Construction Risk Management Plan
Construction Risk Management Plan
Construction Risk Management Plan
Part 1: Preconstruction
Submitted by:
Julie Meredith
SR 520 Program Director
SR 520 Bridge Replacement and HOV Program
Washington State Department of Transportation
600 Stewart Street, Suite 520
Seattle, WA 98101
Table of Contents
1. PROJECT ENDORSEMENT 5
Part 1: Preconstruction
Part 1 of the project management plan describes project management for
preliminary engineering activities up to award of the design-build contract
in January 2010. For the most part, schedule dates that are presented in
Part 1 are the assumed dates that were used for development of the
Design-Build Request for Proposals. In some instances, notation has been
added to this document to provide updated information for clarification of
delivery status. However, the reader is advised that Part 1 was completed
in April 2009 and applies primarily to activities through January 2010.
Except for the limited updates described above, Part 1 has not been
revised beyond that time frame because project management from that
point forward is described in Part 2.
The casting basin and project pontoons will be constructed at the newly
purchased site in Grays Harbor County. The Concrete Technology Corporation’s
facility in Tacoma has been provided to the construction industry as addition
pontoon construction capacity, but will require a complete ESA Analysis if
utilized. Based on the schedule described above, all project pontoons will be
complete by early 2014 and ready for use in case of a catastrophic event on the
existing SR 520 Evergreen Point Bridge.
The 2010 Legislative supplemental budget provided $2.641 billion for the SR 520
Program with intent to complete a new floating bridge across Lake Washington
and Eastside corridor. Of the total program funding, the Pontoon Construction
Project will receive approximately $591 million to complete all work and deliver
pontoons into storage for use on the SR 520 floating bridge. The approximate
allocation of funds to each project phase is as follows:
The PCPACT is currently focused on NEPA and ESA compliance and will later
shift to project permitting. SAFETEA-LU overlays a procedural process on
traditional NEPA coordination, including creation of a group of “Participating
Agencies,” in addition to “Cooperating Agencies.” SAFETEA-LU also establishes
specific review and comment points prior to issuing a draft environmental impact
statement. The additional steps include:
State Agencies
Local Authorities
City of Aberdeen
City of Hoquiam
Grays Harbor County
Port of Grays Harbor
Tribal Authorities
Regional Groups
During Construction, the Pontoon Construction Project Team will follow and
adhere to the WSDOT stewardship agreement with the FHWA.
The SR520 Project desires a strong owner role. With this in mind key project
management positions for decision making and contracting will be staffed with
WSDOT employees. Examples of these are the Engineering Managers and
Project Engineers.
WSDOT Headquarters
Olympic Region
All Pontoon Construction Project construction will occur at sites in Grays Harbor
County. Construction sites are located in the WSDOT Olympic Region, which will
provide direct construction management for the Pontoon Construction Project.
The SR 520 Program, the HQ Construction Office and the Olympic Region
management groups are in the process of establishing a construction
organization and protocols for management of the construction process. An
organizational breakdown is currently being developed and will be included at the
next Project Management Plan update.
3.3.1.5.3 Utilities
Identifies existing utilities in the project vicinity for inclusion in the base
map.
Develops utility relocation plan, as needed.
Coordinates with affected utility owners for identification and relocation of
facilities.
3.3.1.5.4 Roadway
Develops roadway geometrics in accordance with state and local
guidelines.
Coordinates and provides design for traffic mitigation measures.
Coordinates pavement design, and develops paving plans and roadway
sections.
3.3.1.7.3 Gate and Hydraulic Control Structure Electrical and Controls Lead
Manages electrical and controls design of the gate and hydraulic control
structure.
In addition, the project team has prepared a work plan that addresses the tasks
and deliverables for the current biennium as well as the project’s work
breakdown structure and budget. This project work plan is reviewed monthly with
the SR 520 Program Management Team, and quarterly with the task leads. The
work plan will be revised as necessary throughout the current biennium. Three
months prior to the start of a new biennium the work plan will be updated to
include revised and new tasks associated with the current scope of the project.
A detailed Finance Plan has been developed for the SR 520 Pontoon
Construction Project to meet FHWA requirements. This plan was completed in
December 2010, and is expected to be approved in January 2011. The Pontoon
Construction Project Initial Finance Plan includes finance information for the
Pontoon Mitigation and Pontoon Moorage Projects, which will be constructed
under contracts separate from the Pontoon Construction Design-Build Contract.
The initial estimate for pontoon construction was $600 million. Bids lower than
expected resulted in an initial project construction budget of $419 million and risk
reserve of $63 million. The balance of funding was used for preconstruction and
right-of-way activities and will be used to complete environmental mitigation and
the construction of the moorage facility.
Understanding Conflict
The SR 520 Program and project teams will use an approach referred to as
confronting, which is described as problem solving, integrating, collaborating or
win-win style. It involves the conflicting parties meeting face-to-face and
collaborating to reach an agreement that satisfies the concerns of both parties, if
after the first meeting a successful resolution does not occur the project manager
will involve a neutral third party to facilitate resolution. If this approach does not
work, then the process shown on the fourth line of the flow chart below will be
enacted.
The objective of Change Control is to identify the various scope, cost and
schedule impacts to the project, and to help HQ and the projects’ managers
deliver projects on time and on budget as expected. The scope, schedule and
cost, as identified in the budget approved by the Legislature, establish the
baseline from which all work is measured, managed and reported.
These changes can result from a variety of causes. Often, an item is added to
the scope at a partner’s request, after the estimate has been completed and the
agreement signed. The causes of other types of scope and cost change may be
more difficult to identify. For example, the project team may be asked to perform
additional traffic or environmental discipline studies, or the project team during
the design phase directs a change after a drawing is 90 percent complete and
the drawing has to be taken back to the 30 percent design level. These two
examples demonstrate the importance of all members of the project team
knowing the scope of the project.
The specific document used to identify the impacts of such change is called a
Change Request Form. The form requires a written description of the change
The Project Task Manager uses the form to determine whether the identified item
is truly a change in the scope of work. If the Project Task Manager determines
the item constitutes a change, the Change Request is forwarded to the Project
Scheduler and Cost Engineer for analysis. Once Project Controls is complete,
the Project Task Manager determines which review and approval process must
be followed.
WSDOT HQ’s Project Control process has been aligned to coincide with the
development of the quarterly Gray Notebook/Beige Page and Quarterly Project
Report (QPR) updates. (See HQ’s website on Change Management at
http://wwwi.wsdot.wa.gov/ppsc/pgmmgt/dpsb/) The Project Control and
Reporting Manual and the Project Management Online Guide will guide Change
Control for the SR 520 Program.
The Pontoon Construction Project Design Office will develop and maintain the
Project Master Schedule. (See Appendix B: SR 520 Pontoon Construction
Project Integrated Schedule Summary for more detail.) Subsidiary or subnet
schedules to the Project Master Schedule will be assigned to and developed by
the design and construction teams as the project progresses. The Project
Controls Lead will review and manage subsidiary or subnet schedule effects and
inputs to the Project Master Schedule. The Project Master Schedule establishes
the project timeline with emphasis on the timing of the production of key
deliverables and review of project progress.
The Project Master Schedule follows the project’s scope of work breakdown by
task and budget, as outlined in the Work Breakdown Structure. (See Appendix C:
SR 520 Pontoon Construction Project Work Breakdown Structure for more
detail.) The Master Schedule shows procurement activities; indicates the
performance of work relating to the NEPA process, preliminary engineering and
environmental permitting; and shows specified times for delivery, review and
approval by WSDOT, as well as local and federal agencies with jurisdiction. The
Master Schedule integrates all existing consultant schedules, and ties the
schedule through inter-project links so consultants and SR 520 staff maintain
their baselines.
The project’s status, schedule conflicts and changes are reported on in the
Monthly Progress Report prepared by task leaders and distributed to the project
team and other involved parties. It provides a consistent vehicle for reporting and
evaluating progress, and allows the various managers to focus on exceptional
events and negative trends. The Project Controls Lead can also produce special
studies and analyses of particular topics as needed. The format and distribution
of such reports will be tailored to the specific needs of the situation.
Each discipline manager or reporting party will provide the percentage complete,
remaining duration, and actual start and finish of each task. In addition, progress
reports will be provided for each task. The Project Controls Lead will incorporate
the information into the Project Master Schedule, determine the overall status of
the work and produce a series of schedule reports.
The schedule updating process is intended to provide the most accurate picture
possible of the progress achieved by all levels and organizations involved in the
project and to demonstrate the effect of this progress on the overall project
schedule. (See the Business Procedures Manual for more details.)
Schedule Audits
The Project Controls Lead will closely monitor and perform periodic audits of the
consultants and contractors to verify that scheduling software is used properly;
that the resulting schedules and updates meet contractual requirements; and that
In addition, the SR 520 Program Controls Group will perform routine audits of the
Project Master Schedule to ensure that the content and form are consistent with
the project’s scope and goals.
Schedule Analyses
Right of Way needs are identified during the design process by overlaying the
proposed design onto existing right of way limits and examining the differences.
The WSDOT Real Estate services office will help the project determine property
value assessments. Additional markups may be added for appraisals, labor,
property management and other right of way expenses.
Basis of Quantities
Quantities of individual items of work are obtained from various disciplines such
as roadway, traffic, illumination, urban design, existing utilities, structures,
environmental mitigation, and stormwater management. These disciplines
estimate the quantities for items of work that relate to their section of the project.
The quantities are developed using CADD drawings, design standards and
engineering judgment.
The unit prices are based on historical bid prices for similar road construction
projects that were recently advertised, as well as updated prices provided by the
WSDOT Bridge and Structure Office. If historical data is unavailable, unit prices
will be developed from built-up prices based on material, equipment, labor,
markup, etc. If historical data is available but outdated, estimates will rely on a
price escalation factor that accounts for inflation. The final base cost estimate is
calculated by multiplying quantities by the unit prices. WSDOT Region and HQ
support and regional traffic management support should also be considered in
program cost estimate determinations.
4.2.2.6.5 Escalation/Inflation
Cost estimates will be inflated to the Year of Expenditure according to WSDOT
Instructional letter IL 4071.01 dated May 7, 2010
http://wwwi.wsdot.wa.gov/docs/OperatingRulesProcedures/4071.pdf
Inflation rates for construction, right of way, and preliminary engineering will be
estimated using the CPMS inflation tables. (For additional information visit
http://www.wsdot.wa.gov/NR/rdonlyres/FC8BA06E-6561-49FB-AFB9-
27A3B98EA228/0/4071.pdf)
SR 520 Work Product Quality Control Task leads are responsible for ensuring
that a standard process is used to review
and verify work products before they are
finalized.
The SR 520 Program will follow all standard auditing guidelines. Program
management has access to the resources of the Washington State Auditor’s
Office, the State Attorney General’s Office and WSDOT Internal Audits.
Project Controls
Finance Controls
Document Controls
Consultant and Intra-WSDOT Task Agreements
Local Agreements
Utility Agreements
Invoices
The output from the risk management process used on the Pontoon Construction
Project is a risk register that identifies and describes the project risks to be
monitored and controlled; prioritizes the risks by analyzing their probability of
occurrence and their impacts; provides a response strategy and actions to be
taken; and assigns responsibility for monitoring the risk and taking the
appropriate actions to a Pontoon Construction Project Team member.
The risk management process used by the Pontoon Construction Project Team
includes completion of an annual CEVP workshop. The results of these
workshops, as well as the current risk register, are documented in the SR 520
Program’s ProjectWise file.
The following table describes the risk management and response approach that
will be used throughout the life of the Pontoon Construction Project.
Contingency and Risk Reserve funds are the “last resort” and are used
only after all other means for Abatement, Avoidance or Mitigation of risks
have been exhausted.
Use of Contingency funds are “in general” used for typical construction
changes that are within the contingency budget and authority of the
construction manager
Use of the Risk Reserve is managed by the Program Director and is
reserved for the unforeseen changes that are outside the scope and
authority of the construction manager.
Local Government
City of Aberdeen
City of Cosmopolis
City of Cosmopolis Beach
City of Elma
City of Hoquiam
City of McCleary
City of Montesano
City of Oakville
City of Ocean Shores
City of Taholah
City of Westport
Grays Harbor County
Port of Grays Harbor
Co-lead Agencies
Media
Community Groups
General Public
Press releases
Reporter briefings
Media events
Daily tracking of related media stories (maintaining logs)
Major interfaces will be identified between the Pontoon Construction Project and
functional teams. Responsibilities, authorities and communications procedures
(meetings, memorandums, authorizations, reviews, etc.) will be established and
documented at each identified interface.
6.4.2 Audience
To deliver a program the size of SR 520, WSDOT relies on resources from
different agency region offices and groups (HQ, Olympic Region, Northwest
Region), as well as private contractors organized into both functional and project
teams. Because the Pontoon Construction Project will take place in Grays Harbor
County, staff from WSDOT’s Olympic Region will be involved.
The goal of the quality plan is to establish, maintain and continually improve the
efficiency of quality procedures that are consistent with project-specific
requirements. The quality plan is designed to ensure that technical tasks: (1)
result in improved work products and services, (2) are performed according to
accepted industry practice, (3) are consistent with emerging technologies, (4)
comply with laws and regulations, and (5) conform to WSDOT Quality Assurance
policy.
The Pontoon Construction Project will follow the Quality Control and Assurance
Plan that has been developed for the SR 520 Bridge Replacement and HOV
Program, which is incorporated by reference into this document.
For these reasons, the Pontoon Construction Project Management Team is in the
process of developing a “Transition Plan” that will include the following elements:
Project Office. The direction of the Pontoon Construction Project Office, after
completion of the Preliminary Engineering (PE) is to transition project staff to 1)
support pontoon project construction activities, or 2) support other SR 520
Program projects, or 3) non-SR 520 Program assignments.
Early agency and tribal coordination was initiated prior to beginning the
NEPA/SEPA process in order to ensure that milestone NEPA/SEPA decisions -
such as purpose and need, alterative screening criteria, range of alternatives,
and preferred alternative – are aligned with applicable plans, laws and
regulations, tribal treaty rights, and tribal interests. Preliminary design, and
environmental reconnaissance and analysis work will continue to be advanced to
the level necessary to respond to issues of regulatory concern and support
environmentally-informed and compliant decisions throughout the NEPA/SEPA
process.
WSDOT has been working in cooperation with the federal services that oversee
ESA since 2007 to analyze and determine potential effects of the project on ESA-
listed species. The Biological Assessment is expected to be complete in the
spring of 2010, and the Biological Opinion from the services is expected in the
fall of 2010 before the FEIS is issued.
Update, December 2010: The Biological Opinion was signed by NMFS in October 2010.
Close coordination with both the Washington DAHP and interested tribes was
initiated before the NEPA/SEPA process began in order to identify issues early
and ensure decisions that were in alignment with the NHPA and tribal interests.
8.1.2 Construction
The WSDOT Olympic Region will provide most, if not all, staff for day-to-day
management of construction activities during the construction phase. Because
the Pontoon Construction Project will be a design-build project, the design-build
contractor will complete final design during the construction phase. The SR 520
Program office will retain ultimate regional authority and responsibility for project
direction and decisions.
This PMP will be updated to further address the project’s transition phase once
transition plans are complete.
Acceptance of work – Plan for and implement specific procedures for the
acceptance of the work involved in the transition or closure, including
formal acknowledgement of the transfer of responsibility.
Agreements and Commitments – Develop and implement a plan to close
all governmental, local and utility agreements and to close any
environmental commitments.
Demobilization of staff and resources – Plan for and implement specific
procedures for staff reassignment; the return of facilities and equipment;
and the termination of services no longer needed for the project.
Financial closure activities – Review, identify and implement
region/organization and program management requirements, and
Additional information on the project file structure for the SR 520 Program can be
found in the SR 520 Program Quality Control and Assurance Plan. Following the
Quality Audit of a quality control review package, hard copies of the items below
will be filed in the project file:
Additional information on document control for the SR 520 Program can be found
in the referenced SR 520 Business Procedures Manual.
Within the current design-build context, the project team produces a Design
Approval Package (DAP) and initiates the DDP, while the responsibility for
completing the balance of the DDP rests with the design-builder. Allocation of
responsibility for completing the DDP is called out within the DDP Checklist, as
provided within the DAP.
The approved DDP and DAP provide the basis by which WSDOT can defend
itself against litigation concerning project design.
Selection of consultants for the project will comply with WSDOT “Consultant
Services Procedures Manual” M 27-50. Consultant Master Agreement contracts
and Task Orders will be prepared and administered in accordance with WSDOT
Manual M 27-50 and SR 520 Business Management Procedures.
Construction
The project’s contracting strategy must accommodate the project schedule and
budget, and satisfy federal, state and local requirements concerning such issues
as Disadvantaged Business Enterprise (DBE) participation. The selection of
contractors will conform to WSDOT’s contracting procedures, and a competitive
process will be used.
Pontoon Construction Project – Project Management Plan
Part 1: Preconstruction
Data Date: July 2009 Page 61
The WSDOT standard contracting procedures outlined in the documents listed
below will be used in the bidding and contract award process.
For federal fiscal year (FFY) 2006, WSDOT established a proposed interim goal
of 12.70 percent.
WSDOT encourages the voluntary use of DBE firms in the design and
construction of its projects, as these will be counted toward WSDOT’s overall
race-neutral goals. The Office of Equal Opportunity (OEO) is closely monitoring
these race-neutral activities and their results.
Part 1: Preconstruction
Appendices
APPENDIX A: SR 520 PROGRAM CHARTER
APPENDIX B: PONTOON CONSTRUCTION PROJECT
INTEGRATED SCHEDULE SUMMARY
Activity ID SR520 Program Actual Total Cost EAC CPI SPI Start Finish 07 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Plan (Global) Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2
1 SR 520 Bridge Replacement & HOV Program $727,056,554 $24,828,185 $746,302,772 1.09 0.95 07-01-05 A 06-02-23
1.04 SR520 Pontoon Construction Project $712,749,622 $24,668,040 $712,427,704 1.09 0.95 07-01-05 A 10-03-14
1.04.1 Preliminary Engineering Pontoon Project Design U52003 $35,933,345 $23,869,596 $39,084,449 1.09 0.95 07-01-05 A 03-06-12
1.04.1.1 Pontoon Project Site Design $21,853,552 $16,652,241 $21,285,383 1.05 0.96 07-01-05 A 01-28-11
1.04.1.1.01 Project Management / Strategic $5,228,739 $4,532,752 $5,153,859 1.09 0.99 07-01-05 A 11-30-10
1.04.1.1.99 HQ Redistribution / SPMG $1,098,515 $624,794 $1,464,794 0.52 1.00 07-01-07 A 01-28-11
n Complete
1.04.1.1.10 Design / Build $5,490,526 $4,419,795 $4,853,431 1.08 0.87 07-01-07 A 04-30-10
01-25-10 01-25-10*
NTP - #1 Preliminary Design
1.04.1.1.63 Stipends for unsuccessful bidders $2,500,000 $0 $2,500,000 0.00 0.00 12-23-09 02-18-10
1.04.1.2.01 Project Management $1,710,118 $1,209,462 $2,458,126 1.06 0.97 07-01-07 A 01-14-11
1.04.1.2.02 Technical Studies $669,267 $472,990 $573,791 1.40 0.94 01-02-08 A 06-30-10
1.04.1.2.04 Section 106 Consultation $3,038,434 $1,930,089 $2,726,597 1.58 1.03 09-02-08 A 09-10-10
1.04.1.2.05 Endangered Species Act Consultation for Pontoon Constr. $1,410,225 $626,238 $1,776,028 0.95 0.55 07-01-07 A 02-25-11
1.04.1.2.03 NEPA/SEPA Compliance $6,192,912 $2,769,418 $9,346,618 1.04 0.95 07-01-07 A 12-31-10
02-12-10
DEIS
09-09-10
FEIS
08-27-10 09-10-10
FEIS- NOA Published in FR
10-14-10
ROD
09-27-10 10-15-10
Issue ROD
1.04.1.2.07 Permitting Activities $1,058,837 $209,158 $913,305 1.66 1.09 03-03-08 A 03-06-12
1.04.2.1 Pontoon Project Right of Way $10,426,207 $798,444 $6,953,189 0.98 1.01 07-01-07 A 10-03-14
1.04.2.1.03 Leases - Tacoma $4,139,587 $178,487 $678,487 0.94 1.06 07-01-07 A 06-30-13
1.04.2.1.04 Grays Harbor $5,813,638 $532,000 $5,813,638 1.00 1.00 07-01-07 A 10-03-14
1.04.3 Construction Pontoon Project Construction U52003A / 00 $666,390,070 $0 $666,390,066 0.00 0.00 04-01-09 A 06-11-14
1.04.3.1.01 Grays Harbor Construction $644,375,254 $0 $644,375,250 0.00 0.00 04-01-09 A 05-22-14
11-07-12
D/B Pontoon Site Design & Construction
03-19-12 03-19-12
Pontoon Bay 1 Completed
1.11 SR520 Pontoon Mitigation Project $14,306,932 $127,776 $14,696,699 0.95 0.90 01-02-08 A 06-02-23
07-21-11 07-21-11
Plans ready for Ad
1.15 SR520 Pontoon Site Restoration Project $0 $32,369 $478,369 0.77 1.06 08-12-09 A 02-08-10
1.04.1.1.02 Engineering
1.04.1.1.XX Deobligation
1.04.1.2.00 Milestones
1.11.1.3.06 Mitigation
Last Review Date Estimated PE Cost 37.0 $M Expected Value Total Risk After Response -19.7 $M Design/PS&E 1.8 $M 2.1 $M Utilities 0.0 $M 0.0 $M
Environmental &
Project Manager Estimated ROW Cost 16.9 $M Estimated Cost to Respond 0.0 $M Railroad 0.0 $M 0.0 $M 0.4 $M 5.6 $M
Hydraulics
Est $ Impact of Signficant
Partnerships and Contracting and
Project Risks ( cost & Estimated CN Cost 693.4 $M Potential Cost Savings 2.5 $M 0.4 $M 0.4 $M 2.1 $M 2.2 $M
schedule)
Stakeholders Procurement
Pre-Response Post-Response
Responded Probability
Response Strategy
(cost of delay +
Update History
Risk Owner
Probability/
RBS Group
Response)
or WSDOT)
Probability
Probability
Summary Detailed Description of Risk Event
ACTION TO BE TAKEN Responded Risk
Impact
Impact
Status
Risk #
Phase
Description (Specific, Measurable, Attributable, Relevant, Risk Risk Impact Date, Status and
Type Risk Matrix Response Actions including advantages Impact Risk Matrix
Threat and/or Timebound) Trigger ($M or Mo) Review Comments
and disadvantages (include dates) ($M or Mo)
Opportunity [SMART]
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) [10a] (11) (12) (13) (14) (15) (15a) (16) (17) (18) (19) (20) (21) (22) [22a] (23) (24) (25) (26) (27) (28) (28a)
Very Low
Very Low
-0.3$M
-0.3$M
Cost
50%
50%
MAX -2.0$M H MAX -2.0$M H
Probability
Most Likely -0.5$M M $,Mo Most Likely -0.5$M -$0.1 M $,Mo
Probability
Moderate
Moderate
Active
0.2$M
0.3$M
VE1
Design/PS&E
Very Low
Very Low
Schedule
0.4 $M
0.5 $M
0.8Mo
MAX 3.0Mo VL L M H VH MAX 3.0Mo 0.8Mo 0.0Mo VL L M H VH
Threat Most Likely 1.5Mo Impact Most Likely 1.5Mo 0.0Mo Impact
-9.4$M
-9.4$M
Cost
75%
75%
Low
Low
MAX -15.0$M H Mo $ MAX ###### H Mo $
Probability
Most Likely -12.5$M M Most Likely ###### $0.1 M
Probability
VE recommendation #2, modifications for the basin floor. VE
-9.7$M
-9.8$M
Active
High
High
decision report revises VE design to use lesser different type of piles
VE2
Design/PS&E
Very Low
Very Low
Schedule
-0.4 $M
-0.5 $M
-0.8Mo
MAX -2.0Mo VL L M H VH MAX -2.0Mo -0.8Mo 0.0Mo VL L M H VH
Opportunity Most Likely -1.0Mo Impact Most Likely -1.0Mo 0.0Mo Impact
-4.0$M
-4.0$M
Cost
33%
33%
Low
Low
MAX -15.0$M H MAX ###### H
Probability
Most Likely -12.0$M M Most Likely ###### $0.1 M
Probability
-4.1$M
-4.2$M
Active
Low
Low
Design/PS&E
Wall-Center L Mo $ L Mo $ Contractor
Implementation of a fully movable wall.
Current
Very Low
Schedule
-0.2 $M
-0.2 $M
-0.5Mo
Opportunity Most Likely -1.5Mo Impact Most Likely -1.5Mo 0.0Mo Impact
Moderate
Moderate
-22.5$M
-22.5$M
Cost
75%
75%
MAX -60.0$M H Mo $ MAX ###### H Mo $
Probability
VE recommendation #5, revised basin concept (at grade casting Most Likely -30.0$M M Most Likely ###### $0.7 M
Probability
-23.9$M
-24.6$M
yard). This recommendation is mutually exclusive from VE
Active
High
High
VE5
Design/PS&E
At Grade Casting Yard recommendations 1 through 4. Add a risk for schedule delay due to L L Contractor
this VE recommendation (correlated with this opportunity), delay of 0
to 9 months for NEPA/permitting, 25% probability.
Current
Very Low
Schedule
-1.4 $M
-2.1 $M
-3.4Mo
Opportunity Most Likely -4.5Mo Impact Most Likely -4.5Mo 0.0Mo Impact
Moderate
Moderate
6-Aug-09
4.7$M
4.7$M
Cost
25%
25%
MAX 24.9$M H MAX $24.9 H
Probability
Most Likely 18.7$M M Most Likely $18.7 $0.0 M
Construction
Construction
Change Order is
CNS 900.07
Acceptance
Probability
Corridor
required to create There is a chance that a delay to this project causes permanent
Active
4.7$M
4.7$M
ROD is not
Low
Low
Design/PS&E
permanent Pontoon pontoon moorage to be necessary while only temporary is costed in L $ Update this risk as more information becomes available. L $ WSDOT
obtained as
Moorage due to effect the base costs.
scheduled
on the next project
Current
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
1.1$M
1.1$M
Contracting and Procurement
Cost
15%
15%
Low
Low
MAX 10.0$M H MAX $10.0 H
Issues with contract documents due to short time line; change
Probability
permit conditions from assumptions; alternative technical concepts; Most Likely 7.5$M M Most Likely $7.5 $0.0 M
Construction
CTR 40.02
Probability
Additional project RFP document will be issued on partial pontoon design could lead to
Mitigation
Very Low
Very Low
Active
1.1$M
1.1$M
costs incurred due to more or less costs when final design is completed; With only 3 Increase the amount of the stipend; Limit the amount and changes that are in
Design/PS&E
L L Contractor
current accelerated months for the RFP response, the contractor may be less the addendums that would require any type of redesign;
base schedule comfortable with their design and bid up price to cover the
Current
uncertainty; premium may apply to the casting basin costs 2.5% to MIN VL $ MIN 0.0Mo VL $
Schedule
NO RISK
NO RISK
0.0 $M
0.0 $M
5% of the casting basin costs
0.0Mo
Very Low
Very Low
2.0$M
2.0$M
100%
100%
Cost
Probability
Design/PS&E
Acceptance
DES 10.01
Probability
Local road Haul route improvement costs don't seem to be in the base;
Very High
Very High
Active
2.0$M
2.0$M
maintenance that the discussions with the cities and the Port have occurred and may
Design/PS&E
O RISK
O RISK
0.0 $M
0.0 $M
0.0Mo
Last Review Date Estimated PE Cost 37.0 $M Expected Value Total Risk After Response -19.7 $M Design/PS&E 1.8 $M 2.1 $M Utilities 0.0 $M 0.0 $M
Environmental &
Project Manager Estimated ROW Cost 16.9 $M Estimated Cost to Respond 0.0 $M Railroad 0.0 $M 0.0 $M 0.4 $M 5.6 $M
Hydraulics
Est $ Impact of Signficant
Partnerships and Contracting and
Project Risks ( cost & Estimated CN Cost 693.4 $M Potential Cost Savings 2.5 $M 0.4 $M 0.4 $M 2.1 $M 2.2 $M
schedule)
Stakeholders Procurement
Pre-Response Post-Response
Responded Probability
Response Strategy
(cost of delay +
Update History
Risk Owner
Probability/
RBS Group
Response)
or WSDOT)
Probability
Probability
Summary Detailed Description of Risk Event
ACTION TO BE TAKEN Responded Risk
Impact
Impact
Status
Risk #
Phase
Description (Specific, Measurable, Attributable, Relevant, Risk Risk Impact Date, Status and
Type Risk Matrix Response Actions including advantages Impact Risk Matrix
Threat and/or Timebound) Trigger ($M or Mo) Review Comments
and disadvantages (include dates) ($M or Mo)
Opportunity [SMART]
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) [10a] (11) (12) (13) (14) (15) (15a) (16) (17) (18) (19) (20) (21) (22) [22a] (23) (24) (25) (26) (27) (28) (28a)
0
N
N
S
Most Likely Impact Most Likely 0.0Mo Impact
Very Low
Very Low
6-Aug-09
1.0$M
1.0$M
Cost
50%
50%
MAX 3.0$M H MAX 3.0$M H
Probability
Most Likely 2.0$M M $ Most Likely 2.0$M $0.0 M $
Right Of Way
Construction
Acceptance
ROW 50.03
Probability
Concrete Tech agrees
Moderate
Moderate
CTC
Active
1.0$M
1.0$M
to work on site but Updated: CTC has not been saying that they will require any
Design/PS&E
Schedule
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
MAX VL L M H VH MAX 0.0Mo 0.0Mo VL L M H VH
Very Low
Very Low
0.2$M
0.2$M
Cost
15%
15%
Environmental & Hydraulics
Probability
Most Likely 1.0$M M Most Likely 1.0$M -$0.3 M
Construction
Acceptance
ENV 40.01
Probability
Very Low
Very Low
Potential issues with Artifacts discovered during construction, historical burial discovery
Active
1.1$M
1.3$M
Write the MOA to assume they may find some cultural resources; Complete
Design/PS&E
Section 106 during during construction; Update Two, currrently the site is undergoing a L L WSDOT
extensive cultural resource investigations;
construction cultural resources review so expect less chance of an issue during
construction.
Current
Very Low
Very Low
Schedule
0.9 $M
1.2 $M
1.4Mo
MAX 12.0Mo VL L M H VH MAX 12.0Mo 1.4Mo 0.0Mo VL L M H VH
Threat Most Likely 9.0Mo Impact Most Likely 9.0Mo 0.0Mo Impact
MIN VH MIN VH
May-09
23-Jun-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
40%
20%
MAX H MAX H
Probability
Most Likely M Mo Most Likely $1.2 M
Right Of Way
Construction
ROW 50.04
Mitigation
If CTC refused because of environmental regulations and had to Met with CTC and will meet every other Thursday with the services to make a
Active
1.2$M
0.0$M
on site, have to build
Low
Design/PS&E
move to build all pontoons at Gray's Harbor; Risk 50.04 and Risk L case that consultation is not necessary, failing that the team will negotiate L Mo WSDOT
all pontoons at Gray's
50.03 are mutually exclusive terms that are acceptable to CTC.
Harbor
Current
Very Low
Schedule
1.2 $M
0.0 $M
2.4Mo
Threat Most Likely 6.0Mo Impact Most Likely 6.0Mo 1.2Mo Impact
MIN VH MIN VH
May-09
6-Aug-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
10%
10%
Environmental & Hydraulics
14 hour work days are planned, could include extensive pile driving, MAX H MAX H
this could lead to community opposition to noise and vibration
Probability
Most Likely M Most Likely -$0.3 M
Construction
Acceptance
ENV 80.02
Probability
Very Low
over time there could be opposition due to long work days and day
Active
0.9$M
1.1$M
construction lead to Currently planning work hours of 7am to 9pm and keep the City of Aberdeen
Design/PS&E
after day of noise. Reduction in the work hours would be the impact L L Contractor
alteration of informed.
if community opposition occurs. Already employing 3 sets of crews
construction plan
which is the maximum possible. Update Two: The cities seem
Current
Very Low
Schedule
1.1 $M
0.2Mo
Threat Most Likely 1.5Mo Impact Most Likely 1.5Mo 0.0Mo Impact
MIN VH MIN VH
May-09
23-Jun-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
Environmental & Hydraulics
7%
7%
MAX H MAX H
Probability
Pre-construction
Probability
Very Low
Active
1.8$M
1.3$M
Legal Challenge to groups, NGOs, etc. (will team up) as a result of construction site.
Design/PS&E
Very Low
Schedule
1.8 $M
1.3 $M
0.9Mo
Threat Most Likely 13.5Mo Impact Most Likely 13.5Mo 0.0Mo Impact
Very Low
Very Low
1.0$M
1.0$M
Contracting and Procurement
Cost
50%
50%
MAX 2.0$M H MAX 2.0$M H
Probability
Most Likely 2.0$M M $ Most Likely 2.0$M $0.0 M $
Construction
CTR 50.03
Probability
Moderate
Active
1.0$M
1.0$M
use some stainless steel and this can be difficult to get domestic;
Design/PS&E
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
MIN VH MIN VH
May-09
15-May-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
30%
30%
MAX H MAX H
Probability
Most Likely M Most Likely $0.0 M
Construction
Construction
CNS 40.08
Probability
Risk of delay to Contractor may need to do the mock up more than once until
Active
0.9$M
0.9$M
pontoon construction accepted; have seen this issue in past projects; minor changes won'
Low
Low
sign/PS&E
L Mo L Mo
due to unacceptable trigger a new mockup; Base assumes 4 months after ROD to allow
mock up for a mockup;
rent
ow
ule
M
o
Post- Pre- Post- Pre-
Project Title WSDOT SR-520 Pontoon Construction RISK MANAGEMENT SUMMARY RESULTS Functional Area
Response Response
Functional Area
Response Response
Management /
Estimate Date Target AD date 07/17/09 Planned and Actual ($ M) Construction 4.7 $M 5.7 $M 0.0 $M 0.0 $M
Funding
Project PIN # Estimated CN Duration 57.9Mo Expected Value Total Risk Before Response -17.1 $M Right-of-Way 0.0 $M 0.0 $M Structures & Geo-tech 1.6 $M 1.6 $M
Last Review Date Estimated PE Cost 37.0 $M Expected Value Total Risk After Response -19.7 $M Design/PS&E 1.8 $M 2.1 $M Utilities 0.0 $M 0.0 $M
Environmental &
Project Manager Estimated ROW Cost 16.9 $M Estimated Cost to Respond 0.0 $M Railroad 0.0 $M 0.0 $M 0.4 $M 5.6 $M
Hydraulics
Est $ Impact of Signficant
Partnerships and Contracting and
Project Risks ( cost & Estimated CN Cost 693.4 $M Potential Cost Savings 2.5 $M 0.4 $M 0.4 $M 2.1 $M 2.2 $M
schedule)
Stakeholders Procurement
Pre-Response Post-Response
Responded Probability
Response Strategy
(cost of delay +
Update History
Risk Owner
Probability/
RBS Group
Response)
or WSDOT)
Probability
Probability
Summary Detailed Description of Risk Event
ACTION TO BE TAKEN Responded Risk
Impact
Impact
Status
Risk #
Phase
Description (Specific, Measurable, Attributable, Relevant, Risk Risk Impact Date, Status and
Type Risk Matrix Response Actions including advantages Impact Risk Matrix
Threat and/or Timebound) Trigger ($M or Mo) Review Comments
and disadvantages (include dates) ($M or Mo)
Opportunity [SMART]
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) [10a] (11) (12) (13) (14) (15) (15a) (16) (17) (18) (19) (20) (21) (22) [22a] (23) (24) (25) (26) (27) (28) (28a)
0.9 $M
0.9 $M
Des
1.1Mo
Very Lo
Very Lo
Schedu
Cur
Threat Most Likely 3.5Mo Impact Most Likely 3.5Mo 0.0Mo Impact
NO RISK
NO RISK
0.0$M
0.0$M
Cost
75%
75%
Environmental & Hydraulics
Probability
Most Likely 1.1$M M Most Likely 1.1$M $0.0 M
Construction
ENV 50.02
Probability
NO RISK
NO RISK
Retired
Soil Contamination Would add cost but if caught early would not lead to schedule
0.0$M
0.0$M
Design/PS&E
discovery during pre- impacts Retired as of final update, Geotech did not find L L
construction/geo-tech contamination. Retired as of Update Two.
Current
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
MAX VL L M H VH MAX 0.0Mo 0.0Mo VL L M H VH
Very Low
Very Low
-0.8$M
-0.8$M
with an opportunity to develop a more innovative or cost effective
Cost
50%
50%
design. RFP will have some restrictions because there is another MAX -2.0$M H MAX -2.0$M H
project coming after this that would also need to use the same
Probability
Opportunity for
Design/PS&E
Probability
Contractor Innovation
Moderate
Moderate
remove one of the gates; change the wall type; savings (low end)
-0.8$M
-0.8$M
Active
could be single gate $8M to $12M savings, different pile types (pre- L L
Design or Construction
cast concrete pile is the base) possibly $10M savings on foundation
Methods (Excavation
driving from a floating crane inside the hole could save 1 to 2
Current
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
move to sheetpile or MSE wall, $4M to $5M savings; Possibly no MAX VL L M H VH MAX 0.0Mo 0.0Mo VL L M H VH
need for the wall; Excavation changes $1M to $3M savings Steep
Slopes
Most Likely Impact Most Likely 0.0Mo Impact
MIN VH MIN VH
May-09
6-Aug-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
50%
25%
MAX H MAX H
Probability
Pre-construction
Design/PS&E
Probability
WSDOT to apply for most of the permits not requiring contractor to do this;
Moderate
Mitigation
No time in the construction schedule to allow for permit changes in
Active
1.8$M
0.3$M
Delay to final design of Those permits that are more concerned with work process will be obtained by
Low
Design/PS&E
final design; Corps permit may be the big issue as the permit may L L Mo Contractor
facilities the design builder. Environmental impacts are captured elsewhere for NEPA,
have to be reinitiated and lead to a delay;
changing the impacts to 1 to 3 months.
Current
Very Low
Schedule
1.8 $M
0.3 $M
2.8Mo
Threat Most Likely 5.5Mo Impact Most Likely 2.0Mo 2.3Mo Impact
MIN VH MIN VH
May-09
6-Aug-09
NO RISK
NO RISK
0.0$M
0.0$M
Contracting and Procurement
Cost
50%
25%
MAX H MAX H
Follow WSDOT's proven design builder process; WSDOT is holding a
Probability
Pre-construction
Most Likely M Mo voluntary submitters meeting on July 1, 2009, to provide potential bidders with Most Likely $0.0 M
CTR 30.01
Probability
Mitigation
information and answer questions; Work with other support groups on
Active
0.1$M
0.1$M
Delays in proposal preparation time; depending on the severity of the
Low
Design/PS&E
L addendum coordination and set key milestone dates for when major changes L Mo WSDOT
Ad/Bid/Award Process addendum delay could be larger; there is a tight schedule for this
are accepted. Weekly coordination meetings with AG's office. Update,
large of a job.
submittals have been tendered to WSDOT still on schedule. Still chance of a
Current
Very Low
Schedule
0.1 $M
1.0Mo
Threat Most Likely 2.0Mo Impact Most Likely 2.0Mo 0.5Mo Impact
MIN VH MIN VH
May-09
23-Jun-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
10%
10%
Environmental & Hydraulics
MAX H MAX H
Probability
Most Likely M Most Likely -$0.1 M
Construction
ENV 80.03
Probability
Very Low
One truck every 30 seconds during basin excavation for 6 to 8
Active
0.2$M
0.3$M
community complaints When VE recommendation #5 occurs this risk lessens in impact. Correlate
Design/PS&E
months. This can lead to long traffic queues. If reduce the number L L Contractor
either air quality or this mitigated impact with the VE#5 Opportunity.
of trucks by 50% leads to the 6 month upper impact
traffic.
Current
Very Low
Schedule
0.2 $M
0.3 $M
0.5Mo
Threat Most Likely 5.0Mo Impact Most Likely 2.5Mo 0.3Mo Impact
MIN VH MIN VH
May-09
23-Jun-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
15%
15%
Environmental & Hydraulics
MAX H MAX H
Probability
Pre-construction
Probability
Corps of Engineers
Very Low
Very Low
Corps might not accept this site as the Least Environmentally
Active
0.2$M
0.5$M
May Not Accept Grays Continue to work with WSDOT execs and Quinault indian nation in
Design/PS&E
Very Low
Schedule
0.2 $M
0.5 $M
0.5Mo
Threat Most Likely 3.0Mo Impact Most Likely 3.0Mo 0.0Mo Impact
MIN VH MIN VH
May-09
15-May-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
10%
10%
MAX H MAX H
Probability
Most Likely M Most Likely $0.1 M
nstruction
nstruction
NS 30.04
robability
Very Low
Very Low
Risk that fish windows
Active
0.1$M
0.0$M
June 15th through Feb 28th is the assumed fish window; base
S&E
Last Review Date Estimated PE Cost 37.0 $M Expected Value Total Risk After Response -19.7 $M Design/PS&E 1.8 $M 2.1 $M Utilities 0.0 $M 0.0 $M
Environmental &
Project Manager Estimated ROW Cost 16.9 $M Estimated Cost to Respond 0.0 $M Railroad 0.0 $M 0.0 $M 0.4 $M 5.6 $M
Hydraulics
Est $ Impact of Signficant
Partnerships and Contracting and
Project Risks ( cost & Estimated CN Cost 693.4 $M Potential Cost Savings 2.5 $M 0.4 $M 0.4 $M 2.1 $M 2.2 $M
schedule)
Stakeholders Procurement
Pre-Response Post-Response
Responded Probability
Response Strategy
(cost of delay +
Update History
Risk Owner
Probability/
RBS Group
Response)
or WSDOT)
Probability
Probability
Summary Detailed Description of Risk Event
ACTION TO BE TAKEN Responded Risk
Impact
Impact
Status
Risk #
Phase
Description (Specific, Measurable, Attributable, Relevant, Risk Risk Impact Date, Status and
Type Risk Matrix Response Actions including advantages Impact Risk Matrix
Threat and/or Timebound) Trigger ($M or Mo) Review Comments
and disadvantages (include dates) ($M or Mo)
Opportunity [SMART]
(0) (1) (2) (3) (4) (5) (15) [22a] (23) (28)
float out (6) (7) (8) (9) (10) [10a] (11) (12) (13) (14) (15a) (16) (17) (18) (19) (20) (21) (22) (24) (25) (26) (27) (28a)
A
are missed
Con
Con
Design/PS
CN
Pr
V
V
Current
Very Low
Very Low
Schedule
0.1 $M
0.0 $M
0.2Mo
MAX 3.0Mo VL L M H VH MAX 3.0Mo 0.2Mo 0.0Mo VL L M H VH
Threat Most Likely 2.0Mo Impact Most Likely 2.0Mo 0.0Mo Impact
MIN VH MIN VH
May-09
15-May-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
Environmental & Hydraulics
5%
5%
MAX H MAX H
Probability
Pre-construction
Probability
Very Low
Very Low
Corps has to deal with extensive comments on their permit or the
Active
0.1$M
0.2$M
Risk of the 401/404
Design/PS&E
Very Low
Very Low
Schedule
0.1 $M
0.2 $M
0.2Mo
MAX 4.0Mo VL L M H VH MAX 4.0Mo 0.2Mo 0.0Mo VL L M H VH
Threat Most Likely 3.0Mo Impact Most Likely 3.0Mo 0.0Mo Impact
MIN VH MIN VH
May-09
15-May-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
20%
20%
MAX H MAX H
Probability
Most Likely M Most Likely $0.0 M
Construction
Construction
CNS 40.03
Probability
Uncertain production
Active
0.1$M
0.2$M
20 hrs per day excavation assumed equates to a truck every 30
Low
Low
Design/PS&E
Very Low
Very Low
Schedule
0.1 $M
0.2 $M
0.2Mo
Threat Most Likely 0.8Mo Impact Most Likely 0.8Mo 0.0Mo Impact
MIN VH MIN VH
May-09
15-May-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
Environmental & Hydraulics
5%
5%
MAX H MAX H
Probability
Pre-construction
Probability
Very Low
Other Endangered
Active
0.0$M
0.0$M
incremental consultation process; minor issues may occur with
Design/PS&E
Very Low
Schedule
0.0 $M
0.0 $M
0.2Mo
Threat Most Likely 3.0Mo Impact Most Likely 3.0Mo 0.0Mo Impact
MIN VH MIN VH
May-09
6-Aug-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
15%
15%
Environmental & Hydraulics
MAX H MAX H
Probability
Most Likely M Most Likely $0.0 M
Construction
Acceptance
ENV 30.03
Probability
DNR aquatic land use lease, HPA, Shoreline, Section 10. Risk is
Very Low
Very Low
Delay in Gray's Harbor
Active
0.4$M
0.4$M
that DNR requests information late before willing to issue the aquatic
Design/PS&E
Very Low
Schedule
0.4 $M
0.4 $M
0.5Mo
Threat Most Likely 3.0Mo Impact Most Likely 3.0Mo 0.0Mo Impact
MIN VH MIN VH
May-09
15-May-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
Environmental & Hydraulics
5%
5%
MAX H MAX H
Probability
Most Likely M Most Likely -$0.1 M
Construction
ENV 30.05
Probability
DNR aquatic land use lease, HPA, Shoreline, Section 10, DMMO
Very Low
Very Low
Active
0.3$M
0.4$M
Delay in dredge (Dredge Material Management Office). Risk is that DNR requests
Design/PS&E
L L WSDOT
channel construction information late before willing to issue the aquatic land use lease;
Believes there is enough time to address issues with DNR.
Current
Very Low
Schedule
0.3 $M
0.4 $M
0.2Mo
Threat Most Likely 3.0Mo Impact Most Likely 3.0Mo 0.0Mo Impact
MIN VH MIN VH
May-09
23-Jun-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
20%
20%
Environmental & Hydraulics
MAX H MAX H
Probability
Currently contemplating sites that don’t require much excavation, Most Likely M Most Likely $0.0 M
Construction
ENV 40.04
Probability
Cultural Resources such as converted intertidal areas. Field reconnaissance will be done
Mitigation
Identify the site and do the cultural survey. This mitigation will not impact the
Active
0.0$M
0.0$M
Issues at Mitigation during the wetland survey. A database evaluation has been done on
Low
Low
Design/PS&E
L Mo critical path of the delivery of the pontoons and therefore does not have delay L Mo WSDOT
Site cause delay currently identified sites. Possibility of encountering cultural issues
to the pontoon project but could delay the completion of the mitigation project.
during construction since 4 sites that are possible all had tribal villages at some point in
Current
Very Low
Schedule
0.0 $M
0.0 $M
0.9Mo
Threat Most Likely 4.5Mo Impact Most Likely 4.5Mo 0.0Mo Impact
Very Low
Very Low
0.2$M
0.2$M
Cost
30%
30%
Hydraulics
ability
Most Likely 0.8$M M Most Likely 0.8$M $0.0 M
tion
.02
ity
M
Post- Pre- Post- Pre-
Project Title WSDOT SR-520 Pontoon Construction RISK MANAGEMENT SUMMARY RESULTS Functional Area
Response Response
Functional Area
Response Response
Management /
Estimate Date Target AD date 07/17/09 Planned and Actual ($ M) Construction 4.7 $M 5.7 $M 0.0 $M 0.0 $M
Funding
Project PIN # Estimated CN Duration 57.9Mo Expected Value Total Risk Before Response -17.1 $M Right-of-Way 0.0 $M 0.0 $M Structures & Geo-tech 1.6 $M 1.6 $M
Last Review Date Estimated PE Cost 37.0 $M Expected Value Total Risk After Response -19.7 $M Design/PS&E 1.8 $M 2.1 $M Utilities 0.0 $M 0.0 $M
Environmental &
Project Manager Estimated ROW Cost 16.9 $M Estimated Cost to Respond 0.0 $M Railroad 0.0 $M 0.0 $M 0.4 $M 5.6 $M
Hydraulics
Est $ Impact of Signficant
Partnerships and Contracting and
Project Risks ( cost & Estimated CN Cost 693.4 $M Potential Cost Savings 2.5 $M 0.4 $M 0.4 $M 2.1 $M 2.2 $M
schedule)
Stakeholders Procurement
Pre-Response Post-Response
Responded Probability
Response Strategy
(cost of delay +
Update History
Risk Owner
Probability/
RBS Group
Response)
or WSDOT)
Probability
Probability
Summary Detailed Description of Risk Event
ACTION TO BE TAKEN Responded Risk
Impact
Impact
Status
Risk #
Phase
Description (Specific, Measurable, Attributable, Relevant, Risk Risk Impact Date, Status and
Type Risk Matrix Response Actions including advantages Impact Risk Matrix
Threat and/or Timebound) Trigger ($M or Mo) Review Comments
and disadvantages (include dates) ($M or Mo)
Opportunity [SMART]
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) [10a] (11) (12) (13) (14) (15) (15a) (16) (17) (18) (19) (20) (21) (22) [22a] (23) (24) (25) (26) (27) (28) (28a)
Proba
Dredge material is not
Construct
Active
0.2$M
0.2$M
Probabil
ENV 900
Environmental &
Low
Low
Design/PS&E
Schedule
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
MAX VL L M H VH MAX 0.0Mo 0.0Mo VL L M H VH
NO RISK
NO RISK
0.0$M
0.0$M
Cost
50%
50%
MAX 2.0$M H MAX 2.0$M H
Maximum necessary may require 2 commercial properties
Probability
Pre-construction
relocation, widen some roads may require some more row. Volume
ROW 50.07
Probability
NO RISK
NO RISK
Retired
Traffic issues lead to of truck traffic may lead to more row necessary to mitigate the traffic
0.0$M
0.0$M
Design/PS&E
more ROW acquisition impacts on congestion; delay risk comes from if had to move to L L Contractor
necessary condemnation. Updated due to assignment of this risk to the
contractor, believe they will price in a higher probability than in past
Current
Very Low
Schedule
NO RISK
0.0 $M
0.0 $M
0.0Mo
MAX 3.0Mo VL L M H VH MAX 3.0Mo 0.0Mo 0.0Mo VL L M H VH
Threat Most Likely 2.5Mo Impact Most Likely 2.5Mo 0.0Mo Impact
Very Low
Very Low
-0.5$M
-0.5$M
Cost
33%
33%
MAX -2.0$M H MAX -2.0$M H
Probability
Most Likely -1.5$M M Most Likely -1.5$M $0.0 M
Construction
Construction
CNS 40.01
Probability
Production rate due to Have defined a wet weather season from oct 15th to april 15th, lowe
-0.5$M
-0.5$M
Active
weather is better or production rates for weather affected activities; basin excavation
Low
Low
Design/PS&E
L $ L $
worse than assumed affected, base will be changed to gravel borrow, opportunity to use
in the base less costly method. -1.0, 0.0, 1.0 Impact
Current
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
Threat Most Likely 0.0Mo Impact Most Likely 0.0Mo 0.0Mo Impact
Very Low
Very Low
0.5$M
0.5$M
Cost
80%
80%
MAX 1.0$M H MAX 1.0$M H
Probability
Most Likely 0.6$M M Most Likely 0.6$M $0.0 M
Construction
Construction
CNS 900.05
Probability
Settlement occurs at
Very High
Very High
Applies to site grading, utilities; stormwater, conduit; estimates 4 to
Active
0.5$M
0.5$M
the site leading to
Design/PS&E
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
MIN VH MIN VH
May-09
15-May-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
10%
10%
MAX H MAX H
Structures & Geo-tech
Probability
Most Likely M Most Likely $0.0 M
Construction
STG 20.02
Probability
Productivity of pile
Very Low
Very Low
Base assumes 5.5 piles per day per crew for each 3 crews over a 14
Active
0.0$M
0.0$M
driving is uncertain
Design/PS&E
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
Threat Most Likely 0.0Mo Impact Most Likely 0.0Mo 0.0Mo Impact
Very Low
6-Aug-09
1.6$M
1.6$M
due to negative issues that can arise due to no hazard analysis
Cost
80%
80%
Geotechnical baseline information being available before the bid; seismic risk issues; MAX 3.0$M H MAX 3.0$M H
Structures & Geo-tech
report will not contain assumption is design criteria for 1,000 year event life safety only;
Probability
Most Likely 2.0$M M Most Likely 2.0$M $0.0 M
Construction
hazard analysis and ground improvements may be necessary to solve the issue leading
STG 30.01
Probability
Very High
Very High
due to lack of to high cost; IBC requires for special structures if there is an
Active
1.6$M
1.6$M
Design/PS&E
information there is a applicable code use that if not the owner develops a specific code; L L Contractor
higher risk of a higher could design to survive lesser earthquakes; upper cost is design to
bid due to fears that make the structural serviceable after an earthquake; have the
Current
lateral spreading contractor to design for lateral spreading; risk is for lateral spreading
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
occurs costs; analysis supplied is conservative; cost is to allow the structure MAX VL L M H VH MAX 0.0Mo 0.0Mo VL L M H VH
to hold together and float if it has to move sideways because of
liquifaction. Update: Geotech information now seems to indicate
Most Likely Impact Most Likely 0.0Mo Impact
that lateral spreading will occur.
Very Low
Very Low
0.2$M
0.2$M
Cost
20%
20%
MAX 1.0$M H MAX 1.0$M H
Discussions with the city to solidify haul routes have not occurred;
Probability
changes may occur; some concern has been expressed about base
Design/PS&E
Probability
Change to base haul routes; if a different route is chosen could be different traffic
Active
0.2$M
0.2$M
assumed haul routes mitigation necessary; basin excavation is the activity that could be
Low
Low
Design/PS&E
L $ L $
lead to delay and/or delayed if the haul routes are changed; possibly improvements
costs required by the city in negotiations could also require new ROW;
Current
this risk should be carried by WSDOT as earlier solution reduces the MIN VL MIN 0.0Mo VL
Schedule
NO RISK
NO RISK
0.0 $M
0.0 $M
impact greatly.
0.0Mo
MIN VH MIN VH
May-09
5-May-09
O RISK
O RISK
0.0$M
0.0$M
Cost
10%
10%
MAX H MAX H
Post- Pre- Post- Pre-
Project Title WSDOT SR-520 Pontoon Construction RISK MANAGEMENT SUMMARY RESULTS Functional Area
Response Response
Functional Area
Response Response
Management /
Estimate Date Target AD date 07/17/09 Planned and Actual ($ M) Construction 4.7 $M 5.7 $M 0.0 $M 0.0 $M
Funding
Project PIN # Estimated CN Duration 57.9Mo Expected Value Total Risk Before Response -17.1 $M Right-of-Way 0.0 $M 0.0 $M Structures & Geo-tech 1.6 $M 1.6 $M
Last Review Date Estimated PE Cost 37.0 $M Expected Value Total Risk After Response -19.7 $M Design/PS&E 1.8 $M 2.1 $M Utilities 0.0 $M 0.0 $M
Environmental &
Project Manager Estimated ROW Cost 16.9 $M Estimated Cost to Respond 0.0 $M Railroad 0.0 $M 0.0 $M 0.4 $M 5.6 $M
Hydraulics
Est $ Impact of Signficant
Partnerships and Contracting and
Project Risks ( cost & Estimated CN Cost 693.4 $M Potential Cost Savings 2.5 $M 0.4 $M 0.4 $M 2.1 $M 2.2 $M
schedule)
Stakeholders Procurement
Pre-Response Post-Response
Responded Probability
Response Strategy
(cost of delay +
Update History
Risk Owner
Probability/
RBS Group
Response)
or WSDOT)
Probability
Probability
Summary Detailed Description of Risk Event
ACTION TO BE TAKEN Responded Risk
Impact
Impact
Status
Risk #
Phase
Description (Specific, Measurable, Attributable, Relevant, Risk Risk Impact Date, Status and
Type Risk Matrix Response Actions including advantages Impact Risk Matrix
Threat and/or Timebound) Trigger ($M or Mo) Review Comments
and disadvantages (include dates) ($M or Mo)
Opportunity [SMART]
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) [10a] (11) (12) (13) (14) (15) (15a) (16) (17) (18) (19) (20) (21) (22) [22a] (23) (24) (25) (26) (27) (28) (28a)
15
Probability
Pre-construction
If significant changes are made at the last minute, then delays may
Design/PS&E
Probability
result. Risk is better held by WSDOT; construction related permits;
Very Low
Very Low
Design Delays
Active
0.1$M
0.0$M
changes to the inwater work (channel, moorage) the terms and
Design/PS&E
are acquired need to make a change that wasn't accounted for prior. MIN 0.5Mo VL Mo MIN 0.5Mo 0.0Mo VL Mo
Very Low
Very Low
Schedule
0.1 $M
0.0 $M
0.1Mo
MAX 1.0Mo VL L M H VH MAX 1.0Mo 0.1Mo 0.0Mo VL L M H VH
Threat Most Likely 0.8Mo Impact Most Likely 0.8Mo 0.0Mo Impact
Very Low
Very Low
0.4$M
0.4$M
Cost
10%
10%
MAX 5.0$M H MAX 5.0$M H
Probability
Design/PS&E
Probability
Very Low
Very Low
Risk that additional May require 2 more flanker pontoons for the 4 lane; change in
Active
0.4$M
0.4$M
Design/PS&E
pontoon is required for alignment for the 4 lane bridge happened, so more pontoons may be L L
4 lane bridge needed.
Current
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
MAX VL L M H VH MAX 0.0Mo 0.0Mo VL L M H VH
MIN VH MIN VH
May-09
15-May-09
NO RISK
NO RISK
0.0$M
0.0$M
Cost
5%
5%
MAX H MAX H
Probability
Pre-construction
Design/PS&E
Probability
RFP ready pontoon
Very Low
Very Low
Manpower issue to draft the design could be an issue; issue if wind
Active
0.0$M
0.0$M
design is delayed for
Design/PS&E
and wave analysis comes back with unanticipated results may delay L L
reasons other than
a final addendum.
those explicitly listed
Current
Very Low
Schedule
0.0 $M
0.0 $M
0.1Mo
Threat Most Likely 1.0Mo Impact Most Likely 1.0Mo 0.0Mo Impact
MIN VH MIN VH
May-09
6-Aug-09
NO RISK
NO RISK
Partnerships and Stakeholders
0.0$M
0.0$M
Cost
50%
50%
MAX H MAX H
Probability
Pre-construction
Duration for reaching satisfactory conclusions / agreements. Issues Most Likely M Most Likely -$0.4 M
Acceptance
PSP 10.01
Probability
NO RISK
NO RISK
Retired
0.0$M
0.4$M
Agreements with
Design/PS&E
being discussed. Agreement issues can lead to a delay the RFP. L Meeting with the tribes to resolve the issue with PA; L
Tribes
Update: Did not receive the PA, have increased the probability from
25% to 50%. Retired as of Update Two.
Current
Very Low
Schedule
NO RISK
0.8 $M
0.4 $M
0.0Mo
Threat Most Likely 1.5Mo Impact Most Likely 1.5Mo 0.0Mo Impact
NO RISK
NO RISK
0.0$M
0.0$M
Cost
0%
0%
MAX 0.0$M H MAX 0.0$M H
Probability
Most Likely 0.0$M M Most Likely 0.0$M $0.0 M
Probability
NO RISK
NO RISK
Retired
0.0$M
0.0$M
VE4
Design/PS&E
NO RISK
NO RISK
0.0 $M
0.0Mo
NO RISK
NO RISK
The single contract approach was selected to provide the contractor
0.0$M
0.0$M
Cost
75%
with an opportunity to develop a more innovative or cost effective MAX -10.0$M H MAX H
design. RFP will have some restrictions because there is another
Probability
Opportunity for project coming after this that would also need to use the same
Design/PS&E
Probability
Contractor Innovation criteria; slide launch; elevator launch barges, dual stage pontoons;
NO RISK
NO RISK
Retired
0.0$M
0.0$M
on Casting Basin Site removal of one of the gates; changing of the wall type; savings (low
Design/PS&E
Types) foundation driving from a floating crane inside the hole could save 1 MIN -1.0Mo VL MIN -0.8Mo VL
Schedule
NO RISK
NO RISK
-1.3 $M
0.0 $M
to 2 months schedule; wall changes (base is cast in place wall)
0.0Mo
could move to sheetpile or MSE wall, $4M to $5M savings; Possibly MAX -2.0Mo VL L M H VH MAX 0.0Mo -1.5Mo VL L M H VH
no need for the wall;
Opportunity Most Likely -1.5Mo Impact Most Likely -1.1Mo Impact
Opportunity The single contract approach was selected to provide the contractor MIN -8.0$M VH MIN VH
May-09
23-Jun-09
NO RISK
NO RISK
with an opportunity to develop a more innovative or cost effective
0.0$M
0.0$M
Cost
50%
design. RFP will have some restrictions because there is another MAX -12.0$M H MAX H
Opportunity for
project coming after this that would also need to use the same
Contractor Innovation
Probability
criteria; Slide launch; elevator launch barges, dual stage pontoons;
Design/PS&E
Probability
remove one of the gates; change the wall type; savings (low end)
NO RISK
NO RISK
Retired
Design or Construction
0.0$M
0.0$M
could be single gate $8M to $12M savings, different pile types (pre-
Design/PS&E
months schedule; wall changes (base is cast in place wall) could MIN VL MIN 0.0Mo VL
Schedule
NO RISK
0.0 $M
0.0 $M
move to sheetpile or MSE wall, $4M to $5M savings; Possibly no
0.0Mo
SK
SK
M
M
Post- Pre- Post- Pre-
Project Title WSDOT SR-520 Pontoon Construction RISK MANAGEMENT SUMMARY RESULTS Functional Area
Response Response
Functional Area
Response Response
Management /
Estimate Date Target AD date 07/17/09 Planned and Actual ($ M) Construction 4.7 $M 5.7 $M 0.0 $M 0.0 $M
Funding
Project PIN # Estimated CN Duration 57.9Mo Expected Value Total Risk Before Response -17.1 $M Right-of-Way 0.0 $M 0.0 $M Structures & Geo-tech 1.6 $M 1.6 $M
Last Review Date Estimated PE Cost 37.0 $M Expected Value Total Risk After Response -19.7 $M Design/PS&E 1.8 $M 2.1 $M Utilities 0.0 $M 0.0 $M
Environmental &
Project Manager Estimated ROW Cost 16.9 $M Estimated Cost to Respond 0.0 $M Railroad 0.0 $M 0.0 $M 0.4 $M 5.6 $M
Hydraulics
Est $ Impact of Signficant
Partnerships and Contracting and
Project Risks ( cost & Estimated CN Cost 693.4 $M Potential Cost Savings 2.5 $M 0.4 $M 0.4 $M 2.1 $M 2.2 $M
schedule)
Stakeholders Procurement
Pre-Response Post-Response
Responded Probability
Response Strategy
(cost of delay +
Update History
Risk Owner
Probability/
RBS Group
Response)
or WSDOT)
Probability
Probability
Summary Detailed Description of Risk Event
ACTION TO BE TAKEN Responded Risk
Impact
Impact
Status
Risk #
Phase
Description (Specific, Measurable, Attributable, Relevant, Risk Risk Impact Date, Status and
Type Risk Matrix Response Actions including advantages Impact Risk Matrix
Threat and/or Timebound) Trigger ($M or Mo) Review Comments
and disadvantages (include dates) ($M or Mo)
Opportunity [SMART]
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) [10a] (11) (12) (13) (14) (15) (15a) (16) (17) (18) (19) (20) (21) (22) [22a] (23) (24) (25) (26) (27) (28) (28a)
23-Jun-0
May
0.0$M
0.0$M
NO RIS
NO RIS
Cost
5%
MAX 80.0$M H MAX H
Structures & Geo-tech
Probability
possible reasons are more information from geotech, or permit from Most Likely 70.0$M M Most Likely $0.0 M
Construction
STG 30.02
Avoidance
Probability
the city to go to a different criteria; performance criteria is currently
NO RISK
NO RISK
Retired
Change in structural
0.0$M
0.0$M
tied to a mechanism; Possibly the performance criteria could change Received a written response from the City of Aberdeen that accepted the
Design/PS&E
extra cost minus $25m for piles and floor and $25m for the wall net MIN 3.0Mo VL MIN 0.2Mo VL
Schedule
NO RISK
NO RISK
0.4 $M
0.0 $M
$70M is the median cost
0.0Mo
MAX 12.0Mo VL L M H VH MAX 0.0Mo 0.6Mo VL L M H VH
The single contract approach was selected to provide the contractor MIN VH MIN VH
May-09
15-May-09
NO RISK
NO RISK
with an opportunity to develop a more innovative or cost effective
0.0$M
0.0$M
Cost
50%
design. RFP will have some restrictions because there is another MAX H MAX H
Opportunity for project coming after this that would also need to use the same
Probability
Contractor Innovation criteria; Slide launch; elevator launch barges, dual stage pontoons;
Design/PS&E
Probability
on Casting Basin Site remove one of the gates; change the wall type; savings (low end)
NO RISK
NO RISK
Retired
0.0$M
0.0$M
Design or Construction could be single gate $8M to $12M savings, different pile types (pre-
Design/PS&E
Risk Impact for DES months schedule; wall changes (base is cast in place wall) could MIN 1.0Mo VL MIN 0.5Mo VL
Schedule
NO RISK
NO RISK
0.0 $M
0.0 $M
60.03) move to sheetpile or MSE wall, $4M to $5M savings; Possibly no
0.0Mo
need for the wall; This risk is a schedule impact due to the cost MAX 3.0Mo VL L M H VH MAX 0.0Mo 1.5Mo VL L M H VH
opportunity of DES 60.03, both DES 60.03 and DES 60.10 impacts
Threat occur simultaneously. Most Likely 2.0Mo Impact Most Likely 1.0Mo Impact
NO RISK
NO RISK
0.0$M
0.0$M
Cost
25%
Probability
Design/PS&E
Probability
Risk that an epoxy
NO RISK
NO RISK
Retired
saltwater until needed; if the project was delayed many years, this
0.0$M
0.0$M
coating for the pontoon
Design/PS&E
NO RISK
NO RISK
0.0 $M
0.0 $M
0.0Mo
NO RISK
NO RISK
0.0$M
0.0$M
contractor would do a pile load test during design; and could gain
Cost
50%
some useful information still from doing the test pile program. For MAX -4.0$M H MAX H
the RFP will have some borings, and lab test raw data; information
Probability
Most Likely -2.5$M M Most Likely $0.0 M
Construction
Construction
Probability
NO RISK
Retired
0.0$M
0.0$M
implemented leads to
Design/PS&E
NO RISK
0.0 $M
0.0 $M
0.0Mo
$4m at the largest. This program needs to be done by the State MAX VL L M H VH MAX 0.0Mo 0.0Mo VL L M H VH
before bids to get the information out to save on bids. Update: A
decision has been made that this cannot be performed before the
Most Likely Impact Most Likely 0.0Mo Impact
RFP goes out.
NO RISK
NO RISK
0.0$M
0.0$M
Cost
10%
The single contract approach was selected to provide the contracto MAX -5.0$M H MAX H
with an opportunity to develop a more innovative or cost effective
Probability
Opportunity for
Design/PS&E
Probability
Contractor Innovation
NO RISK
NO RISK
Retired
project coming after this that would also need to use the same
0.0$M
0.0$M
on Casting Basin Site
Design/PS&E
criteria; foundation driving from a floating crane inside the hole could L L
Design or Construction
save 1 to 2 months schedule; wall changes (base is cast in place
Methods (Change Wall
wall) could move to sheetpile or MSE wall, $4M to $5M savings;
Current
NO RISK
0.0 $M
0.0 $M
0.0Mo