Mos For Precast Concrete Works
Mos For Precast Concrete Works
Mos For Precast Concrete Works
TABLE OF CONTENTS
1. SITE DESCRIPTION............................................................................................................... 3
2. SCOPE.................................................................................................................................... 3
3. REFERENCE DOCUMENTS...................................................................................................3
4. DEFINITIONS AND ABBREVIATIONS....................................................................................4
5. CONSTRUCTION CONTRACTOR DUTIES AND RESPONSIBILITIES..................................4
6. MANPOWER........................................................................................................................... 6
7. EQUIPMENTS AND TOOLS...................................................................................................7
8. PRE CAST WORKSHOP AREA PREPARATION...................................................................8
9. WORK PROCEDURE.............................................................................................................. 8
10. SAFETY REQUIREMENTS...................................................................................................11
11. ATTACHMENT...................................................................................................................... 12
This document is the property of COMPANY it must not be stored, reproduce without written authorization from the
COMPANY. PRE-CAST CONCRETE METHOD STATEMENT, H99-ZA-E-0004203 (Rev. D)
PROJECT TITLE
HAWIYAH GAS PLANT (HGP) EXPANSION PROJECT SN AM PROGETTI
SAUDI ARABIA CO. LTD.
1. SITE DESCRIPTION
The Saudi Arabian Oil Company (Saudi ARAMCO) is the owner of the development of
HAWIYAH GAS PLANT EXPANSION Project (HGP). The project is located in the Eastern Province
of Saudi Arabia, approximately 65 km southwest of the City of Hofuf in the Al-Hasa region and
approximately 175 km southwest of Dammam. CONTRACTOR has been awarded the engineering,
procurement, construction, installation, pre-commissioning activities, commissioning & start-up
support to provide additional gas processing facilities at Hawiyah Gas Plant (HGP) to process 1070
million standard cubic feet per day (MMSCFD).
SUBCONTRACTOR has been awarded the execution of the Civil, Mechanical, Electrical,
Instrumentation and Telecom activities until Mechanical Completion
2. SCOPE
The intent of this Method Statement is to identify the required procedure in carrying out the pre-cast
items on site workshop (Preparation - Formwork - Reinforcement and embedment - Concrete
placing, curing and finishing, and installation) at HAWIYAH GAS PLANT EXPANSION Project
(HGP) in accordance with COMPANY and CONTRACTOR Specifications, Procedures and all
applicable regulatory requirements.
Reinforced concrete structures covered by this Method Statement are all foundations and U/G units
such as manholes, Catch Basins, Valve Boxes, and Lift Stations with weight not exceeding 25 ton.
D
3. REFERENCE DOCUMENTS
SAES-Q-001 Criteria for Design and Construction of Concrete Structures
SAES-Q-005 Concrete Foundations
SAES-Q-012 Criteria for Design and Construction of Precast and Pre-stressed Concrete
Structures
09-SAMSS-088 Aggregates for Concrete
09-SAMSS-097 Ready-Mixed Concrete
ACI 318 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE
ACI 315 Details and Detailing of Concrete Reinforcement
ACI 550R Design Recommendations for Precast Concrete Structures
H99-ZA-E-0009609 Rev. B QA/QC Requirements for Construction Contractors
H99-ZA-E-0009612 Rev. A Quality Control Specification For Civil Work
H99-ZA-E-0004612 Rev. A Quality Control Plan for Civil Work.
BA-617401-001 AND BA-617401-002 CONCRETE WORK GENERAL NOTES
BA-736080-001 LEGEND AND ABREVIATIONS
SAUDI ARAMCO Construction Safety Manual.
H99-ZA-E-0009701 Contractor Site Safety Program
PROJECT TITLE
HAWIYAH GAS PLANT (HGP) EXPANSION PROJECT SN AM PROGETTI
SAUDI ARABIA CO. LTD.
CONTRACTOR /
AFFILIATED : SAIPEM S.P.A. (OOK), Snamprogetti S.A. (IK)
CONTRACTOR
Contract : the agreement entered between SAIPEM and CONSTRUCTION
CONTRACTOR for Project
Overall direction ,monitoring and control all concrete works activities to the required Job
Specifications / time schedule
Notify QC team when works are ready for inspections, as depicted in the ITPs and QCPs.
Coordination with construction team to provide all facilities (i.e. access ways , scaffolding , etc.)
for inspection, testing and concrete placing process
Ensure that notification time to QC is sufficient to meet notifications times to CONTRACTOR and
COMPANY, as depicted in the ITPs and QCPs.
Provide the proper and sufficient facilities for NC clearance
5.2. QC SUPERVISOR
Submit and verify the approval of all documents that are necessary for inspection (Material – MS
– Procedures)
PROJECT TITLE
HAWIYAH GAS PLANT (HGP) EXPANSION PROJECT SN AM PROGETTI
SAUDI ARABIA CO. LTD.
Ensure that all other discipline activities that must be inspected within the concrete works
construction program have been inspected and cleared.
Organize and allocate inspection works to the Site Quality Control Inspectors.
Coordination between TPTL and Site QC Inspector for the required testing as well as follow up
the issue of laboratory reports.
Ensuring that all inspections are performed and recorded as per project requirements / specs.
Coordination between CONSTRUCTION CONTRACTOR & CONTRACTOR QC teams for
solving quality issues
Follow up the clearance of non-conformances and quality issues
Preparation of all handing over dossiers to the other disciplines
Review and Maintain proper document system with tracing facilities and logs for all construction
activities including IFC updated drawings , Approved Mix Designs ,MS and procedures ,
,Calibration Certificates , Material Approvals, Material Receiving , TPTL Test Reports, Third
Party Test Reports , approved R.F.I ,NCR and Quality Issues,
Regular reporting to CONTRACTOR QC Supervisor.
Attend the regular quality meeting with CONTRACTOR and COMPANY.
5.3. SITE QC INSPECTOR
Verify all construction activities are completed and ready for inspection in coordination with
construction team.
Perform / ensure that all inspections are performed in a timely manner and record as per
Specifications, ITPs and QCPs requirements.
Ensuring that notification times to CONTRACTOR and COMPANY are upheld as per ITPs and
QCPs
Coordination with Batch Plant QC Inspector and to ensure the correct type of concrete mix and
no concrete released from batch plant before acceptance of pre-pouring inspection by
CONTRACTOR and COMPANY.
Coordinates with other QC Disciplines, as necessary.
Inform CONTRACTOR/COMPANY inspectors by the official Request for Inspection, and when
their presence is required to carry out Inspections.
Accompany CONTRACTOR/COMPANY inspectors to carry out Inspections and release
hold/witness points.
Follow up the implementation of the corrective actions for any Non-Conformance as well as
raising any NCR to the QC Supervisor.
Follow up concrete placing process from the start to concrete finishing and curing.
PROJECT TITLE
HAWIYAH GAS PLANT (HGP) EXPANSION PROJECT SN AM PROGETTI
SAUDI ARABIA CO. LTD.
Coordination with TPTL on site before and during concrete placing process for concrete
sampling.
Coordinate with Batch Plant QC Inspector for any incidents (ie. Rejection of concrete due to
delay or unauthorized re-Tempering).
5.4. BATCH PLANT QC INSPECTOR
Fully present in concrete batch plant during the whole pouring time with well contact facility
Full Coordination between worksite both quality team & construction team and concrete batch
plant for ordering the correct mix ID (Class – Cement Type ) & quantities and arrival time
Coordination between TPTL and concrete batch plant for the start of loading
Initial check for batch plant conditions before loading the concrete
Initial check for the fresh concrete (visual – print out check)
Follow up concrete delivery to the pouring location
Preparation of the daily concrete pouring log in coordination with Site QC Inspector
5.5. TPTL TECHNICIAN
6. MANPOWER
Foreman
Helper
Flagman
PROJECT TITLE
HAWIYAH GAS PLANT (HGP) EXPANSION PROJECT SN AM PROGETTI
SAUDI ARABIA CO. LTD.
Painter
Operator (Crane,…etc)
Rigger
Safety officer
HSE Personnel
Site Supervisor
QC Inspector
Surveyor
Banks man
Carpenters
Scaffolders
Steel Fabricators / Fixers
Concrete workers / finisher
Masons
Permit Receiver
9. WORK PROCEDURE
9.1 INITIAL VERIFICATION
Assign the items that will be precast according to site conditions
Estimate the concrete volume per precast element .Max. weight of the precast element will be 12
ton
Decide according to the nature of concrete element the position of formwork (Normal – inverted –
horizontal)
Manholes, Catch Basins, Valve Boxes, Sleepers will be cast in an inverted position. This process
allows for concrete casting one time and without joints, water stop shall be fixed when required
by design drawing.
Foundations with pedestals but without anchor bolts or embedded plates will also be poured in
an inverted position
Foundations that have long posts protruding concrete (such as fence foundations) will be cast in
the horizontal position. This process doesn’t need vertical fixations for such posts
Other items such as foundation with anchor bolts shall be casted in the normal position.
For any U/G pits or chambers it should be confirmed the correct opening (box out) size directions
from U/G arrangement drawings.
PROJECT TITLE
HAWIYAH GAS PLANT (HGP) EXPANSION PROJECT SN AM PROGETTI
SAUDI ARABIA CO. LTD.
Concrete curing to be carried out for 7 days using saturated burlaps covered with a plasticized
sheet vapor barrier, minimum 0.15 mm (6 mils) in thickness and shall be kept in contact with the
concrete surface at all times.
De-molding when concrete exceeding the de-molding force, the pre-cast elements (casted at
D inverted position) will be put on their side to allow removal of internal formwork.
Cut the temporary hooks only (that were used for turning the manholes) over to the cover depth
requirements by chipping and fill with the approved repair mortar as per mortar manufacturer’s
recommendation.
Concrete finishing and coating will be after 7 days or achieving 70% of the concrete
characteristic strength-which is earlier.
Compressive strength shall be verified according to ACI requirements, by preparing on-site cured
specimens for compressive strength, to be tested to ensure that concrete actual compressive
strength is minimum 70% of concrete characteristic strength, this may shorten the period
required for transporting the pre-cast element from concrete casting location to storing location.
Mark the element no. and destination immediately after external formwork removal.
Final inspection for the precast item prior to installation.
9.5 PREPARATION FOR INSTALLATION
According to SAES-Q-005, installation of precast foundations shall comply with one of the
following methods:
A 50 mm lean concrete seal slab shall be placed in the bottom of the excavation immediately
before placing the precast concrete foundation. The precast concrete foundation shall then be
set in place prior to hardening of the lean concrete. This shall help in level adjustment.
A layer of clean sand not more than 50 mm thick shall be placed in the bottom of the excavation.
If clean sand is used, it must be carefully leveled prior to placing the precast concrete foundation
and a 0.15 mm (6 mils) plasticized sheet vapor barrier shall be place beneath the foundation.
The foundation level shall be adjusted and checked to loading of precast element.
The coordinates of the precast items shall be located by means of strings adjusted and
intersected at the corner of the element.
Check the precast item no. and destination before directing to the site.
9.6 LIFTING, TRANSPORTING AND UNLOADING
CONSTRUCTION CONTRACTOR will submit Lifting and rigging plan including the suitable
crane and safety precautions for CONTRACTOR/COMPANY approval.
The lifting of the Pre-cast element will be conducted by the verified lifting points of each item
Precast item will be lifted and transported either to stock area or directly to worksite.
Precast items will be transported by using suitable heavy truck. They should be put in the vertical
positions and secured from falling down.
PROJECT TITLE
HAWIYAH GAS PLANT (HGP) EXPANSION PROJECT SN AM PROGETTI
SAUDI ARABIA CO. LTD.
Unloading of each pre-cast element will be using suitable crane as per the lifting plan / procedure
near the exact location.
9.7 FINAL INSTALLATION OF PRE-CAST ELELMENT IN SITE
Each element to be installed in its location according to the exact elevation and orientation.
Final Survey check for the elevation and orientation and conduct necessary adjustments.
Close the manhole opening temporarily using wood until further piping and sealing works to
prevent soil ingress inside manholes.
Carryout external concrete coating and backfilling as required.
Method for surface preparation and filling the lifting lug holes with approved materials and as per
manufacturer's procedures.
9.8 INSPECTION
RFI shall be submitted 24 hrs prior to inspection designated time (and 48 hours for weekend,
holidays and remote area locations) attached with the necessary documents (SATIP – SAIC –
IFC Drawings – Survey Report).
SAPID, CONTRACTOR QC and SUBCONTRACTOR area QC Inspector will conduct the
inspections and tests as per stages identified in the SATIP’s.
SATIP-Q-001-02 and its relevant checklist will be utilized according to QUALITY CONTROL
PLAN FOR CIVIL WORK, H99-ZA-E-0004612
Particular log sheet will be established to follow up the pouring and installation of precast items.
U/G Manholes shall be leak tested on site after installation.
11. ATTACHMENT
Lifting hook calculation
Appendix A – Job Safety Analysis