1.2 Retail Contractor HS Requirements - Version 5.2
1.2 Retail Contractor HS Requirements - Version 5.2
Requirements
Version 5.2
HEALTH
11.0 Alcohol & Drugs 9
12.0 Asbestos & Refractory Ceramic Fibres 10
13.0 Fitness to Work 12
14.0 Health Risk Assessment 12
15.0 Hearing Conversation 13
16.0 Legionella 14
17.0 Malaria 15
18.0 Occupational Exposure Limits 17
ENVIRONMENTAL MANUAL
29.0 Ozone Depleting Substances 29
30.0 Soil and Groundwater (RBSAM) 30
31.0 Waste 30
TRANSPORT MANUAL
32.0 Driver Safety 31
33.0 Road Safety in High Risk Environments 32
Applicable country laws shall be complied with when performing all work. In the event of
any inconsistency between the provisions of this document and applicable law, the more
stringent requirement shall prevail.
Please be aware that these are the Shell Control Framework Manual Requirements. These
requirements are the minimum level and the adherence with local legislation is mandatory.
If a local Market can’t comply with the requirements, they have to report this to their local
Network Delivery Manager as soon as possible.
Shell has a structured process in place to check, monitor and review the compliance. The
Contract Holder of the Contractor plays a leading role in this Assurance Process.
Purpose is to establish a process to identify HSSE Hazards and to reduce the Risks to ALARP
(as Low as reasonably practicable).
REQUIREMENTS
HSSE Risks are identified and classified in the Retail Engineering and SGW Contractor Safety
Case, available in GIDS. For all medium risks Partner Organizations have created Safe Work
Guidelines, in which controls are identified to mitigate the risks to ALARP. These Guidelines
are available in English (to be translated by the Partner Organizations) and all can be found
in GIDS.
FMC, EPCM, and SGW partners specifically need to review the Retail Engineering and SGW
Contractor Safety Case as existing operations/activities can change in a way that the
effectiveness of the Controls and Recovery Measures are reduced.
This review should take place once a year and all Incidents, Near Misses and Potential
Incidents, Audit Findings and new Activities are taken into consideration.
After the review Shell should be informed and all Contractors should also update their
Contract HSSE Plan, Toolbox Talks or JHAs to ensure mitigation of the new risks.
5 EMERGENCY RESPONSE
Purpose is to plan and prepare for Emergency Response to incidents that mitigates the
Consequences and enables normal operations to be resumed
REQUIREMENTS
There are 3 actions coming from the requirements of this Control Framework Manual
1) Partner Organizations should have a MU Emergency Response Plan (ERP) effective 24/7
for all risk scenarios under their control. This means that in case of Emergency after
Office Hours or in the Weekend, L2 should be available in order to call a L3 Contractor
to assist in the emergency (i.e. safeguarding a Site/Canopy).
2) Be aware of their responsibilities in the Shell MU ERP and provide resources accordingly.
o In case of an incident on Site, the Retailer/Site Manager is the Incident Manager and
everybody, including the Contractors, should listen to his/her instructions.
Purpose is to manage the HSSE & SP risks resulting from unforeseen consequences of
Changes.
The Manual section applies to:
- Specification or Procedural Changes
- Organizational Changes
REQUIREMENTS
1) Partner Organizations should develop and apply their own MoC Procedure
2) Notify Shell if it has a HSSE impact for Shell.
Ad 1) MU Partner Organizations should inform the relevant Shell Contract Holder in the MU
if there is a process Change, a Procedural Change or an Organizational Change within their
Organization or their activities which has a HSSE impact for Shell.
Purpose is to manage the risk of Hazardous work and work that could interfere with other
hazardous operations.
REQUIREMENTS
There are 2 actions coming from the requirements of this Control Framework Manual
1) Establish, Implement and maintain the Retail Permit to Work Procedure (see latest
version Retail PtW version in GIDS HSSE).
2) Train all Contractors, Permit Issuers and Permit Holders when needed
Ad 2) Train all Contractors, Permit Issuers and Permit Holders when needed
- Partner Organizations to keep a record of all competent Permit Issuers. Also to ensure,
via L3 Contractors, that Permit Holders are competent.
The Retail HSSE CoE will provide the latest version of the PtW version in English and it is up
to the Partner Organizations to translate and adapt it to the local situation as long the
minimum requirements of the Global version are guaranteed.
The Purpose is to integrate the requirements of the Shell HSSE & Control Framework into
Business Plans and Procedures
REQUIREMENTS
There are 3 requirements from this Control Framework Manual
1) Integrate the HSSE & SP Objectives, HSSE & SP targets and HSSE plans into the
operational Plan
2) Develop and maintain Procedures to implement the requirements of the CF and to
manage the HSSE Risks
3) Communicate the Plan and Procedures
Ad 1) Integrate the HSSE & SP Objectives, HSSE & SP targets and HSSE plans into the
operational Plan
- Partner Organizations to integrate the HSSE Objectives, the HSSE targets and the HSSE
plans into their Business Plan. This should be done at Global and at Local level ensuring
alignment between the two.
REQUIREMENTS
There are 7 actions coming from the requirements of this Control Framework Manual
1) Contractors should report all Incidents, including Near Misses and Potential Incidents.
They can use their own systems for this.
2) In case of an incident (see below) the relevant Shell Contract Holder should be
notified as soon as possible
3) Partner Organizations should make an initial classification of the Incident, if needed
with the support of the local HSSE Manager
4) The relevant Shell Contract Holder to log the Incident in Fountain Incident
Management
5) Partner Organizations to investigate the Incident within 30 days
6) Make a final classification based on the outcome of the incident investigation
7) Learn from Incidents, Fatalities, High Potential Incidents and High Severity Incidents
through communication and implementation of required actions
Retail Contractor
Incident Reporting Procedure_March 2015.docx
Ad 1) All Contractors’ workers should report Near Misses and Potential Incidents. Partner
Organizations should report the number of Near Misses and Potential Incidents (NMPI) to the
Shell MU HSSE Manager on the 15th working day of the month. If there are any trends or
potentially High NMPI’s they should be reported separately and Partner Organizations
should focus on these in the coming month.
Ad 2) Partner Organizations need to notify their relevant Shell Contract Holder of all
Incidents (fatalities, LOPC > 100 KG (>120L), Total Recordable Cases (TRC), Medical
Treatment Cases (MTC) and LSR Breaches within 24 hours. The relevant Shell Contract Holder
should inform the MU NDM and the MU HSSE Manager.
Ad 3) Partner Organizations should make an initial classification of the Incident Fatality, Lost
of Primary Containment (LOPC), Total Recordable Case (TRC), Medical Treatment Case
(MTC) and LSR Breaches within 3 days with the support of the Shell MU HSSE Manager
Classification TRC or
FAC.doc
Ad 5) Partner Organizations should set up an Investigation team and this Team needs to
finalize the Investigation Report within 1 month (30 Calendar days) after Incident occurring.
This Investigation Report should contain a root cause Analysis, learnings and actions to
prevent the same Incident from recurring
Ad 6) After the Investigation report and the review with the NDM the Incident should be
classified as final by the Partner Organization
Ad 7) Partner Organizations should make Learning from Incident (LFI) within 6 weeks
(Calendar Days) after the Incident occurrence. This LFI should be sent to the relevant Shell
Contract Holder and the Shell MU HSSE Manager and should be communicated to all
relevant persons to ensure that the incident will not reoccur.
The Purpose is to report HSSE Performance data to Group that are relevant, consistent,
transparent, accurate and complete, for consolidation by the VP HSSE Reporting for internal
review and public disclosure.
REQUIREMENTS
There are 3 actions coming from the requirements of this Control Framework Manual
1) Local Partner Organizations to collect HSSE & SP Performance data. This data that
needs to be collect every month is:
a. Exposure hours for all contractors (L2, L3, L4 etc.)
• The exposure hours need to be reported by the Partner Organizations
to the MU HSSE manager. This means all exposure hours of all
contractors (L2, L3, L4 etc.) working for the Shell Account.
• The number of hours can be estimated based on for example the
budget. Actual hours would be preferred, if this is possible.
• The estimations must be re-calculated 2 x per year. This should be
interpreted as revisiting any assumptions which have been made in
calculating exposure hours to ensure they are still valid.
b. KM driven for all contractors
• The KM driven need to be reported by the Partner Organizations to
the MU HSSE Manager. Only the kilometers of the Partner
Organization’s Staff working 100% for the Shell account (including
Mobile Technicians of FMC) need to be reported.
• The number of kilometers can be estimated
• The estimations must be re-calculated 2 x per year.
c. Number of Near Misses / Potential Incidents
• Number of NMPI should be reported to the MU HSSE Managers.
2) Local Partner Organizations to report this data to the local HSSE manager before the
15th Working day of the month.
3) Global Partner Organizations to report this data according to their Contract
requirements
The purpose is to manage the risk caused by the use of Alcohol and Drugs
REQUIREMENTS
There are 2 actions from the requirements of this Control Framework Manual
1) Establish and Maintain an Alcohol & Drugs Policy
2) Establish and maintain procedures to implement this Policy
Explanation *:
Alcohol and / or Drug testing may be required where the contractor Staff appearance,
actions, or behavior suggest that they may be affected by drugs and/or alcohol (“Reasonable
Cause”). In practice there should usually be at least two people who have seen the person
and have reason to believe that the person may be affected by drugs/alcohol, and that the
person may be a source of actual or potential harm to themselves or others in the workplace.
Persons involved in an incident (vehicle & mobile equipment incidents, injuries, property
damage and near miss incidents) should also be tested if this is required in the investigation
of the incident.
It is up to the Partner Organizations to take more proactive steps like random tests to all
personnel working on a Site (including visitors). This is however not mandatory
Purpose is to manage risks associated with exposure of Asbestos and Refractory Ceramic
Fibres on Shell assets, facilities, operations and projects.
Be Aware: Where ever it says Partner Organizations in this particular Asbestos Manual we
mean: FMC, SGW and competent EPCM if allowed by EPCM’s Corporate Policy
REQUIREMENTS
There are 3 actions coming from the requirements of this Control Framework Manual
1) Identify where we have Asbestos on our Sites and maintain a Register
2) Manage Asbestos on Site and make the risks as low as reasonably practicable
3) Develop a Procedure to remove the Asbestos
Ad1) Identify where we have Asbestos on our own Sites and make a Register
Identify where we have Asbestos on our Sites by:
- Partner Organizations to do a Desk Top Exercise; find out where we could have
Asbestos on Shell Retail Sites. Register should be made per country based on the local
legal requirements.
Per OU there should be list of:
Category 1 – Sites where we think that there is Asbestos.
Category 2 – Sites where we think there is no Asbestos but we are not sure.
Category 3 – We know that there is no Asbestos on Site.
Reasonable Criteria Partner Organizations can use to define the risk categories are:
i. Any previous asbestos identified at site
ii. Local knowledge
iii. Local documentation
iv. Global documentation
v. Type of construction i.e. steel work and no materials used have history
of containing asbestos
vi. Age
1) If any of the above indicates that there is Asbestos Containing Materials on site
we would categorise as Category 1 Sites - Definitely have asbestos identified
2) If above indicates that there is no Asbestos however potential for asbestos i.e.
age, history of asbestos on site but removed , type of construction indicates ACM
could have been used it would categorize them as Category 2 Sites – potential
to have asbestos however not thought to
3) If above states that there is definitely no asbestos then it categorise them a
Category 3 Sites – no Asbestos
- If there are any Category 1 Sites, Partner Organizations or their certified Contractor
should carry out an onsite survey to identify Asbestos on site – this would cover
identifying asbestos which could be damaged or disturbed by normal activities
- HSSE CoE to inform Site Staff working for High and Medium risk Sites about the risks.
- Partner Organizations will create a generic Register for the medium risk Sites. In this
generic Register we will mention the typically places where Asbestos could be located.
- Partner Organizations will train Contractors to be aware of Asbestos and to identify
Asbestos when they are working on Site. If Asbestos is found they should stop the
maintenance or construction activities and Partner Organizations should ask the certified
Contractor to do an assessment on the Asbestos (condition quantity, type and location),
remove it when possible or mark it.
- Partner Organizations to determine what frequency of inspection is required to
determine the condition of the Asbestos which is to remain in-situ
- The Partner Organizations should be aware that if there is any construction or Knock
down rebuild (KDR) occurring on a Retail Site where Asbestos is present, the procedure
to remove the Asbestos (see Ad 3) needs to commence in order to remove the Asbestos
before the construction begins.
- If the Asbestos, during the Site Visits, can be removed without any construction, a
procedure to remove this Asbestos (see Ad 3) needs to be documented by the Partner
Organizations and their approved Contractor in order to remove the Asbestos as soon
as possible.
Ad 2) Manage Asbestos on Site and make the risks as low as reasonably practicable
- Shell will inform and explain to Site Staff how to handle Asbestos via the Site Policy and
Procedure Manual, this is the HSSE manual for the Retailers
13 FITNESS TO WORK
The purpose is to reduce the risk of Injury, Illness or Incidents be evaluation of fitness to
Work
REQUIREMENTS
There are actions coming from the requirements of this Control Framework Manual:
- Partner Organizations to verify that the Contractors are familiar with these requirements
of having a Fitness to work certificate before they can start doing their work.
- Contractors doing activities which apply to this manual should have a Fitness to Work
process to ensure that the Contractor worker is deemed unfit for the works until the
Fitness to work evaluations are completed and the person is deemed fit.
The purpose is to avoid harm to people due to Health Hazard by carrying out Health Risk
Assessment (HRA) and implementing the control and recovery measures specified
For contractors, the inclusion of identified health hazards and controls in JHAs is sufficient – a
specific HRA will not be required if this is completed.
REQUIREMENTS
- The Contractor is responsible for implementing the following requirements:
• Include identified health hazards and how to manage those Health Risks
associated in all JHA’s (hazards and controls can be found in the Safe Work
Guidelines in GIDS)
15 HEARING CONSERVATION
REQUIREMENTS
There are 8 actions coming from the requirements of this Control Framework Manual:
Partner Organizations to identify and assess through Health Risk Assessment those
tasks and areas where Noise Levels could result in Noise Induced Hearing Loss.
a. Update noise assessments when equipment or conditions change in a way
that may increase the exposure of personnel to noise.
Contractors to reduce noise exposure to As Low As Reasonably Practicable in the
workplace using the following Hierarchy of Controls.
a. Beginning with the first Control, assess each in turn to select a control or
controls that reduce exposure to noise to As Low As Reasonably Practicable:
i. First: Eliminate equipment that makes noise.
ii. Second: Substitute equipment with other equipment that makes less
noise.
iii. Third: Isolate equipment that makes noise.
iv. Fourth: Apply engineering Controls to equipment that cannot be
eliminated or substituted to reduce Noise Levels in the workplace to
less than 85 dB (A).
v. Fifth: Apply procedural Controls to reduce duration or magnitude of
exposure.
vi. Sixth: Provide personal hearing protection.
b. Do maintenance to keep Noise Levels in line with the equipment design
criteria.
Keep peak Noise Levels in the workplace below 140 dB(C).
a. This value applies irrespective of the duration of the exposure or the use of
hearing protection.
Keep the exposure of personnel to noise below 85 dB (A) for an eight-hour Noise
Dose.
Do the following when hearing protection or procedural Controls are used to
maintain exposure below 85dB(A) for an eight-hour Noise Dose:
a. Establish hearing protection zones based on a Noise Contour of 85 dB (A)
and identify them with marking/signage.
i. When portable equipment is the source of the noise use location
drawings, equipment marking or other controls to identify hearing
protection zones.
16 LEGIONELLA
The Purpose is to manage risks associated with exposure to Legionella in the Workplace.
REQUIREMENTS
There are 3 actions coming from the requirements of the Control Framework Manual
1) Identify and document water systems and equipment on a Retail Site that are a
potential source of Legionella
2) Assess these Water systems and equipment for the risk of Legionella.
3) Determine a monitoring and control program for Legionella in water systems at the
Retail Site and in equipment at risk, and document results.
Ad 1) Identify and document water systems and equipment on a Retail Site that are a
potential source of Legionella
- FMC to identify and document possible Legionella sources on a Retail Site. (Key Factors
to identify possible Legionella sources – see GIDS 04.008 vs. 1.1 Chapter 5).
- FMC is the owner of this document and also responsible for updates
Here is a risk assessment document that can be used to assess the risk of Legionella
Ad 2) Assess these Water systems and equipment for the risk of Legionella.
- FMC to assess these water systems for the risk of Legionella.
1) FMC to evaluate risk factors, including water aerosol formation, stagnant water,
dead zones, water temperature, mineral deposits and visible Biofilm
2) FMC to reassess the Legionella risk if there is a change in design or operational
change.
Ad 3) Determine a monitoring and control program for Legionella in water systems at the
Retail Site and in equipment at risk, and document results.
- A program should be set up by the FMC to
1) Minimize water misting, stagnant water and dead zones (action FMC)
2) Manage water temperature (Retailer to monitor and FMC to support)
3) Implement a preventative maintenance and inspection program to monitor
equipment (action FMC)
4) Conduct Legionella testing of water systems and equipment (sampling by Retailer
and FMC)
- Restrict access and apply corrective action to clean and disinfect Legionella
contaminated systems and equipment when Legionella water test exceed local
requirements or exceed more than 100 CFU/ml. (action FMC via certified Contractor)
- Appoint certified L3 Contractor for work activities (trained and experienced) on
Legionella contaminated systems and equipment (action FMC)
- Establish alerts to inform Site Staff and Customers about the presence of Legionella
contamination and the measures to be taken (CoE HSSE to update SPPM)
17 MALARIA
REQUIREMENTS
There are 5 actions for Partner Organizations coming from the requirements of this Control
Framework Manual:
1) Partner Organizations to develop a Malaria program based on an assessment of Malaria
Risk according to the Malaria Zone Classification provided by Shell Health.
a. Partner Organizations to appoint or obtain an Authorized Subject Matter Expert
for Malaria to lead the development of the Malaria program based on the local
Risk.
b. Partner Organizations to provide the resources required for the Malaria
program.
3) Partner Organizations to implement the Malaria program as shown in the table below,
based on the ABCDEF principles and the Malaria Zone Classification.
Recommended Controls
Zone
Principles of Malaria Prevention Responsible Person / People
1 2&3 4
The Purpose is to manage the Health Risk of occupational exposure to chemical and physical
agents by using Occupational Exposure Limits (OELs).
This Manual Section covers Occupational Exposure of Contractors to chemical and physical
agents at Shell facilities and installations (like Retail Sites)
COMPLAINCE PROCESS
There are actions coming from the requirements of this Control Framework Manual:
- Shell to manage occupational exposure to chemical and physical agents to whichever of
the following is lower
1) Occupational Exposure limits set by legislative authorities (HSSE Manager to
check)
2) Shell Occupational Exposure limits (see below)
Shell Benzene OEL: 0.5 ppm or 1.6 mg/m3 (8 hour time weighted average Limit)
2.5 ppm or 8 mg/m3 STEL (15 min short term exposure limit)
Ethylene Oxide: 1 ppm or 1.8 mg/m3 (8 hour time weighted average limit)
The purpose is to manage the risk associated with the cleaning of Storage tanks
REQUIREMENTS
There are actions coming from the requirements of this Control Framework Manual:
- FMC/EPCM to apply the Hierarchy Of Control as follows:
First: Minimize the need for or reduce the frequency of tank cleaning.
Second: Use Online Cleaning methods that do not require the opening of, or entry
into tanks.
Third: Use mechanical cleaning options that do not require workers to enter tanks.
Fourth: Allow personnel entry and manual cleaning of tanks where supported by a
documented Risk Assessment. Reference Confined Space Work.
- Contractors to establish and maintain Procedures for tank cleaning in accordance
with Internationally Recognized Standards.
- Procedures must include:
REQUIREMENTS
This section applies to work in Confined Spaces. A Confined Space is a fully or partially
enclosed space:
• that is not designed and constructed for continuous human occupancy, and
• has limited or restricted means for entry or exit, and
• where there is a risk of injury or health effect from hazardous substances or conditions.
See Appendix 2 of the Retail Permit to Work system for examples of Confined Spaces at
Retail locations. For specific requirements related to tank entry, see the Global Standard for
Manned Entry and Non-Manned Entry of USTs for Cleaning and Inspection.
• An Authorised Gas Tester must carry out the gas test before the Permit is issued. The test
must be documented and provided with the Permit.
All persons involved in gas testing should be adequately trained in the use of gas testing
equipment and the interpretation of results, prior to being authorised to undertake gas tests
and certify results. The Permit Issuer must ensure
• The work area is clear of flammable and combustible materials before the
work starts.
• The tester is competent/trained (incl. a record)
• The equipment has been calibrated and tested.
• The Authorised Gas Tester must test atmosphere continuously to establish that the Confined
Space remains free of flammable materials during the work, by means of an Authorised Gas
Tester or flammable gas monitoring equipment so occupants in the Confined Space are
protected from atmospheric hazards. Investigate any deviation in the oxygen level or in the
contaminant level of toxics or flammables, assess the risks and take appropriate action.
• Allow entry into Confined Spaces, with respiratory protection, only when the source,
nature and concentration of the hazardous atmosphere are understood. A competent person
must approve the selection of respiratory protection. A competent person must verify the
quality of air supplied from bottles, compressors or ventilators.
• If contaminants or heat in the Confined Space can affect entrants’ health, provide a plan
for ventilation or other controls prior to entry, list the controls with the Permit and verify that
the controls are put in place. Do not use oxygen or oxygen-enriched air to ventilate a
Confined Space.
• Include in the Permit the controls required to manage the risks from any energy sources
used inside the Confined Space. If electrical equipment is needed inside the Confined Space
(e.g. lighting) use low voltage equipment if available. If low voltage equipment is not
available, an earth leakage current device or ground fault circuit interrupter must be used to
protect entrants against electric shock.
• Verify that lighting in the Confined Space allows entrants to see well enough to work safely
and to exit the space quickly in an emergency.
• Establish a rescue plan for recovering people from the Confined Space. All equipment and
other resources including trained responders needed for a rescue must be readily available
whenever people are in the Confined Space.
Version 5.2—October 2016 20
• Indicate the entry points to be used, and barricade or use signs at all other openings to
prevent unauthorized entry.
• Station an Attendant outside the Confined Space.
• Verify that the Attendant is present at all times while entrants are in the Confined Space.
Before people enter the Confined Space establish effective means of communication
between the people inside the Confined Space and the Attendant outside.
The Contractor is responsible for implementing the following requirements (to be maintained
by the Attendant during the work):
• Prevent unauthorized entry and take action if conditions change.
• Maintain a record of numbers and names of people in the Confined Space.
• Monitor the Confined Space from outside at all times while entrants are inside, and
maintain communication with the entrants.
• Stop the work and evacuate the Confined Space if ventilation systems fail, contaminants
exceed agreed limits, conditions become unsafe, or other emergencies at the site require
evacuation.
• Activate the emergency response plan in the event of emergency.
• The Attendant must not attempt a rescue unless it is defined in the rescue plan.
22 ELECTRICAL SAFETY
REQUIREMENTS
The Contractor is responsible for implementing the following requirements:
• Use a person who is competent in electrical safety to develop and maintain the Electrical
Safety Rules for each site. The Electrical Safety Rules of the site must be in line with
Internationally Recognized Standards and local legislation.
• Define which people can work on electrical equipment.
• Set responsibilities and requirements for operation, maintenance, identification (labeling)
and inspection of electrical equipment.
• Identify the Internationally Recognised Standards, legislation, or requirements to use for
equipment design and for control of electrical craftwork.
See latest version of Retail PtW in GIDS HSSE for the uses of Electrical devices
23 EXCAVATION
REQUIREMENTS
The Contractor is responsible for implementing the following requirements:
• Reduce risk by applying the hierarchy of controls:
First: Eliminate the need for excavation by applying trenchless technology.
Second: Apply Maximum Allowable Slopes or Benching.
Third: Use Shoring or Trench Shields.
• Control excavations in line with the Retail Permit to Work System.
• Apply the Confined Space Work section when working in a confined space.
On Greenfield sites where the risk of striking underground services is small, the Contractor
shall agree with the Partner Organization in which areas and how deep permit control is
not required. Excavations deeper than 1.2 meters shall be considered as a confined space
and subject to permit control, both on existing and Greenfield sites.
The Authorised Person for excavation (Permit Issuer) is responsible for the following
requirements:
• Implement the procedures established for the type of excavation, including the following:
o Identify and mark the route of cables, live lines, pipelines or other hazardous
infrastructure.
o Confirm the location of underground and overhead infrastructure before starting
work.
o Apply the specified procedures for soil testing and classification.
o Inspect excavations and shoring, including areas adjacent to the excavation, for
signs of ground instability before each shift, before resuming work after adverse
weather conditions and following any incident that may affect its stability.
Note:
If sewers or other underground pipes need to be broken into as part of the work, rats (as they
are attracted to wet places) can become a problem and could cause Health issues like
Leptospirosis. Leptospirosis is transmitted via direct contact with the body fluid of an acutely
infected animal or by exposure to soil or fresh water contaminated with the urine of an
animal infected.
24 HOT WORK
The Purpose is to manage the risk of ignition of flammable materials during Hot Work
REQUIREMENTS
There are actions coming from the requirements of this Control Framework Manual:
The Contractor is responsible for implementing the following requirements:
Minimum Specific PPE requirements for working in Hydrocarbon/ Hazardous Zones (e.g.
Non-static and Flame Retardant) must be defined and implemented.
Examples of PPE requirements for working in hazardous zones can be found in GIDS.
REQUIREMENTS
The Contractor is responsible for implementing the following requirements:
• Establish competence assurance requirements for people who supervise or perform
lifting and hoisting operations and who inspect and maintain lifting equipment.
• Equipment to be used for lifting and hoisting must be inspected, maintained and
certified in line with the manufacturer’s specifications and local legislation. Use
equipment only for its intended purpose and within its designed operating limits.
• Apply procedures that are approved by a subject matter expert for lifting and
hoisting, which must include the following:
o Assign an Authorised Person for the lifting and hoisting operation, and a
Person In Charge Of The Lift.
o Conduct a specific JHA to define the lift plan;
o Assess site factors to define logistics, crane stability, and radius of
operation;
o Assess load factors to define load integrity and stability.
The Authorised Person (Permit Issuer) for lifting and hoisting is responsible for the following:
• Check the lifting and hoisting equipment before all lifts and confirm that:
The Purpose is to manage the risk to people where personal protective equipment is used
REQUIREMENTS
At a minimum, all contractor workers must wear a high visibility vest, Safety helmet and
safety boots / shoes at all times. Other PPE including gloves, eye protection, etc must be used
as required by the contractor’s risk assessment (i.e. Work Clearance Form / JHA) or by the
Partner Organizations’ PPE Guidelines.
All Contractor workers must use the following Hierarchy of Control to manage additional PPE
use:
First: Eliminate the Hazard or exposure.
Second: Substitute materials or equipment to reduce the Hazard or exposure.
Third: Use engineering controls to keep the hazard from reaching the worker
Fourth: Use procedural controls to keep the hazard from reaching the worker
Fifth: Use PPE
In cases where PPE must be used, All Contractor workers must have a procedure to manage
PPE usage.
This procedure must:
• Specify where and when PPE must be used
• Specify the types of PPE to be used
• Specify methods for making people aware of when and where PPE must be used
• Specify how people are fitted for PPE
• Specify how people are trained to put on and use PPE and trained in the limitations
of its use
• Specify how people verify that PPE remains effective when the hazard, exposure or
controls change
• Specify how to issue, inspect, maintain, store and replace PPE
• Document the arrangements for people to have fitness evaluation prior to the use of
The Purpose is to manage the risk of exposure of people to Energy and hazardous
substances by isolating of equipment and placement of locks and tags
REQUIREMENTS
There are actions coming from the requirements of this Control Framework Manual:
The Contractor is responsible for implementing the following requirements:
• Protect people from energy and hazardous substances by isolation of equipment,
locking movable isolation devices and placing a tag at each point of isolation.
• Establish and maintain isolation and lock out tag out procedures that include the
Requirements below:
o Specify the people who are authorised to isolate, lock out and tag out
equipment.
o Identify the types of work that need to be controlled by lock out and tag out
and the methods of isolation.
o Specify the method to place and remove locks and tags at each point of
isolation and the method to control locks and keys.
o Specify the additional controls required and the method of removal that will
Maintain an equivalent level of protection when the person who
placed a lock or tag is not available to remove it (i.e. if the person is
forced to leave the site unexpectedly).
o Specify the tests to prove that isolation is complete.
• Apply the following Hierarchy of Control for isolation to protect people from energy
and hazardous substances:
First: Remove equipment from the sources of hazards, or create an air gap or
physical break that prevents the hazard from contacting people.
Second: Isolate equipment from hazards by using a solid physical barrier.
Third: Move to the safe position and lock movable devices, electrical circuit
breakers and valves that isolate hazards.
o When applying this control to isolate electrical equipment, verify
that electrical back feed is not possible.
• Control isolation and placement and removal of locks and tags by doing the
following:
• Shut equipment down and remove or drain any sources of stored energy.
28 WORKING AT HEIGHT
The Purpose is to prevent falls and reduce the consequences if a fall occurs when Working at
Height
The Purpose is to manage the risk from the release of Ozone Depleting Substances
REQUIREMENTS
For more Information see also the GIDS Technical Bulletin 05.002
There are actions coming from the requirements of this Control Framework Manual:
The FMC is Accountable for the following requirements:
o Identify Ozone Depleting Substances and maintain an inventory until they are
eliminated.
o Eliminate Halons and Hard CFCs in all operations by end-of-year 2010 and
eliminate HCFCs by end 2020 in accordance with the Montreal Protocol.
o Do the following until the substances in requirement 2 are eliminated:
Remove Ozone Depleting Substances from Non-Sealed Systems.
Provide controls to prevent loss of Ozone Depleting Substances.
Provide controls for recovery and destruction of Ozone Depleting
Substances.
• Do not transfer Ozone Depleting Substances to third parties
for re-use. Where permitted by legislation, in-company
transfers and transfer to Halon banks are permitted.
o Put controls in place so that new installations are not fitted with HCFCs from
beginning of year 2010 onwards.
o Provide terms that comply with the requirements above in contracts for the
purchase, service or disposal of equipment or refrigerant that contains Ozone
Depleting Substances.
o Make Contractor Workers aware of any equipment that contains Ozone
Depleting Substances and the controls required before they perform work that
could release these substances.
Retail compliance with Soil and Groundwater Manual is called the RBSAM (risk based site
asset management) program.
REQUIREMENTS
There are actions coming from the requirements of this Control Framework Manual:
Standards applicable to RBSAM cover the site life cycle (Acquisition, Operation, Minimum
equipment standards & disposal) managed by Real Estate, Environmental services , HSSE
and Engineering.
For Engineering the applicable standards include
• GIDS 08.001 Governing principles for fuel systems
• GIDS 08.024 Product loss investigation procedure
• GIDS 08.040 UPSS minimum requirements
• GIDS 04.011 Retail HSSE Critical Equipment Inspection and Testing Requirements
• GIDS 04.012 NTS checklist
- FMC/EPCM should install and maintain equipment and/or comply with procedures to
minimize the risk of leaks and spills.
- FMC to inspect and maintain leak detection and/or containment systems
31 WASTE
The Purpose is to minimize the generation and optimize the re-use of recycling and disposal
of Waste
REQUIREMENTS
32 DRIVER SAFETY
The Purpose is to manage the risk of driving and transportation of people and goods on
Company Business
For Retail Contractors this manual applies to all Contractors who work and drive 100% for
Shell and no other Company (example FMC Mobile Technicians). So this means that L3
Contractor do not need to comply with this Manual only Partner Organizations’ Staff who
work 100% on the Shell Account (for example ROMs, PMs, JCI MTs, Brokers, etc.) . Private
cars are out of scope. Commuting is out of scope.
REQUIREMENTS
There are 14 actions coming from the requirements of this Control Framework Manual:
1) Partner Organizations to identify which Contractors (Staff) work and drive 100% only
for Shell
2) All these Drivers need to have a current driving license that is valid for the location,
type of vehicle and, where appropriate, the cargo
3) All the Drivers need to be physically and mentally capable of operating the Vehicle
a. Be rested and alert to maintain attention throughout the trip
b. Stop the vehicle and take the rest break if attention is lost
c. Do not operate a vehicle while under the influence of alcohol, drugs, narcotics
or medication that could impact driving ability
4) All the drivers not to make a call or answer a mobile phone or page, send or read a
text message or use a hands free mobile phone device while driving a vehicle
Version 5.2—October 2016 31
5) All Cars (all types of vehicle) need to have a three point seatbelt system; the driver
needs to use this and also make sure the passengers do so as well.
6) All Drivers not to allow unauthorized Passengers in the vehicle
7) All Drivers to attend a accredited defensive driving course within 3 months of
assignment and refresh training every 2 years, if you drive more than 7500 km a
year on Company business
8) All drivers need to visually inspect the vehicle daily for roadworthiness including tires
and windscreen/windshield
9) All drivers need to drive with lights on during daytime except where prohibited by
law
10) Use Vehicles (company cars, Lease cars, Rental cars, Private cars) equipped with
a. Seatbelts and head restraints
b. Anti-lock braking system, Vehicle Side Impact Protection and airbags for
Company owned contracted, privately owned or leased light vehicle.
11) Partner Organizations to challenge the need for people to drive on Company
Business
12) Drivers to prepare a Journey Management Plan and agree on driving and rest
schedule for trips of more than 4 and a half hours. Drivers are not allowed to have
trips for more than 10 hours or a combination of work and driving for more than 14
hours
13) Partner Organizations do not allow the use of motorbikes with 2 or 3 wheels for
Company Business
14) Partner Organizations to maintain and equip Company owned or leased vehicles (if
under contract for more than 3 months) so that they are
a. Fit for purpose based on an assessment of usage
b. Kept in safe working order in line with manufactures specifications and local
legislative requirements
c. Equipped as described in requirement 10
The Purpose is to manage the risk of driving and transportation of people and goods on
Company Business in Road Safety high risk areas
These requirements are additional to the requirements of the previous Manual (Driver Safety).
This manual applies to all Contractors who work and drive 100% for Shell so this means that
L3 Contractor do not need to comply with this Manual only Partner Organizations’ Staff who
work 100% on the Shell Account (for example ROMs, PMs, FMC MTs, Brokers, etc.)
c. Periodically question and review the number of Journeys with the intent to
eliminate Journeys and lower the risk. Reduce the risk to As Low As
Reasonably Practicable by applying the following Hierarchy Of Controls.
Beginning with the first Control, assess each in turn to select a Control that is
Reasonably Practicable for the task:
i. Eliminate the Journey.
ii. Change to a lower risk transportation mode.
iii. Apply Vehicle Controls