Faas Pharmaceuticals (PVT.) Limited: Tested On: Mar 13, 2019 Next Due Date: Mar 12, 2020

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6

Tested On: Mar 13, 2019 Next Due date: Mar 12, 2020

Performed by

________________
Zaffar

Written By

______________
Iqra Bano

Checked by

________________
Abdul Wahid
Mechanical officer

Approved by

_____________________
Mr. Wajahat
Head of Quality Operations

Report submitted to (client)

FAAS PHARMACEUTICALS (PVT.) LIMITED


F-748L S.I.T.E, KARACHI
Table of Content

S. No. Content Page No.

1 Background 1
2 Objectives 1
3 Documentation 1
4 Verification Of Corrective Action Report 1
5 Washing , Cleaning & Sanitization of entire production 2
6 Environmental Performance Test 2
6.2 Air Flow and Uniformity Test 2
6.2.1 Measurement of Air Volume in Supply and Return Air Ducts 3
6.2.2 Measurement of Differential Pressure 3
6.2.3 Measurement Of Air Changes Per Hour 3
6.3.3 HEPA Filter Leakage Test 4
QUALIFICATION REPORTS OF HVAC SYSTEM, AIR BALANCING

P a g e | 1of 4

1.0 BACKGROUND:

M/s FAAS PHARMACEUTICALS (PVT.) LIMITED has Carried out Air Balancing of Production


area. Production area has designed for the manufacturing of products. Air balancing and
qualification of HVAC system was verified for the compliance of current Good Manufacturing
Practices (cGMP) and all other regulatory obligations.

2.0 OBJECTIVE:

The objectives of this validation report is


 To verify recommended corrective actions report (CAR).
 To validate the HVAC system of microbiological section and production area for the
successful manufacturing the cephalosporin’s sterile and non sterile products.
 To verify that the HVAC, supporting utilities and the circulation pump have been built and
installed in compliance with their design specifications.( IQ)
 To verify that the AHU, supporting utilities and the circulation pump operate in accordance
with their design specifications. (OQ)
 To verify that the AHU specific process will consistently produce a product meeting its
predetermined specifications and quality attributes. (PQ)
 To verify the HVAC system meets the current Good Manufacturing Practices (cGMP)
requirements and all other regulatory obligations.

3.0 DOCUMENTATION:
 Identity numbers of the entire air handling unit (AHU) were
labeled.
 All the relevant drawing of HVAC system was checked.

4. VERIFICATION OF CORRECTIVE ACTION REPORT

Before starting air balancing , the completion of Corrective Action Report was verified.
QUALIFICATION REPORTS OF HVAC SYSTEM, AIR BALANCING

P a g e | 2of 4

5. WASHING, CLEANING & SANITIZATION OF PRODUCTION AREA


Production area were verified for the dust and microbial contamination level on surfaces. Before air
balancing test the Production area were washed down, cleaned and disinfected with approved
disinfectant by trained pharmacist.

6. ENVIRONMENTAL PERFORMANCE TEST


Production area were subjected to the following set of environmental performance tests after
completion cleaning.
i. HVAC System
ii. Air Flow And Uniformity Tests
iii. Temperature And Humidity Control Test
iv. Differential pressure

6.1 HVAC SYSTEM

Description:
The air-conditioning system for the Production area consists of the following major component.
 Three Air Cool self-contain package units,

Following key elements were considered for implementation and control of air the HVAC system and
air handling (AHU) system in the overall design.
 Air flow regime
 Filtration
 Pressure differential across filters and areas
 Temperature
 Humidity
6.2 AIR FLOW AND UNIFORMITY TEST

Air Balancing:

Air balancing activity consists on the following steps.


1. Measurement of air volumes in supply and return air ducts.
2. Measurement of Differential pressure
3. Pressure per Hour-Rooms
QUALIFICATION REPORTS OF HVAC SYSTEM, AIR BALANCING

P a g e | 3of 4

6.2.1 Measurement of Air volume in supply and return air ducts.


 The test method was carrying out according approved procedure.
 Equipment:

S.No. Equipment/ Instruments


1 Portable Manometer
2 Pitot tube
3 Digital Tachometer

 Acceptance criteria:
 Allowable Tolerance for Airflow rate is ± 10% of Designed Volume.
 Reading will be taken at 40 in. above the floor in the center of the grid for minimum 15
seconds. (If 40 inch space is not available then the reading will take at height of the false ceiling
and length of diffuser hood)
 No object within 10 ft of the anemometer, except fixed equipment.
6.2.2 Measurement of Differential pressure

 Pressure control test was carried out by TS services test.


 The HVAC was in continuous operation when the test was performed.
 To avoid unexpected changes in pressure and to establish a baseline, all doors in the
production area were closed and no traffic is to be allowed during test.
 The reading was taken of the different locations mentioned in drawing.
 The results were noted which attached with report according to AHUs.

 Acceptance criteria:

Under class 10,000 the system should meet design specification (minimum 0.05 In. w.g.)
Under class 100,000 the system should meet design specification (minimum 0.03 In. w.g.)
QUALIFICATION REPORTS OF HVAC SYSTEM, AIR BALANCING

P a g e | 4of 4

6.2.3Measurement of Air Changes per Hour


 Room Air changes per hour for the class 10,000 and 100,000 were taken from each room of the
individual AHU.
 The readings were taken of the different locations mentioned in drawing.
 The results were noted which attached with report according to AHUs.
 Total supply air to the room will first calculate.
 Length, width and height of rooms are to be measured and volume is calculated by multiplying
all.
 The air changes will be calculated as below:

Calculation:

Volume of Room = Length × Breadth × Height of the Room

Total Actual Supply Air CFM × 60 min .


Air Changes per hour =
Room Volume (cu.ft )

You might also like