Subcontracting Plan
Subcontracting Plan
Subcontracting Plan
TABLE OF CONTENTS
1. INTRODUCTION...............................................................................................................................3
1.1. Purpose.........................................................................................................................................3
2. SCOPE OF SUBCONTRACT WORKS.............................................................................................3
2.1. Identification of Subcontract Works.............................................................................................3
2.2. Execution of Subcontract Agreement...........................................................................................3
2.3. Commencement of Subcontractor Works.....................................................................................3
2.4. Programme....................................................................................................................................4
3. SELECTION OF SUBCONTRACTORS............................................................................................4
3.1. Issue of Invitations to Price..........................................................................................................4
3.2. Choice of Proposed Subcontractor...............................................................................................4
4. SUPERVISION OF SUBCONTRACTORS.......................................................................................5
4.1. Sub-contractor’s Surveillance Audit.............................................................................................5
4.2. Subcontractor’s Meetings.............................................................................................................5
5. CONTROL OF SUBCONTRACTING...............................................................................................6
5.1. Subcontract Agreement Constraints.............................................................................................6
5.2. Performance of Sub-Let Works....................................................................................................6
5.3. Payment for Sub-Let Works.........................................................................................................6
6. MONITORING OF SUB-CONTRACTOR.........................................................................................6
6.1. Progress of the Subcontractor.......................................................................................................6
6.2. Quality of Subcontracted Works..................................................................................................7
6.3. Subcontractor Safety & Environmental........................................................................................7
6.4. Subcontractor Plant and Equipment.............................................................................................7
6.5. Review of Subcontractor’s Performance......................................................................................7
7. ATTENDANCE AND ACCESS.........................................................................................................7
7.1. Attendance Requirements.............................................................................................................7
7.2. Access Requirements....................................................................................................................8
8. MANAGEMENT REVIEW AND IMPROVEMENT........................................................................8
8.1. Management Review and follow-up action on matters arising....................................................8
1. INTRODUCTION
1.1. Purpose
The purpose of this Subcontract Plan is to outline the manner to be employed in the
selection of subcontractors to ensure that only those subcontractors that have the
capability to complete the works assigned to them in accordance with the
requirements of both the Client and SAPAC.
This plan also sets the mechanism for monitoring, supervision, management, and
control adopted to ensure that all subcontractors meet the required quality standards.
3. SELECTION OF SUBCONTRACTORS
3.1. Issue of Invitations to Price
The following steps will be taken to decide which subcontractors to obtain
quotations from:
The Client's list of approved subcontractors will be accessed, if available to
obtain a list of subcontractors that carry out the work detailed in a proposed
subcontract scope.
A check will be carried out to ensure that the subcontractor’s qualifications meet
the requirements set out in the Main Contract documents.
Enquiries will not be sent to subcontractors who have not performed
satisfactorily on previous projects (safety, quality, environmental, contractual,
programme etc.)
A new sub-contractor will be considered subject to satisfactory references.
Enquiries will be sent to at least three subcontractors.
4. SUPERVISION OF SUBCONTRACTORS
The Project Manager and his staff will be responsible for overseeing the work of the
subcontractor to ensure it complies with quality and safety programmes.
6. MONITORING OF SUB-CONTRACTOR
6.1. Progress of the Subcontractor
The progress of works undertaken by each subcontractor is to be closely monitored
by the site team and weekly meetings will be held with each subcontractor to discuss
progress and programme.
Progress shall be monitored against the following programmes:
Three week rolling programme
Three month rolling programme
Current working programme
Any significant deviations in subcontract progress will be immediately reported
(together with reasons for the deviations) to the PM, who will decide on an
appropriate course of action in conjunction with the Commercial Manager.
6.2. Quality of Subcontracted Works
The quality of the works will be inherently recorded by site inspections. Should non-
conformances become apparent the subcontractor will be required to propose
remedial measures for approval prior to making good.
If the intensity of non-conformances is considered to be too frequent the
subcontractor will be required to provide improved supervision of the works until the
daily quality is deemed to be of a standard compliant with the Specification and the
Contractor’s quality system.