Faas Pharmaceuticals (PVT.) Limited: Tested On: Mar 13, 2019 Next Due Date: Mar 12, 2020
Faas Pharmaceuticals (PVT.) Limited: Tested On: Mar 13, 2019 Next Due Date: Mar 12, 2020
Faas Pharmaceuticals (PVT.) Limited: Tested On: Mar 13, 2019 Next Due Date: Mar 12, 2020
Performed by
________________
Zaffar
Written By
______________
Iqra Bano
Checked by
________________
Abdul Wahid
Mechanical officer
Approved by
_____________________
Mr. Wajahat
Head of Quality Operations
1 Background 1
2 Objectives 1
3 Documentation 1
4 Verification Of Corrective Action Report 1
5 Washing , Cleaning & Sanitization of entire production 2
6 Environmental Performance Test 2
6.2 Air Flow and Uniformity Test 2
6.2.1 Measurement of Air Volume in Supply and Return Air Ducts 3
6.2.2 Measurement of Differential Pressure 3
6.2.3 Measurement Of Air Changes Per Hour 3
6.3.3 HEPA Filter Leakage Test 4
QUALIFICATION REPORTS OF HVAC SYSTEM, AIR BALANCING
P a g e | 1of 4
1.0 BACKGROUND:
2.0 OBJECTIVE:
3.0 DOCUMENTATION:
Identity numbers of the entire air handling unit (AHU) were
labeled.
All the relevant drawing of HVAC system was checked.
Before starting air balancing , the completion of Corrective Action Report was verified.
QUALIFICATION REPORTS OF HVAC SYSTEM, AIR BALANCING
P a g e | 2of 4
Description:
The air-conditioning system for the Production area consists of the following major component.
Three Air Cool self-contain package units,
Following key elements were considered for implementation and control of air the HVAC system and
air handling (AHU) system in the overall design.
Air flow regime
Filtration
Pressure differential across filters and areas
Temperature
Humidity
6.2 AIR FLOW AND UNIFORMITY TEST
Air Balancing:
P a g e | 3of 4
Acceptance criteria:
Allowable Tolerance for Airflow rate is ± 10% of Designed Volume.
Reading will be taken at 40 in. above the floor in the center of the grid for minimum 15
seconds. (If 40 inch space is not available then the reading will take at height of the false ceiling
and length of diffuser hood)
No object within 10 ft of the anemometer, except fixed equipment.
6.2.2 Measurement of Differential pressure
Acceptance criteria:
Under class 10,000 the system should meet design specification (minimum 0.05 In. w.g.)
Under class 100,000 the system should meet design specification (minimum 0.03 In. w.g.)
QUALIFICATION REPORTS OF HVAC SYSTEM, AIR BALANCING
P a g e | 4of 4
Calculation: