0% found this document useful (0 votes)
207 views131 pages

Draft Grid Code of Bangladesh 2010

This document provides a draft of the Bangladesh Grid Code from November 2010. It contains 18 sections that establish procedures and technical requirements for the operation and use of the Bangladesh transmission system. The code is intended to govern the relationship between transmission licensees and grid users to facilitate a coordinated, efficient and economical electricity system. It covers topics such as planning, connections, operations, performance standards and dispute resolution. The code seeks to ensure the secure and reliable operation of the grid while avoiding discrimination between users.

Uploaded by

parvezblog
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
207 views131 pages

Draft Grid Code of Bangladesh 2010

This document provides a draft of the Bangladesh Grid Code from November 2010. It contains 18 sections that establish procedures and technical requirements for the operation and use of the Bangladesh transmission system. The code is intended to govern the relationship between transmission licensees and grid users to facilitate a coordinated, efficient and economical electricity system. It covers topics such as planning, connections, operations, performance standards and dispute resolution. The code seeks to ensure the secure and reliable operation of the grid while avoiding discrimination between users.

Uploaded by

parvezblog
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 131

ovember, 2010

BAGLADESH

GRID CODE
(DRAFT)

Bangladesh Energy Regulatory Commission

Approval Date: ………………..

Grid Code (Draft) November 2010


i
Grid Code (Draft) November 2010
ii
GRID CODE COTETS

SECTIO SUBJECT PAGE


GRID CODE REVISION SCHEDULE v
1. INTRODUCTION 1

2. DEFINITIONS 6

3. MANAGEMENT OF THE BANGLADESH GRID CODE 15


4. TRANSMISSION SYSTEM PLANNING 19

5. CONNECTION CONDITIONS 23
6. OUTAGE PLANNING 31
7. SCHEDULE AND DESPATCH 35

8. FREQUENCY AND VOLTAGE MANAGEMENT 40

9. CONTINGENCY PLANNING 46

10. CROSS BOUNDARY SAFETY 51


11. OPERATIONAL EVENT/ACCIDENT REPORTING 54

12. PROTECTION 58

13. METERING, COMMUNICATION AND DATA

ACQUISITION 64
14 TESTS 70

15 NUMBERING AND NOMENCLATURE 76

16 DATA REGISTRATION 80
17 PERFORMANCE STANDARD FOR TRANSMISSION 111
18 FINANCIAL STANDARD FOR TRANSMISSION 118

Grid Code (Draft) November 2010


iii
GRID CODE REVISIOS

REVISIO DATE SECTIO(S) REVISED


UMBER ISSUED

Grid Code (Draft) November 2010


iv
1. ITRODUCTIO

In exercise of the powers conferred by section 59 of the Bangladesh Energy Regulatory


Commission Act 2003 (Act 13 of 2003), read with sub-sections 2(e) and 2(f) thereof and
for the fulfilment of the objectives of the Act, the Bangladesh Energy Regulatory
Commission is pleased to make the following regulations for electrical transmission
system, namely:-

1.1 Short Title:


The regulation may be called Bangladesh Energy Regulation Commission Electrical
Transmission System Regulation (Grid Code), 2010.

1.2 GEERAL

The Grid Code is a document that governs the boundary between the Licensee and
Users and establishes procedures for operations of facilities that will use the
Transmission System. It lays down both the information requirements and the
procedures governing the relationship between the Licensee and Users. It should be
noted that the Grid Code is not concerned with the detailed design and operation of
Generators’ Power Stations and Suppliers’ Distribution Systems, provided that
their overall compatibility with the Transmission System needs is assured.

The Grid Code covers all material technical aspects relating to Connections to and
operation and use of the Transmission System including the operation of electric
lines and electrical plant connected to the Transmission System in so far as is
relevant to the operation and use of the Transmission System. It is designed to
permit the planning, development, maintenance and operation of an efficient, co-
ordinated and economical Transmission system, to facilitate competition in the
generation and supply of electricity. It is conceived as a statement of what is optimal
(particularly from a technical point of view) for all Users as well as the Buyer in
relation to the planning, operation and use of the Transmission System. It seeks to
avoid any undue discrimination between Users and categories of Users.

It should be noted that the holder of the Transmission Licence is also defined as a
User.

Grid Code (Draft) November 2010


1
The Grid Code Contains criteria and provisions on the following arena:

i. Management of the Code: specifying the responsibilities of the


Transmission Licensee (Licensee), formation and functioning of Code
Review Panel, and Grid Code review and revision;

ii. Planning: specifying the technical and design criteria and procedures to be
applied by the Transmission Licensee (Licensee) in the planning and
development of the Transmission System and by other Users connected or
seeking Connection to the Transmission System;

iii. Connection: specifying the technical design criteria and standards to be


complied with by the Licensee and other Users connected or seeking
Connection to the Transmission System;

iv. Outage: specifying the procedures relating to coordination of the Outages


for scheduled maintenance of the Transmission System, Generating unit
and Distribution System that will use the Transmission System;

v. Schedule and Despatch: specifying the procedures to be followed by the


Licensee and Users relating to the scheduling and despatch of Generating
Units to meet the electrical demand;

vi. Operations: specifying the conditions under which the Licensee shall
operate the Transmission System and other Users of the Transmission
System shall operate their plant and/or systems for the generation and
distribution of electricity in so far as necessary to protect the security and
quality of supply and safe operation of the Licensee’s Transmission
System under both normal and abnormal operating conditions. Operation of
the Grid generally covers:
Frequency and Voltage Management
Contingency Planning
Cross Boundary Safety
Operational Event and Accident Reporting
Tests
Numbering and Nomenclature
Data Registration;

Grid Code (Draft) November 2010


2
vii. Protection: specifying the coordination responsibility and minimum
standards of protection that are required to be installed by Users of the
Transmission System;

viii. Metering: specifying the minimum operational and commercial metering to


be provided by the Licensee and Users, Communication requirements, Data
acquisition;

ix. Performance Standard: specifying the technical standards, uniform


accounting system and financial standards and reporting indices in these
respects to be implemented by the Licensee.

1.3 SCOPE

The Licensee shall comply with the Grid Code in its capacity as holder of the
Transmission Licence and Generators, Distribution Utilities, Suppliers and Bulk
Power Consumers shall also comply with it as User’s of the Transmission System
in the course of their generation, supply and utilisation of electricity.

1.4 ITERPRETATIO

The meaning of certain terms (which are printed in bold letters) used in the Grid
Code shall be in accordance with the definitions listed in Section 2, “Definitions”, of
the Grid Code.

Section 2 of this code has been developed on the premise that accepted engineering
terms do not require additional definitions.

The term “Grid Code” means any or all parts of this document.

1.5 IMPLEMETATIO AD OPERATIO OF THE GRID CODE

The Licensee has the duty to implement the Grid Code. All Users are required to
comply with the Grid Code that will be enforced by the Licensee. Users must
provide the Licensee reasonable rights of access, service and facilities necessary to
discharge its responsibilities in the Users’ premises and to comply with instructions
Grid Code (Draft) November 2010
3
issued by the Licensee, reasonably required to implement and enforce the Grid
Code.

If any User fails to comply with any provision of the Grid Code, it shall inform the
Licensee without delay of the reason for its non-compliance and shall remedy its
non-compliance promptly. Consistent failure to comply with the Grid Code may
lead to Disconnection of the User’s plant and/or facilities.

The operation of the Grid Code will be reviewed regularly by the Grid Code
Review Panel in accordance with the provisions of the relevant Section of the Grid
Code.

1.6 GEERAL REQUIREMETS

The Grid Code contains procedures to permit equitable management of day to day
technical situations in the Power System, taking into account a wide range of
operational conditions likely to be encountered under both normal and abnormal
circumstances. It is nevertheless necessary to recognise that the Grid Code cannot
predict and address all possible operational conditions.

Users must therefore understand and accept that the Licensee in such unforeseen
circumstances may be required to act decisively to discharge its obligations under its
Licence. Users shall provide such reasonable co-operation and assistance as the
Licensee may request in such circumstances.

1.7 CODE RESPOSIBILITIES

In discharging its duties under the Grid Code, the Licensee has to rely on
information that other Users supply regarding their requirements and intentions. The
Licensee shall not be held responsible for any consequences that arise from its
reasonable and prudent actions on the basis of such information.

1.8 COFIDETIALITY

Under the terms of the Grid Code, the Licensee will receive information from Users
relating to their intentions in respect of their Generation or Supply businesses. The
Licensee shall not, other than as required by the Grid Code, disclose such
Grid Code (Draft) November 2010
4
information to any other person without the prior written consent of the provider of
the information.

1.9 PROCEDURES TO SETTLE DISPUTE

In the event of any conflict between any provision of the Grid Code and any
contract or agreement between the Licensee and a User, the provision of the Grid
Code will prevail.

In the event of any dispute regarding interpretation of any part of the Grid Code
provision between any User and the Licensee, the matter may be referred to the
Commission for its decision. The Commission’s decision shall be final and binding.

1.10 COMMUICATIO BETWEE THE LICESEE AD USERS

All communications between the Licensee and Users shall be in accordance with the
provisions of the relevant Section of the Grid Code.
Unless otherwise specifically required by the Grid Code, all communications shall
be in writing, save that where operation timescales require oral communication,
these communications shall be confirmed in writing as soon as practicable.

1.11 PARTIAL IVALIDITY

If any provision or part of a provision of the Grid Code should become or be


declared unlawful for any reason, the validity of all remaining provisions, or parts of
provisions, of the Grid Code shall not be affected.

1.12 DIRECTIVE

Under the provisions of Section 24 of the Act, the Government may issue policy
directives on matters concerning electricity including on measures that are
considered necessary for the overall planning and coordination for the development
of the electricity sector. The Licensee shall promptly inform the Commission and all
Users of the requirement of such direction that affects the Grid Code. The Users
shall comply with the directions.

Grid Code (Draft) November 2010


5
1.13 MAITEACE

It is a requirement that all User’s Plant and Apparatus on the Licensee’s Sites are
maintained properly to ensure that they do not pose a threat to safety of any of the
Licensee’s Plant, Apparatus or Personnel on the Licensee’s site. The Licensee shall
have the right to inspect test results and maintenance records relating to such Plant
and Apparatus at any time.
It is also a requirement that all the Licensee’s Plant and apparatus on User’s Sites
are maintained properly to ensure that they do not pose a threat to the safety of any
User’s Plant, Apparatus or Personnel on the User site. Users shall have the right to
inspect test results and maintenance records relating to such Plant and Apparatus at
any time.

1.14 CITIZE CHARTER

The Licensee shall publish Citizen Charter incorporating also its obligation under
the License issued by the Commission and the Grid Code.

Grid Code (Draft) November 2010


6
2. DEFIITIOS AD ABBREVIATIOS

2.1 DEFIITIOS

Defined Term Definition

Act The Bangladesh Energy Regulatory


Commission Act, 2003, (Act 13 of 2003).

Apparatus Electrical Apparatus and includes all


machines, fittings, accessories and
appliances in which conductors are used.

Appendix An Appendix to a Section of the Grid


Code.

Area of Supply The area within which alone a Licensee is


for the time being authorised by his licence
to supply electricity.

Back to Back Back to Back is an interface substation


where both Rectifier and Inverter are present
for conversion and reconversion of AC and
DC transmission.

Back-Up Metering System The tariff metering system installed, owned


and maintained by the User.

BERC Bangladesh Energy Regulatory


Commission. Also known as the
Commission.
Established by Bangladesh Energy
Regulatory Commission Act 2003.

Grid Code (Draft) November 2010


7
BPDB Bangladesh Power Development Board
formed in 1972. Responsible for the
majority of the Generation, Transmission,
Distribution and purchase of power in
Bangladesh.
Black Start The process of recovery from a total or
partial blackout of the Transmission
System.
Bulk Power Consumer A person or establishment to whom
electricity is provided and who has a
dedicated supply at 33KV, 66KV, 132KV or
230KV.

Connection The electric lines and electrical equipment


used to effect a Connection of a User’s
system to the Transmission System.

Connection Agreement An agreement between the Licensee and a


User setting out the terms relating to the
Connection to and/or use of the
Transmission System.

Connection Conditions The technical conditions to be complied


with by any User having a Connection to
the Transmission System as laid down in
Section 5: “Connection Conditions” of the
Grid Code.

Control Person A person identified as having responsibility


for cross-boundary safety under Section 10:
“Cross Boundary Safety” of the Grid Code.

Grid Code (Draft) November 2010


8
Declared Available Capacity The estimated net capacity of the
Generating Units announced by the
Generator that equals the Dependable
Capacity less any reductions due to
scheduled outage, forced outage or
maintenance.

DPDC Dhaka Power Distribution Company


Limited. Responsible for distribution of
electricity in defined areas of Dhaka.

DESCO Dhaka Electricity Supply Company formed


1996. Responsible for the distribution of
electricity in defined areas of Dhaka.

Detailed Planning Data As referred to Data Registration Section.

Directive A policy Directive issued by the


Government of Bangladesh under the
provision of the Act.

Disconnect The act of physically separating a User’s or


Bulk Power Consumer’s electrical
equipment from the Transmission System.

Distribution Utility An organisation who is licensed, or exempt


from the requirements to be licensed to own
and/or operate all or part of the
Distribution System.

Distribution System The system of electric lines and electrical


equipment owned and operated by a
Distribution Utility.

Electricity Rules, 1937 The Electricity Rules formulated in 1937.

Grid Code (Draft) November 2010


9
Electricity Operator Any person or establishment who owns and
/ or operates generating plant or who holds a
Licence under the Act, connected to the
Licensee’s Transmission System for
operation of the Transmission System.

External Interconnection Electric lines and electrical equipment used


for the transmission of electricity between
the Transmission System and any other
Transmission System other than the
Bangladesh Power System.

Extra High Voltage (EHV) Nominal voltage levels of 132KV and


above.

Generating Unit The combination of an alternator and a


turbine set (whether steam, gas, water or
wind driven) or a reciprocating engine and
all of its associated equipment, which
together represents a single electricity
generating machine.

Generator An organisation that has a licence to


generate electricity and who is subject to the
Grid Code.

Grid Code / Code The set of principles and guidelines


managed and serviced by the Licensee in
accordance with the terms and conditions of
the Transmission Licence and approved by
the Commission.

Grid Code Review Panel / Panel The Panel set up under Section 3:
“Management of Bangladesh Grid Code”
of the Grid Code.

Grid Code (Draft) November 2010


10
IPP Independent Power Producer being a Power
Station owned by a Generator who is not
classified as a Public Sector Entity.

Licensee The holder of the Transmission Licence for


the bulk transmission of electricity between
Generators and Distributors.

Load Despatch Centre The control room situated in Dhaka,


operating round the clock for the purpose of
managing the operation of the
Transmission System and coordination of
generation and distribution on a real time
basis.

Metering System The tariff metering system installed, owned


and maintained by the Transmission
System Licensee
MPEMR Ministry of Power, Energy and Mineral
Resources

ational Load Despatch Centre (LDC) Same as definition of LDC

ational Plan National Development Plan prepared and


produced by the Planning Commission.

et Electrical Output The net electrical energy expressed in KW


or KWh delivered to the Interconnection
point by the Generator as measured at the
HV bushings of the step up transformer
Operating Committee The committee with members representing
the Generator and the Licensee dealing
with all operational matters effecting the
Transmission System and meeting
quarterly.

Grid Code (Draft) November 2010


11
Off Peak Period That period in a day when electrical demand
is at its lowest.

Outage The reduction of capacity or taking out of


service of a Generating Unit, Power
Station or part of the Transmission System
or Distribution System

PBS Palli Bidyut Samities, Rural Electric Co-


operatives formed to purchase electricity
and distribute within its own Distribution
System to its customers.

Peak Period That period in a day when electrical demand


is at its highest level.

PGCB Power Grid Company of Bangladesh formed


1996. Responsible for the transmission of
electricity in Bangladesh.

Power Purchase Agreement or PPA The agreement between a Generator and a


buyer in which, subject to certain conditions,
the buyer agrees to purchase the electrical
output of the Generator’s Generating Unit
and the Generator agrees to provide
services from this Unit.

Power Station An installation of one or more Generating


Units (even when sited separately) owned
and/or operated by the same Generator and
which may reasonably be considered as
being managed as a single integrated
generating complex.

Grid Code (Draft) November 2010


12
Power System The combination of the Transmission
System, Distribution System and Power
Stations.

Power System Master Plan Master plan for the Power System reviewed
and updated periodically, preferably every 5
years, covering all issues relating to the
Power System.

Private Generator A Generator which is not classified as a


Public Sector Entity and operates on BOO/
BOT/ Rental/ Commercial/ Merchant/
Captive basis.

Public Sector Entities The Bangladesh Power Development Board,


the Rural Electrification Board and the
Dhaka Electric Supply Authority constituted
under the relevant Order, Ordinance and Act
or any other power sector entity wholly
owned by the Government.

REB Rural Electrification Board formed 1977.


Responsible for the development of rural
electrification.

Section A Section or part of this Grid Code that is


identified as covering a specific topic.

Grid Code (Draft) November 2010


13
Buyer An Entity in the public sector purchasing
electricity from both public and private
generators and selling them to distributors
under Power Purchase and Power Sales
Agreements respectively. It may ultimately
be responsible for planning of least cost
generation expansion; arranging
establishment of private power generating
stations as per generation expansion plan
and for power system operation including
economic despatch of generation.

Standard Planning Data As referred to in Data Registration section.

Supervisory Control and Data The combination of transducers,


Acquisition / SCADA communication links and data processing
systems which provides information to the
LDC on the operation of the
Transmission System and the Generators’
Generating Units.

Supplier A person or establishment authorised to


supply electricity under a Licence granted
under the Act and who is subject to the
Grid Code.

System Planner The organization assigned by the


government time to time (presently BPDB
as Buyer or Power Cell) for preparing
Master Plan for Power Sector
Transmission Licence / Licence The Licence granted to the Transmission
Company by the Commission as per
provisions of the Act.

Grid Code (Draft) November 2010


14
Transmission System (Grid System) The system of EHV electric lines and
electrical equipment owned and/or operated
by the Licensee for the purpose of the
transmission of electricity between Power
Stations, External Interconnections and
the Distribution System.

User A person or establishment, including the


Licensee, Buyer, Generator and the
Supplier, who uses the Transmission
System and who must comply with the
provisions of the Grid Code.

Grid Code (Draft) November 2010


15
2.2 ABBREVIATIOS

Term Meaning

AACIR Average Annual Customer Interruption Rate


ABCB Air break Circuit Breaker
ACP Average Collection Period
AVR Automatic Voltage Regulator
B2B Back to Back
BERC Bangladesh Energy Regulatory Commission.
BPDB Bangladesh Power Development Board.
DPDC Dhaka Power Distribution Company Limited
DESCO Dhaka Electricity Supply Company Limited
EBIT Earnings Before Interest and Taxes
EHV Extra High Voltage
HP Horse Power
HV High Voltage
HVAC High Voltage Alternating Current
HVDC High Voltage Direct Current
Hz Hetrz
IEC International Electro-Technical Commission.
IEEE Institute of Electrical and Electronics Engineers
IPP Independent Power Producer.
kA Kilo Ampere
kV Kilovolt
kVAR Kilovolt Ampere Reactive
kW Kilowatt
kWh Kilowatt Hour
LDC Load Despatch Centre
mG Milli-Gauss
MPEMR Ministry of Power Energy and Mineral Resources.
MOCB Minimum Oil Circuit Breaker
mT Milli-Tesla

Grid Code (Draft) November 2010


16
MTBF Mean Time Between Failures
MTTR Mean Time To Repair
MW Megawatt
MWh Megawatt Hour
MVA Megavolt Ampere
MVAR Megavolt Ampere Reactive
LDC National Load Despatch Centre
PBS Palli Bidyut Samity.
PGCB Power Grid Company of Bangladesh Limited.
PPA Power Purchase Agreement.
REB Rural Electrification Board.
RMS Root Mean Square
ROA Return on Assets
SCADA Supervisory Control And Data Acquisition.
SF6 Sulphur Hexafluoride
TDD Total Demand Distortion
THD Total Harmonic Distortion
USoAC Uniform System of Accounts

Grid Code (Draft) November 2010


17
3. MAAGEMET OF THE GRID CODE

3.1 ITRODUCTIO

The Licensee is required to implement and comply with the Grid Code and
periodically review the same and its implementation. For the above purpose a Grid
Code Review Panel comprising of representatives of all Users of the Transmission
System shall be established.

Subject to the conditions in the next paragraph of this Section, a specific and
important feature of the Grid Code is that no revision or modification of the Code,
however large or small, may be made without being discussed at the Grid Code
Review Panel meeting and approved by the Commission.

The Commission may issue directions requiring the Licensee to revise the Grid
Code in such a manner as may be specified in those directions and the Licensee shall
promptly comply with any such directions.

This document defines the procedure to be followed by the Licensee in maintaining


the Grid Code and also in pursuing any change.

3.2 OBJECTIVE

The objective of this procedure is to define the method of managing the Grid Code,
submitting and pursuing of any proposed change to the Grid Code and the
responsibilities of all Users to effect that change.

3.3 RESPOSIBILITIES

The Licensee will be responsible for managing and servicing the Grid Code for
discharging its obligations under the Licence.

The Licensee shall establish and service the requirements of the Grid Code Review
Panel in accordance with provisions of Section 3.4 of the Code.

Grid Code (Draft) November 2010


18
3.4 GRID CODE REVIEW PAEL

The Grid Code Review Panel shall be maintained to undertake the following:

i. To keep and maintain the Grid Code and its workings under scrutiny and
review.
ii. To analyse any major grid disturbances soon after the occurrence and evolve
any consequent revision to the Grid Code.
iii. To consider all requests for amendment to the Grid Code which any User
makes.
iv. To publish recommendations for changes to the Grid Code together with
the reason for the change and any objections, if applicable.
v. To issue guidance on the interpretation and implementation of the Grid
Code.
vi. To examine problems raised by Users.

The Panel shall be chaired by the Transmission Company in its capacity as the
transmission Licensee and consist of the following members:

1. A Chairman who is an officer of the Licensee not below the rank of


Board Director;
2. A Technical Member (Secretary) who is an officer of the Licensee not
below the rank of Deputy Director;
A Single representative from each of the following:
3. One Member from BPDB (to represent Generation);
4. Two members from Distribution Utilities;
5. One Member from REB (to also represent the PBSs);
6. One Member from IPPs/ Private Generators (for tenure of one year
each on rotation basis to be notified by the Licensee, to represent all the
IPPs/ Private Generators in Bangladesh).
7. One Member to represent Buyer (if not represented from above)

The Licensee will inform all Users of the names and addresses of the Panel
Chairman and Technical Secretary at least seven days before the first Panel meeting,
and shall inform Users in writing of any subsequent changes.

Grid Code (Draft) November 2010


19
Each User shall inform the Panel Technical Secretary of the name and designation
of their Panel Representative not less than 3 working days before the first Panel
meeting and shall inform the Panel Technical Secretary, in writing, of any
subsequent change.

The Rules to be followed by the Panel in conducting their business shall be


formulated by the Panel themselves and shall be approved by the Commission. The
Panel will meet at least once in three months.

Sub-meetings may be held by the Licensee with a User to discuss individual requirements
and with groups of Users to prepare proposals for the Panel meeting. The Panel may set
up sub-committees for detailed studies of related problems.

3.5 GRID CODE REVIEW AD REVISIOS

The Technical Secretary shall present all proposed revisions of the Grid Code to the
Panel for its consideration.

The Licensee shall send to the Commission following reports at the conclusion of
each Review Meeting of the Panel.

(a) A report on the outcome of such review.


(b) Any proposed revisions to the Grid Code as the Licensee reasonably
thinks necessary for the achievement of the defined objectives.
(c) All written representations or objections from Users arising during the
review.

All revisions to the Grid Code shall require approval of the Commission. The
Commission shall publish revisions to the Grid Code once approved by the
Commission.

The Licensee shall present proposals to the Commission to allow relaxation, where
Users have difficulties in meeting the Grid Code requirements.

The revision number and date of issue shall appear on every page of the Grid Code.

Grid Code (Draft) November 2010


20
Every change from the previous version shall be clearly marked in the margin. In
addition, a revision sheet shall be placed at the front of the revised version that lists
the number of every changed sub-Section, together with a brief description of
change.

The Licensee shall keep an up-to-date list of the recipients and locations of all
serviced copies of the Grid Code.

Grid Code (Draft) November 2010


21
4. TRASMISSIO SYSTEM PLAIG

4.1 ITRODUCTIO

This Section identifies the method for data submissions by Users to the Licensee for
the planning and development of the Transmission System. This Section also
specifies the technical and design criteria and procedure to be applied by the
Licensee in the planning and development of the Transmission System.

A requirement for reinforcement or extension of the Transmission System may


arise for a number of reasons, including but not limited to the following.

i. Development on a User’s system already connected to the Transmission


System.
ii. The introduction of a new Connection point between the User’s system
and the Transmission System.
iii. An increase in system capacity to remove operating constraints and
maintain standards of security.
iv. Stability considerations.
v. Cumulative effect of any of the above.

Accordingly, the reinforcement or extension of the Transmission System may


involve work at an entry or exit point (Connection point) of a Generator or
Distribution Utility to the Transmission System.

Since development of all Users’ systems must be planned well in advance to permit
consents and wayleaves to be obtained and detailed engineering design/construction
work to be completed, the Licensee will require information from Users and vice
versa. To this effect the Planning Code imposes a time scale, for exchange of
necessary information between the Licensee and Users having regard, where
appropriate, to the confidentiality of such information.

Grid Code (Draft) November 2010


22
4.2 OBJECTIVE

The provisions of this section are intended to enable the Licensee in consultation
with Generators and Users, to provide an efficient, co-ordinated, secure and
economical Transmission System to satisfy requirement of future demand.

4.3 PERSPECTIVE PLA

4.3.1 The organization assigned by the government time to time, termed as System
Planner, will prepare and submit a long-term (preferably 20 years which may be
termed as planning-term) Power System Master Plan to the Commission for
generation expansion and for Transmission System expansion to meet the future
demand.

4.3.2 For fulfilment of the above requirement the System Planner and the Licensee
shall work together to:

i. Forecast the demand for power within the Area of supply in each of
the succeeding planning-term and provide to the Commission details
of the demand forecasts, data, methodology and assumptions on which
the forecasts are based.

ii. Prepare a least cost generation plan for the Power System to meet the
long-term load demand as per the forecast, after examining the
economic, technical and environmental aspects of all available
alternatives taking into account the existing contracted generation
resources and effects of demand side management.

iii. Prepare a long-term plan for the expansion of the Transmission


System compatible with the above load forecast and generation plan.

iv. Combine the three elements above to form the Power System Master
Plan which shall be reviewed yearly to identify any major
changes/requirements and communicated to the Commission

Grid Code (Draft) November 2010


23
v. The Power System Master Plan shall be updated periodically,
preferably every 5 years and used as an input to the ational Plan

4.4 PLAIG STADARDS AD PROCEDURES

The Transmission System shall be planned in accordance with the Transmission


System planning and security standards.

Voltage limits at 132 kV, 230 kV and 400 kV Bus


+/- 10% during emergencies.
+/-5% during normal operations.

Line outages
single contingency of a permanent three-phase outage of any one circuit
element or transformer.

Stability
to be maintained stable during a fault clearance by three-phase trip within 5
cycles and followed by successful reclosure within 15 cycles.

Power factor
on 400 kV side of 400/230/132 kV substation 0.95 lagging on 230 kV side
of 230/132 kV substation 0.95 lagging
on 132 kV side of 132/33 kV substation 0.9 lagging

The generation expansion planning shall be carried out in accordance with the power
supply planning and security standards.

4.5 PLAIG RESPOSIBILITY

4.5.1 The primary responsibility of load forecasting within its area rests with each of
the Distribution Utilities. The Distribution Utilities shall determine peak load and
energy forecasts of their respective areas for each category of loads for each of the
succeeding planning-term and submit the same annually by 31st March to the
Licensee and System Planner, along with details of the demand forecasts, data,
methodology and assumptions on which the forecasts are based. The load forecasts
Grid Code (Draft) November 2010
24
shall be made for each of the interconnection points between the Licensee and User
and shall include annual peak load and energy projections and daily load curve. The
demand forecasts shall be updated annually or whenever major changes are made in
the existing forecasts or planning. While indicating requirements of single
consumers with large demands (5 MW or higher) the Distribution Utility shall
satisfy itself as to the degree of certainty of the demand materialising.

4.5.2 The Licensee and System Planner are responsible for integrating the load
forecasts submitted by each of the Distribution Utilities and determining the long-
term (20 years) load forecasts for the Power System. In doing so the Licensee and
System Planner may apply appropriate diversity factors, and satisfy itself regarding
probability of materialisation of bulk loads of consumers with demands above 5 MW
in consultation with that Distribution Utility concerned.

4.5.3 The Licensee and System Planner may also review the methodology and
assumptions used by the Distribution Utility in making the load forecast, in
consultation with the Distribution Utility. The resulting overall load forecast will
form the basis of planing for expansion of generation and the Transmission System.

4.6 PLAIG DATA REQUIREMET

4.6.1 To assist the System Planner to discharge its responsibilities under his licence
the Licensee and the System Planner shall jointly conduct System Studies and
prepare perspective plans for the Transmission System as detailed in paragraph 4.3
of this Section. The Users shall furnish data to the Licensee and System Planner
from time to time as detailed under Data Registration Section and categorised as
Planning Data (PD).

4.6.2 To enable Users to co-ordinate planning, design and operation of their plants
and systems with the Transmission System they may seek certain salient data of
Transmission system as applicable to them, which the Licensee shall supply from
time to time as detailed under Data Registration Section and categorised as Detailed
System Data (Transmission).

Grid Code (Draft) November 2010


25
5. COECTIO CODITIOS

5.1 ITRODUCTIO

Connection Conditions specify the technical, design and operational criteria that
must be complied with by any User connected to the Transmission System.

5.2 OBJECTIVE

The objective of this Section is to ensure the following:

i. All Users or prospective Users are treated equitably.


ii. Any new Connection shall not impose any adverse effects on existing
Users, nor shall a new Connection suffer adversely due to existing Users.
iii. By specifying minimum design and operational criteria, to assist Users in
their requirement to comply with Licence obligations and hence ensure that
a system of acceptable quality is maintained.
iv. The ownership and responsibility for all items of equipment is clearly
specified in a schedule (Site Responsibility Schedule) for every site where a
Connection is made.

5.3 SITE RESPOSIBILITY SCHEDULE

For every Connection to the Transmission System for which a Connection


Agreement is required, the Licensee shall prepare a schedule of equipment with
information supplied by the respective Users. This schedule, called a Site
Responsibility Schedule, shall state the following for each item of equipment
installed at the Connection Site:

i. The ownership of equipment.


ii. The responsibility for control of equipment.
iii. The responsibility for maintenance of equipment.
iv. The responsibility for operation of equipment.
v. The manager of the site.
vi. The responsibility for all matters relating to safety of persons at site.

Grid Code (Draft) November 2010


26
An illustrative Site Responsibility Schedule is provided at Appendix.

5.3.1 The User owning the Connection site shall provide reasonable access and
other required facilities to another User whose equipment is installed at the
Connection site for installation, operation and maintenance, etc.

5.4 SYSTEM PERFORMACE

All equipment connected to the Transmission System shall be of such design and
construction as to satisfy at least the requirements of the relevant Bangladesh
Standard Specification, where no Standard exists the appropriate IEC Standard or
other International Standard will apply.

Installation of all electrical equipment shall comply with Electricity Rules, 1937.

For every new Connection sought, the Licensee shall specify the Connection Point
and the voltage to be used, along with the metering and protection requirements as
specified in the Metering and Protection Sections.

The Generator shall ensure that each Generating Unit is capable of generating at
full rated power output within the frequency range of 48.5 – 51.5 Hz, +/- 10% rated
voltage and power factor 0.8 lagging to 0.95 leading.

The Transmission System frequency shall normally be 50.0 Hz and shall normally
be controlled in the range 49.0 – 51.0 Hz (50 Hz ± 2%). The User shall however be
subject to the grid discipline directed by the Commission.

Voltage variation on the Transmission System shall normally be +/- 10% during
emergencies and +/- 5% during normal operation, in accordance with the provisions
of Planning and Security Standards for Transmission System.

Insulation coordination of the Users’ equipment and rupturing capacity of switchgear


shall conform to applicable Bangladesh Standards/Codes.

Protection schemes and Metering schemes shall be as detailed in the Protection &
Metering Sections of the Code.

Grid Code (Draft) November 2010


27
For existing Power Stations, the equipment for data transmission and
communications shall be owned and maintained by the Licensee, unless alternative
arrangements are mutually agreed.

For new Power Stations the equipment within their site for data transmission and
communications shall be owned and maintained by the respective Generator.

5.5 REACTIVE POWER COMPESATIO

For new connections

Reactive Power Compensation and/or other facilities, shall be provided by


concerned Users as far as possible in the low voltage systems close to the load
points to avoid the need for exchange of reactive power to/from the Transmission
System and to maintain Transmission System voltage within the specified range.

For existing connections

Concerned Users shall ensure to improve load power factor by providing reactive
compensation facilities at load end within time frame agreed between the Licensee
and the User. Such time frame shall not, however exceed 24 months from the date of
the agreement.

5.6 COECTIO POIT

5.6.1 Generator

Voltage may be 400 kV/ 230 kV/ 132 kV or as agreed with the Licensee

For new Power Stations or connections

Unless specifically agreed with the Licensee the Connection point shall be the
outgoing gantry of Power Station switchyard. The metering point shall be at the
outgoing connection point. All the terminal communication, protection and metering
equipment owned by the Generator within the perimeter of the Generator’s site
shall be maintained by the Generator. Other Users’ equipment shall be maintained
by the respective Users. From the outgoing feeder gantry onwards, the Licensee
shall maintain all electrical equipment.
Grid Code (Draft) November 2010
28
For existing Power Stations

As for new connections excepting that the existing arrangement of maintenance of


all line bay equipment installed within the substation attached to the Power Station,
viz. Circuit Breaker, Isolator, Lightning Arrester, Current Transformer, Voltage
Transformer etc., by the Power Station, shall continue until fresh agreements are
made in this regard. However, maintenance of protection and communication
equipment shall continue to be the responsibility of the Licensee as before.

5.6.2 Distribution Utility

Voltage may be 132 kV/ 33 kV/ 11 kV or as agreed with the Licensee.


The Connection point shall be the outgoing feeder gantry of the Licensee’s Grid
substation. The metering point shall be at the outgoing feeder. The Licensee shall
maintain all the terminal, communication, protection and metering equipment within
the premises of the Licensee. From the outgoing feeder gantry onwards, the
respective Distribution Utility shall maintain its own electrical equipment.

5.6.3 Bulk Power Consumers

Voltage may be 132 kV/ 33 kV or as agreed with the Licensee.


The Connection point shall be the outgoing feeder gantry of the Licensee’s Grid
substation. The metering point shall be at the outgoing feeder. From the outgoing
feeder gantry onwards, Bulk Power Consumer shall maintain its own electrical
equipment.
Substation at consumer’s premises shall be built, owned and maintained by the Bulk
Power Consumer unless otherwise agreed with the Licensee. The Bulk Power
Consumer’s substation shall be fed by redial feeder(s) from nearest Grid substation.
To ensure Grid safety, transmission lines shall not be diverted to consumer’s
substation i.e., Line In and Line Out shall not be permitted by the Licensee.

5.7 DATA REQUIREMETS

Users shall provide the Licensee with data for this Section as specified in the Data
Registration Section.

Grid Code (Draft) November 2010


29
5.8 PROCEDURE FOR APPLICATIOS FOR COECTIO TO AD USE OF
THE TRASMISSIO SYSTEM

5.8.1 Any User seeking to establish new or modified arrangements for Connection
to and/or use of the Transmission System shall submit the following report, data
and undertaking along with an application to the Licensee:

i. Report stating purpose of proposed Connection and/or modification,


Connection site, description of Apparatus to be connected or
modification to Apparatus already connected.
ii. Data as applicable and as listed in the Data Registration Section.
iii. Confirmation that the prospective installation complies with the
provisions in the Electricity Act, 1910 and revisions thereof.
iv. Construction schedule and target completion date.
v. An undertaking that the User shall abide by Grid Code and provisions of
the Electricity Rules, 1937, for installation and operation of the
Apparatus.

5.8.2 The Licensee shall normally make a formal offer to the User within 2 months
of receipt of the application complete with all information as may reasonably be
required, subject to provision in paragraph 5.8.5.

5.8.3 The offer shall specify and take into account any works required for the
extension or reinforcement of the Transmission System to satisfy the requirements
of the Connection application and for obtaining statutory clearances, wayleaves as
necessary.

5.8.4 In respect of offers for modification of existing Connection, the terms shall
take into account, the existing Connection Agreement.

5.8.5
i. If the nature of complexity of the proposal is such that the prescribed time
limit for making the offer is not adequate, the Licensee shall make a
preliminary offer within the prescribed time limit. The offer shall indicate

Grid Code (Draft) November 2010


30
the extent of further time required with the consent of the Commission for
more detailed examination of the issues.

ii. On receipt of the preliminary offer, the User shall indicate promptly
whether the Licensee should proceed further to make a final offer within the
extended time limit.

5.8.6 All offers (other than preliminary offers) including revised offers shall remain
valid for 60 days of issue of offer.

5.8.7 The Licensee shall make a revised offer, upon request by a User, if
necessitated by changes in data earlier furnished by the User.

5.8.8 In the event of the offer becoming invalid or not being accepted by any User
within the validity period, no further action shall be taken by the Licensee on the
Connection applications.

5.8.9 The Licensee may reject any application for Connection to and/or use of
Transmission System:

i. If such proposed Connection will violate any provisions of the


Transmission Licence.

ii. If the proposed works stated in the application do not lie within the purview
of the Licence or do not conform to any provision of the Grid Code.

iii. If the applicant fails to give confirmation and undertakings according to


sub- Section 5.8.1 and 5.8.2 of this Section.

5.9 ITERATIOAL AD ITER-REGIOAL COECTIO

5.9.1 International and Inter-regional connection will be:


a) Synchronous or
b) Asynchronous

The procedure for International Connection to the Grid and the execution of
agreement for the same shall be done by the Licensee in consultation with the
Commission and the Line Ministry.
Grid Code (Draft) November 2010
31
5.9.2 HVDC Transmission
Asynchronous connection may be established by HVDC transmission having any of
the following options:
a) Rectifier at sending end and Inverter at receiving-end
b) Back to Back (B2B) with Rectifier and Inverter at both ends.

HVDC transmission design and appropriate configuration of overhead and


underground transmission connections will be determined following international
standards. Configurations may be:
a) Monopole with ground return
b) Monopole with metallic return grounded at both-ends
c) Bipolar, opposite polarity, grounded neutral at both ends
d) Bipolar, opposite polarity, with metallic return conductor

5.9.3 HVAC Asynchronous Connection


Asynchronous connection may be established by HVAC transmission running up to
Back to Back (B2B) interface substation.

5.10 COECTIO AGREEMETS

A Connection Agreement shall include, as appropriate, within its terms and


conditions the following:
i. a condition requiring both parties to comply with the Grid Code;
ii. details of Connection and/or use of system charges;
iii. details of any capital related payments arising from necessary reinforcement
or extension of the system;
iv. a Site Responsibility Schedule;

5.11 APPEDIX

General format for Site Responsibility Schedule.

Grid Code (Draft) November 2010


32
APPEDIX
COECTIO CODITIOS
SITE RESPOSIBILITY SCHEDULE

Name of Power Station/Substation: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Site Owner: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .


Tel. Number: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fax Number: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Safety Control Operation Maintenance
Item of Plant/Apparatus Plant Owner Responsibility Responsibility Responsibility Responsibility Remarks
1 2 3 4 5 6 7
........ kV Switchyard
All equipment including busbars
Feeders

Generating Units

Grid Code (Draft) 33 November 2010


6. OUTAGE PLAIG

6.1 ITRODUCTIO

This Section describes the process by which the Licensee carries out the planning of
Transmission System Outages, including interface coordination with Users.

6.2 OBJECTIVE

The objective of this Section is to define the process that will allow the Licensee to
optimise transmission Outages with generator and other Users’ Outages while
maintaining system security to the extent possible.

6.3 DEMAD ESTIMATIO

Demand estimation is necessary both in the medium time scale to ensure adequate
system plant margins and ratings and in the shorter time scale to assist with frequency
control (see Schedule and Despatch Section).

Distribution Utilities shall provide to the Licensee their estimates of demand at each
inter-connection point for the period from July to June by 31st March of each year on
a 2 year ahead, year ahead, month ahead, week ahead and day ahead basis as required.

Based on this, the Licensee shall make monthly peak and off peak period demand
estimates for the year ahead, daily peak and off peak period demand estimates for the
month ahead and hourly demand estimates for the day ahead.

Distribution Utilities shall provide to the Licensee estimates of load that may be
shed, when required, in discrete blocks with the details of the arrangements of such
load shedding.

All data shall be collected in accordance with procedures agreed between the
Licensee and each User.

The Licensee shall maintain a database of demand on an hourly basis.

Grid Code (Draft) 34 November 2010


6.4 GEERATOR OPERATIG COMMITTEES

The Licensee, the LDC and the Generators shall establish Operating
Committees, consisting of at least 2 members for each party, which shall serve as a
point of coordination for the respective parties.

They shall meet once a month and establish the procedures relating to the operational
interfaces between the parties. They shall include

a) The coordination of programmes for testing and operation of the interconnections


and associated transmission grid system apparatus, the metering system and the
site.
b) Incident coordination (i.e., force majeure events)
c) Outage coordination
d) Generation Scheduling
e) Safety matters
f) Emergency Plans
g) Protection coordination
h) Any other operational matters agreed by the Committees

6.5 TRASMISSIO OUTAGE PLAIG PROCESS

The Licensee shall produce a yearly transmission Outage programme for the period
July to June.

All Generators shall provide the Licensee and the LDC with their proposed
Outage programmes in writing for the 2 year ahead and year ahead (July to June) by
31st March each year.

All Distribution Utilities shall provide the Licensee with their proposed Outage
programmes in writing for the 2 year ahead and year ahead (July to June) by 31st
March each year.

Outage programmes shall contain identification of unit (for Generating Units),


Outage start date and duration of Outage.

Grid Code (Draft) 35 November 2010


The Licensee shall produce a draft Outage programme based on the information
received from Generators and Distribution Utilities, taking into account demand
estimation and shall carry out studies as required each year.

The Licensee shall interact with all Users as necessary to review and optimise the
draft plan, agree to any changes and produce an acceptable co-ordinated generation
and transmission Outage plan. The Licensee shall release the finally agreed
transmission Outage plan, which takes account of User requirements, to all Users by
31st May each year.

The Licensee shall review the final Outage plan monthly in consultation with Users,
who shall be informed by Licensee of any proposed changes.

Users’ requests for additional Outages will be considered by Licensee and


accommodated to the extent possible.

The Licensee shall inform Users promptly of any changes that affect them.

6.6 RELEASE OF CIRCUITS AD GEERATOR UITS ICLUDED I


OUTAGE PLA

Notwithstanding provision in any approved Outage plan, no cross boundary circuits


or Generating Unit of a Generator shall be removed from service without specific
release from the LDC.

Once an Outage has commenced, if any delay in restoration is apprehended, the


LDC or User concerned shall inform the other party promptly together with revised
estimation of restoration time.

6.7 DATA REQUIREMETS

Users shall provide the Licensee with data for this Section as specified in the Data
Registration Section.

Grid Code (Draft) 36 November 2010


7. SCHEDULE AD DESPATCH

7.1 ITRODUCTIO

This Section specifies the procedure to be adopted for the scheduling and despatch of
Generating Units to meet system demand.

7.2 OBJECTIVE

The objective of this Section is to detail the actions and responsibilities of the
Licensee and LDC in preparing and issuing generation schedules and the
responsibilities of Users to supply the necessary data and to comply with those
schedules.

7.3 GEERATIO SCHEDULIG

7.3.1 Yearly/ Quarterly/ Monthly/ Weekly Schedules

The LDC and the Licensee shall co-ordinate and prepare yearly/quarterly/monthly
and weekly load/generation balance schedules and Generation schedules. The demand
estimation for each case shall be made by the Licensee using the data made available
by the Distribution Utilities and historical data maintained by the Licensee.

The LDC shall prepare a yearly schedule of net electrical output on a monthly
basis, using the information from the yearly outage programme and estimated
demands.

The Generator shall inform the LDC promptly of any changes to any of the net
electrical output notifications.

The LDC shall provide to the Licensee and Generators yearly estimates of
requirements for net electrical output on a monthly basis for the year ahead (year
ahead notification) not less than 90 days before the beginning of each calendar year.
The Licensee in turn submit the monthly estimates of net electrical output
requirement to the Commission.

Grid Code (Draft) 37 November 2010


The LDC shall prepare a quarterly schedule of Generation on a week by week basis,
using any net electrical output changes provided by the Generator and estimated
demands.

The LDC shall provide to the Licensee and the Generators quarterley estimates of
requirements for net electrical output on a week by week basis for the quarter ahead
(quarter ahead notification), with revised estimates for the remaining quarters of the
current year, not less than 60 days before the beginning of each quarter.

The LDC shall prepare a monthly schedule of Generation on a day by day basis,
using any net electrical output changes provided by the Generator and estimated
demands.

The LDC shall provide to the Licensee and Generators monthly estimates of
requirements for net electrical output on a weekly basis for the month ahead (month
ahead notification), with provisional estimates for the following 2 months, not less
than 14 days before the beginning of each month.

The LDC shall prepare a weekly schedule of Generation on an hourly basis, using
any net electrical output changes provided by the Generator and estimated
demands.

The LDC shall provide to the Licensee and Generators weekly estimates of
requirements for net electrical output on an hourly basis for the week ahead (week
ahead notification), with provisional estimates for the following week, not less than
48 hours before the beginning of each week.

7.3.2 Day ahead schedule

The LDC shall co-ordinate and prepare day ahead schedules of Generation

All Generators shall provide the MW/ MVAR declared availability capacity (00.00 -
24.00 hours) of all Generating Units, to the LDC during each hour of the day
commencing 36 hours ahead and provisionally, for the day immediately after (plant
availability notification) by 12.00 hours.

Grid Code (Draft) 38 November 2010


In working out the MW/ MVAR availability, Hydro Power Stations shall take into
account their respective reservoir levels and any other restrictions and shall report the
same to the LDC.

The LDC shall produce a day ahead hourly generation schedule after consolidation
of the data provided by the Generators. It shall consist of availability, scheduled
generation, allocated spinning reserve and Generating Unit standby requirements. It
shall also take into account the hourly demand estimates and the following:

Transmission System constraints


Generating Unit availability
Generating Units Schedule and Despatch parameters
Requirements for voltage control
Operating reserve
Requirements for frequency control
Economic order of Generating Units

The LDC shall provide to the Licensee and Generators the generation schedule
requirements for net electrical output, start ups and reactive power on an hourly
basis for that day, with provisional estimates for the following day, not less than 7
hours before the beginning of each day.

Generators shall promptly report to the LDC, changes of Generating Unit


availability or capability, or any unexpected situation that could affect its operation.

The LDC shall advise Users as soon as possible of any necessary rescheduling.

The LDC shall instruct Generators to hold capacity reserves (spinning and/or
standby) to the agreed Commission guidelines or as determined for local conditions.

The LDC may also require the Generators to generateMVAR within their
respective capability limits to hold station bus bar voltages at specified levels.

Grid Code (Draft) 39 November 2010


7.4 GEERATIO DESPATCH

All Generators will be subject to central despatch instructions and shall regulate
generation according to these instructions.

In absence of any despatch instructions by the LDC, Generators shall generate


according to the day ahead generation schedule.

Despatch instructions shall be in standard format. These instructions will recognise


declared availability, economic data and other parameters that have been made
available by the Generator to the LDC. These instructions shall include time,
Power Station, Generating Units, name of operators sending and receiving the
same.

Despatch instructions include but not limited to:

i. Switching a Generating Unit into or out of service.


ii. Details of reserve to be carried on a unit.
iii. To increase or decrease MVAR generation to assist with voltage profile.
iv. To begin pre-planned Black Start procedures.
v. To hold spinning reserve.
vi. To hold Generating Units on standby.

7.5 COMMUICATIO WITH GEERATORS

Despatch instructions shall be issued by telephone, confirmed by exchange of names


of operators sending and receiving the same and logging the same at each end. All
such oral instructions shall be complied with forthwith and written confirmation shall
be issued promptly by Fax, Tele-printer or otherwise.

7.6 ACTIO REQUIRED BY GEERATORS

All Generators shall comply promptly with a despatch instruction issued by the
LDC unless this action would compromise the safety of plant or personnel.

Grid Code (Draft) 40 November 2010


The Generator shall promptly inform the LDC in the event of any unforeseen
difficulties in carrying out an instruction.

Generators shall immediately inform the LDC by telephone of any loss or change
(temporary or otherwise) to the operational capability of any Generating Unit which
is synchronised to the system or which is being used to maintain system reserve.
Generators shall inform the LDC of any change of AVR and/or governor control
mode of service with reasons.

Generators shall not de-synchronise Generating Units without instruction from the
LDC except on the grounds of safety to plant or personnel, which shall be promptly
reported to the LDC.

Generators shall report any abnormal voltage and frequency related operation of
Generating Units / feeders promptly to the LDC.

Generators shall not synchronise Generating Units without instruction from the
LDC. In emergency situations, the Generator may synchronise Units with the grid
without prior intimation in the interest of the operation of the grid following standing
instructions developed for such purpose under “contingency planning”.

Should a Generator fail to comply with any of the above provisions, it shall inform
the LDC promptly of this failure.

The LDC shall ensure that the Licensee is kept informed and up to date with all
operation changes and deviations from the planned schedule

7.7 DATA REQUIREMETS

Users shall provide the LDC with data for this Section as specified in the Data
Registration Section.

Grid Code (Draft) 41 November 2010


8. FREQUECY AD VOLTAGE MAAGEMET

8.1 ITRODUCTIO

This Section describes the method by which all Users of the Transmission System
shall cooperate with the Licensee in contributing towards effective control of the
system frequency and managing the EHV voltage of the Transmission System.

The LDC has the overall responsibility of enforcing grid discipline and managing
the frequency of the Power System. The Users are required to follow the instructions
of the LDC for the backing down generation, regulating load, etc. to meet the
objective. The LDC shall accordingly instruct Generating Units to regulate
generation/export and hold reserves of active and reactive power, within their
respective declared parameters. The LDC shall also regulate load as may be
necessary to meet this objective.

High voltages generally occur during high frequency and vice versa, therefore system
frequency regulation must be recognised as an important method of voltage control.
The Licensee shall optimise voltage management in joint consultation with the
LDC by adjusting transformer taps to the extent available and switching of
circuits/reactors and other operational steps. The LDC will instruct Generating
Units to regulate MVAR generation within their declared parameters. The LDC
shall also instruct Distribution Utilities to regulate demand if necessary.

The supply of quality power at proper voltage and frequency is dependent on active
cooperation of Generators and Distribution Utilities as well as fulfilment of
obligations of individual Users of the Transmission System.

8.2 OBJECTIVE

The objectives of this Section are as follows:

i. To define the responsibilities of all Users in contributing to frequency


management.

Grid Code (Draft) 42 November 2010


ii. To define the actions required to enable the Licensee to maintain
Transmission System voltages and frequency within acceptable levels in
accordance with Commission guidelines, and Planning and Security
Standards for Transmission System.

8.3 FREQUECY MAAGEMET

The normal frequency range will be 49.0 – 51.0 (50 Hz ± 2.0%). The LDC shall
identify frequency deviations beyond the normal range and take the appropriate action
to bring the frequency back within the normal range.

8.4 RESPOSIBILITIES

The LDC shall monitor actual generation and load generation balance AND
regulate generation to maintain frequency within the prescribed limits.

The Licensee shall continuously monitor 400KV/230KV/132KV transmission grid


line loadings on the Transmission System.

Generators shall follow the despatch instructions issued by the LDC.

All Generating Units shall have the governor available and in service and must be
capable of automatic increase or decrease in output within the normal declared
frequency range and within their respective capability limit.

Under certain conditions the system frequency could rise to 52Hz or fall to 47Hz. All
Generating Units should be capable of operating within the range and the LDC
informed promptly of any restrictions. Generators shall be responsible for protecting
their Generating Units against damage should frequency excursions outside 52Hz
and 47Hz ever occur. Should such excursions occur, the Generator should decide
whether or not to disconnect his apparatus for reasons of safety of Apparatus, Plant
and/or Personnel. The Generator shall inform the LDC immediately after taking
such action.

Distribution Utilities shall co-operate with the LDC in managing load on


instruction from the LDC as required.

Grid Code (Draft) 43 November 2010


8.4.1 Sustained rising frequency

Under rising frequency conditions, the LDC shall take appropriate action to issue
instructions to Generators to arrest the rising frequency and restore frequency within
normal range. Such instructions may include reducing generated output or de-
synchronising Generating Units from the Transmission System.

When the frequency rises above 51.0 Hz actions must be taken immediately by the
Generator without reference to the LDC. All synchronised Generating Units shall
decrease their Generating Output at a rate of – (minus) 2% per 0.1 Hz for departure of
frequency above 51.0 Hz until the frequency is restored within the normal range. The
Generator shall inform the LDC immediately after taking such action.

8.4.2 Sustained falling frequency

Under falling frequency conditions, the LDC shall take appropriate action to issue
instructions to arrest the falling frequency and restore it to be within normal range.
Such instructions may include despatch instructions to Generators to increase
output, to synchronise standby Generating Units to the Transmission System and/or
instructions to Distribution Utilities to reduce load demand by appropriate manual
and /or automatic load shedding.

When the frequency falls below 49.0 Hz all synchronised Generating Units shall
increase their Generating Output at a rate of + (plus) 2% per 0.1 Hz (if available) for
departure of frequency below 49.0 Hz until the frequency is restored within the
normal range. The Generator shall inform the LDC immediately after taking such
action.

All Generating Units that have been declared available shall be required to be
synchronised and loaded in the event of the sustained low frequency below 49.0 Hz
provided local and safety conditions permit. This action shall be performed without
delay after failed attempts to contact the LDC. The Generator shall inform the
LDC immediately after taking such action.

Grid Code (Draft) 44 November 2010


The LDC shall be responsible for the coordination, selection and settings of staged
automatic relay initiated under-frequency load shedding designed for system
protection.

8.5 VOLTAGE MAAGEMET

The Licensee and LDC shall carry out load flow studies from time to time to
predict where voltage problems may be encountered and to identify appropriate
measures to ensure that voltages remain within the defined limits. On the basis of
these studies the LDC shall instruct Generators to maintain specified voltage
levels at interconnecting points.

The Licensee shall co-ordinate with the Distribution Utilities to determine voltage
levels at the interconnection points with Distribution Utilities.

The Licensee shall continuously monitor 400 kV/ 230 kV/ 132 kV transmission grid
voltage levels at strategic substations.

The LDC and the Licensee shall regulate voltage levels within the prescribed
levels.

The LDC and the Licensee shall jointly take appropriate measures to control
Transmission System voltages that may include but not be limited to transformer tap
changing and use of MVAR reserves with Generating units within technical limits
agreed to between the LDC, Licensee and Generating units.

All Generating Units shall have Automatic Voltage Regulator (AVR) in service.

Generators shall inform the LDC of their reactive reserve capability promptly on
request.

Generators shall make available to the LDC the up-to-date capability curves for all
Generating Units, as detailed in Section 5, indicating any restrictions, to allow
accurate system studies and effective operation of the Transmission System.

Grid Code (Draft) 45 November 2010


Distribution Utilities shall participate in voltage management by regulating their
demand as may be required.

8.6 GEERAL

Close coordination between Users and the LDC shall exist at all times for the
purposes of effective frequency and voltage management.

8.7 MOITORIG OF GEERATIO

8.7.1 For effective operation of the Transmission System, it is important that a


Generator’s declared availability is realistic and that any departures are continually
fed back to the Generator to help effect improvement. The monitoring by the LDC
of Generating Unit output, and active and reactive reserve capacity, shall be carried
out to evaluate the reliability and performance of plant.

The LDC shall continuously monitor Generating Unit outputs and bus voltages.
More stringent monitoring may be performed at any time, as detailed in the Testing
Section, when there is reason to believe that a Generator’s declared availability may
not match the actual availability or declared output does not match the actual output.

Generators shall provide to the LDC hourly generation summation outputs where
no automatically transmitted metering or SCADA equipment exists.

The Generator shall provide other logged readings, that the LDC may reasonably
require, for monitoring purposes where SCADA data is not available.

8.7.2 Generating Unit Tripping

Generators shall promptly inform the tripping of a Generating Unit, with reasons,
to LDC in accordance with the Operational Event/Accident Reporting Section.
LDC shall keep a written log of all such tripping, including the reasons with a view
to demonstrating the effect on system performance and identifying the need for
remedial measures.

Grid Code (Draft) 46 November 2010


Generators shall submit a more detailed report of all trippings and forced
outage/shutdowns of each Generating Unit to LDC monthly.

8.7.3 Data Requirements

Generators shall submit data to LDC as listed in Data Registration Section, termed
as Frequency and Voltage Management.

Grid Code (Draft) 47 November 2010


9. COTIGECY PLAIG

9.1 ITRODUCTIO

This Section describes the recovery process to be followed by the Licensee and all
Users in the event of Transmission System total or partial blackouts.

9.2 OBJECTIVE

The objective of this Section is to define the responsibilities of all Users to achieve
the fastest recovery in the event of a Transmission System blackout, taking into
account essential loads, Generator capabilities and system constraints.

9.3 STRATEGY

The situation prevailing prior to the occurrence of the contingency, e.g. availability of
specific generators, transmission circuits and load demands, will largely determine
the restorations process to be adopted in the event of a total blackout. LDC shall
advise all Users of the situation and follow the strategy as outlined below for
restoration.

User’s persons authorised for operation and control shall be available at User’s end
for communication and acceptance of all operational communications throughout the
contingency. Communication channels shall be restricted to operational
communications only till normality is restored.

9.3.1 Total System Blackout

LDC shall instruct all relevant Generators having Power Stations with Black
Start capability to commence their pre-planned Black Start procedure.

LDC shall prepare the Transmission System for restoration by creating discrete
power islands with no interconnection. Close coordination with concerned
Distribution Utilities shall be maintained during the restoration process to arrange
for discrete demand blocks becoming available to stabilise Generating Units, as

Grid Code (Draft) 48 November 2010


these become available in individual islands. Generators to whom start up power
supply is made available shall sequence their start up to match their auxiliary power
demand with supply available.

Generators shall inform LDC as Generating Units become available to take load,
in order that the LDC may assess the MW demand which the Generating Unit is
likely to pick up on circuit breaker closure.

LDC shall co-ordinate with Generators and Distribution Utilities to:

i. Form discrete power islands with one Generating Unit feeding some local
demand.
ii. Extend islands by adding more Generating Units and more demand in a co-
ordinated manner maintaining load generation balance.
iii. Synchronise islands to form a larger, more stable island.

LDC shall utilise any inter-Bangladesh assistance available, if appropriate, at any


time to assist in the above process.

9.3.2 Partial Transmission System Blackout

LDC shall ensure with the Licensee and Users that security of the healthy part of
the Transmission System is maintained.

LDC and the Licensee shall gradually extend the healthy system to provide start-up
power to appropriate Generating Units.

LDC and the Licensee with close coordination with Distribution Utilities and
Generators shall gradually restore demand to match generation as it becomes
available.

All Users shall take care to ensure load generation balance is maintained at all times
under LDC’s direction.

Grid Code (Draft) 49 November 2010


9.4 RESPOSIBILITIES

LDC shall maintain a record of Power Station Black Start capability and
associated Power Station Black Start plans.

The LDC shall prepare, distribute and maintain up-to-date Black Start procedures
covering the restoration of the Transmission System following total or partial
blackout. Updated Black-Start procedures shall be submitted to the Commission.

Users shall agree regarding Black Start procedures with the LDC and the Licensee
and promptly inform LDC when unable to follow the procedure.

LDC and the Licensee shall be responsible for directing the overall Transmission
System restoration process by coordination with all Users.

Distribution Utilities shall be responsible for sectionalising the Distribution System


into discrete, unconnected blocks of demand. They shall advise LDC of the amount
of MW likely to be picked up by the synchronising Generator.

Generators shall be responsible for commencing their planned Black Start


procedure on the instruction of LDC and steadily increasing their generation
according to the demand that the LDC is able to make available.

9.5 SPECIAL COSIDERATIOS

During the restoration process following Transmission System blackout conditions,


normal standards of voltage and frequency shall not apply.

A list of essential loads and priority of restoration is shown in the Appendix.

Distribution Utilities with essential loads shall separately identify non-essential


components of such loads, which may be kept off during System contingencies.
Distribution Utilities shall draw up an appropriate schedule with corresponding load
blocks in each case. The non-essential loads can be put on only when system
normalcy is restored, as advised by LDC.

Grid Code (Draft) 50 November 2010


All Users shall pay special attention in carrying out the procedures so that secondary
collapse due to undue haste or in-appropriate loading is avoided.

Despite the urgency of the situation, careful, prompt and complete logging of all
operations and operational messages shall be ensured by all Users to facilitate
subsequent investigation into the incident and the efficiency of the restoration
process. Such investigation shall be conducted promptly after the incident.

9.6 APPEDIX

Essential loads and priority of restoration.

Grid Code (Draft) 51 November 2010


APPEDIX

COTIGECY PLAIG

ESSETIAL LOADS AD PRIORITY OF RESTORATIO

Priority Type of Load Name of Substation Remarks

Grid Code (Draft) 52 November 2010


10. CROSS BOUDARY SAFETY

10.1 ITRODUCTIO

This Section sets down the requirements for maintaining safe working practices
associated with cross boundary operations. It lays down the procedure to be followed
when work is required to be carried out on electrical equipment that is connected to
another User’s system.

10.2 OBJECTIVE

The objective of this Section is to achieve agreement and consistency on the


principles of safety as prescribed in the Electricity Rules, 1937 and widely practiced
international rules by concern of the Licensee when working across a control
boundary between the Licensee and another User.

10.3 COTROL PERSOS

The Licensee and all Users shall nominate suitably authorised persons to be
responsible for the coordination of safety across that company boundary. These
persons shall be referred to as Control Persons.

10.4 PROCEDURE

The Licensee shall issue a list of Control Persons (names, designations and
telephone numbers) to all Users who have a direct control boundary with the
Licensee. This list shall be updated promptly whenever there is change of name,
designation or telephone number.

All Users with a direct control boundary with the Licensee shall issue a similar list
of their Control Persons to the Licensee, which shall be updated promptly whenever
there is a change to the Control Persons list.

Whenever work across a control boundary is to be carried out, the Control Person,
of the User (which may be the Licensee), wishing to carry out work shall directly

Grid Code (Draft) 53 November 2010


contact the other relevant Control Person. Code words will be agreed at the time of
work to ensure correct identification of both parties.

Contact between the Control Persons shall normally be by direct telephone. Should
the work extend over more than one shift the Control Person shall ensure that the
relief Control Person is fully briefed on the nature of the work and the code words in
operation.

The Control Persons shall co-operate to establish and maintain the precautions
necessary for the required work to be carried out in a safe manner. Both the
established isolation and the established earth shall be locked in position, where such
facilities exist, and shall be clearly identified.

Work shall not commence until the Control Person, of the User (which may be the
Licensee), wishing to carry out the work, is satisfied that all the safety precautions
have been established. This Control Person shall issue agreed safety documentation
to the working party to allow work to commence.

When work is completed and safety precautions are no longer required, the Control
Person who has been responsible for the work being carried out shall make direct
contact with the other Control Person to request removal of those safety precautions.

The equipment shall only be considered as suitable for return to service when all
safety precautions are confirmed as removed, by direct communication using code
word contact between the two Control Persons, and return of agreed safety
documentation from the working party has taken place.

The Licensee shall develop an agreed written procedure for cross boundary safety and
continually update it.

Any dispute concerning Cross Boundary Safety shall be resolved at an appropriate


higher level of authority.

Grid Code (Draft) 54 November 2010


10.5 SPECIAL COSIDERATIOS

For cross boundary circuits all Users shall comply with the agreed safety rules which
must be in accordance with the Electricity Rules, 1937. and widely practiced
international rules.

All equipment on cross boundary circuits which may be used for the purpose of
safety coordination and establishment of isolation and earthing, shall be permanently
and clearly marked with an identification number or name, that number or name
being unique in that substation. This equipment shall be regularly inspected and
maintained in accordance with manufacturer's specification.

Each Control Person shall maintain a legibly written safety log, in chronological
order, of all operations and messages relating to safety coordination sent and received
by themselves. All safety logs shall be retained for a period of not less than 10 years.

Grid Code (Draft) 55 November 2010


11. OPERATIOAL EVET/ACCIDET REPORTIG

11.1 ITRODUCTIO

This Section describes the requirements for reporting, in writing, incidents that were
initially reported orally by/to other Users.

11.2 OBJECTIVE

The objective of this Section is to define the incidents to be reported, the reporting
route to be followed and the information to be supplied to ensure a consistent
approach to the reporting of incidents and accidents on the Transmission System.

11.3 REPORTABLE ICIDETS

Typical examples of reportable incidents that could affect the Transmission System
are the following:

i. Exceptionally high/low system voltage or frequency.


ii. Serious equipment problem, e.g. major circuit, transformer or bus-bar.
iii. Loss of major Generating Unit.
iv. System split, Transmission System breakaway or Black Start.
v. Major fire incidents.
vi. Major failure of protection.
vii. Equipment and transmission line overload.
viii. Minor equipment alarms.

The last two reportable incidents are typical examples of those that are of lesser
consequence, but which still affect the Transmission System and can be reasonably
classed as minor. They will require corrective action but may not warrant
management reporting until a later, more reasonable time.

Grid Code (Draft) 56 November 2010


11.4 REPORTIG PROCEDURE

11.4.1
i. All reportable incidents occurring in lines and equipment of 11 kV and
above at grid substations shall promptly be reported orally by the User
whose equipment has experienced the incident (The Reporting User) to any
other significantly affected Users and to the LDC who shall immediately
inform the Licensee.
ii. Within 1 (one) hour of being informed by the Reporting User, the LDC or
the Licensee may ask for a written report on any incident.
iii. If the reporting incident cannot be classed as minor then the Reporting User
shall submit an initial written report within two hours of asking for a written
report by LDC. This has to be further followed up by the submission of a
comprehensive report within 48 hours of the submission of the initial
written report.
iv. In other cases the Reporting User shall submit a report within 5 (five)
working days to LDC.
v. The NLDC shall immediately communicate all oral or written reportable
incidents to the Licensee.

11.4.2 LDC or the Licensee may call for a report from any User on any reportable
incident affecting other Users and the Licensee in case the same is not reported by
such User whose equipment might have been source of the reportable incident.

The above shall not relieve any User from the obligation to report events in
accordance with the Electricity Rules, 1937.

The format of such a report will be as agreed at the Grid Code Review Panel, but
will typically contain the following information:

i. Location of incident.
ii. Date and time of incident.
iii. Plant or equipment involved.
iv. Supplies interrupted and duration if applicable.
v. Amount of generation lost if applicable.
vi. Brief description of incident.
vii. Estimate of time to return to service.
Grid Code (Draft) 57 November 2010
viii. Name of originator.

11.5 REPORTIG FORM

The standard reporting form other than for accidents, shall be as agreed from time to
time by the Grid Code Review Panel. When such a form has been agreed in Grid
Code Review Panel meeting it will be included as an Appendix in this Section of
the Grid Code.

11.6 MAJOR FAILURE

Following a major failure, the Licensee and other Users shall co-operate to inquire
and establish the cause of such failure and produce appropriate recommendations.
The Licensee shall report the major failure to the Commission immediately for
information and shall submit the enquiry report to the Commission within 2 (two)
months of the incident.

11.7 ACCIDET REPORTIG

Reporting of accidents shall be in accordance with the Electricity Rules, 1937. In


both fatal and non-fatal accidents, the report shall be sent to the Electrical Inspector
and to the Commission in the prescribed form.

Grid Code (Draft) 58 November 2010


APPEDIX

ICIDET REPORTIG

FIRST REPORT ______________ Date : .....................


Time : ....................

1. Date and time of incident :

2. Location of incident :

3. Type of incident :

4. System parameters before the incident :


(Voltage, Frequency, Flows, Generation, etc.)

5. System parameters after the incident :

6. Network configuration before the incident :

7. Relay indications received and performance


of protection :

8. Damage to equipment :

9. Supplies interrupted and duration, :


if applicable

10. Amount of Generation lost, if applicable :

11. Estimate of time to return service :

12. Cause of incident :

13. Any other relevant information and :


remedial action taken

14. Recommendations for future improvement/


repeat incident :

15. Name of the Organisation : ]

Grid Code (Draft) 59 November 2010


12. PROTECTIO

12.1 ITRODUCTIO

In order to safeguard a User’s system from faults that may occur on another User’s
system, it is essential that certain minimum standards of protection be adopted. This
Section describes these minimum standards.

12.2 OBJECTIVE

The objective of this Section is to define the minimum protection requirements for
any equipment connected to the Transmission System and thereby minimise
disruption due to faults.

12.3 GEERAL PRICIPLES

No item of electrical equipment shall be allowed to remain connected to the


Transmission System unless it is covered by appropriate protection aimed at
reliability, selectivity, speed and sensitivity. Guidelines mentioned in protection
manuals may be kept in view.

All Users shall co-operate with the Licensee to ensure correct and appropriate
settings of protection to achieve effective, discriminatory removal of faulty
equipment within the time for target clearance specified in this Section.

Protection settings shall not be altered, or protection bypassed and/or disconnected


without consultation and agreement of all affected Users. In the case where
protection is bypassed and/or disconnected, by agreement, then the cause must be
rectified and the protection restored to normal condition as quickly as possible. If
agreement has not been reached the electrical equipment will be removed from
service forthwith.

Generator personnel shall not work upon or alter busbar Protection, mesh corner
Protection, circuit breaker fail Protection, AC or DC Wiring (other than power
supplies or DC tripping associated with the Generating Unit itself) in the absence of
a representative of the Licensee. Protection and relay settings shall be coordinated,

Grid Code (Draft) 60 November 2010


both on connection and subsequently, across Connection Point to ensure effective
disconnection of faulty Apparatus.

12.4 PROTECTIO coordination

The Licensee shall be responsible for arranging periodical meetings between all
Users to discuss coordination of protection. The Licensee shall investigate any mal-
function of protection or other unsatisfactory protection issues. Users shall take
prompt action to correct any protection mal-function or issue as discussed and agreed
to in these periodical meetings.

The Licensee shall be responsible for carrying out any required system studies to
determine the necessary protection discrimination settings.

12.5 FAULT CLEARACE TIMES

From a stability consideration the maximum fault clearance times for faults on any
User’s system directly connected to the Transmission System, or any faults on the
Transmission System itself, are as follows:

Target Clearance Times:

i. 400 kV : 100 ms
ii. 230 kV : 160 ms
iii. 132 kV : 160 ms

Slower fault clearance times for faults on a Users system may be agreed to but only
if, in the Licensee’s opinion, system conditions allow this.

12.6 GEERATOR REQUIREMETS

All Generating Units and all associated electrical equipment of the Generator
connected to the Transmission System shall be protected by adequate and
coordinated protection so that the Transmission System does not suffer due to any
disturbance originating from the Generating Unit.

Grid Code (Draft) 61 November 2010


In the event of failure of the protection systems provided to meet the fault
requirements detailed above, back up protection shall be provided by the Generator
with a fault clearance time not slower than 300ms for faults on the Generating
Unit’s HV connections.

The protection shall also cover EHV lines and transformers to the standards as for the
Transmission System and circuit breaker fail, pole slipping, loss of excitation, power
system stabilizer and negative phase sequence tripping.

12.7 TRASMISSIO LIE REQUIREMETS

Every EHV line taking off from a Power Station or a substation shall have main
protection and back up protection as mentioned below. The Licensee shall notify
Users of any changes in its policy on protection from time to time.

12.7.1 400 kV Line and 230 kV Line

Two distance protections plus directional earth fault protection (in directional
comparison scheme) shall be provided as the main protection. One distance relay plus
one (stand alone) directional earth fault relay (in directional comparison scheme) plus
two over-current and one earth fault relays shall provide the backup protection. Three
pole and/or single pole single shot auto-reclosing equipment shall be fitted, as
appropriate, as considered by the Licensee. All auto-reclosing equipment will be
made inoperative for three phase trip-out.

12.7.2 132 kV Line

One distance protection plus directional earth fault protection (in directional
comparison scheme) shall be provided as the main protection. One distance relay plus
one (stand alone) directional earth fault relay (in directional comparison scheme) plus
two over-current and one earth fault relays shall provide the backup protection. The
back up shall be directional three poles over current and earth fault protection. Three
pole and/or single pole single shot auto-reclosing equipment shall be fitted, as
appropriate, as considered by the Licensee. All auto-reclosing equipment will be
made inoperative for three phase trip-out.

Grid Code (Draft) 62 November 2010


12.7.3 General

For short transmission lines alternative appropriate protection schemes may be


adopted and clearly identified.

Relay Panels for the protection of lines of the Licensee taking off from a Power
Station shall be owned and maintained by the Licensee. Generators shall provide
space, connection facility, access to the Licensee for such purpose.

The Generator shall ensure that all common facilities needed for installing required
protective relaying are made available to the Licensee.

12.8 DISTRIBUTIO LIE REQUIREMETS

All 132kV lines, not owned by the Licensee, at Connection points shall have the
same protection requirements as for the Transmission System, detailed above

All 33 kV and 11 kV lines at Connection points shall be provided with a minimum


of over-current and earth fault protection with or without directional features as given
below.

12.8.1 on-Parallel Radial Feeders

Non-directional time lag over current and earth fault relay with suitable settings to
obtain discrimination between adjacent relay stations.

12.8.2 Parallel Feeders/ Ring Feeders

Directional time lag over current and earth fault relays.

12.8.3 Long Feeders/Transformer Feeders

For long feeders or transformer feeders, the relays should incorporate a high set
instantaneous element.

Grid Code (Draft) 63 November 2010


12.9 TRASFORMER REQUIREMETS

12.9.1 Generating Station/ Transmission System

All windings of auto-transformers and power transformers of EHV class shall be


protected by differential relays and REF relays. In addition there shall be back up time
lag over current and earth fault protection. For parallel operation such back up
protection shall have directional feature. For protection against heavy short circuits,
the over current relays should incorporate a high set instantaneous element. In
addition to electrical protection, gas operated relays, winding temperature protection
and oil temperature protection shall be provided. Overvoltage and over-fluxing
protection should also be provided.

12.9.2 Distribution system

For smaller transformers of HV class on the Distribution System differential


protection shall be provided for 10 MVA and above along with back up time lag over
current and earth fault protection (with directional feature for parallel operations).
Transformers 1.6 MVA and above and less than 10 MVA shall be protected by time
lag over current, earth fault and instantaneous REF relays. In addition all
transformers 1.6 MVA and above shall be provided with gas-operated relays,
temperature protection and winding temperature protection and oil temperature
protection.

12.10 SUBSTATIO BUS BAR AD FIRE PROTECTIO

12.10.1 All Users shall provide adequate main and back up bus zone protection for
substation bus bars in all 400 kV, 230 kV and 132 kV class substations.

12.10.2 Adequate precautions shall be taken and protection shall be provided against
fire hazards to all Apparatus of the Users conforming to relevant Bangladesh
Standard Specification and/or provisions in the Electricity Rules, 1937 and
amendments thereof and other standard engineering practices.

Grid Code (Draft) 64 November 2010


12.11 DATA REQUIREMETS

Users shall provide the Licensee with data for this Section as specified in the Data
Registration Section.

Grid Code (Draft) 65 November 2010


13. METERIG, COMMUICATIO AD
DATA ACQUISITIO

13.1 ITRODUCTIO

This Section specifies the minimum operational and commercial metering,


communication and data acquisition requirements to be provided by each User at the
inter-connection points and also at the cross boundary circuits.

13.2 OBJECTIVE

The objective of this Section is to define the minimum acceptable metering and
communication and data acquisition requirements to enable the Licensee to manage
the Transmission System in a safe and economic manner consistent with Licence
requirements.

13.3 GEERATIO OPERATIOAL METERIG

13.3.1 This sub-Section specifies the facilities that shall be provided for practices that
shall be employed for monitoring output and response of Power Stations and
Generating Units

13.3.2 The Generator shall install operational metering to the Licensee’s and
Buyer’s specification so as to provide operational information for both real time and
recording purposes in relation to each Generating Unit at each Power Station in
respect of:

i. Bus Voltage
ii. Frequency
iii. MW
iv. MWhr
v. MVAR
vi. any other additional data as agreed between the Licensee, Buyer and
Generator.

Grid Code (Draft) 66 November 2010


13.3.3 All current transformers and voltage transformers used in conjunction with
operational metering shall conform to relevant Bangladesh Standard Specifications or
the relevant IEC, of accuracy class 0.5 and of suitable rating to cater to the meters
and the lead wire burdens. All new or replacement current and voltage transformers
shall be of accuracy class 0.2.

13.3.4 Metering shall be calibrated, so as to achieve overall accuracy of operational


metering in the limits as agreed between the Licensee and Generator. All new
metering systems shall provide an overall measured accuracy of +/- 0.5%. Records of
calibration shall be maintained for reference and shall be made available to the
Licensee upon request.

13.3.5 Generators shall furnish recorded data of all electrical measurements and
events recorded by the operational metering to the Licensee daily or as agreed
between the Licensee and the Generator.

13.4 TRASMISSIO SYSTEM OPERATIOAL METERIG

13.4.1 This sub-Section specifies the facilities that shall be provided for practices that
shall be employed for monitoring electrical supply and load characteristic at each
substation.

13.4.2 The Licensee shall install operational metering so as to provide operational


information for both real time and recording purposes in relation to each feeder,
transformer and compensation device at each substation in respect of:

i. Bus Voltage
ii. Frequency
iii. MW
iv. MWhr
v. MVAR
vi. Power Factor
vii. Current
vii. any other additional data as agreed between the Licensee and Generator.

Grid Code (Draft) 67 November 2010


13.4.3 All current transformers and voltage transformers used in conjunction with
operational metering shall conform to relevant Bangladesh Standard Specifications or
the relevant IEC, of accuracy class 0.5 and of suitable rating to cater to the meters
and the lead wire burdens. All new or replacement current and voltage transformers
shall be of accuracy class 0.2.

13.4.4 The Licensee shall furnish such data of all electrical measurements and events
recorded by the operational metering to the Generator as required on request or as
agreed between the Licensee and the Generator.

13.5 SUPERVISORY COTROL AD DATA ACQUISITIO (SCADA)

13.5.1 The LDC shall install and make operative an operational metering data
collection system, including the tariff Metering System, under SCADA for storage,
display and processing of metering data. All Users shall make available outputs of
their respective operational meters to the SCADA interface equipment.

13.5.2 The data collection, storage and display centre of shall be at the LDC.

13.5.3 The responsibilities for SCADA are detailed in Metering, Communication and
Data Acquisition Section.

13.6 GEERATIO/ COMMERCIAL (TARIFF) METERIG

13.6.1 This sub-Section specifies provision of commercial (Tariff) metering at


Connection points between the Transmission System and Generating Stations, and
the Transmission System and Distribution Systems. It also specifies metering
facilities that shall be provided for the measurement of electricity produced by
Generating Units and for measurement of electricity consumed at Power Stations.

13.6.2 Metering shall be installed to measure:

i. Active energy for export.


ii. Active energy for import.
iii. Reactive energy for import.
iv. Reactive energy for export.

Grid Code (Draft) 68 November 2010


13.6.3 At each metering point associated with determination of energy exported or
imported the Licensee shall install, own and maintain a metering system defined as
the Metering System.

13.6.4 The Generator or Distribution Utility shall install, own and maintain a
metering system defined as the Back-Up Metering System.

13.6.5 Minimum standard of accuracy of meters shall be of class 0.2 or as agreed


between the Generator, Distribution Utility, Buyer and the Licensee and shall
conform to the relevant Bangladesh Standard Specification or relevant IEC.

13.6.6 All current transformers and voltage transformers used in conjunction with
commercial (Tariff) metering shall conform to the relevant Bangladesh Standard
Specification or relevant IEC. These shall be of accuracy class 0.2 and of suitable
rating to cater to the meter burden and lead wire burden.

13.6.7 The Metering System and the Back-Up Metering System shall be designed and
installed based on Prudent Utility Practices providing a measured accuracy of +/-
0.5% or as agreed between the Generator, Distribution Utility, Buyer and the
Licensee

13.6.8 Data collection shall be used to integrate impulses from meters over each
integration period as per agreement, store values and transmit values to the data
collection system of the LDC. Data shall be collected from the Metering System.

13.6.9 Voltage supply to the metering shall be assured with necessary voltage
selection schemes. Voltage failure relays shall be provided which will initiate alarm
on loss of one or more phases of the voltage supply to any meter.

13.6.10 The Buyer shall ensure that the testing and calibration of the Metering
System is carried out at intervals of not less than one hundred and eighty days (180).
The Buyer shall give no less than fifteen days notice to the User according to
guidelines provided in relevant Bangladesh Standard Specification or relevant IEC as
applicable. Records of meter calibration test shall be maintained for future reference.
The User may, at any time, request to inspect the test results and/or request a test if
the User suspects the meter is incorrect

Grid Code (Draft) 69 November 2010


13.6.11 The Buyer and the User shall jointly seal the Metering System and the Back-
Up Metering System. The Buyer shall break the seals only after giving at least
twenty-four (24) hours notice except under emergency conditions. The User may
attend the breaking of the seals if considered necessary by the User.

13.6.12 Any dispute arising between the parties that cannot be resolved between the
parties shall be referred to a joint sub-committee convened by the Grid Code Review
Panel Chairman and consisting of representatives of the parties in dispute and 2
independent Grid Code Review Panel Members representatives. If the joint sub-
committee cannot resolve the dispute the Buyer shall refer it, with all supporting
documentation, to the Commission for a decision.

13.7 COMMUICATIO

Independent dedicated communication links for voice communication, for written


communication and for data acquisition shall be installed by the Buyer between all
Power Station, Transmission System substations and LDC. In addition, similar
links between adjacent Transmission System substations shall be established.
Communication shall be available by dialling discrete numbers. The Licensee shall
establish direct links between Power Station/important substation and the LDC.

The Licensee, LDC and Generators are authorised to tape record all telephoned
voice communications relating to Declared Availability Capacity control and
schedule and despatch and shall supply at the request of the other party a copy or
transcript of any such recording.

The Licensee, LDC and Users are authorised to tape record all cross boundary
safety communications and shall supply at the request of the other party a copy or
transcript of any such recording.

13.8 DATA ACQUISITIO

13.8.1 For effective control of the Transmission System, the LDC needs real time
data as follows:

i. MW generated in each Power Station.

Grid Code (Draft) 70 November 2010


ii. MVAR generated or absorbed in each Power Station.
iv. Voltage in all system buses.
vi. Frequency in Transmission System.
vii. MW & MVAR flow in each transmission line.

13.8.2 The Licensee shall provide and install all the facilities and equipment for
telemetering, communication, control and monitoring, including voice channels,
between the Connection point and the LDC

13.8.3 The Generators shall provide and install within the complex such equipment,
including power line Carrier equipment, as needed for the complex to interconnect
with the Transmission System equipment for telemetering, communication, control
and monitoring, including voice channels, compatable to the Licensee’s system or as
agreed by the Licensee.

13.8.4 For the SCADA system the Buyer shall be resposible for providing and
installing the equipment including any Remote Terminal Units (RTUs) within the
Generator or Distribution Utility sites. The Generator and Distribution Utility
shall provide and install within the complex interface terminals on the Metering
System and such other equipment needed to interface with the SCADA system.

13.10 AGREED PROCEDURE FOR COMMUICATIO AD


DATA TRASMISSIO

Mutually agreed procedures shall be drawn up between the Licensee, LDC and
other Users outlining inter responsibility, accountability and recording of day to day
communication and data transmission on operational matters.

13.10.1 Data Requirement

The Licensee, LDC and Users shall furnish metering data to each other, as
applicable and as detailed in Data Registration Section.

Grid Code (Draft) 71 November 2010


14. TESTIG

14.1 ITRODUCTIO

This Section specifies the responsibilities and procedures for arranging and carrying
out Tests which have (or may have) an effect on the Transmission System or the
Generator’s or Distributor’s systems.

14.2 OBJECTIVE

The objective of the Section are to establish whether Generating Units can operate
within their Generation Schedule and Despatch parameters as registered under the
Data Registration Section and that the Generator and Distributor comply with the
Connection Section. It shall also establish whether each Generating Unit’s declared
availability capacity is as declared and that the requirements of the provisions of
frequency, voltage management and reserve capability are met in accordance with the
provisions of the Grid Code.

14.3 RESPOSIBILITIES

The LDC is responsible for ensuring that the following procedures are carried out.
All Users are required to fully co-operate to ensure that the costs of testing are kept to
a minimum.

14.4 PROCEDURE

The LDC shall monitor the performance of Generating Units against the registered
parameters and the compliance by the Generator or Distributor with the
Connection Section of the Grid Code.

The LDC shall inform a Generator, and confirm in writing, if monitoring


demonstrates an apparent persistent or material mismatch in meeting the Generating
Unit registered parameters or breach of the Connection Conditions.

Grid Code (Draft) 72 November 2010


For all parameters, except availability, the relevant Generator shall, as soon as
possible, provide the LDC with an explanation of the reasons for the failure to meet
the requirements and the details of the action it proposes to take to meet the
requirements and comply with the Grid Code.

The LDC and the Generator will then discuss the action and endeavour to reach
agreement on the actions required.

In the event that agreement cannot be made within 10 days of the notification the
LDC shall be entitled to propose that a test be carried out.

For the allocation of the costs of testing the general principle shall be that the Test
Proposer (LDC) shall bear the costs if the results show that the test was not justified
and the Generator or Distribution Utility shall bear the costs if the results show the
test was justified.

14.5 TEST PROCEDURES

14.5.1 Declared Availability Capacity Testing

If the LDC has reasonable suspicion that the declared availability capacity of a
Generating Unit is not as declared he may test that availability by issuing a despatch
instruction to the Generating Unit to attain the declared availability capacity. This
may be instructed at any time even though it had not been previously scheduled or
despatched on merit order or system grounds.

The issue of a Despatch instruction shall initiate the test.

The Generating Unit will pass the test if it can attain and maintain its load to the
declared availability capacity for 2 hours

14.5.2 Schedule and Despatch Instruction Testing

If the LDC has reasonable suspicion that the Scheduling and Despatch parameters
of a Generating Unit are not as registered and have not had notification of a
temporary change to the parameters he may instruct the Generating Unit to

Grid Code (Draft) 73 November 2010


demonstrate the capability of meeting its parameters. The Generator shall be given at
least 48 hours notice of the test and the duration shall be consistent with the time
taken to measure the result.

The issue of a Despatch instruction shall initiate the test.

The performance of the Generating Unit shall be recorded on a chart recorder


(measured on the HV side of the generator transformer) in the presence of a
representative of the LDC and the Generator.

The Generating Unit will pass the test if the parameters under test are within +/-
2.5% of the declared value tested.

14.5.3 Reactive Power Testing

If the LDC has reasonable suspicion that the reactive power capability of a
Generating Unit is not as registered and have not had notification of a temporary
change he may instruct the Generating Unit to demonstrate the capability of meeting
its registered capability. The Generator shall be given at least 48 hours notice of the
test and the duration will be for a period up to 60 minutes. The Transmission System
voltage at the entry point shall be maintained by the Generator at the voltage
specified by test proposer by adjustment of reactive power on the remaining units (if
available) or by the Licensee by appropriate tap changing at the substation, as
necessary.

The issue of a Despatch instruction shall initiate the test.

The performance of the Generating Unit shall be recorded on a chart recorder


(measured on the Generating Unit stator terminals) in the presence of a
representative of the LDC and the Generator.

The Generating Unit will pass the test if it is within +/- 5% of the registered
capability. Due account shall be taken of any conditions on the system that may affect
the test.

Grid Code (Draft) 74 November 2010


14.5.4 Automatic Frequency Sensitive Testing

If the LDC has reasonable suspicion that the capability of the automatic frequency
sensitive performance of a Generating Unit is not as registered and have not had
notification of a temporary change he may instruct the Generating Unit to
demonstrate the capability of meeting its registered capability. The Generator shall
be given at least 48 hours notice of the test.

The performance of the Generating Unit shall be recorded on a chart recorder as well
as system frequency (measured on the HV side of the generator transformer) in the
presence of a representative of the LDC and the Generator. Where measurements
of the Governor pilot oil/valve position are to be made such measurements should
indicate that the Governor parameters are within limits.

The Generating Unit will pass the test if it is within +/- 5% of the level of response
registered.

14.5.5 Fast Start Capability Testing

If the LDC has reasonable suspicion that the capability of the fast start performance
of a Generating Unit is not as registered and have not had notification of a temporary
change he may instruct the Generating Unit to demonstrate the capability of meeting
its registered capability. The Generator shall be given at least 48 hours notice of the
test.

The issue of a Despatch instruction shall initiate the test.

The performance of the Generating Unit shall be recorded on a chart recorder in the
Generator’s Control Room as well as system frequency in the presence of a
representative of the LDC and the Generator. Where measurements of the
Governor pilot oil/valve position are to be made such measurements should indicate
that the Governor parameters are within limits.

The Generating Unit will pass the test if when synchronizing and running up to full
declared availability it meets its fast start capability

Grid Code (Draft) 75 November 2010


14.5.6 Black Start Testing

The LDC may, at any time require a Generator with Black Start capability to carry
out a “Black Start Test” on a Generating Unit in order to demonstrate that the
Black Start Power Station has a Black Start capability.

Where the LDC requires the Generator to carry out the “Black Start Test” the
LDC shall not require the test to be carried out on more than one Generating Unit.
The LDC would not, in the absence of exceptional circumstances, expect any of the
Generators other Generating Units to be directly effected.

The LDC shall not require a Generator with a Black Start capability to carry out a
“Black Start Test” more than once every 2 calendar years in respect of any particular
Generating Unit.

When the LDC requires a “Black Start Test” it shall notify the relevant Generator
at least 7 days prior to the start of the test with details of the proposed test.

All “Black Start Tests” shall be carried out at a time specified by the Licensee in the
notice given and shall be undertaken in the presence of a representative of the LDC
and the Generator.

The Generating Unit will pass the test if it meets its Black Start capability.

14.6 FAILURE OF GEERATOR TO PASS TEST AD DISPUTES

If a Generating Unit fails to pass a test, the Generator shall provide the LDC
with a written report detailing the reasons for the failure, as far as they are known,
within 3 days of the test. If a dispute arises relating to the failure the LDC may,
with the agreement of the Generator, carry out a re-test on 48 hours notice.

If the Generating Unit fails to pass the test or re-test and a dispute occurs, then
either party may refer the dispute to the Commission. The decision of the
Commission shall be binding on both parties

Grid Code (Draft) 76 November 2010


If the LDC and the Generator agree that the Generating Unit has failed the test,
or re-test, the Generator shall submit in writing for approval the date and time by
which the Generator shall restore the faulty unit to a condition where it would pass
the test. If the LDC cannot agree to the time and date then the matter may be
referred to the Commission. The decision of the Commission shall be binding on
both parties

If the Generating Unit fails to pass the test or re-test the Generator may amend the
relevant registered parameters of that Generating Unit to the capability achieved
under test until the Generating Unit can achieve the previously registered values in
a further re-test.

Once the Generator has indicated to the LDC the time and date that the
Generating Unit can achieve the previously registered parameters, the LDC may
either accept them or require a further test on 48 hours notice to demonstrate that
they can be achieved. If a dispute occurs, then either party may refer the dispute to
the Commission. The decision of the Commission shall be binding on both parties

Grid Code (Draft) 77 November 2010


15. UMBERIG AD OMECLATURE

15.1 ITRODUCTIO

This Section sets out the requirement that:

a. Licensee’s HV apparatus on User’s sites and

b. User’s HV apparatus on Licensee’s sites

shall have numbering and nomenclature in accordance with the system used from
time to time by the Licensee.

The numbering and nomenclature of each item of HV apparatus shall be included in


the Operation Diagram prepared for each site

15.2 OBJECTIVE

The objective of this Section is to ensure, in so far as possible, the safe and effective
operation of the Power System and to reduce the risk of human error faults by
requiring that the numbering and nomenclature of User’s apparatus shall be in
accordance with the Licensee’s system at connection point sites.

15.3 SCOPE

The Section applies to the Licensee and all Users

15.4 PROCEDURE

Licensee’s HV Apparatus on User’s Sites

i) Licensee’s HV apparatus on a User’s sites shall have numbering and


nomenclature in accordance with the system used by the Licensee.

Grid Code (Draft) 78 November 2010


ii) When the Licensee is to install it’s HV apparatus on a User’s site, the Licensee
shall notify the relevant User of the numbering and nomenclature to be adopted
for that HV apparatus at least eight months before installation.

iii) The notification shall be made in writing to the relevant User and will consist of
a proposed Operation Diagram incorporating the proposed new HV apparatus to
be installed, its proposed numbering and the date of installation

iv) The relevant User shall respond in writing within one month of the notification,
confirming receipt and confirming either that any other HV apparatus of the
User on the site does not have that numbering and/or nomenclature which could
be confused with that proposed by the Licensee, or, to the extent that it does
and that the relevant numbering and/or nomenclature will be changed before
installation of the Licensee’s HV apparatus

v) The relevant User shall not install, or permit the installation of, any HV
apparatus on the site which has numbering and/or nomenclature that could be
confused with the Licensee’s HV apparatus which is either already on that site
or which the Licensee has notified that User will be installed on that site.

User’s HV Apparatus on Licensee’s Sites

i) User’s HV apparatus on Licensee’s sites shall have numbering and


nomenclature in accordance with the system used by the Licensee.

ii) When a User is to install it’s HV apparatus on the Licensee’s site, or wishes to
replace existing HV apparatus on the Licensee’s site and also wishes to adopt
new numbering and nomenclature for such HV apparatus, the User shall notify
the Licensee of the details of the HV apparatus and the proposed numbering
and nomenclature to be adopted for that HV apparatus at least eight months
before installation or change.

iii) The notification shall be made in writing to the Licensee and will consist of a
proposed Operation Diagram incorporating the proposed new HV apparatus to
be installed, its proposed numbering and the date of installation.

Grid Code (Draft) 79 November 2010


iv) The Licensee shall respond in writing within one month of the notification,
confirming receipt and confirming whether or not the Licensee accepts the
User’s proposed numbering and nomenclature and, if they are not acceptable,
shall give details of the numbering and/or nomenclature which will be adopted
for the User’s HV apparatus.

Changes

Where the Licensee, in its reasonable opinion has decided that it needs to change the
existing numbering or nomenclature of the Licensee’s HV apparatus on a User’s site
or the User’s HV apparatus on the Licensee’s site:

i) The provisions of the above paragraphs shall apply to such change of


numbering of Licensee’s HV apparatus with any necessary amendments to
those provisions to reflect that only a change is being made, and

ii) In the case of a change in the numbering or nomenclature of User’s HV


apparatus on the Licensee’s site, the Licensee shall notify the User of the
numbering or nomenclature the User shall adopt for that HV apparatus at least
eight months prior to the change being needed and the User shall respond in
writing to the Licensee within one month of the notification confirming receipt.

In either case the notification shall indicate the reason for the proposed change.

Users shall be provided upon request with details of the Licensee’s current
numbering and nomenclature system.

When either the Licensee or the User installs HV apparatus which is subject to this
section, the Licensee or the User, as the case may be installing such apparatus shall
be responsible for the provision and erection of clear and unambiguous labelling
showing the numbering and nomenclature. Where a User is required to change the
numbering and nomenclature he shall be responsible for the provision and erection of
clear and unambiguous labelling showing the numbering and nomenclature by the
required date.

Grid Code (Draft) 80 November 2010


Where the Licensee changes the numbering and nomenclature of its HV apparatus,
under this section, then the Licensee shall be responsible for the provision and
erection of clear and unambiguous labelling showing the numbering and
nomenclature by the required date.

The Licensee shall not change its system of numbering and nomenclature unless to
reflect new or newly adopted technology or reasons of safety.

The Licensee shall submit the Numbering and Nomenclature to the Commission
whenever adopted and whenever changed or revised.

Grid Code (Draft) 81 November 2010


16. DATA REGISTRATIO

16.1 ITRODUCTIO

This Section contains a list of all data required by the Licensee that is to be provided
by Users and data required by Users to be provided by the Licensee at times
specified in the Grid Code. Other Sections of the Grid Code contain the obligation
to submit the data and defines the times when data is to be supplied by Users.

16.2 OBJECTIVE

The objective of the Section is to list all the data required to be provided by Users to
the Licensee and vice versa, in accordance with the provisions of the Grid Code.

16.3 RESPOSIBILITIES

All Users are responsible for submitting up-to-date data to the Licensee in
accordance with the provisions of the Grid Code.

All Users shall provide the Licensee with the name, address and telephone number of
the person responsible for sending the data.

The Licensee shall inform all Users of the name, address and telephone number of
the person responsible for receiving data.

The Licensee shall provide up-to-date data to Users as provided in the relevant
schedule of the Grid Code.

Responsibility for the correctness of data rests with the concerned Users providing
the data.

16.4 DATA CATEGORIES AD STAGES I REGISTRATIO

Data as required to be exchanged have been listed in the Appendices of this Section
under various categories with cross-reference to the concerned Sections.

Grid Code (Draft) 82 November 2010


16.5 CHAGES TO USERS DATA

Whenever any User becomes aware of a change to any items of data that is registered
with the Licensee, the User must promptly notify the Licensee of the changes. The
Licensee on receipt of intimation of the changes shall promptly correct the database
accordingly. This shall also apply to any data complied by the Licensee regarding to
its own system.

16.6 DATA OT SUPPLIED

Users are obliged to supply data as referred to in the individual Section of the Grid
Code and listed out in the Data Registration Section Appendices. In case any data is
missing and not supplied by any User, the Licensee may, acting reasonably, if and
when necessary, estimate such data depending upon the urgency of the situation.
Similarly in case any data is missing and not supplied by the Licensee, the concerned
User may, acting reasonably, if and when necessary, estimate such data depending
upon urgency of the situation. Such estimates will in each case, be based upon
corresponding data for similar plant or Apparatus or upon such other information,
the User or the Licensee, as the case may be, deems appropriate.

16.7 SPECIAL COSIDERATIOS

The Licensee and any other User may at any time make reasonable request for extra
data as necessary.

Grid Code (Draft) 83 November 2010


APPEDICES

APPEDIX SUBJECT PAGE

A STANDARD PLANNING DATA 79

B DETAILED PLANNING DATA 87

C OPERATIONAL PLANNING DATA 100

D PROTECTION DATA 104

E METERING DATA 105

Grid Code (Draft) 84 November 2010


APPEDIX- A

DATA REGISTRATIO

STADARD PLAIG DATA

REFERECE TO:
SECTIO 4 SYSTEM PLAIG
SECTIO 5 COECTIO CODITIO

A.1 STADARD PLAIG DATA (GEERATIO)

A.1.1 THERMAL ( FOSSIL FUEL)

A.1.1.1 GEERAL

i. Site Give location map to scale showing roads,


railway lines, transmission lines, rivers
and reservoirs if any.
ii. Fossil Fuel Give information on means of coal
Liquid Natural Gas, Naptha, transport from coal mines in case of
Coal etc, pithead stations or means of coal carriage
if coal is to be brought from (distance).
3
[In case of other fuels, give details of
source of fuel and their transport.]
Iii. Water Sources Give information on availability of water
for operation of the Power Station.
iv. Environmental State whether forest, lands mining
clearance areas are affected.
v. Site map (To Scale) Showing area required for Power Station
coal linkage, coal yard, water pipe line,
ash disposal area, colony etc.
Vi. Approximate period of
construction.

Grid Code (Draft) 85 November 2010


A.1.1.2 COECTIO

i. Point of Connection Give single line diagram of the proposed


Connection with the system.
ii. Step up voltage for Connection
in kV.

A.1.1.3 STATIO CAPACITY

i. Total Power Station capacity Bangladesh whether development will be


(MW) carried out in phase and if so, furnish
details.
ii. No. of units & unit size MW

A.1.1.4 GEERATIG UIT DATA

i. Steam Generating Unit Bangladesh type, capacity, steam pressure,


steam temperature etc.
ii. Steam turbine Bangladesh type, and capacity.
iii. Generator a. Type
b. Rating ( MVA)
c. Terminal voltage (kV)
d. Rated Power Factor
e. Reactive Power Capability (MVAR) in
the range 0.95 of leading and 0.85
lagging
f. Short Circuit Ratio
g. Direct axis transient reactance (% on
MVA rating)
h. Direct axis sub-transient reactance ( %
on MVA rating)
i. Auxiliary Power Requirement (MW)

Grid Code (Draft) 86 November 2010


iv. Generator Transformer a. Type
b. Rated capacity (MVA)
c. Voltage Ratio ( HV/LV)
d. Tap change Range (+ % to - %)
Percentage Impedance (Positive Sequence
at Full load)

Grid Code (Draft) 87 November 2010


A.1.2 HYDRO ELECTRICAL

A.1.2.1 GEERAL

i. Site Give location map to scale showing roads,


railway lines and transmission lines.
ii. Site map ( To scale) Showing proposed dam, reservoir area,
water conductor system, fore-bay, power
house etc.
iii. Submerged Area Give information on area submerged,
villages submerged, submerged forest
land, agricultural land etc.
iv. Approximate period of
construction.
.
A.1.2.2 COECTIO

i. Point of Connection Give single line diagram proposed


Connection with the Transmission
System.
ii. Step up voltage for Connection KV

A.1.2.3 STATIO CAPACITY

i. Total Power Station capacity State whether development be carried out


(MW) in phases and if so furnish details.
ii. No of units & unit size MW

Grid Code (Draft) 88 November 2010


A.1.2.4 GEERATIG UIT DATA

i. Operating Head (in Mtr.) a. Maximum


b. Minimum
c. Average.
ii. Turbine. State Type and capacity
iii. Generator a. Type
b. Rating (MVA)
c. Terminal voltage (kV)
d. Rated Power Factor
e. Reactive Power Capability (MVAR) in
the range 0.95 of leading and 0.85 of
lagging
f. Short Circuit Ratio
g. Direct axis transient reactance (% on
rated MVA)
h. Direct axis sub-transient reactance (%
on rated MVA)
i. Auxiliary Power Requirement (MW)
iv. Generator Transformer a. Type
b. Rated Capacity (MVA)
c. Voltage Ratio HV/LV
d. Tap change Range ( +% to -%)
e. Percentage Impedance ( Positive
sequence at full load).

Grid Code (Draft) 89 November 2010


A.2 STADARD PLAIG DATA (TRASMISSIO)

ote : The compilation of the data is the internal matter of the Licensee, and as such
the Licensee shall make arrangements for getting the required data from different
Departments of the Licensee to update its Standard Planning Data in the format
given below:

i. Name of line (Indicating Power Stations and substations to be connected).


ii. Voltage of line (kV).
iii. No. of circuits.
iv. Route length (km).
v. Conductor sizes.
vi. Line parameters (PU values).
a. Resistance/km.
b. Inductance/km.
c. Susceptance/km (B/2).
vii. Approximate power flow expected MW & MVAR.
viii. Terrain of route - Give information regarding nature of terrain i.e. forest
land, fallow land, agricultural and river basin, hill slope etc.
ix. Route map(to Scale) - Furnish topographical map showing the proposed
route showing existing power lines and telecommunication lines.
x. Purpose of Connection - Reference to scheme.
xi. Approximate period of Construction.

Grid Code (Draft) 90 November 2010


A.3 STADARD PLAIG DATA DISTRIBUTIO

A.3.1 GEERAL

i. Area map (to Scale)- Marking the area in the map for which Distribution
Licence is applied for.
ii. Consumer Data- Furnish categories of consumers, their numbers and
connected loads.
iii. Reference to Electrical Divisions presently in charge of the Distribution.

A.3.2 COECTIO

i. Points of Connection- Furnish single line diagram showing points of


Connection.
ii. Voltage of supply at points of Connection
iii. Names of grid substation feeding the points of Connection

A.3.3 LIES AD SUBSTATIOS

i. Line data- Furnish lengths of line and voltages within the Area.
ii. Substation data- Furnish details of 33/11 kV substations, 11/0.4 kV
substations, capacitor installations.

A.3.4 LOADS

i. Loads drawn at points of Connection.


ii. Details of loads fed at EHV, if any. Give name of consumer, voltage of
supply, contract demand and name of Grid Substation from which line is
drawn, length of EHV line from Grid Substation to consumer's premises.

Grid Code (Draft) 91 November 2010


A.3.5 DEMAD DATA (FOR ALL LOADS 5 MW AD ABOVE)

i. Type of load - State whether furnace loads, rolling mills, traction loads,
other industrial loads, pumping loads etc.
ii. Rated voltage and phase.
iii. Electrical loading of equipment- State number and size of motors, types
of drive and control arrangements.
iv. Sensitivity of load to voltage and frequency of supply.
v. Maximum Harmonic content of load.
vi. Average and maximum Phase unbalance of load.
vii. Nearest substation from which load is to be fed.
viii. Location map (to scale)- Showing location of load with reference to lines
and substations in the vicinity.

A.3.6 LOAD FORECAST DATA

i. Peak load and energy forecast for each category of loads for each of the
succeeding 20 years.
ii. Details of methodology and assumptions on which forecasts are based.
iii. If supply is received from more than one Substation, the substation wise
break up of peak load and energy projections for each category of loads for
each of the succeeding 20 years along with estimated daily load curve.
iv. Details of loads 5 MW and above.
a. Name of prospective consumer.
b. Location and nature of load/complex.
c. Substation from which to be fed.
d. Voltage of supply.
e. Phasing of load.

Grid Code (Draft) 92 November 2010


APPEDIX- B

DETAILED PLAIG DATA

REFERECE TO:
SECTIO 4 SYSTEM PLAIG
SECTIO 5 COECTIO CODITIOS

B.1 DETAILED PLAIG DATA (GEERATIO)

PART 1. FOR ROUTIE SUBMISSIO

B.1.1 THERMAL POWER STATIOS (FOSSIL FUEL)

B.1.1.1 GEERAL

i. Name of Power Station.


ii. Number and capacity of Generating Units (MVA).
iii. Ratings of all major equipments (boilers and major accessories, turbines,
alternators, Generating Unit transformers etc.).
iv. Single line diagram of Power Station and switchyard.
v. Relaying and metering diagram.
vi. Neutral Grounding of Generating Units.
vii. Excitation control (What type is used? e.g. Thyristor, Fast Brushless?).
viii. Earthing arrangements with earth resistance values.

B.1.1.2 PROTECTIO AD METERIG

i. Full description including settings for all relays and protection systems
installed on the Generating Unit, Generating Unit transformer, auxiliary
transformer and electrical motor of major equipment listed, but not limited
to above.
ii. Full description including settings for all relays installed on all outgoing
feeders from Power Station switchyard, tie circuit breakers, incoming
circuit breakers.

Grid Code (Draft) 93 November 2010


iii. Full description of inter-tripping of circuit breakers at the point or points of
Connection with the Transmission System.
iv. Most probable fault clearance time for electrical faults on the User's
system.
v. Full description of operational and commercial metering schemes.

B.1.1.3 SWITCHYARD

In relation to interconnecting transformers:


i. Rated MVA.
ii. Voltage Ratio.
iii. Vector Group.
iv. Positive sequence reactance for maximum, minimum, normal Tap. (% on
MVA).
v. Positive sequence resistance for maximum, minimum, normal Tap. (% on
MVA).
vi. Zero sequence reactance. (% on MVA).
vii. Tap changer Range (+% to -%) and steps.
viii. Type of Tap changer. (OFF/ON).

In relation to switchgear including circuit breakers, isolators on all circuits connected to the
points of Connection:
i. Rated voltage (kV).
ii. Type of circuit breaker (MOCB/ABCB/SF6).
iii. Rated short circuit breaking current (kA) 3 phase.
iv. Rated short circuit breaking current (kA) 1 phase.
v. Rated short circuit making current (kA) 3 phase.
vi. Rated short circuit making current (kA) 1-phase.
vii. Provisions of auto reclosing with details.

Lightning Arresters-
Technical data.

Communication-
Details of equipment installed at points of Connections.

Grid Code (Draft) 94 November 2010


Basic Insulation Level (kV)-
i. Bus bar.
ii. Switchgear.
iii. Transformer bushings.
iv. Transformer windings.

B.1.1.4 GEERATIG UITS

(a) Parameters of Generating Units:


i. Rated terminal voltage (kV).
ii. Rated MVA.
iii. Rated MW.
iv. Inertia constant (MW Sec./MVA) H.
v. Short circuit ratio.
vi. Direct axis synchronous reactance (% on MVA) Xd
vii. Direct axis transient reactance(% on MVA) X'd
viii. Direct axis sub-transient reactance(% on MVA) X"d
ix. Quadrature axis synchronous reactance (% on MVA) Xq
x. Quadrature axis transient reactance (% on MVA) X'q
xi. Quadrature axis sub-transient reactance (% on MVA) X"q
xii. Direct axis transient open circuit time constant (Sec) T'do
xiii. Direct axis sub-transient open circuit time constant (Sec) T"do
xiv. Quadrature axis transient open circuit time constant (Sec) T"qo
xv. Quadrature axis sub-transient open circuit time constant (Sec) T'qo
xvi. Stator resistance (Ohm) Ra
xvii. Stator leakage reactance (Ohm) Xl
xviii. Stator time constant (Sec).
xix. Rated field current (A).
xx. Open circuit saturation characteristic for various terminal
giving the compounding current to achieve the same.

(b) Parameters of Excitation Control System:


i. Type of excitation.
ii. Maximum field voltage.
iii. Minimum field voltage.

Grid Code (Draft) 95 November 2010


iv. Rated field voltage.
v. Details of excitation loop in block diagrams showing transfer functions
of individual elements using IEEE symbols.
vi. Dynamic characteristics of over-excitation limiter.
vii. Dynamic characteristics of under-excitation limiter.

(c) Parameters of Governor:


i. Governor average gain (MW/Hz).
ii. Speeder motor setting range.
iii. Time constant of steam or fuel governor valve.
iv. Governor valve opening limits.
v. Governor valve rate limits.
vi. Time constant of turbine.
vii. Governor block diagram showing transfer functions of individual
elements using IEEE symbols.

(d) Operational Parameters:


i. Minimum notice required to synchronise a Generating Unit from
de-synchronisation.
ii. Minimum time between synchronising different Generating Units in a
Power Station.
iii. The minimum block load requirements on synchronising.
iv. Time required for synchronising a Generating Unit for the following
conditions:
a. Hot
b. Warm
c. Cold
v. Maximum Generating Unit loading rates for the following conditions:
a. Hot
b. Warm
c. Cold
vi. Minimum load without oil support (MW)

Grid Code (Draft) 96 November 2010


B.1.2 HYDRO-ELECTRIC STATIOS

B.1.2.1 GEERAL

i. Name of Power Station.


ii. No. and capacity of units. (MVA)
iii. Ratings of all major equipment.
a. Turbines (HP).
b. Generators (MVA).
c. Generator Transformers (MVA).
d. Auxiliary Transformers (MVA).
iv. Single line diagram of Power Station and switchyard.
v. Relaying and metering diagram.
vi. Neutral grounding of generator.
vii. Excitation control.
viii. Earthing arrangements with earth resistance values.
ix. Reservoir Data.
a. Salient features
b. Type of Reservoir
(i) Multipurpose
(ii) For Power
c. Operating Table with
(i) Area capacity curves
and (ii) Unit capability at different net heads

B.1.2.2 PROTECTIO

i. Full description including settings for all relays and protection systems
installed on the Generating Unit, generator transformer, auxiliary
transformer and electrical motor of major equipment included, but not
limited to those listed above.
ii. Full description including settings for all relays installed on all outgoing
feeders from Power Station switchyard, tie breakers, incoming breakers.
iii. Full description of inter-tripping of breakers at the point or points of
Connection with the Transmission System.

Grid Code (Draft) 97 November 2010


iv. Most probable fault clearance time for electrical faults on the User's
System.

B.1.2.3 SWITCHYARD

(a) Interconnecting Transformers:


i. Rated MVA.
ii. Voltage ratio.
iii. Vector group.
iv. Positive sequence reactance for maximum, minimum and normal tap. (%
on MVA).
v. Positive sequence resistance for maximum, minimum and normal Tap (%
on MVA).
vi. Zero sequence reactance (% on MVA).
vii. Tap changer range (+% to -%) and steps.
viii. Type of tap changer. (OFF/ON).

(b) Switchgear (including circuit breakers, isolators on all circuits connected to the
points of Connection.)
i. Rated voltage (kV).
ii. Type of Breaker (MOCB/ABCB/SF6).
iii. Rated short circuit breaking current (kA) 3 phase.
iv. Rated short circuit breaking current (kA) 1 phase.
v. Rated short circuit making current (kA) 3 phase.
vi. Rated short circuit making current (kA) 1 phase.
vii. Provisions of auto reclosing with details.

(c) Lightning Arresters:


Technical data.

(d) Communications:
Details of communications equipment installed at points of Connections.

(e) Basic Insulation Level (kV):


i. Bus bar .
ii. Switchgear.

Grid Code (Draft) 98 November 2010


iii. Transformer Bushings.
iv. Transformer windings.

B.1.2.4 GEERATIG UITS

(a) Parameters of Generator


i. Rated terminal voltage (kV).
ii. Rated MVA.
iii. Rated MW.
iv. Inertia constant (MW sec/MVA) H.
v. Short circuit ratio.
vi. Direct axis synchronous reactance. (% on MVA) Xd
vii. Direct axis transient reactance (% on MVA) X'd.
viii. Direct axis sub-transient reactance (% on MVA) X"d.
ix. Quadrature axis synchronous reactance (% on MVA) Xq
x. Quadrature axis transient reactance (% on MVA) X'q
xi. Quadrature axis sub-transient reactance (% on MVA) X"q
xii. Direct axis transient open circuit time constant (sec) T'do
xiii. Direct axis sub-transient open circuit time constant (Sec) T"do
xiv. Quadrature axis transient open circuit time constant (Sec) T'qo
xv. Quadrature axis transient open circuit time constant (Sec) T"qo
xvi. Stator Resistance (Ohm) Ra
xvii. Stator leakage reactance (Ohm) Xl
xviii. Stator time constant (Sec).
xix. Rated Field current (A).
xx. Open Circuit saturation characteristics of the generator for various
terminal voltages giving the compounding current to achieve this.
xxi. Type of Turbine.
xxii. Operating Head (Mtr.).
xxiii. Discharge with Full Gate Opening (cusecs).
xxiv. Speed Rise on total Load throw off (%).

(b) Parameters of Excitation Control System:


As applicable to thermal Power Stations.

Grid Code (Draft) 99 November 2010


(c) Parameters of Governor:
As applicable to thermal Power Station.

(d) Operational Parameter:


i. Minimum notice required to synchronize a Generating Unit from
de-synchronization.
ii. Minimum time between synchronizing different Generating Units in a
Power Station.
iii. Minimum block load requirements on synchronizing.

Grid Code (Draft) 100 November 2010


PART 2. FOR SUBMISSIO O REQUEST BY LICESEE

B.1.3 THERMAL POWER STATIOS

B.1.3.1 GEERAL

i. Detailed Project report.


ii. Status Report.
a. Land.
b. Fossil Fuel.
c. Water.
d. Environmental clearance.
e. Rehabilitation of displaced persons.
iii. Techno-economic approval by the Commission.
iv. Approval of Bangladesh Government
v. Financial Tie-up.

B.1.3.2 COECTIO

i. Reports of Studies for parallel operation with the Transmission System:


a. Short circuit studies.
b. Stability studies.
c. Load flow studies.

ii. Proposed Connection with Transmission System:


a. Voltage.
b. Number of circuits.
c. Point of connection

B.1.4 HYDRO-ELECTRIC POWER STATIOS

B.1.4.1 GEERAL

i. Detailed Project Report.


ii. Status Report.
a. Topographical survey.

Grid Code (Draft) 101 November 2010


b. Geological survey.
c. Land.
d. Environmental clearance.
e. Rehabilitation of displaced persons.
iii. Techno-economic approval by the Commission.
iv. Approval of Bangladesh Government.
v. Financial Tie-up.

B.1.4.2. COECTIO

i. Reports of Studies for parallel operation with the Transmission System:


a. Short circuit studies.
b. Stability studies.
c. Load flow studies.

ii. Proposed Connection with Transmission System:


a. Voltage.
b. Number of circuits.
c. Point of Connection.

B.2 DETAILED SYSTEM DATA, TRASMISSIO

B.2.1 GEERAL

i. Single line diagram of the Transmission System down to 33 kV bus at grid


Substation detailing:
a. Name of Substation.
b. Power Station, connected.
c. Number and length of circuits.
d. Interconnecting transformers.
e. Substation bus layouts.
f. Power transformers.
g. Reactive compensation equipment.
ii. Substation layout diagrams showing:
a. Bus bar layouts.
b. Electrical circuitry, lines, cables, transformers, switchgear etc.

Grid Code (Draft) 102 November 2010


c. Phasing arrangements.
d. Earthing arrangements.
e. Switching facilities and interlocking arrangements.
f. Operating voltages.
g. Numbering and nomenclature:
i) Transformers.
ii) Circuits.
iii) Circuit breakers.
iv) Isolating switches.

B.2.2 LIE PARAMETERS (For all circuits)

i. Designation of Line.
ii. Length of line (km)
iii. Number of circuits.
iv. Per Circuit values.
a. Operating voltage (kV).
b. Positive Phase sequence reactance (pu on 100 MVA) Xl
c. Positive Phase sequence resistance (pu on 100 MVA) Rl
d. Positive Phase sequence susceptance (pu on 100 MVA) Bl
e. Zero Phase sequence reactance (pu on 100 MVA) Xo
f. Zero Phase sequence resistance (pu on 100 MVA) Ro
g. Zero Phase sequence susceptance (pu on 100 MVA) Bo

B.2.3 TRASFORMER PARAMETERS (For all transformers)

i. Rated MVA.
ii. Voltage Ratio.
iii. Vector Group.
iv. Positive sequence reactance, maximum, minimum and normal (pu on 100
MVA) Xl
v. Positive sequence, resistance maximum, minimum and normal (pu on 100
MVA) R1
vi. Zero sequence reactance (pu on 100 MVA).
vii. Tap change range (+% to -%)and steps.
viii. Details of Tap changer.(OFF/ON).

Grid Code (Draft) 103 November 2010


B.2.4 EQUIPMET DETAILS (For all Substations)

i. Circuit Breakers
ii. Isolating switches
iii. Current Transformers
iv. Potential Transformers

B.2.5 RELAYIG AD METERIG

i. Relay protection installed for all transformers and feeders along with their
settings and level of coordination with other Users.
ii. Metering Details.

B.2.6 SYSTEM STUDIES

i. Load flow studies (peak and off peak loads for maximum hydro and
maximum thermal generation).
ii. Transient stability studies for three phase fault in critical lines.
iii. Dynamic Stability Studies
iv. Short circuit studies (three phase and single phase to earth)
v. Transmission and distribution losses in the system.

B.2.7 DEMAD DATA (For all Substations)

i. Demand Profile (Peak and off peak load)

B.2.8 REACTIVE COMPESATIO EQUIPMET

i. Type of equipment (fixed or variable).


ii. Capacities and/or inductive rating or its operating range in MVAR.
iii. Details of control.
iv. Point of Connection to the System.

Grid Code (Draft) 104 November 2010


B.3 DETAILED PLAIG DATA, DISTRIBUTIO

B.3.1 GEERAL

i. Distribution map (To scale) showing all lines up to 11 kV and substations


belonging to the Supplier.
ii. Single line diagram of Distribution System (showing distribution lines
from points of Connection with the Transmission System, 132/33/11 kV
substations, 11/0.4 kV substations, consumer bus if fed directly from the
Transmission System).
iii. Numbering and nomenclature of lines and substations (Identified with
feeding grid substations of the Transmission System and concerned
132/33/11 kV substation of Supplier).

B.3.2 COECTIO

i. Points of Connection (Furnish details of existing arrangement of


Connection).
ii. Details of metering points of Connection.

B.3.3 LOADS

i. Connected load - Furnish consumer details, Numbers of consumers


category wise, details of loads 1 MW and above.
ii. Information on diversity of load and coincidence factor.
iii. Daily demand profile (current and forecast) on each 132/33/11 kV
substation.
iv. Cumulative demand profile of Distribution System (current and forecast).

Grid Code (Draft) 105 November 2010


APPEDIX- C
C. OPERATIOAL PLAIG DATA

C.1 OUTAGE PLAIG DATA

REFERECE TO:
SECTIO 6 OUTAGE PLAIG

C.1.1 DEMAD ESTIMATES


Item To be Submitted By
i. Estimated aggregate annual sales of energy in 31st March of current
million units and peak and off peak demand in MW year
& MVAR at each Connection point for the period
from July of current year to June of next year.
ii. Estimated aggregate monthly sales of energy in 15th of current month
million units and peak and off peak demand in MW
& MVAR at each Connection point for the next
month.
iii. Hourly demand estimates for the day ahead. 10.00 Hours every day

C.1.2 ESTIMATES OF LOAD SHEDDIG

Item To be Submitted By
i. Details of discrete load blocks that may be shed to Soon after connection
comply with instructions issued by LDC when is made.
required, from each Connection point.

C.1.3 YEAR AHEAD OUTAGE PROGRAMME


(For the period July to June)

C.1.3.1 GEERATORS OUTAGE PROGRAMME

Item To be Submitted By
i. Identification of Generating Unit. 31st March each year
ii. MW which will not be available as a result of 31st March each year
Outage.

Grid Code (Draft) 106 November 2010


iii. Preferred start date and start time or range of start 31st March each year
dates and start times and period of Outage.
iv. If outages are required to meet statutory 31st March each year
requirements, then the latest date by which Outage
must be taken.

C.1.3.2 YEAR AHEAD DISTRIBUTIO UTILITY'S OUTAGE


PROGRAMME

Item To be Submitted By
i. Loads in MW not available from any Connection 31st March each year
point.
ii. Identification of Connection point. 31st March each year
iii. Period of suspension of drawal with start date and 31st March each year
start time.

C.1.3.3 THE LICESEE’S OVERALL OUTAGE PROGRAMME

Item To be Submitted By
i. Report on proposed Outage programme 31st April each year
ii. Release of finally agreed Outage plan. 31st May each year

C.2 GEERATIO SCHEDULIG DATA

REFERECE TO:
SECTIO 7 SCHEDULE AD DESPATCH

Item To be Submitted By
i. 36 hour ahead hourly MW & MVAR Declared 12.00 Hours every
Availability Capacity (00.00 - 24.00 Hours) of all day.
Generator Units.
ii. Status of Generating Unit excitation AVR in 12.00 Hours every
service (Yes/No). day.
iii. Status of Generating Unit speed control system. 12.00 Hours every
Governor in service (Yes/No). day.

Grid Code (Draft) 107 November 2010


iv. Spinning reserve capability (MW) 12.00 Hours every
day.
v. Backing down capability with/without oil support 12.00 Hours every
(MW) day.
vi. Hydro reservoir levels and restrictions 12.00 Hours every
day.
vii. Generating Units hourly summation outputs (MW) 12.00 Hours every
day.
vii Provisional day after Declared Availability Capacity 12.00 Hours every
notification day

C.3 CAPABILITY DATA

REFERECE TO:
SECTIO 8 FREQUECY AD VOLTAGE MAAGEMET

Item To be Submitted By
i. Generators shall submit to the Licensee up-to-date On receipt of request
capability curves for all Generating Units. by the Licensee

C.4 RESPOSE TO FREQUECY CHAGE

REFERECE TO:
SECTIO 8 FREQUECY AD VOLTAGE MAAGEMET

i. Primary response in MW at different levels of loads ranging from minimum


generation to registered capacity for frequency changes resulting in fully
opening of governor valve.
ii. Secondary response in MW to frequency changes.

Item To be Submitted By
i. Generators shall provide hourly generation To be submitted by
summation to LDC. real time basis
ii. Logged readings of Generators to LDC. As required
iii. Detailed report of Generating Unit tripping on In the first week of the
monthly basis. succeeding month

Grid Code (Draft) 108 November 2010


C.5 ESSETIAL AD O-ESSETIAL LOAD DATA

REFERECE TO:
SECTIO 9 COTIGECY PLAIG

Item To be Submitted By
i. Schedule of essential and non-essential loads on As soon as possible
each discrete load block for purposes of load after Connection
shedding.

Grid Code (Draft) 109 November 2010


APPEDIX- D
D. PROTECTIO DATA

REFERECE TO:
SECTIO 12 PROTECTIO

Item To be Submitted By
i. Generators shall submit details of protection As applicable to
requirement and schemes installed by them as detailed planning data
referred to in B.1. Detailed Planning Data under sub-
Section "Protection And Metering".
ii. The Licensee shall submit details of protection As applicable to
equipment and schemes installed by them as referred detailed planning data
to in B.2. Detailed System Data, Transmission under
sub-Section "Relaying and Metering" in relation to
Connection with any User.

Grid Code (Draft) 110 November 2010


APPEDIX- E
E. METERIG DATA

REFERECE TO:
SECTIO 13 METERIG

Item To be Submitted By
i. Generators shall submit details of metering As applicable to
equipment and schemes installed by them as referred detailed planning data
in B.1. Detailed Planning Data under sub-Section
"Protection and Metering".
ii. The Licensee shall submit details of metering As applicable to
equipment and schemes installed by them as referred detailed planning data
in B.2. Detailed System Data, Transmission under
sub-Section "Relaying and Metering" in relation to
Connection with any User.

Grid Code (Draft) 111 November 2010


17. PERFORMACE STADARDS FOR TRASMISSIO

17.1 PURPOSE AD SCOPE

17.1.1 Purpose
(a) To ensure the quality of electric power in the Grid;
(b) To ensure that the Grid will be operated in a safe and efficient manner
and with a high degree of reliability; and
(c) To specify safety standards for the protection of personnel in the work
environment.
17.1.2 Scope of Application
This Chapter applies to all Grid Users including:
(a) The Grid Owner;
(b) The System Operator;
(c) Generators;
(d) Distributors; and
(e) Any other entity with a User System connected to the Grid.

17.2 POWER QUALITY STADARDS

17.2.1 Power Quality Problems


For the purpose of this Article, Power Quality shall be defined as the quality of the
voltage, including its frequency and the resulting current, that are measured in the
Grid during normal conditions.
A Power Quality problem exists when at least one of the following conditions is
present and significantly affects the normal operation of the System:
(a) The System Frequency has deviated from the nominal value of 50 Hz;
(b) Voltage magnitudes are outside their allowable range of variation;
(c) Harmonic Frequencies are present in the System;
(d) There is imbalance in the magnitude of the phase voltages;
(e) The phase displacement between the voltages is not equal to 120
degrees;
(f) Voltage Fluctuations cause Flicker that is outside the allowable Flicker
Severity limits; or
(g) High-frequency Over-voltages are present in the Grid.
Grid Code (Draft) 112 November 2010
17.2.2 Frequency Variations
The nominal fundamental frequency shall be 50 Hz.
The control of System frequency shall be the responsibility of the System Operator.
The System Operator shall maintain the fundamental frequency within the limits of
49.0 Hz and 51.0 Hz during normal conditions.

17.2.3 Voltage Variations


For the purpose of this Section, Voltage Variation shall be defined as the deviation of
the root-mean-square (RMS) value of the voltage from its nominal value, expressed in
percent. Voltage Variation will either be of short duration or long duration.
A Short Duration Voltage Variation shall be defined as a variation of the RMS value
of the voltage from nominal voltage for a time greater than one-half cycle of the
power frequency but not exceeding one minute. A Short Duration Voltage Variation
is a Voltage Swell if the RMS value of the voltage increases to between 110 percent
and 180 percent of the nominal value. A Short Duration Voltage Variation is a
Voltage Sag (or Voltage Dip) if the RMS value of the voltage decreases to between
10 percent and 90 percent of the nominal value.
A Long Duration Voltage Variation shall be defined as a variation of the RMS value
of the voltage from nominal voltage for a time greater than one minute. A Long
Duration Voltage Variation is an Under-voltage if the RMS value of the voltage is
less than or equal to 90 percent of the nominal voltage. A Long Duration Voltage
Variation is an Overvoltage if the RMS value of the voltage is greater than or equal to
110 percent of the nominal value.
The Grid Owner and the System Operator shall ensure that the Long Duration Voltage
Variations result in RMS values of the voltages that are greater than 95 percent but
less than 105 percent of the nominal voltage at any Connection Point during normal
conditions.

17.2.4 Harmonics

For the purpose of this Section, Harmonics shall be defined as sinusoidal voltages and
currents having frequencies that are integral multiples of the fundamental frequency.
The Total Harmonic Distortion (THD) shall be defined as the ratio of the RMS value
of the harmonic content to the RMS value of the fundamental quantity, expressed in
percent.

Grid Code (Draft) 113 November 2010


The Total Demand Distortion (TDD) shall be defined as the ratio of the RMS value of
the harmonic content to the RMS value of the rated or maximum fundamental
quantity, expressed in percent.
The Total Harmonic Distortion of the voltage and the Total Demand Distortion of the
current at any Connection Point shall not exceed the limits given in Tables 17-1 and
17-2, respectively.

Table 17-1 : Maximum Harmonic Distortion Factor

Harmonic Voltage Distortion

Voltage Level THD * Individual


Odd Even
400 kV 1.5% 1.0% 0.5%
132-230 kV 2.5% 1.5% 1.0%
66 kV 3.0% 2.0% 2.0%
* Total Harmonic Distortion

Table 17-2 : Maximum Harmonic Distortion Factor

Harmonic Current Distortion

Voltage Level TDD * Individual


Odd Even
400 kV 1.5% 1.0% 0.5%
132-230 kV 2.5% 2.0% 0.5%
66 kV 5.0% 4.0% 1.0%
* Total Demand Distortion

17.2.5 Voltage Unbalance

For the purpose of this Section, the Negative Sequence Unbalance Factor shall be
defined as the ratio of the magnitude of the negative sequence component of the
voltages to the magnitude of the positive sequence component of the voltages,
expressed in percent. For the purpose of this section, the Zero Sequence Unbalance
Factor shall be defined as the ratio of the magnitude of the zero sequence component

Grid Code (Draft) 114 November 2010


of the voltages to the magnitude of the positive sequence component of the voltages,
expressed in percent.
The maximum Negative Sequence Unbalance Factor at the Connection Point of any
User shall not exceed one (1) percent during normal operating conditions.
The maximum Zero Sequence Unbalance Factor at the Connection Point of any User
shall not exceed one (1) percent during normal operating conditions.

17.2.6 Voltage Fluctuation and Flicker Severity

For the purpose of this Section, Voltage Fluctuations shall be defined as systematic
variations of the voltage envelope or random amplitude changes where the RMS
value of the voltage is between 90 percent and 110 percent of the nominal voltage.
For the purpose of this Section, Flicker shall be defined as the impression of
unsteadiness of visual sensation induced by a light stimulus whose luminance or
spectral distribution fluctuates with time.
In the assessment of the disturbance caused by a Flicker source with a short duty
cycle, the Short Term Flicker Severity shall be computed over a 10-minute period.
In the assessment of the disturbance caused by a Flicker source with a long and
variable duty cycle, the Long Term Flicker Severity shall be derived from the Short
Term Flicker Severity levels.
The Voltage Fluctuation at any Connection Point with a fluctuating demand shall not
exceed one percent (1%) of the nominal voltage for every step change, which may
occur repetitively. Any large Voltage Fluctuation other than a step change may be
allowed up to a level of three percent (3%) provided that this does not constitute a risk
to the Grid or to the System of any User.
The Flicker Severity at any Connection Point in the Grid shall not exceed the values
given in Table 17-3.

Table 17-3 : MAXIMUM FLICKER SEVERITY

Short Term Long Term


132 kV and above 0.8 unit 0.6 unit
below 132 kV 1.0 unit 0.8 unit

Grid Code (Draft) 115 November 2010


17.2.7 Transient Voltage Variations

For the purpose of this Section, Transient Voltages shall be defined as the high-
frequency Over-voltages that are generally shorter in duration compared to the Short
Duration Voltage Variations.
Infrequent short-duration peaks may be permitted to exceed the levels specified in
Section 17.2.4 for harmonic distortions provided that such increases do not
compromise service to other End-users or cause damage to any Grid equipment.
Infrequent short-duration peaks with a maximum value of two (2) percent may be
permitted for Voltage Unbalance, subject to the terms of the Connection Agreement
or Amended Connection Agreement.

17.3 RELIABILITY STADARDS

17.3.1 Criteria for Establishing Transmission Reliability Standards


The Commission shall impose a uniform system of recording and reporting of Grid
reliability performance.
The numerical levels of performance (or targets) shall be unique and shall be based
initially on the Grid’s historical performance.
The Grid shall be evaluated annually to compare its actual performance with the
targets
.
17.3.2 Transmission Reliability Indices
The Commission shall prescribe a reliability index that will measure the total number
of sustained power interruptions in the Grid. Initially the following indices will be
applicable:
(a) Availability Factor
(b) AACIR - Average Annual Customer Interruption Rate
(c) MTTR - Mean Time to Repair
(d) MTBF - Mean Time Between Failures.

The Commission shall prescribe a reliability index that will measure the total
duration of sustained power interruptions in the Grid.
After due notice and hearing, the Commission may impose other indices that will
monitor the reliability performance of the Grid.

Grid Code (Draft) 116 November 2010


17.3.3 Inclusions and Exclusions of Interruption Events
A power Interruption shall include any Outage in the Grid which may be due to the
tripping action of protective devices during faults or the failure of transmission lines
and/or power transformers, and which results in the loss of service to a Grid User or a
group of Users.
The following events shall be excluded in the calculation of the reliability indices:
(a) Outages that occur outside the Grid;
(b) Outages due to generation deficit;
(c) Planned Outages where the Users have been notified at least seven (7)
days prior to the loss of power;
(d) Outages that are initiated by the System Operator or Market Operator
during the occurrence of Significant Incidents or the failure of their
facilities;
(e) Outages caused by Adverse Weather or Major Storm Disasters which
result in the declaration by the government of a state of calamity; and
(f) Outages due to other events that the Commission shall approve after
due notice and hearing.

17.3.4 Submission of Transmission Reliability Reports and Performance Targets


The Grid Owner and the System Operator shall submit every three (3) months the
monthly Interruption reports for each Grid using the standard format prescribed by the
Commission.
The Commission shall set the performance targets for each Grid after due notice and
hearing.

17.4 SYSTEM LOSS STADARDS

17.4.1 System Loss Classifications


System Loss shall be classified into three categories: Technical Loss, Non-Technical
Loss, and Administrative Loss.
The Technical Loss shall be the aggregate of conductor loss, the core loss in
transformers, and any loss due to technical metering error.
The Non-Technical Loss shall be the aggregate of the Energy loss due to meter-
reading errors and meter tampering.
The Administrative Loss shall include the Energy that is required for the proper
operation of the Grid.

Grid Code (Draft) 117 November 2010


17.4.2 System Loss Cap
The Commission shall, after due notice and hearing, prescribe a cap on the System
Loss that can be passed on by the Grid Owner to the Grid Users. The cap shall be
applied to the aggregate of the Technical and Non-Technical Losses.
The Grid Owner shall submit to the Commission an application for the approval of its
Administrative Loss. The allowance for Administrative Loss shall be approved by the
Commission, after due notice and hearing, based on connected essential load.

17.5 SAFETY STADARDS

17.5.1 Safety Compliance


The Grid Owner and the System Operator shall develop, operate, and maintain the
Grid in a safe manner and shall always ensure a safe work environment for their
employees. The Electricity Rules 1937 govern the safety requirements for electrical
installation, operation, and maintenance which covers electrical Equipment and
associated work practices employed by the electric utility. Compliance with these
Codes is mandatory. Hence, the Grid Owner and the System Operator shall at all
times ensure that all provisions of these safety codes are not violated.

17.5.2 Measurement of Performance for Personnel Safety

Following pertinent matters are to be ensured for the measurement of performance for
personnel safety that shall be applied to the Grid Owner and the System Operator:

(a) Exposure to work injuries shall be measured by the total number of


hours of employment of all employees in each establishment or
reporting unit.
(b) Employee-hours of exposure for calculating work injury rates are
intended to be the actual hours worked. When actual hours are not
available, estimated hours may be used.
(c) The Disabling Injury/Illness Frequency Rate shall be based upon the
total number of deaths, permanent total, permanent partial, and
temporary total disabilities, which occur during the period covered by
the rate. The rate relates those injuries/illnesses to the employee-hours

Grid Code (Draft) 118 November 2010


worked during the period and expresses the number of such injuries in
terms of a million man-hour units.
(d) The Disabling Injury/Illness Severity Rate shall be based on the total of
all scheduled charges for all deaths, permanent total, and permanent
partial disabilities, plus the total actual days of the disabilities of all
temporary total disabilities, which occur during the period covered by
the rate. The rate relates these days to the total employee-hours worked
during the period and expresses the loss in terms of million man-hour
units.

17.5.3 Submission of Safety Records and Reports


The Grid Owner and System Operator shall submit to BERC copies of records and
reports. These shall include the measurement of performance specified in Section
17.5.2.

17.6 Electric and Magnetic Field (EMF)

The Licensee shall calculate the intensity of Electric and Magnetic Field (EMF) at the edge
of right of way for different line configuration and operating voltages. The values of
Electric Field shall be determined in V/m and that of Magnetic Field in mT (milli-Telsa) or
mG (milli-Gauss). Actual intensity shall practically be measured in accordance with IEEE
Standard-644 (latest revision) and the finding shall be submitted to the Commission. Safety
level with respect to human exposure to electromagnetic field shall also be determined and
maintained in accordance with IEEE C95.1 thru IEEE C95.6 (2002 or latest revision).

17.7 oise Level

Noise level having its source at grid substations and Noise level around the transmission
lines shall be in accordance with the Environmental laws of Bangladesh. International
standards shall be followed if boundary conditions are missing in the pertinent laws of the
country.

Grid Code (Draft) 119 November 2010


18. FIACIAL STADARDS FOR TRASMISSIO

18.1 PURPOSE AD SCOPE


18.1.1 Purpose

(a) To specify the financial capability standards for the Generators and for
the Grid Owner and System Operator;
(b) To safeguard against the risk of financial non-performance;
(c) To ensure the affordability of electric power supply while maintaining
the required quality and reliability; and
(d) To protect the public interest.

18.1.2 Scope of Application


This Chapter applies to all Grid Users including:
(a) The Grid Owner;
(b) The System Operator; and
(c) Generators.

18.2 FIACIAL STADARDS FOR GEERATORS


18.2.1 Financial Ratios
The following Financial Ratios shall be used to evaluate the Financial Capability of
Generators:
(a) Leverage Ratios;
(b) Liquidity Ratios;
(c) Financial Efficiency Ratios; and
(d) Profitability Ratios.

18.2.2 Leverage Ratios

Leverage Ratios for the Generators shall include the following:


(a) Debt Ratio;
(b) Debt-Equity Ratio; and
(c) Interest Cover.

Grid Code (Draft) 120 November 2010


The Debt Ratio shall measure the degree of indebtedness of the Generator. The Debt
Ratio shall be calculated as the ratio of total liabilities to total assets.

The Debt Ratio shall be used to measure the proportion of assets financed by
creditors. The risk addressed by the Debt Ratio is the possibility that the Generator
cannot pay off interest and principal.

The Debt Ratio can also be calculated as the ratio of Long-Term Debt plus Value of
Leases to Long-Term Debt plus Value of Leases plus Equity. Equity is the sum of
Outstanding Capital Stock, Retained Earnings, and Revaluation Increment.

The Debt-Equity Ratio shall indicate the relationship between long-term funds
provided by creditors and those provided by the Generators. The Debt-Equity Ratio
shall be calculated as the ratio of the sum of Long-Term Debt plus Value of Leases to
Equity. Equity shall be the sum of Outstanding Capital Stock, Retained Earnings, and
Revaluation Increment.

The Debt-Equity Ratio shall be used to compare the financial commitments of


creditors relative to those of the Generators.

The Debt-Equity Ratio shall be used as a measure of the degree of financial leverage
of the Generator.

The Interest Cover shall measure the ability of the Generator to service its debts. The
Interest Cover shall be computed as the ratio of Earnings Before Interest and Taxes
(EBIT) plus Depreciation to Interest plus Principal Payments.

The Interest Cover shall also be used as a measure of financial leverage for the
Generator that focuses on the extent to which contractual interest and principal
payments are covered by earnings before interest and taxes plus depreciation. The
Interest Cover is identical to Debt Service Coverage Ratio because principal payments
due during the year are included in the denominator of the ratio.

18.2.3 Liquidity Ratios

Liquidity Ratios shall include the following:


(a) Current Ratio; and
(b) Quick Ratio.
The Current Ratio shall measure the ability of the Generator to meet short-term
obligations. The Financial Current Ratio shall be calculated as the ratio of Current

Grid Code (Draft) 121 November 2010


Assets including inventories to Current Liabilities. Current Assets shall consist of cash
and assets that can readily be turned into cash by the Generator. Current Liabilities
shall consist of payments that the Generator is expected to make in the near future.

The Current Ratio shall be used as a measure of the margin of liquidity of the
Generator.

The Quick Ratio shall measure the ability of the Generator to satisfy its short-term
obligations as they become due. The Quick Ratio shall be calculated as the ratio of the
sum of Cash, Marketable Securities, and Receivables to the Current Liabilities.
The Quick Ratio shall be used to measure the safety margin for the payment of current
debt of the Generator if there is shrinkage in the value of cash and receivables.

18.2.4 Financial Efficiency Ratios


Financial Efficiency Ratios shall include the following:

(a) Sales-to-Assets Ratio; and


(b) Average Collection Period.

The Sales-to-Assets Ratio shall measure the efficiency with which the Generator uses
all its assets to generate sales. The Sales-to-Assets Ratio shall be calculated as the
ratio of Sales to Average Total Assets. The Average Total Assets shall be determined
using the average of the assets at the beginning and end of the year. The higher the
Sales-to-Assets Ratio, the more efficiently the Generator’s assets have been used.
The Average Collection Period (ACP) shall measure how quickly other entities pay
their bills to the Generator. The Average Collection Period shall be calculated as the
ratio of Average Receivables to Daily Sales. The Average Receivables shall be
determined using the average of the receivables at the beginning and end of the year.
Daily Sales shall be computed by dividing Annual Sales by 365 days.
The Average Collection Period shall be used to evaluate the credit and collection
policies of the Generator.

Two computations of the Average Collection Period shall be made:

(a) ACP with government accounts and accounts under litigation; and
(b) ACP without government accounts and accounts under litigation.

Grid Code (Draft) 122 November 2010


18.2.5 Profitability Ratios

Profitability Ratios shall include the following: (a) Net Profit Margin; and (b) Return
on Assets.
The Net Profit Margin shall measure the productivity of sales effort. The Net Profit
Margin shall be calculated as the ratio of Net Profits After Taxes to Sales. The Net
Profits After Taxes shall be computed as Earnings Before Interest and Taxes minus
Tax (EBIT – Tax).
The Net Profit Margin shall be used to measure the percentage of Generator sales that
remain after all costs and expenses have been deducted.
The Return on Assets shall measure the overall effectiveness of the Generator in
generating profits from its available assets. The Return on Assets shall be calculated
as the ratio of Earnings Before Interest and Taxes minus Tax to the Average Total
Assets. The Average Total Assets shall be computed as the average of the assets at the
beginning and end of the year.

18.2.6 Submission and Evaluation


Generators shall submit to the Commission true copies of audited balance sheet and
financial statement for the preceding financial year on or before December 31 of the
current year.

Generators shall submit to the Commission the average power consumption for each
class of customers for the preceding financial year. This requirement is due on or
before December 31 of the current year.

Failure to submit to the Commission the requirements shall serve as grounds for the
imposition of appropriate sanctions, fines, penalties, or adverse evaluation.

All submissions are to be certified by a duly authorized officer.

18.3 FIACIAL STADARDS FOR GRID OWER AD SYSTEM OPERATOR


18.3.1 Financial Ratios
The following Financial Ratios shall be used to evaluate the Financial Capability of
the Grid Owner and System Operator:
(a) Leverage Ratios;
(b) Liquidity Ratios;

Grid Code (Draft) 123 November 2010


(c) Financial Efficiency Ratios; and
(d) Profitability Ratios.

18.3.2 Leverage Ratios

Leverage Ratios for the Grid Owner and System Operator shall include the following:
(a) Debt Ratio;
(b) Debt-Equity Ratio; and
(c) Interest Cover.
The Debt Ratio shall measure the degree of indebtedness or financial leverage of the
Grid Owner and System Operator. The Debt Ratio shall be calculated as the ratio of
Total Liabilities to Total Assets.

The Debt Ratio shall be used to measure the proportion of assets financed by
creditors. The risk addressed by the Debt Ratio is the possibility that the Grid Owner
and System Operator cannot pay off interest and principal.

The Debt Ratio can also be calculated as the ratio of Long-Term Debt plus Value of
Leases to Long-Term Debt plus Value of Leases plus Equity. Equity shall be the sum
of Outstanding Capital Stock, Retained Earnings, and Revaluation Increment.

The Debt-Equity Ratio shall indicate the relationship between long-term funds
provided by creditors and those provided by the Grid Owner and System Operator.
The Debt-Equity Ratio shall be calculated as the ratio of the sum of Long-Term Debt
plus Value of Leases to Equity. The Equity shall be the sum of Outstanding Capital
Stock, Retained Earnings, and Revaluation Increment.

The Debt-Equity Ratio shall be used to compare the financial commitments of


creditors relative to those of the Grid Owner and System Operator.

The Debt-Equity Ratio shall be used as a measure of the degree of financial leverage
of the Grid Owner and System Operator.

The Interest Cover shall measure the ability of the Grid Owner and System Operator
to service their debts. The Interest Cover shall be computed as the ratio of Earnings
Before Interest and Taxes (EBIT) plus Depreciation to Interest plus Principal
Payments.

The Interest Cover shall also be used as a measure of financial leverage for the Grid
Owner and System Operator that focuses on the extent to which contractual interest
and principal payments are covered by earnings before interest and taxes plus

Grid Code (Draft) 124 November 2010


depreciation. The Interest Cover is identical to Debt Service Coverage Ratio because
principal payments due during the year are included in the denominator of the ratio.

18.3.3 Liquidity Ratios


Liquidity Ratios shall include the following:
(a) Current Ratio; and
(b) Quick Ratio.
The Current Ratio shall measure the ability of the Grid Owner and System Operator to
meet their short-term obligations. The Current Ratio shall be calculated as the ratio of
Current Assets to Current Liabilities. The Current Assets shall consist of cash and
assets that can readily be turned into cash by the Grid Owner and System Operator.
The Current Liabilities shall consist of payments that the Grid Owner and System
Operator are expected to make in the near future.
The Financial Current Ratio shall be used as a measure of the margin of liquidity of
the Grid Owner and System Operator.
The Quick Ratio shall measure the ability of the Grid Owner and System Operator to
satisfy their short-term obligations as they become due. The Quick Ratio shall be
calculated as the ratio of the sum of Cash, Marketable Securities and Receivables to
the Current Liabilities.
The Quick Ratio shall be used to measure the safety margin for the payment of current
debt of the Grid Owner and System Operator if there is shrinkage in the value of cash
and receivables.

18.3.4 Financial Efficiency Ratios

Financial Efficiency Ratios shall include the following:

(a) Sales-to-Assets Ratio; and


(b) Average Collection Period.

The Sales-to-Assets Ratio shall measure the efficiency with which the Grid Owner
and System Operator use all their assets to generate sales. The Sales-to-Assets Ratio
shall be calculated as the ratio of Sales to Average Total Assets. The Average Total
Assets shall be determined using the average of the assets at the beginning and end of
the year. The higher the Sales-to-Assets Ratio, the more efficiently the assets of the
Grid Owner and System Operator have been used.
Grid Code (Draft) 125 November 2010
The Average Collection Period (ACP) shall measure how quickly other entities pay
their bills to the Grid Owner and System Operator. The Average Collection Period
shall be calculated as the ratio of Average Receivables to Daily Sales. The Average
Receivables shall be determined using the average of the receivables at the beginning
and end of the year. Daily Sales shall be computed by dividing Annual Sales by 365
days.

The Average Collection Period shall be used to evaluate the credit and collection
policies of the Grid Owner and System Operator.
Two computations of the Average Collection Period shall be made:

(a) ACP with government accounts and accounts under litigation; and
(b) ACP without government accounts and accounts under litigation. 18.3.5
Profitability Ratios
Profitability Ratios shall include the following: (a) Net Profit Margin; and (b) Return
on Assets.

The Net Profit Margin shall measure the productivity of sales effort. The Net Profit
Margin shall be calculated as the ratio of Net Profits After Taxes to Sales. The Net
Profits After Taxes shall be computed as Earnings Before Interest and Taxes minus
Tax (EBIT – Tax). The Average Total Assets shall be computed as the average of the
assets at the beginning and end of the year.

The Net Profit Margin shall be used to measure the percentage of each peso of sales of
the Grid Owner and System Operator that remains after all costs and expenses have
been deducted.
The Return on Assets (ROA) shall measure the overall effectiveness of the Grid
Owner and System Operator in generating profits from their available assets. The
Return on Assets shall be calculated as the ratio of Earnings Before Interest and Taxes
minus Tax to the Average Total Assets. The Average Total Assets shall be computed
as the average of the assets at the beginning and end of the year.

The Return on Assets shall be used to measure the overall effectiveness of the Grid
Owner and System Operator in generating profits from their available assets.

18.3.6 Submission and Evaluation

Grid Code (Draft) 126 November 2010


The Grid Owner and System Operator shall submit to the Commission true copies of
audited balance sheet and financial statement for the preceding financial year on or
before December 31 of the current year.

The Grid Owner and System Operator shall submit to the Commission a profile of
customers, indicating the average power consumption for each class of customers for
the preceding financial year. This requirement is due on or before December 31 of the
current year.

Failure to submit to the Commission the requirements shall serve as grounds for the
imposition of appropriate sanctions, fines, penalties, or adverse evaluation.

All submissions are to be certified by a duly authorized officer.

18.4 Uniform System of Accounts (USoAC)

The Licensee shall follow the accounting procedures of the Commission namely the
Uniform System of Accounts (USoAC) in fulfilling the requirements of Financial
Standard of Transmission stated in this Grid Code.

Anything of the Financial Standard of Transmission contradictory to the provisions/


procedures of the USoAC then the provisions/ system of the later shall prevail.

Grid Code (Draft) 127 November 2010

You might also like