.5 3
5 2018/19 3,442.90 3,031.70 88 312.5 9 98.6 3
6 2019/20 4,289.10 3,920.60 91.4 270 6.3 98.45 2.3
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
55

Figure 5: A line graph showing the relationship between road development and road
maintenance

6.2.1.6 Golden Indicator 6: Compliance with Axle Load Regulations

This indicator measures progress in compliance with axle load limits on the national roads
network. The indicators are:

• % of vehicles with overloaded axles

• Number of vehicles weighed

Axle Load Control

The total number of vehicles weighed was 1,220,753 compared to 1,364,562 to last FY 2018/19
and 1,247,931 in FY 2017/18. The percentage of weighed vehicles that were overloaded
increased from 3.1% in FY 2018/19, to 3.8% in the FY 2019/20. The performance of axle load
control over the past 8 years is shown in the Table 22.

Table 22: Performance of Axle Load Control

Financial Year Total No. Vehicles % Of Vehicles Amount Paid In Fines


Weighed Overloaded.
(Ugx Million)

FY 2012/13 203,000 54 453.330


FY 2013/14 191,620 55 382.730
FY 2014/15 215,067 50 -
FY 2015/16 654,369 2.1 1,489.35
FY 2016/17 575,211 3.7 1,335.72
FY 2017/18 1,247,931 3.8 2,486.64
FY 2018/19 1,364,562 3.1 3,228.98
FY 2019/20 1,220,753 3.8 2,084.94
56 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

At the end of the FY 2019/20, 08 weigh stations were operational with an average availability
of 97.16%, compared to 98.03% registered in the previous FY 2018/19.

The status and location of each is summarised in the table 23.

Table 23:Location and Operational Status of Weighbridges

S/N Weigh Station Status % Availability FY % Availability FY


2018/19 2019/20
1 Magamaga Operational 95.70 96.02
2 Mbale Operational 97.00 99.18
3 Mubende Operational 99.30 99.64
4 Luwero Operational 99.20 99.55
5 Mbarara Operational 99.00 98.75
6 Lukaya Operational 98.10 99.66
7 Busitema Operational 96.40 97.80
8 Elegu Operational since 5th 99.30 91.20
March 2019
9 Malaba Operational since 17th 91.20
January 2020
Average Availability 98.00 97.16

The table 24 details the progress of works on the weighbridge operations projects.

Table 24: Progress of Weighbridge Operation Projects

S/N Project Status as of June 30, 2019


1 5 Multi-deck weighbridges • The civil works for four sites were completed; the
first shipment of 02 multi-decks is expected in July
2019.

2 Paving Mbarara Weigh Station Parking yard • Concrete for the single axle-weighing lane
completed, Earthwork for the approaches and the
parking yard at 90%. Mix design done.

3 3 High Speed Weigh In Motion Systems for • The contact for installation of the three systems
Magamaga, Luwero and Mbarara Weigh was signed towards the end of the 4th quarter. The
Stations. project expected to commence immediately with the
construction of the slip lanes.

4 Boarder post Weigh Stations at Mutukula, • The parking yards for the two stations were
Elegu and Malaba improved to the 2nd layer of gravel, Elegu station
started operations on 05 March 2019 while Mutukula
and Malaba still await calibration by UNBS

5 Centralized and Integrated Weighbridge Oper- • Three (3) indicators (Legal for trade type) that allow
ation and Monitoring System integration have been procured.
A prototype system is being developed and tests have
been carried out using the new indicators.

6 Procurement of three (03) enforcement vans Bidding notice was sent out in preparation for the
bidding exercise, which is due in July.

7 Procurement of Handheld GPS Trackers The evaluation report was submitted to Contracts
Committee for review.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
57

6.2.2 Other Achievements

I. Bridge Development
In the Last 5 Years, UNRA has constructed a total of 26 Bridges including six (6) and one
culvert box which were substantially completed during FY 2019/20, as shown in the table 29.

Table 25: Bridges substantially completed in the past three Financial Years FY 2017/18 – FY
2019/20

NO. OF
S/N PROJECT LOCATION DISTRICT
BRIDGES

Substantially Completed In FY 2019/20


1. Nsongi Along Kasisi – Rutete 1 Bunyangabu
– Kabata – Rwenkerizi -
Kyanga Road
2. Multi-Cell Box Connects Amuria, Otuke, 1 Amuria, Otuke,
Culvert at Opot Abim and Kotido. Abim and Kotido
3. Kagandi On Kagandi Natete - 1
Busanza - Mpaka Road
4. Dungulwa On Kinyamaseke – Kisin- 1
ga – Kyarumba - Kibirizi
Road
5. Enyau Along River Enyau on 1 Arua
Owaffa - Omugo Road
6. Odroo On Arua – Biliafe - Otre- 1 Arua
vu Road
7. Wariki Bridge On Logiri - Bondo Road 1

Substantially Completed In 2018/19


1. Source of the Nile A cable stayed bridge on 1
Bridge Kampala - Jinja Highway
in Jinja
2. Nalakasi Nalakasi – Arimoi - Kaa- 1 Kaabong
bong Road in Karamoja
Sub-region
3. Lopei Moroto - Kotido Road in 1 Moroto - Kotido
Karamoja Sub-region,
4. Kaabong Kaabong - Kotido Road in 1 Kaabong
Karamoja Sub-region
5. Ruzairwe Ruzairwe Bridge on 1 Kibaale
Kibaale – Kyebando -
Pacwa road
58 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

II. Ferry services


UNRA operates ten (10) ferry routes that link national roads at nine strategic locations where
the national roads cross major water bodies.

Table 26: Ferry crossing along the national road network

Route Year of Passenger


Ferry Crossing
No. Commissioning Capacity
1 Nakiwogo – Buwaya on L. Victoria 1987 120
2 Kiyindi – Kirongo (Buvuma) on L. Victoria 1987 120
3 Masindi Port – Kungu on L. Albert 1997 70
4 Mbulamuti - Nabuganyi on R. Nile 2010 120
5 Obongi – Sinyanya on Albert Nile 2010 120
6 Laropi – Umi on Albert Nile 2011 180
7.1 Kyoga 1: Zengebe-Namasale on L. Kyoga 2011 120
7.2 Kyoga 2: Zengebe-Namasale on L. Kyoga 2016 120
8 Agule – Okokorio on L. Bisina 2015 120
Albert Nile: Wanseko - Panyimur on L.
9 2017 300
Albert

Sigulu Ferry (Watega-Bumalenge on Lolwe


10 2020 300 
Island) on L. Victoria

Ferry Operations

The ten (10) ferries at Kiyindi, Mbulamuti, Masindi Port, Laropi, Obongi, Kyoga 1, Kyoga 2,
Nakiwogo and Bisina were operational and registered 95% adherence to scheduled trips. Ferry
utilization fell from 99% in the FY 2018/19 to 82 % in the FY 2019/20 due to the COVID-19
lockdown that put restrictions on private transport.

MV Sigulu Ferry that will connect Namayingo district to the Islands of Lolwe & Sigulu will
provide safe means of transport to the communities of Namayingo, Lolwe and Sigulu Islands.
Ferry construction was completed and handed over to UNRA. However, high water levels
submerged the temporary landing sites hence delay in actual operation

Table 27 summarizes the status of ferry operations


Table 27: Performance of UNRA Ferry Services

S/N Ferry Crossing Districts Linked By No. Passengers No. Passengers


The Ferry Carried Carried

(FY 2018/19) (FY 2019/20)

% Availability
FY2018/19
% Utilization
FY2018/19
% Availability
FY2019/20
% Utilization
FY2019/20
1 Masindi - Kungu Kiryandongo and 99 109 94 82 214,694 246,921
Apac
2 Bisina - Agule Katakwi and Kumi 100 101 100 84 334,578 226,615

3 Wanseko - Pany- Buliisa and Nebbi 86 92 99 97 237,073 241,926


imur
4 Nakiwogo - Buwaya Wakiso and Entebbe 98 98 100 75 499,926 335,160

5 Kiyindi - Buvuma Kiyindi – Buvuma 93 93 87 73 194,871 144,259

6 Mbulamuti Ferry Kayunga and Kamuli 98 88 90 56 792,976 437,383

7 Obongi - Sinyanya Moyo and Adjumani 100 102 94 93 629,409 597,061

8 Laropi - Umi Moyo and Adjumani 100 107 94 96 856,875 396,749

9 Namasale – Zenge- Amolatar and Naka- 99 97 95 80 352,970 248,966


be songala
10 Watega-Bumalenge Namayingo, Lolwe - - - -
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

and Sigulu
Total 97 99 95 82 4,113,372 2,875,040
59
60 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Table 28 details the status of on-going Ferry Services Projects

Table 28: Status of on-going Ferry Services Projects

S/N PROJECT NAME REMARKS

Ferry Construction is at 100% and handed over to UNRA.


1 Sigulu Ferry (Lake Victoria)
Temporary landing sites - High Water levels submerged
the temporary landing sites hence delay in actual operation

Construction of a new ferry


to replace the Old Kiyindi
2 Ferry - Construction of the ferry was completed 100%
Ferry (Using the former
Bukakata Frame)

Buyende – Kagwara - Ferry Equipment - The ferry construction contract has


3
Kaberamaido (BKK) Project been signed.

Ferry - Preparation of the ferry equipment (engines, pontoons


and passenger sheds) is ongoing in the ferry workshop at
Luweero. Pontoons at Rhino camp are undergoing retrieval
Amuru - Rhino Camp from the water before they are repaired and assembled.
4
Project
Ferry Landing sites - Construction of waiting shed, toilet,
guardhouse and staff quarters have been done up to roof
level.

Draft detailed engineering design submitted on 05 June


2019
5 Wanseko landing site Final Detailed Engineering Design accepted. Construction
of the jetty, dozing and spreading rock fill into the lake at
120m. Cofferdam works ongoing. Progress is at 58%.

Ferry - Keel laying of the vessel was carried out on 8th


February 2020. Construction of the hull is ongoing.
Kiyindi - Buvuma Ferry Progress is at 20%
6 landing and Facility
Development.
Ferry Permanent Landings - Draft Detailed Engineering
Design submitted for review.

III. Studies & Designs for Road Upgrading


ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
61

Table 29: Completed Studies and Designs for Road Projects

S/N Activity Key Outputs

1 Capacity Project Status


Improvement
projects Kampala - Jinja Expressway (KJE) Prequalification and
Preparation of RFPs
Kampala - Bombo Expressway Draft detailed design
Kampala Outer Beltway and Namugon- Final Detailed design
go Master Plan
Nakasero - Northern Bypass Express- Final RAP report
way
 Busega – Kyengera - Maya, Development of Concept
 Bwaise – Kawempe - Matugga and layouts
 Kalerwe - Gayaza - Manyangwa
roads
Kampala Flyover Construction and Detailed design for Lot 2:
Road Upgrading project (KFCRUP) Stage 1 and Stage 2 still
ongoing
In-house Design Projects

Detailed Detailed Engineering Design for Upgrading roads (27.5 Km)


Engineering
Upgrading of Tororo - Busia road 24 Km
Design for
Upgrading roads Access Road to the Kabaale International 3.5 Km
(27.5 Km) Airport
Detailed Completed Detailed Engineering Design of 135 Km of Town Roads for
Engineering Upgrading projects
Design of 135 Km
Iganga – Bulopa - Kamuli/Buwenge - 98 Km
of Town Roads
Kaliro
for Upgrading
projects Kakira – Namasiga - Bulongo 37 Km
Engineering Completed Preliminary Designs for Rehabilitation
designs for
Kampala Northern Bypass 21 Km
Rehabilitation
Projects - Design Kikorongo - Bwera - Mpondwe Including 53 Km
for 582.5 Km Kasese – Kilembe - Kyanjuki and Kasese
railway station (2 Km)
Kafu - Migeera 28 Km
Jokas Silver Springs 6.5 Km
Draft detailed engineering designs for the following Rehabilitation proj-
ects
Olwiyo - Packwach 62.5 Km
Karuma - Olwiyo 43.5 Km
Busunju - Kiboga 72 Km
Kiboga - Hoima 72 Km
Mbarara - Bwizibwera 19 Km
Nebbi - Alwii 33 Km
Mityana – Mubende Road 100 Km
Final Detailed design of Rehabilitation project roads
Kampala-Jinja Highway 72 Km
62 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Engineering Preparation of Engineering designs for Town roads


designs for Town
Rukungiri Nakalama - Tirinyi Town roads
roads
Town roads

Masaka Kagadi town roads


Town roads
Access Road Nebbi - Packwach town roads
to Entebbe
Hospital
Structural design Completed Structural design for Bridges
for Bridges
Laropi Bridge
Semiliki Bridge
Omposo, Agugura and Agora Bridges
1. 6 Engineering Final detailed Engineering design of 3No.
designs for
Weighbridge • Magamaga
Stations
• Luweero
• Mbarara
Design Projects under External Consultants
Feasibility study Final Detailed Engineering Design Report - 516 Km
and Detailed
Lot 1: Kanoni – Misigi - Mityana 39 Km
Engineering
Design of 913Km Lot 1: Bombo - Ndejje - Kalasa 19 Km
of roads Lot 2: Nabumali - Butaleja - Namutumba 90 Km
Lot 3: Hamurwa – Kerere – Kanungu – 143 Km
Kanyantorogo – Butogota - Buhoma/Ha-
mayanja – Ifasha - Ikumba Road
Lot 4: Katunguru - Ishasha 88 Km
Luku Kalangala - Mulabana 66 Km
Lot 6: Kisoro – Rubuguli - Muko/ Rugubu- 71 Km
li - Nteko
Draft Feasibility study and Preliminary Engineering Design Reports -
300Km
Lot 2: Mayuge – Mbaale – Nakivumbi – 95 Km
Bugiri – Namayingo - Lugaala
Lot 4: Muhanga – Kisiizi - Rwashamaire 50 Km
Karenga – Kapedo - Kaabong 73 Km
Kazo - Buremba – Kabagole - Kyeggegwa 82 Km
Road
Commencement
Lot 3: Kyenjojo (Kahunge) - Nyarukoma – 97 Km
Kigarale - Rwamwanja–Kiruhura

Environment and Social Safeguards

UNRA endeavours to identify and evaluate environmental and social risks, and impacts of
road/bridge and ferry projects in accordance with national laws and development partners’
requirements. Appropriate safeguards mechanisms are put in place to ensure that adverse
effects resulting from the project activities are eliminated or minimised.

The Green Right of Way (GROW) tree planting project was launched in March 2017 on the
Northern Bypass as part of the environmental restoration activities on all road reserves.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
63

Table 30: Road projects were Green Right of Way was done

Green Right of Way (GROW) Programme


FY 2018/19 FY 2019/20
Gayaza-Zirobwe Nakalama - Tirinyi - Mbale Road
Kampala-Entebbe Expressway Soroti - Katakwi - Akisim
Fort Portal - Bundibugyo
Fort Portal - Mubende
Jinja – Kamuli
Kabale - Katuna

In FY 2019/20, 10,300 trees were planted along various road corridors including; Nakalama
- Tirinyi - Mbale Road, Soroti - Katakwi - Akisim, Fort Portal -Bundibugyo, Fort Portal
- Mubende, Jinja – Kamuli, Kabale - Katuna among others. With 23 nurseries across the
country, UNRA intends to plant over 10 million trees on the national network over the next
2 years. In addition, treebanks have been established in 19 UNRA Stations with 139,058 trees.

Building The Local Construction Capacity

In FY 2019/20, Contracts worth UGX 306.530 Bn were awarded to local or resident providers
in accordance with the PPDA Guidelines for Reservation schemes for promoting local content.
This represents 25% by value of the contracts signed in the FY, down from 28% in FY 2018/19
but higher than the 24% in the FY 2017/18. However, the entire 25% was only for reservation
by threshold and there was no service provided under the subcontracting component. There
was a reduction in the total amount awarded under the reservation scheme from 737 Bn to
306.5 Bn in FY 2018/19 however, this was also seen in the overall amount of signed contracts
from 2.2 Tr to 1.2 Tr.

This breakdown of the contracts signed and includes reservation by threshold and sub-
contracting is shown in the Table 31:

Table 31: Breakdown of contracts signed in FY 2019/20 (Bn UGX)

S/N Category Reservations For Local & National


To Foreign

Providers
Contracts
Awarded
Contract

Signed

By Threshold By 30% Sub-


Firms

contracting

1 Works 163.079 - 774.597 937.677


2 Consulting Services 125.213 - 16.765 141.978
3 Supplies & Ncons 3.867 - 64.972 68.840
4 Addenda 1.145 - 63.018 64.164
5 Delegated 13.223 - - 13.224
Sub-Total 306.530 - 919,352 1,225.883
TOTAL AMOUNTS 306.530 919,352 1,225.883

% OF AWARDS 25% 75% 54.17

Professional Qualification of Technical Staff

Status of Registration of Engineers


64 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

The end of FY 2019/20 saw a number of fully registered Engineers increase from 75 to 88
representing a 17.3% increase. Nineteen (19) engineers are currently at corporate membership
stage while thirty (30) are preparing for corporate membership while sixty-seven (67)
graduates are eligible for registration with ERB but are not yet registered.

Table 32: Status of Registration of Engineers

6.3 CHALLENGES FACED DURING THE FY 2019/20

i) The Covid-19 pandemic greatly affected UNRA’s ability to achieve the set targets. Several
of UNRA’s activities such as road construction were affected by the lockdown and
partial lockdown. Activities like land acquisition were halted while projects continued
to be implemented under very strict Standard Operating Procedures (SoPs). The result
of this has been a delay in progress with some contractors giving the notice to claim for
extension of time or cost.
ii) The heavy and long rainy season resulted in:
o the slow progress of the construction projects;
o Several cut-offs which required emergency interventions to reinstate the road
sections;
o The rapid deterioration of the condition of the roads, reducing the service level and
increasing the urgent need for periodic maintenance and rehabilitation of some
road sections;

iii) The financing for the road development programme remains constrained and not in
harmony with the five-year plan. This distorted effort to prepare and implement the
NDPII as was envisaged.
iv) A rigid Public Finance Management Act which does not allow flexibility in utilisation of
funds to drive the development programme.
v) The road maintenance budget remains lower than the required, which makes providing
the desired level of service and response to emergencies which result in network cut-offs
a challenge and reduced ferry services.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
65

vi) UNRA’s operational budget has remained inadequate and the same over the years, despite
the increase in the development and maintenance programme, the increase in operation
and administrative costs and the increase in staff numbers. This has constrained the
ability of the organisation to effectively supervise its programmes.
vii) Procurement delays occasioned on the programme by the external stakeholders.

6.4 FUTURE PLANS

Roads and Bridges Development

During FY 2020/21, UNRA will construct 400 Km-equivalent for road upgrading projects
and substantially complete twelve road projects adding 383 Km to the stock of the national
road network.

Table 33: Upgrading projects to be substantially completed in FY 2020/21

SN PROJECT LENGTH (KM)

1 Bulima-Kabwoya (Town Roads) 3


2 Bumbobi-Lwakhakha (Town Roads) 5.8
3 Kyenjojo-Kabwoya (Town Roads ) 11
4 Tirinyi Pallisa Kumi Lot 1 67
5 Pallisa Kamonkoli Lot 2 44
6 Masaka-Bukakata 41
7 Olwiyo-Gulu Town Roads 10
8 Soroti-Akisim (Town Roads) 26.2
9 Mubende-Kakumiro-Kagadi (Town Roads) 24
10 Mpigi Town Roads 20
11 Mbarara Town Roads 20
12 Hoima Butiaba Wanseko 111
TOTAL 383

UNRA will also commence upgrading of 19 road projects with a total length of 963.4 Km. Ta-
ble 35 shows the upgrading of road projects to commence in 2020/21.

Road Development-Road Rehabilitation

During the 20/21 fiscal year, UNRA shall construct 252.5 KM-Equiv of road rehabilitation
projects and substantially complete three (3) road rehabilitation projects totalling 166 km.
Three road rehabilitation projects totalling to 134.7 Km will commence in 2020/21.
66 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Table 34: Rehabilitation projects to be completed in 2020/21

S/N Project Name Length (KM) % Progress June 2020


1 Nakalama - Tirinyi - Mbale 102 85.5
2 Nakawa-Seeta 9 75
3 Fortportal –Hima 55 85.6
Total 166  

Table 35: Rehabilitation projects to commence in 2020/21

S/N Project Name Length (Km) Financing


1 Mityana-Mubende (including 14km of 86 GOU
town roads
2 Nebbi-Alwii (including 4.3km of town 33 GOU
roads)
3 Kampala (Banda) - Mukono 15.7 GOU
Total 134.7

Bridges Development
UNRA will continue construction on 56 bridges and structures of which, 15 will be completed
in FY 2020/21.

Table 36: Bridge development projects to commence in FY 2020/21

S/N Project Location No. of Bridges District

1 Ayugi Bridge Atiak-Adjumani – Moyo – 1 Amuru


Yumbe - Manibe Road
2 Ceri and Opio Bridges Pakele - Pabbo Road 2 Amuru
3 Adidi Bridge Pakele - Pabbo Road 1 Adjumani
4 Kampala – Mubende - Fort 1 Kasese
Portal - Uganda/DRC border
Mpondwe Bridge
Road
5 Mpanga-6 Bridge Kamwenge - Kabambiro 1 Kamwenge
Road
6 Ajeleik Amuria – Adwa - Usuk - 1 Amuria
Katakwi Road
7 Aji Bridge Ullepi - Offaka Road 1 Madi-Okollo
8 Ora-1 and Awa Pakwach – Inde - Ocoko Road 2 Madi-Okollo
9 Olemika Bridge Pakwach – Inde - Ocoko Road 1 Arua
10 Awoo Bridge Bobi - Ayer Road 1 Omoro
11 Nariamabune Bridge Kaabong - Kapedo Road 1 Kaabong
12 Chololo Bridge Chosan - Amudat Road 1 Nakapiripirit
13 Isimba Public Bridge & Ac- 1 Kayunga
cess Roads
  Total 15  
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
67

Land Acquisition for FY 2020/21


• UNRA plans to acquire 2,216 hectares during 2020/21.

Road Maintenance
UNRA will ensure that the national roads network in fair to good condition will be kept at
above 85 % for paved roads and 70% for unpaved roads by implementing the following main-
tenance interventions.

Table 37: Planned road maintenance interventions for FY 2020/21

S/N Planned Intervention Target (Km)


1 Routine: Km of Paved Roads Maintained 6,413
2 Routine: Km of Unpaved Roads Maintained 25,995
3 Periodic: Km of Paved Roads Maintained 14.5
4 Periodic: Km of Unpaved Roads Maintained 531

Axle Load Control


During FY 2020/21, UNRA will complete the installation of five (5) multi-deck weighbridges
at Mbale, Mubende, Kamdini, Kamengo and Magamaga, as well as, three (3) high speed weigh
in motion systems at Magamaga, Luwero and Mbarara.
Ferry Services
In FY 2020/21, UNRA will operate twelve (12) ferries and ensure that the level of compliance
to published ferry schedules is at least 90%.
68 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Terminal operations center – UCAA


ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
69

7.0 PERFORMANCE OF UGANDA CIVIL AVIATION AUTHORITY

7.1 FINANCIAL PERFORMANCE FOR THE FY2018/19

Total recurrent expenditure amounted to UGX145bn compared to a budget of UGX198.9bn


reflecting a favourable variance of UGX53.9bn. Capital expenditure amounted to UGX 39.7bn.
Table 38 shows expenditure by directorate.

DRAFT FINANCIAL PERFORMANCE FOR THE FY2019/20

Table 38: Financial Performance for The FY2019/20

No Department Approved Budget Expenditure


(‘000 Shs)
(‘000 Shs)
1 Directorate of Human Resource and
Administration
- Employment
- Administration 103,857,776 86,795,282
24,846,491 19,639,452
2 Directorate of Air Navigation Services 13,235,453 5,215,538
3 Directorate of Airports and Aviation 21,731,266 13,020,464
Security
4 Directorate of Finance 10,986,226 1,238,953
5 Directorate of Safety, Security and 3,954,604 3,039,092
Economic Regulation
6 Corporate Office 20,361,899 16,051,569
7 Capital Projects 61,677,293 39,700,988
Total 260,651,008 184,701,338

7.3 PHYSICAL PERFORMANCE

Air traffic performance was promising to beat the target as up to the month of February
2020. All this was brought to near zero when the airport was shut down by government as a
way to contain the spread of Covid 19. Consequently, the performance of air passenger traffic
was below target averaging just above 70% of the projected levels. The drop in international
passenger traffic can be seen as of March 2020. Import cargo however, performed above
projection because cargo planes remained operational despite lockdown. Tables 41 show the
traffic performance at Entebbe International Airport as well as UCAA managed regional
airports.
70 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Table 39: Traffic performance at Entebbe International Airport

No. Traffic Item Actual Target Actual Target Actual Performance


2017/18 2018/19 2018/19 2019/2020 2019/2020 Against Target
(%)
1 International 1582670 1,610,200 1728779 1858437 1355772 73.0
Passengers
(Nos)
  EmbInt 795302 810,000 885449 951857 699859 73.5
  Dis Int 787368 800,200 843330 906580 655913 72.4
2 Transit 122334 122,400 192894 207361 133659 64.5
Passengers
(Nos)
3 Domestic 22301 17,061 27600 28980 20281 70.0
Passengers
(Nos)
  Emb Dom 10958 11,050 13235 13897 9339 67.2
  Dis Dom 11343 11,900 14365 15083 10942 72.5
4 22499 23,200 20788 21412 21985 102.7
Imports (Tonnes)
5 Exports 45032 41,715 41339 42579 37829 88.8
(Tonnes)
6 Commercial 29,782 29,900 32735 33717 28327 84.0
Aircraft
movements
(Nos)
  Non 10,031 11,020 8310 8559 6996 81.7
Commercial
8 Overflights 15,281 17,436 15,730 16,988 12,363 72.8

7.3.1 TEN YEAR TRAFFIC PERFORMANCE AT ENTEBBE INTERNATIONAL AIRPORT

Table 40: Traffic Performance at Entebbe International Airport

YEAR 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20

JUL 87299 100068 107083 114101 122060 115282 124902 135253 145020 158508 166980

AUG 88340 100582 97476 109194 120316 123545 130628 136344 140743 153325 163344

SEP 77459 81777 89772 107533 113905 105248 113664 119658 128215 148382 155664

OCT 87319 92298 99558 108856 112864 108821 110935 117015 122065 138873 148028

NOV 75788 87878 95034 101924 112439 114863 118936 116803 121116 135841 152296

DEC 84306 92997 103779 110900 122685 117951 124528 136615 147590 157382 179323

JAN 82086 86657 107929 113347 114595 112465 115655 125833 135975 147346 158615

FEB 70932 69904 89415 97711 101757 99195 89170 107174 120155 128624 144334

MAR 76967 79098 97203 103708 104770 112460 106063 115277 130104 138461 83163

APR 72640 83452 95838 100882 101596 102431 104499 117551 127969 136334 987

MAY 82405 83379 93189 109478 108169 109138 112072 120153 129596 140108 1146

JUN 82807 90417 102452 114568 115902 115862 112432 120500 134122 145595 1892

TOTAL 968348 1048507 1178728 1292202 1351058 1337261 1363484 1468176 1582670 1728779 1355772

S
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
71

7.3.2 TEN YEAR PASSENGER TRAFFIC PERFORMANCE AT UPCOUNTRY AIRPORTS

Table 41: Passenger traffic performance at Upcountry airports

AIRPORT 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
ARUA 1845 1380 1601 2226 2305 1336 1464 1804 2298 1994
GULU 301 235 297 210 398 428 390 226 476 313
KASESE 51 75 94 442 544 520 692 800 1445 1412
PAKUBA 141 155 200 1202 464 210 266 298 440 356
SOROTI 380 404 497 3883 768 4804 410 752 268 200
MOROTO 64 94 111 364 336 366 400 422 512 491
MBARARA 4 3 2 160 80 182 150 102 98 122
MASINDI 190 183 168 12 14 2 0 0 0 0
JINJA 250 397 378 187 202 138 168 294 844 625
LIRA 62 456 708 114 128 58 42 100 86 100
KISORO 0 12 31 488 566 488 634 774 1082 1192
KIDEPO 221 206 238 365 444 314 330 260 465 390
TORORO 204 246 291 90 56 44 102 170 105 74
TOTAL 3713 3846 4616 9743 6305 8890 5048 6002 8119 7269

Figure 6.. Passenger traffic performance at Upcountry airports


72 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

7.3.3 PROGRESS OF MAJOR UCAA PROJECTS

(a) Progress of CAA Major Projects at Entebbe International Airport By June 2020

Table 42: Progress of CAA Major Projects at Entebbe International Airport By June 2020

No. Project Name / Activity Progress (June 2020) Remarks


1 Expansion and Upgrade Activity Progress UCAA is making
of Entebbe International regular engagements
Airport FY FY with MoFPED and
2019/2020 MoWT to ensure that
2018/19
implementation of the
Cargo Apron 85% 98% project is on schedule.
Cargo Terminal 77% 96%
Apron 1 Expansion 90% 100%
Service road 83% 96%
Works on Runway 85% 98%
12/30
Works on Runway n/a 94%
17/35 and associated
taxiways
Apron 1 rehabilitation n/a 34%
OVERALL PROGRESS 67.5% 73%

(b)Progress Other Projects at Entebbe International Airport as at the End of June2020

Table 43: Progress Other Projects at Entebbe International Airport as at the End of
June2020

SN Project name / TARGET Progress at 30th Remark


activity June ,2020
2 Improvement of 60% 89% Still on going.
departures at EIA
3 Search Park at EIA 80% 100% Construction of shelter and road lanes
for infrastructure as per phase I and
in accordance to the court order is
complete.
4) Fuel Hydrant line • Cargo Apron fuel 90% • Cargo Apron fuel line completed
and Fuel Farm line completed and and pressure tested
pressure test- • Construction of the Foundation for
ed(100%) the fuel tanks ongoing is still on
Construction of the going
Foundation for the
fuel tanks ongoing
5) Water Tanks Still on going
• Concrete works 90%
for water tanks
at 90%
• Fire water
tanks progress 90%
at 85%
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
73

6) Acquisition of This project commenced in March


electronic Terrain 2020 and is estimated to last for 9
and Obstacle Data months
(eTOD) Area 1 for
the entire terri-
tory of Uganda
and(eTOD) Area 2
for Entebbe Inter-
national Airport
7) Installation of Contract awarded 100% Project completed
CCTV cameras in
PTB, Cargo, Car
parking, VVIP
Terminal and
CAA Headquar-
ters

(c) Status of Progress of UCAA Projects at Upcountry Airport as at the end of June, 2020

Table 44: Status of Progress of UCAA Pr ojects at Upcountry Airport as at the end of June,
2020

SN PROJECT TITLE LOCATION COST Status /Progress in Status /Progress in


UGX(000) FY2018/19 FY2019/20
1 Construction of the Arua 4,613,676.938 85% 100%
Apron at Arua Airport
phase III
2 Perimeter fencing of Tororo 800,209.389 75% 98%
Tororo Airfield
3 Perimeter fencing of Gulu 544,412.883 30% 75%
Gulu Airport (Phase II).
Fencing of the recently
acquired land.
4 Perimeter fencing of Arua 687,928.079 15% 55%
Arua Airport phase 1
5 Airfield Ground light- Soroti $758,640.5 Contract signed. Lights delivered instal-
ing system for Soroti lation ongoing. However
progress affected by the
COVID-19 lockdown
6 Construction of land Soroti 305,316.258 Contract signed and 95%
side airside demarca- contractor mobiliz-
tions fence at Soroti ing to commence
Airport work.
7 Construction of Fire Soroti and 269,883.936 Contract signed and 100%
truck shed for newly Kisoro contractor mobiliz-
Acquired fire trucks at ing to commence
Soroti and Kisoro work.
8 Relocation of Lira Lira 3,100,000 Cadastral, Consultant submitted
Airport to new site at topographic and inception report.
Anai geotechnical survey Consultative meeting
of the new sit: held with the district
Survey works on leaders and then with the
going. Construction encroachers on the land at
of perimeter, Anai. The community was
runway, Apron and hostile and demanded for
terminal facility: compensation. However
Refining designs and further engagement was
BOQs pending result affected by the COVID-19
of the survey. lockdown.
74 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

09 Construction of staff Arua and 645,378.0 CC approved meth- Bids evaluated and
quarters at Arua and Moroto ods of procurement. progress affected by the
Moroto COVID-19 lockdown
10 Repairs of the runways Kisoro 4,880,000 Forwarded to Con- Procurement initiated but
at KISORO Airfield tracts Committee for slowed down due to inad-
approval of methods equate funding.
of procurement.

7.3.3 Other Achievements

The Uganda Civil Aviation Authority was also able to achieve the following:

a) On the Certification of Entebbe International Airport; the Evaluation of EIA


Aerodrome Manual was completed and Inspection and verification was expected to
commence on 15/09/2020 while certification is expected by end of March 2021.
b) Concerning the Certification of EACAA; The ATO certificate was issued on May 18,
2019 for 6 months. An extension for a further 6 months was granted up to 18/08/2020.
A team of inspectors will visit the academy again when the schools and institutions
are opened.
c) On the Revival of the National Airline; Certification of Uganda Airlines was completed
and the Airline commenced operations.
d) As regards, to Implementation of CAP for ICAO USOAP / ICVM; Technical input
regarding Civil Aviation Regulations was completed and submitted to MoJCA for
review and promulgation and the process is still ongoing and being handled with
MoJCA.
e) Regarding the Implementation of CAP for ICAO USAP; Development of the Corrective
Action Plan was done and submitted to ICAO and it was accepted. Corrective actions
such as amendment of the CAA act have been completed. Implementation of the CAP
is underway.
f) ICAO Council President Certificate in Aviation Security was awarded to UCAA during
the 40th Session of the ICAO Assembly in Montreal.
g) Government Agency of the year “Going Global” award to UCAA from the International
Trade Council in the Aviation Category, which was awarded in Chicago, USA in
October 2019.
h) Successfully hosted the ICAO Flag at the Source of the Nile, Jinja in, 2019 to
commemorate the 75th Anniversary for ICAO.
i) In conjunction with Uganda Aeronautical Information Services Officers’ Association
(UGAISOA), successfully organized an Aviation Run in Entebbe on Sunday November
10th 2019 as part of efforts to give back to Entebbe Regional Referral Hospital’s
Emergency Care Unit, in commemoration of ICAO’s 75th Anniversary.
j) Successful ISO 9001:2015 Quality Management Systems (QMS) Surveillance Audit
of Uganda Civil Aviation Authority, conducted in November 2019, where the QMS
Certification was retained.
k) Facilitated and supported ICAO USAP CMA, where Uganda scored 80.81%.
l) Completed amendment of the Civil Aviation (Amendment) Act, 2019.
m) Participated in Electronic Government Procurement (e-GP) activities and UCAA is a
pilot Entity on the implementation of the e-GP.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
75

7.4 CHALLENGES / CONSTRAINTS AND MEASURES

UCAA faced the following challenges / constraints during the FY;

• Increasing Government Debt most especially due to nonpayment of the UN


debt by
Government as promised.
• Outbreak of Covid-19: all international passenger flights in and out of Uganda were
suspended. This has adversely affected the authority’s revenue.

• The infrastructure is inadequate to cope with the current COVID-19 pandemic port
health requirements
• Inadequate funding for development of infrastructure in order to position EIA and
other priority airports to attract more regional and international airlines into the
country.
• Land requirements for future developments
• Lack of funding to commence the plan for operationalization of Hoima International
Airport, activities such as recruitment and training of technical staff and technical
studies-ETOD need have commenced.
• The process of promulgating of Regulations takes longer time that is not in
synchronization with the latest amendments of ICAO Standards i.e. ICAO standards
are amended annually
• Implementation of the established independent Aircraft Accident
Investigation (AIG) Unit at Ministry of Works and Transport, is taking
long
• Lack of an Appeals Tribunal for Civil Aviation negatively impacts on the resolution
of aviation safety concerns
• Lack of a Policy for Attraction and Retention of Aviation Inspectors
• Training of Inspectors is highly specialized and costly. COVID-19 has
affected the fast-tracking of training of inspectors
• Essential Tools and office space for Inspectors
• Slow responsiveness of the Industry on Certification and Surveillance
Requirements
76 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Export train with wheat brand

Re-sleeping exercise done at Sezibwa section


ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
77

8.0 PERFORMANCE OF UGANDA RAILWAY CORPORATION

8.1. FINANCIAL PERFORMANCE

The total approved budget for 2019/2020 was Ugx.84.9Billion, out of which Ugx.9 Billion was
expected from the Government and Ugx.75.9 Billion was to be generated internally. However,
due to the low achievement of the budget for the FY 2018/19, the Board of Directors of the
Corporation undertook to revise the budget and was approved by the Ministry of Works and
Transport. The revised budget was Ugx.77.4Bn, out of which Ugx.8.5Bn was expected from
the Government and Ugx 42.3Bn was to be generated internally.
Table 45: URC Financial performance for the FY2019/2020
78

GOU FUNDING PERFORMANCE FINANCIAL YEAR 2019-20


  Actual-Q1 Actual-Q2 Actual-Q3 QUARTER 4 %age var. CUMMULATIVE %age var. REASONS FOR
VARIANCE
July-Sept.19 Oct.19- Jan.20-
Dec.19 Mar.20
FY2019/20

Ugx.bn Ugx.bn Ugx.bn Budget Actual Budget Actual


      Apr.20- Apr.20-Jun.20 Q1-Q4 Q1-Q4
Jun.20

      Ugx.bn Ugx.bn Ugx.bn Ugx.bn

Total Income 2.14 1.5 2.12 2.13 2.74 29% 8.50 8.50 0%
ANNUAL SECTOR PERFORMANCE REPORT

GoU approved 2.14 1.5 2.12 2.13 2.74 29% 8.50 8.50 0% GoU indicated low re-
release source envelop of GoU
Total expenditure 4.15 1.34 1.08 3.08 2.59 16% 9.46 9.15 -3%  
Wage               -    
Non-wage 0.23   0.21 0.21 0.21 0% 0.96 0.65 -32% Funds from prior year
balances
Development 3.92 1.34 0.87 2.88 2.38 17% 8.50 8.50 0%  

OPERATIONAL PERFORMANCE (INTERNAL REVENUE SOURCES)


Total income 4.82 4.23 8.16 16.78 11.02 -34% 42.32 28.24 -33%  
Freight 4.27 3.43 3.57 10.23 1.57 -85% 32.73 12.83 -61% Poor state of assets, Covid
business effects
Other 0.56 0.80 2.66 6.55 3.06 -53% 9.59 7.08 -26% Storage and demurrage
charges to a defaulting
customer
Exceptional Income     1.93   6.40   - 8.33 100% Funds allocated for capaci-
ty building
Total Expenditure 6.55 7.39 8.65 12.06 6.51 46% 42.36 29.10 31%  
Wage 2.73 2.95 2.82 2.77 3.73 -35% 11.07 12.23 -10%  
Non-wage 3.82 4.44 3.89 9.29 2.78 70% 31.29 14.95 52% Low level of operations
OPERATIONAL PERFORMANCE (INTERNAL REVENUE SOURCES)
Exceptional expen-     1.93       - 1.93 -100% Capacity building expens-
diture es not in budget
EBITDA 1.73 3.16 0.49 4.73 4.51 -5% 0.04 0.86    
Depreciation & 22.48 1.43 10.52 10.52 10.52 0% 42.10 42.10 0%  
Arm
Finance charges 0.03 0.01 0.00 0.28 0.47 -69% 0.38 0.51 -35%  
EBT 24.23 1.74 11.02 6.07 6.48 -7% 42.52 43.47 -2%  
Tax provn 0.10 0.11 0.01 0.12 0.29 -153% 0.63 0.51 19%  
EAT 24.33 1.85 11.02 6.19 6.77 -9% 43.15 43.98 -2%  
Add exceptional - -   - 6.40   - 6.40    
income
Add Non-recurrent 2.14 1.50 2.12 2.13 2.74     8.50    
income
Grand total surplus 22.19 0.35 8.90 4.06 2.37 0.09 43.15 29.08    
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
79
80 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

The Corporation generated a total of Ugx.43.15bn in income, (Ugx,28.24bn in operational


income, 8.5bn in non-operational income(from Government);and Ugx.6.4bn in exceptional
income).This performance was 17% above that of the FY 2018/19.

The Corporation continued to raise revenue from various sources including freight, rent and
charges. Income from freight operations was Ugx.12.83bn a 1% drop from that of the last FY
(which was Ugx.12.96bn). COVID-19 very much affected this performance as there was little
or no economic activity in the last quarter of the year under review. Other sources included;
Assets hire contributing 0.23bn, Rent 3.39bn, Passenger services 0.54bn among others. See
figure 7.

Funding of URC

Figure 4: Summary of URC financial performance over years

Figure 5: URC internal income sources


ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
81

Exceptional income included debtors’ balances brought forward from the previous FY, cash at
hand and cash at bank. Also, revenue was generated from other fees which included cranage,
handling, port and docking fees, gate fees and hire of the dry dock. Further, there was income
generated from sale of mechanical and other scrap assets in the year which constituted the
miscellaneous receipts.

Table 46:Summary of financial performance

(Bn)UGX
Income 2017/18 2018/19 2019/20
Cargo Freight Income 5.24 12.96 12.83
Passenger Freight Income 0.40 0.54 0.544
Other Income 4.81 1.96 14.87
Total EBITDA -4.13 6.36 1.07
GoU funding 21.07 9.78 8.5

EBITDA- Earnings Before Interest Tax, Depreciation & Amortization. Other income includes
Asset hire, other fees, rent, miscellaneous receipts and exceptional income.

Figure 6: Trend in income performance

Northern route continued to generate more revenue followed by the southern route and
then local haulage. Revenues from the southern route dropped significantly towards the end
of the third quarter and the rest of the fourth quarter because both ships (Kaawa and Umoja)
were on dry dock.

8.3 PHYSICAL PERFORMANCE

8.3.1 Performance of the Golden Indicators

URC contributes to five golden indicators, i.e. Rail Freight Volume, Rail Modal share at
Malaba, Busia and Port Bell Border Points, Rail Modal Share on Lake Victoria Ferries, Rail
Efficiency and Wagon Utilization. The performance of the Corporation against the golden
indicators are shown in Table 8.2
Table 47: The Golden Indicators for URC
82

No Jun- 17 Actual Target


Jun -20 Jun- 20 % performance
against target
Description Jun-15 Jun-16 Jun-18 Jun -19
FY2019/20

9 Rail Freight Volume


Total freight carried (million- tonne-km)
171.1 165.7 118.9 7.54 39 40.172 7.5 535.63
10 Rail Modal share at Malaba, Busia and Port Bell Border Points
ANNUAL SECTOR PERFORMANCE REPORT

145.02 500 29%


Total Freight crossing the three borders (1000 8,325 5,162.70 5107.1 179
tonnes)
1.74 3 58%
Freight that crosses the three borders by rail (% of 6 8.3 6.5 3.5 1.5
total)
11 Rail Modal Share on Lake

Victoria Ferries
Freight transported on ferries by rail, registered at
Port Bell border post (% of total).
12 Rail Efficiency
Locomotive productivity(km/loco/day) 74 150 49.33

147 69 78 148 472.95

13 Wagon Utilization
Wagon Transit time (days) 25 12 208

8 13 12 7 19
Wagon Turn-round time (days) Wagon Turn- 76 28 271.4
round time (days)
28 25 34 28 31
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
83

In FY2019/20, the corporation railed a total of 169,255.09 tones. This tonnage railed consisted
of 68% as imports, 18% as exports and 14% as local haulage. Compared to last financial
year, there was a 14.19% decrease in performance and this was attributed to the COVID-19
pandemic effects and the wash aways in Kenya that affected trains movement.

A total of 2,263 trains were run during the financial year 2019/2020. During the financial
year, a total of one hundred twenty-nine (129) incidents for both mainline plus yards and
sidings were recorded. Out of the 129 only nineteen (19) were mainline accidents and one
hundred ten (110) were other incidents. Of the mainline accidents, three (3) were capsizements,
ten (10) derailments and six (6) level crossing accidents. These accidents cost the corporation
clearance times and resulted in delayed cargo delivery causing customer frustrations and
loss of business to other means of transport, mainly road.

During the financial year 2019/2020 Net Ton kilometre (NTK) achieved was 40,172,632.84
whereas Gross Ton kilometre (GTK) was 77,539,394. This represented a 52% pay load
performance, an improvement from 45% registered in the previous financial year.

The Corporation insured its assets against loss or damage and both the client’s cargo and its
own assets. The required operational licences for the ship (MV Kaawa) were also acquired
during the year. These included the Seaworthiness Certificate, Class Certificate and the
Manning Certificate.

Table 48: Performance against targets

Performance indicator Target Actual %age of Implications/Notes


the target
Gross Ton Kilometer 100,000,000 77,539,394 78 Target not achieved due to
COVID effect on the business
world. This was worsened by
wash-aways in Kenya.
Net Ton Kilometer 60,000,000 40,172, 67 This was attributed to less
export cargo due to shortage
633 of assets required especially
flat beds since most export
customers use containers.
Metric Tons 347,127 169,255 48.76 There is potential to improve
if the track is rehabilitated
and well maintained and
the assets like wagons,
locomotive are increased on.
Passengers carried 558,000 488,951 88 There were no operations for
4 months due to COVID-19.
However, due to the high
demand for the service, there
is need to increase on the
number of coaches from five,
and open up other routes to
Kyengera and beyond.
Number of trains run 3,000 2,263 75 Low volumes railed
Trains speed (Kmph) 35 20 57 The track needs more
rehabilitation and routine
spot maintenance.
84 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Delivery days 10 25 250 These were greatly affected


by the different wash aways
especially one at Kijabe.
Kenya that had the line closed
for almost 60 days.
Wagon turn-around 30 76 253 These were greatly affected
by the different wash aways
especially one at Kijabe.
Kenya that had the line closed
for almost 60 days.
Accidents

Derailments 26 10 38 Line needs more


rehabilitation to reduce
on time lost clearing these
derailments.

Capsizements 6 3 50 Rehabilitation and


improvements on the line
which will help reduce on
the number of capsizements
thus improve on rail
customer confidence.

NOTE:

1. For gross tonne kilometre, net tone kilometre, metric tonnes, passengers carried, Number
of trains and trains speed, higher figures indicate a good performance.

2. For delivery days, wagon Turn around, and accidents, a smaller figure indicates a good
performance.

8.2.2 Performance on projects

Table 49: Ongoing projects and respective status

SN  Project Contract Details Status

1 Contract for rehabilitation Contract amount: Completed


of Jinja Pier line (3.2 Km)
Ugx. 488,958,960
Delivery Period: 2 months
Delivery date: 4th May,
2020

2 Rehabilitation of Tororo Contract amount: Preliminary assessment of track


Gulu Railway line (375 Km) condition, design review and
Euro. 39,337,756 contractor mobilization ongoing
Delivery Period: 48 Physical progress is at 2.1% and
months time elapse at 16.6%
Intended Delivery date: NEC subcontracted to clear the
line (bush clearing) which was
4 Feb, 2024
th
completed by 16th July 2020.
Work progress affected by nation-
al COVID-19 travel restrictions.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
85

3 Construction of Gulu ICD Contract amount: Site handover meeting held in


January 2020.
USD. 12 Mn
Works commenced though it was
Delivery Period: 18 months affected by national COVID-19
travel restrictions.
Intended Delivery date:
Actual progress is 16% against a
12th September, 2021
planned 28% progress
4 Contract for minor Contract amount: Ugx. Substantial completion achieved.
civil works for the 177,354,000
reinstatement and
modification of the roof at Delivery Period: 3 months
Mukono ICD
Delivery date: 10th January,
2020

5 Technical Assistance and Still on going


Capacity Building project
A strategy report on
encroachment to be submitted by
the supplier before end of August
2020

6 Passenger Services Expan- Contract amount: 300,000 Still ongoing – 99% complete
sion Euros
Report submitted and currently
under review.
URC to engage government and
development partners.

Feasibility report submitted and its


To cater for the need under review
currently exhibited by the
public.(Ridership exceeded
budget by 38%)
86 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Table 50: Performance against set outputs for the FY

Key Planned output Annual Annual Budget Actual output Status


GoU - Board spent of
approved adjusted June 2020
budget budget

(UGX’Bn) (UGX’Bn) (UGX’Bn)

CIVIL ENGINEERING DEPARTMENT

1 Improve permanent
way to support
business
7.85 6.56 0.546
• Install 1,088 No pillars installed Activity
reinforced rescheduled to
concrete the new FY
pillars

3.26
• Routine 2.38
mainte- 250km of track
routinely maintained; Maintenance
nance of works
250km of weeding, packing,
realignment and continue to be
railway trac carried out on
opening drains -
Ugx.0.23M the track

2.6 km of track
partially renewed (re-
sleepered) Ugx.456M.
Very bad sections of More sections
the line between Jinja to be renewed
and Busembatia and
between Kawolo and
Jinja were fitted with
new sleepers.

2 0.150 0.795 - Jinja pier All the


line (1.9km) planned re-
Improve port constructed pairs done and
operations and (1.3km) completed.
repaired-Ugx
.386M;
Portbell ware house
repaired-Ugx.5.6M
3 Renovate/repair 0.901 0.94 - dpf stores
some URC properties repaired-Ugx
and develop a fully- .67M
fledged property - Kampala
management goods shed
function repaired-Ugx
.103M
Mukono ICD Roof
repaired-Ugx.249M
4 Improve direct & 0.649 8.12 0.449 -Property expenses Settled fully
indirect support undertaken
services -Ugx.342M
-Rates paid -Ugx.107M
MECHANICAL ENGINEERNG SERVICES
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
87

5 Increase motive pow-


er & handling capac-
ity
• Leasing of 3 1.46 2.1
locomotive 4.24 No loco was leased Plans to lease
at Us$900 aborted,
per loco per 18.87 instead 4 new
day 1.1 locos will be
4.6 Spares for purchased in
• Rehabilitate 2.89 rehabilitation of locos
2 locos the next FY
purchased -Ugx.477M
• Rehabilitate
42 railway Locomotive & wagon
wagons tyres purchased Some spares
-Ugx.496M for loco
rehabilitation
Locomotive batteries, were
spares & repairs delivered and
procured-Ugx.2.8bn rehabilitation
works were
Rehabilitation of
started.
wagons undertaken
-76 in number- 5 wagons
Ugx.464M were repaired
and 76 were
Fuel & lubes for cargo
modified.
movement purchased
-Ugx.4.6Bn Supplied and
consumed.
6 Improve security of 3.2 0.6 Insurance of the assets
URC assets – Ugx600M
13.0 14.51 4.0
Direct and indirect
Improve direct & support to operations
indirect support
services
FINANCE, COMMERCIAL & PROCUREMENT DEPARTMENTS
7 Commercial & 3.04 0.285 0.118 -Advertising & public
operations-Improve relations paid-Ugx
direct & indirect .118M
support services
8 Operations 2.56 2.13 4.088 -Capacity building
expenses-paid
Ugx.1.9bn
-Travel to support
operations undertaken
Improve direct & 8.78 Ugx.1.3Bn
indirect support Costs like
-Passenger services
services cleaning
costs paid -Ugx.303M
coaches,
-Utilities paid
tickets printing
-Ugx.585M
9 Procurement & 0.206 0.057 0.183 -Stationery paid
disposal -Ugx.171M
-Tender adverts paid
-Ugx.12M
HUMAN RESOURCE DEPARTMENT
10 Improve staff welfare 2.29 1.79 2.78 -Staff welfare paid
-Ugx.423M
-workers’ Gratuity paid
compensation paid was for some
-Ugx.292M staff
-Gratuity paid
-Ugx.903M Medical
-Medical expenses insurance
paid -Ugx.668M premiums

-Other employee costs


paid -Ugx.489M
88 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

11 Improve direct & 4.57 7.43


indirect support
services
12 Build capacity of the 15.72 10.93 12.42 -Salaries & wages paid All salaries
human resource -Ugx.12.22bn were fully paid
-Workshops &
seminars undertaken
-Ugx.162M
-Staff training
& recruitment
undertaken-Ugx.42M
INFORMATION TECHNOLOGY
13 Improve IT Systems 3.3 0.391 0.539 -Telecommunications This included
expenditure paid-Ugx airtime
Improve direct & .285M and data
indirect support -Computer supplies subscriptions.
services paid -Ugx.16M Paid fully.
-CCTV, computers All supplies,
paid -Ugx.163M computers
CCTV
-Budgeting tool pur- delivered.
chased -Ugx.75M Training in the
tool carried
out and its
now in use.
LEGAL DEPARTMENT
14 Support a fully func- 0.56 0.56 0.67 -Board expenses paid All paid
tional board -Ugx.650M
-Committee allowanc-
es paid-Ugx.18M
15 Support a fully func- 3.78 3.17 0.95 -Legal expenses paid All paid
tional legal system -Ugx.952M
TOTAL FUNDS 84.91 74.6 36.98 50% of the adjusted
budget and 44% of the
GoU approved budget.

8.4 CHALLENGES AND PROPOSED MITIGATION MEASURES

A number of challenges were experienced by the corporation during the year, some of
which are outlined in the Table 51;
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
89

Table 51: Challenges and proposed mitigations measures

Challenge Description/Impact Proposed remedy/Mitigation measure


Rampant washa- The Meter Gauge Railway line in Civil Engineering teams on both KRC and
ways and acci- both Kenya and Uganda was in a URC railway networks will be engaged to
dents (derailments poor state of disrepair and therefore undertake preventive maintenance and put
and capsizements) continued to seriously hamper in place teams-rapid accident response teams-
safe and reliable freight services so as to reduce time spent repairing the line
between Mombasa and Kampala. especially following accidents. These wash
The situation was made worse aways occurred during the peak rainy seasons
by the severely wet season in the in December and in April. In addition, routine
second quarter which resulted in
check -ups should be carried out in flood/wash-
several wash-aways and landslides
costing the Corporation over 100 away -prone areas.
operating days in lost time. Wash
– aways were reported in Kijabe
in quarter four and Sabatia-Maji
Mazuri section in Quarter two
blocking over 266 loaded wagons.
In financial terms. These accidents
cost the Corporation an estimated
USD 700,000 in revenue, and this
reduced customer confidence.
COVID 19 pan- Due to COVID-19 pandemic, the The governments of Uganda and Kenya
demic and its ef- country was under lock down advocated for rail usage by all heavy cargo
fects to the sector. between Mid-March to early June. transporters, which is hoped will generate
The worldwide lockdown left more business for the Corporation in the
major sectors of the economy like coming year.
transport and logistics paralysed.
Further, SOPs from the Ministry of Health
The pandemic further affected have been adhered to during all operations and
the global supply chain as a result activities.
closure of incoming shipments to
Mombasa/Dar es salaam, further
contributing to about 38,000
MT in lost revenue due to order
cancellations.

Unavailability of MV Kaawa was docked for its The works on MV Kaawa was expedited and it
MV Umoja and scheduled maintenance and was undocked in the last month of the FY.
the delay of MV repairs rendering the vessel non-
Kaawa repairs operational for 5 months (February Engagements with TRC are ongoing so as to
(Both ships were to June). In May, MV Umoja was speed up the repairs of Umoja.
on the dry dock) also docked in Mwanza. With
both vessels unoperational, this
meant that URC couldn’t carry
Central (Southern) corridor cargo,
which mainly comprised WFP.
The Corporation further lost an
estimated 20,000MT from GSM,
about 7000Mts of cargo that had
already been confirmed by clients
for haulage.
Continued use of These wagons do not to serve the The Corporation negotiated a charge to the
URC wagons for Transit purpose which affected TRC management and meetings were held to
internal haulage cargo movement on the central discuss the same.
within Tanzania corridor.
Further, TRC has been asked to return these
wagons so that they can be used on the
northern corridor.
90 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Continuous lack There is no visibility on cargo There are plans to procure a joint system with
of a cargo tracking beyond PortBell keeping all TRC.
system on the stakeholders in the dark about the
Central route location of wagons/cargo. Operations team have a daily online meeting
with TRC representatives where they share po-
sitions of transit cargo in their network.

Poor state of loco- The Corporation operated with Continued maintenance of the available
motives only one mainline locomotive locomotives through procurement of the
whose average availability was at required spares.
16% in the year, due to lack of funds
for its adequate maintenance. Lease of locomotives from Tanzania to
temporarily improve on our capacity.
This meant that for delivery of car-
go, use of other weak locomotives Procurement of new mainline locomotives.
had to be engaged, delaying cargo Process are completed pending delivery of
delivery and causing accidents. locos.

Poor state of real The real estate property was Rehabilitation and renovation of these proper-
estate property grossly affected by the period ty to increase their value.
of the concession during which
period many assets - especially
real estate- (those not considered
core to the business) were left
idle /abandoned, following which
many deteriorated.
Encroachment / Because many assets were left idle On the property management portfolio, URC
theft or unused for too long, some were management will follow-up with the line
occupied by squatters. Minister to intervene in the matter of the
Encroachers have put up struc- ownership claims of the Nalukolongo land and
tures, cultivated and put up many have the ministry of lands issue Special Titles
businesses. to URC.

Theft of track Rampant vandalism of track Beefing up police patrols and facilitating the
Materials (Van- materials especially sleepers and track with motorcycles was planned (shortage
dalism) pandrol clips of funds).

The corporation started welding of sleeper fit-


tings in some areas.

8.5 STRATEGIES FOR THE FUTURE

8 . 5 . 1 Rally GoU support for Railway


Among her future plans, URC will continue with the objective of maintaining railways
operations by driving for more efficient and effective railway and marine operations. This
will be done through cost management, mitigating accidents and incidents, and striving for
lower costs of doing business that will lead to profitability for the business community, and
thus tax income to the GoU. It is planned that the above will be achieved by partnering with
the GoU and requesting for their support through the avenues discussed in the Table 55.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
91

Table 52: How the Government can support railway

Strategy Status
Setting a national Transport The overall policy aims & framework that govern
Strategy how railways and other modes of transport will be
developed & operated

Creating railways sector Primary industry institutions, balance of public and


structures private sector roles, the competitive framework for
railways
Purchasing Transport Methods by which Governments specify and
services purchase railway services or special fare concessions
on behalf of the community

Regulating the industry Institutional methods of administering economic,


technical, environmental and safety regulations

Facilitating international Inter-governmental frameworks that promote inter-


railway integration operation ability and seamless service across the border.
i.e. Helping to emphasize adherence to any Bilateral or
Tripartite agreements by international partners. (Say
KRC and TRC)

Establishing the The organizational of ministries to perform the


administrative above roles generally including supervision of
apparatus railway sector entities

Project proposals geared towards improving the railway operations will continue to be
written for the GoU’s consideration and funding either using own resources or those of
international funders.

In the long term, URC’s strategy is to run both Meter Gauge and Standard Gauge Railway
under the reviewed railway policy. It is anticipated that URC will be able to operate profitably
after fully implementing most of the projects geared towards improving the efficiency
of its operations. The areas of priority and business focus will include:

8.5.2 Rehabilitate Infrastructure:

In a bid to catch up with the deferred maintenance, URC has a plan to design and implement
a rehabilitation programme with spot improvement of the main line (Kampala-Malaba) by
re- laying 30,000 sleepers with new materials and ballasting. Expansion of the Portbell and
Bukasa Port are also planned to handle marine operations.

8.5.3 Rehabilitate Rolling stock

(1) Locomotives:

The current capacity of the rolling stock is very low due to long periods of deferred
maintenance of the assets. The Corporation had 5 mainline locomotives out of which 2
were active during the FY 2019/20, with an average availability of about 12%. URC plans to
salvage the current 16 locomotives by carrying out a complete overhaul, projected to cost
92 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Ugx.760M per locomotive.

There are also plans to buy 10 high capacity locomotives, 4 in the next FY2020/21 and 6
in the following FY and install IT Infrastructure and tracking equipment on board. URC
tendered out procurement of 4 main Line locos expected to be delivered early next year
2021, two (02) reach stackers (container cranes) expected to be delivered before end of 2020.
(2) Wagons

URC currently has 1,351wagons available on the network, out of which 569 were active by
the end of June 2020. There are also plans to purchase 200 wagons within the stipulated
five years’ period, (of the investment plan) and to rehabilitate 150 Wagons.
(3) Human Resource Personnel:

URC carried out an evaluation of its current staff for competences and experiences
required for operations especially in operations and mechanical engineering skills. Plans
are underway to send various staff in the rolling stock sections for training, in partnership
with Kenya Railways Corporation (KRC), at the railways training school in Kenya. In order
to improve productivity, employee retention, efficiency and effectiveness of human capital
at URC, select staff training is planned.

8.5.4 Passenger service operations:

This service was originally initiated as a Passenger service with the GoU subsidy. However,
URC is running this service fully, which has strained its resources. The current operational
costs of this service at Ugx.80M per month. For operational continuity therefore, URC
plans to source for GoU support.

With a limited sitting /standing capacity of 120-150 persons per coach, URC intends to
rehabilitate 10 more coaches and to acquire five sets of Diesel Multiple engines so as to
increase capacity and expand the passenger services across Greater Kampala Metropolitan
Area. The expansion is planned to cover Kampala station to Port Bell on the southern line,
and from Nalukolongo station to Bujjuko on the western line.

Commuter ridership has continued to grow over the past months which is a reflection of
the high demand for this service in the city. In spite of this, the service was operating at a
loss throughout the year, due to the high costs involved in running the service (Ugx,80M
pm). There is need to invest in infrastructure to increase the number of coaches, construct
platforms and halts and park and ride facilities. To make full utilisation of the passenger
service, the following will be done:

• request the GoU for more funding to expand the service, and also for the GoU to
continuously support this service financially as a fulfilment of the NRM objective of
improving connectivity within the GKMA through provision of light railways etc.
• extend the service to cover the Greater Kampala Metropolitan Area to 3 routes
namely, Kampala – Namanve; Kampala - Port Bell; and Kampala - Kyengera.
• rehabilitate and increase the number of coaches to 10 and above for each route,
procurement or rehabilitation of two additional locomotives.
• the Ministry of Works and Transport is in advance stages of presenting a com-
prehensive cabinet memorandum to cabinet for inventions to decongest the Greater
Kampala Metropolitan Area.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
93

8.5.5 Wagon ferries:

URC currently operates only one wagon ferry MV Kaawa which is inadequate for the
anticipated volumes on the Southern route. There are plans to rehabilitate MV Pamba and
acquire a new wagon ferry.

8.5.6 Property Development


A property development proposal was made to the board of URC and it was approved. It
entailed the development, rehabilitation and management of the URC real estate property
to improve their income generation capacity.

8.5.7 URC plans t o exploit the opportunities below to improve its income generation
capacity;

• Develop capacity to enable negotiations for access rights for both Kenya and
Tanzania to solve problems in foreign networks currently affecting service
delivery.
• Plan to procure Reach stackers for container terminals.
• Hire agencies to manage URC interests in KRC and TRC networks.
• Start moving fuel from Eldoret to Kampala as soon as tanks are calibrated.
• Renovation of the big fuel tank at Kampala depot to facilitate fuel supply
management.
• Push for closure of negotiations with VIVO Energy, Equator shipping and
Kampala salt, push for an increase in imports from Spedag and DAMCO to match
their export needs and also drive for sugar exports along Central Corridor from
Madhvani and SCOUL.
• Through direct marketing, the commercial department is to conduct weekly client
visits and include visit engagements.
• More coordination planning and communication to be pushed for especially among
the sister networks especially on the central corridor.
• Push for civil department to develop necessary infrastructure for clients that
requested for sidings.
• Harmonization of rates with our sister partner networks against the ongoing
competitor rates so as to remain competitive throughout the network.
• URC is considering offering first and last mile solutions for their clients. This could
be through establishing sidings to all major and prospective client premises. Clients
like Steel, tube and petroleum product. Tasco Industries have expressed need for a
siding at their factory on a cost sharing basis.
• Up-selling other services like clearing services together with having reliable
partners in the other networks like clearing firms should be considered to improve
the services.
• Attain exports business from Madhvani and SCOUL on the southern route.
• Schedule weekly Client visits: Provide client engagement reports and follow ups
focusing on COVID19 SOPs
• Operationalization of Mukono ICD bond
94 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Earthmoving equipment in
Amuria District
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
95

9.0 PERFORMANCE OF UGANDA ROAD FUND VOTE 118

9.1 FINANCIAL PERFORMANCE

9.1.1 Performance of Funds Inflow in FY 2019/20

In FY 2019/20 URF received a sum of UGX 443.282bn from the Treasury, in quarterly
tranches, which constituted 99.1% of the approved annual budget for road maintenance.
Table 53 shows the performance of the receipts from MoFPED during FY 2019/20.

Table 53: Summary of Funds Inflow to Vote 118, FY 2019/20

S/N Description Approved Quarterly Releases FY 2019/20 (UGX bn) Total % of


Annual Bud- Release Annual
get UGX (bn) Q1 Q2 Q3 Q4 (UGX Budget
bn) Released
1 MoFPED Releases
  UNRA 270.000 67.164 80.125 104.5%
66.503 68.399 282.191
  DUCAR 162.133 41.165 28.197 92.5%
40.533 40.048 149.943
  URF Sec. Recur- 8.350 1.486 2.043 100.0%
rent 3.117 1.703 8.350
  URF Sec. Dev’t 6.620 0.524 - 2.799 42.3%
0.813 1.463
  Total Amount 447.103 110.365 99.1%
110.966 111.613 110.338 443.282
2 Dates of Release   25-Jul-19 15-Oct-19 17-Jan-20 14-Apr-20    
  Delay (No. of cal- Annual 24 14 16 13 16.75  
endar days from Target for FY
start of Quarter) 2019/20 = 14 (average)

Key indicators to note in Table 53 are: the budget releases performed at 99.1% of the approved
budget estimates, and on average took 16.75 calendar days from the start of each quarter.
Table 54 shows performance of the KPIs for funds inflow against target.

Table 54: Performance on KPIs for Funds Inflow, FY 2019/20

S/N KPI Target in FY 2019/20 Actual Realised in Remarks


OYRMP FY 2019/20
1 Efficiency (% of potential revenue collect- 98% min 99.1% Achieved
ed in each category)
2 Timeliness (Average days from collection 14 calendar days max 16.75 calendar days Not Achieved
to deposit for each category) average

It can be seen from Table 54 that the performance target for Efficiency was achieved with
99.1% of the targeted minimum potential revenue collected. The performance target for
Timeliness was not achieved. The KPI for efficiency in revenue inflows performed well at
1.1% above the target, and, the KPI for timeliness of revenue under performed at 101.2% of
the maximum allowable time.
96 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

9.2 PHYSICAL PERFORMANCE

9.2.1 PERFORMANCE ON GOLDEN INDICATORS MONITORED BY URF

9.2.1.1 Road Maintenance Costs

The costs were derived from aggregation and averaging of unit costs from annual work
plans of DUCAR agencies. The work plans conformed to the prevailing policy on use of force
account on road maintenance works in local government agencies. The data of maintenance
costs on national roads is measured and reported directly by UNRA and was therefore not
taken into account. Table 55 shows the data for district and urban roads for the period FY
2018/19 and FY 2019/20.

Table 55: Road Maintenance Unit Costs in the period FY 2018/19 – FY 2019/20

Indicator FY FY 2019/20 Notes


2018/19
1,000 USD/km
1.1     District Roads – Periodic Maintenance 5.3 5.4

1.2    District Roads – Routine Maintenance 0.7 - 1.6 0.8 - 1.8 1


1.3    Urban Roads – Periodic Maintenance, paved 186.9
1.4   Urban Roads – Routine Manual Maintenance, Paved 2.1 – 2.5 2.2 – 2.7 2
1.5 Urban Roads – Routine Mechanised Maintenance, Paved 3.8 – 4.8 4.1 – 4.9 3

1.6    Urban Roads – Periodic Maintenance, Unpaved 7.2 – 13.9 7.4 – 14.2 4

1.7    Urban Roads – Routine Maintenance, Unpaved 0.7 – 2.4 0.8 – 2.6 5

Notes

1. Lower end of range for manual works; higher end for mechanized

2. Lower end of range for town councils; higher end for municipal councils

3. Lower end of range for low traffic; higher end for high traffic urban roads (KCCA and GKMA
MCs).

4. Lower end of range for town councils; higher end for municipal councils

5. Lower end of range for manual works; higher end for mechanized

It can be observed from Table 55 that there was a general increase in the unit cost of
road maintenance in FY 2019/20 compared to FY 2018/19. This is attributed to general
inflationary pressures that pushed up the cost of road maintenance inputs like fuel, gravel,
equipment repairs and maintenance, equipment hire, and labour rates. Observably, the
increase was more pronounced in urban local governments which were not beneficiaries of
newly acquired equipment from Japan and as such spent more on equipment hire.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
97

9.2.1.2 Maintenance Budget Relative to Requirements

The performance indicators for maintenance budget relative to requirements were


computed as the ratio of available maintenance budgets (for different network categories)
to the unconstrained annual maintenance needs of the networks. This considered
only the proportions of the networks in maintainable state devoid of backlogs. The
maintenance backlogs were measured separately using two sub-indicators: annual budget
for rehabilitation/ backlog removal; and unconstrained cost for rehabilitation/removal of
backlog on all roads. The details are presented in Table 56.

Table 56: Maintenance Budget in FY 2019/20 Relative to Requirements

Indicator Unit FY 2018/19 FY 2019/20


2.1    National roads (Maintenance) % 29% 25%
2.2   District roads (Maintenance) % 27% 15%
2.3   Urban roads (Maintenance) % 26% 15%
2.4   Budget all roads (Rehabilitation) Million - USD 179.2 186.2
2.5   Backlog all roads (Rehabilitation) Million - USD 1,520 1,154.3

The budget relative to requirement indicators decreased from FY 2018/19 to FY 2019/20 for
all road categories following decreased budget for road maintenance from UGX 542.517bn
in FY 2018/19 to UGX 448.833bn in FY 2019/20. The road maintenance backlog decreased
as shown in Table 56 due to increased allocation for rehabilitation particularly under the
USMID Programme, but also due to a rebasing of the computation of maintenance needs on
the Community Access Roads during the year.

9.2.1.3 Maintenance Expenditure Relative to Releases

The indicators for maintenance expenditure relative to releases were derived as a percentage
of URF releases expended by the designated agencies within the FY. Absorption of funds
under rehabilitation programmes in UNRA and DUCAR agencies was not considered in line
with the approved indicator definition. Table 57 shows the absorption of road maintenance
funds on national roads, KCCA roads and the DUCAR network.

Table 57: Maintenance Expenditure Relative to Releases


Indicator FY 2018/19 FY 2019/20
Status at Q4
2.6   National roads 100% 98.9%
2.7 KCCA roads 100% 100%
2.7   DUCAR 1
62% 64%
1
No data yet to enable reporting on DUCAR absorption of road maintenance funds at end of
Q4 FY 2019/20.

It can be seen from Table 57 that whilst UNRA and KCCA had essentially expended all the
funds released to them at close of FY 2019/20, the expenditure of DUCAR Agencies in Q1-3
FY 2019/20 stood at 64% of the annual funds availed them.
98 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

9.2.2 PERFORMANCE OF ROAD MAINTENANCE FINANCING IN FY 2019/20

9.2.2.1 Trend of Road Maintenance Financing

Prior to the establishment of URF, the Treasury, within the framework of annual budgetary
appropriations, directly disbursed road maintenance funding to agencies. However, the
approach did not prioritise road network maintenance needs against the backdrop of
competing demands. Consequently, and owing to the funding shortfall, the national roads
network for instance, accumulated a maintenance backlog of 3,500Km (equivalent 33% of
its 11,000Km network at the time) between 1997/98 and 2007/08. Over the same period, the
district roads network in poor to very poor condition also escalated from 30% to 55%. Part
of the reason for establishment of the Road Fund in 2008 was to address these condition
declines.

A road fund in essence is an institutional setup through which a selected stream of revenues
is put at the disposal of a government roads department or agency without being subjected to
general procedures associated with the Consolidated Fund. An enabled road fund offers best
opportunity to ensure adequate level and predictability of road maintenance funding. URF
has not yet attained this status owing to legal impediments constraining its independent
realization of revenues from road user charges. As such the current method of financing
road maintenance through quarterly releases from the Treasury is not fully responsive to
the road condition and road network needs as to adequately check maintenance backlog
growth.

Table 58: Road Maintenance Funding Fy2010/11 – Fy2020/21

FY UGX, Bn
Needs Available1 Un-met Needs
M’tce Backlog Total M’tce Others 2
Total Amount %tage
2010/11 632 451.5 1,083.5 273.1 119.5 392.6 690.9 63.8%
2011/12 672.8 579.6 1,252.4 273.1 170.9 444 808.4 64.5%
2012/13 958.5 656.2 1,614.7 273.1 359.3 632.4 982.3 60.8%
2013/14 836.4 584.2 1,420.6 345.6 377.5 723.1 697.5 49.1%
2014/15 1,083.40 769.5 1,852.9 420.9 410.7 831.6 1,021.3 55.1%
2015/16 1,273.30 822.4 2,095.7 410.9 441.6 852.5 1,243.2 59.3%
2016/17 1,732.80 1,235.80 2,968.6 399.4 583.5 982.9 1,985.7 66.9%
2017/18 1,756.70 1,243.50 3,000.2 399.4 335.4 734.8 2,265.4 75.5%
2018/19 1,807.20 1,258.00 3,065.2 512.24 337.1 849.34 2,215.9 72.3%
2019/20 1,867.40 1,280.60 3,148.0 419.106 348.9 768.0 2,380.0 75.6%
2020/21 1,939.90 1,306.30 3,246.2 427.1 350.2 777.3 2,468.9 76.1%

1
MTEF Projections in National Budget Estim1ates, FY 2019/20

Include others for rehabilitation such as PRDP, RRP, KIIDP, USMID and others but excluding
2

major upgrading works

Figure 10 shows the trend of road maintenance needs, road maintenance financing and the
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
99

un-met needs (including funding under USMID, RRP, KIIDP and PRDP), since FY 2010/11 and
as projected to FY 2020/21.

Figure 10: TREND OF ROAD MAINTENANCE FINANCING, FY 2010/11 – 2020/21

As shown in Figure 10, the total funds availed for road maintenance and rehabilitation has
been growing in nominal terms from UGX 393 billion in FY 2010/11 to UGX 768 billion in FY
2019/20 and is projected to further increase to UGX 777.3 billion in FY 2020/21. However,
the total maintenance needs (maintenance and rehabilitation) of the public road network is
increasing steadily at a faster rate than the increment in available funds. This is expected
since the funding for road maintenance and rehabilitation is not yet linked to road usage
represented by both traffic loading (cargo freight) and traffic volumes (number of vehicles).
Therefore, the total available funds need to be increased and sustained at a critical level to
force a steady decrease of the total maintenance needs. Funding of road maintenance also
needs to be linked to road usage through introduction of road user charges envisaged in the
URF Act.

Table 10 shows the Medium-Term Expenditure Framework (MTEF) projections to FY


2020/21, which indicates that the available funding in FY 2019/20 only met 24.4% of needs,
leaving funding of 75.6% of needs unmet. URF was allocated a total of UGX 447.103 billion
in FY 2019/20 under the MTEF, of which net allocation to road maintenance needs was UGX
419.106 billion against total requirements estimated at UGX 1.8674 trillion and therefore
leaving a shortfall of UGX 1.448 Trillion (77.5% of total).

9.2.2.2 Allocation of funds

A sum of UGX 448.833bn was allocated to URF for road maintenance in FY 2019/20, by
Parliamentary appropriations. This was UGX 93.7bn (17.3% decrement) less than the UGX
542.517bn in FY 2018/19. The funds were allocated to various expenditure heads by category
and by allowed uses as shown in sections 3.2 and 3.3.
100 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

9.2.2.3 Allocation by category of expenditure heads

Allocation of funds in FY 2019/20 by category of expenditure heads was as shown in Table


59.

TABLE 59: ALLOCATION OF FUNDS, 2019/20

Item FY 2018/19 FY 2019/20 FY 2019/20


Maintenance of National roads (UNRA) 312.563 270.000 60.2%
Maintenance of DUCAR network 184.179 139.747 31.1%
Maintenance of KCCA Roads 30.555 22.387 5.0%
URF Secretariat 8.350 8.350 1.9%
Project for Strengthening Capacity of URF 6.870 6.620 1.5%
Donor - 1.729 0.4%
Grand Total 542.517 448.833 100.0%

Source: URF OYRMP FY 2019/20

Comparatively, the allocation to national roads maintenance was decreased by UGX 42.6bn
(13.6%), the allocation to DUCAR network was decreased by UGX 44.4bn (24.1%), the allocation
to KCCA network was decreased by UGX 8.2bn (26.7%), while that for the URF Secretariat
was maintained at UGX 8.35bn.

9.2.2.4 Allocation by Allowed Uses

The funds appropriated to URF in FY 2019/20 were applied for various categories of works,
goods and services in line with section 22 of the URF Act, as detailed in Table 60 - UNRA,
Table 61 - KCCA, and Table 62 - DUCAR.

Table 60: Physical Performance of the National Roads Maintenance Programme in FY


2019/20

S/N Works Category FY 2018/19 FY 2019/20


    Planned Financed Achieved Planned Financed Achieved % of
Quantity Quantity Quantity Quantity Quantity Quantity Financed
Quantity
Achieved
1 Routine Maintenance              
  Manual (km) 17,803 17,803 17,872 15,968 15,968 15,968 100%
  Mechanized (km) 11,930 11,930 11,243 10,098 19,346 19,346 100%
2 Periodic Maintenance              
  Paved (km) 61 61 4 7.5 3.8 3.8 100%
  Unpaved (km) 636 636 780 225.2 24.5 24.5 100%
3 Bridges              
  Routine (No.) 337 337 324 348 348 348 100%
  Periodic (No.) 0 0 0 0 0 0  
4 O&M weighbridges (No.) 20 20 20 20 20 20 100%
5 O&M ferries (No.) 9 9 9 9 9 9 100%

It can be observed from Table 60 that not all the planned quantities of works on the national
roads network were funded in FY 2019/20. This is because some funds were reallocated to
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
101

emergency works and outstanding payments for contractors and suppliers. Implementation
of planned activities for both routine and periodic maintenance performed well as all funded
targets were achieved.

TABLE 61: PHYSICAL PERFORMANCE OF THE CITY ROADS MAINTENANCE PRO-


GRAMME IN FY 2019/20

S/N Works Category FY 2018/19 FY 2019/20

    Planned Financed Achieved Planned Financed Achieved % of


Quantity Quantity Quantity Quantity Quantity Quantity Financed
Quantity
Achieved
1 Routine              
Maintenance
  Manual (km) 879 879 1,021 587 1,008 1,008 100%
  Mechanised (km)
2 Periodic              
Maintenance
  Paved (km) 4.8 4.8 5 0.76 4.0 4.0 100%
  Unpaved (km) 0 0 0 0 0 0  

It can be observed from Table 61 that all the planned quantities of works on the city roads
network were funded in FY 2019/20. Actually, more works were funded than were planned
for in the FY. The extra funding was to cater for emergencies including dilapidated roads
and other facilities on Kampala City Roads. On average, the achievements were 100% of the
financed quantities when measured at the end of FY 2019/20.

TABLE 62: PHYSICAL PERFORMANCE OF THE DUCAR MAINTENANCE PROGRAMME


IN FY 2019/20

Works Category FY 2018/19 FY 2019/20


  Planned Financed Achieved Planned Financed Achieved % of Financed
Quantity Quantity Quantity at Quantity Quantity Quantity Quantity
Q3 at Q3 Achieved at Q3

Routine              
Maintenance
Manual (km) 29,725 29,725 23,576 28,567 21,538 19,765 91.8%
Mechanised (km) 15,951 15,951 9,568 14,957 83.2%
11,344 9,437
Periodic              
Maintenance
Paved (km) 5,308 5,308 1,988 4,962 3,912 2,985 76.3%
Unpaved (km)
Bridges              
Routine (No) 40 40 20 35 27 21 77.8%
Periodic (No)
Culvert Installation 7,429 7,429 5,248 629 473 396 83.7%
(Lines)

Table 62 shows the physical performance of DUCAR agencies based on analysis of 94.3% of
the agencies (125 DLGs and 40 MCs) that had submitted Q3 FY2019/20 accountability reports
at the time of compilation of this report. The agencies constitute 96% of the funds released for
102 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

maintenance of the DUCAR road network in FY 2019/20.

It can be observed from Table 7 that the planned quantities of works on the DUCAR network
were under funded in FY 2019/20. This was due to COVID-19 outbreak that distorted normal
operations across the country and thus affected release and disbursement of funds to LGs in
Q4 FY 2019/20. It can also be observed that the physical performance was in the range 76.3%
- 91.8% but on average 82.6% of the financed quantities across the various works categories
when measured at the end of Q3 FY 2019/20.

9.2.2.5 Performance of Funds Inflow in FY 2019/20

In FY 2019/20 URF received a sum of UGX 443.282bn from the Treasury, in quarterly
tranches, which constituted 99.1% of the approved annual budget for road maintenance.
Table 63 shows the performance of the receipts from MoFPED during FY 2019/20.

TABLE 63: SUMMARY OF FUNDS INFLOW TO VOTE 118, FY 2019/20

S/N Description Approved Quarterly Releases FY 2019/20 (UGX bn) Total % of


Annual Release Annual
Budget Q1 Q2 Q3 Q4 (UGX bn) Budget
UGX (bn) Released
1 MoFPED Releases
  UNRA 270.000 67.164 80.125 282.191 104.5%
66.503 68.399
  DUCAR 162.133 41.165 28.197 149.943 92.5%
40.533 40.048
  URF Sec. 8.350 1.486 2.043 8.350 100.0%
Recurrent 3.117 1.703
  URF Sec. Dev’t 6.620 0.524 - 2.799 42.3%
0.813 1.463
  Total Amount 447.103 110.365 99.1%
110.966 111.613 110.338 443.282
2 Dates of Release   25-Jul-19 15-Oct-19 17-Jan-20 14-Apr-20    
  Delay (No. of Annual 24 14 16 13 16.75  
calendar days Target for
from start of FY 2019/20 (average)
Quarter) = 14

Key indicators to note in Table 63 are: the budget releases performed at 99.1% of the approved
budget estimates, and on average took 16.75 calendar days from the start of each quarter.
Table 64 shows performance of the KPIs for funds inflow against target.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
103

TABLE 64: PERFORMANCE ON KPIS FOR FUNDS INFLOW, FY 2019/20

S/N KPI Target in FY Actual Realised in Remarks


2019/20 OYRMP FY 2019/20
1 Efficiency (% of potential 98% min 99.1% Achieved
revenue collected in each
category)
2 Timeliness (Average days from 14 calendar days 16.75 calendar days Not Achieved
collection to deposit for each max average
category)

It can be seen from Table 64 that the performance target for Efficiency was achieved with
99.1% of the targeted minimum potential revenue collected. The performance target for
Timeliness was not achieved. The KPI for efficiency in revenue inflows performed well at
1.1% above the target, and, the KPI for timeliness of revenue under performed at 101.2% of
the maximum allowable time.

9.2.2.6 Performance of Funds Disbursements in FY 2019/20

In FY 2019/20, URF made disbursements amounting to UGX 442.294bn, as shown in


Table 65, of which UGX 431.146bn was disbursed to DAs for maintenance of the various
categories of the public roads network whilst UGX 8.350bn and UGX 2.799bn were retained
for administrative expenses of the URF Secretariat and project to strengthen capacity of URF
respectively. On average, disbursements to UNRA took 10 calendar days and 17 calendar
days to DUCAR agencies, from the dates of receipt of funds from MoFPED.

TABLE 65: SUMMARY OF FUNDS DISBURSEMENTS–FY 2019/20

S/N Description Disbursements FY 2019/20 (UGX bn) Total Approved % of


Approved
Q1 Q2 Q3 Q4 Disbursement Annual Annual

Budget Budget

  FY Disbursed
2019/20
1 URF              
Disbursements
  UNRA 66.503 68.399 67.164 80.125 282.191 270.000 104.5%
  KCCA 5.748 4.357 6.201 15.496 31.801 22.387 142.1%
  Districts 14.484 10.980 15.626 - 41.089 56.414 72.8%
  Municipalities 7.019 5.321 7.572 - 19.911 27.338 72.8%
  Town Councils 6.159 4.669 6.644 - 17.472 23.989 72.8%
  CARs - 12.996 - - 12.996 12.996 100.0%
  Special Funds 7.124 1.610 5.122 11.829 25.686 19.009 135.1%
  URF Sec. 3.117 1.703 1.486 2.043 8.350 8.350 100.0%
Recurrent
  URF Sec. Dev’t 0.813 1.463 0.524 - 2.799 6.620 42.3%
  Total 110.966 111.498 110.338 109.493 442.294 447.103 98.9%
104 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

2 Av. Delay of 8.0 5.5 7.0 10.0 Average 10 days


Disbursement to
UNRA (Calendar
days)
3 Av. Delay of 21.62 12.39 15 17 Average 17 days
Disbursement
to DUCAR
(Calendar days)

It can be seen from Table 65 that disbursements to Local Governments and the URF de-
velopment project were significantly below 100%. This was occasioned by the COVID-19
pandemic that led to change in MoFPED’s funding priorities. Figure 1 shows the percentage
disbursements to the different categories of DAs and sub-agencies made by URF during FY
2019/20.

FIGURE 8: DISBURSEMENTS BY CATEGORY OF AGENCIES – FY 2019/20

It can be seen from Figure 11 that the biggest portion of the disbursements went to UNRA
(63.8%) for maintenance on the national road network while the rest was shared between
maintenance of the DUCAR network and KCCA roads, with the residual going to the URF
Secretariat. Figure 12 shows a disaggregation of the disbursements as percentages of the
respective approved annual budgets in FY 2019/20 across the various expenditure heads.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
105

FIGURE 9: DISBURSED FUNDS AGAINST IPFS OF DAS AND SUB-AGENCIES, FY 2019/20

It can be seen from Figure 12 that Local Governments and the URF development project
received significantly less than 100% of their approved Indicative Planning Figures
(IPFs)

9.2.2.7 Performance of Funds Expenditure in FY 2019/20

Table 66 shows the summary of performance of expenditures against available funds for FY
2019/20.

TABLE 66: SUMMARY OF EXPENDITURES AGAINST AVAILABLE FUNDS, FY 2019/20

Funds Total
Annual Actual Unspent % of avail-
rolled Releas- Funds
Bud- Expendi- balanc- able funds
Agency over es FY avail-
get FY ture FY es FY absorbed
from FY 2019/20 able FY
2019/20 2019/20 2019/20 FY 2019/20
2018/19 2019/20

  (UGX (UGX (UGX (UGX bn) (UGX bn) (UGX  


bn) bn) bn) bn)
(a) (b) (c) (d) = (b+c) (e) (f) = (d-e) (g) = (e/d)
          At End of Q4 FY 2019/20
UNRA 282.191 284.650 281.619 3.030 98.9%
270.000 2.459
KCCA 31.801 34.783 34.783 0.000 100.0%
22.387 2.982
URF Sec - 8.350 8.350 8.317 0.032 99.6%
Rec. 8.350
URF Sec. - 2.799 2.799 2.546 0.252 91.0%
Dev’t 6.620
Subtotal 307.357 325.140 330.581 327.266 3.315 99.0%
1 5.441
          At End of Q3 FY 2019/20
DUCAR - 118.142 118.142 75.611 42.531 64.0%
139.747
Subtotal 139.747 - 118.142 118.142 75.611 42.531 64.0%
2
Total 447.103 443.282 448.723 402.877 45.846 89.8%
5.441
Source: URF Final Accounts & Quarterly Progress Reports from the DAs

It can be observed from Table 66 that when measured at the end of Q4 FY 2019/20: UNRA,
KCCA and the URF Secretariat had absorbed all the funds that were availed to them during
the FY; while as at the end of Q3 FY 2019/20, DUCAR agencies had not yet absorbed 36% of
the annual funds availed to them. Total absorption of road maintenance funds was at 89.8%
of releases, however it was expected to rise in excess of 98% upon consideration of the Q4
absorption by DUCAR agencies.
106 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Figure 13 shows a graphical representation of the financial performance of the various main
expenditure lines in FY 2019/20.

FIGURE 10: GRAPH SHOWING THE FINANCIAL PERFORMANCE OF AGENCIES

It can be observed from Figure 13 that while UNRA, KCCA, and the URF Secretariat had good
absorption of the funds availed to them in FY 2019/20, the absorption of DUCAR agencies
was out of sync with time progress by about 11% as at the end of Q3.

9.2.3 PERFORMANCE AGAINST THE 14TH JTSR ACTION PLAN MATRIX AND
PROGRESS

The key action points for URF in the 15th JTSR action plan matrix and the respective achieve-
ments are provided in Table 67.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
107

TABLE 67: PROGRESS OF URF ON THE 15TH JTSR ACTION PLAN MATRIX

Code Issue Action Deadline Responsible Progress to date Remark


Organization

R1 Inadequate Submit a June 2020 URF Completion of the Partially


Sector fi- Cabinet Memo Cabinet Memo was Achieved
nancing for on the need delayed pending
road main- to increase finalization of the
tenance funding for road study on funding
maintenance models for URF.
Funding for road
maintenance was
however increased
by 14.1% (from
UGX 448.8Bn in
FY 2019/20 to
UGX 512.1Bn in FY
2020/21) through
engagement efforts
with MFPED,
Parliament and
PACOB

Finalize the June 2020 URF Finalization of Partially


study on insti- the study was Achieved
tutional and delayed as a result
optimal fund- of the onset of the
ing models for COVID-19 pandemic
Uganda Road and subsequent
Fund suspension of
the EU funded
programme under
which the study was
being undertaken.
Key milestones
undertaken during
the study included: a
study tour to Namibia
and South Africa;
and a stakeholder
consultative
workshop.

Complete the June 2020 URF A draft of the funds Partially


review of the allocation formula Achieved
URF funds allo- was produced
cation formula but was yet to be
to ensure that it progressed through
is equitable and the approval process.
consistent Completion of the
funds allocation
formula was
delayed as a result
of the onset of the
COVID-19 pandemic
and the subsequent
suspension of the EU
funded programme
under which the
review was being
undertaken.
108 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

9.3 FUTURE PLANS – 3 YEARS

9.3.1 GLOBAL ALLOCATION FOR FY 2019/20

The budget estimate for road maintenance under vote 118 in FY 2020/21 is UGX 512.175bn.
This represents an increment of UGX 63.343bn which is 14.1% of the FY 2019/20 approved
budget. Table 68 shows the broad allocation of the funds across the various road network
categories.

TABLE 68: Global allocation of funds, FY 2020/2021

No. Programme Item FY FY % of Total Allocation


2019/20 2020/21 FY 2019/20
Amount Amount
(UGX bn) (UGX bn)
1 UNRA 258.439 298.724 58.32%
Joint training between UNRA & 0.500   0.00%
URF
UNRA Operations 11.061 11.561 2.26%
Total National roads  270.000 310.285 60.58%
  Districts 54.902 56.181 10.97%
2 Cities   7.590 1.48%
CAR 12.974 13.203 2.58%
Town Councils 23.949 23.967 4.68%
Extended Periodic Maintenance 10.799 14.992 2.93%
Towns Councils
Municipal Councils 25.486 23.302 4.55%
KCCA 22.387 25.551 4.99%
Special interventions on DUCAR 3.566 10.0000 1.95%
Small Bridges on DUCAR Net- 1.783   0.00%
work
Special Allocation to agencies in 3.364   0.00%
GKMA
Affirmative Action for distressed 1.456 1.456 0.28%
areas
Establishment of TSUs 0.781   0.00%
M&E of DUCAR 0.343   0.00%
Technical & Financial Reviews of 0.343   0.00%
DUCAR
Total for maintenance of DUCAR net- 162.133 176.242 34.41%
work
3 Administration of Secretariat 8.350 9.758 1.91%
Project for Strengthening 6.620 15.890 3.10%
Capacity of URF
Donor Funding 1.729   0.00%
Total URF Secretariat 16.699 25.648 5.01%
Grand Total  448.832 512.175 100.00%
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
109

Source: URF OYRMP FY 2020/21

Based on expressed needs of Agencies in the amount of UGX 1.2 Trillion in FY 2020/21, there
will be a shortfall in funding of UGX 653Bn made up as follows: National roads UGX 398bn;
and UGX 255Bn for the DUCAR network including KCCA. The effect of the shortfall will be
reduced level of periodic maintenance especially on the DUCAR network, which will conse-
quently increase the maintenance backlog.

9.3.2 PLANNED ROAD MAINTENANCE ACTIVITIES IN FY 2019/20

Table 69 shows a summary of the key road maintenance activities planned to be funded in FY
2020/21 as compared to FY 2019/20.

TABLE 69: Summary of road maintenance activities planned to be funded in fy 2020/21

Sn Works FY2019/20 FY2020/21


Category
National Roads DUCAR Network National Roads DUCAR Network
Network Network
Qty Amount Qty Amount Qty Amount Qty Amount
(UGX Bn) (UGX (UGX Bn) (UGX Bn)
Bn)
1 Routine                
Mainte-
nance
  Manual (Km) 18,948 24.343 24,030 20.562 19,742 28.565 26,121 22.348

  Mechanized 12,274 128.287 15,505 33.255 12,675 104.339 16,854 36.121


(Km)
2 Periodic
Mainte-
nance
  Paved (Km) 33 23.401 5,122 34.357 14.5 9.474 5,568 37.621
  Unpaved 314 30.484 531.4 35.569
(Km)
3 Bridges

  Routine (No) 337 1.761 45 0.743 684 2.034 47 0.821


  Periodic (No) - - - -
4 Culvert - - 5,145 8.436 - - 5,581 9.138
Installation
(Lines)

It can be seen from Table 69 that, on both national roads and DUCAR network, there was a
general increase in the quantities planned to be funded under all works categories due to a
12.6% increase in the budget for maintenance of national roads and DUCAR network.

9.3.3 PLANS FOR THE MEDIUM TERM

In the medium term, FY 2020/21 – 2022/23, URF plans to adopt the strategies in Table 70 to
improve operations of the Fund and road maintenance financing.
110 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

TABLE 70: Strategies to improve road maintenance financing

SN STRATEGY ACTIONS TIMING REMARKS

1 Promote use of • Revamping the use of road FY 2020/21 This is expected to support
road management maintenance management – 2021/22 planning and programming
tools/software systems of road maintenance works in
DUCAR agencies.

2 Establish regional • Zone LGs into 4 regions FY 2020/21 TSUs will support LGs in
Technical Support • Progress the Roll out and implementation of their road
Units (TSUs) for strengthening the TSUs maintenance programmes
LGs including preparation of good
quality work plans, works
implementation, preparation
of good quality reports and in
a timely manner.

A pilot TSU in northern


region of Uganda was
successfully trialled in FY
2019/20. Subsequently 2 TSUs
have been rolled out to 50
select LGs scattered all over
the four regions of Uganda in
FY 2020/21.
3 Introduction of • Launch of a bespoke web-based FY 2019/20 This is expected to improve
online reporting Road Maintenance Management management and reporting
and Monitoring System (RMMS) on URF business processes;
to form an interface between and to improve planning,
URF and its DAs. reporting and accountability
among DAs
4 Acquire • Progress construction works for FY 2020/21 Construction of office
permanent a 12-storey building. – 2022/23 building is progressing and
premises for the physical progress was at 57%
Fund at end of July 2020.
5 Build and enhance • Support and monitor FY 2020/21 Support and monitoring of
partnerships functionality of DRCs – 2023/24 functionality of DRCs was
to strengthen • Establish partnerships rolled out starting with
oversight in the with various categories of districts that were deemed
utilisation of road stakeholders most critical
maintenance • Build synergies with oversight
funds functions resident in DAs/ other
government institutions
6 Establish a road • Coordinate with key sector FY 2020/21 2019 Road User Satisfaction
users forum institutions to establish the road – 2024/25 Survey (RUSS) which was the
and undertake users forum 7th RUSS done in Uganda and
periodic road • Undertake periodic road user the 3rd RUSS to be undertaken
user satisfaction satisfaction surveys and track by URF was completed. A
surveys improvements, perceptions and report was produced and
draw lessons disseminated to stakeholders.
• The survey provides
a mechanism through
which road users provide
feedback to road agencies
on the quality of road
services they provide.
• Results of the survey
indicated that the
percentage of satisfied
road users more than
doubled from 27.2% in
2017 to 57% in 2019.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
111

9.4 CHALLENGES AND PROPOSED MITIGATION MEASURES

The key challenges experienced during the period include:

1) Inadequate funding for road maintenance which has fundamentally reduced periodic
maintenance and driven backlog build-up. The approved road maintenance budget for
FY 2019/20 (UGX 448.833bn) constituted 0.36% of Uganda’s GDP (UGX 126,258bn), well
below the minimum recommended of 0.85%.

In mitigation, URF will continue pursuance of increased parliamentary appropriations


towards road maintenance in order to protect the road asset and check backlog build-
up. Side by side, the quest for empowering URF to a truly second generation (2G) Fund
will continue.

2) Failure to commercialise roads management to entrench market principles all through the
management cycle to save and protect asset value and ensure significant gains for road
users. This is occasioned by parliamentary appropriations based on normal budgetary
allocations which are not related to road usage and condition as envisaged in the URF
founding Act.

In mitigation, URF continues to engage stakeholders to agitate for completion of sector


reforms one of whose cardinal objectives was to commercialise roads management by
moving roads out of the general consolidated fund arena into to market driven ‘user
pays’ principle.

3) Lack of precise real-time knowledge on size and state of the road asset which clouds
planning and budgeting, more seriously dampening ability of URF to accurately evaluate
the programmes of DAs.

In mitigation, URF will plans to establish an on-line based road maintenance


management and monitoring system which will enable real time consolidation of work
plans, accountabilities, as well as data collection on road inventories and condition.

4) Weak institutional capacities of DUCAR agencies especially in planning, management,


reporting, and accountability which has resulted into poor maintenance practices,
accumulation of backlog, and low absorption by DAs.

In mitigation, URF is incrementally rolling out TSUs and it will continue to work with
other government entities in addressing the various forms of capacity gaps in DUCAR
agencies.

5) Procurement delays hampering the implementation of road maintenance programmes


and absorption of funds.

In mitigation, URF will continue coordination with other government entities in


addressing the underlying issues in delays to procurements.
112 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

District equipment at
Ngora District yard
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
113

10.0 PERFORMANCE OF LOCAL GOVERNMENTS – VOTE 500

10.1 RURAL TRANSPORT INFRASTRUCTURE PROJECTS

The rural Transport Infrastructures (RTI) is implemented by the Ministry of Works and
Transport. It is a continuation of 15 years of Danish support to Uganda Road Sector Programme
(RSPS) and Rural ROAD Programme (RRP).

10.2 LOCATION OF PROJECTS UNDERTAKEN IN THE FINANCIAL YEAR 2019/20

The districts in which projects were undertaken in the financial 2019/20 were 24 namely;
Katakwi, Kumi, Lira, Soroti, Amuria, Oyam, Dokolo, Bukedea, kole, Kwania, Kapelebyong,
Alebtong, Serere, Ngora, Kitgum, Apac, Kaberamaido, Nwoya, Pader, Amolatar, Lamwo, Am-
uru, Kalaki, Otuke, Omoro, Agago and Gulu.

10.3 FINANCIAL PERFORMANCE

• Approved was UGX 10,908,810,129/=


• Funds released were UGX 10,908,810,129/=
• Percentage release 100%
• Percentage utilised 99%

10.4 PHYSICAL PERFORMANCE OF RURAL TRANSPORT INFRASTRUCTURE PROJECTS


IN FY 2019/20

Table 71: showing the physical performance of the RTI projects in FY 2019/20

Sn District Road/Bridge/CAS Target in Progress at Remarks


intervention FY2019/20 end of June
2020
1 Katakwi LCS of Alleles- Omodoi- 1.3 km 100% Completed
Aderet Road
Section 4
2 Kumi LCS of Kanyum-Atutue- 0.7 km 100% Completed
Malera rd
3 Lira LCS of Odokomit-University 1.2 km 100% Completed
Rd
4 Soroti LCS-Lira Rd-Kamuda Aboket 1.0 km 100% Completed
Road
5 Amuria 1)Completion of LCS of 0.3 km 100% Completed
District Office access road
and Dainage works
6 Oyam LCS of Alidi- Awangi Rd 1.7 km 100% Completed

7 Dokolo LCS of Acandyang Oturu Rd 1.2km 100% Completed

8 Bukedea LCS of Kidongole- Bukedea- 1.1 km 100% Completed


Kabarwa road
114 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

9 Alebtong LCS of kaguta avenue 0.6 km 100% Completed

10 Serere LCS of kamoda- kasilo Rd 0.75km


section
11 Ngora 1) LCS of mukura 0.6km 100% Completed
-Ngora Road
2) Maintenance of 1.85km 100% Completed
mukura -Ngora
Road
12 Kole 1) LCS Construction of 0.7km 100% Completed
Access Roads within
the District HQ
2) Rehabilitation of 38 km 100% Completed
Akalo Adwilia Rd
13 Kwania LC S of Aduku- Apire Rd 0.6 km 100% Completed

14 Kapelebyong Stone pitching of Tc Roads 0 100% Completed


15 Kitgum LCS of Awuch-Lanyandang 1.3km 100% Completed
Road section 7
16 Apac LCS of Aleng-Kungu Road 0.3km sealed 100% Achieved
section 1
17 Kaberamaido LCS of Kaberamaido-Kalaki 0.6km sealed 100% Achieved
road Section 1
18 Nwoya LCS of Anaka TC-Amuru TC 1.0km !00% Achieved
road Section 4
19 Pader LCS of Pader TC-Moro-Adet 0.4km sealed 100% Achieved
road
20 Amolatar LCS of Cr. Bangladesh- 0.9km sealed 100% Achieved
Landing Site
21 Lamwo LCS of Fr. Simon-Palago road 1.3km 100% Achieved
section 2
22 Amuru LCS of Yoweri-Kaguta-Pabro 0.8km 100% Achieved
road
23 Kalaki LCS of Kalaki-Otubata- 0.6km 100% Completed
Kaberamaido road
24 Otuke LCS of Ogoro road (0.6km) 1.0 km 100% Completed
and RDC Road (0.4km)
25 Omoro LCS of Apit-Awoo road 0.5km 100% Achieved
section 3
26 Agago LCS of Lukol-Lawuch road 0.5km sealed 0.6km sealed Excellent
with surface performance
dressing
27 Gulu Rehabilitation of Angululu- Culvert Rehabilitation of The planned
Acholi inn road construction Angululu-Acholi target
road

Total Low 23km


Cost seal
roads
completed
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
115

Fareway junction
116 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

11.0 PERFORMANCE OF KAMPALA CAPITAL CITY AUTHORITY

11.1 FINANCIAL PERFORMANCE

Table 1.1 shows the financial performance of KCCA under the Directorate of Engineering and
Technical Services (DETS) for FY 2019/20 for Transport Sector projects and programmes. The
budget release for FY 2019/20 was 100 % of the approved budget.

The total GOU released funds as at June 2020 was UGX 96.8bn against a budget of UGX
96.8bn, which is 100% of the budgeted funds released. Of the UGX 96.8bn released a total of
UGX 48.1bn was specifically for roads construction.

The total URF released funds as at June 2020 were UGX 31.9bn against a budget of UGX
31.9bn which is 100% of the budgeted funds.
Table 72: KCCA Financial Performance for FY 2019/2020

DIRECTORATE OF ENGINEERING AND TECHNICAL SERVICES BUDGET ABSORPTION REPORT JULY- JUNE FOR FY 2019/20

DESCRIPTION OF EXPENDITURE ITEM BUDGET TOTAL WARRANTS TOTAL EXPENDITURE BALANCE ON Budget Vs Releases Vs
WARRANT Releases Expenditure

    Q1,Q2,Q3,Q4 Q1,Q2,Q3,Q4      
DETS-Operations Mechanical
DETS-MV Repairs and Maintenance- 1,500,000,000 1,500,000,000 1,494,076,463 5,923,537 100% 100%
Road Equipment
Maintenance and Repairs of Street 900,000,000 900,000,000 900,000,000 5,923,537 100% 100%
Lights and traffic lights
Sub-Total 2,400,000,000 2,400,000,000 2,394,076,463 11,847,074 100% 100%
DETS- Casuals 300,000,000 300,000,000 300,000,000 - 100% 100%

DETS- Casuals 800,000,000 800,000,000 800,000,000 - 100% 100%


Sub-Total 1,100,000,000 1,100,000,000 1,100,000,000 - 100% 100%
Road Constructions
DETS-Roads Constructions- Engineering 4,500,000,000 4,500,000,000 4,438,552,449 61,447,551 100% 99%
Designs and Consultancies
DETS-RAP Costs KIIDP 2 8,730,000,000 8,730,000,000 8,682,816,544 47,183,456 100% 99%
DETS-Roads Constructions 48,130,287,224 48,130,287,223 48,078,853,568 51,433,655 100% 100%
Sub-Total 61,360,287,224 61,360,287,223 61,200,222,561 160,064,662 100% 100%
DETS TOTAL 64,860,287,224 64,860,287,223 64,694,299,024 165,988,199 100% 100%
UGANDA ROAD FUND -

Transport studies-Research in 400,000,000 400,000,000 400,000,000 - 100% 100%


alternative technologies
Quality control testing 250,000,000 250,000,000 250,000,000 - 100% 100%

COSTS FOR SUPERVISION OF 200,000,000 200,000,000 200,000,000 - 100% 100%


SELECTED ENGINEERING WORKS
UNDER URF
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

Hired Labour -Casuals 732,000,000 732,000,000 721,779,740 10,220,260 100% 99%


Supervision / Administration costs 100,000,000 100,000,000 98,740,000 1,260,000 100% 99%
117

roads
DESCRIPTION OF EXPENDITURE ITEM BUDGET TOTAL WARRANTS TOTAL EXPENDITURE BALANCE ON Budget Vs Releases Vs
WARRANT Releases Expenditure
118

Professional Bodies subscription 50,000,000 50,000,000 45,589,277 4,410,723 100% 91%


Professional training for Engineers 80,000,000 80,000,000 67,436,000 12,564,000 100% 84%
Tools & equipment 120,000,000 120,000,000 119,805,800 194,200 100% 100%
Safety signs & protective wear 210,000,000 210,000,000 210,000,000 - 100% 100%
FY2019/20

Fuel & Lubricants 1,050,000,000 1,050,000,000 1,049,934,388 65,612 100% 100%


Maintenance of equipment 1,000,000,000 1,000,000,000 987,374,305 12,625,695 100% 99%
Bridge Maintenance 266,000,000 266,000,000 266,000,000 - 100% 100%
Road elements repair through 13,413,216,423 13,413,216,423 13,228,535,090 184,681,333 100% 99%
framework-Road elements repair
through framework - Kawempe-Road
elements repair through framework -
Lubaga, Makindye, Central Nakawa.
ANNUAL SECTOR PERFORMANCE REPORT

Maintenance of street lights and traffic 1,000,000,000 1,000,000,000 985,392,760 14,607,240 100% 99%
junctions
Road marking and Road Furniture-Road safety & Traffic management works 1,298,400,001 1,599,999 100%

1,300,000,000 100%

1,300,000,000
Purchase of new light equipment 734,000,000 734,000,000 734,000,000 - 100% 100%
Asphalt -concrete Stone- base- Road 11,063,160,749 11,063,160,749 11,090,031,010 (26,870,261) 100% 100%
aggregate-Hardcore-Quarry dust
Cement Safety signs & protective wear
Extra Funding for the Kyanja yard-
Murram-Tack Coat K160-Emulsion
Primer-Sand-Bitumen -Periodic
Maintenance

URF TOTAL 31,968,377,172 31,968,377,172 31,753,018,371 215,358,801 100% 99%


KIIDP 2 TOTAL 224,230,000,000 97,764,846,667 92,952,810,418 4,812,036,249 44% 95%
GRAND TOTAL 321,058,664,396 194,593,511,062 189,400,127,813 5,193,383,249 61% 97%
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
119

11.2 PHYSICAL PERFORMANCE

11.2.1 PERFORMANCE ON THE GOLDEN INDICATORS

KCCA contributes towards the performance of mainly two golden indicators i.e. Paved roads
and travel time within GKMA.

Kampala City comprises 2,110km of roads of which 623km is paved and 1487km is unpaved.
These figures were derived from a study commissioned by KCCA in 2013 to undertake a roads
inventory and conditions assessment, which established an accurate database/inventory of
all road infrastructure within KCCA area of jurisdiction and its condition.

i) In the period June 2019 to June 2020 only 10.05km of roads was completed under GOU
funding. These included NMT Pilot Corridor (Namirembe-Luwum-1.5Km), Munaku
Road-0.8Km, Sebatendera-0.6Km Nsambya-Katwe-0.9Km, Kevina-1.2Km, Jjuko-
1.3Km, Kirombe Road-1.2Km, Queensway-1.6Km, Kalema Road-0.4Km, Lakedrive-
1.8Km, Naguru Hill Rise- 0.5Km
The travel time in Kampala is 4.1 minutes /km. which translates to 14.6Km/hr compared to
4.2minutes/km in FY 2017/18.

11.2.2 ROADS IMPROVEMENT

In the FY2019/20 KCCA did not sign any new contracts for new road upgrading/reconstruction
works. This is because there were ongoing multiyear contracts that were signed at the end of
FY2016/2017 and these have been running over last three financial years under GOU funding
and have now been completed. These contracts involved upgrading and reconstruction of
selected city roads totaling 44.85Km.

Road improvement works under ongoing contracts in the reporting period FY 2019/2020
had the following roads and have now been completed:

Table 73: Road improvement works under ongoing contracts in the reporting period FY
2019/2020

No. Road Name Division Length (Km) Intervention Status


1 NMT Pilot Corridor Central 1.5km Reconstruction Completed
(Namirembe-Luwum)
2 Munaku Road Lubaga 0.8Km Upgrading to paved standard Completed
3 Nsambya-Katwe- Makindye 0.95km Upgrading to paved standard Completed
4 Kevina Makindye 1.2km Upgrading to paved standard Completed
5 Jjuko Makindye 1.3km Upgrading to paved standard Completed
6 Kirombe Road Makindye 2.1Km Upgrading to paved standard Completed
7 Queensway Makindye 1.6Km Reconstruction Completed
8 Sebatendera Road Kawempe 0.6Km Upgrading to paved standard Completed
9 Kalema Road Nakawa 0.5Km Upgrading to paved standard Completed
10 Naguru Hill Rise Nakawa 0.5Km Upgrading to paved standard Completed
11 Lake Drive road Nakawa 1.8Km Upgrading to paved standard Completed

The road works under these contracts are all completed. The progress on the various ongoing
roads contracts is summarized in Table 74;
Table 74: Status of Ongoing Road Projects
120

Item Total Contractor and Commencement Duration Completion Progress as at June Progress to date
No. Length Contract Sum Date (Months) Date 2019 and Remarks
Contract Name
Km)
Roads Contracts (GOU Funding)
FY2019/20

1 Lot-1; Design update and construction of 5.4 M/s. Stirling 16th June 2016 36 Months 28th Febru- All roads were All roads
roads in the City-; Reconstruction and/or Civil Engineer- ary 2020 completed except completed and
Upgrading of roads in Central Division. ing Ltd Namirembe-Luwum works under
Street Defects Liability
a) NMT pilot corridor Namirembe-Lu- Period
wuum-1.5km,
b) Archer-0.75km,
c) Mengo hill-0.75km, Overall progress was
d) Nakivubo channel-0.5km, at 89%.
ANNUAL SECTOR PERFORMANCE REPORT

e) Mpabaana-0.75km,
Contract Sum
f) Luzige-0.3km ,
g) Mutebi-0.45km, UGX
Semugooma-0.4km
29,965,137,084

2 Lot-2; Design update and construction of 16.10 M/s. Energo 17th June 2016 36 Months 17th Decem- Works had been sub- All roads
roads in the City; Reconstruction and/or Projekt Nisko- ber 2019 stantially completed completed and
Upgrading of roads in Lubaga and Kawempe gradnja A.D on all roads except works under
Division Munaku Road Defects Liability
Period
a) Jakaana -0.65km,
b) Nsooba-0.75km,
c) Kafeero-0.8km, Overall progress was
d) Lumasi-0.55km, at 86%.
e) Muganzi-Awongera-1.6km,
Contract Sum
f) Waligo- 4.2km
g) Lungujja road-1.6km, UGX
h) Nakibinge-Bawalakata-2.9km,
i) Mackay-1.6km
j) Sembera-1.5km, 65,510,289,035
k) Concrete Box Culvert at Nalukolongo
Channel
l) Munaku Road-0.8Km
m) Sebatendera Road 0.6Km
3 Lot-3; Design update and construction of 7.35 M/s. Abubak- 13th June 2016 36 Months 20th June Works were complete Works are
roads in the City; Reconstruction and/or er Technical 2020 on Kulekana and Kev- ongoing on Ns-
Upgrading of roads in Makindye division Services and ina Road. ambya –Katwe
General Sup- road, Appas
a) Kulekana-2.1km, plies Ltd road and Juuko
b) Nsambya-Katwe-0.95km, Road.
c) Jjuko-1.3km, Contract Sum: Works were ongoing
d) Kevina-1.2km, on
e) Appas-1.3km UGX
f) Kirombe Road-2.1km Nsambya –Katwe Overall, physi-
road, Appas road cal progress is at
38,463,800,967 64%.
and Juuko Road.

Overall, physical prog-


ress was at
64%.

4 Lot-4; Design update and construction of 12.15 M/s. Stirling Wednesday 8th 16th Decem- Works had been sub- All roads com-
roads in the City; Reconstruction and/or Civil Engineer- June 2016 ber 2019 stantially pleted and
Upgrading of roads in Nakawa Division ing Ltd works under
complete on all Defects Liability
a) Magambo-0.9km, Period
b) Dembe-Kilowoza-3.0km, roads.
c) Kiziri-0.75km, Contract Sum:
d) Kigoowa-1.9km,
e) Kimera-1.4km, UGX
Overall physical prog-
f) Kisalita-0.7km,
ress was at 96%
g) Kisosonkole-1.0km, and
34,784,061,713
h) Robert Mugabe-1.8km

Road Contracts under URF

5 Extended periodic maintenance of Park lane 0.5 Kiru General 16th April 2020 4Months Works are ongo-
road-0.5km, in Central Division Services ing and overall
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

16th August progress stands


Contract 2020 at 85%.
sum UGX
2,799,943,902
121
122 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Table 75: Transport Planning Projects

PROJECT FUNDING STATUS REMARKS

Signalization of Ben Works involved traffic Signalisation of the Works were completed
Kiwanuka/Luwum street Ben Kiwanuka/Luwum street junction as by 20th July 2020.
junction GoU part of the Non-Motorised transport Project

KCCA projects under the Kampala Institutional Infrastructure Development Project (KIIDP)
with funding from the World Bank. The Government of the Republic of Uganda received a
Credit from the International Development Association (IDA) -Cr. 4367-UG, to implement the
Kampala Institutional and Development Infrastructure Development Programme Phase-2
(KIIDP2) through KCCA. In this period, KCCA continued with implementation of signed
contracts for execution of the following road works under KIIDP. A tender for reconstruction
and upgrading of several roads in the city using funds from the World Bank was awarded
which has a component of installation of traffic signals at thirteen (13) locations and works
commenced in May 2019.

The Batch-2 roads subproject is divided into three lots. The details of the respective contracts
signed for the civil works are as highlighted in Table 76 below.

This tender has the following Lots:

i) Lot 1: Upgrading to paved of 5.52Km, Reconstruction and dualling of 4.25Km roads


including signalisation of 10 junctions in Nakawa and Central Divisions Batch 2A-
Awarded to Contractor M/S China State Construction Engineering Corporation
Limited,

ii) Lot 2: Upgrading to paved standard of Kabuusu – Bunamwaya - Lweza Road (8.06Km)
- Awarded to Contractor M/S China State Construction Engineering Corporation
Limited,

iii) Lot 3: Recycling and Overlay of Lukuli Road (7.71Km) including signalisation of Lukuli/
Namasoole/Kayembe junction- awarded to: M/s Stirling -Sobetra Joint Venture.
Table 76: Details of the Batch 2 Civil Works Contracts

Contractual Dates Original Revised


Current
Total Total % time
Lot Contractor Name of Contract Original Revised days – June
Signature Commencement Duration Project Project elapsed
Completion Completion 2020
days days

Upgrading to Paved Stan-


dards of Kulambiro Ring
Road (4.82km) including
a spur to Najjera (0.7km),
M/S China State Reconstruction and Du-
Construction alling of Nakawa-Ntinda 21st 18th
25th March 18
Lot 1 Engineering Road (2.80km) (including 22nd May 2019 November February 550 639 406 68.4
2019 months
Corporation Ltd. signalization of four Junc- 2020 2021
(CSCEC) tions) and Reconstruction
and Widening of Acacia
Road (1.45km) (including
signalization of six Junc-
tions)

Under
review.
Contractor
M/S China State
Upgrading to Paved Stan- has
Construction
dard of Kabusu – Bu- 28th March 15 16th August requested
Lot 2 Engineering 17th May 2019 458 N/A 410 89.5
namwaya - Lweza Road 2019 months 2020 for
Corporation Ltd.
(8.06km) extension
(CSCEC)
up to 31st
December
2020

Recycling and Overlay


Stirling Civil 5
of Lukuli Road (7.71Km) 31st
Engineering 25th March 15 12th August
Lot 3 including Signalization 13th May 2019 December 458 599 415 74.5
Limited/Sobetra 2019 months 2020
of Lukuli /Namasoole / 2020
Joint Venture
Kayemba Junction
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
123

5 EoT approved by CC during their 432th sitting on 12th June 2020 and was submitted to the Bank and now waiting for their No Objection
124 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

KCCA also engaged and signed contracts with M/s C. Lotti & Associati Società Di Ingegneria
SpA of Italy in association with UB Consulting Engineers Ltd of Uganda) to provide the
following services:

Table 77: Details of the Batch 2 Service Contracts

Lot Name of Contract Contractual Dates


Signature Commencement Duration Completion
Lot 1 Consultancy Services for Design 8 November
th
17 December
th
33 months 21st
Review and Construction 2018 2018 including November
Supervision for Upgrading to Defects 2021
Paved Standards of 5.52 Km Liability
of Road, Reconstruction and Period (DLP)
Dualling of 4.25 Km of Road
including signalization of 10
Junctions in Nakawa and Central
Divisions

Lot 2&3 Consultancy Services for Design 28th March 17th December 30 months 16th August
Review and Construction 2019 2018 including DLP 2021
Supervision for Upgrading to
Paved Standards of 8.5 Km of
Kabuusu - Kitebi - Bunamwaya
Link under Lot 2 and Recycle
and Overlay of 7.8 Km, including
signalization of 1 Junction
of Lukuli Road in Makindye
Division

In addition, KCCA and JICA are in advanced stages of commencing a project for signalization
of thirty (30) more junctions in the city and construction of a traffic control center. This
project is expected to start in December 2020.

11.2.3 STREET LIGHTS

In the FY2019/20 a total of UGX 1.9 billion was allocated for maintenance and repair of street
and traffic lighting. As at end of June 2020, UGX 1.9 billion had been released and UGX
1.89Bn was spent on the maintenance and repairs for street and traffic lights. The streets
where lights were installed are in the Table 78:

Table 78: New Street Lights Installations for FY 2019/20

SN Road Name No of lights installed Lighting Technology


1 Allen road 13 LED
2 Nakasero market 31 LED
3 Nakasero road 11 LED
4 Bukoto street 14 LED
5 Ben Kiwanuka street 19 LED
6 Namirembe road-NMT 50 LED
7 William Kalema road 26 LED
8 Fort road 14 LED
9 Kisenyi road 10 Sodium Vapour
10 Katwe road 9 LED
11 Kamwokya slums 10 Solar
12 Muwafu road 9 Mercury Vapour
13 Naguru road 4 LED
TOTAL 220
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
125

11.3 CHALLENGES AND MITIGATIONS

i. Disruption of works due to the government restrictions imposed following the out-
break of the COVID-19 pandemic, as the Contractors had to suspend works for some
period after the partial lockdown directed by the President of Uganda. They subse-
quently declared a force majeure event as a result.
ii. Dilapidated Road Network. Most of the roads need overhaul as they have outlived
their existence and the road repairs tend to be too costly and serve little or no value
as new potholes continue to develop.
iii. Limited capacity of Road Network: The road network in Kampala has limited capacity
and was not built for the high volume traffic of recent years that has contributed to
severe congestion.
iv. Lack of adequate road reserves: Most roads are unplanned and lack adequate rights
of way for improvement. This makes road improvements very costly as the required
geometrical designs cannot be achieved without significant resettlement and acquisi-
tion of rights of way.
v. Lack of safe NMT facilities: Although most trips are pedestrian, there is a lack of pe-
destrian facilities on most roads. In many cases pedestrians are forced to share car-
riageways with vehicles exposing themselves to accidents. Provision of walkways and
cycle paths is hampered by lack or right of way and limited funding.
vi. Lack of an integrated and affordable public transport system: The public transport
system is fragmented and dominated by low capacity minibuses and boda bodas. A
mass transit system is needed to serve as the back bone of the transport system in
Kampala.
vii. Under Funding: The combined funds available to road construction from Govern-
ment allocations and KCCA’s own resources are insufficient to finance needed infra-
structure improvements that address the continuous growth of traffic in Kampala,
notwithstanding the current traffic problems in the city.
126 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Uganda airline A330


leaving the hanger
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
127

12.0 PERFORMANCE OF UGANDA NATIONAL AIRLINES


COMPANY

12.1 FINANCIAL PERFORMANCE

Government of Uganda through MoWT appropriated UGX 558.32 billion to the Uganda
National Airline project, UGX 525.49 billion was received (94.1%) and spend by the end of the
financial year. USD 53.6784 million approximately UGX 199.41 billion was to complete the
pre-delivery payments on the two Airbus A330-800neos, USD 41.5 million approximately
UGX 154.01 billion to Bombardier to pay for the last batch of the two CRJ-900 aircraft, USD
20 million approximately UGX 74.3 billion as refund to the operational funds that were used
to pay the initial Airbus prep-delivery payments and UGX 19.7 billion as part of the GOU
funds to capitalize the Airline.

In addition to the above, the Government has committed to release a total amount of UGX
112.5 billion in batches of UGX 28.125 billion as subvention expenditures towards the compa-
ny’s capitalization.

All pre-delivery payments to Airbus were made, the final payments to Bombardier were
made and the two CRJ -900 Aircraft were delivered in October 2019.

As at end of the financial year UGX 32.825 billion relating to Airline’s capitalization had not
been received.

12.2 PHYSICAL PERFORMANCE

Prior to the two aircraft delivered in October 2019 making the total fleet of four Aircraft, the
first batch of two CRJ900 Aircraft had been delivered in April 2018 and payments were fully
made

Pre-inspection team from the sector in Canada


128 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

CRJ-900 aircraft ready for delivery.

Eight regional routes have been opened and finished in Somalia, Juba, Nairobi, Dar es Salaam,
Bujumbura, Kilimanjaro, Mombasa and Zanzibar. Staff were recruited and currently they are
operational.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
129

The airline has been realizing the increasing trends of passengers and revenues before
Covid-19. From January 2020 till closure of commercial operations in Mach 2020, the Airline
was realizing reduction in passenger numbers and as a result of Covid-19.

Table 79: Showing Monthly Passenger Numbers and Number of flights

Month No Flights Passenger Numbers Revenue

Aug-19 32 375 170,216,080.


Sep-19 300 5,892 1,572,715,309
Oct-19 341 9,618 2,533,027,261
Nov-19 413 11,614 3,556,586,218
Dec-19 433 15,656 7,365,830,994
Jan-20 427 12,495 4,768,840,288
Feb-20 440 12,631 3,827,819,400
Mar-20 476 9,074 2,873,387,667
Total 2,862 77,355 26,668,423,217

Figure 14: Analysing Monthly Passenger Numbers

Government through Ministry of Works and Transport also made all agreed pre delivery
payment for two Airbuses for the National Airline which are expected to be delivered in
December 2020 and January 2021 respectively
130 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

12.3 FUTURE PLANS

The Airline plan to do the following in the near future

• Implement the Airlines core systems; that is the Enterprise Resource Planning system
and the Passenger Service System.
• Take delivery of the two A330-800 Neo Aircraft and launch long haul operations into
China, London, and Dubai.
• Set up a unit for self-handling of the Aircraft at Entebbe International Airport
• Conclude plans to register a local Approved Maintenance Organisation and start
self-maintenance
• Conclude negotiations for slots in all destinations planned for expansion

The plan also includes the identification of opportunities for joint-venture investment in non-
core airline related businesses business class lounges, on-board self-catering, and customer
services at Entebbe airport.

12.4 CHALLENGES AND MITIGATIONS

(a) The COVID 19 affected the operation of the airline which forced the government
shut down of the airport for passengers leaving only the operations of the cargo.
The Airline has not developed its cargo business yet and as such missed out on this
opportunity to carry cargo in and out of the country.
(b) Slow process of designation process of the Airline in the different countries and
destinations of choice that has delayed the launch of other regional routes that are on
the Airline’s plan.
(c) Non-disbursement of the of the Government Budgetary Support as committed and
scheduled that has an impact on the operationalization of the planned activities of
the Airline.
(d) Delayed implementation of approved airline incentives by government especially
those relating to waivers of taxes, charges, the grant of premises for the airline head
office, business class lounge and the grant of land for building hangars, catering units
and other complimentary services.
(e) Delayed activation of the Airline in the Global Distribution systems which makes the
Airline not visible by the Global Travel agents hence missed possible sales. This also
makes the indirect access the Company goes through using its Interline Partner APG
for it to be visible costly as this comes with an additional cost of Euro 30 per ticket sold
through this channel.
(f) High operating costs through third party service providers of inflight catering,
handling services at Entebbe and Aircraft maintenance services which make the
operation costly.
(g) Inability to activate code share and full interline partnerships with legacy Airlines
because the Airline is not yet IOSA certified. This limits the additional revenues that
could come from such partnerships.
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
131

Annexs

Taxiway on Runway 12/30


132 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

1
Annex 1
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
133

2
134 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

3
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
135

4
136 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

5
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
137

6

138 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

7


ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
139

8
140 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

9
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
141

10


142 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

11


ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
143

12
144 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

13
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
145

14
146 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

15
Annex 2

PROGRESS ON THE CONSTRUCTION OF THE MAJOR SELECTED BRIDGES

SN Bridge District Progress Progress in FY Progress in Annual perfor- Comment


2018/19 FY 2019/20 mance(%Increase)
in FY 2017/18
1 Gem Farm Bridge Amuru 0% 90% 100% 10% Construction works
completed.
2 Bambala Bridge Kakumiro 0% 90% 99% 9% Project handed over.
3 Kisaigi Bridge Kyankwanzi 0% 80% 99% 19% Contract under DLP
4 Kabindula Bridge Kyankwanzi 0% 75% 95% 20% Contract under DLP
5 Kangai Bridge Dokolo 0% 55% 70% 15% Construction ongoing
6 Wangobo-Nsonkwe-Na- Iganga 0% 45% 83% 38% Construction ongoing
munyumya swamp
crossing
7 Muzizi Bridge Mubende 0% 25% 25% 0% Works have just
commenced.
8 Amodo Swamp Dokolo 0% 5% 5% 0% Construction ongoing
9 Kabahuna Bridge Kibale 0% 70% 98% 28% Construction ongoing
10 Aleles Bridge Pallisa n/a n/a 8.3% 8.3% Construction ongoing
11 Buhindagye Bridge Ibanda n/a n/a 90% 90% Main structure
completed.
12 Kyabahanga Bridge Rukungiri n/a n/a 70% 70% Construction ongoing

13 Bulandi-Gyra (Sezibwa Kayunga/ n/a n/a 25% 25% Construction ongoing


swamp) Nakasongola

14 Ojonai Bridge Amuria n/a n/a 100% 100% Construction works


completed.
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
147
148 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Annex 3

The progress on the Bridges under procurement, Handed over to contractor and feasibility
/study/designs

Sn Bridge Name District Status at end June2020


1 Bunyitsa Balambuli Designed

2 kambuga Kanungu Designed

3 Kafu Masindi Designed


4 Kishuro Isingiro Designed

5 Kahompo Kyenjojo Designed

6 Ayumo Alebtong Designed

7 Mpologoma Namutumba/ Butaleja Designed

8 Bunadasa Bugibuni Sironko Designed

9 Kagera Designed

10 Ongino Tisai Designed

11 NakadidirLukolwe- Designed
Namuganga swamp crossing

12 NyahukaMirambi Designed

13 Komorotot Designed

14 Mutti-Gwa Kirevu Designed

15 Rwammable swamp crossing Designed

16 Karujumba Designed

17 Bugibuni-Bunadasa Designed
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
149

Annex 4
Performance of Roads Rehabilitation in FY 2019-2020 by the District Road Units in the
Central

Sn Roads Name Intervention District Planned Achieved Remarks


Length Km Km
1 Zito-Bubwa landing Full gravelling Buikwe 10 10.6 Completed
site

2 Kirasi-Buleragate- Full gravelling Gomba 23 8.6 Completed


Katwe Kanyanya
3 Maddu-kikonoka Full gravelling Gomba 15 7 Completed

4 Bukalagi-Namabeya Full gravelling Gomba 12 13.2 Completed

5 Kankugube- Full gravelling Kasanda 10.5 8.2 Gravelling


Kanamukwiri on-going
6 Kayonjo-Kyayaya Full gravelling Kayunga 12.2 - Gravelling to
(3.2km), Gogwa- start soon
Wantete-Nakatovu-
Bugir (9.0km)

7 Ibanda-Kisaara Full gravelling Kikuube*** 8.8 - Opened &


Mukabara*** shaped

8 Wobulenzi- Full gravelling Luwero* 9 4.5 Graveled


Woluleta*

9 Kyazanga-Bijaba- Full gravelling Lwengo 18 - Gravelling to


Kakoma-Ndagwe start soon

10 Mpamevu- Full gravelling Mukono 3.9 3.9 Remaining


Bulyamuti-Kyabasala headwalls

11 Namaliga-Kimeketa- Full gravelling Mukono 2 2.2 Remaining


Nalubabwe headwalls

12 Gwafu-Kwagalakwe Full gravelling Mukono 1.6 1.6 Completed

13 2nd Street, South Full gravelling Mukono## 0.9 0.9 Completed


A Estate, Kampala
Industrial Business
Park

14 Lumasi-Kituntu Full gravelling Nakaseke 4.2 4 Completed

Total 131.1 64.7

*** Ibanda-Kisara-Mukabara road; Works on this road will not go as planned due to land
related issues that are attracting compensation.
* Wobulenzi-Woluleta was done under the training program
## 2nd Street Road – These were emergency works requested by OPM Corona Virus Taskforce.
Annex 5
PERFORMANCE OF INTERCONECTIVITY PROJECTS IN THE FINANCIAL YEAR 2019/20
150

Physical Prog- Physical Prog- %ge


S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
FY2019/20

001 Kayolo - Kijwala - Kivumbula - Sanje - Manjeri Road Rakai - 11.0 98% 100% 2% Works completed
(11.0km) in Kooki Consticuency, Rakai District Kooki

002 Buyojwa - Lyakisana Road (2.1km), Katoogo - Kamuraba - Rakai 11.5 75% 100% 25% Works completed
Kayunga Road (2.3km), Bwenyege - Runoni Road (4.2km) -Buyamba
and Nsimbo - Kyabalemela Road (2.9km) in Buyamba Con-
sticuency in Rakai District; (Total Length =11.5km)

003 Kyankanda - Bwooga - Kibirya Road (15.0km) in Buhweju Buhweju 15.0 48.0% 100% 52% Works completed
ANNUAL SECTOR PERFORMANCE REPORT

District

004 Nfasha - Kigunguzo - Rwabahondame Road (8.0km) and Rubanda 11.5 50% 95% 45% Works substantially
Kitagata - Mushanje Road (3.5km); Total Length = 11.5km complete

005 Rwesande - Kisoda - Kabatunda - Kitoha - Butswa Road Kasese 13.5 100% 100% 0% Works completed
(7.0km) and Kikonzo - Kinyabwamba - Kihyo - Kithoma
market road (6.5km) in Busongora North Constituency
(Total Length = 13.5km)
006 Kizungu Rise in Nyamwamba division (0.6km), Mariseri Kasese Mu- 8.1 90% 100% 10% Works completed
road in Nyamwamba division (0.5km), Mumbuzi-Basecamp nicipality
road (1.5km), Nyamwamba west road (0.5km), Mumbuzi 2
(0.1km), Nyakasanga Upper (1.0km), Mutanywana road in
Central division (1.8km), Kidodo road (1.2km) and Land fill
road (0.9km) (Total Length =8.1 km)

007 Butungama - Budiba (6.3km) and Makondo - Kanyamukura Ntoroko 12.3 92% 98% 5% Works substantially
(6km); Total Length = 12.3km complete

008 Nagweny Road (4.58km), Nawango Kifayunjwa Road Kamuli 20.28 95% 100% 5% Works completed
(1.2km), Bufasaga Buwoya Butasaga Road (1.9km) and Bu-
nandolo - Buyanda Busuubo - Namaira Buyero - Budaudhi
(4.3km) in Bugabula South and Kisakye - Kazinga - Nan-
sololo - Kisaikye Road (8.3km) in Bugabula North; Total
Length = 20.28km
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change

009 Namanda - Manyanwe - Bubalya Road (3.0km), Muhuyu Butalleja 13.5 95% 100% 5% Works completed
- Binda - Malagha road (3.0km), Busolwe - Busaba road
(4.5km) and Busaba - Budira - Bugumu - Busolwe road
(3.0km); Total length = 13.5km

010 Otimong Road (2.6km), Kongoto Amukaru Road (2.1km), Serere 16.63 98% 100% 2% Works completed
Okulukulun Kagwara Road (1.9km), Olwa Kanungu - Ogan-
gai - Opeduru Road (7.40km) and Nakabira - Atiragato Road
(2.63km); Total Length =16.63km

011 Chebinyiy Kaptum Sundit Road (11.6km) Kween 11.6 35% 95% 60% Works completed.
Challenges with rock
blasting.

012 Akura Health Centre II – Agoro- Atiriglwo- Okwalo Moko Alebtong 9.0 80% 100% 20% Works completed
Market Road (6.9km), J B Odwee Road (1.1km) and Okello
Field Marshall Road (1.0km); Total length = 9.0km

013 Ocen - Olekata - Matailong Road (5.0km) and Nyada Road Amuria 10.0 100% 100% 0% Works completed
(5.0km); Total length = 10.0km

014 Atabu – Alenga Road (8.8km) Dokolo 8.8 95% 100% 5% Works completed

015 Iiri Iri - Nabwal Road (10.0km) Napak 10.0 90% 100% 10% Works completed

016 Bunaseke - Bugiboni Road (2.2km), Buyobo - Logotani - Sironko 10.8 76% 100% 24% Works completed
Soroti (4.0km), Nangooli -Butandiga Road (2.6km) and
Nakayindira Road (2.0km); Total km = 10.8km

017 Kabole - Chebeser Road Section (4.0km), Sirimityo - Amukol Kapchorwa 13.8 70.0% 98.0% 28% Works substantially
- Kapsayik TC (7,1km), Kayeywa - Loch Road (2.7km); Total complete.
length = 13.8km
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

018 Asuret - Magalo Road (6.9km) and Asuret - Atiira Road Soroti 10.3 100% 100% 0% Works completed
(3.4km); Total km=10.3km
151
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
152

019 Bong Cao-Corner Boroboro Road (7.1km), Awiirao Prima- Lira South 20.0 80% 100.0% 20% Works completed
ry School - Otai Village Banya Parish Road Section (3km)
includes Swamp Filling, Abongo Rwot Corner Pajero Road
(4.0Km) including Swamp Raising and Barjwinya - Barobo-
FY2019/20

go - Acwao - Ayago Boarder (5.9km); Total length = 20.0km

020 Anai P/S-Wigweny Road (5.4km), Barpwo - Ongicab Road Lira North 19.6 80% 97.5% 18% Works substantially
Section (4.2km), Aromo T.C - Bapii - Aromo P/S Via Aleka completed. In DLP
Swamp (5.0km), Aromo TC - Bapii - Aromo P/S - including
Aleka swamp crossing (5.0km); Total length = 19.6km

021 Kinyara - Mukangala - Maguniya - Kandaha (4.2km), Mukono 16.8 95% 97.5% 3% Works substantially
Namaziba - Kitovu - Buyizi (2.9km) and Mbogo Road (2.7km) and Buikwe completed. In DLP
ANNUAL SECTOR PERFORMANCE REPORT

in Buikwe District and Kakukulu - Kikube (Nkooko) - Ki-


goloba (7.0km) in Mukono District; Total length = 16.8km

022 Busabala - Kibila - Salama Road (2.1km), Kibila - Kabuuma Wakiso 7.1 80% 90% 10% Works substantially
- Gangu (2.8km), Kibutika II (1.2km), Ndejje - Zaana (1.0km); complete. Had chal-
Total length = 7.1km in Makindye Ssabagabo Municipality lenges with relocation
of service lines.
023 Butanza - Ngabo - Lutembe (4.0km), Lukiizi - Kibaaga - Luwero 26.2 85% 95% 10% Works substantially
Nanywa (6.4km), Kawula - Nalulya (2km), in Katikamu complete
County North and Bugalama - Buyondo - Kamwano - Kan-
juki (4.8km), Bukembya - Buwakibila - Bakijulula (3.2km)
and Kibiike - Gangu - Kiryambidde - Kungu (5.4km); Total
length = 26.2km

024 Buwungilo - Kawuku (4.9km), Buyobe HCII - Bulyankuyege Kayunga 20.3 90% 100% 10% Works completed
(2km), Bulyankuyege - Busolo - Kiyagi (3.6km), Katikamu -
Busaale (1.5km), Katikamu - Namatogonya (1.3km), Bubajjwe
- Nalumuli - Nakaiba - Nakatovu (4.3km), Bwetyaba Kafuge
- Ntooke (2.7km) in Ntenjeru North, Kayunga District; Total
length = 20.3km

025 Rehabilitation of Kawongo - Kitwe - Kalenge - Misozi Road Kayunga 20.5 100% 100% 0% Works completed
(5.4Km), Baale - Kyasande - Kyantala Road (5.0Km), Bu- Baale
lawula - Nawankonge Road (5.1Km), Nsamba Close (0.6km),
Wankya Road (3.1km) and Kavule 2 Road (1.3km) in Baale
Consticuency, Kayunga District; Total length = 20.5km
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change

026 Nsobiiri A Shopping centre to Kalamba Gombolola via Kis- Mpigi 4.9 100% 100% 0% Works completed
unwinu and Kalagala road (4.9km)

027 Ojigo Pakwinyo Emin Pasha Road (5.9 km), Ajibu Thendir Pakwach 11.3 92% 100% 8% Works substantially
Landing Site Road (2.53 km) and Palam Community Road complete.
(2.9 km); Total length = 11.3km

028 Wabusana Lugogo Road (2.83km) and Lugogo Lwenyana Nakason- 10.13 95% 95% 0% Works substantially
Road ( 7.3km); Total length = 10.1km gola complete

029 Streets in Pakele Town (Perina - 0.8km, Drani - 0.7km, Olal - Adjumani 15.23 90% 100% 10% Works completed
0.4km, Rasigala - 0.4km, Alakai - 0.15km, Adikesi - 0.15km, - Adjumani
Koli - 0.15km, Husen - 0.9km, Ingi - 0.4km, Eture - 0.65km, East
Lazaro - 0.65km, Duka - 0.8km, Ereme - 0.3km, Mondia -
0.4km, UNHCR - 0.4km) roads, Army road - 1.6km and Olia
- Tilorio - 5.1km; Total length = 15.23km

030 Tindibakira Road (0.7km), Banyagyi Road (0.95km) and Ntungamo 3.05 95% 95% 0% Works substantially
Kajyinya road (1.4km); Total length = 3.05km complete

031 Olua - Katirina road (5.5km), Cilio road (5.1km), Onai - Arua 20.25 62% 95% 33% Works Substantially
Oluodri road (2.5km), Ozufe road (4.5km) and Liria Ajiraku complete
Road (2.65km); Total length = 20.25km

032 Kyabagyenyi – Kyanda Road (10.8km) in Nyabushozi Kiruhura 23.1 50% 100% 50% Works completed
County and Rwozi I – Banywana Farm – Kabambaija Bright
Heart School (4.0km) and Nyaburunga I Coffee Factory –
Rwemamba TC (8.3km) in Kashonji County; Total length
=23.1km

033 Buyenja – Kashuro – Kyakatugunda TC (10.9km) Mbarara 10.9 98% 100% 2% Works completed
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

034 Kati – Bitereko – Rutokye Road (18.1km) Mitooma 18.1 55% 70% 15% Works ongoing

035 Kinyamashe – R. Kiruruma - Kanyambeho - Katafari Kanungu 12.0 80% 98% 18% Works ongoing
153

(5.0km), Kihihi - Rukarara – Nyanga Road (4.8km) and Kad-


eregye – Kihembe Road (2.1km); Total length = 12.0km
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
154

036 Rwambu - Rwenkuba - Burambira - Kayanja - Rusoro - Ibanda 20.1 50% 97.5% 48% Works substantially
Rwanyakabogo - Kamwiri - Rwenkobwa Road (20.1km) complete

037 Busweka - Naluntuntu Road (5Km) and Kabudubutu - Mubende 10 100% 100% 0% Works completed
Bbinikira Road (5km); Total length = 10.0km
FY2019/20

038 Nyakinombe - Kyewanura - Buyanja road (9.5km) and Off- Lyantonde 9.62 98% 100% 2% Works completed
set road - Lwengo boarder (0.12km); Total length = 9.62km

039 Ruyanga - Kibuba - Kabatangare (13.2km) Isingiro 13.2 95% 100% 5% Works completed

040 Bweza - Busimo - Nvunjwa (4.80km), Minoni - Nawankole Mayuge 20.7 65% 97.5% 33% Works substantially
- Kasokwe (2.90km) and Kyikubo - Ivugunhu Road (1.4km) complete. In DLP
in Bunya East Constituency and Bulubudde - Corner bar -
ANNUAL SECTOR PERFORMANCE REPORT

Bubode Road (11.6km) in Bunya South Consticuency; Total


length = 20.7km

041 Nabiina - Buwabe - Nsozi ibiiri (12.0km) and Kiwanyi - Iganga 35.5 75% 90% 15% Works ongoing
Namusiisi - Bugambo - Bunyokano - Bugongo - Nawandala
(23.30Km) in Iganga District; Total length = 35.5km

042 Kitaleesa - Mwaro - Mukabingo - Nkakwa - Kiterede Road Kyegegwa 11.5 80% 100% 20% Works completed
(11.5Km)
043 Runga - Waaki - Butiaba (19.2km) Hoima 19.2 90% 100% 10% Works completed

044 Katungo - Kyantamba - Muyenje Road (8.0km) in Kiboga Kiboga and 23.9 80% 100% 20% Works completed
District and Lubiri - Cardinal Nsubuga - Kasejere Road Kyankwan-
(10.5km) and Kasejere - Nakakabara P/S (5.41km) in Kyank- zi
wanzi District; Total length = 23.9km

045 Kakumiro - Kinena - Mpanga (7.7km), Kyabashija CoU - Kakumiro 24.7 78% 100% 22% Works completed
Mukasagazi - Bendikito including Kitanda - Irwaniro Road
branch (8.5km) and Kisiita Market - Kyakajoro - Kadandali
(8.5km); Total length = 24.7km

046 Kachuru P/S - Kongoidi Road (1.1km), Kachuru - Komolo Bukedea 21.4 50% 100% 50% Works completed
Road (5.4km) and Amus Sapir - Amus Kireka Road (4.7km) and Kumi
in Bukedea District and Apuda - Isaiah Oonyu road (0.8km),
Atutur - Kalomongole (3.5km), Kakomongole - Bukedea road
(0.8km) and Olupe - Ongerei (5.1km) in Kumi District; Total
length = 21.4km
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change

047 Buluganya - Buhokadala - Bulago Road (10.2km) Bulambuli 10.2 85% 98% 13% Works substantially
- Elgon complete
County
048 Tabagonyi - Logi - Atari Road (9.8Km) Bulambuli 9.8 55.0% 90.0% 35% Works ongoing.
-1 Heavy rains delayed
progress and some in-
stalled culverts were
washed away
049 Gadumire - Nsamule Road (9.2km) in Kaliro District and Kaliro and 22.2 97.5% 97.5% 0% Works substantially
Nawansagwa - Bugobi - Kyabakaire (13.0km) in Namutum- Namutum- complete. In DLP
ba District ba

050 Senda - Mwenge Road (starts Opp Senda P/S) (7.7km), Pas- Tororo 11.8 55% 100% 45% Works completed
aulo - Morikiswa - Namwaya road via Rukuli road (2.0km)
and Atapara - sengo road (2.1Km); Total length=11.80km

051 Mile 9 Off Tarmarc of Mbale Highway - Kamonkoli S/C Budaka 14.8 95% 100% 5% Works completed
Headquarter (4.3km), Namirembe TC - Late Balachi Kiirya
Farm - Hajji Yusuf Road Section (4.9km) and Nabugabo
TC - Kameruka PS terminating into Ikiki Kanghima road
(5.6Km); Total length = 14.8km

052 Bulucheke - Muchomu - Nyende Road (8.4km) Bududa 8.4 50% 50% 0% Works suspended.
Works delayed due
to heavy rains and
the need for blasting
rocks in the road
corridor.

053 Pagirinya - Latodo Road (11.7km) Adjumani 11.7 90% 95% 5% Works substantially
complete. In DLP

054 Ikulwe - Buyemba - Bukatube - Lwanika Landing Site Road Mayuge, 33.3 60% 100% 40% Works completed
(13.3km) and Baitambogwe - Mbilizi - Magunga - Mbaale Luuka and
Road (9.0km) in Mayuge District and Wainya - Bulanga - Jinja
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

Bute - Igeyero Road Section (11.0km) (traversing the districts


of Luuka, Mayuge and Jinja); Total length = 33.3km
155

055 Rehabilitation of Elema - Kalamuka - Mgbili Road Section Adjumani 14.4 0% 48% 48% Progress was slowed
(8.4km), and Eciya - Boroli Central Village (6.0km) in Adju- down by Covid 19 and
mani district; Total Length= 14.4km bad weather
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
156

056 Rehabilitation of Ogini Junction – Awiepek Center Road Alebtong 14.4 0% 68% 68% Works ongoing (grav-
(6.9km), St Monica sign post - Apunga – Ateno (3.5km) and elling, filling & culvert
Anara P/S - Te Oriang (4.0km) in Alebtong district; Total km installation)
FY2019/20

= 14.4km
057 Rehabilitation of Okoboi - Akulony - Acinga Road (9.7km) Amuria 15.3 0% 90% 90% Works ongoing. In-
and Olekat - Matailong Road (5.6km) in Amuria district; stallation of culverts
Total length = 15.3km & end structures in
progress

058 Rehabilitation of Itia -Ogboa Road (10.0km) in Arua district Arua 10 0% 90% 90% Completion expected
within the Contract
Period
ANNUAL SECTOR PERFORMANCE REPORT

059 Rehabilitation of Naboa Kakoli - Kabyonga Road (6.2km), Iki Budaka 16 0% 90% 90% Works substantially
Iki - Petete - Kadenge Road (5.5km), Puwatah - Nyire Road completed. Contractor
(2km) and Asadi - Hamudan (2.3km) in Budaka district; issued with a snag list
Total km = 16.0km to rectify before is-
suance of completion
cert. Cert 1 paid.

060 Rehabilitation of Natoolo - Kikholo - Sakusaku (5.6km) and Bududa 11.1 0% 48% 48% Opened the two
Mabale - Wakamala (5.5km) in Bududa district; Total length roads; gravelling and
= 11.1km drainage works in
progress

061 Rehabilitation of Itoolo Bulidha - Busano - Busakira - Mako- Bugiri 14.7 0% 70% 70% Works ongoing.
ma I Road (14.7km) in Bugiri district Change order adding
another road issued

062 Rehabilitation of Karokogoto - Ahamudara - Kamukaki Buhweju 15 0% 60% 60% Works ongoing.
(5.0km), Bwooga - Kibate (2.0km), Kikondera - Kidandari - Shaping and common
Kanunka (6.0km) and Kidandari - Itorero (2.0km) in Buhwe- excavation in progress
ju district; Total Length = 15.0km
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change

063 Rehabilitation of Mpummude Kiyunga (konko parish) Buikwe 23.38 0% 45% 45% Works ongoing.
Wakisi Division Road (1.95km), Matovu Kidaga (Wakisi Hindered by Covid 19
ward Division) Road (1.2 km), Wankwale Bugoba Health pandemic
Centre II (Kabizi ward) - Nyenga Division Road (5.7km),
Owuma Kaibirwamu Gandege (Nyenga ward Division) Road
(1.2 km), Kaggwa Rd (1.65km), Kafeero Rd (0.6km), Nakawu-
ma Kokoola Road (4.1km), Tukulu Nkompe Katete Road
( 3.65km) and Bulamazi Zinga Road (3.33km) in Buikwe
district; Total length = 23.38km

064 Rehabilitation of Kachaboi - Kawo Swamp Crosisng Road Bukedea 10.6 0% 50% 50% Works ongoing
(2.6km) and Kongatuny - Acabule - Amee - Komelekes
Swamp Crossing (8km) in Bukedea district; Total km =
10.6km

065 Rehabilitation of Bufumbula - Muyembe Road (4.6km), Bulambuli 14.1 0% 65% 65% Works ongoing.
Bukewa - Kidutu Moses Road (6.0km), Shilimi - Joseph Gravelling and drain-
Bukhali Road (3.5km) in Bulambuli district; Total length = age works ongoing.
14.1km Cert 1 being refined

066 Rehabilitation of Kyeizooba - Bugongi (6.1km), Kitagata - Bushenyi 16.5 0% 50% 50% Cert 1 pending
Kabaale (2.1km), Kanyinemuyanga - Mwengura - Rwenye- payment. Culvert
na - Kabuba (5.3km), and Rwentuha P/S - Kyamuzoora P/S installation ongoing.
- Nyamirima P/S (3.0km) in Bushenyi district; Total km = Cluster 3 delayed by
16.5km land challenges.

067 Rehabilitation of Mugunu P/S - Bubalya Road (3.4km), Butaleja 15.1 0% 75% 75% Most of the work has
Namunyagwe Catholic Church - Ali Hasalya - Bunghanga been executed. Cert 1
Road (3km), Busabi P/S - Buwobowo - Habiga (4.5km) and being processed
Mwiha - Kasuleta road (4.2km) in Butaleja district; Total
length = 15.1km

068 Rehabilitation of Masagala - Bunyenye Loop Road (4.3km) Butambala 6.2 0% 80% 80% Gravelling complete.
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

and Buligi Village Road (1.9km) in Butambala district; Total Drainage works ongo-
length = 6.2km ing. Cert 1 paid.
157
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
158

069 Rehabilitation of Gombe – Kinoni – Kwezi – Kabalamba – Butambala, 10 0% 80% 80% Gravelling complete.
Mayombwe – Kalenge (10.0km) in Butambala district Butambala Drainage works
County ongoing. Cert 1 paid.
FY2019/20

070 Rehabilitation of Mushunga - Kayembe - Kashozi (3.8km), Ibanda 14 0% 36% 36% Cert 1 pending
Katengeto - Rushambya Nyabigoye (6.1km) and Bururuma payment
Bridge - Nyabigoye - Kakyere Road (4.1km) in Ibanda dis-
trict; Total length = 14.0km

071 Rehabilitation of Namungalwe - Bulanga - Namukanga Iganga 17.9 0% 85% 85% Works ongoing.
- Nabukone (11.9km), Namusisi P/S - Buganza (2.3km), Addendum 1 worth
ANNUAL SECTOR PERFORMANCE REPORT

Buganza Road - Kiringa Road (1.7km), Buganza Road 126m signed for
(1.0km) and Namusisi CoU - Busabi - Buyonga Road (1.1km) additional works
in Iganga district; Total Length = 17.9km

072 Rehabilitation of Rwenkumba - Mukonomura - Buhara Kabarole 15 0% 75% 75% Cert 1 pending
(5.7km), Mukonomura - Kasindikwa (2.0km), Kasindikwa payment. Gravelling
- Lake Saaka Acess (1.3km), Kyamukube - Hamuzigiti- and culvert
Busoma - Hamabale - Karago (3.0km), and Hakigere - installation ongoing
Kalyango - Canon Apollo (3.0km) in Kabarole district; Total
Length = 15.0km

073 Rehabilitation of Kanyabebe - Kinyarwanda - Bweranyangi Kagadi 12.4 0% 75% 75% Progress hampered
- Rugashari Road (12.4km) in Kagadi district by financial con-
straints. Cert 1 pend-
ing payment

074 Rehabilitation of Kyabazinga - Butongole - Bugodo - Kyani Kaliro 23.9 0% 78% 78% Works ongoing
Road (12.2km), Gadumire - Nasere Road (4.0km), Kisinda - (gravelling and filling
Namuntu Road (4.0km), and Kanabugo - Kabiri Kalalu Road in progress). Cert 1
(3.7km) in Kaliro district; Total length = 23.9km pending payment
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change

075 Rehabilitation of Mailo T/C via Buyugu - Kibuye - Kitega Kaliro 21.3 0% 86% 86% Works on going.
(6.4km), Kitega - Namawa (1.4km), Lwanda - Beeda Naka- - Bulam- Variation I for addi-
longo road (5.5km), Budi - Nantamuli Swamp (3km), Bulike oji North tional works being
T/C - Budeba - Nswamire road (3km), and Nzirakahindi - County processed. Cert 1 paid.
Nswamme Swamp (2km) in Bulamoji North County, Kaliro Cert 2 being pro-
District; Total km = 21.3km cessed

076 Rehabilitation of Nakiwulo - Kitayundwa Road (7.8km), Kamuli Mu- 19.6 0% 50% 50% Works being slowed
Wakalumba - Wako - Buwaiswa Road (3.5km), Buwudha - nicipality down due to financial
Busutwa - Kayabya - Busanga P/s - Bukose - Budhumbula constraints. Cert 1
(4.8km), Kaima - Kirondo - Busubo Zone (3.5km) in Kamuli pending payment
Municipality; Total length = 19.6km

077 Rehabilitation of Nawanyago - Wankole Road (8.40km) Kamuli - 14.6 0% 56% 56% Works ongoing. Cert
including 1.65km swamp raising and Kidali - Bukagena - Buzaaya 1 pending payment
Bugabudyeri (6.2km) in Buzaaya county, Kamuli district; county
Total length = 14.6km

078 Rehabilitation of Kafewo - Kafule - Bulundo P/S - Kyama- Kamuli - 15 0% 50% 50% Works ongoing. Cert
tende Ring Road (15km) in Bugabula North County, Kamuli Bugabula 1 pending payment
district North

079 Rehabilitation of Ragon Road (off Mbale Highway)(3.0Km), Kapchorwa 12.7 0% 62% 62% Works on going
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

Tandikwa Road (off Mbale Highway (2.7km), Katogolo - (gravelling and


Chebonet (4.1km) and Kaptono Road (2.9km) in Kapchorwa drainage works). IPC
district; Total length = 12.7km I submitted and being
159

refined
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
160

080 Rehabilitation of Katoke - Kirongo - Ndughuth West - Mu- Kasese - 20 0% 65% 65% Works ongoing
hambo - Kihindi (10.0km) and Kihyo - Kitoma - Minana - Busongora (gravelling & culvert
Kasaka - Nyanorongo (10.0km) in Busongora North, Kasese North installation). Change
FY2019/20

district; Total length = 20km order I issued. Cert 1


being processed

081 Rehabilitation of Mbabu Road (1.5km), Kanyageya (3.5km), Kasese 14.95 0% 80% 80% Gravelling and
Kyondo (2.3km), Lugoki Road (1.05km), Nsenyi - Mughende culvert installation in
- Kajwenge (4.0km), Kisinga - Mughende (2.1km) and Ngole- progress
randi spur (0.5km) in Kasese district; Total length = 14.95km

082 Rehabilitation of Migongo - Palabul - Kasokwe (9.3km) and Kayun- 17.5 0% 40% 40% Works ongoing.
ANNUAL SECTOR PERFORMANCE REPORT

Namizo- Namavundu B - Kitimbwa Kyetume Road Junction ga - Bbale Progress affected


(8.2km) in Bbale County, Kayunga district; Total length = county by Covid. More fill
17.5km required. Variation 1
being processed. Cert
1 being prepared

083 Rehabilitation of Kayonjo - Nanyuki (3.77km), Kiwangula - Kayunga 23.63 0% 98% 98% Works substantially
Nalumuli - Wajjanzi (3.1km), Ssekajja Muslim P/S - Kitered- - Ntenjeru complete. Change
de (1.6km), Ssekajja Atama Saafi (1.1km), Ssekajja Kagoye County order I issued. Cert 1
(1.45km), Kanjuki Wabusonko (7.85km), Ndeeba Mukasa is pending paymentd
Kyampisi (1.2km), Najjemba Kyampisi Namulanda (0.8 km),
Nabunya Namulanda (0.65 km), Tamale Kagoma Bbaali
(0.55km), Mayanja Nsejere Kalungi (0.6km) and Lugema
Ndeeba C/U P/S (0.96km) in Ntenjeru County, Kayunga
district; Total length = 23.63km

084 Rehabilitation of Nyamiringa - Budimbo Road (11.8km) in Kiboga 11.8 0% 91% 91% Works almost com-
Kiboga district plete. Cert 1 paid. Cert
2 being processed

085 Rehabilitation of Byanamira - Lwozi (5.0km), Muganda Kiruhura 20.6 0% 62% 62% Works ongoing with
Farm - Kashonji P/S (4.3km) and Byazo - Keitanturegye gravelling. Advance
(11.3km) in Kiruhura district; Total length = 20.6km and Cert 1 being pro-
cessed
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change

086 Rehabilitation of Atulinga - Mudi - Ija - Anyau Road Section Koboko 10 0% 81% 81% Works ongoing.
(10.0km) in Koboko district

087 Rehabilitation of Rikitae - Moroto Road (10.6km) in Kotido Kotido 10.6 0% 100% 100% Completion cert is-
district sued. Change Order I
issued. Cert 1 pending
payment.

088 Rehabilitation of Kalungar - Bukedea Road (2.8km), Apapai Kumi 11.4 0% 40% 40% Works ongoing.
- Oswapai Road (2.2km) and Ceele - Oseera - Aduka Road Advance and Cert 1
(6.4km) in Kumi district; Total length = 11.4km being processed

089 Rehabilitation of Kitwala - Namutokwa - Mwangi Road Kyankwan- 11.5 0% 41% 41% Works ongoing
(11.5km) in Kyankwanzi district zi

090 Rehabilitation of Kidindimya P/S – Kayembe – Nyabuliko Kyegegwa 14.4 0% 55% 55% Works ongoing. Cert
– Isemitwe – Kikoboza – Visionary P/S Road (14.4km) in 1 being processed
Kyegegwa district

091 Rehabilitation of Wiodyek - Ayito Road (4.0km), Ayito-Wig- Lira 24.8 0% 80% 80% Works ongoing. End
weng (10.0km), Kulu Omati - Awita - Akolodong Road structures in progress.
(6.0km) and Acanadiro - Adyelowango - Alyanga Road Change order 1 being
(4.8km) in Lira district; Total km = 24.8km processed

092 Rehabilitation of Busanda - Budhuba - Buwutu - Ikumbya Luuka 10 0% 35% 35% Works ongoing. Cert
Road (10.0km) in Luuka district 1 pending payment.
Noted slow Progress
of works due to Covid.

093 Rehabilitation of Kiiya - Kasaala - Bukusu - Ngogolo Luwero 14.9 0% 60% 60% Gravelling in prog-
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

(3.4km), Nakakono - Kyampisi (5.9km) and Kyampisi - ress


Sombwe - Kyambogo (5.6km) in Luwero district; Total km =
14.9km
161
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
162

094 Rehabilitation of Byangiri - Luti - Nanywa T/C Road (7.2km) Lwengo 7.2 0% 45% 45% Works ongoing. Cert
in Lwengo district 1 pending payment
FY2019/20

095 Rehabilitation of Kinuuka - Kyenshama - Kasagama Road Lyantonde 21.4 0% 50% 50% Works ongoing.
(21.4km) in Lyantonde district Contractor expects to
finish works in Q1 if
Cert 1 is paid

096 Rehabilitation of Buwangani - Sikunga Road (4km), Buwan- Manafwa 12.8 0% 45% 45% Two roads have been
gani - Butooto Road (3.0km), and Masaka - Magodes (5.8km) opened; opening of
in Manafwa district; Total length = 12.8km the 3rd road is in
ANNUAL SECTOR PERFORMANCE REPORT

progress

097 Rehabilitation of Wandegeya - Kikandwa - Kayanja Road Mayuge 9.8 0% 40% 40% NFA stopped works
(9.8km) in Mayuge district waiting for environ-
mental clearance.
Need for EoT

098 Rehabilitation of Bulanga - Wainha - Nabalongo Road Mayuge, 30.9 0% 92% 92% Cert 1 pending pay-
(6.9km), Buwerere - Mbirabira - Bufuta - Luubu - Buka- Mayuge ment. Works ongo-
sero - Buseera Road (11.0km), Mukuta-Wagona-Buba- West ing. End structures
bwe-Namusenyu Road (6.5km) and Kyankuzi - Nalwesam- ongoing
bula A - Nalwesambula B - Mukuta Road (6.5km) in Mayuge
district; Total length = 30.9km

099 Rehabilitation of Zigoti T/C – Ssali – Namalele – Nkwale Mityana 9.3 0% 65% 65% Works ongoing. Cert
Road (4.3km) and Nkwale - Namungo Road (5.0km) in Mi- 1 pending payment.
tyana district; Total km = 9.3km

100 Rehabilitation of Loyaraboth - Natgumkale Road (7.5km) in Moroto 7.5 0% 90% 90% Works substantial-
Mororo district ly complete. Cert 1
paid. Cert 2 being
processed. Variation 1
being processed
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change

101 Rehabilitation of Kawongo - Magonga - Kiwafu (5.9km), Mukono 44.4 0% 50% 50% Works ongoing. Cert
Kawuku- kiwafu (2.9km), Kasala - Kasinyinyinya - Lun- 1 pending payment
ya - Masiko (7.5km), Nakayi - Mamese manji - Kawoomya
(2.7km), Nenyodde -Namyooya C/U (2.9km) and Namyoya -
Nabalanga (4.5km), Wabusolo-Kalagala (2.5km) and Kala-
gala-Namugongo(1.6km) Kyambogo - Namuganga(6.9km),
Kyanika - Kyewanise (2.3km), and Kiyagi - Buteyongera
- Kitwe - Kakira (4.7km) in Mukono district; Total length =
44.4km

102 Rehabilitation of Kanana - Kiyaga - Kasana - Kayini P/S Mukono 17.4 0% 80% 80% Gravelling works
(5.5km), Kayini T/C - Kasala - Ndiba - Kiyagi - Ndese T/C completed, end
(6.2km) and Kabimbiri - Nasejobi - Kakukukulu - Kibamba structures being
(5.7km) in Mukono district; Total length = 17.4km constructed.

103 Rehabilitation of Timuna - Lugogo Road (8.0km) and Ki- Nakaseke 9.8 0% 70% 70% Cert 1 pending pay-
kamulo - Kibaale Road (1.8km) in Nakaseke district; Total ment. Cert 2 being
length = 9.8km processed

104 Rehabilitation of Nakitoma - Nabiswera Road (10.4km) in Nakason- 10.4 0% 35% 35% Grading and culvert
Nakasongora district gola installation complete.
Gravelling to
commence

105 Rehabilitation of Nyakasenyi - Masaka Road (9.2km) in Ntoroko 9.2 0% 75% 75% Work on filling and
Ntoroko district culvert installation in
progress

106 Rehabilitation of Masaka - Kyebukungulu Road (7.4km) in Ntoroko, 7.4 0% 85% 85% Gravelling & end
Ntoroko district Ntoroko structures in progress
County

107 Rehabilitation of Majeri - Kivumbula Road (9.1Km), Kamate Rakai - 16.8 0% 30% 30% Works ongoing. 2 out
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

Road (5.0Km) and Kaluluza - kaseese Road (2.7km) in Kooki Kooki of 3 roads fully bush
County, Rakai district; Total length = 16.8km cleared, shaped and
compacted.
163
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change
164

108 Rehabilitation of Rwamunonko-Rwamahungu Road Rakai 18 0% 20% 20% Covid-19 pandemic


(5.6km), Kyabahindura-Kakabagyo S.S Road (4.0km), Kya- -Buyamba related restrictions
bahindura town offset Road (0.3km), Mataara-Kasenge-Ka- hampering progress
FY2019/20

toosi Road (3.0km), Natete - Lwabanda COU - Binoni Road as well.


(3.3km) and Kibingo-Hajji Kasamba Road (1.8km) in Buyam-
ba County, Rakai; Total length = 18km

109 Rehabilitation of Rubona - Kiraaro - Kacwekano Road Rubanda 9.62 0% 10% 10% Works ongoing
(9.62km) in Rubanda district

110 Rehabilitation of Karo - Katobo - Nyabihuku Road (3.95km), Rukungiri 6.59 0% 35% 35% Works ongoing.
ANNUAL SECTOR PERFORMANCE REPORT

Rwakabengo - Nshure Road (1.1km) and Kibimbiri Road


(1.54km) in Rukungiri district; Total length 6.59km

111 Rehabilitation of Kashekure – Kikonkoma – Omukashabo – Rwampara 10.5 0% 56% 56% Shaping and instal-
Kashwojera TC Road (10.5km) in Rwampara district lation of culverts
complete

112 Rehabilitation of Otirono - Ajuba (2.6km), Makai Coners Serere 16.4 0% 43% 43% Works ongoing. De-
- Otekat Road (3.0km), Apapai - Agule (6.2km) and Kabes - layed by Covid
Nyanera (4.6km) in Serere district; Total km = 16.4km

113 Rehabilitation of Walawenji - Mukwana TC Road (2.0km), Tororo 15.5 0% 84% 84% Works ongoing. Cert
Mukwana P/S - Son - Ogwang (2.8km), Mukera - Matindi 1 paid. Cert 2 being
T/C (5.0km), Puwele Lwiza - Kainja (2.2km) and Poyo - Sugu- processed
da (3.5km) in Tororo district; Total length = 15.5km

114 Rehabilitation of Ssempala Kigozi Road (2.1km), Greenlight Wakiso – 13.2 0% 35% 35% Works ongoing
- Ssebowa (0.8km), Philly Bongole Lutaaya Road (1.7km), Makindye though slowed down
Kiziba - Gangu (3.3km), Kanaaba - Ziranumbu (2.1km), Ssabagabo by Covid 19 pandemic
Banalya Road (0.8km), Naume - Mukiibe Road (1.0km) and
Leticia Road (1.4km) in Makindye Ssabagabo, Wakiso dis-
trict; Total km = 13.2km
Physical Prog- Physical Prog- %ge
S/N PROJECT TITLE DISTRICT KM Remarks
ress (June 2019) ress (June 2020) Change

115 Rehabilitation of Kiwamirembe Road (4.5km) in Wakiso Wakiso 4.5 0% 35% 35% Works hindered by
district land challenges

  Total km   1707.0 38% 78% 40%  

647.5 1334.9 687.4


FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT
165
Annex 6
Performance of Rehabilitation of District Roads under the Jinja Road Unit
166

ROAD CULVERTS
SN DISTRICT ROAD NAME OPENED GRADED GRAVELLED REMARKS
LENGTH INSTALLED
FY2019/20

Lambala- Nawangoma-Busand-
1 Kamuli ha-Bulopa-Namwendwa-Nda- 58.22 48.60 56.00 - -
like-Buyende Dist. H/Q

Opening and grading


Bugeywa-Namujenji- 0.6mm 8 culverts,
2   Kamuli 10.5   - -  10.5 works done before
ra-Lubaizi-Bugeywa T/C road 0.9mm 17 culverts
FY2019/20

Namisu T/C in Kagumba SC via 0.6mm 16 culverts,


3   Kamuli 7.3 0.00 7.40 7.4
ANNUAL SECTOR PERFORMANCE REPORT

Nabitalo to Kyamatende 0.9mm 32 culverts

4   Kamuli Additional 10 No. roads 30.70 30.20 22.90 0.35 - Swamps raised, gravelled
Not graveled due to lack
5 Buyende 1. Namulikya-Nabitula-Gwase 11.00 0.00 11.00 - -
of equipment
6 Buyende 2. Ngandho-Buyamba-Iraapa 9.4 0.00 9.40 - -ditto-
0.6mm 9 culverts,
7 Jinja West 1. Kimaka by-pass 3.09   - 1.60
0.9mm 12 culverts
Graveling, headwalls,
8 Jinja West 2. Kabalega road 0.38   - 0.38
stone-pitching. 100%
9 Jinja West 3. Wanje road 0.73   - 0.60 0.6mm 8 culverts complete 

10 Jinja West 4. Camulas road 0.50   0.50 0.50

0.6mm 196 culverts,


11 Bugiri 1. Nansaga-Kibuye-Wakawaka 17.31 - 18.40 18.40 0.9mm 32 culverts,
1.2mm 59 culverts

0.6mm 56 culverts, Included 1.45 Km total


0.9mm 48 culverts, length swamps raising of
12   Bugiri 2. Nankoma-Walugoma-Nabiina 17.00 15.00 15.00 1.45
1.2mm 32 culverts,
1.5mm 8 culverts

TOTAL (Km) 166.13 93.80 140.60 41.18


Annex 7
Performance of Rehabilitation of District Roads under Force Account in FY 2019-20 by the Eastern Unit
S/No. Road Name District Targeted Opened Graded Graveled Drainage works Remarks
Length (km) (km) (km)
(Km)

1 Alupe-Abunget Tororo 6.0 0.0 0.0 6.0 1 line of 1.8m, 4 lines of 0.9m and Handed over
5lines of 0.6m culverts installed

2 Buyembe Tororo 5.0 4.1 4.1 4.1 1lines of 1.8m , 1 line of 0.9m, and Substantially completed.
-Kasipodo 5 lines of 0.6m culvert installed However, construction of
culvert end structures in
progress.

3 Nakisi - Bulafwa- Namutumba 13.2 13.2 2.2 0.0 - Forming of road in


Bubutya - Kidali progress. Road to
be completed in FY
2020/2021

4 Magada Namutumba 11.6 13.4 13.4 13.4 1 line of 1.5m, 1 line of 1.2m,8 Handed over.
- Nabikabala – lines of 0.9m and 15 lines of 0.9m
Buwidi - Mulama culverts installed
- Kimenyulo

5 Usuk - Ngongoja Katakwi 14.0 15.0 15.0 15.0 17 lines of 0.9 and 22 lines of Substantially completed.
0.6m culverts installed. However, construction of
culvert end structures in
progress.

6 Apapai – Agule . Serere 6.3 6.0 6.0 6.0 7 lines of 0.6m culvert installed Handed over

7 Nambweke Busia 7.9 0.0 0.0 0.0 - No funds received


- Bushabala -
Buhunya
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

8 Busia - Tira- Busia 12.5 12.5 12.5 12.5 11 lines of 0.6m and 3lines of Handed over, but minor
Busitema 0.9m culverts installed corrections in progress.
167
S/No. Road Name District Targeted Opened Graded Graveled Drainage works Remarks
Length (km) (km) (km)
168

(Km)

9 Angola - Tororo 7.0 0.0 0.0 0.0 - No funds received,


Pukurotho -
Katerema Rolled over to next FY
FY2019/20

2020/2021.
10 Busia - Mikiya PS Tororo 7.7 7.7 3.5 0.0 - Forming of road in
progress.Road to be
completed in FY
2020/2021

11 Kachonga - Butaleja 6.5 5.3 5.3 5.3 1 line of 1.2m, 1 line of 0.9m and Substantially completed
ANNUAL SECTOR PERFORMANCE REPORT

Kachekere 21 lines of 0.6m culverts installed


Construction of culvert
end structures in progress
12 Kachonga - Butaleja 7.0 6.7 6.7 6.7 2 lines of 0.9m and 14 lines of Substantially completed.
Mudodo 0.6m culverts installed
Construction of culvert
end structures in progress
13 Budaka - Iki-Iki Budaka 12.3 0.0 0.0 0.0 - No funds received,
Rolled over to next FY
2020/2021.
14 Olago - Kangodo Serere 7.6 7.6 2.4 0.0 - Forming of road in
progress.Road to
be completed in FY
2020/2021
15 Butaleja 2.0 0.0 0.0 - Forming of road in
progress.Road to
Gaba - Eriga
be completed in FY
2.0 2020/2021
16 Opiko - Kalapata Bukedea 0.0 0.0 - No funds received,
Rolled over to next FY
6.2 0.0 2020/2021.
Total 132.8 93.5 77.1 69
Annex 8
PERFORMANCE OF FORCE ACCOUNT PROJECTSIN THE WEST IN FY 2019/20
S/N Road Name District Targeted Opened Graded Graveled Drainage works % of Physical Remarks
Length (km) (km) (km) Progress
(Km)

1 Rwabukwitsi Ntungamo 2.0 0 2.0 2.0 8 line of 1.2m, 18 lines of 100% Completed and handed
0.9m and 30lines of 0.6m over to the district.
culverts installed.

2 Mukungu Ntungamo 1.7 0 0 1.7 29 lines of 0.9m and 36lines 100% Completed and handed
of 0.6m culverts installed over to the district.
and

3 Kabirizi-Katere- Mbarara/Rwampara 6.5 0 6.5 6.5 - 100% Completed.


ro-Kabarama
4 Kyanya-Bikone Kasese 3.3 3.3 3.3 3.3 8 line of 1.5m, 54 lines of 100% Completed. However
0.9m and 49lines of 0.6m section of the road was
culverts installed. washed away by the flood.

5 Rwebisen- Ntoroko 8.0 8.0 8.0 0.0 16 line of 1.2m, 16 lines of 63% Progress affected by
go-Budiba 0.9m and 57lines of 0.6m lockdown due to Covid-19
culverts installed. Pandemic

6 Itojo-Kakindo Ntoroko 4.0 4.0 4.0 4.0 15 lines of 0.9m and 15lines 86% Works in progress
of 0.6m culverts installed.

7 Matan- Kanungu 3.3 3.0 2.0 0 0 14% Work still in progress.


da-Nyamirama Culvert construction not
yet started.

8 Kihihi-Matan- Kanungu 4.1 0 0 4.1 8 line of 1.2m, 14 lines of 100% Completed


da-Katokye 0.9m and 14lines of 0.6m
Gate culverts installed.

9 Kinaba- Ba- Kanungu 7.0 10.0 1.0 0 9 line of 1.2m, 32 lines of 75% Progress was hampered
kundeine 0.9m and 64lines of 0.6m by the lockdown due to
culverts installed. Covid-19 spread
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

10 Omukyiyan- Kanungu 8.0 0 0 10 80 lines of 0.9m and 24 72% Work scope increased
169

ja-Maba- lines of 0.6m culverts from 8.0 km to 10.0 km.


re-Nyamug- installed. work still in progress.
ari-Karuhinda
S/N Road Name District Targeted Opened Graded Graveled Drainage works % of Physical Remarks
Length (km) (km) (km) Progress
170

(Km)

11 Rutoto-Ki- Rubirizi 15.0 15.0 10.0 15.0 39 line of 1.5m,58 line of Casting of reinforced
noko-Bitooma 1.2m, 154 lines of 0.9m and concrete culverts in
235 lines of 0.6m culverts 85% progress. Progress was
FY2019/20

installed. hampered by the lockdown


due to Covid-19 spread
12 Mbonjera-Mbu- Kisoro 12.5 12.5 0 0 0 10% The progress was
lambuturo-Ga- hampered by lack of
tare-Foto Kigezi quarter four funds.
13 Kyanjuki- Kasese 10.0 12.5 0 0 0 12.5% The progress was
Kyambogho- hampered due to lack of
Ngangi access to the site as a result
of floods that washed
ANNUAL SECTOR PERFORMANCE REPORT

away the roads leading to


project site.
14 Kishebeshebe- Kazo 23.7 18.0 18.0 0 48 lines of 0.9m and 72 25% Work in progress
Kiguma- lines of 0.6m culverts
Kanungu- installed.
Rwigibisya
15 Kataten- Rakai 2.5 2.5 0 0 0 14% The progress was
ga-Rwidoga hampered by lack of
quarter four funds.
16 Kiwee- Rakai 1.0 1.0 0 0 0 12.5% The progress was ham-
ka-Kyenjokyi pered by lack of quarter
four funds.
17 Nabuzi- Rakai 3.5 3.5 0 0 0 18.0% In progress
ba-Lwoyo-Taba
18 Kituntu A- Rakai 3.0 3.0 0 0 0 25% In progress
Kituntu B
19 Kabuso- Rakai 1.0 1.0 0 0 0 12.5% In progress
ta-Rubare
Total 130.1 97.3 54.8 46.6

Performance of Rehabilitation of District Roads Under force Account in the FY 2019-20 By the Northern Unit
Annex 9
S/N Road Name District Targeted Opened Graded Graveled Drainage works % of Physical Remarks
Length (Km) (km) (km) (km) Progress

1 Bajere-Alune Kitgum 19.5 19.5 19.5 19.5 14 lines installed 100% Completed and handed over to the
District

2 Patira-Anaka Nwoya 19.0 19.0 19.0 19.0 32 lines installed 95% Substantially completed. Construction
of culvert end structures commenced

3 Moroto Municipality Moroto 15.6 14.6 13.8 12.6 11 lines installed 70% Awaiting approval of extra budget to
Roads Complete remaining works.

4 Tecwao-Onir-Oloo Alebtong 7.8 7.8 7.8 0.0 4 lines installed 45% Works suspended due to flooding of
the swamp. To re-commence during
dry season
5 AbongodyangA- Alebtong 8.4 7.4 7.4 7.4 7 lines installed 95% Substantially completed. Construction
tingtwo-Teowello of culvert end structures to commence
soon
6 Abia Centre-Anwata PS Alebtong 10.5 0.0 0.0 0.0 - - No funds received. Rolled over tonext
FY2020-21

7 Kororom-Pece -Labora Omoro 8.0 0.0 0.0 0.0 - - No funds received. Rolled over to next
FY2020-21
8 Kangai-Adekinino Dokolo 6.8 0.0 0.0 0.0 - - No funds received. Rolled over to next
FY2020-21

9 Tee-Okole-AlirSwampA- Lira 22.0 0.0 0.0 0.0 - - No funds received. Rolled over to next
nyom Orem-Nngetta FY2020-21
Mission-KitgumRd/Kole
District Boarder

10 Ibuje-Abongokoko-Cor- Apac 12.6 0.0 0.0 0.0 - - No funds received. Rolled over to next
ner Agwen FY2020-21
11 Desilting of Lalikan Dam Kitgum - - - - - 80% Excavation works ongoing.

12 Spot Improvement of Nwoya 5.0 1.5 0.0 0.0 4 lines installed - Culvert Installation at the first
Lungulu-LebngecArana majorcrossing completed
FY2019/20
ANNUAL SECTOR PERFORMANCE REPORT

Total 135.2 69.8 67.5 58.5

Status of Rehabilitation of Urban Roads under Force Account in the FY 2019/20


171
172 ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20

Annex 10
SN Road Name Length Physical Remarks
progress by
(km) end of June
,2020
1 Upgrading to bitumen standard of 2.91 60% Contract Progress was affected
Bulindo – Nakwero road section in when No funds were released
Kira M.C for quarter four.

2 Tarmacking selected roads in 1.54 19% Work Progress was affected


Lyantonde T.C –Phase 1, (Kyamera, when No funds were released
Ntambazi and Kijjukizo roads) for quarter four.

3 Construction of 8m span by 2.5m N/A 18% Work Progress was affected


deep stone arch bridge on River when No funds were released
Rwembyo and 9m span by 2.3m deep for quarter four.
stone arch bridge on river Nyakatsya
in KisingaT.C

4 Upgrading to Bitumen Standard of 1.0 0% No funds received in Q4. and


roads in Kaliro TC physical work execution was
deferred to FY2020/21 .

5 Rehabilitation of roads in Mityana 2.15 85% Physical works execution was


M.C Roads – Kiyudaya - katovu road affected by COVID -19 lockdown
and UMSC Mosque Parking Area
(1111m2)

6 Rehabilitation of Cliff road in Jinja 1.3 98% Works substantially completed


M.C (Leading to Source of The River
Nile)

7 Upgrading to bitumen standard 1.3 85% Physical works execution was


Circular Road in Gayaza High Sch. - affected by COVID -19 lockdown
Phase 2

8 Upgrading to bitumen standard of 1.2 97% Works substantially completed


roads leading to (including parking
areas) to Bugembe Cathedral in
Bugembe T.C

9 Upgrading to bitumen standard 2.2 94% Works substantially completed


of internal roads at the National
Agricultural & Trade Show Grounds
in Jinja M.C

10 Upgrading to bitumen standard of 1.2 98% Works substantially completed


movit road in Makindye-Ssabagabo
Municipal Council

11 Upgrading to bitumen standard 1.2 100% Planned Phase II works were


Chebrot road in Kapchorwa completed
Municipality - Phase 2)

Total 16
ANNUAL SECTOR PERFORMANCE REPORT
FY2019/20
173
Plot 57 -59 Jinja Road
P.o.Box 7174 Kampala Uganda
Telephone: +256 259 137 / 322
Fax: +256 414 231 369
Email: [email protected] Website: www.works.go.ug

You might also like