Installation Guide
Installation Guide
Installation Guide
CONTENTS
Storage 3
Handling 7
The contractor is responsible for analyzing and eliminating any risks during
Blutop® / Blutop® Vi / Topaz® / Topaz® Vi joint 11
installation (especially the use of personal protective equipment).
Standard joint / Standard Vi / ViLoK® joint 15
1 PREPARE THE STORAGE AREA
Express® New joint / Express® New Vi joint 19
The storage area for pipes, fittings and accessories must be organized for each
Express® joint 23 type of products and also by diameter.
Universal Vi joint 27
Universal Ve joint 29
Standard Ve joint 35
Flanged joint 43
Hydraulic testing 73
2 STORE THE GASKETS
External coating repairs 77 (according to the latest version of ISO 2230)
Internal lining repairs 81 In particular, avoid:
•Removing gaskets from their bags
Repair products 83
•Exposing gaskets to sunlight
Polyethylene sleeve 87 •High storage temperatures
support beam
120 x 80
D
Nail chocks to the support
Always ensure a good tension of the bundle straps. Never lift a bundle beams on the ground
Pb
with hooks or vacuum pads. Use slings that support the bundle from (at the ends and
underneath (the straps used to secure the bundles are not slings and between each pipe). H
45°
are not designed to withstand the load).
45°
Ep
Bundle stack heights Gb
60
(24 pipes/bundle) 6 6 6.3 0.54 0.49 1411 Nail chocks to the end
80
5 6 6.3 0.57 0.42 1148 of each spacer.
(15 pipes/bundle)
100
(15 pipes/bundle) 5 6 6.3 0.67 0.50 1398
125
4 5 6.3 0.65 0.58 1380
NATURAL (12 pipes/bundle)
INTEGRAL 150
(9 pipes/bundle) 3 5 6.3 0.59 0.66 1272
200
(6 pipes/bundle) 3 5 6.3 0.75 0.56 1190
250
(4 pipes/bundle) 2 4 6.3 0.63 0.67 1044
300
(4 pipes/bundle) 2 4 6.3 0.74 0.77 1319
1m D
75 5m
(30 pipes/bundle) 4 6 6.3 0.534 0.564 927
90 1m
(30 pipes/bundle) 3 5 6.3 0.635 0.605 1095
110
3 4 6.3 0.608 0.621 904
BLUTOP (20 pipes/bundle)
TOPAZ 125
(20 pipes/bundle) 3 4 6.3 0.668 0.697 1032
To improve storage safety, add two extra support beams at the ends of
140
(12 pipes/bundle) 3 4 6.3 0.631 0.531 902 the stack as shown above.
160
(12 pipes/bundle) 3 5 6.3 0.626 0.71 825
4 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 5
Storage Handling
6 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 7
Handling Handling
from underneath. L
l
aution! Never lift a bundle with hooks or vacuum pads. The straps
C
used to secure the bundles are not designed to withstand the load.
8 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 9
Blutop / Blutop Vi / Topaz /
Topaz Vi joint
One-piece gaskets Plastic segment gaskets
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment).
1 CLEAN
Carefully clean the inside of the socket, the
spigot and the gasket.
Keep all parts clean until assembly has
been completed.
2 LUBRICATE
Using a clean paintbrush, lubricate the
fitting's gasket groove.
10 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 11
Blutop / Blutop Vi / Topaz / Blutop / Blutop Vi / Topaz /
Topaz Vi joint Topaz Vi joint
4 LUBRICATE 8 CHECK THE POSITION OF THE GASKET
Metal rule
The inserted gasket and the spigot must be lubricated with Blutop lubricant
paste (ref. 214616).
Before deflecting the joint, insert a metal rule into the socket gap and ensure
5 CHECK THE CHAMFER that the depth of penetration is the same around the whole circumference.
PAM metal rule ref: 241031.
If the pipe needs to be cut, chamfer the edge as shown below. After
chamfering the edge, there should not be any sharp edges.
9 INFORMATION
Angular deflection
5 mm mini
Δθ
Δd +6° = +63 cm
20°
0,5 mm mini Δd -6° = -63 cm
Δθ
6 ASSEMBLE
The pipe or fitting must be perfectly centered and aligned with the centerline L
of the installed pipe. Pipes must be connected together while keeping them perfectly aligned with
Refer to the "Assembly equipment" guide. their centerlines.
The joint must only be deflected when fully assembled and before
pressurizing the system.
AXIS AXIS
12 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 13
Standard joint /
Standard Vi / ViLoK joint
Standard gasket Standard Vi / ViLoK gasket
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment).
1 CLEAN
Carefully clean the inside of the socket, the spigot
and the gasket.
Keep all parts clean until assembly has been
completed.
14 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 15
Standard joint / Standard joint /
Standard Vi / ViLoK joint Standard Vi / ViLoK joint
4 MARK THE INSERTION DEPTH 5 LUBRICATE
P P-J mm
(if there is no original marking, i.e. if the pipe Coat:
has been cut or a spigot is used from a different • The exposed surface of the gasket
range). • The pipe chamfer and spigot
Never lubricate the interior of the gasket groove.
Mark the spigot at a distance of P-J mm. Apply a sufficient amount of lubricant paste with a
paintbrush (refer to the quantities table on the next
Caution: failure to adhere to the insertion depth page).
will affect the performance of any angular deflections. Comply with the recommended applications
PAM lubricant
paste
16 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 17
Standard joint / Express New joint /
Standard Vi / ViLoK joint Express New Vi joint
8 INFORMATION Express New joint Express New Vi joint
Cuts and chamfers
DN m (mm) n (mm)
m
60 to 600 9 3
n 700 to 1200 15 5
The contractor is responsible for analyzing and eliminating any risks during
1400 to 1600 20 7 installation (especially the use of personal protective equipment).
Cutting the chamfer
1800 to 2000 23 8
Lubricant paste
1 C
LEAN
Number of boxes for 100 joints Carefully clean the inside of the socket, the spigot
DN No. DN No. DN No. DN No. and the gasket.
60 2 250 4 600 9 1200 24 Keep all parts clean until assembly has been
80 2 300 5 700 13 1400 40 completed.
100 2 350 5 800 15 1500 45
125 2 400 6 900 17 1600 50
150 3 450 6 1000 19 1800 60
200 3 500 7 1100 21 2000 71 2 LUBRICATE
Using a clean paintbrush, lubricate the
Angular deflection inside of the socket, the inside of the gland
Pipes must be connected together while keeping Δθ and the gasket.
Δd
them perfectly aligned with their centerlines. Δθ
Δd
tu
st
Expre
ng
n
- Is
I
ss N
-
Kit de
truz
se
ew V
tape measure or with the template provided.
po
joint
ioni d
verro
DN 15i
de
uillé
DN Lm Δ d (cm) for L
e
Δ θ (°)
i m ontagg io -
tic
0
No
A
11
cm
Ass
60 to 300
e
5 6 52
mb
ly
in
st
B
ru
ct
io
2 cm n
350 to 600
0
18 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 19
Express New joint / Express New joint /
Express New Vi joint Express New Vi joint
Angular deflection
E
NSURE THE CORRECT DEPTH
Values (for guidance only) for a 6-meter pipe from DN 60 to DN 150.
Re-tighten if necessary.
8 1
10 11
Failure to observe the tightening rules could lead to the risk of leaks.
3 6
5 4
12 9
2 7
20 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 21
Express joint
DN ≤ 1200 DN ≥ 1400
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment).
1 CLEAN
Carefully clean the inside of the socket, the spigot
and the gasket.
Keep all parts clean until assembly has been
completed.
2 LUBRICATE
Using a clean paintbrush, lubricate the
fitting's gasket groove and the inside of
the gland.
22 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 23
Express joint Express joint
5 ASSEMBLE
Slide the gasket onto the pipe barrel until
properly seated and bring the gland into L
contact.
Ensure that the gland and gasket are Pipes must be connected together while keeping them perfectly aligned with
perpendicular to the pipe centerline. their centerlines.
Insert the bolts and pre-tighten while keeping
the joint in alignment. The pipe must be deflected after pre-tightening but before final tightening.
12 9
2 7
24 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 25
UNIVERSAL Vi joint
This joint requires the use of UNIVERSAL STANDARD pipes featuring a double
chamber socket to receive the:
•STANDARD gasket, which ensures a watertight seal
•UNIVERSAL Vi locking ring with inserts; the inserts anchor the assembly
during interlocking.
1 CLEAN
Carefully clean the inside of the socket, the spigot,
the gasket and the locking ring.
Keep all parts clean until assembly has been
completed.
A - J mm
J = 20 mm
26 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 27
UNIVERSAL Vi joint UNIVERSAL Ve joint
6 INFORMATION
Angular deflection
Maximum admissible deflection:
DN Δ θ (°) Lm Δ d (cm) for L
80 to 450 3° 5.95 32 Hold the locking ring in place with the mounting wedges.
500 2° 5.97 21
600 2° 5.97 21
Δθ
Δd
Δd
Δθ
28 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 29
UNIVERSAL Ve joint UNIVERSAL Ve joint
DN 250 to 700
Fit the locking ring into its groove by reducing its external diameter using the
appropriate tool.
Tool locking ring Top view
Insert the wedge (sideways) between the end edge of the locking ring.
Twist by 90° to create a gap between the two ends.
Fold down the wedge against the face of the socket.
In both cases, place the opening of the locking ring at the top of the pipe (for 100
3
easier removal). 125
150
4
200
DN 800 to 1600 250
300
Insert a connector at the end of a first 350
segment on the flat side (internal).
400
1
450
Line up a pin (previously covered in
lubricant paste) opposite its groove and 500
point its inclined face like that of the connector.
600
700
PAM lubricant
800 7
paste
900 8
Drive in the pin with a hammer and Ø3.9 mm
punch. 1000 9
10
1200 10
1
To keep the tension evenly balanced in the 1400 10
elastomer connectors, proceed in the specified 7 8
order. 1500 12
5 4
1600 12
3
6
9
2
30 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 31
UNIVERSAL Ve joint UNIVERSAL Ve joint
4 ASSEMBLE Lubricant
paste
7 INFORMATION
The joint must be perfectly aligned during assembly.
Angular deflection
Δθ
50 mm
Δd
Δd
Introduce the spigot in the locking Introduce the spigot fully into the
Δθ
ring and then remove the wedge socket. When the locking ring is open,
(the weld bead is approximately it opens when the weld bead passes
50 mm from the socket). through and then clamps to the barrel.
L
Displacement Δ d
Angular deflection L
DN for L
degree cm m
Check that the locking ring is not partially 100 3° 32
touching the weld bead due to insufficient 125 3° 32
insertion of the spigot or an excessive 150 3° 32
angular deflection. 200 3° 32
Pull on each part of the locking ring with 250 3° 32
the mounting hook to ensure that it is
300 3° 32 5.97
properly positioned.
350 3° 32
400 3° 32
5 EXTEND THE JOINT 450 3° 32
500 2° 21
600 2° 21
700 2° 21
6.89
800 2° 25
900 1.5° 18 6.87
1000 1.2° 15 6.88
Extend the joint by pulling the spigot out of the socket until the locking ring 1200 1.1° 15 8.15
comes into contact with its groove in the socket. 1400 0.8° 10
To do so, use a collar fitted with hydraulic jacks or pull with the bucket of a 8.08
1600 0.5° 7
digger using a suitable textile strap.
32 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 33
Standard Ve joint
Standard gland
The one-piece locking ring is an open ring The locking ring is supplied preassembled
DN80-200 DN250-700 DN800-1200
Segment to be assembled: DN 800 to 1200
punch.
34 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 35
Standard Ve joint Standard Ve joint
1 POSITION THE GLAND AND LOCKING RING 4 POSITION AND CHECK THE GASKET
Slide the gland and locking ring over the weld bead. Wrong Right
Locking
ring
Weld bead
Lubricant
paste
Use a trapezoidal wedge Pass the ring over the weld bead using a crowbar
or similar tool
6 ASSEMBLE
Center and introduce the spigot into
the perfectly aligned socket up to the
line corresponding to "a":
36 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 37
Standard Ve joint TAG /IM joint
B
Insert the bolts and nuts.
Screw by hand until in contact with the gland. L
Tighten the bolts diagonally until the gland touches the socket face. Lip gasket Alveolar
gasket
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment).
Δθ
Δd
Δd
Δθ
38 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 39
TAG /IM joint TAG /IM joint
6 ASSEMBLE Δθ
Δd
Center and introduce the spigot into the perfectly
aligned socket: Δd
P Δθ
(a) Up to the marked line corresponding to "P-J mm"
(b) Up to the area between the white lines (b)
(a)
J mm
Pipes must be connected together while keeping them perfectly aligned with
their axes.
The joint must only be deflected when fully assembled and before
pressurizing the system.
40 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 41
Flanged joint
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment).
1 METAL-REINFORCED GASKETS
Metal reinforcement Metal reinforcement
C
2 CLEAN AND ALIGN THE FLANGES
•Check the appearance and cleanliness of the
flange and flange gasket
•Align the parts to be mounted.
•Leave a large enough gap for the flange gasket
between the two flanges.
42 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 43
Flanged joint Flanged joint
Center the reinforced gasket according to the method specified in the tables: Insert the bolts. 3 6
60 2 7
65
80 Do not exert any tractive force on the junction when
100 tightening the bolts.
125
150
200 5 COMPLY WITH THE TIGHTENING TORQUE VALUES
250
300
The recommended torque values are for greased threads (mechanical
350
400 grease).
450 The bolts are only tightened to compress the reinforced gasket and not exert
500 any tractive force on the pipeline elements.
600
700 Metal-reinforced gasket
800 Bolt tightening torque values for flanges
900
1000 DN PN 10 PN 16 PN 25 PN 40 PN 63
1100 daN.m daN.m daN.m daN.m daN.m
1200
40 4 4 4 4 4
1400
1500 50 4 4 4 4 4
1600 60 4 4 4 4 6
1800 65 4 4 4 4 6
2000
80 4 4 4 4 6
Gasket resting on Pins resting on the 100 4 4 6 6 8
Visual centering
the bolts lower bolts 125 4 4 8 8 12
Overmolded gaskets DN ≤ 300 150 6 6 8 8 15
200 6 6 8 12 18
250 6 8 12 15 18
300 6 8 12 15 18
350 6 8 15 18 30
400 8 12 18 30 40
450 8 12 18 30
500 8 15 18 40 50
600 12 18 30 50
Clipped gaskets DN > 300
700 12 18 40 60
800 15 30 50
900 15 30 50
1000 18 40 60
1100 18 40 60
1200 30 50 60
1400 40 50 70
1500 40 60 70
1600 50 60 70
1800 50 60 80
2000 50 70 80
44 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 45
Flanged joint Assembly equipment
The contractor is responsible for analyzing and eliminating any risks during
6 SOCKET DIMENSIONS installation (especially the use of personal protective equipment).
PN 10 PN 16 PN 25
DN
40
Bolt
M16
Socket
24
Bolt
M16
Socket
24
Bolt
M16
Socket
24 1 CROWBAR
50 M16 24 M16 24 M16 24
60 M16 24 M16 24 M16 24
Pipes and fittings - DN 125
E
65 M16 24 M16 24 M16 24 LIN
ER
80 M16 24 M16 24 M16 24 NT
CE
100 M16 24 M16 24 M20 30
125 M16 24 M16 24 M24 36
IN
E
150 M20 30 M20 30 M24 36 RL
NTE
200 M20 30 M20 30 M24 36 CE
46 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 47
Assembly equipment Assembly equipment
pipe.
MAX. 335 DaN D
Pull the lever as shown in [D] and
Comply with the insertion depth assemble while ensuring that the fitting
(or pipe) is aligned with the centerline.
AXE
Blutop / Topaz pipes and fittings DN 75, 90, 110, 125, 140, 160
Attach the collar to the spigot.
Pre-tighten with a spanner. Deflect after assembly if necessary (maximum deflection of 6°).
Position the cams by turning them towards
the spigot.
Attach the collar to the pipe's socket.
Bring the two half-collars together, so that the Check that the gasket is properly positioned
junction between both parts is located by the using the metal rule supplied in the Blutop or
pipe's assembly crown. Topaz joint box.
Pre-tighten with a size 4 hex key.
Connect the collar links to the cams on the
barrel collar.
Use the levers to tension the assembly.
Once the collars are correctly positioned, tighten as necessary.
Position the two levers on the cam nuts of the barrel collar as shown. Pull both
levers together at the same time.
Join the pipes according to the depth lines indicated on the spigot of each
pipe.
48 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 49
Assembly equipment Assembly equipment
Pipes and fittings with non-restrained joints or anchored joints Ratchet chain winches
(Blutop Vi, Standard Vi and Universal Vi)
Maximum service
Reference
load
Pull lift or ratchet
chain winch
250 265417
750 265418
1500 158511
3000 158513
6000 158518
DN
Pipe / Pipe Pipe / Fitting 4 ACCESSORIES
Ratchet chain Number Ratchet chain Number
Blutop / Topaz Flat textile straps
winch winch
WITH FLAT STRAPS 2t Chain length 2m
125 750 kg 1 750 kg 1 Color Max. load Length Reference
140 -- -- 250 kg 2
150 750 kg 1 750 kg 1 Purple 1.5 t 2m 158511
160 -- -- 250 kg 2 2m 158512
Green 2t
200 1500 kg 1 1500 kg 2 8m 158380
250 1500 kg 1 1500 kg 2 3m 158514
300 1500 kg 2 1500 kg 2 Yellow 3t 4m 158515
350 1500 kg 2 1500 kg 3 5m 158516
WITH FLAT STRAPS 3t Chain length 3m 5m 158517
Gray 4t
400 1500 kg 2 1500 kg 3 8m 219996
450 1500 kg 2 1500 kg 3 Red 5t 6m 158388
500 1500 kg 2 1500 kg 3 Brown 6t 5m 158519
600 3000 kg 2 1500 kg 3 4m 158383
700 3000 kg 2 3000 kg 2 6m 199148
Blue 8t
800 3000 kg 2 3000 kg 2 7m 199201
WITH FLAT STRAPS 6t Chain length 5m 10 m 158520
900 6000 kg 2 6000 kg 3 To recognize the straps, count the number of seams
1000 6000 kg 2 6000 kg 3 (e.g. 3 seams = 3 t).
1100 6000 kg 2 6000 kg 3
1200 6000 kg 2 6000 kg 3 Hooks for connecting pipes
WITH FLAT STRAPS 8t Chain length 6m
1400 6000 kg 3 6000 kg 3 DN Visual Reference
1500 6000 kg 3 6000 kg 3
60 to 300 158 021
1600 6000 kg 3 6000 kg 3
1800 6000 kg 3 6000 kg 3
2000 6000 kg 3 6000 kg 3 350 to 600 158 025
These values are provided for guidance only and may vary according
to the installation conditions (temperature, lubrication, assembly of cut 700 to 1200 158 026
sections, etc.).
1400 to
158 605
2000
50 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 51
Assembly equipment Pipe cutting
The contractor is responsible for analyzing and eliminating any risks during
5 DIGGER BUCKET DN 125 AND OVER installation (especially the use of personal protective equipment).
Insert a wooden batten between the bucket and the pipe.
1 EQUIPMENT AND TOOLS REQUIRED
•Gloves, protective mask and goggles
•Brush, abrasive paper and cutter
•Paintbrushes, roller
•Gas burner
52 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 53
Pipe cutting Pipe cutting
|ZMU PIPES
Draw the cutting marks (L) according to the following table:
DN ≥ 700: use a compressed air saw (e.g. FEIN) with
a special attachment for chamfering the pipe.
DN 80 100 125 150 200 250 300 350 400 500 600 700
5 CUTTING SPECIAL COATINGS TYT / STD
/ TYT-SIT
|TT PE AND PLUS/ L 95 100 105 110 115 120 130 145 225
TT PUX PIPES STD VI
CPe UNIVERSAL L 130 155 170 165 170 180 195 225 190 215 230 265
Draw the cutting marks (CPe) according to the following table: Cut away the cement without damaging the iron.
STANDARD TT pipe UNIVERSAL TT pipe You can use a special disc with a 5 mm shoulder
DN (ref.185104).
mm mm
60 and 80 95 NK
100 100 NK
125 and 150 105 NK
Preheat the area between the cuts
200 and 250 115 NK
in the cement coating. Max 50°C.
300 120 NK
Create a lengthwise cut with a
350 and 400 120 205 chisel.
450 and 500 125 225
600 and 700 NK NK
54 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 55
Pipe cutting Pipe cutting
|ISOPAM PIPES
Draw the cutting area according to the following table: For Blutop and Topaz pipes, remember to use the bluCut machine,
which is capable of cutting and chamfering the pipe at the same time.
DN Insulation to be removed A (mm) DN Insulation to be removed A (mm)
100 97 300 130
125 100 350 148
150 103 400 150
200 109 500 155
250 108 600 Contact us
Cut the polyethylene coating and insulation (be careful not to cut into the iron).
Remove the insulation and properly clean the spigot.
56 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 57
Pipe cutting Pipe cutting
58 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 59
Locking weld bead on site
1 REQUIRED EQUIPMENT
•Electric welding machine with a minimum capacity of 150 amperes.
•Electric or pneumatic grinder.
•Copper guide in accordance with the table on the next page.
•Recommended electrodes: ferro-nickel electrodes - Ø3.2 mm Solid wire: FeNi
alloy with 55% Ni according to ISO 1071. Electrode grades are available as SC
Ni Fe1 and SC Ni Fe2.
•Ref. 158179 5 kg box of electrodes (160 electrodes).
2 SURFACE PREPARATION
Draw the position of the bead using the copper
guide while complying with dimension a.
60 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 61
Locking weld bead on site Locking weld bead on site
62 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 63
Anchor blocks
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment).
All the values contained in this document are provided by SAINT-GOBAIN
PAM for guidance only. They are no substitute for carrying out prior studies or
enlisting the services of a consultant.
1 CONSTRUCTION RECOMMENDATIONS
The concrete anchor blocks presented hereinafter have been designed for the
most frequently encountered types of soil and laying conditions.
If the laying conditions are not covered by the following tables, contact
SAINT-GOBAIN PAM.
64 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 65
Anchor blocks Anchor blocks
66 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 67
Anchor blocks Anchoring
3 HYDRAULIC THRUST
Thrust F = test P x f (1 bar)
4 SOIL CHARACTERISTICS Anchoring is recommended in case of space constraints (urban areas) or non-
cohesive soils.
The values below are those generally accepted for soil characterization. They
are no substitute for actual site or laboratory measurements.
The length to be anchored does not depend on the anchoring joint used.
Dry / wet Submerged
Soil type φ γ φ γ The length to be anchored depends on the pipe's type of external coating:
degrees t/m3 degrees t/m3 •Usual coatings: BioZinalium, Zinalium or Zinc
Fragmented rock 40 2 35 1.1 •Special coatings: Standard TT, PUX, ZMU or PE sleeve
Gravel, sands 35 1.9 30 1.1
Length L to be anchored according to the diagrams below:
Gravel, sands
30 2 25 1.1
Silts / clays
Silts / clays 25 1.9 15 1.1
L
Humus L
15 1.5 no mean characteristics L
Organic clays / silts F F
Anchored joint F
φ: soil internal friction angle Blank flange
Tee
γ: soil density
(standard geotechnical data) L
Bend
2 ANCHORING PRINCIPLE
68 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 69
Anchoring Anchoring
4 ANCHORING LENGTHS
hydraulic
Assumptions for the calculation:
thrust on
the joint •Internal friction: φ = 30°
•Soil strength: σ = 0.6 daN/cm2
soil/pipe
•Mass density: γ = 2t / m3
friction •No groundwater
length to be
anchored Usual coatings:
•BioZinalium, Zinalium or Zinc
The technique involves anchoring joints over a sufficient length L on both
sides of a bend so as to harness the friction forces (f) between the anchored Anchoring lengths (in m) calculated with the above assumptions
sections (L) and the soil to withstand the hydraulic thrust (F). Blank flange,
Joint type 1/4 bend 1/8 bend 1/16 bend 1/32 bend valve or tee
3 SOIL CHARACTERISTICS Height of cover
(m)
1 1.5 2 1 1.5 2 1 1.5 2 1 1.5 2 1 1.5 2
The values below are those generally accepted for soil characterization. They
are no substitute for actual site or laboratory measurements. Test
DN pressure Lengths to be anchored (m)
Dry / wet Submerged 10 4.6 3.1 2.4 2.9 1.9 1.5 1.6 1.1 0.8 0.8 0.6 0.4 5.8 4.0 3.0
60 16 7.3 5.0 3.8 4.6 3.1 2.3 2.6 1.7 1.3 1.4 0.9 0.7 9.4 6.4 4.8
Soil type φ γ φ γ 25 11.5 7.8 5.9 7.1 4.8 3.7 4.0 2.7 2.1 2.1 1.4 1.1 14.6 9.9 7.5
degrees t/m3 degrees t/m3 10 5.8 4.0 3.0 3.6 2.5 1.9 2.0 1.4 1.0 1.1 0.7 0.6 7.4 5.0 3.8
Fragmented rock 40 2 35 1.1 80 16 9.3 6.3 4.8 5.8 3.9 3.0 3.2 2.2 1.7 1.7 1.2 0.9 11.8 8.1 6.1
Gravel, sands 35 1.9 30 1.1 25 14.5 9.9 7.5 9.0 6.1 4.7 5.1 3.4 2.6 2.7 1.8 1.4 18.5 12.6 9.5
10 7.0 4.7 3.6 4.3 2.9 2.2 2.4 1.7 1.3 1.3 0.9 0.7 8.9 6.0 4.6
Gravel, sands 100 16 11.1 7.6 5.8 6.9 4.7 3.6 3.9 2.6 2.0 2.1 1.4 1.1 14.2 9.7 7.3
30 2 25 1.1
Silts / clays 25 17.4 11.9 9.0 10.8 7.4 5.6 6.1 4.1 3.1 3.2 2.2 1.7 22.1 15.1 11.5
Silts / clays 25 1.9 15 1.1 10 8.4 5.8 4.4 5.2 3.6 2.7 2.9 2.0 1.5 1.6 1.1 0.8 10.7 7.3 5.6
125 16 13.5 9.2 7.0 8.4 5.7 4.3 4.7 3.2 2.4 2.5 1.7 1.3 17.2 11.7 8.9
Humus 25 21.1 14.4 10.9 13.1 8.9 6.8 7.3 5.0 3.8 3.9 2.7 2.0 26.8 18.3 13.9
15 1.5 no mean characteristics
Organic clays / silts 10 9.9 6.8 5.1 6.1 4.2 3.2 3.4 2.4 1.8 1.8 1.2 0.9 12.6 8.6 6.5
150 16 15.8 10.8 8.2 9.8 6.7 5.1 5.5 3.8 2.9 2.9 2.0 1.5 20.1 13.8 10.5
φ: soil internal friction angle 25 24.7 16.9 12.9 15.3 10.5 8.0 8.6 5.9 4.5 4.6 3.1 2.4 31.4 21.5 16.4
γ: soil density 10 12.7 8.7 6.7 7.9 5.4 4.1 4.4 3.0 2.3 2.3 1.6 1.2 16.2 11.1 8.5
(standard geotechnical data) 200 16 20.3 14.0 10.7 12.6 8.7 6.6 7.1 4.9 3.7 3.8 2.6 2.0 25.9 17.8 13.6
25 31.8 21.9 16.7 19.7 13.6 10.4 11.1 7.6 5.8 5.9 4.0 3.1 40.4 27.8 21.2
10 15.4 10.7 8.1 9.6 6.6 5.1 5.4 3.7 2.8 2.8 2.0 1.5 19.6 13.6 10.4
250 16 24.6 17.0 13.0 15.3 10.6 8.1 8.6 5.9 4.5 4.5 3.1 2.4 31.3 21.7 16.6
25 38.5 26.6 20.4 23.9 16.5 12.7 13.4 9.3 7.1 7.1 4.9 3.8 49.0 33.9 25.9
10 18.0 12.5 9.6 11.2 7.8 6.0 6.3 4.4 3.3 3.3 2.3 1.8 22.9 15.9 12.2
300 16 28.8 20.0 15.4 17.9 12.4 9.5 10.0 7.0 5.3 5.3 3.7 2.8 36.6 25.5 19.6
25 45.0 31.3 24.0 27.9 19.4 14.9 15.6 10.9 8.4 8.3 5.8 4.4 57.2 39.8 30.6
10 20.5 14.4 11.0 12.7 8.9 6.9 7.1 5.0 3.8 3.8 2.7 2.0 26.1 18.3 14.1
350 16 32.8 23.0 17.7 20.4 14.3 11.0 11.4 8.0 6.1 6.1 4.2 3.3 41.8 29.2 22.5
25 51.3 35.9 27.6 31.9 22.3 17.1 17.9 12.5 9.6 9.5 6.6 5.1 65.3 45.7 35.1
10 23.0 16.1 12.4 14.3 10.0 7.7 8.0 5.6 4.3 4.2 3.0 2.3 29.3 20.5 15.8
400 16 36.8 25.8 19.9 22.8 16.0 12.4 12.8 9.0 6.9 6.8 4.8 3.7 46.8 32.9 25.3
25 57.5 40.3 31.1 35.7 25.1 19.3 20.0 14.0 10.8 10.6 7.5 5.7 73.1 51.4 39.6
70 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 71
Anchoring Hydraulic testing
Spoil
2/3 L
L
72 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 73
Hydraulic testing Hydraulic testing
Calculate the volume of water Pressurizing the pipe compresses the temporary end restraints. If necessary,
use screw jacks to compensate for any compression.
Calculation for the volume of water in m3
Thrust F
Block the ends of the test section with blank flanges equipped with valves
for water filling and air venting.
Upper end
Absorb the forces using timbers laid across the trench or by sheet piling (also
provide lateral restraints).
Avoid using the end of a previously laid and hydraulically tested pipe section
Air vent Test pump as a buttress.
2 Checking filling
Any air in the main must be completely removed.
4 Check that the air valves are functioning.
1 Open the wash-out valves to check the arrival of water.
8 3 PRESSURE TEST
3
Thrust F With the pipes completely filled, slowly increase the pressure until the planned
7 5 6 test pressure is reached.
7
Keep a constant eye on the restraints
Flush out the main thoroughly to remove any foreign bodies trapped during
laying.
74 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 75
External coating repairs
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment).
76 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 77
External coating repairs External coating repairs
5.2 Moderate damage In case of major damage to the PUX coating, follow procedure 5.1 in the
previous chapter.
Repair kit ref. 111216 comprising abrasive
paper, mastic and a repair strip.
78 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 79
External coating repairs Internal lining repairs
The contractor is responsible for analyzing and eliminating any risks during
7 PIPES WITH A CEMENT EXTERNAL COATING installation (especially the use of personal protective equipment).
For all mixtures of resins and hardeners, you must comply with the
specified proportions.
Prepare the affected surface by removing the
damaged and loose mortar.
1 EQUIPMENT AND TOOLS REQUIRED
•Gloves, protective mask and goggles
•Brush, abrasive paper and cutter
•Spatula, mastic knife
Brush to remove any dirt or loose particles and •Paintbrushes, roller
then clean the surface. •Gas burner
2 P IPES WITH A CEMENT INTERNAL
LINING (DRINKING WATER AND SEWAGE): Natural,
Integral, Classic (all versions).
Prepare the ZMU repair kit (DN 80 to 600: ref. Prepare the SIKADUR 31DW mixture (ref.
218842). 158009) with three parts R (resin) and one part
H (hardener). Mix to an even consistency.
•Mix the dry components
Preferably position the area to be repaired facing
•Add the liquid while stirring vigorously
downwards.
•Leave for five minutes and then mix again
Remove any damaged and loose mortar.
Clean until spotless.
Dampen the surface. Apply the mixture and compact to ensure the
correct thickness.
Smooth the surface.
Fill with mortar using a spatula and then For a socket without a cement lining, use:
smooth the surface. - NATURAL: NatZinc ref. 251222 (5 kg dose) FINISHING
and then Aquacoat (0.75 kg dose) ref. 240991
- CLASSIC and STANDARD TT: NatZinc ref.
251222 (5 kg dose) and then Endolac (1 kg
dose) ref. 158134
- INTEGRAL and INTEGRAL TT or PUX: NatZinc
(DN ≥ 700: ref. 158009)
ref. 251222 (5 kg dose) and then Eurokote (1
Prepare the SIKADUR 31DW mixture with three parts R (resin) and one part H kg dose) ref. 236283
(hardener). Mix to an even consistency.
Preferably position the area to be repaired facing downwards. 3 PIPES WITH A DUCTAN AND
Remove any damaged and loose mortar. EPOXY INTERNAL LINING
Clean until spotless. (DRINK. WATER AND SEWAGE):
Apply the mixture and compact to ensure the correct thickness. Blutop, Topaz, Tag32.
Smooth the surface.
Deburr the edges of the damaged area with a
cutter.
Minimum application temperature: + 5°C. Sand and clean the damaged area.
Apply the Eurokote 4820 mixture to the
damaged area with a paintbrush.
Cover with plastic film or a damp cloth to •Blutop: ref. 158255 (1 kg dose) or 220815
maintain a high level of humidity and ensure (five 50 ml syringes)
that the mixture sets properly. •Topaz: ref. 184653 (1 kg dose) or 220817
Optimal drying time: 2 hr 30 min. (five 50 ml syringes)
•Tag32: ref. 184653 (1 kg dose) or 220817
(five 50 ml syringes)
Allow to dry.
80 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 81
Internal lining repairs
Allow to dry.
For a socket without a polyurethane lining, use:
- NATURAL PUR: ref. 158255 (1 kg dose) or 220815 (five 50 ml syringes)
- INTEGRAL pH1: ref. 184653 (1 kg dose) or 220817 (five 50 ml syringes)
Allow to dry.
Comply with the recommended applications specified in the safety data sheets
available in the Downloads section on www.pamline.com.
82 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 83
Repair products Repair products
The contractor is responsible for analyzing and eliminating any risks during TT PUX range - DN 800 to 2000
installation (especially the use of personal protective equipment).
area ref. product packaging
1 DRINKING WATER AND SEWAGE PIPES & FITTINGS ➀ exterior 185005
EUROKOTE 4820
Ivory 1 kg dose (R80%+H20%)
3 2
EUROKOTE 4820
➀ exterior 220818 Kit of five 50 ml syringes
Ivory
BLUTOP range - DN/OD 75 to 160 C25
ISO 2531
EN 545
EN 15189
Ivory
2 ➁ interior EUROKOTE 4820
EUROKOTE 4820 1 kg dose (R80%+H20%) 220818 Kit of five 50 ml syringes 1
➀ exterior 158255 Ivory
Blue
EUROKOTE 4820
➁ interior 158255 Blue 1 kg dose (R80%+H20%) CLASSIC PUR range - DN 800 to 2000
1
area ref. product packaging
CLASSIC range - DN 700 to 1200
➀ exterior 251222 NATZINC 5 kg dose (R90%+H10%)
3 2 3 2
area ref. product packaging ➂ interior 265365 AQUACOAT 0.75 kg box
socket CLASSIC PLUVIAL
➀ exterior 251222 NATZINC 5 kg dose (R90%+H10%)
185005 EUROKOTE 4820
➂ interior AQUACOAT 1 kg dose (R80%+H20%)
Ivory
ISO 2531
➁ interior
Standard ISO2531
socket PLUVIAL
220818 EUROKOTE 4820
1 Kit of five 50 ml syringes
➁ interior 158009 SIKADUR 31 DW 6 kg kit (R75% + H25%) Ivory 1
ISO 2531
C30 EN 14628
UNIVERSAL TT PE
84 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 85
Repair products Repair products
TOPAZ range - DN 75 to 160
2 SEWAGE PIPES AND FITTINGS area ref. product packaging
➁ cut
BioZinalium C25
INTEGRAL
BioZinalium
DN600
Standard
EN598
ISO7186 ➂ interior 158255 Eurokote 4820 blue 1kg dose (R80%+H20%)
➁ interior 158009 SIKADUR 31 DW 6 kg dose (R75% + H25%)
251222 NATZINC 5 kg dose (R90%+H10%) 1 INTEGRAL and TOPAZ fittings (all versions) - DN 75 to 2000
➂ int. and
ext. spigot 240990 AQUACOAT 0.75 kg dose area ref. product packaging
184653 EUROKOTE 4820 1 kg dose (R80%+H20%)
red brown
INTEGRAL pH1 range - DN 150 to 2000
2
➀ exterior EUROKOTE 448
220817 Kit of five 50 ml syringes
Red Brown
area ref. product packaging
184653 EUROKOTE 4820 1 kg dose (R80%+H20%) 1
➁ interior 158009 SIKADUR 31 DW 6 kg dose (R75% + H25%) TAG 32 BioZinalium range - DN 150 to 300
251222 NATZINC 5 kg dose (R90%+H10%)
➂ int. and 1 3 area ref. product packaging
ext. spigot 236283 EUROKOTE 448
Red Brown 1 kg dose (R80%+H20%)
251222 NATZINC 5 kg dose (R90%+H10%)
➀ exterior AQUACOAT Red 0.75 kg dose
240990
INTEGRAL TT PUX range - DN 150 to 2000 EUROKOTE 4820
3 2
Red Brown
459
BENOR
1 kg dose (R80%+H20%) 3 2
Ivory EUROKOTE 4820
1
Comply with the recommended applications specified in the safety data sheets
available in the Downloads section on www.pamline.com.
86 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 87
Polyethylene sleeve Polyethylene sleeve
General instructions Sleeving the barrel
The process of fitting a PE sleeve involves applying a continuous barrel sleeve
(outside the trench) and subsequently a joint sleeve (at the bottom of the NATURAL, INTEGRAL (ZINALIUM + BIOZINALIUM), ZMU, STANDARD
trench). TT and INTEGRAL TT pipes do not require sleeves.
•Pipes must be clean and dry (no soil entrapped between the pipe and sleeve).
•The pipe bed and backfill must not contain any stones or fragmented rock
that could damage the sleeve during laying or in service (soil load).
1 SLIDE
Before lowering into the trench, lift the pipe in the middle (refer to the
SPECIAL INSTRUCTIONS "Handling" guide) and slide the pleated barrel sleeve over the spigot.
2 UNFOLD
DETAIL 1 Since the pipe is supported by two battens, spread the barrel sleeve over the
Barrel sleeve full length of the pipe and carefully wrap the sleeve tightly around the pipe
Carefully apply the PE sleeve so that it is tight (the PE sleeve must not billow).
against the pipe. Fold the sleeve at the top.
3 FASTEN
Secure the fold down with adhesive tape.
Fix the ends of the sleeve to the pipe barrel with adhesive tape overlapping
both the barrel and the sleeve (around the full circumference).
Add fasteners (plastic-coated steel wire) every 1.5 m.
Slip on the joint sleeve.
4 ASSEMBLE
DETAIL 2
Joint sleeve Lower the pipe into the trench.
STANDARD joint Join the pipe. The fold must always be positioned at the top the pipe.
Carefully fit the joint sleeve closely around
the junction and overlap the barrel sleeves Joint sleeve Adhesive tape
WRAP
Fastener
(upstream and downstream). 5
Barrel sleeve Adhesive
Secure with a fastener as close as possible Bring the joint sleeve over the socket and spigot.
to the gland (EXPRESS joint) or socket
face (STANDARD joint).
Make sure that you create a large enough gap under the pipe to easily
Fix the ends with adhesive tape EXPRESS joint fit the sleeve (and secure with adhesive tape and fasteners) - see
overlapping the barrel sleeve and joint Plastic-coated
Joint sleeve Adhesive tape diagrams.
sleeve. fastener
88 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 89
Polyethylene sleeve Polyethylene sleeve
Sleeving the barrel Sleeving the joint
The contractor is responsible for analyzing and eliminating any risks when
installing the PE sleeve (especially the use of personal protective equipment). 1 PULL
Pull the joint sleeve over the spigot and socket. Make sure that you create
1 a large enough gap under the pipe to easily fit the sleeve (and secure with
Barrel sleeve
adhesive tape).
Ground
Gap
2 2 FIX
Fold the joint sleeve over and wrap as tightly as possible, overlapping the
Ground adjoining barrel sleeves (the fold must always be positioned at the top).
Secure with adhesive tape as close as possible to the gland (STANDARD Ve or
EXPRESS joint) or socket face (STANDARD or UNIVERSAL joint).
Fix the ends on the adjoining barrel sleeves with adhesive tape wrapped
3 Adhesive Plastic-coated fastener around the whole circumference to make a watertight overlap.
Standard Ve or EXPRESS joint Standard or UNIVERSAL joint
Plastic-coated Adhesive Adhesive
fastener Joint sleeve tape Fastener Joint sleeve tape
Barrel
Adhesive
Ground Barrel
sleeve Adhesive
sleeve
4
Joint sleeve Joint sleeve 3 ASSEMBLE
Ground Successive assembly of barrel and joint sleeves must form a continuous
protection.
Ground
Gap
5 Ground Lj
50 mm adhesive tape
w (width
when flat)
Lf
L Plastic-coated steel
fastener Ø 24/10
90 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 91
Polyethylene sleeve Preparing the barrel and joint
Sleeving fittings sleeves
Use the same polyethylene sleeve to protect fittings. 50 mm adhesive tape
Lj
Polyethylene sleeves must be fitted according to the same recommendations
(in particular, the polyethylene sleeve must be wrapped around the pipe as
tightly as possible).
w (width
when flat)
Bend
Lf
L Plastic-coated steel
fastener Ø 24/10
Adhesive tape
92 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 93
Ovality correction Ovality correction
DN 200 to 700 DN 200 to 700
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment). 4 CHECK
Check that the spigot is perfectly round.
Using a circometer, ensure that the outer diameter complies with the following
Ensure that the procedure has not damaged the cement lining.
values:
Outside diameter OD (mm) 5 ASSEMBLE
DN
Nominal value Limit deviations
200 222 + 1 / -3.0 With the device still in position, assemble the joint.
The nuts must be kept tight while mounting the joint to compensate for any
250 274 + 1 / -3.1
elastic deformation in the pipe.
300 326 + 1 / -3.3
350 378 + 1 / -3.4
In case of a small diameter pipe, you can rotate the bars using the
400 429 + 1 / -3.5 adjustable pads.
450 480 + 1 / -3.6
500 532 + 1 / -3.8
600 635 + 1 / -4.0
700 738 + 1 / -4.3
Excerpt from EN 545 - Table 15
However, pipes may become oval-shaped due to transportation and handling,
meaning that fittings cannot be assembled correctly.
Ovality (%)
2 FIT
Fit the tackle according to the diagram.
The tackle can be set up 50 cm from the end
of the pipe so that sleeves can be fitted.
3 TIGHTEN
Tighten the nuts by hand so that the tackle
is stable.
With a size 30 spanner, tighten the nuts on
the rods alternately and gradually.
94 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 95
Ovality correction Ovality correction
DN ≥ 800 DN ≥ 800
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment). 3 ADJUST
Adjust the support according to the diameter.
TACKLE ref. 225018 (DN 800 to 1000) – ref.
158333 (DN 1200 to 2000)
•Hydraulic jack
4 OPERATE
•Adjustable support Operate the jack and check that the spigot is perfectly round.
5 CHECK
Using a circometer, ensure that the outer diameter Ensure that the procedure has not damaged the cement lining.
complies with the following values:
Outside diameter OD (mm) 6 ASSEMBLE
DN
Nominal value Limit deviations With the device still in position, assemble the joint.
800 842 + 1 / -4.5
900 945 + 1 / -4.8
1000 1048 + 1 / -5.0
1100 1152 + 1 / -6.0
1200 1255 + 1 / -5.8
1400 1462 + 1 / -6.6
1500 1565 + 1 / -7.0
1600 1668 + 1 / -7.4
1800 1875 + 1 / -8.2
2000 2082 + 1 / -9.0
Ovality (%)
2 POSITION
Position the parts according to the diagram
dm
DM
96 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 97
Dismantling joints Dismantling joints
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment). 3 POSITION THE EXTRACTOR SHIMS
Slide the first shim into the slot in the anvil.
|STANDARD Vi, UNIVERSAL Vi AND
BLUTOP Vi
1 REQUIRED EQUIPMENT
Ref. Steel Number
Ref. anvil
DN 1
shim of shims
Coat the exposed part of the shim with lubricant
2 required
paste (both sides).
Standard Vi and UNIVERSAL Vi
60 3
80 110680 4
100 5
125 110681
6
150 7
200 9 Place the shim + anvil in the annular space.
250 110682
11 The large side of the shim must be in contact with the
300 13 joint.
350 15
400 110683 16 •Gloves, goggles, safety shoes
450 18 •Brush, cloth
500 19 •Lump hammer
600 23 •Lubricant paste
700 27
Blutop Vi •Textile straps Gradually drive the shim between the joint and the
75 3 pipe.
90 110680 4
110 110 682
4 Keep the shim flat against the pipe barrel if necessary.
125 5
140 110681 5
160 6
2 PREPARATION
Repeat all the way round the joint for the other
Rinse with water and brush the joint. shims.
Clean the annular space as much as possible.
Push the spigot fully into the socket to Overlap the shims by approximately 4 to 5 mm.
release the inserts. The final shim can be slipped beneath the first shim.
98 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 99
Dismantling joints Dismantling joints
Under no circumstances must the dismantled Standard Vi / Push the spigot fully into the socket to
Universal Vi / Blutop Vi joint be reused. release the locking ring.
Number 3 4 4 5 14 16 18 20 20 24 24 Repeat all the way round the joint for the other
shims.
•Gloves, goggles, safety shoes
•Brush, cloth
•Lump hammer
•Lubricant paste
•Textile straps
DN 350 to DN 700
Insert shims between the metal locking ring and
the pipe, starting at opposite ends of the open
ring.
100 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 101
Dismantling joints
DN 800 to DN 1600
Introduce the extractor shims between the pipe
and the metal locking ring (one shim at the end
of each segment).
102 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 103
Repairing pipes Repairing pipes
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment). 2 BROKEN PIPE (NON-ANCHORED SECTION)
ULTRALINK, LINK GS, ULTRAQUICK, QUICK GS, EXPRESS
1 PIERCED PIPES COUPLINGS
Repair collar •Carefully remove the soil around the existing
pipeline.
Longitudinal fracture ≤ 35% of the collar
•Use a circometer to check the pipe's diameter.
Circumferential fracture ≤ 10 mm
•Cut out the damaged area of the existing pipe
(refer to PIPE CUTTING).
•Clean the part of the pipe that needs to be •Remove the damaged section.
repaired.
•Check the length before creating the replacement
•Fit the collar around the damaged section. section UU while allowing for an admissible gap:
•Ensure that the gasket is not folded and mated Length of replacement section UU = C – 2 x J
firmly against the pipe.
•Present replacement section UU with the junction
elements in alignment with the two pipes that
need to be connected.
Lubricate the gasket with soapy water or lubricant paste.
•Position the fittings while creating an equal gap
on each side of the replacement section UU.
•Bring each of the components together and
•Position the opposite end of the collar on top of the gasket. insert the bolts. Check that all parts are perfectly
•Insert the bolts and tighten by hand. positioned.
•Turn the collar in the direction indicated by the arrow on the label.
•Ensure that the damaged section is beneath the vulcanized part of the joint.
•Gradually tighten the nuts until the jaws close together. In case of drinking water systems, all parts must be disinfected before
assembly.
The vulcanized part of the joint must not be deformed, otherwise leaks
could occur.
3 LEAKING JUNCTION (NON-ANCHORED SECTION)
•Carefully remove the soil around the existing pipeline.
Different types of repair collars •Use a circometer to check the pipe's diameter.
•Draw the cutting marks (between 150 and 250 mm):
•Cut and remove the marked section (refer to the PIPE CUTTING guide)
104 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 105
Repairing pipes Repairing pipes
•Free the spigot cut-out and remove the joint: •Cut according to D and then remove the damaged section.
•Insert a new STANDARD JOINT (refer to the STANDARD JOINT guide) in the
socket. A special tool may be required depending on the type of anchored joints (refer
•Draw the marks for the position of the EXPRESS coupling (refer to the to the DISMANTLING ANCHORED JUNCTIONS guide).
EXPRESS JOINT guide). For the section remaining in place: insert the gland,
gasket and coupling:
•Recreate a locking weld bead on each of the two cut sections.
On each of the two ends of the pipe, re-assemble the cut sections fitted with
Standard Ve glands.
4 BROKEN PIPE (ANCHORED SECTION)
•Parts required for the repair:
–1 flanged short pipe
–2 STANDARD socket flanges
–2 flanged joints
–2 STANDARD Ve anchoring kits (gland and locking ring) Present and assemble the two flange sockets.
•Mark the cutting lines according to the following formula:
•Position the flanged short pipe and the two flat joints between the flange
P L P sockets
•
e D e
D (cut length) = L + (2 x e) + (2 x P)
e = 20 mm / L= 250 or 500 mm / P = according to the DN
106 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 107
Repairing pipes
•Install the bolts in the holes and gently tighten (by hand).
•Position the four STANDARD glands and bolts.
Tighten slightly by hand.
•Finally, tighten the flange bolts and then the gland bolts.
Refer to the FLANGE JOINTS guide
Refer to the STANDARD Ve JOINTS guide
108 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 109
Branches for sewage pipes - Branches for sewage pipes -
rectangular hole round hole
Saddle branches 90° saddle branches
1 DRAW 1 BORE
Using the template provided, draw the following on Use a boring machine with a centering
the pipe barrel: >1m base.
•The external rectangular outline of the plate. Bore with a hole saw specifically for iron
•The internal outline of the pipe neck from the saddle (Ø172 mm for 150 branches and Ø232 mm
branch. for 200 branches).
•A rectangle corresponding to the dimensions Lubricate with water.
specified in the following table and positioned
around the circle drawn during the previous step.
Opening dimensions
DN
Length (mm) Width* (mm) 2 PUNCH AND DRILL
200 190 190
250 190 250 Mark the position of the two holes with a
300 240 250 center punch.
400 300 300 Drill a hole with a 13 mm diameter.
500 300 300 Preferably use a drill bit with a tungsten
600 300 300
carbide tip for hardened steel and abrasive
* Cut on the line. Measure on the circumference (circle arc).
materials.
3 REPAIR 4 COAT
Repair the coating on the exposed part of the Coat the exposed parts with ISOLARM
pipe after cutting by applying fast-drying epoxy paste (INTEGRAL, TAG 32) or EUROKOTE
paint with a paintbrush. (INTEGRAL PUX, INTEGRAL pH1).
If necessary, repair the lining.
Product used: ISOLARM protective paste (ref.
179099)
4 ASSEMBLE
Fit the gasket in the housing on the internal face 5 MOUNT THE BOLTS
of the plate.
Lubricate the gasket once seated in its housing. Mount the two bolts with their compressed
Start assembly in the middle of each straight plastic rings in the holes.
section and progressively fit by hand. Use a
mallet if necessary.
Fit the plate to the pipe barrel.
Gradually tighten the bolts, alternating on both sides until the plate is perfectly
in contact with the pipe barrel.
Fit and tighten the stirrups (until the part is in contact with the pipe).
110 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 111
Branches for sewage pipes - Branches for sewage pipes -
round hole round hole
Saddle branches Swivel saddle branches
The contractor is responsible for analyzing and eliminating any risks during
6 POSITION THE GASKET installation (especially the use of personal protective equipment).
Position the gasket A
according to the type of 1 BORE
joint (see diagrams A and
B). Use a boring machine with a centering
Check that the gasket is base and a hole saw specifically for iron
properly seated. B (Ø172 mm for 150 branches and Ø232 mm
for 200 branches).
Lubricate the gasket.
Lubricate with water.
Hole saws that are suitable for iron are marketed by PAM.
5 MOUNT THE BOLTS
DN Ø bore (mm) reference Mount the two bolts with their compressed
150 172 111173 plastic rings in the holes.
200 232 111174
112 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 113
Branches for sewage pipes - Branches for sewage pipes -
round hole round hole
Swivel saddle branches Swivel saddle branches
6 POSITION THE GASKET 9 ASSEMBLE
Position the gasket A
according to the type of Re-mount the upper elements.
joint (see diagrams A and Turn the assembly towards its connection
B). position and hold in place.
Check that the gasket is Fit and tighten the stirrups.
properly seated. B
Lubricate the gasket.
Hole saws that are suitable for iron are sold by PAM.
7 ASSEMBLE
Mount the fully assembled iron part with a
single bolt.
Place a washer and nut on the bolt, but
without tightening.
Finish mounting the iron part. If necessary,
use a wooden lever to avoid damaging
the coating. Gradually apply increasing
pressure and avoid jerky movements.
8 TIGHTEN
Add the second bolt.
114 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 115
Branches for sewage pipes - Branches for sewage pipes -
rectangular hole rectangular hole
Swivel saddle branches Swivel saddle branches
The contractor is responsible for analyzing and eliminating any risks during
installation (especially the use of personal protective equipment). Lubricate the joint once seated in its housing.
Fit the plate to the pipe barrel.
1 DRAW Start assembly in the middle of each straight
section and progressively fit by hand. Use a
Draw the centerline at the top of the pipe using an mallet if necessary.
>1m
angle bar.
Using the template provided, Gradually tighten the bolts, alternating on
draw the following on the pipe both sides until the saddle is perfectly in
barrel. contact with the pipe barrel.
Position the template provided Re-mount the upper elements.
on the top centerline using the Turn the assembly towards its connection
two markings indicated. position and hold in place.
Fit and tighten the stirrups.
2 CUT AND CLEAN
Using a disc cutter, cut the rectangular opening
in the pipe barrel on the inside of the line.
Comply with the centerline of the pipe shown on
the cutting template.
Use a multi-material cutting disc.
Avoid cutting over the line in the corners.
Using a cloth, clean the part of the pipe barrel to
which the plate will be mounted, as well as the
inside of the pipe and the face to be re-coated.
3 REPAIR
Repair the coating on the exposed part of the
pipe after cutting by applying fast-drying epoxy
paint with a paintbrush.
If necessary, repair the lining.
Product used: ISOLARM protective paste (ref.
179099)
4 ASSEMBLE
Unmount the branch so that the plate can first
be fitted.
Fit the gasket in the housing on the internal face
of the plate.
116 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 117
Watch our tutorials and subscribe to our channel:
PamlineTV | Saint-Gobain PAM
Assembly equipment
link to Natural assembly tutorial
Pipe cutting
link to Pipe cutting tutorial
118 Installation guide for drinking water and sewage systems – 2019 Installation guide for drinking water and sewage systems – 2019 119