0% found this document useful (0 votes)
276 views4 pages

Free Monthly Cost Excel Template For Construction Projects

This document provides a cost summary for the Abu Dhabi Flage Pole project as of December 31, 2010. It outlines the budget, actual costs to date, remaining balance, and expected total costs for builders work, sub-contractor work, and site overheads. The contractor is Ghantoot Transport and Gent. Contracting and the project manager is Morganti Group Inc.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
276 views4 pages

Free Monthly Cost Excel Template For Construction Projects

This document provides a cost summary for the Abu Dhabi Flage Pole project as of December 31, 2010. It outlines the budget, actual costs to date, remaining balance, and expected total costs for builders work, sub-contractor work, and site overheads. The contractor is Ghantoot Transport and Gent. Contracting and the project manager is Morganti Group Inc.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Project : Abu Dhabi Flage Pole

Client : Abu Dhabi Judicial Department


Consultant: Beirut Engineering Consulting Burea
Project Manager : Morganti Group Inc
Contractor : Ghantoot Transport and Gent. Contracting

GRAND SUMMARY
As On : 31.12.2010

Sl No Item BOQ Actual up to date Balance Total Expected Save/ Loss

A BUILDERS WORK 0.00 221,955.64 3,165.00 225,120.64 0.00

B SUB-CONTRACTOR WORK 0.00 1,221,940.00 798,900.00 2,020,840.00 0.00

C SITE OVER HEAD 0.00 249,484.55 79,500.00 328,984.55 0.00

Dry costs 2,886,000.00 1,693,380.19 881,565.00 2,574,945.19 311,054.81

Prepared By Checked By

Eng. Mohamed Yasir Eng. Emad Mohamed Fathy

Page 1 of 1
Qnty. Surveyor / C.C Engr Project Director

Page 2 of 1
Project : Abu Dhabi Flage Pole
Client : Abu Dhabi Judicial Department
Consultant: Beirut Engineering Consulting Burea
Project Manager : Morganti Group Inc
Contractor : Ghantoot Transport and Gent. Contracting
Monthly Cost Complete Report
As On : 31.12.2010
1 2 3 4 5 6 7
Budget Up to date actual cost Balance Cost to finish
Sl. Unit Save/Loss
Item Expect cost
No. Qty Rate Amount Qty Rate Amount Qty Rate Amount
(4+5) (3-6)

A BUILDER'S WORK 0.0 221,955.6 3,165.0 225,120.6 0.0

1 EARTH WORK 0.0 60,683.0 3,000.0 63,683.0 0.0

4 CONCRETE WORKS 0.0 142,372.6 0.0 142,372.6 0.0

5 BLOCK WORKS 0.0 11,430.0 0.0 11,430.0 0.0

6 WATER PROOFING 0.0 3,055.0 0.0 3,055.0 0.0

7 FINISHES 0.0 4,415.0 165.0 4,580.0 0.0

Prepared By, Page 1 of 4


Checked By,
Quantity Surveyor / Cost Control Engr. Project Director.
Project : Abu Dhabi Flage Pole
Client : Abu Dhabi Judicial Department
Consultant: Beirut Engineering Consulting Burea
Project Manager : Morganti Group Inc
Contractor : Ghantoot Transport and Gent. Contracting
Monthly Cost Complete Report
As On : 31.12.2010
1 2 3 4 5 6 7
Budget Up to date actual cost Balance Cost to finish
Sl. Unit Save/Loss
Item Expect cost
No. Qty Rate Amount Qty Rate Amount Qty Rate Amount
(4+5) (3-6)

B SUB - CONTRACT WORKS 0.0 1,221,940.0 798,900.0 2,020,840.0 0.0

1 Dermolition of the existing Building S/C 1.0 36,000.0 36,000.0 1.0 24,000.0 24,000.0 60,000.0

2 Excavated Material Removal S/C 1.0 12,000.0 12,000.0 0.0 12,000.0

3 Piling work with Testing S/C 1.0 48,300.0 48,300.0 0.0 48,300.0

4 MEP works S/C 1.0 220,000.0 220,000.0 1.0 55,000.0 55,000.0 275,000.0

5 Fountain work S/C 1.0 144,000.0 144,000.0 1.0 96,000.0 96,000.0 240,000.0

6 Granite work by ABU DHABI ARCH S/C 1.0 189,000.0 189,000.0 189,000.0

7 Stainless steel work by AL BARJEEL S/C 1.0 250,000.0 250,000.0 250,000.0

8 Flage and Pole by ARITIES S/C 1.0 745,100.0 745,100.0 1.0 184,900.0 184,900.0 930,000.0

9 Water proofing by WATER SEAL S/C 1.0 16,540.0 16,540.0 16,540.0

C SITE OVER HEADS 0.0 249,484.6 79,500.0 328,984.6 0.0

1 Material for Mobilisation work MAT 1.0 2,805.0 2,805.0 2,805.0

2 Equipment, Fuel, and Plant Charges S.O.H 1.0 174,730.0 174,730.0 1.0 50,000.0 50,000.0 224,730.0

3 Light machinery and Loose Tools MAT 1.0 1,200.0 1,200.0 0.0 1,200.0
4 Insurance Charges S.O.H 1.0 3,000.0 3,000.0 1.0 1,000.0 1,000.0 4,000.0

5 Staff salaries (incld sectradory) Lab 1.0 40,000.0 40,000.0 0.0 40,000.0

6 Refreshment S.O.H 1.0 889.0 889.0 1.0 1,500.0 1,500.0 2,389.0

7 Professional Fees S.O.H 0.0 1.0 10,000.0 10,000.0 10,000.0

8 Consultant Expenses S.O.H 1.0 10,013.0 10,013.0 1.0 10,000.0 10,000.0 20,013.0

9 Other Expenses (petty cash) S.O.H 1.0 10,000.0 10,000.0 1.0 5,000.0 5,000.0 15,000.0

10 Government, Finance & Permit Charges S.O.H 1.0 6,847.6 6,847.6 1.0 2,000.0 2,000.0 8,847.6

Prepared By, Page 2 of 4


Checked By,
Quantity Surveyor / Cost Control Engr. Project Director.

You might also like