Unit Cum: Taking Output 195 Cum (450 Tonnes)
Unit Cum: Taking Output 195 Cum (450 Tonnes)
to
Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
ref.
Spec.
5.7 508 Semi-Dense Bituminous Concrete
Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP
producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 4.5 to 5 per cent of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor
control to the required grade, level and alignment, rolling with smooth wheeled, vibratory
and tandem rollers to achieve the desired compaction as per MoRTH specification clause
No. 508 complete in all respects
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 315.00 264.60 L-12
Mazdoor working with HMP, mechanical broom, paver, roller, asphalt cutter and day 16.000 280.00 4480.00 L-13
assistance for setting out lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 300.00 1500.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 13227.50 79365.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 cum per hour hour 6.000 1163.65 6981.90 P&M-034
Generator 250 KVA hour 6.000 832.50 4995.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 962.00 5772.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x 3 19.24 25974.00 Lead =11 km &
P&M-058
Add 10 per cent of cost of carriage to cover cost of loading and unloading 2597.40
Smooth wheeled roller 8-10 tonnes for initial break down rolling. hour 6.00x0.65* 1365.30 5324.67 P&M-044
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1365.30 5324.67 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem roller hour 6.00x0.65* 1838.90 7171.71 P&M-045
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix tonne 18.630 27908.00 519926.04 M-074
Plastic waste @ 8% of bitumen 1.620 22000.00 35640.00
ii) Aggregate 20.25
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 1141.60 65413.68 M-044
10 - 5 mm 38 per cent cum 108.870 756.60 82371.04 M-040
5 mm and below 40 per cent cum 114.600 646.60 74100.36 M-030
Filler @ 2 per cent of weight of aggregates. tonne 5.730 871.60 4994.27 M-188
*Any one of the alternative may be adopted as per approved design
(i) for Grading I ( 13 mm nominal size )
d) Overhead charges @ 12.5% on (a+b+c) 116524.54
e) Contractor's profit @ 0.1 on (a+b+c+d) 104872.09
Add Rooyality Stone grite @ 160/cum cum 166.170 160.00 26587.20
Add Rooyality Stone Dust @ 100/cum cum 120.330 100.00 12033.00
Cost for 205 cum = a+b+c+d+e 1192213.17
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 6113.91
say 6114.00