100% found this document useful (1 vote)
167 views16 pages

2021 C - ACTIVATE12 Exam Questions and Answers

The document provides information about a website that offers free and premium practice questions to prepare for various certification exams. It includes sample questions and answers for the SAP Certified Associate - SAP Activate Project Manager exam, covering topics related to the SAP Activate methodology.

Uploaded by

Deng Lili
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
167 views16 pages

2021 C - ACTIVATE12 Exam Questions and Answers

The document provides information about a website that offers free and premium practice questions to prepare for various certification exams. It includes sample questions and answers for the SAP Certified Associate - SAP Activate Project Manager exam, covering topics related to the SAP Activate methodology.

Uploaded by

Deng Lili
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

Pdfprep.

com is a good website providing free and premium prep


questions for you to practice and study all the questions and answers,
such as Microsoft, Cisco, IBM, Huawei, and so on.

C_ACTIVATE12 SAP Certified


Associate Exam
Exam name: SAP Certified Associate - SAP Activate Project
Manager

Full Q&As: 198 Q&As

Version: PDF

Update: Free in 90 Days

SAP SAP Certified Associate


C_ACTIVATE12 Premium Dumps
Free SAP C_ACTIVATE12 exam prep questions are available
below, you can study them to prepare this C_ACTIVATE12 SAP
Certified Associate exam.

1.Which accelerations can you use during the Scope Validation/Fit-Gap Analysis
activity in the Explore Phase? There are 2 correct answers to this question.
A. Sprint Backlog Template
B. RICEF Specification Template
C. Solution Validation Workshop
D. Quality Gate Checklist
Answer: B,C

2.Which of the following is not correct about workstreams? There are 2 correct
answers to this question.
A. It is assigned as attribute to phases, deliverables and tasks.
B. It can span phases
C. It is a collection of related deliverables
D. Workstreams are dependent on phase start and end
Answer: A,D

3.Which value chains does SAP solution manager 7.2 deliver? There are 3
correct answers to this question.
A. Hire-to-retire
B. Detect-to-correct
C. Cash-to-order
D. Requirements-to-deploy
E. Request-to-fulfil
Answer: B,D,E

4.What are the three cornerstones of SAP's cloud security strategy?


A. Secure People
B. Secure Operations
C. Secure Company
D. Secure Cloud
E. Secure Products
Answer: B,C,E

5.What are deliverables of the Application: Integration work stream in the prepare
phase? There are 3 correct answers to this question.
A. Fit/Gap Analysis
B. Data Cleansing
C. Security Checks
D. Adaptation Specifications
E. Network Connectivity Checks
Answer: C,D,E

6.What does "SSCUI" stand for?


A. Self-Service Customization User Interface
B. Self-Service Configuration User Interface
C. Self-Service Creation User Interface
D. Self-Service Collection User Interface
Answer: B

7.What does SAP Activate recommend to keep team members informed and
aligned? Please choose the correct answer.
A. Daily status meeting with project manager
B. Daily team stand-up meeting
C. Daily e-mail status updates to project manager
D. Daily progress review meeting with sponsor
Answer: B

8.Which of the following is true about a cloud implementation project? There are
2 correct answers to this question.
A. The entire transport system is kept intact and up and running.
B. Starter Systems are not required to be in place for the 'Fit to Standard'
workshops.
C. The Starter System is specific to SAP S/4HANA Cloud.
D. In the prepare phase of a cloud implementation project the project team
provide the customer with materials to review as self-enablement.
Answer: C,D
9.What are some of the defined recommendations for organizational change
success?
A. Don't worry about the scale of change for end users.
B. Promote the case for change and look forward to avoid change fatigue.
C. Collect feedback from employees occasionally.
D. Be aware of cultural and language barriers for regions, countries, and Lines of
Business impacted by v u change.
E. Maintain a robust governance structure, especially in the Run phase.
Answer: B,D,E

10.What are some of the required customer activities to maintain their SAP
S/4HANA Cloud system post go-live?
A. Activate new scope (if applicable)
B. Conduct regression testing on business processes
C. Maintain business catalogs
D. Stay current
E. Test new features in the Stay Current Early Knowledge Enablement Sandbox /
Trial environment
Answer: A,B,C

11.What is a difference between the SAP Activate methodology for a new


implementation of SAP S/4HANA cloud edition and a new implementation of SAP
S/4HANA on-premise? Please choose the correct answer.
A. For the cloud edition, there is an additional work stream for integration with on-
premise systems
B. For the cloud edition, there is an additional Q-Gate for integration with on-
premise systems
C. For on-premise, there is an additional Q-Gate for system installation
D. For on-premise, there are additional deliverables for the system setup
Answer: D

12.What accelerator can help you document the configuration definition in the
explore Phase?
A. Change request template
B. Backlog template
C. Test strategy
D. Data definition
Answer: B

13.In the System conversion to SAP S/4 HANA Deploy phase, which of the
following tasks are included? Please choose the correct answer.
A. Scheduling project plan
B. Final testing
C. Interface setup
D. Hyper care support
Answer: B

14.When do you perform User Acceptance Testing during the Agile Build?
Please choose the correct answer.
A. Before Integration Testing
B. During each Firm-up Sprint
C. After each Sprint
D. After Integration Testing
Answer: D

15.What can users do in the Roadmap Viewer tool? Please choose the correct
answer.
A. Display and navigate detailed SAP Activate methodology WBS
B. Upload SAP Activate WBS into SAP Solution Manager7.1
C. Download full SAP Activate methodology content for use off-line
D. Create a customer-specific version of SAP Activate Methodology
Answer: A

16.What are some responsibilities of customer key users after go-live of an SAP
S/4HANA Cloud project?
A. Complete the implementation activities as assigned.
B. Responsible for inspection and approval of results and of the overall project.
C. Search for solutions and process incidents from end users directly and when
necessary, request help from SAP.
D. Manage Users and Task Assignment.
E. Monitor internal/external communications such as printers and integration with
third-parties.
Answer: C,D,E
17.What must be defined in the Preset Phase of implementation to enable
configuration of business processes?
A. Organizational Structure
B. Master Data
C. Expert Configuration
D. Chart of Accounts
Answer: A,D

18.Which of the following are not phases of the SAP Activate methodology?
There are 2 correct answers to this question.
A. Go-Live & Support
B. Preparation
C. Prepare
D. Realize
Answer: A,B

19.What are some characteristics of the "Cloud" mindset?


A. Make the company fit the software
B. Heavy customizations and modifications
C. Business blueprint phase
D. Workarounds and light extensions
E. Fit-to-Standard workshops
F. Make the software fit the company
Answer: A,D,E

20.What is the key characteristic of Agile project delivery? Please choose the
correct answer.
A. Frequent and detailed project scheduling
B. Formal and detailed documentation
C. Iterative build with frequent inspections
D. Frequent Quality Gates
Answer: C

21.What does it mean if an SSCUI has a "Yes" in the "Redo in P System"


column?
A. You must manually redo the configuration in the production system, because it
is not captured in change projects.
B. SSCUI records are specific to a company or country and every country has its
own unique configuration records.
C. The configuration is transferred from the quality system to the production
system in change projects.
D. The configuration records are the same for all countries and all country
solutions have the same data.
Answer: A

22.What are the two options for transferring data to SAP S/4HANA Cloud?
A. Data Aging (1K8)
B. Data Migration to SAP S/4HANA from Staging (2Q2)
C. Data Migration to SAP S/4HANA from File (BH5)
D. Data Migration to SAP S/4HANA from SAP (BH3)
Answer: B,C

23.What are some of the key topics covered in the customer team enablement
workshops? NOTE: There are 3 correct answers to this question.
A. Technical expertise
B. Project management
C. Project sourcing approach
D. Solution expertise
E. Planning skills
Answer: A,B,D

24.Arrange the following in the correct sequence of steps followed for a Fit to
Standard workshop. Please choose the correct answer.
A. Demonstrate Business Scenarios and Concepts, Review Best Practice
Process Flow, Identify required configuration, Discuss how the process fit with
customer requirements, Enable customer on execution of scenarios, Identify
gaps
B. Review Best Practice Process Flow, Demonstrate Business Scenarios and
Concepts, Discuss how the process fit with customer requirements, Identify gaps,
Identify required configuration, Enable customer on execution of scenarios
C. Review Best Practice Process Flow, Demonstrate Business Scenarios and
Concepts, Identify required configuration, Discuss how the process fit with
customer requirements, Enable customer on execution of scenarios, Identify
gaps
D. Discuss how the process fit with customer requirements, Review Best Practice
Process Flow, Demonstrate Business Scenarios and Concepts, Identify required
configuration, Enable customer on execution of scenarios, Identify gaps
Answer: B

25.What SAP S/4HANA deployment model has the characteristics of a core ERP
scope with rapid innovation, SAP-led governance, and standardization?
A. SAP S/4HANA Cloud, single tenant edition
B. SAP S/4HANA deployed in SAP HANA Enterprise Cloud
C. SAP S/4HANA Cloud
D. SAP S/4HANA on premise
Answer: C

26.What does SAP define as the three key components of how a data center
works?
A. Cooling
B. Backup Retention Procedures
C. Power Supply
D. Certification Standards
E. Controlled Access
Answer: A,C,E

27.Which of the following are components of SAP Model company? There are 3
correct answers to this question.
A. Quality gate checklist
B. Accelerators
C. Business-driven configuration questionnaire
D. Business process content for SAP solution manger
E. Preconfigured solution
Answer: B,D,E

28.What configuration cannot be changed after Preset phase activation"


A. New country activation
B. Organizational structure keys
C. Maintain Takeover Date for Asset Accounting
D. Fiscal year variant
Answer: B,D
29.Which of the following content best outlines the sequence of testing within the
application Design and configuration workstream in the realize phase?
A. integration test
User acceptance test
String test
B. string test
User acceptance test
Integration test
C. string test
Integration test
User acceptance test
D. data migration
String test
User acceptance test
Answer: C

30.Which of the following is not a characteristic that the quality principles are
based on? Please choose the correct answer.
A. Experience of Typical Pitfalls
B. SAP Quality Award example winners
C. International standard
D. Best Practices
Answer: C

31.What must you do when you implement SAP Business Suite On-Premise with
SAP Best Practices? Please choose the correct answer.
A. Activate and apply SAP Best Practices content with the self-service
configuration UI
B. Activate and apply SAP Best Practices with SAP Solution Manager
C. Apply SAP Best Practices with the Configure your Solution application
D. Assemble and apply SAP Best Practices to the system
Answer: B

32.What is the basis for approving work results (signing act of acceptance) on a
project phase level?
A. Definition of done for user story
B. Scrum of scrums meeting decision
C. Definition of ready for sprint
D. Agreed and met acceptance criteria within quality gate
Answer: D

33.When is provisioning of the production system requested?


A. After the starter system is decommissioned
B. Immediately after receive the inactive quality system (Preset phase)
C. Immediately after receiving the active quality system
D. After completing configuration of the business processes in the quality system
Answer: C

34.What do you do during post cutover? Please choose the correct answer.
A. Setup Operational Support
B. Perform the Verification Session of the SAP Going Live Check
C. Perform Technical System Test
D. Conduct Organizational Readiness Check
Answer: B

35.Which content packages are available in the SAP Package Library? There are
2 correct answers to this question.
A. SAP Activate Methodology
B. SAP Best Practices
C. Solution Builder
D. Rapid Deployment Solutions
Answer: B,D

36.Why might you choose to migrate data to SAP S/4HANA Cloud with the
Staging approach?
A. If you can import the data manually
B. If you need to find a way to automate the transfer of data
C. If you need transfer a lot of data
D. If you need to import a small amount of data
Answer: B

37.Which of the following activities are part of the Deploy Phase of a Landscape
Transformation journey to SAP S/4HANA On-Premise Edition? There are 2
correct answers to this question.
A. Solution Activation
B. Optimize software Change Control Management
C. Training delivery
D. Access organizational and production readiness
Answer: C,D

38.How are the build and test tasks planned and executed in the Realize phase?
Please choose the correct answer.
A. By using the sprint backlog list as input for each iteration.
B. By executing regression tests after each iteration
C. With Q-Gates for sign off after each iteration
D. By using incremental build in fixed-scope iteration
Answer: D

39.What are some of the training tools / resources available in SAP Learning
Hub?
A. Live Sessions in SAP Learning Rooms
B. Learning Center App
C. SAP Learning Rooms
D. SAP Best Practice Business Processes
E. SAP Learning Journeys
Answer: A,C,E

40.What is the most granular level of the methodology you can view in the
Roadmap Viewer? Please choose the correct answer.
A. Scenario
B. Task
C. Deliverables
D. Phase
Answer: B

41.Which navigation option do you use in the Roadmap Viewer to access the
SAP Activate Methodology content? Please choose the correct answer.
A. Navigate by assigned Delivery Mode
B. Navigate by RACI matrix accountability
C. Navigate by work stream
D. Navigate by Project Team Member Role
Answer: C

42.What are some characteristics of SAP S/4HANA Cloud?


A. SAP S/4HANA Cloud is single-tenant; meaning your service runs in a
dedicated environment.
B. SAP S/4HANA Cloud is multi-tenant, meaning your service runs in a shared
environment.
C. SAP S/4HANA Cloud includes quarterly innovation cycles.
D. SAP S/4HANA Cloud runs in an infrastructure with private, managed services
for SAP solutions.
E. SAP S/4HANA Cloud provides additional functionality for customers that
require broad extensions and deep configuration capabilities.
Answer: B,C

43.Which estimation technique can be used in Agile project delivery to size the
user stories during sprint planning? Please choose the correct answer.
A. Detailed bottom-up effort estimate the breaks each user story up into hours or
shorter tasks
B. Relative estimate in ideal person days that reflects the best estimate provided
by the project team
C. Detailed bottom-up effort estimate by the SCRUM Master in story points
based on the user story complexity
D. Product Owner’s relative estimate of the effort that will be needed to
implement the user story
Answer: D

44.How do you achieve frequent checkpoints with the end user in an Agile
delivery approach? There are 2 correct answers to this question.
A. Demo the SAP model company
B. User acceptance test
C. Solution demo for sprints
D. Solution review for waves
Answer: C,D

45.Which tools does SAP Activate provide to support Guided Configuration?


There are 3 correct answers to this question.
A. Solution Builder
B. Expert Configuration
C. Self Service Configuration
D. SAP Solution Composer
E. Model Company
Answer: A,B,C

46.Which new role is introduced in the SAP activate methodology in a full scrum
team?
A. Project manager
B. Application consultant
C. Product owner
D. System administrator
Answer: C

47.Which of the following is not correct about Fit/Gap Analysis? There are 2
correct answers to this question.
A. Prioritize delta requirement and gaps.
B. Drive towards adopting customers processes.
C. Minimize the needs for rework during realization.
D. Validate pre-activate and pre-assembled solution in the development system.
Answer: B,D

48.How would you describe the realise phase in the "new implementation of SAP
S/4HANA" transition path?
A. Configure and adjust custom code
B. Configuration copy
C. Configure
D. Configure and develop
Answer: A

49.Which deliverable is specific to on-premise and NOT for the cloud? Please
choose the correct answer.
A. Technical Design Solution
B. Knowledge Transfer
C. Adaptation Specification
D. Learning Needs Analysis
Answer: B

50.Which activity helps the project team to add the user stories to the product
backlog? Please choose the correct answer.
A. Planning the User Acceptance Test
B. Preparing a Project Schedule
C. Conducting the Solution Validation
D. Assessing Project Risks
Answer: C

51.In which of the following project phases is it important to plan and schedule
data loads followed by load validation activities?
A. Deploy
B. Realize
C. Prepare
D. Explore
Answer: B

52.Which activities are critical for delivering Agile projects? There are 2 correct
answers to this question.
A. Retrospective agenda creation
B. Sprint planning
C. Release planning
D. Blueprint scheduling
Answer: B,C

53.What do you do during an iterative approach to build a solution? Please


choose the correct answer.
A. Build the solution module by module
B. Deliver a prototype of the solution
C. Provide a working solution only at the end of the release
D. Include frequent inspection check-points
Answer: D

54.Which of the following are available in the initial SAP Methodologies JAM
Page? There are 2 correct answers to this question.
A. Task description
B. Accelerators
C. Summary
D. Roadmaps
Answer: B,D

55.What is the best transition scenario for a customer looking for some, but not
full process redesign, and re-use of existing processes in some areas that still fit?
A. Selective Data Transition
B. New Implementation
C. System Conversion
Answer: A

56.In what respect is SAP Activate Methodology different from the ASAP
Methodology? Please choose the correct answer.
A. Supports cloud deployments
B. Supports only new implementations
C. Leverages iterative incremental build
D. Includes Fit/Gap analysis instead of Blueprint
Answer: D

57.What is the minimum number of quality gates mandated by the SAP Activate
methodology? Please choose the correct answer.
A. 0
B. 3
C. 4
D. 5
Answer: C

58.Which accelerator can help you document the detailed design of solution
extensions? Please choose the correct answer.
A. Change Request Template
B. Product Backlog Template
C. Sprint Backlog Template
D. RICEF Specification Template
Answer: D
59.Which of the following are levels in the structure of an SAP Best practices
solution package? There are 2 correct answers to this question.
A. Building blocks
B. Configuration guides
C. Business process scenarios
D. Scope items
Answer: A,D