Detailed Estimates

The document provides estimates for a proposed mixed-use building project including excavation and backfilling works, concrete works, steel reinforcement works, masonry works, ceiling works, and roofing and structural steel works. It lists materials, quantities, unit costs, and totals for each item. Labor costs are estimated at 40% of material costs.

Uploaded by

Mac KY
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
170 views

Detailed Estimates

The document provides estimates for a proposed mixed-use building project including excavation and backfilling works, concrete works, steel reinforcement works, masonry works, ceiling works, and roofing and structural steel works. It lists materials, quantities, unit costs, and totals for each item. Labor costs are estimated at 40% of material costs.

Uploaded by

Mac KY
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Project Title : Proposed Tow-Storey with Roof Deck Mixed Used Buiding

Owner :
Location :

DETAILED ESTIMATES

Note: Labor Cost is 40% of the material cost.


ITEM UNIT COST
WORK DESCRIPTION UNIT QUANTITY AMOUNT
NO. MATERIAL LABOR
3
I Excavation and Backfilling Works m 180.92 ₱150.31 ₱27,193.09
3
a Exavation m 180.92 ₱120.00 ₱21,710.16
3
b Select fill m 180.41 ₱20.00 ₱3,608.19
3
c Gravel Bed m 13.39 ₱100.00 ₱40.00 ₱1,874.74
Sub-Total ₱27,193.09
3
II Concrete Works m 169.22 ₱5,124.00 ₱867,066.63
3
a Footing m 26.98
Portland Cement bags 242.811 ₱240.00 ₱96.00 ₱81,584.50
3
Sand m 13.4895 ₱1,000.00 ₱400.00 ₱18,885.30
3
Gravel m 26.979 ₱1,000.00 ₱400.00 ₱37,770.60
3
b Wall Footing m 4.80
Portland Cement bags 43.2 ₱240.00 ₱96.00 ₱14,515.20
3
Sand m 2.4 ₱1,000.00 ₱400.00 ₱3,360.00
3
Gravel m 4.8 ₱1,000.00 ₱400.00 ₱6,720.00
3
c Tie Beam m 10.53
Portland Cement bags 94.77 ₱240.00 ₱96.00 ₱31,842.72
3
Sand m 5.265 ₱1,000.00 ₱400.00 ₱7,371.00
3
Gravel m 10.53 ₱1,000.00 ₱400.00 ₱14,742.00
3
d Column m 32.19
Portland Cement bags 289.7325 ₱240.00 ₱96.00 ₱97,350.12
3
Sand m 16.09625 ₱1,000.00 ₱400.00 ₱22,534.75
3
Gravel m 32.1925 ₱1,000.00 ₱400.00 ₱45,069.50
3
e Beams m 30.59
Portland Cement bags 275.31225 ₱240.00 ₱96.00 ₱92,504.92
3
Sand m 15.295125 ₱1,000.00 ₱400.00 ₱21,413.18
3
Gravel m 30.59025 ₱1,000.00 ₱400.00 ₱42,826.35
3
f Slab m 64.13
Portland Cement bags 577.125 ₱240.00 ₱96.00 ₱193,914.00
3
Sand m 32.0625 ₱1,000.00 ₱400.00 ₱44,887.50
3
Gravel m 64.125 ₱1,000.00 ₱400.00 ₱89,775.00
Sub-Total ₱867,066.63
III Steel Reinforcement Works kg 18072.79 ₱62.39 ₱1,127,478.66
a Footing kg 1975.57
20mm dia. steel bar @ 6m long pcs 25 ₱510.00 ₱204.00 ₱17,850.00
16mm dia. steel bar @ 6m long pcs 116 ₱330.00 ₱132.00 ₱53,592.00
12mm dia. steel bar @ 6m long pcs 90 ₱220.00 ₱88.00 ₱27,720.00
b Wall Footing kg 168.00
12mm dia. steel bar @ 6m long pcs 33 ₱220.00 ₱88.00 ₱10,164.00
3
c Tie Beam m 1987.56
16mm dia. steel bar @ 6m long pcs 137 ₱330.00 ₱132.00 ₱63,294.00
10mm dia. steel bar @ 6m long pcs 188 ₱180.00 ₱72.00 ₱47,376.00
d Column kg 7799.31
20mm dia. steel bar @ 6m long pcs 372 ₱510.00 ₱204.00 ₱265,608.00
16mm dia. steel bar @ 6m long pcs 88 ₱330.00 ₱132.00 ₱40,656.00
10mm dia. steel bar @ 6m long pcs 293 ₱180.00 ₱72.00 ₱73,836.00
e Beams kg 6142.36
16mm dia. steel bar @ 6m long pcs 497 ₱220.00 ₱88.00 ₱153,076.00
10mm dia. steel bar @ 6m long pcs 557 ₱180.00 ₱72.00 ₱140,364.00
f Slab kg 3291.36
12mm dia. steel bar @ 6m long pcs 467 ₱220.00 ₱88.00 ₱143,836.00
10mm dia. steel bar @ 6m long pcs 217 ₱180.00 ₱72.00 ₱54,684.00
g. Tie Wire kg 361.46
Gauge 26 G.I. Tie Wire kg 361.46 ₱70.00 ₱28.00 ₱35,422.66
Sub-Total ₱1,127,478.66
2
IV Masonry Works m 512.00 ₱696.69 ₱356,707.23
4" CHB pcs 6528 ₱10.50 ₱4.20 ₱95,961.60
10mm dia. steel bar @ 6m long pcs 345 ₱180.00 ₱72.00 ₱86,940.00
Gauge 26 G.I. Tie Wire kg 16.38 ₱70.00 ₱28.00 ₱1,605.63
Portland Cement bags 350 ₱240.00 ₱96.00 ₱117,600.00
3
Sand m 39 ₱1,000.00 ₱400.00 ₱54,600.00
Sub-Total ₱356,707.23
Ceiling Works (Fiber Cement Board on 2
V m 487.35 ₱566.09 ₱275,883.22
Metal Frame)
4.5mm thk Fiber Cement Board sheets 163.54 ₱545.00 ₱218.00 ₱124,781.22
12mm x 38mm x 5m x 0.8mm thk. Metal
length 545 ₱150.00 ₱60.00 ₱114,450.00
Double Furring Channel
12mm x 38mm x 5m x 0.8mm thk. Metal
length 100 ₱145.00 ₱58.00 ₱20,300.00
Carrying Channel
25 x 25mm x 300mm Wood Vent with insect
pcs 6 ₱280.00 ₱112.00 ₱2,352.00
screen
Consumables lot 1 ₱10,000.00 ₱4,000.00 ₱14,000.00
Sub-Total ₱275,883.22
2
VI Roofing and Structural Steel Works m 84.28 ₱2,068.97 ₱174,372.80
Guage 26 Colored Roof ln.m 120 ₱230.00 ₱92.00 ₱38,640.00
2"x3" C-Purlins @ 6m long length 27 ₱956.00 ₱382.40 ₱36,136.80
2"x6" C-Purlins @ 6m long length 6 ₱1,180.00 ₱472.00 ₱9,912.00

10mm dia. sagrods withstandard turn buckle length 4 ₱135.00 ₱54.00 ₱756.00

Prefabrigated Gauge 26 Metal Gutter ln.m. 8 ₱430.00 ₱172.00 ₱4,816.00


G.I. Flushing ln.m. 8 ₱430.00 ₱172.00 ₱4,816.00
Fiber Cement Fascia Board with Metal
ln.m. 8 ₱450.00 ₱180.00 ₱5,040.00
Frame
4" G.I. Pipe length 7 ₱2,800.00 ₱1,120.00 ₱27,440.00

1 1/2"x1 1/2"x1/4" Angle Bar length 32 ₱420.00 ₱168.00 ₱18,816.00

Miscellaneuous lot 1 ₱20,000.00 ₱8,000.00 ₱28,000.00


Sub-Total ₱174,372.80
2
VII Painting Woks m 1511.35 ₱88.78 ₱134,183.00
Acrylic Latex Paint Primer gal 50 ₱580.00 ₱232.00 ₱40,600.00
Acrylic Gloss Latex Paint gal 50 ₱580.00 ₱232.00 ₱40,600.00
Neutralizer gal 50 ₱400.00 ₱160.00 ₱28,000.00
Concrete Putty gal 4 ₱435.00 ₱174.00 ₱2,436.00
Paint Thinner gal 3 ₱120.00 ₱48.00 ₱504.00
Patching Compound sacks 15 ₱530.00 ₱212.00 ₱11,130.00
Masking Tape rolls 20 ₱48.00 ₱19.20 ₱1,344.00
No.36 Sand Paper sheets 50 ₱85.00 ₱34.00 ₱5,950.00
No.120 Sand Paper sheets 50 ₱32.00 ₱12.80 ₱2,240.00
Paint Roller pcs 5 ₱115.00 ₱46.00 ₱805.00
Paint Brush (No.3) pcs 5 ₱82.00 ₱32.80 ₱574.00
Sub-Total ₱134,183.00
VIII Doors and Windows lot 1.00 ₱235,060.00 ₱235,060.00
1.5mx2.1m Double Swing Panel Complete
set 1 ₱5,500.00 ₱2,200.00 ₱7,700.00
with Accessories
1.0mx2.1m Double Swing Panel Complete
sets 17 ₱3,800.00 ₱1,520.00 ₱90,440.00
with Accessories
0.7mx2.1m Standard PVC Door With
sets 11 ₱2,100.00 ₱840.00 ₱32,340.00
Accessories
1.2mx1.2m Sliding Glass Window on
sets 13 ₱4,200.00 ₱1,680.00 ₱76,440.00
Analok Frame
0.60mx1.2m Fixed Glass Window on Analok
sets 3 ₱1,900.00 ₱760.00 ₱7,980.00
Frame
2.1mx2.2m Pre-fabricated Glass Window on
set 1 ₱400.00 ₱160.00 ₱560.00
Analok Frame
0.60mx0.60m Awning Glass Window on
sets 6 ₱1,100.00 ₱440.00 ₱9,240.00
Analok Frame
1.1mx2.2m Pre-fabricated Glass Window on
sets 1 ₱3,200.00 ₱1,280.00 ₱4,480.00
Analok Frame
Grilled Window (10mmθ Round Bar on
lot 1 ₱4,200.00 ₱1,680.00 ₱5,880.00
Metal Frame)
Sub-Total ₱235,060.00
2
IX Tile Works m 163.54 ₱1,273.90 ₱208,334.00
600mmx600mm Glazed Tiles pcs 400 ₱180.00 ₱72.00 ₱100,800.00
400mmx400mm Glazed Tiles pcs 200 ₱95.00 ₱38.00 ₱26,600.00
400mmx400mm Unlazed Tiles pcs 450 ₱95.00 ₱38.00 ₱59,850.00
Tile Trim pcs 17 ₱180.00 ₱72.00 ₱4,284.00
Portland Cement bags 11 ₱240.00 ₱96.00 ₱3,696.00
Tile Adhesive bags 13 ₱320.00 ₱128.00 ₱5,824.00
Tile Grout kg 5 ₱40.00 ₱16.00 ₱280.00
Consumables lot 1 ₱5,000.00 ₱2,000.00 ₱7,000.00
Sub-Total ₱208,334.00
X Eletrical Works lot 1.00 ₱131,376.00 ₱131,376.00
2
3.5mm TW Copper wire box 2 ₱4,800.00 ₱1,920.00 ₱13,440.00
2
5.5mm TW Copper wire box 2 ₱6,200.00 ₱2,480.00 ₱17,360.00
20mm dia. PVC conduit corrugated pipe ln. m. 280 ₱100.00 ₱40.00 ₱39,200.00
Convenience Outlet pcs 35 ₱130.00 ₱52.00 ₱6,370.00
Lighting Fixtures set 71 ₱200.00 ₱80.00 ₱19,880.00
Switch pcs 53 ₱180.00 ₱72.00 ₱13,356.00
Circuit Breaker pcs 1 ₱4,000.00 ₱1,600.00 ₱5,600.00
Panel Board pcs 1 ₱4,900.00 ₱1,960.00 ₱6,860.00
4" Junction Box pcs 10 ₱65.00 ₱26.00 ₱910.00
Consumables lot 1 ₱6,000.00 ₱2,400.00 ₱8,400.00
Sub-Total ₱131,376.00
XI Plumbing Works lot 1.00 ₱211,162.00 ₱211,162.00
Water Closet Complete with Accessories set 9 ₱3,800.00 ₱1,520.00 ₱47,880.00
Lavatory Complete with Accessories set 8 ₱2,100.00 ₱840.00 ₱23,520.00
Kitchen Sink Complete with Accessories set 1 ₱3,500.00 ₱1,400.00 ₱4,900.00
4" Stainless Floor Drain pcs 11 ₱300.00 ₱120.00 ₱4,620.00
4" Clean Out pcs 4 ₱120.00 ₱48.00 ₱672.00
Stainless Faucet set 12 ₱350.00 ₱140.00 ₱5,880.00
Shower Complete with Accessories pcs 5 ₱1,200.00 ₱480.00 ₱8,400.00
Bidet Complete with Accessories pcs 9 ₱900.00 ₱360.00 ₱11,340.00
3" P-trap pcs 1 ₱200.00 ₱80.00 ₱280.00
4'' dia. PVC Pipe Length 30 ₱450.00 ₱180.00 ₱18,900.00
3" dia. PVC Pipe Length 10 ₱380.00 ₱152.00 ₱5,320.00
PVC Assorted Fittings for Waste Water Line lot 1 ₱8,000.00 ₱3,200.00 ₱11,200.00
Catch Basin lot 1 ₱10,000.00 ₱4,000.00 ₱14,000.00
Septic Vault complte with Accessories and
lot 1 ₱15,000.00 ₱6,000.00 ₱21,000.00
Manhole Cover
1/2" dia. PVC Pipe Length 35 ₱450.00 ₱180.00 ₱22,050.00
PVC Assorted Fittings for Water Line lot 1 ₱5,000.00 ₱2,000.00 ₱7,000.00
Consumable lot 1 ₱3,000.00 ₱1,200.00 ₱4,200.00
Sub-Total ₱211,162.00
XII Forms and Scaffolding Works lot 1.00 ₱56,000.00 ₱56,000.00
Forms Aand Scaffolds lo1 1 ₱40,000.00 ₱16,000.00 ₱56,000.00
Sub-Total ₱56,000.00
TOTAL COST (MATERIALS + LABOR) = ₱3,804,816.64