CPJP8029 STD C 001 Rev 2 Horizontal Directional Drilling S
CPJP8029 STD C 001 Rev 2 Horizontal Directional Drilling S
CPJP8029 STD C 001 Rev 2 Horizontal Directional Drilling S
Technology
Standard for Horizontal Directional
Drilling
CONTENTS
1.0 BACKGROUND 1
2.0 DEFINITIONS 1
3.0 SYSTEM DESIGN CONCEPT AND PARAMETERS CONSIDERATION 2
4.0 MATERIALS AND EQUIPMENT 4
4.1 Equipment Requirements 4
4.1.1 Drill Rig 4
4.1.2 Drill Head 5
4.1.3 Reaming Head 6
4.1.4 Pull Back 7
4.1.5 Drill pipes 8
4.1.6 Bore Tracking Equipment 9
4.1.7 Ancillary Equipment 9
4.1.8 Drilling Fluid or Slurry 9
4.2 Pipe Materials 10
4.3 Entry and Exit Pit 10
5.0 INSPECTION AND TESTING 10
6.0 CONSTRUCTION 11
6.1 Construction Sequencing and Programming 11
7.0 REFERENCES 11
1.0 BACKGROUND
This Standard has been developed by the Australasian Society for Trenchless
Technology (ASTT) to assist users of Trenchless Technology in Australia and New
Zealand in selecting and utilising HDD method.
This document does not replace any existing relevant manuals or standards. It remains
the users responsibility to ensure that all relevant laws, standards and specifications
are adhered to during the course of a Works.
Additional Horizontal Directional Drilling information can be obtained from the ASTT
website (www.astt.com.au), they are:
2.0 DEFINITIONS
A number of abbreviations and technical terms have been used in this standard:
Work designed to be undertaken using HDD methods entails many considerations and
parameters that are unique to each project. A table of key parameters and appropriate
considerations for HDD work is depicted in Table 3.1. This table serves as a reference
tool to assist TT Users in understanding the key issues when undertaking HDD work.
PARAMETERS
GROUND DRILLING
BORE PLAN PIPE
CONDITIONS FLUID/SLURRY
Geotechnical
Depth & length of Bore Wall thickness sampling Mixture calculation
Std Penetration
Depth of Cover Allowable Stress Test Containment size
Pipe & Joints Std Classification of
Penetration Angles coating Soil Recycle methods
Radius of curvature Pipe Diameter Water Source
Profile Survey Joint type
Site access
Work space layout
The Client and Contractor should consider processes that should be undertaken prior
to commencing HDD outlined as follows;1
A wide range of HDD units exist in the market place today. The smallest drilling rigs
are typically used for installing residential telecommunication service cables. Larger rigs
are capable of installing pipelines up to 1200mm in diameter and over 1000m in
length. HDD rigs can be generally classified into three categories (Table 4.1). Each
category can perform different tasks. The choice of drill rig can be determined by
parameters including soil conditions and pipe diameters.
HDPE pipe is the most commonly used for HDD projects around the world. HDPE pipes
have characteristics that include abrasion resistance, flexibility, toughness, and low
profile butt-fused joints. They are available in both high and medium density material,
and in coil form (for smaller diameters). Traditional pipes (e.g. Concrete, clay, and
ductile iron) and sectional pipes that are manufactured in 4m, 6m and 12m straight
sections. HDPE piping also maintains full tensile strength at the joints as a result of
butt fusion welding.
The designer or contractor should only propose to use pipes other than HDPE if the
installation parameters of the alternative pipe materials can be shown to meet or
exceed the properties of HDPE pipe.
Drill rigs are classified into small, medium or large, as per Table 4.1. The rig is typically
anchored onto the surface on the centreline of the bore path at a distance ranging
from 1m to 6m away from the entry point. The angle of initial ground penetration cvan
be as high as 20 degree to the horizontal, depending on the diameter of the drilling
dead.
HDD processes make use of a fluid assisted drill head. There are a wide variety of drill
bits available in today’s TT industry, and they suit many different ground conditions.
Some of the most commonly used drill bits and their applications are shown in Table
4.2:
Organic Soils
Modified Spade Hard ground conditions Modified by adding teeth, taper etc.
to match conditions
Rock Bits Rock Small surface steering area;
Hard pan abrasion and impact resistant cutters
Rock drilling Bits
Roller–cone, mill tooth Soft rock (<35 Mpa) Are these used in HDD?
Sealed Bearing Roller- Medium rock (35 – 70
cone, Tungsten-Carbide Mpa)
Inserts
Sealed Bearing Roller- Hard rock (>70 Mpa) No moving parts
cone, Drag bit
Polycrystal Diamond Hard rock formations Generally too expensive and fragile
Compact(PDC) Drag bit for HDD applications
After the pilot bore has been completed all the way to the exist chamber, the pilot drill
bit is replaced with a reamer, which is then used to enlarge the borehole. The reaming
head is pulled back whilst rotating to enlarge the borehole. The number of passes
required in the reaming process depends on the fluid diameter of the borehole. For a
ratio of borehole to pipe diameter typically in the range of 1 to 1.5. This can be
achieved in between 3 to 5 passes.
Pull back is the process of drawing the new pipe backwards trough the borehole. The
swivel connecting the new pipe to the reeming head ensures that the pipe is not
twisted by the rotation of the drill string and reamer. This allows the new pipe to be
pull through safety. After the reamer has completed reaming the borehole, the pull
back process begins. A swivel is attached between the new pipe and the reaming
head. The safety break-away swivel reacts only to axial tension force. A safety break-
away swivel is also installed between the pipe and the reamer head. The safety break-
away swivel acts as a tension fuse. The break-away force is set at such a level that no
tension damage will be done to the pipe. This ensures that if the pulling force of the
drill pipe is greater than the maximum allowed for the new pipe, the break-away swivel
will disconnect first before damaging the pipe.
CATEGORY TYPE OF
APPLICATION COMMENTS
OF REAMER REAMER
The drill string must have sufficient strength to withstand the rotational torques and
longitudinal forces that are encountered during HDD process. The drill pipes must also
be flexible and smooth enough to accommodate the required curvature along the drill
path. The drill pipe also transports drilling fluid to the drill and reaming head.
Drill string material specifications are provided by the equipment manufacturer. These
should indicate its bending radii, grade of steel and water tightness requirement for
tubing sizes when transporting the drilling fluid, associated tensional and torsional load
capabilities, thickness, minimum and maximum tool joint torque capacity, type of each
tube connection, and connection thread type.
The drill head is to be tracked during the drilling operation by using either a walk-over
or a hand-wired system. The tracking system will transmit the following data to the
operator; position, pitch, depth, direction, roll, temperature and battery status.
Walk-over systems involve inserting a transmitter in the drill head. Walk over systems
should only to be used where an operator has full access to all the surface area directly
above the bore path. Varieties of transmitters are available for different penetration
depth. These systems generally function at depths of up to 40 m. The receiver is often
a small, hand held portable device. The Operator must be qualified and skilled, as
sufficient care must be taken when interpreting data, due to possible electronic or
electrical interferences. The contractor is normally required to keep a logbook
containing drill pipe number, pitch, depth, steering commands, apparent underground
obstructions and ground conditions.2
In situations where access above the bore path is not feasible (e.g. drilling under a
body of water) or where the bore depth is over 40m, then hard-wire systems shall be
used.
Bore tracking accuracy can be significantly improved using supplemental surface
monitoring systems. One such system involves setting up a grid with known corner
point locations to track the bore. This system can track bore depth 3 times the width of
the grid, and can track under bodies of water by setting up the corner points on the
shores. The grid may have up to 32 corners.
The tools that are used to attach the product pipe to the drill pipe during the pull back
process are called as Swivel connectors. The main function of the swivel is to connect
the new pipe and other tools to the pulling tools. They are also designed to prevent
damage to the new pipe from the rotation force exerted from the drill pipe.
Other equipment may include pipe support rollers for the new pipe on the surface
during the installation process, cable pullers and breakaway swivel connectors. The
contractor should be fully aware of industry available HDD accessories, as well as their
functions and capabilities, and utilise these accessories whenever required for any HDD
works.
The ?most commonly use? drilling fluid used for HDD is a Bentonite mixture which is
modified with a Polymer and water mix. The drilling fluid performs the following
functions:
The HDD process relies on the drilling fluid as the main means of ensuring the
borehole does not collapse. Critical fluid characteristics that need to be considered are
viscosity, gel strength, fluid loss & fluid density, sand content, pH, filtration control and
filter cake.
HDD projects require separate mixing systems, holding tanks, and mud recycling
systems. The mixing system provides proper mixture containment for the drilling fluid,
additives and the water. The holding tank is not only use as a water containment area,
but also provides drilling fluid mixing and a washing point during the project. The
drilling fluid is mixed to meet requirements dictated by the geological conditions of the
Works. Recycling systems are used to clean out debris during the cutting so the fluid
may be recycled. (These are often referred to as mud recycling systems)
The HDD process requires the utilisation of pipe materials that can withand the
expected axial tension and bending loads. They should also be abrasion resistant
.HDPE pipe is normally sufficient in all these areas.The designer or contractor may
propose the use pipes other than HDPE if the proposed pipe properties can be clearly
shown meets or exceed the properties of HDPE pipe for the HDD project.
HDD entry is mostly executed from the surface without the need for a large entry pit. A
small containment of drilling fluid is created at the entry end for removal or recycling of
the slurry. In addition, an exit pit shall be identified, or excavated, prior to any HDD
implementation. Any requirements to excavate small access potholes (for accessing
crossing utilities either for location or load limitation reasons) should also be identified
and considered.
6.0 CONSTRUCTION
7.0 REFERENCES
Bennett, D. Ariaratnam, S.T. Como, C.E. 2004, Horizontal Directional Drilling Good
Practices Guidelines, HDD Consortium, Virginia, USA
Canadian Association of Petroleum Producers (CAPP) 2004, Planning Horizontal
Directional Drilling for Pipeline Construction, Guideline, Alberta, Canada
DISCLAIMER: Neither ASTT, nor any person acting on its behalf, makes a warranty,
express or implied, with respect to the use of any information, equipment, method, or
process disclosed in this document, or that such use may not infringe on privately
owned rights; or assumes any liabilities with respect to the use of, or for damages
resulting from the use of, any information, equipment, method, or process disclosed in
this report.
1
Canadian Association of Petroleum Producers (CAPP) 2004, Planning Horizontal Directional Drilling for Pipeline Construction, Guideline,
Alberta, Canada
2
Bennett, D. Ariaratnam, S.T. Como, C.E. 2004, Horizontal Directional Drilling Good Practices Guidelines, HDD Consortium, Virginia,
USA