Event Management Complex Rs. 82.36 Million May-2016
Event Management Complex Rs. 82.36 Million May-2016
Event Management Complex Rs. 82.36 Million May-2016
HEAD OFFICE
4th Floor, Building No. 3, Aiwan-e-Iqbal Complex, Egerton Road,
Lahore
Tel: (92 42) 111 111 456, Fax: (92 42) 36304926-7
[email protected]
Aiwan-e-Iqbal Complex, Complex II, M.T. Khan Road, State Life Building Chaman Housing Scheme
Egerton Road Lahore, Karachi. The Mall, Peshawar. Airport Road, Quetta.
Tel: (042) 111-111-456 Tel: (021) 111-111-456 Tel: (091) 9213046-47 Tel: (081) 831623, 831702
Fax: (042) 36304926-7 Fax: (021) 5610572 Fax: (091) 286908 Fax: (081) 831922
[email protected] [email protected] [email protected] [email protected]
May 2016
Pre-Feasibility Study Event Management Complex
Table of Contents
1 DISCLAIMER.......................................................................................................................................... 2
2 EXECUTIVE SUMMARY ...................................................................................................................... 3
3 INTRODUCTION TO SMEDA............................................................................................................. 3
4 PURPOSE OF THE DOCUMENT........................................................................................................ 4
5 BRIEF DESCRIPTION OF PROJECT & PRODUCT........................................................................ 4
5.1 PRODUCT AND SERVICE MIX..................................................................................................................... 5
5.2 OVERALL SERVING AND OPERATIONAL CAPACITY................................................................................ 5
6 CRITICAL FACTORS ............................................................................................................................ 6
7 GEOGRAPHICAL POTENTIAL FOR INVESTMENT ..................................................................... 7
8 POTENTIAL TARGET CUSTOMERS / MARKETS........................................................................ 7
9 PROJECT COST SUMMARY................................................................................................................ 8
9.1 PROJECT ECONOMICS ................................................................................................................................. 8
9.2 PROJECT FINANCING................................................................................................................................... 8
9.3 PROJECT COST ............................................................................................................................................. 9
9.4 SPACE REQUIREMENT ................................................................................................................................ 9
9.5 MACHINERY & EQUIPMENT REQUIREMENT ....................................................................................... 10
9.6 FURNITURE, FIXTURES AND VEHICLE REQUIREMENT....................................................................... 11
9.7 OFFICE EQUIPMENT REQUIREMENT..................................................................................................... 12
9.8 HUMAN RESOURCE REQUIREMENT ...................................................................................................... 13
9.9 RAW MATERIAL REQUIREMENT ........................................................................................................... 13
9.10 UTILITIES AND OTHER COSTS................................................................................................................ 14
9.11 REVENUE GENERATION .......................................................................................................................... 15
10 CONTACTS – SUPPLIERS................................................................................................................. 15
11 USEFUL WEB LINKS.......................................................................................................................... 16
12 ANNEXURES ........................................................................................................................................ 17
12.1 INCOME STATEMENT............................................................................................................................... 17
12.2 BALANCE SHEET....................................................................................................................................... 18
12.3 CASH FLOW STATEMENT........................................................................................................................ 19
13 KEY ASSUMPTIONS........................................................................................................................... 20
13.1 OPERATING COST ASSUMPTIONS .......................................................................................................... 20
13.2 PRODUCTION COST ASSUMPTIONS ....................................................................................................... 20
13.3 REVENUE ASSUMPTIONS ........................................................................................................................ 20
13.4 FINANCIAL ASSUMPTIONS ...................................................................................................................... 21
May 2016 1
Pre-Feasibility Study Event Management Complex
1 DISCLAIMER
Document Control
May 2016 2
Pre-Feasibility Study Event Management Complex
2 EXECUTIVE SUMMARY
3 INTRODUCTION TO SMEDA
May 2016 3
Pre-Feasibility Study Event Management Complex
May 2016 4
Pre-Feasibility Study Event Management Complex
organizing / hosting requirements of both individual and corporate clients. With the
help of specialized team of professionals, proposed event management complex
will be fully equipped to make events more attractive and theme based through
provision of multiple stage setup, background props, entrance, reception, seating
arrangement, etc.
A purpose built building having a covered area of 9,600 square feet will be
constructed or acquired along with a parking facility of around 6,400 square feet in
the proximity of any residential or commercial locality of any major city for the said
complex. All necessary equipment such as kitchen utensils, burners, deep
freezers, air conditioners, tables, chairs, fixtures and other items are estimated to
be purchased to cater around 800 guests per event. The services of the event
organizing are offered at per-person basis with options of a standard one dish or
combination of different dish menus. Additionally, charges for other arrangements
and services will be based on the client’s requirements.
The project will provide employment opportunity to 09 individuals including owner
manager and contractual employees who will be engaged on event piece rate
basis. It is assumed that, necessary food item procurement will be made on event
day basis to maintain quality, reduce wastage and taste standardizations.
According to the nature of events different combinations of menu mix are assumed
for this project; product service mix along with operational capacities is provided in
the succeeding section.
May 2016 5
Pre-Feasibility Study Event Management Complex
Capacity utilization during year one is worked out at 60% with 05% increase in
subsequent years up to the maximum capacity utilization of 90%.
Table 1: Capacity Utilization
Product Capacity Capacity Capacity
Distribution of Events Mix Utilization Utilization Utilization
(60%) (90%)
Wedding Ceremonies 60% 96,000 57,600 86,400
One Dish with Chicken 40% 38,400 23,040 34,560
One Dish with mutton 40% 38,400 23,040 34,560
One Dish with Beef 10% 9,600 5,760 8,640
Mehndi Event 10% 9,600 5,760 8,640
Corporate Events 20% 32,000 19,200 28,800
Economy Pack 40% 12,800 7,680 11,520
Medium Pack 40% 12,800 7,680 11,520
Premium Pack 20% 6,400 3,840 5,760
Ceremonial Parties 10% 16,000 9,600 14,400
Lunch Buffet 35% 5,600 3,360 5,040
Dinner Buffet 35% 5,600 3,360 5,040
Hi-Tea 30% 4,800 2,880 4,320
Civic Events & Social 10% 16,000 9,600 14,400
Gathering
Buffet Cum-HI Tea 100% 16,000 9,600 14,400
6 CRITICAL FACTORS
Following are the factors critical for the success of this business venture:
Industry knowledge and prior experience of entrepreneur.
Ability to generate work orders through networking, direct marketing
and negotiating long term contracts.
Development of strong linkages with raw material suppliers for sourcing
quality material on time coupled with economical prices.
Location consideration for providing easy access to the
customers. Competitive pricing for the quality of services offered.
May 2016 6
Pre-Feasibility Study Event Management Complex
The proposed project of event management complex will cater to the needs of
middle and upper middle class families and individuals as well as corporate sector
including but not limited to:
Educational institutions
Private organizations
Public sector organization
Business firms
May 2016 7
Pre-Feasibility Study Event Management Complex
A detailed financial model has been developed to analyze the commercial viability
of Event Management Business. Various cost and revenue related assumptions
along with results of the analysis are outlined in this section.
The projected Income Statement, Cash Flow Statement and Balance Sheet are
also attached as annexure.
May 2016 8
Pre-Feasibility Study Event Management Complex
May 2016 9
Pre-Feasibility Study Event Management Complex
Table 5: Space Requirment
May 2016 10
Pre-Feasibility Study Event Management Complex
The costing for machinery and equipment is undertaken considering the fact that
there is easy and cheaper access to the requirement in local market. However,
with regards to utensils, the entrepreneur can also choose from international
brands such as Ikea, Harrods, The Alpha Collection, though the cost may be
higher. Chinese brands have also gained popularity over the years and can also
be considered.
Details of the furniture, fixtures and vehicle required for the project are given
below:
Table 7: Furniture, Fixture and Vehicle Requirement
Description Quantity Unit Cost Total Cost
(Rs.) (Rs.)
Furniture
Round Tables 100 4,500 450,000
Buffet Table 40 2,500 100,000
Round Table Cover 500 500 250,000
May 2016 11
Pre-Feasibility Study Event Management Complex
May 2016 12
Pre-Feasibility Study Event Management Complex
The raw material for daily operations of event management complex includes:
Chicken
Mutton
Beef
Rice Oil
Spices
Milk
May 2016 13
Pre-Feasibility Study Event Management Complex
An essential cost to be borne by the project is the cost of utilities. The water, gas,
telephone expenses are estimated to be around Rs. 94,750 per month.
May 2016 14
Pre-Feasibility Study Event Management Complex
Based on the capacity utilization of 60%, sales revenue during the first year of
operations is estimated as under:
Table 11: Revenue Generation – Year 1
Distribution of Product Persons Sales Persons In Revenue
Year 1 Generation In
Events Mix Price
(60%) Year 1
Wedding Ceremonies 60% 96,000 57,600
650 23,040 14,976,000
One Dish with Chicken 40% 38,400
One Dish with mutton 40% 38,400 1,000 23,040 23,040,000
750 5,760 4,320,000
One Dish with Beef 10% 9,600
Mehndi Event 10% 9,600 800 5,760 4,608,000
19,200
Corporate Events 20% 32,000
500 7,680 3,840,000
Economy Pack 40% 12,800
700 7,680 5,376,000
Medium Pack 40% 12,800
1,000 3,840 3,840,000
Premium Pack 20% 6,400
9,600
Ceremonial Parties 10% 16,000
1,000 3,360 3,360,000
Lunch Buffet 35% 5,600
1,200 3,360 4,032,000
Dinner Buffet 35% 5,600
800 2,880 2,304,000
Hi-Tea 30% 4,800
9,600
Civic Events & Social 10% 16,000
Gathering
1,100 9,600 10,560,000
Buffet Cum-HI Tea 100% 16,000
80,256,000
Total Revenue
10 CONTACTS – SUPPLIERS
May 2016 15
Pre-Feasibility Study Event Management Complex
Kitchen Care Plot# 103, Golden Plaza F-7, Blue (92 51) 32875226
Area, Islamabad, Capital, Pakistan (92 51) 32277176
May 2016 16
Pre-Feasibility Study Event Management Complex
12 ANNEXURES
Cost of goods sold 59,316,159 70,674,089 83,710,444 98,647,329 115,734,487 135,252,603 157,516,997 173,268,696 190,595,566 ##########
Gross Profit 20,939,841 24,964,311 29,584,276 34,878,591 40,935,926 47,855,942 55,750,603 61,325,663 67,458,229 74,204,052
General administration & selling expenses
Administration expense 2,039,400 2,243,340 2,467,674 2,714,441 2,985,886 3,284,474 3,612,922 3,974,214 4,371,635 4,808,799
Rental expense - - - - - - - - - -
Utilities expense 120,000 132,000 145,200 159,720 175,692 193,261 212,587 233,846 257,231 282,954
Travelling & Comm. expense (phone, fax, etc.) 495,000 544,500 598,950 658,845 724,730 797,202 876,923 964,615 1,061,076 1,167,184
Office vehicles running expense 154,500 169,950 186,945 205,640 226,203 248,824 273,706 301,077 331,184 364,303
Office expenses (stationary, etc.) 138,600 152,460 167,706 184,477 202,924 223,217 245,538 270,092 297,101 326,812
Promotional expense 1,605,120 1,912,768 2,265,894 2,670,518 3,133,408 3,662,171 4,265,352 4,691,887 5,161,076 5,677,183
Insurance expense - - - - - - - - - -
Professional fees (legal, audit, etc.) 160,512 191,277 226,589 267,052 313,341 366,217 426,535 469,189 516,108 567,718
Depreciation expense 2,614,134 2,614,134 2,614,134 2,614,134 2,614,134 3,109,422 3,109,422 3,109,422 3,109,422 3,109,422
Amortization expense 310,080 310,080 310,080 310,080 310,080 11,080 11,080 11,080 11,080 11,080
Property tax expense - - - - - - - - - -
Miscellaneous expense - - - - - - - - - -
Subtotal 7,637,346 8,270,508 8,983,173 9,784,906 10,686,397 11,895,868 13,034,065 14,025,421 15,115,913 16,315,455
Operating Income 13,302,496 16,693,802 20,601,103 25,093,684 30,249,529 35,960,074 42,716,538 47,300,242 52,342,316 57,888,598
Other income - - - - - - - - - -
Earnings Before Tax 7,537,083 11,800,602 16,702,224 22,328,332 30,375,401 35,960,074 42,716,538 47,300,242 52,342,316 57,888,598
Tax 1,717,030 3,182,343 4,867,012 6,800,745 9,576,716 11,485,085 13,797,069 15,364,044 17,087,716 18,983,755
NET PROFIT/(LOSS) AFTER TAX 5,820,052 8,618,259 11,835,212 15,527,587 20,798,685 24,474,989 28,919,468 31,936,198 35,254,600 38,904,843
May 2016 17
Pre-Feasibility Study Event Management Complex
Current assets
Cash & Bank 500,000 3,539,508 7,516,454 13,606,738 22,124,580 28,845,233 55,389,625 86,300,817 119,908,801 156,630,207 201,516,690
Accounts receivable - - - - - - - - - - -
Finished goods inventory - - - - - - - - - - -
Equipment spare part inventory 40,000 50,050 62,255 77,040 94,913 116,476 142,444 164,522 190,023 219,477 -
Raw material inventory 455,077 596,530 777,324 1,007,746 1,300,664 1,672,166 2,142,339 2,592,231 3,136,599 3,795,285 -
Pre-paid annual land lease - - - - - - - - - - -
Pre-paid building rent - - - - - - - - - - -
Pre-paid lease interest - - - - - - - - - - -
Pre-paid insurance - - - - - - - - - - -
Total Current Assets 995,077 4,186,088 8,356,033 14,691,524 23,520,157 30,633,875 57,674,408 89,057,571 123,235,424 160,644,969 201,516,690
Fixed assets
Land 40,000,000 40,000,000 40,000,000 40,000,000 40,000,000 40,000,000 40,000,000 40,000,000 40,000,000 40,000,000 40,000,000
Building/Infrastructure 30,507,653 28,982,271 27,456,888 25,931,505 24,406,123 22,880,740 21,355,357 19,829,975 18,304,592 16,779,209 15,253,827
Machinery & equipment 2,364,510 2,128,059 1,891,608 1,655,157 1,418,706 4,200,036 3,661,806 3,123,577 2,585,348 2,047,119 1,508,890
Furniture & fixtures 5,257,000 4,731,300 4,205,600 3,679,900 3,154,200 2,628,500 2,102,800 1,577,100 1,051,400 525,700 -
Office vehicles 1,545,000 1,236,000 927,000 618,000 309,000 2,488,238 1,990,590 1,492,943 995,295 497,648 -
Office equipment 88,000 70,400 52,800 35,200 17,600 112,313 89,850 67,388 44,925 22,463 -
Total Fixed Assets 79,762,163 77,148,030 74,533,896 71,919,762 69,305,629 72,309,826 69,200,404 66,090,982 62,981,561 59,872,139 56,762,717
Intangible assets
May 2016 18
Pre-Feasibility Study Event Management Complex
Net profit - 5,418,772 8,140,067 11,268,739 14,859,957 20,015,333 23,559,446 27,853,130 30,763,226 33,964,331 37,485,547
Add: depreciation expense - 2,614,134 2,614,134 2,614,134 2,614,134 2,614,134 3,109,422 3,109,422 3,109,422 3,109,422 3,109,422
amortization expense - 310,080 310,080 310,080 310,080 310,080 11,080 11,080 11,080 11,080 11,080
Deferred income tax - - - - - - - - - - -
Accounts receivable - - - - - - - - - - -
Finished good inventory - - - - - - - - - - -
Equipment inventory (40,000) (10,050) (12,205) (14,785) (17,873) (21,563) (25,967) (22,079) (25,501) (29,454) 219,477
Raw material inventory (455,077) (141,453) (180,794) (230,421) (292,918) (371,502) (470,174) (449,891) (544,368) (658,686) 3,795,285
Pre-paid building rent - - - - - - - - - - -
Pre-paid lease interest - - - - - - - - - - -
Advance insurance premium - - - - - - - - - - -
Accounts payable - 1,078,111 207,963 239,159 274,608 314,872 360,584 409,531 294,125 324,713 265,672
Other liabilities - - - - - - - - - - -
Cash provided by operations (495,077) 9,269,595 11,079,244 14,186,905 17,747,988 22,861,353 26,544,391 30,911,193 33,607,983 36,721,406 44,886,483
Financing activities
Change in long term debt 41,181,520 (6,230,086) (7,102,299) (8,096,620) (9,230,147) (10,522,368) - - - - -
Change in short term debt - - - - - - - - - - -
Change in export re-finance facility - - - - - - - - - - -
Add: land lease expense - - - - - - - - - - -
Land lease payment - - - - - - - - - - -
Change in lease financing - - - - - - - - - - -
Issuance of shares 41,181,520 - - - - - - - - - -
Purchase of (treasury) shares - - - - - - - - - - -
Cash provided by / (used for) financing act 82,363,040 (6,230,086) (7,102,299) (8,096,620) (9,230,147) (10,522,368) - - - - -
Investing activities
NET CASH 500,000 3,039,508 3,976,946 6,090,285 8,517,841 6,720,654 26,544,391 30,911,193 33,607,983 36,721,406 44,886,483
May 2016 19
Pre-Feasibility Study Event Management Complex
13 KEY ASSUMPTIONS
Description Details
Administration Benefit Expenses 3% of Administration Cost
7% of Administration
Office Expenses (Stationery, Entertainment etc)
expenses
Communication Expenses 15% of Administration Cost
Promotional Expenses 0.5% of Revenue
Professional Fee 0.2% of Revenues
Depreciation Method Accelerated depreciation
0% on Land
10% on Machinery
Depreciation Rate 20% on Office Equipment
10% on Furniture & Fixture
20% on Office Vehicles
Inflation Growth Rate 10%
Electricity Price Growth Rate 10%
Salaries Growth Rate 10%
Description Details
Growth in Sales Price 10%
Per Function Serving Capacity 800 Persons
Average Function Capacity 500 Persons
Function in Year 1 (60%) 192 Functions
Production Capacity in First Year 60%
Percentage Increase in Production Capacity every
05%
Year
Maximum Production Capacity 90%
May 2016 20
Pre-Feasibility Study Event Management Complex
13.4 Financial Assumptions
Description Details
Debt 50%
Equity 50%
Interest Rate on Debt 14%
Debt Tenure 5 Years
Debt Payment / Year 1
May 2016 21