Saes A 007
Saes A 007
Saes A 007
Contents
1 Scope .............................................................. 2
2 Conflicts and Deviations .................................. 2
3 References ...................................................... 2
4 Definitions ........................................................ 4
5 Roles and Responsibilities............................... 6
6 General Requirements..................................... 8
7 Lay-up Procedures’ Requirements ................ 11
8 Special Systems’ Requirements .................... 20
9 Health, Safety, and Environmental
Requirements ........................................ 23
Revision Summary .............................................. 25
1 Scope
1.1 This standard establishes requirements to control internal corrosion during and
after hydrostatic testing of new, revalidated, and refurbished equipment when
equipment is hydrostatic tested in accordance with SAES-A-004, SAES-L-150
or as required by other standards that specifically reference SAES-A-007.
1.2 Equipment covered by this standard includes, but is not limited to, storage tanks,
pressure containing equipment, plant piping, and pipelines both onshore and
offshore. Systems that are completely made of non-metallic materials, internally
lined with non-metallic materials, or internally coated are exempt from this
standard’s water quality and lay-up requirements.
1.3 The procedures in this standard are designed to prevent corrosion due to oxygen
(air) ingress and to prevent microbial-influenced corrosion (MIC). Hydrostatic
test procedures and lay-up procedures shall prevent oxygen ingress except as
specifically allowed in this standard.
1.4 Non-toxic liquids other than water may be used for pressure testing if the
operating fluid or the equipment can be adversely affected by water or by
freezing conditions. Water/methanol or water/glycol mixtures may be required
in locations where freezing is a concern. Contact the Group Leader, Corrosion
Engineering Group (CEG), Materials Engineering Division (MED), Consulting
Services Department (CSD), for the selection and treatment of the appropriate
fluid. Such a fluid shall not have a flash point below 54°C (129°F).
1.5 Special requirements for specific systems are presented in Paragraph 8 of this
standard. If there is an apparent conflict between it and the general requirements
in the remainder of the Standard, Paragraph 8 shall govern.
Any conflicts between this document and other applicable Mandatory Saudi Aramco
Engineering Requirements (MSAERs) shall be addressed to the EK&RD Coordinator.
Any deviation from the requirements herein shall follow internal company procedure
SAEP-302.
3 References
The selection of material and equipment, and the design, construction, maintenance, and
repair of equipment and facilities required by this standard shall comply with the latest
edition of the references listed below, unless otherwise noted.
ASTM International
ASTM D4412 Standard Test Methods for Sulfate-Reducing
Bacteria in Water and Water-Formed Deposits
NACE International
NACE TM0194 Field Monitoring of Bacterial Growth in Oil and
Gas Systems
NACE TM0208 Laboratory Test to Evaluate the Vapor-Inhibiting
Ability of Volatile Corrosion Inhibitor Materials
for Temporary Protection of Ferrous Metal
Surfaces
McKetta, J.J. and Wehe, A.H. 1958. Petroleum Refiner 37 (8): 153.
4 Definitions
Dew Point: The temperature at which a given concentration of water vapor in a gas
will form moisture. The lower a gas dew point temperature becomes, the less amount
of moisture is in the gas.
Flash Point: The lowest temperature at which vapors of a volatile material will ignite
in presence of an ignition source.
Plant Piping: Includes above and below-ground piping inside a plant area, as defined
in SAES-L-100.
Project Management Team (PMT): Refers to the Saudi Aramco organization that
contracts engineering, procurement, and/or construction work to outside contractors
under their supervision.
Sulfate-Reducing Bacteria (SRB): Are bacteria that can obtain energy by oxidizing
organic compounds or molecular hydrogen while reducing sulfate to form hydrogen
sulfide.
Total Dissolved Solids (TDS): A measure of the combined content of all inorganic and
organic substances contained in a liquid.
Total Suspended Solids (TSS): A measure of the dry weight of particles contained in
a liquid trapped by a filter.
5.1.1 Ensure the implementation of this standard and compliance with all
requirements.
5.1.2 Facilitate and resolve any issues related to the implementation of this
standard with other Saudi Aramco organizations.
5.1.3 Review and approve water quality of hydrostatic test and lay-up
procedure for each equipment or system prior to the Inspection Authority
as per SAEP-1150.
5.1.5 Maintain a permanent written record of the water supplied for testing
stainless steels including a record of tests performed on the water.
5.2.1 Develop and propose the hydrostatic and lay-up procedure(s), when
required, to PMT and the Proponent for review prior to hydrostatic
testing.
5.2.2 Ensure the implementation of this standard and compliance with all
requirements.
5.2.3 Provide all resources and materials required to implement the hydrostatic
test and lay-up procedure.
5.2.5 Regularly report all hydrostatic test and lay-up testing results to PMT.
5.2.6 Provide records for water supplied for testing stainless steels for
examination by PMT and inspection authority at all times.
5.2.7 Provide all records to PMT for each hydrostatic test and lay-up activity
and shall be included in the Project Records turnover to PMT at the end
of the project.
5.3.2 For other facilities, equipment, or systems, the hydrostatic test and
lay-up procedures shall be approved by the Saudi Aramco Engineering
Superintendent (Proponent) or his designate.
Commentary Note:
5.4.2 For existing facilities, the proponent's Operations Inspection Units shall
be the authority monitoring quality of hydrostatic test fluid and planning
and execution of the lay-up activities per this standard and approved
procedure(s).
5.4.3 In case water quality report and/or lay-up procedures are not meeting
minimum mandatory requirements outlined in this standard, then the
Inspection Authority shall reject the report and/or procedure with the
violation and outline necessary remedial action plan.
For existing facilities, the Plant Operations shall be responsible for executing
and adhering to the approved hydrostatic test and lay-up procedure.
5.6.2 CSD shall only review and approve lay-up methods not specifically
discussed in this standard prior to the hydrostatic testing.
Commentary Note:
6 General Requirements
Water used for any part of the hydrostatic testing or subsequent wet lay-up shall
meet the following requirements before equipment is filled with water; Table 1
provides a summary of these requirements.
Commentary Note:
If these tests are reported by water source plant, then there is no need for
additional testing.
6.1.1 Sulfate Reducing Bacteria (SRB) count of 1,000 cells per mL or less as
determined by serial dilution laboratory test methods following
ASTM D4412 or NACE TM0194 or by on-site SRB detection test kits.
Water with higher SRB count could be used after biocide treatment and
re-testing upon approval of the Group Leader, CEG/MED/CSD.
When the total equipment contact time with water may exceed 30 days,
biocide shall be used as per paragraph 7.4.2.7.
6.1.2 Clean and free from suspended matter using a filter capable of removing
99% of all particles 53 µm (2.1 mil) in diameter and larger, or equivalent
6.1.3 When the equipment contact time with hydrostatic test water could
exceed 14 days for carbon steel and low alloys or 4 days for austenitic
stainless steel systems, dissolved oxygen concentration shall be
maintained at 20 parts per billion (ppb) or less by maintaining residual
oxygen scavenger concentration at 20 parts per million (ppm) or greater.
Approved oxygen scavenger shall only be used as given in Appendix A.
For Dry Gas and Refined Hydrocarbon Product Pipelines, an oxygen
scavenger shall always be added to the hydrostatic test water as per
paragraph 8.4.3, even when the hydrostatic test water contact time is less
than 14 days.
Commentary Note:
Refer to paragraph 8.4 for dry gas and refined hydrocarbon product
service requirements.
Seawater and high TDS aquifer water shall not be used for testing
austenitic stainless steel systems. Refer to paragraph 7.2.1 for
exceptions.
6.1.5 Water containing hydrogen sulfide (H2S) shall not be used for
hydrostatic testing or subsequent wet lay-up.
Commentary Note:
6.1.6 The use of seawater/high salt hydrostatic test water in facilities under the
responsibility of Pipelines Department shall be pre-approved in writing
by the General Supervisor, PTSD, and by the Saudi Aramco Engineering
Superintendent of the concerned Pipeline Department (Proponent) or his
designate. For equipment other than subsea pipelines, all mitigation
actions shall be presented for approval by Saudi Aramco Engineering
Superintendent (Proponent) at the design stage prior to commencement
of construction. Otherwise, it will not be a permissible option once
construction has commenced. For subsea pipelines; flooding, cleaning,
gauging, baseline in-line inspection and lay-up/mothballing procedures
may be developed during the design phase.
6.2.1 The quality of water to be used for hydrostatic testing and for wet lay-up
shall be determined well ahead of the actual testing date so that
alternative water sources may be identified if the original source water
fails to meet the abovementioned requirements.
Commentary Note:
A fixed testing timeframe for the water quality initial test shall be
determined on a case-by-case basis depending on the source of the
water. In general, initial testing of the water source that will be used for
hydrostatic testing could start during the initial phase of construction
(two months from construction start). A retest is required to reconfirm the
water quality before the hydrostatic test is performed.
6.2.1.3 If the water used in the hydrostatic test or wet lay-up process is
from more than one source, ensure that mixing the waters will
not cause scaling.
Commentary Notes:
6.2.3 Any treatment chemicals shall be continuously injected at a rate that will
provide the specified concentration while filling the system with water in
preparation for the hydrostatic test. The chemicals’ injection rates shall
be monitored on-site using displacement gauges.
6.2.4 For pipelines, use batching scrapers and a slug of nitrogen to separate the
air in the system from coming in contact with the treated water.
6.2.5 When multiple treating chemicals are required, ensure that the chemicals
proposed for use are compatible with one another. Separate
proportioning pumps shall be used for each chemical to avoid adverse
reactions. Chemicals shall not be mixed prior to injection.
Multicomponent products, as provided by the chemical vendors, are
exempt from the pre-mixing restriction.
7.1.2 Once equipment has been laid up, lay-up shall be maintained until
equipment start-up can be initiated.
Commentary Note:
lines, size of drainage system, size of evaporation pond and all other
logistics’ requirements shall take into account this requirement.
This information shall be part of the initially developed hydrostatic test
and lay-up procedures as per paragraph 5.2.1.
7.2 For stainless steel systems or components, the water quality requirements in
Paragraph 6.1 shall be strictly followed.
7.2.1 In special cases, with the prior written approval of the Group Leader,
Corrosion Engineering Group, MED/CSD, water of up to 250 ppm
chloride might be used provided the following steps are all followed:
7.2.1.1 The hydrostatic test period is less than four (4) days
7.2.1.2 After removing the water with up to 250 ppm chloride, the
system is rinsed with steam condensate or demineralized water
until the effluent chloride content is determined to be less than
50 ppm for two consecutive measurements taken 30 minutes
apart.
7.2.2 Austenitic (type 300-series) stainless steel valve trims shall not be a
sufficient sole criterion for classifying a carbon steel system as
“stainless” for the purpose of applying paragraph 6.1 unless there are
also other stainless steel components included.
7.3 If the system and/or equipment cannot be operated before the periods outlined in
paragraphs 7.1 and 7.2, one of the following approved lay-up methods detailed
in paragraphs 7.4 – 7.7 shall be implemented.
7.3.1 For all materials not specifically covered in this standard and for
acceptance of other lay-up methods, prior written approval must be
obtained.
7.3.2 In cases where safety concerns may arise, obtain the approval of the
General Supervisor, Workplace Environment Division, EPD.
7.4.2.3 Once minimum residuals are verified, keep the system tightly
closed to prevent air entry.
7.4.2.4 Repeat tests and ensure chemical residual levels every month
during lay-up unless the physical location of the line or
equipment makes this impossible. If a leak occurs or air enters
the system, lay-up the system again after completing repairs.
7.4.2.6 Use gauges with a scale range not exceeding three (3) times the
target pressure to monitor the positive pressure in the system
during lay-up.
Commentary Note:
7.4.2.7 When the total equipment contact time with water may exceed
30 days, microbial growth shall be controlled by one (1) of the
following chemicals:
a) Use proprietary chemical 9CAT #1000022136 (combined
biocide, corrosion inhibitor and oxygen scavenger) at a
concentration of 350 – 500 ppm.
b) Use proprietary chemical (combined biocide and corrosion
inhibitor) at a concentration of 150 – 200 ppm with
compatible oxygen scavenger.
c) For discharge to environmentally sensitive locations, use
Tetrakis Hydroxymethyl Phoshonium Sulfate (THPS)
which degrades to non-toxic components. 70% pure THPS
shall be applied at 50 ppm. THPS is also available as
blends with other products which may be less
environmentally friendly.
d) Polyhexamethylene biguanide hydrochloride (PHMB)
9CAT # 1000178704, may also be used in hydrostatic tests
at 200 ppm.
Saudi Aramco: Company General Use
Page 14 of 29
Document Responsibility: Corrosion Control Standards Committee SAES-A-007
Issue Date: 1 January 2018
Next Planned Update: 24 August 2019 Hydrostatic Testing Fluids and Lay-Up Requirements
7.5.1 Dry lay-up may be achieved using several different drying media.
These include hot dry air, controlled dew point inert gas, and drying
chemicals such as glycol or methanol applied between two pipeline
scrapers or as a gelled scraper. The best results may be achieved by
using a combination of these techniques.
7.5.1.1 Dry air may be used only if it has been pre-approved. For dry
gas and refined hydrocarbon product pipeline and piping, dry
lay-up by using air is prohibited as per paragraph 8.4.4.
7.5.1.2 Dry lay-up using hot or dew point controlled air may only be
used for systems where the required dew point can be
successfully reached within one (1) week.
Commentary Note:
7.5.1.3 Sweet gas may be used for dehydration only if it has been pre-
approved. Before using it ensure that hydrate formation will
not occur at low temperatures and elevated pressures.
7.5.2 Ensure the removal of the hydrostatic test water from the system:
7.5.2.1 For facilities other than pipelines, drain the system completely,
sweep and mop, as required, to ensure that no visible traces of
water remain.
7.5.3 When seawater or similar high salinity water has been used as the
hydrostatic test media, the following shall be applied:
7.5.4 If using inert gas to dry a pipeline, the remaining water shall be removed
with a methanol or glycol slug between two scrapers to achieve drying in
a short period. Then, dry with dehydrated inert gas. Gelled chemicals
may also be used. Ensure compatibility of dehydrating chemicals with
all materials in the system, including coating, if present.
7.5.5 Hydrostatic tests should be performed after the valves are removed.
However, if not possible, valves shall be dewatered as follows:
7.5.5.3 When the bulk of the water has been removed, blow a
compatible vapor-phase corrosion inhibitor (VpCI) at a proper
concentration, as per NACE TM0208, with nitrogen until it is
visibly discharged at the bottom of the valve.
7.5.6 Immediately after dewatering, start drying the system to a dew point of
30°F (-1°C) or less at the final lay-up pressure at all exit points.
7.5.6.2 After the blowing cycle, shut-in the system and maintain
positive pressure of 20 to 30 psig (140 to 210 kPa) for a
minimum of 12 hours. The objective is to allow any remaining
moisture to come to equilibrium with the above drying gases.
7.5.6.5 Record the pressure of the line or system at the time of the dew
point measurement. Record the pressure at which the dew
point measurement is made if different to the actual system or
line pressure.
7.5.6.7 If valves were removed for hydrotest, when the required dew
point is reached, re-install all valves and repeat steps in above
paragraphs 7.5.6 to 7.5.6.6.
7.5.6.8 When the required dew point is reached, pressurize the system
with nitrogen or sweet gas to the final lay-up pressure. Dry air
may be used only if it has been pre-approved. The system shall
be maintained at a positive pressure of 30 to 50 psig (210 to
7.5.6.9 Shut-in the system, maintain and monitor the pressure per
paragraph 7.4.2.6 during the lay-up period. Pressure shall be
monitored daily for 7 days, then weekly for the next 3 weeks
and then monthly for the duration of the lay-up period.
7.5.6.10 For pipelines, re-measure the dew point at all original test
locations one (1) week after reaching final lay-up pressure.
If any dew point reading is found to be higher at the lay-up
pressure, then the entire line shall be dried again as per
paragraph 7.5 or an alternative lay-up procedure shall be
implemented.
7.6.1 Displace the hydrostatic test water by positive pressure with nitrogen
or sweet gas until no water drains out of the low points in the system.
Do not vent the system or allow air entry; water displacement will be
accomplished under positive pressure of nitrogen or sweet gas only.
Shut in the system under positive pressure from 30 to 50 psig (210 to
350 kPa) until commissioning and start-up. Ensure that systems being
drained have vacuum relief valves and pressure relief valves as
necessary. Pressure shall be monitored daily for 7 days, then weekly for
the next 3 weeks and then monthly for the remaining duration of the lay-
up period.
7.6.2 For pipelines for which inert gas lay-up is proposed, valves shall remain
in place during hydrostatic testing. Following hydrostatic testing,
requirements outlined in paragraph 7.5.5.3 shall be followed.
For pipelines, displace water by pushing the scraper with inert gas or
sweet gas. Dry air may be used only if it has been pre-approved.
Scraper shall have a three (3) or four (4) cup displacement scraper or
better system such as a gelled scraper.
7.6.3 Microbial control per paragraph 7.4.2.7 is not required even though some
residual water is left in the system.
Commentary Note:
Stainless Steel.
7.7.1 Ambient lay-up shall be used for non-critical systems only after pre-
approval. The ambient lay-up procedure shall provide a technical
assessment and address all the following items and all other conditions
that may negatively impact the system’s integrity:
7.7.1.3 Rust deposits can be tolerated during operations, e.g., for cases
where there is no strict product specifications and where black
powder is not an operational concern.
Commentary Note:
7.7.2 If ambient lay-up is approved, the lay-up shall be conducted using the
following procedure:
7.7.2.1 Remove all water from the system. For facilities other than
pipelines, drain the system completely, sweep and mop as
required to ensure that no visible traces of water remain.
7.7.2.3 After removal of all water, close the system to prevent the
entry of sand or rainwater.
Other lay-up methods are acceptable with the prior written approval of the
Group Leader, Corrosion Engineering Group, Materials Engineering Division,
CSD. In cases where safety concerns may arise, the procedure shall be
approved by the General Supervisor, Workplace Environment Division, EPD.
Saudi Aramco: Company General Use
Page 19 of 29
Document Responsibility: Corrosion Control Standards Committee SAES-A-007
Issue Date: 1 January 2018
Next Planned Update: 24 August 2019 Hydrostatic Testing Fluids and Lay-Up Requirements
Hydrostatic testing treated water and lay-up procedure are exempted for
abovementioned systems with no construction or fabrication quality concerns.
If there are concerns, water quality, and lay-up procedure requirements shall be
implemented.
8.2 Systems that are partially internally coated, where coating does not cover girth
welds and/or bends, then requirements of this standards shall apply.
8.3.1 Utility and potable water systems shall be tested in accordance with
SAES-S-060 or SAES-S-070, as appropriate.
8.3.2 Potable water systems shall be tested with fresh potable water only,
following the requirements of SAES-S-070, Paragraph 18.2.
Oxygen scavengers and biocides shall not be used in potable water
systems.
8.3.3 For potable water systems, use dry lay-up per paragraph 7.5, inert gas
lay-up using nitrogen per paragraph 7.6, or ambient lay-up per
paragraph 7.7. However, for dry-up, sweet gas, methanol, or other
dehydrating chemicals shall not be used.
8.3.5 Lube oil systems shall be pressure tested following the requirements of
SAES-L-150. Water shall not be used.
8.4 Dry Gas and Refined Hydrocarbon Product Pipelines and Piping
Commentary Note:
8.4.2 All debris shall be removed before hydrostatic testing using brush
scrapers and magnetic scrapers in pipelines and piping large enough to
fit scrapers.
8.4.3 For pipelines and piping in dry gas or refined hydrocarbon product
service, an oxygen scavenger shall always be added to the hydrostatic
test water, even when the hydrostatic test water contact time is less than
14 days specified in paragraph 6.1.3. This does not apply to plant piping
which shall be treated per paragraph 6.1.3.
Use batching scrapers and a slug of nitrogen to separate the air in the
system from coming in contact with treated water, and then fill the
system with treated water by injecting sufficient oxygen scavenger to
maintain a minimum oxygen scavenger residual concentration of 20 ppm
and an oxygen concentration less than 20 ppb.
8.4.4 Pipelines in dry gas or refined hydrocarbon product service shall be laid-
up using either the wet lay-up procedure per paragraph 7.4 or dry lay-up
procedure per paragraph 7.5 with the line pressurized with dry sweet gas
or dry nitrogen. Dry air shall not be used except if chemical cleaning
shall follow the lay-up procedure for pipelines defined in SAES-L-488.
8.4.5 When water is finally removed from the pipe at the end of the hydrostatic
test, chemical and/or mechanical cleaning, or wet lay-up, the system shall
be thoroughly dried. Air drying shall not be used for pipelines except if
chemical cleaning shall follow the lay-up procedure for pipelines defined
in SAES-L-488. Air drying may be used for small in-plant piping
systems, if drying can be completed in less than one (1) week. Chemical
desiccants such as glycol or methanol may only be used if necessary and
specifically pre-approved in the hydrostatic test procedure.
Commentary Note:
8.5.1 Prior to the introduction of sour process fluids, the lines shall be dried as
required for dry lay-up and as detailed in paragraph 7.5. For upstream
offshore lines, proceed directly to the batch treatment recommended in
paragraph 8.5.2.
Commentary Note:
8.5.3 PMT shall provide all equipment and chemical required to perform the
inhibitor treatment. When there is an unavoidable delay between
signature of the Mechanical Completion Certificate and introduction of
process fluids into the line, PMT shall provide funds for all associated
expenses.
8.6.1 For carbon steel open-roof tanks, floating-roof tanks, or API atmospheric
cone roof tanks that are not designed for service above atmospheric
pressure, treatment of hydrostatic test water shall not be required.
All traces of visible water shall be drained and removed from these tanks
immediately after completing the hydrostatic test.
8.6.2 For any galvanized pipe not covered by paragraph 8.3, treat galvanized
steel pipe per paragraph 6.1.3 and lay-up per paragraphs 7.4 – 7.7.
8.6.3 For yard or shop fabricated piping systems that are constructed,
hydrostatic tested, then shipped, PMT shall submit the lay-up procedure,
including water quality, to the Group Leader, CEG/MED/CSD, for
approval. In addition to one of the lay-up methods from paragraphs 7.4
– 7.7, the use of a vapor phase corrosion inhibitor (VpCI) may be used
upon approval of the detailed procedure.
9.1 Disposal of all hydrostatic test and lay-up waters shall be in accordance with the
requirements of SAEP-327, SAES-A-103 and Saudi Aramco Hazardous Waste
Code (SAHWC). Disposal plans shall be part of all hydrostatic and lay-up
procedures.
9.2 Follow procedures outlined in the Chemical Hazard Bulletins and Hazardous
Materials Communications Program (HazCom) labeling per GI-0150.100
provided by the Environmental Compliance Division, EPD, for handling,
storage, and mixing of the chemicals to be used for hydrostatic test water
treatment.
9.3 Provide an eyewash station and emergency shower per SAES-B-069 at the
mixing site of the chemicals.
9.4.1 Procedures shall ensure that explosive mixtures of air and gas are
avoided.
Commentary Notes:
9.4.2 Methanol is a toxic and inflammable chemical and may be used only
when adequate safety precautions are in place as per HazCom.
9.4.3 Caution shall be exercised when using nitrogen. While nitrogen is not
toxic, it displaces breathable air in confined spaces, as defined in
SAES-B-008, such as pipe trenches, vessel skirts, or vessels that can lead
to suffocation. Caution shall also be given to the use of cryogenic
nitrogen and its effect on both personnel and equipment.
Saudi Aramco: Company General Use
Page 23 of 29
Document Responsibility: Corrosion Control Standards Committee SAES-A-007
Issue Date: 1 January 2018
Next Planned Update: 24 August 2019 Hydrostatic Testing Fluids and Lay-Up Requirements
9.4.4 The hydrostatic test procedure shall include a complete copy of all
relevant Materials Safety Data Sheets (MSDS) and chemical hazard
bulletins for the chemicals used in the hydrostatic test. The hydrostatic
test procedures shall address safety and environmental concerns listed in
the MSDS or chemical hazard bulletin as per GI-0002.102.
9.5 Caution shall be taken in situations where hydrostatic tests are performed on
systems where pyrophoric iron sulfide, as defined by SAES-A-210, might be
present. Also, personnel shall not be exposed to water containing hydrogen
sulfide levels that will result in 10 ppmw in the air. Refer questions concerning
the safety of air and water to the General Supervisor, Workplace Environment
Division, EPD.
Revision Summary
24 August 2016 Major revision by clarifying, aligning, and optimizing mandatory requirements in SAES-A-007.
The review also incorporated comments from Inspection Department/Project Inspection
Divisions and Pipeline Technical Support Division.
a) Clarify exception of systems that are completely made of non-metallic materials, internally
lined with non-metallic lining, or internally coated from this standard’s water quality and
lay-up requirements in paragraphs 1.2 and 8.1.
b) Update References in Section 3.
c) Add new Section 4 for “Definitions”
d) Add new Section 5 for “Roles and Responsibilities”
e) Re-organize Section 6 “General Requirements” to include all “Water Quality Specifications”
and “Hydrostatic Test and Wet Lay-Up Water Preparation” requirements.
f) Include all Hydrostatic Testing Water Quality Requirements in Table 1.
g) Align maximum O2 concentration with SAES-L-133 in Table 1 and paragraphs 6.1.3, 6.2.2,
7.4.2.1, and 8.4.3.
h) Limit use of water containing H2S without treatment in paragraph 6.1.5.
i) Add pH requirement in line with SAES-L-133 in Table 1 and paragraph 6.1.7.
j) Specify a maximum period of 2 weeks for testing water before initial water filling in 6.2.1.1.
k) Add guidelines to predict scaling tendency when using multisource water in paragraph 6.2.1.3.
l) Clarify requirements to reuse hydrostatic water in paragraph 6.2.2.
m) Add new Section 7 for “Lay-Up Procedures’ Requirements” and included in it all
requirements under previous paragraphs on “Carbon Steel and Low Alloy Steel Equipment”
and “Stainless Steel Equipment”
n) Clarify requirement for lay-up for heat exchangers if not put in service within 14 days of
commencing water filling and 30 days for all other systems in paragraph 7.1.1.
o) Add requirement of continuous pressure monitoring during lay-up in paragraphs 7.2.5,
7.5.6.9, and 7.6.1.
p) Add new paragraph 7.3.3 to mandate including remedial action in the lay-up procedure in
case of lay-up breach and/or lay-up failure for lay-up exceeding 3 months.
q) Re-organize and restructure requirements for wet lay-up in paragraph 7.4, dry lay-up in
Paragraph 7.5, inert gas lay-up in paragraph 7.6, and ambient lay-up in paragraph 7.7.
r) Clarify chemical dosage requirements for prolonged lay-up periods (more than 6 months)
paragraph 7.4.2.7 (f).
s) Clarify requirement to obtain pre-approval before using dry air for dry lay-up in 7.5.1.1.
t) Clarify using prediction models to estimate dry-out time in paragraph 7.5.1.2.
u) Clarify the need to measure dew point during system shut-in in paragraph 7.5.6.
v) Add commentary note to emphasize need for proper water drainage especially for stainless
steel system before inert gas lay-up in paragraph 7.6.3.
w) Restrict use of ambient lay-up to non-critical systems only in paragraph 7.7.1.
x) Re-organize Section 8 “Special Systems’ Requirements” to include utility systems, dry gas
and refined products systems, and sour gas and sour gas pipelines.
y) Add reference to chemical cleaning hydrocarbon services identified in SAES-L-488 in
accordance with SAEP-388 in paragraph 8.4.6.
z) Add new paragraph 8.4.7 to clarify recommended sequence for pre-commissioning of refined
products’ pipelines defined in SAES-L-488.
aa) Clarify the need to dry the lines before the introduction of sour process fluids in 8.5.1.
bb) Clarify the chemical treatment for Sour Gas and Sour Oil Pipelines designed with corrosion
inhibition in paragraph 8.5.2.
cc) Add new Section 9 “Health, Safety and Environmental Requirements”
dd) Add reference to SAES-A-210 “Management of Pyrophoric Wastes” in paragraph 9.5.
ee) Add new Appendices C and D to clarify “Hydrostatic Test and Lay-Up Flow Chart”
ff) Update Approval Authorities based on CSD and R&DC new structure.
gg) Include both English and SI Units.
1 January 2018 Editorial revision to modify paragraphs 6.1.5 and 7.3.1.
Example:
How much ammonium bisulfite (37%wt concentration) will be required to treat 10,000 liter of
water containing 8 mg/liter of dissolved oxygen?
[(10 x 10,000 liter x 8 mg/liter) + 10,000 liter x 20 mg/liter] / 0.37
(feed ratio x volume x oxygen content) + (volume x residual scavenger concentration) / concentration
= (800,000 mg + 200,000 mg) / 0.37
= 2,702,703 mg
This is approx. 2.7 kg of 37% wt. ammonium bisulfite
Assuming a specific gravity of 37 weight % ammonium bisulfite is 1.185
= 2.7 kg / 1.185 kg/liter = 2.3 liters of ammonium bisulfite to be injected.
McKetta, J.J. and Wehe, A.H. 1958. Use This Chart for Water Content of Natural Gases. Petroleum Refiner 37 (8): 153.
Appendix C - Hydrostatic Test and Lay-up Flow Chart for Carbon Steel Systems
Is contact No
time more
than 14 days?
Yes
Plan for O2 Scavenger
Treatment (Paragraph 6.1.3)
Is contact No
time more
than 30 days?
Yes
Plan for Biocide Treatment
(Paragraph 7.4.2.7)
Appendix D - Hydrostatic Test and Lay-up Flow Chart for Stainless Steel Systems
Is contact No
time more
than 4 days?
Yes
Plan for O2 Scavenger
Treatment (Paragraph 6.1.3)
Is contact No
time more
than 14 days?
Yes
Develop Lay-Up Procedure
(Paragraph 7.3)
Is contact No
time more
than 30 days?
Yes
Plan for Biocide Treatment
(Paragraph 7.4.2.7)