Tugboat Specification
Tugboat Specification
Tugboat Specification
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page i of 177
LNG PROJECT
TABLE OF CONTENTS
PART. 000 GENERAL PROVISION
Page
001. GENERAL 1
001.1 Intent of Specification 2
001.2 Shipbuilder's Responsibility 2
001.3 Definition 3
002. PRINCIPAL PARTICULARS 5
002.1 Principal Dimension 5
002.2 Tank Capacity 5
002.3 Clear Height 6
002.4 Propelling Machinery 6
002.5 Speed, Bollard Pull and Endurance 6
002.6 Rooms and Cabins 6
003. DESIGN 7
004. AMBIENT CONDITION 7
005. CLASSIFICATION 8
006. RULES AND REGULATIONS 8
007. CERTIFICATES 9
008. STANDARDS 10
009. MATERIALS AND WORKMANSHIP 10
010. INSPECTION, TESTS AND TRIALS 10
010.1 General 10
010.2 Shop Test 12
010.3 Shipyard Testing 12
010.4 Dock Trial 13
010.5 Inclining Experiment 14
010.6 Official Sea Trial 14
010.7 Static Bollard Pull Test 15
011. LAUNCHING 16
012. VIBRATIONS 16
013. NOISE 16
_ __
014. TRIM AND STABILITY 17
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page ii of 177
LNG PROJECT
_ __
029. PURCHASER’S REPRESENTATIVE OFFICE 27
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page iii of 177
LNG PROJECT
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page iv of 177
LNG PROJECT
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page v of 177
LNG PROJECT
301. GENERAL 37
304. DOORS 37
304.1 Watertight (Subdivision) Door 37
304.2 Weathertight Doors 37
304.3 Fumetight Doors 37
304.4 Fire Rated Doors 37
304.5 Interior Doors 38
304.7 Door Hardware and Locks 38
Page
315. INSULATION 44
315.1 Thermal Insulation 44
315.2 Fire Insulation 44
315.3 Acoustic Insulation 45
316. ASBESTOS 45
325. FURNITURE 46
325.1 Settees 46
325.2 Tables 47
325.3 Berths 47
325.3.1 Berth, Single 47
325.3.2 Berth, Double 47
325.3.3 Mattresses 47
325.4 Desks 47
325.4.1 Single Pedestal Desk 47
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page vii of 177
LNG PROJECT
Page
326.5 Drawers 50
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page viii of 177
LNG PROJECT
Page
340. CONTROL SPACE OUTFITTING 57
340.1 Wheelhouse 57
340.1.1 Pilot Chair 57
340.1.2 Chart Table 57
340.1.3 Chart Light 57
340.1.4 Flag Locker 57
340.1.5 Communications Desk 57
340.1.9 Miscellany 58
345. MACHINERY SPACE OUTFITTING 58
345.1 Lifting Arrangements 58
345.2 Workbench 58
345.3 Parts and Tool Storage 59
345.6 Engine Room Communication booth 59
345.6 Rag Bins 59
345.7 Guards 59
345.8 Electric Welding Machines 59
350. STORAGE SPACE OUTFITTING 59
350.1 Domestic Stores and Lockers 59
350.2 Ship's Stores 59
350.3 Galley Stores 60
360. FIRE SAFETY EQUIPMENT 60
360.1 Fixed Gas Fire Extinguishing System 60
360.2 Portable Fire Extinguishers 60
360.3 Fire Stations 60
360.4 Fire Safety Equipment, Miscellaneous 61
365. LIFESAVING EQUIPMENT 61
365.1 Rescue Boat 61
365.2 Liferafts 61
365.4 Lifebuoys 61
365.5 Lifejackets 61
365.6 Immersion Suits 62
365.8 Distress Signals 62
365.9 Line Throwing Apparatus 62
380. PAINTING AND COATINGS 62
380.0 General 62
380.1 Pre-Weld Primer 63
380.2 Surface Preparation 63
380.2.1 Steel Work and Aluminium Alloy 63
380.2.2 Wood 64
380.3 Painting, Quality Control 64
380.4 Application Procedures 64
380.5 Pre-Delivery Cleaning 65
380.6 Paint Schedule 65
380.7 Anti-Condensation Treatment 65
384. CATHODIC PROTECTION 66
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page ix of 177
LNG PROJECT
Page
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page x of 177
LNG PROJECT
Page
401. GENERAL 67
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page xi of 177
LNG PROJECT
Page
520. CLUTCHES 80
521. COUPLINGS 80
530. Z-DRIVES 81
530.1 Z-Drive Propeller 81
530.2 Z-Drive Nozzle 81
530.3 Steering Gear 82
530.4 Z-Drive/Clutch/Engine Controls 82
530.5 Z-Drive Mounting 82
530.6 Z-Drive Auxiliary Services and Accessories 82
530.7 Paint and Protection 83
530.8 Tools and Spares 83
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page xii of 177
LNG PROJECT
601. GENERAL 84
601.1 Functional Requirements 84
601.2 System Configuration 85
601.2.1 System Design Parameters 85
601.2.2 Equipment Sizing 85
601.2.3 Electromagnetic Compatibility 85
601.2.4 System Integration 85
601.5 Documentation 86
601.5.1 System Drawings 86
601.5.2 Electrical Load Analysis 86
601.5.3 System Protection 86
601.6 Nameplates, Electrical Equipment 86
601.8 Grounding 87
601.8.1 Equipment Grounding 87
601.8.2 System Grounding 87
601.8.3 Ground Fault Indication 87
602. POWER SUPPLY SYSTEM 87
603. EMERGENCY POWER 88
604. DC POWER 88
604.1 Batteries 88
604.2 DC Power Supplies 88
604.3 Charging and Discharging Boards 89
604.4 Battery Boxes and Connections 89
605. AC POWER GENERATION 90
605.1 Ship's Service Generator Sets 90
605.1.1 Generator Set Prime Movers 90
605.1.1.1 Auxiliary Engine Installation 91
605.1.1.2 Engine Instrument/Control Panel 91
605.1.1.3 Alarms 91
605.1.1.4 Engine Protection Devices 91
605.1.2 Generators 91
605.1.2.1 Rating 91
605.1.2.2 Construction 92
605.1.2.3 Accessories 92
605.1.2.4 Windings 92
605.2 Harbour Genset 92
605.2.1 Harbour Genset Prime Mover 92
605.2.1.1 Auxiliary Engine Installation 93
605.2.1.2 Engine Instrument/Control Panel 93
605.2.1.3 Alarms 93
605.2.1.4 Engine Protection Devices 93
605.2.2 Generator 93
605.2.2.1 Rating 93
605.2.2.2 Construction 94
605.2.2.3 Accessories 94
605.2.2.4 Windings 94
_ __ 605.3 Control 94
__ RA| 605.3.1 Voltage Control 94
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page xiii of 177
LNG PROJECT
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page xiv of 177
LNG PROJECT
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page xv of 177
LNG PROJECT
Page
735. MACHINERY COOLING 119
735.1 General 119
735.2 Cooling Circuits 119
735.3 Jacket Water Circuits 120
735.4 Raw (Sea) Water Circuits 120
735.6 Heat Exchangers 120
740. COMPRESSED AIR SYSTEM 120
740.1 Receivers 121
740.2 Compressors 121
740.3 Air Treatment 121
740.4 Air Distribution 121
740.4.1 Engine Starting 121
740.4.5 Utility Services 121
740.4.6 Whistle 121
745. LUBRICATION SYSTEMS 122
745.1 Lube Oil Storage Tanks 122
745.2 Lube Oil Transfer System 122
745.2.1 Lube Oil Transfer Pump 122
750. OILY BILGE SYSTEM 123
750.1 General 123
750.2 Storage Tanks 123
750.2.1 Oily Water Tank 123
750.3 Oily Water Pump 123
750.4 Oily Water Separator 123
751. WASTE OIL/SLUDGE SYSTEM 124
751.1 General 124
751.2 Waste Oil Tank 124
751.3 Waste Oil Pump 124
755. HYDRAULIC SYSTEMS 124
755.1 General 124
755.2 Hydraulic Oil Tanks 125
755.2.1 Z-Drive Steering Gear Re-supply Tank 125
755.2.2 Hydraulic Oil Storage Tank 125
755.3 Hydraulic Pumps 125
755.3.1 Winch Drives 125
755.3.2 Other Deck Machinery 125
755.4 Hydraulic Oil Piping 126
755.4.1 Control Hydraulic Pipe 126
755.4.2 Main Line Hydraulic Pipe 126
760. EXHAUST SYSTEMS 126
760.1 Vibration Isolators 126
760.2 Piping and Fittings 127
760.3 Silencers 127
760.4 Insulation and Lagging 127
760.5 Installation 127
785. OIL RECOVERY SYSTEMS 127
785.1 Recovered Oil Tank 128
_ __ 785.2 Hydraulic Power Connections 128
__ RA|
785.3 Oil Recovery Equipment 128
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page xvi of 177
LNG PROJECT
Page
801. GENERAL 129
805. HEATING 129
810. VENTILATION, ACCOMMODATION 129
810.1 Air Vents and Louvres 129
810.2 Fans/Air-Handling Units 129
810.2.1 Fresh Air Supply Fans 129
810.2.2 Wheelhouse Demisting Fans 130
810.2.3 Exhaust Fans 130
810.3 Ductwork 130
810.4 Dampers 130
811. VENTILATION, MAIN MACHINERY SPACE 130
811.1 Intake and Relief Air 130
811.2 Fans and Silencers 131
811.3 Ductwork 131
813. VENTILATION, HULL COMPARTMENTS AND LOCKERS 131
815. AIR-CONDITIONING 131
825. POTABLE WATER SYSTEM 132
825.1 Storage Tank 132
825.2 Pumps 132
825.3 Piping 132
825.5 Fresh Water Treatment 132
825.6 Pressure Distribution System 132
825.7 Hot Water Tank 132
825.9 Fixtures 133
826. WINDOW WASHING SYSTEM 133
830. SANITARY, BLACK WATER 133
831. SANITARY, GREY WATER 133
831.2 Sump/Holding Tank 133
832. SCUPPERS AND DRAINS 133
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page xvii of 177
LNG PROJECT
Page
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 1 of 177
LNG PROJECT
0.0.1. GENERAL
The design and equipment of the Vessels proposed by the Builder shall be up-to-
date and proven and in service and similar to that in use for tugboats at other LNG
facilities.
The hull is constructed of all-welded mild steel, in a double chine, fully developable
form. The deckhouse and wheelhouse are also fabricated in steel
The Vessels shall be identical in design and manufacture as far as possible, using
common equipment to enable BP Berau Ltd. (hereinafter referred to as “the
Owner”) and KBR / JGC / PT. Pertafenikki Engineering Joint Operation (hereinafter
referred to as "the Purchaser”) to limit the quantity of essential spare parts carried
to ease maintenance concerns.
The Vessel’s operational area will be the waters of the Berau Bay, Papua,
Indonesia where they will be used for escort both in indirect and direct modes and
the handling of large LNG carriers. The Vessels must be capable of being safely
operated while performing their required duties in both benign and adverse
weather and sea conditions.
The Vessels must therefore have excellent capabilities for towing LNG Carriers
from the stern, from the bow on a long towline, from alongside and in push –pull
mode. Optimum manoeuvring capabilities of them are required in any expected
weather condition.
A main part of the operation of the Vessels is to escort the LNG carriers at a speed
of approximately 7 knots to a point where the berthing manoeuvres are to
commence.
Thereafter the Vessels are to assist in the berthing and un-berthing of the LNG
carriers. During escort operation, the Vessels will be connected to the LNG carrier,
on a long towline aft of the LNG carrier, in order to allow immediate assistance to
the LNG carrier in case of an emergency situation.
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 2 of 177
LNG PROJECT
The Vessels will also act fire fighting and oil recovery vessels. The Vessels must
therefore be suitable for operations in hazardous areas. The equipment and
installation must therefore comply with the relevant standards and regulations to
make possible the safe operation of the Vessels while performing these functions.
The design of the Vessels shall be developed based on proven design package
RAmparts 3200 from Robert Allan Ltd, Vancouver, Canada. The Vessels and the
RAmparts 3200 series escort tugboats which are currently in operation at the oil
terminals in Mediterranean and Arabian Gulf Area shall be identical in hull design,
similar in machinery design and major outfitting design.
0.0.1.3 DEFINITION
Organization
Owner
BP Berau Ltd.
Purchaser
PT PAL Indonesia
Ujung - Surabaya 60155
Indonesia
Naval Architect
Purchaser's Representative
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 4 of 177
LNG PROJECT
Approved or to Approval
Provide
Regulatory Authorities
The finished clear height in any accommodation or control space shall not
be less than 2,100 mm
Main engines
Number of set : Two (2) sets
Maximum continuous output : 1,618 kW at 750 rpm
Propellers : Two (2) sets of 4-blades fixed pitch,
Nickel Aluminium Bronze (JIS-
CAC703), 360 degrees rudder
propeller with Kort Nozzle,
Minimum trial speed at an engine output of 100% MCR with empty oil
recovery tanks and 50% of remaining deadweight 12.0 knots ahead and
11.5 knots astern .
0.0.3. DESIGN
The design shall provide the maximum possible all around visibility from the
wheelhouse bridge. A clear sight onto all working decks and the main deck
equipment is provided. Utmost attention is to be paid with respect to the view on
essential machinery and to the readings of functions in the engine room.
The layout of control and alarm panels or desks within such locations as the
wheelhouse and engine control room shall conform to the latest ergonomic design
criteria.
The Vessels shall be of the azimuth stern drive type and a diesel engine driven, all-
welded steel, tugboat with rudder propellers, having a forecastle/stepped main
deck.
The Vessel shall have a raked stem, chined transom stern and a stepped main
deck, below which the space shall be subdivided by five (5) transverse watertight
bulkheads into six (6) compartments as follows;
Fore peak
Lower accommodation space (over)/ Tank space (below)
Engine room
Hold/Tank compartment
Rudder propeller room
Aft peak tanks
0.0.5. CLASSIFICATION
The Vessel, including its hull, equipment and machinery shall be designed,
manufactured and built under the survey of Lloyd’s Register of Shipping
(hereinafter referred to as “Class”) to be classified with the following class
notations:
The Vessel shall comply with all the relevant IMO Regulations for a ship of Class
IX. (MCA-UK Tug Boat)
Regardless of the class notation, the Vessel shall be designed and outfitted in
accordance with the Lloyds Register’s rule of “Escort Tug” except requirements for
performance trials.
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 9 of 177
LNG PROJECT
0.0.7. CERTIFICATES
The following certificates shall be obtained by the Builder and handed over to the
Owner upon the delivery of the Vessel, as common practice builder will provide
Interim certificate upon delivery of the vessel with validity about three (3) months,
permanent certificates automatically will be issued by Class where validity of
interim certificate is expired.
Issued by Class:
1. Classification Certificate (hull & machinery)
2. International Load Line Certificate
3. Certificates of Anchors, anchor shackles and anchor chains
4. Certificates of Machinery, deck and outfitting equipment
5. Certificate of all towing gear, wire rope, etc
6. Certificate of Bollard pull
7. Certificate for NOX emission according to MARPOL 73/78 annex VI
Issued by Builder:
1. Builder’s Certificate
2. Deadweight Certificate
Issued by Manufacturer:
1. Certificate of Life saving equipment with approval by Government and a copy
of type approval certificate
2. Certificate of Fire fighting equipment with approval by Government
3. Certificate of Navigation lights
4. Certificate of Oil recovery equipment
5. Other appropriate certificates of equipment and outfitting materials with a
copy of type approval certificate
6. Ship radio type approval certificate
7. Certificate of nautical instruments
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 10 of 177
LNG PROJECT
The Purchaser will take the necessary procedures to authorize the Class to issue
the certificates mentioned above on behalf of the Government of Republic of
Indonesia and to obtain the necessary licenses, say call sign, ID number, etc.
0.0.8. STANDARDS
Materials, fittings, machinery and equipment for the construction of the Vessel shall be
designed in accordance with Japanese Industrial Standards (JIS) and Japanese
Shipbuilding Quality Standards (JSQS) or equivalent.
The Builder's and manufacturer's standards shall be reviewed and agreed with the
Purchaser.
The Builder shall supply all materials, equipments and machinery required for completion
of the Vessel specified in the Specifications. All materials, equipment and machinery
supplied and/or mounted by the Builder shall be of a high-class marine standard, suitable
for marine use and shall be new and free from defects and imperfections. The Builder
shall propose makers for purchase approval. The Builder will inform the selected maker to
the Purchaser.
They shall be in accordance with the Rules and Regulations mentioned before and also
other Requirements of the governing authorities concerned.
All workmanship applied at the construction of the Vessel shall be the best available
according to international shipbuilding practice for this kind of vessels and suitable for the
purpose intended.
The Purchaser shall be given the opportunity to carry out quality audits on both the
Builder and subcontractors, who should be declared and agreed prior to Contract.
Steel material used for structuring of the hull shall be certified by the Classification
Society in compliance with its Rules.
Necessary material and equipment certificate should be provided to Purchaser.
Equipment and material, spares and maintenance should be easily sourced and
supported in Indonesia.
0.0.10.1. General
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 11 of 177
LNG PROJECT
Inspections, tests and trials shall be carried out in accordance with Builder’s
standards and Class protocols for inspections, tests and trials, details of which
shall be submitted to the Purchaser for approval.
Builder’s standards for performance of inspections, tests and trials are subject to
approval of the Class, Authority and the Purchaser.
All tests, trials and re-trials will be at the expense of the Builder. The tests and
trials expense shall include fuel oil, lubrication oil, system oils, fresh water, food,
crew, equipment, stand-by vessel and any other expense connected with the trials.
The Builder shall submit in triplicate copies of all inspection, test and trials reports
carried in accordance with the requirement of specification, Class, IMCA etc.
Prior to sea trials, the Vessel shall be dry docked for final inspection and bottom
painting. Where the vessel is in the water for less than 2 months during fitout, it
shall not be necessary to dry dock for bottom paint / inspection.
The Vessel shall only be dry docked after the sea trials in case serious underwater
defects are expected, in order to allow for a complete inspection of the underwater
hull, propellers, anodes and paint.
Before the sea trials all underwater painting work has to be finished, propellers
inspected and polished. After the sea trials the Builder shall submit a sea trial
record book in which all data and records are to be carefully analysed and
compiled.
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 12 of 177
LNG PROJECT
Prior to the commencement of the sea trials the main engines shall run at least for
2 hours.
The sea trials shall be performed at a loading condition of 50 % or above of the full
deadweight capacity except recovered oil under calm deep-sea conditions with a
wind speed not exceeding Beaufort 2. Trial loading condition shall be submitted to
the Purchaser for approval not later than 14 working days in advance of the sea
trials.
Upon completion of sea trials, any machinery considered necessary by the
Purchaser and/or Class shall be opened up for inspection
The results of these tests shall be submitted to the Purchaser within 7 working
days of the tests being completed.
This shop tests program shall be submitted to the Purchaser no later than 30
working days in advance.
Main engine, propulsion machinery, winches and other equipment items shall be
shop tested in accordance with requirements of the Class and/or the standard
protocols of the manufacturers and to the satisfaction of the Purchaser.
The main engines factory test will be conducted in the presence of the Purchaser
and builder at their own expense.
All readings and data of the inspections, tests and trials performed shall be
submitted to the Purchaser for approval.
All tanks and main hull compartments shall be tested for oil and water tightness
according to the Class requirements prior to any paint application except shop
primer. Before testing, all tanks are to be structurally complete, with all external
pipe fittings, connections fitted and cleaned.
Subject to the specific requirements of the Classification Society and the
Purchaser, no tank or compartment boundary welded connections is to be coated
or painted until testing has completed and the tank or compartment has been
passed by the Purchaser.
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 13 of 177
LNG PROJECT
Spaces with steel bulkheads permanently exposed to drip and splash water and
floors which are covered with cement or tiles, before painting and before floor
coverings are laid, will be tested according to the Class requirements.
Weather tightness of exterior doors, windows and hatch covers shall be tested by
means of hose testing as required by relevant regulations.
Water tight door shall be tested by means of hose testing as required by relevant
regulations.
Dock trial shall be carried out at the Builder’s expense prior to the official sea trial
in accordance with the completion program agreed with the Purchaser, to ensure
correct performance of all machinery.
Engine room, machinery and systems shall be cleaned and free from loose
building materials before testing will take place.
The trial shall include the testing of at least the following machinery, installations
and systems but not limited to :
Before trials of main machinery are commenced, test for entire auxiliary machinery
shall have been completed and proven to be in good working order.
The main propulsion system will be tested for a minimum continuous duration of
two hours under the supervision of the main engine manufacturer after ensuring
satisfactory alignment of the main engines, clutches, propulsion units and shafting
in accordance with manufacturers requirements and within their specified limits.
The bilge, ballast and general service pumps shall be operated on the respective
systems and the ballast tanks must be tested before filling.
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 14 of 177
LNG PROJECT
The necessary water and sanitary systems shall be in continuous operation during
trials, and each tap, water closet, shower, etc., together with all fittings are to be
operated and the specified pressures maintained on the systems.
All defects shall be remedied by the Builder and re-tested to the satisfaction of the
Purchaser before sea trials.
Life saving equipment shall be tested and demonstrated to the satisfaction of the
Purchaser, the Class and the Authority.
A final trim and stability booklet shall be prepared after the lightweight vessel data
have been calculated from the inclining experiment, which shall include all relevant
conditions of loading and towing.
The official sea trial shall be conducted at corresponding draft slightly trim to a
loading condition of 50 % or above of the deadweight except oil recovery tank
under calm and deep-sea conditions, with wind speed not exceeding Beaufort.2
The official sea trial shall be held in accordance with the detailed program
approved by the Purchaser, the Class and Authority. During the official sea trial the
Vessel shall be under the command of an experienced captain, nominated by the
Builder.
The Builder shall prepare and submit a detailed trial program twenty one (21)
working days prior to commencement of the official sea trials showing the method,
order and time schedule of the trials to the Purchaser for approval.
The Builder shall perform the following tests and trials under the attendance of the
Purchaser and the Class :
6. Anchoring test
7. Starting test of main engines
8. Dead slow test of main engines
9. Torsion vibration measurement
10. Test and/or adjustment of nautical equipment
11. Noise & Vibration measurement
12. Fire fighting test
13. Air conditioning system test
14. Bollard pull test
Adjustment of the compass shall be done by a recognised compass adjuster
before the start of the official sea trial.
Progressive speed trial shall consist of the following runs over officially measured
mile course and the speed in each case shall be determined as an average of one
(1) double runs = 1 outward + 1 inward run.
On completion of the official sea trial, the Builder shall submit the report including
speed-power curves to the Purchaser.
Main engine output shall be estimated from the measured engine data during the
speed trial using the results of the shop test of main engines.
After the sea trials, some parts of the main engines shall be inspected by the
surveyors of the Class and the Purchaser.
Bollard pull test shall be carried out to demonstrate the achievement of bollard pull.
This test shall be carried out in the ahead and astern mode.
The test shall be conducted in waters having adequate depth and relatively free
from currents.
The bollard pull test shall be performed in accordance with the requirements of the
Class.
Upon completion of the test, the Builder shall submit the record to the Purchaser
_ __ including the following readings:
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 16 of 177
LNG PROJECT
0.0.11. LAUNCHING
The Builder shall be responsible for the satisfactory launching of the Vessel. The
Builder shall make all necessary arrangement and inform the Purchaser in writing
14 working days in advance of the date of launching. The launching shall be
preferably in daylight.
0.0.12. VIBRATIONS
0.0.13. NOISE
The noise levels aboard vessel shall be as close as practicable, using reasonable
measures, to those specified in IMO A 468 XII. (Bearing in mind the IMO standard
was written for conventional cargo vessels of modest power/size ratio, whereas
tugboats have very much higher concentration of power in much smaller
envelopes.)
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 17 of 177
LNG PROJECT
Measure the noise levels during the normal free running condition of vessel at up
to 12 knots, at design draft and level trim (+/- 30cm trim), with all doors and
windows closed
The following measures shall be incorporated into the design to reduce the
generation and propagation of noise throughout the vessel:
Resilient mounting of main engines
Resilient mounting of electrical generators
Resilient mounting of air compressor
Flexible connections on services to all reciprocating machinery
Flexible mounting of all diesel engine exhaust systems
High attenuation, spark-arresting silencers for all diesel engine exhaust
systems
Fire/acoustical insulation throughout engine room
High-density thermal/acoustic insulation throughout accommodation and
control spaces
Use of a Visco-Elastic type membrane and high-density coating as a
"floating floor" in all accommodation and control space floors
High-noise attenuation lining and partition system (NORAC or equal)
Acoustic "planked' ceiling" (Danacoustic or equal)
Use of fire/acoustic insulation in the casings and engine room air plenums
Use of machinery space supply fan silencers
Secondary windows in accommodation spaces (excluding wheelhouse)
The Builder shall issue to the Purchaser, during the design development phase of
the work, calculations providing sufficient evidence that the predicted noise levels
will not exceed the limits specified above. These calculations shall be performed
according to an internationally recognized method approved by the Purchaser. The
final result of RAL noise study will be the criteria for comparison and estimation.
The Vessel shall be designed for adequate stability and seaworthiness in all
service conditions in accordance with the standards for Tug boat as established by
International Maritime Organization resolutions and Indonesian regulations.
The stability of the Vessel shall meet in any condition the requirements of IMO
resolutions, with understanding that the initial meta-centric heights shall be in no
case less than 0.9 m for any operational condition of the Vessel.
The report containing the final trim and stability calculation under the regulated
loading conditions by rules shall be submitted to the Purchaser and the Class.
Stability information booklet for the captain shall be submitted.
In computation of loading conditions, the weight per person with effects shall be
assumed as 150 kilo-grams.
When determining of weight of water and oil in filled storage tanks, water tanks
shall be assumed to be 100 % full and oil tanks 96 % full respectively.
0.0.15.1. General
The Builder shall prepare and submit at his expense to the Purchaser, the Class
and the Authority for approval of drawings, calculations, documentations and other
technical details required for the construction and fitting out of the Vessel.
The Builder shall be responsible for the approval procedures with the Class and
the Authority and shall submit to the Purchaser copies of all correspondence
concerning technical matters between the Builder and the Class and the Authority.
The naval architect shall prepare the following drawings in accordance with Class
and Flag requirements on behalf of the builder:
Prior to commencing the design of the Vessel, the Builder shall submit a list of
drawings including manufacturer’s drawings to the Purchaser for approval. Before
starting prospective works, the Builder shall submit copies of the plans/drawings by
electronic transfer to the Purchaser for approval in accordance with procedures
agreed between the Purchaser and the Builder.
Drawings should be submitted progressively and not in bulk.
The Purchaser shall acknowledge the receipt and comment if any to the Builder
within twenty one (21) working days after the date of receipt of them.
List of drawings for approval shall include the following contents, but not limited to
1. General
1) Technical Specifications
2) General Arrangement
3) Hydrostatic table
4) Initial calculation of weight, trim and stability
5) Cross table
6) Bonjean table
7) Tonnage calculation
8) Tank capacity plan
9) Propeller calculation including Speed-Power and Bollard pull
10) Test method of official sea trial
2. Hull construction
_ __ 1) Midship section
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 20 of 177
LNG PROJECT
3. Hull fitting
1) Wheelhouse arrangement
2) Deckhouse arrangement
3) Mooring arrangement
4) Accommodation arrangement
5) Arrangement of outfitting
4. Machinery
1) Shafting arrangement
2) Engine room arrangement
3) All piping system diagrammatic
_ __ 4) Arrangement of exhaust gas piping in engine room & funnels
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 21 of 177
LNG PROJECT
5. Electric
1) Wiring diagram of power circuit
2) Wiring diagram of lighting circuit
3) Calculation of electric power
4) Wiring diagram of nautical and communication equipment
5) General arrangement of electric installation
6) Remote control system drawing for main engine , clutch and rudder
propeller
7) Electric inventory list
8) Navigation lights
At the time of the delivery of the Vessel, the Builder shall submit to the Purchaser
four (4) sets of final drawings including a list of final drawings generally to include
but not be limited to the above list, results of various tests and inspections and a
detailed list of spare parts, inventories and tools provided, and shall also submit
four (4) sets of the instruction manuals for all items of machinery, electrical, and
electronic equipment written in English.
Those drawings and manuals are to be incorporated into a common indexed filling
system.
One (1) copy shall be provided in electronic format.
One (1) set of the following finished plans shall be mounted in frames and
displayed onboard.
General arrangement
Capacity plan
Pumping diagram
Arrangement of life saving apparatus and fire fighting appliances
Other plans as required by the regulations.
Neatly cut vessel's name (individual letters 250 mm high) from 5 mm plate
and weld on forward bulwarks P&S, and paint
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 22 of 177
LNG PROJECT
Neatly cut name of vessel and port of registry from 5 mm plate and
continuous weld across stern on bulwark, and paint. Name to be 200 mm
high and home port 130 mm
Fillet welds on lettering to be no larger than 3 mm
Attach all markings by neat, continuous weld with fillet welds on lettering no
larger than 3 mm
Cut draft marks in Arabic numerals from 5 mm plate and weld to shell on
four quarters. Carefully locate draft marks and obtain approval of
Purchaser's Representative before final welding. Record and transmit
location to Naval Architect, and indicate on as-fitted Docking Plan ref-
erenced to baseline and docking reference line
Paint draft marks white, and indicate waterlines at 200 mm intervals with
100 mm high numbers (height projected in a vertical plane). Set numerals
with bottom of numeral corresponding to indicated draft at that location
Provide draft marks covering range of design waterline ± 1 metre, or as
close thereto as practical
Cut load line markings (if required) from 5 mm plate and weld to shell.
Carefully locate load line markings and obtain Purchaser's and Class
approval before final welding. Record and transmit location to Purchaser
and indicate on "as fitted" General Arrangement
Paint load line marks in contrasting colour
All tank boundary corners on the outer hull are to be identified with welding
bead and the tank number and contents
Mark lifebuoys and raft with ship's name and port of registry
Provide 50 mm high Lamicoid labels on lube oil and hydraulic oil tanks
indicating service and type of oil
• Provide a cast bronze plaque bearing ship's name, Builder's name, hull
number, and year of construction
• Mount on a hardwood base in a location approved by Purchaser
Representative
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 24 of 177
LNG PROJECT
Standard spare parts, inventories, and tools shall be provided in accordance with the
recommendation by the Rules and Regulations of the Class, and those items for
commissioning/start-up spare not specified in the Rules and Regulations shall be
provided in accordance with the manufacturer's standards. The list for 2 years spare parts
recommended by manufactures will be provided with price. Special tools for maintenance
purpose shall be provided. (To be supplied by manufacturer)
All initial filling water, fuel oil, lubricants and grease, working oil for deck machinery, all
consumable liquids or gas, etc., shall be borne by the Builder.
The Builder shall submit all consumable lists as a document to the Purchaser.
0.0.19. REGISTRATION
The Vessels shall be registered each under the laws and regulations of the Republic of
Indonesia.
The Builder shall pay for all fees for certificates, surveys and registration except for those
relating to owner’s deliveries. All certificates shall become effective on the date of each
delivery.
0.0.21. PRODUCTION
Scheduling
Production Record
The Builder, using its Quality Control Team, shall ensure that the labour standard and
material quality during construction, is in accordance with the Builder’s Standard
Shipbuilding practice, the Rules of the Class, IACS, JSQS and Statutory Regulations.
One member of the Builder’s Quality Control Team shall be assigned to and shall
maintain close liaison with the Purchaser’s inspection staff. The Builder shall provide the
Purchaser’s inspection staff with complete access and availability to tests, test reports, X-
rays, samples and unprice purchase orders etc., involved in the construction.
A quality plan shall be submitted by the Builder and agreed between the Purchaser and
the Builder. The requirements in the Quality plan to include quality assurance system of
sub-contractors.
• Use all practical methods or materials to control excess weight in all areas not
defined by Specification or Drawings. Any redundant weight will be considered
in same light as bad workmanship and will be removed on request of
Purchaser's Representative
• Redundant weight is defined as weight over and above that required for
function in terms of strength, resistance to vibration, or reasonable durability
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 26 of 177
LNG PROJECT
• Handle spares, small parts, small items of outfit, etc., in an orderly manner,
both in shops and at erection site. Check all items into stores and store in a
clean, dry, and secure place
• Do not prematurely order items out of stores nor expose to weather or dirt prior
to stowage aboard or working into ship
• Spares as per 0.0.17 delivered to ship will be checked and accepted by
Purchaser's Representative
0.0.25 CLEANLINESS
• Thoroughly clean fresh water tank before closing up; perform a chlorine shock
treatment and test water quality
• Construct lube oil and hydraulic oil storage tanks of clean, descaled steel, or
pickle after fabrication. Ensure tanks are thoroughly cleaned, vacuumed dust
free, and coated thoroughly with mineral oil before closing up
• Obtain approval signature of Purchaser's Representative before final closing up
of any tank
0.0.27 SAFETY
• Ensure safe working conditions exist in shops and at erection site, and during
outfitting and trials. Provide adequate guard rails; ladders, gang planks, ensure
bridges are of adequate strength and secure against shifting; provide ample
lighting; and keep the site orderly and free from obstruction and hazards
Builder will provide separate office space for Purchaser and Owner
Engineers/Inspectors with AC, internet and yard’s standard office equipment for
total 6 persons. Telephone/internet’s bill shall be Purchaser/Owner account.
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 28 of 177
LNG PROJECT
201. CONSTRUCTION
201.0 General
The hull form of the fore-body shall be moderate V-shape, transitioned to flat
bottom with rise of floor and vertical side and sheer-strake at the mid-ships,
which form is extended to the aft-body with gradual uplifted plane bottom to the
stern for a steady flow of water towards the propellers
The workmanship shall be such as to ensure reasonable fair lines and smooth
surfaces referring to JSQS (Japanese Shipbuilding Quality Standards) guideline.
Prefabrication shall be used where ever possible to maximize the maximum use
of down-hand welding.
Structures contributing to the longitudinal strength of the Vessel shall be
generally continuous.
Abrupt changes of strength shall be prevented and the scantlings of longitudinal
strength members shall be changed gradually where necessary.
The termination of strength members shall be arranged in a manner to minimize
a concentration of stresses.
The main and auxiliary engine girders shall be efficiently integrated with the hull
structure. Main engines and auxiliary engines shall be seated resiliently
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 29 of 177
LNG PROJECT
201.1 Lofting
201.3 Prefabrication
201.5 Workmanship
• Do not cut holes or openings in structural members for pipes, cables, access,
or other purpose unless authorized on approved Drawings and approved
compensation is provided, or as approved by Purchaser’s Representative
• Take care to preserve hull structural integrity. Refer any questions involving
such integrity to Naval Architect
• Neatly and carefully execute all plate edges and holes burned in structure.
Make all cuts regular in outline without notches
• Openings burnt in shell, deck, or other main strength members to be circular or
have well- rounded corners. Grind edges of such cuts smooth and bullnosed
• Remove sharp or jagged edges of exposed structural work
• Remove all erection clips or bridges and grind any projections smooth. Avoid
removal of material from plate, but if occurring, fill with weld deposit. Grind
such locations flush and smooth where exposed to view inside or out
• Provide limber holes for drainage where necessary to permit total drainage to
lowest point of compartment or tank. Cut limber holes and scallops on a
smooth 50 mm minimum radius as far as practical
• Cut relief air holes in framing at tops of tanks where necessary to avoid air
pockets
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 30 of 177
LNG PROJECT
201.6 Welding
• Completely seal all exposed faying steel surfaces by welding so water cannot
gain access to cause corrosion. Do not perform any intermittent welding on
exterior or in washroom or similar wet spaces where exposed finish is steel
• Leave finished work clean and smooth with all projections and rough welds
chipped flush and ground smooth. Grind all underwater hand welds smooth on
crown but not necessarily flush with plating
• Make deck plate reinforcements by fitting insert plates only, and not by use of
doublers
• Chamfer edges of insert plates on a four-to-one bevel down to thickness of
surrounding plate, and make corners with a generous radius
• Generally speaking, welding to longitudinal, bulkhead stiffeners, face bars to
transverses or girders, to be double continuous including all areas likely to be
subject to corrosion or under vibration, or at stated areas subject to impact, or
in fresh water tanks
205.1 Steel
205.2 Aluminium
205.4 Wood
• For cabinet work, lining, trim, and other purposes provide properly seasoned
teak, close-grained hardwood, free of objectionable flaws
• Where plywood is used, provide marine grade plywood
• Thoroughly treat all wood products except plywood or exposed trim with a
vermin/ insect-repellent chemical. Ensure selected product is especially
effective against rot
210.1 Framing
The bottom structure in engine room shall consist of double bottom construction
except the after part of single bottom construction and solid floors shall be provided
at every frame station.
Full depth girders are welded as far as forward and aft as permitted by the shape
of the Vessel. The sea chests for fire fighting shall be integrated in the double
bottom construction of the engine room. The floors in way of the wells are to be
extended to full depth of the well plating and securely connected there to. The
_ __ longitudinal girders forward and aft of the wells are to be constructed in such
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 32 of 177
LNG PROJECT
The shell plating shall be transversely framed, and shall have welded butts and
seams. Thicker plate shall be provided in way of sea chests and anchor pocket.
Stem shall be of fair formed welded steel plate construction well raked forward
provided with suitable stiffening to withstand pushing loads.
Stern shall be executed as a heavy, welded plate stern with well rounded corners
to the side of the Vessel.
• Provide structural tanks with pipe connections and fittings as described in the
applicable system specification
• Provide tank coatings suitable for the application and in accordance with
Section 380
• Provide two (2) manholes per tank in accordance with Part 305.1 for all tanks
larger than one frame space
• Provide one (1) manhole for small tanks occupying only one frame space
• Provide a 42mm dia. Stainless steel bottom plug with mild steel socket welded
to the shell and shall be provided to each bottom compartment. The shape of
heads have to be difference from fuel & water compartment
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 33 of 177
LNG PROJECT
• Provide two (2) sea chests for Fi-Fi system, and minimum two (2) sea chests
as required for shipboard fire system, and other cooling system intakes. Main
sea chests cooling water to be provided with a cross-over line from which the
main cooling water pumps draw suction.
• Size each sea chest to provide an area through intake grating of three times (3
x) the area of all suctions connected to it
• Secure intake gratings of perforated heavy duty galvanized steel grid or
"Fibregrate" to clips using 16 mm stainless steel bolts of minimum length with
threads protected by "Neverseize". Drill and lock bolts with stainless steel wire.
Hinge gratings for ease of underwater access/service
• Mount valves on flange at side of chests where practicable
• Provide sea chests with a 38 mm stainless steel vent to deck with stainless
steel or bronze globe valve on sea chest
• Provide suction tailpipes extending to low level in the sea chest to minimize
drawing air into the suction piping
• Provide 20 mm, round bar hand grips P&S of each sea chest for divers'
inspections of sea chests
• Increase plate thickness in sea chests by a minimum 3 mm over adjacent shell
plating, and fit suitably sized anode in each sea chest (see Section 384 for
Cathodic Protection requirements)
212.0 Keel
The keel shall be incorporated with escort skeg as per described in item 212.1.
212.1 Skeg
• Equip vessel with a low-aspect ratio "escort skeg", biased forward in tug, to
enhance indirect force generation capabilities and to improve directional
stability when running astern
• Construct skeg strongly to support tug during dry-docking operations, to be
watertight, and well supported by primary ship's structure
• Provide 25 mm, 316 stainless steel vents and drain plugs. Fill with a non-
flammable, anti-corrosive solution after all welding is completed, drain and seal
• Weld skeg continuously and completely watertight. Locate vent and drain
plugs near top and bottom respectively
• Thoroughly rust-proof skeg on inside after final welding using a non-flammable,
bituminous type coating
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 34 of 177
LNG PROJECT
For stowing of the Vessel’s anchors, port and starboard pockets shall be
provided, to house the anchor crown flush with the Vessel side.
A bilge keel shall be fitted amidships on each side for approximately one third of
ship’s length. The bilge keel to be constructed of bulb plate section welded to a
flat bar that is welded to the hull. The ends of the bilge keels shall be well tapered
off over at least two frame spaces and in line with Class requirements. .
221. WHEELHOUSE
222. BULWARK
• Bulwark top to follow sheer in a fair curve as shown on Drawings. Finish top
edges smooth, and grind to a radius
• Fit pipe sections at top of bulwarks to provide safe contact areas and a smooth
edge for hawser passage
_ __ • Finish bulwark stanchions to pass lines without snagging
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 35 of 177
LNG PROJECT
• Provide top plate with 38 mm drain leading internally to main deck; fabricate
drain with stainless steel pipe
• See Section 811 for engine room ventilation relief air louvres
224. MASTS
• Fabricate independent tanks to suit the intended service and with due
consideration to design pressures set by height of deck vent and fill piping
• Construct tanks to be bolted in place in final installation
• Provide tanks with capacities as specified in Part 0.0.2.2
• Where practical, form tank corners rather than welding
• Provide each tank of 500 litres or less with clean-out handhole not less than
300 mm dia., baffles, and drain plug
• Provide each tank greater than 500 litres capacity with a full access manhole
(450 x 650 minimum), baffles, and drain plug
• Fit sightglass or contents gauges as specified (705)
•
• Accurately fabricate and install main engine girders. All welding on girders to
be continuous but no larger than Class minimum
• Ensure plate cuts in girder or brackets are smooth and fair; grind any
roughness smooth
• Provide substantial brackets centred under each vibration isolator
• Bolt winches to heavy seating and weld to heavy insert plates in deck. Align
insert with under-deck girders and support by pillars. Provide double
continuous welding in winch support area
• Cut limber holes as necessary to provide complete drainage
• Provide supplied Z-drive units in a "module" arrangement for bolting into ship's
structure
• Arrange mounting "pods" to match with faired lines of tug stern
• Tilt Z-drives from upright in longitudinal plane, as per Shafting Arrangement
Drawing. When viewed from astern Z-drive is upright
• All welding in Z-drive compartment to be double continuous. Take extra care
there are no stress raisers in this compartment
Two chain lockers, of the self-stowing type, shall be constructed in the fore
Vessel and to extend to the main deck with a capacity enough to stow chain
cable and shall have a centerline division wall and a bilge well at bottom.
Access to the chain locker shall be provided through access hatch. Steel plating
shall be provided to the bottom of the locker and wooden sparring to the side
shell.
Chain Locker to be provided with bitter end securing of chain.
***
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 37 of 177
LNG PROJECT
301. GENERAL
• Execute joiner work skillfully to present a neat and attractive appearance with
tasteful choice of materials and colour
• Choose all construction methods and materials with minimum maintenance in
mind; consequently, materials must be highly durable, easily cleaned by wiping
or washing with mild detergent
• Ensure surfaces are free of inaccessible corners or open joints which could
collect dirt
304. DOORS
• Below main deck, provide Class approved, hinged steel watertight doors with
open/ dogged-shut detector and "WT DOOR OPEN" alarm and status indicator(s)
in pilothouse
• Provide Class approved hinged type, weathertight doors for wheelhouse and
deckhouse
• Provide doors as follows:
- steel or alternate approved construction
- steel frame, weld-in type in steel deckhouse
- fitted with heavy duty, marine quality hardware
- all hinges to have grease fittings
- minimum four (4)-dog , single lever actuated on main deck
- latch-set on wheelhouse doors
- all doors lockable
- 500 mm coamings on main and forecastle deck, 150 mm coaming in
wheelhouse
• Provide 300 mm diameter fixed portlights in deckhouse doors
• Fit maximum size upper and lower windows in wheelhouse doors
• Wheelhouse doors should be Aluminium
• Provide A-60 fire-rated, fume-tight steel doors for engine room and ECR
entrance
_ __ • Fit with self-closing device
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 38 of 177
LNG PROJECT
• Provide stainless steel lever type passage sets on passageway doors; lockable
sets on sleeping cabin doors, privacy sets on private washrooms and
"VACANT/OCCUPIED" deadbolt latch on common washroom doors
• Fit wheelhouse and deckhouse doors with substantial built-in brass locks and
common key. Supply two (2) keys for each door
• Fit each interior and exterior door with a non-rattling stainless steel automatic
holdback, complete with rubber faced position stoppers
• Fit stainless steel treadplate on all door sills
• Fit exterior and interior non-slip steps on any coaming greater than 300 mm in
height
• Door locks to be provided on a “Master Key” system
305.1 Manholes
• Provide flush watertight bolted panels in main deck to allow installation and
removal of Z-drives parts
• Provide bolted weathertight access plates or panels as required for installation
and/or maintenance access to auxiliary equipment
• Allocate a "hard patch" space on main deck aft for removal of each Z-drive.
Keep area clear of all piping and wiring
306.1 Portlights
306.2 Windows
• Wheelhouse shall be given panoramic view by means of large windows all way round,
with window wipers cleaning system by fresh water. Front and rear windows shall be of
steel fixed type. Thickness of window panes for wheelhouse, cabins and mess room shall
be increased
• All within accommodation areas except wheelhouse to have “double window” where
required and subject to noise level calculation in order to minimize noise and vibration
_ __ transmission.
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 40 of 177
LNG PROJECT
307.1 Ladders
• Ladders shall be of steel and fitted where required. Vertical ladder in excess of
2500mm should be fitted with safety system such as “Railock System or
similar”. Steel rungs or steps shall be fitted under each manhole
• Steps and / or grips shall be fitted for access to the masts, the exhaust stacks
and where necessary.
• Provide minimum 175 mm toe space between ladders and structure
• Provide lateral support as required
• Grind smooth all burrs, sharp edges, weld spatter, etc.
• Fabricate ladders with steel flat bar stringers and steel square bar rungs
_ __ penetrating stringers in accordance with the Builder’s Standard.
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 41 of 177
LNG PROJECT
307.2 Stairways
• Provide safety treads of heavy duty, non-slip composition, with integral nose
moulding, Wooster or approved equal, over complete surface of all interior stair
treads
• Provide a landing of similar non-slip material at top and bottom of each
stairway
• Construct internal access stairs as follows:
- clear width between handrails -800 mm nominal
- clearance around handrail - 75 mm minimum
- slope - maximum 55º from horizontal
- construction - mild steel
- stringers - channel or flanged plate
- treads - flanged plate
• Provide storm rails of 32 mm painted galvanized steel pipe, running the length
of house, P&S
• Support storm rails from underside with welded brackets of 12 mm dia. solid
round
• Return all pipe ends to plating. Provide storm rails in way of louvres of similar
material
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 42 of 177
LNG PROJECT
307.4 Gangway
Provide one (1) set of certificated portable ship to shore aluminium gangway.
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 43 of 177
LNG PROJECT
310.1.1 General
310.1.2 Wheelhouse
• There are very limited areas in wheelhouse for linings, but it is important to
maximize the amount of "noise -absorbent" surfaces in this space. Treat such
areas as follows:
- provide thermal insulation with vapour barrier between stiffeners on panel
surfaces
- cover insulation with heavy duty, ribbed commercial grade carpet tiles
secured to painted, perforated aluminium panels on all vertical surfaces
below windows
- provide perforations with minimum 20% open areas over insulated cavities
- trim with hardwood mouldings
- leave window posts and headers unlined, but coated with high-build epoxy
_ __ paint, matte finish
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 44 of 177
LNG PROJECT
• Line complete boundaries of all wet places (WC's, showers, laundry, etc.), with
a seamless semi-gloss FRP surface, smooth finish on sides and ceiling,
stippled, non-slip surface on floor
• Fit lower house port-lights and windows with well-finished and attractive
fibreglass window boxes
• Arrange window boxes for convenient removal for glass replacement
• Fit decorative, lined curtains on rods to all windows in mess and staterooms
• Wheelhouse window columns to be unlined to maximize visibility (ref. Section
221)
315. INSULATION
• Before application of any insulation, thoroughly paint and clean all surfaces of
oil, grease, dirt, loose paint, mill scale, or any other matter which might impair
bond. Touch-up paint where required before installation of insulation
• Ensure all insulation is in direct contact with surface insulated, including plates,
beams, and stiffeners, without voids
• Secure insulation with pins and cap-type speed nuts
• Provide a sealed vapour barrier of reinforced aluminium foil on heated (inner)
side of insulation on all exterior surfaces
• Provide fire insulation with a reinforced foil face, suitable for thermal, acoustic,
and fire barrier applications
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 45 of 177
LNG PROJECT
• Insulate engine room deckhead, ship's side to lightship waterline, and fore and
aft bulkhead (to floor plate level) with approved A-60 fire insulation
• Protect insulation in entire engine room and exhaust casings with 22 gauge
perforated aluminium, with minimum 20%
316. ASBESTOS
• Cover wheelhouse deck with an industrial grade, ribbed carpet tile. Provide
one (1) spare box of tiles
• Cover deckhouse sole by a flat layer of high strength wire mesh and crack stop
fibre reinforced concrete to an average depth of 35 mm with minimum depth of
25 mm. Carry concrete out to steel bulkheads and around stiffeners and grade
up to eliminate any possibility of water accumulation behind linings
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 46 of 177
LNG PROJECT
325. FURNITURE
Sections 325, 326, and 327 define individual outfit items. Note that not
all items so described may be called up in this Specification.
Sections 330 to 350 specify the items of outfit required for each space.
325.1 Settees
325.2 Tables
• Construct tables of solid core plywood with plastic laminate on top and bottom,
with raised hardwood edging. Top of table to be 250 mm above settee.
Provide minimum 100 mm radius on corners
• Mount tables on painted pipe pedestals, bolted to deck foundation over a pad
of resilient material
325.3 Berths
• Construction - plywood
• Dimensions (inside) - 2,000 mm x 800 mm
• Separation - 700 mm minimum
• Trim, face - plastic laminate
• Trim, edge - hardwood
• Fittings - leeboards
- ladder to top berth
- two (2) lockable drawers (0.06 m3 each)
325.3.3 Mattresses
• Fit each berth with a low toxicity mattress. Size mattresses to suit bunks
325.4 Desks
Sections 325, 326, and 327 define individual outfit items. Note that not
all items so described may be called up in this Specification.
Sections 330 to 350 specify the items of outfit required for each space.
Provide clean outs at corners of all furniture.
326.1 Cabinets
• Cabinet of varnished hardwood, with felt-lined inner back and brass key hooks,
not less than 12 off, or as required for ship. Fit with hinged, framed, safety
glass door and lock
• Cabinet of moulded plastic, equipped with stainless steel shelves and edge
rails, and plate glass mirror on door. Provide door with secure catch
• Arrange shaving light over, and a conveniently located shaver outlet
• Mount cabinet above sinks
326.2 Lockers
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 50 of 177
LNG PROJECT
326.4 Shelving
326.5 Drawers
• Drawers with nylon wear guides and effective concealed catches (no light
spring catches or turn buttons). Submit details to Purchaser’s Representative
for approval before commencing work. Provide every room with a drawer or
drawers, one lockable drawer per occupant
• Provide drawer hardware of attractive modern design in polished anodized
aluminium, concealed or flush mounted where possible
Sections 325, 326, and 327 define individual outfit items. Note that not
all items so described may be called up in this Specification.
Sections 330 to 350 specify the items of outfit required for each space.
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 51 of 177
LNG PROJECT
327.1 Mats
• Dielectric type; in front of switchboard and motor control centre (MCC), size to
suit, in manageable sections
• Fit non-slip door mats inside each door into deckhouse from weather decks
• Notice board of specified dimensions, one half whiteboard, one half corkboard,
with brushed aluminium frame, and clips for secure mounting complete with set
of markers
327.4.1 Television
327.5 Curtains
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 52 of 177
LNG PROJECT
• Provide privacy curtains on double berths separately for upper and lower bunks
• Provide curtains of durable, good quality, fire-retardant synthetic fabric treated
with Scotchguard. Curtains to be 150% fullness, lined, hemmed, weighted,
pleated and bordered, hung on enamelled I-beam track with nylon rollers and
Velcro holds or tiebacks for open and closed positions
• Select fabric colour and pattern to coordinate with overall decor scheme, to
Owner approval
• In general, supply and fit curtains to all windows and ports in cabins, offices,
and mess/ lounge. Curtains to be of selected fire-resistant materials
• Provide curtains lined and weighted where required with 150% fullness, edges
hemmed and bordered. Provide curtains and rods at least 25% wider than
opening and curtains to be of ample length, to approval
• Fit valances unless rods are of decorative exposed type
• Hang curtains on heavy duty aluminium I-beam track from nylon rollers and
best quality drapery hooks. Provide tiebacks
• All materials to be shrink-proof and sun-fast with milium backings or equal
• Single berth
• Mattress
• Wardrobe locker
• Single pedestal desk
• Revolving Arm Chair c/w chair tie downs
• Bookcase
• Coat hooks (2)
• En suite lavatory (ref. 330.7.2)
• Hold backs
• Berth lights
• Table light
• Waste basket
_ __ • Wall Clock
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 53 of 177
LNG PROJECT
• Double berth
• Mattresses and berth curtains (2)
• Berth ladder or steps
• Wardrobe lockers, incl. rack for lifejacket (2)
• Desk (1)
• Chair c/w tie down (1)
• Coat hooks (2)
• Berth lights (2)
• Table light (1)
• Waste basket (1)
330.7 Washrooms
• WC
• Washbasin
• Mirror
• Coat hooks (2)
• Toilet tissue holder
• Exhaust fan
• Safety grabrails, stainless steel
• Paper towel dispenser
• Liquid soap dispenser
• Waste container
• Small Cabinet (1)
• Laundry equipment (Ref 330.8)
• Electric Hand Dryer (1)
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 54 of 177
LNG PROJECT
330.8 Laundry
• Provide laundry facility in lavatory space on main deck, with suitable ventilation
and floor drains. Equip with top quality compact domestic appliances, Miele or
equal, as follows:
- One (1)- 5 Kg washing machine - front loading type, stackable
- One (1)- 5 Kg dryer - front loading type, stackable
- storage cupboard
- ironing board - with hanging rack
- steam iron
• Vent dryer to weather on deckhouse top
• Stainless steel wash basin
• Provide with table, chair, filling cabinet, desk light, waste paper bin,
inclinometer, clock.
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 55 of 177
LNG PROJECT
• Equip galley to a good commercial standard, using first quality appliances. All
appliances finished in stainless steel
• Construct counters and cupboards from fir-ply with decorative plastic laminate
finish, and hardwood trim, with recessed type drawer and door pulls
• All counter surfaces of 304 stainless steel, with minimum of seams, and an
integral back-splash which reaches to underside of cupboards over
• Secure all equipment as required to resist ship motions
• Design galley layout for ease of cleaning
335.1 Refrigerator
• One 12–14 ft3 refrigerator, with lower section freezer, both doors with securing
latch
335.3 Range/Oven
• One hot-top four (4) plate type electric range/oven, approx. 760 mm wide, 220
volt
• Provide stainless steel fiddle rack for top surface
• Include fire blanket in scope of supply
• One off, 0.7 ft3 compact microwave oven, Panasonic or equal, with clock/timer,
rotating tray, and security lock
• One exhaust fan over stove, with integral automatic fire-smothering and
damper system, grease trap, multiple speed fan. All stainless steel finish
• Provide one (1) automatic coffee maker, with insulated thermal carafe
• Provide one (1) electric water cooler, semi-recessed type, stainless steel finish,
in mess area adjacent to gallery
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 56 of 177
LNG PROJECT
335.10.2 Cupboards
• Provide cupboards with fitted retaining racks for dishes, glasses, cups, pots,
pans, etc., suitable for complement plus 10%
• Bulkhead mounted, yacht type teak cup rack, sufficient for complement plus
10%, in mess area
335.11.2 Wastebasket
340.1 Wheelhouse
• Provide one adjustable chart table light, with dimmer and alternate red light
• Provide one (1) desk with side chair, suitable equipment racks and power
outlets, and an adjustable reading light for radio communications as shown on
G.A.
• Fit as part of GMDSS console (Ref. 930)
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 58 of 177
LNG PROJECT
340.1.9 Miscellany
• Also provide:
- control consoles (ref. 910)
- alarms and instruments (ref. 915)
- binocular boxes, teak (2)
- log book rack
- lifejacket racks (2)
• Ref. also to Sec 920.9
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 59 of 177
LNG PROJECT
• Provide Crezon coated tool board and lockable cupboard for all spares and
tools in neatly finished and painted sheet metal cabinet
• Provide 50 polyethylene parts bins of various sizes (Akro or equal), to approval
of Purchaser’s Representative, complete with lockable storage shelving to suit
• Provide and mount a three-door metal tool cabinet
• Provide two (2) steel bins each approx. 0.1 m3 capacity, with hinged cover.
Secure one (1) to pillars in engine room and one (1) in Z-drive space
345.7 Guards
• Provide protection around all rotating drives and other moving parts by bolted
portable guards of rolled expanded metal with stiffened flat bar edges, or by
polished steel railings where they will provide adequate safeguard
• Equip all stores spaces shown on Drawings with shelving, clips, and hangers
arranged to take maximum advantage of available space
• Provide light, drainage, and ventilation in all store spaces
• Install an approved CO2 or equal total flooding system for protection of engine
room, complete with manual actuators, controls, and alarms in accordance with
Regulatory Authority requirements. Stow cylinders in designated locker on
main deck, subject to compliance with Regulatory Authority requirements
• Fit ventilation system with dampers arranged to close automatically and supply
fan to shut down automatically on deployment of fire extinguishing system
• Arrange shutdown for ventilation dampers and fans as a failsafe "energize to
run" system.
• Supply and install extinguishers to the approval of the National Authority, but
no less than the following types and numbers:
- 4.5 kg dry chemical (ABC) fire extinguisher in:
- mess area (1)
- galley (1)
- engine room ECR near switchboard (1)
- 7 kg CO2 fire extinguisher in wheelhouse (1)
- 10 litres foam:
- machinery space; adjacent to WTDs (2)
- engine room top of stairs (1)
- other strategic locations in engine room (2)
- 23 kg dry chemical (ABC) semi-portable fire extinguisher in engine room
(1)
• Equip vessel to satisfy applicable SOLAS regulations, plus local flag state
safety regulations, incorporating at least the following:
365.2 Liferafts
• Supply and install two (2) approved 15-man SOLAS approved inflatable liferafts
in containers, one each P&S, with:
- hydrostatic release permitted by Regulatory Authorities
- Class A equipment
- installed in aluminium launching rack, suitable to clear ship side
- certificate date to be latest possible
365.4 Lifebuoys
• Supply and install six (6) approved liferings with "retro-reflective" tape:
- with 27.5 metre heaving line only (2)
- with heaving line, whistle, and strobe lights (2)
- with heaving line and self activating smoke signal (2)
• Ref. 0.0.16.3.1 for markings
365.5 Lifejackets
• Supply approved inflatable vest type lifejackets, complete with lights and
whistles, and stow in racks:
- in crew cabins; one per person (10)
- in wheelhouse (2)
- in ECR (2)
• Ref. 0.0.16.3.1. for markings
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 62 of 177
LNG PROJECT
380.0 General
All paints shall be of durable marine paint. The final color scheme shall be
decided in consultation with the Purchaser.
All paintwork shall be carried out according to the paint manufacturer’s
recommendation.
All steel used in the construction of the Vessel shall be shop blasted and
immediately coated with shop primer suitable for the main paint system.
Paint material for outside shell and exposed decks shall be pure epoxy paint for
primary coat and zinc acrylate paint or epoxy paint for finish coat in general.
Airless spray application shall be required to achieve the required dry film
thickness specified.
Brushing and rolling applications will only be allowed for relatively small areas
and after Purchaser’s approval. Where local damage to the primer occurs during
subsequent construction, the coating to be made good before a subsequent coat
will be applied.
The Purchaser shall have the choice of standard color schemes in conjunction
with the Builder. The Purchaser’s funnel color and funnel insignia design shall be
painted by the Builder upon receipt of the appropriate color and design from the
Purchaser.
All hull structural steel plates and sections shall be shot blasted. After shot
blasting, the steel shall be immediately coated with inorganic zinc silicate shop
primer. The grade of shot blast cleaning shall be in accordance with the Swedish
standard SIS Sa 2.5.
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 63 of 177
LNG PROJECT
• Provide paint of best quality for marine application, and for suitability to the
specific service and specific application to all metal surfaces of vessel
• Provide all paint by a single manufacturer, having background of successful
experience in marine field and approved by Purchaser’s Representative,
International Paints or equal
• Provide a coating system to provide 36-months continuous protection after
delivery of vessel.
• Provide fire-retardant low flame spread high temperature tolerant type paint
where required such as funnel unless otherwise approved
• Comply with all relevant safety and environmental regulations
• Carry out surface preparation, application techniques and conditions, drying
between coats, coverage, a mixture of thinners, mixing instructions, etc., in
strict accordance with paint manufacturer's instructions. Provide necessary
means (such as dryers, blower, etc) to meet the conditions for application and
curing of paints as required.
• Document air and surface temperatures and humidity levels during each
painting process to demonstrate compliance with manufacturer's requirements
• Ensure steel behind insulation is fully coated prior to installation of insulation
• Paint all fittings in sight from outside of vessel to correspond with surrounding
area, or as required by Purchaser’s Representative
• Protect final colour coats from soiling or injury until vessel is handed over to
Owner. Touch-up or repaint soiled, damaged, or missed areas to satisfaction
of Purchaser’s Representative. Take care in the application of final coats to
ensure furnishings and fittings are protected from excess spray paint and, in
particular, give special consideration to electronic or other equipment liable to
more serious damage due to excess spray
• Ensure priming coats used as pre-weld primer are non-toxic to welders and do
not detract from quality of weld
• Wire brush areas of excess weld primer in way of welds to eliminate porosity
due to excess primer thickness
380.2.2 Wood
- nameplates
- oil grooves
- packing
- pump shafts
- screw threads
- stainless steel
- strainers
- universal joints
- valve stems
- zinc anodes
and, in general, all working parts
• Shift keel and bilge blocks alternately to ensure all cleaning procedures and
paint coats are properly applied in areas of blocks
• Stripe coating of internals/stiffeners as required to ensure sufficient dry film
thickness is achieved
• In event topsides, etc., are soiled prior to delivery, fully clean and wash them
down with fresh water
• Prior to delivery, remove all protective coatings, thoroughly clean all interiors,
and (where applicable) polish all interior surfaces. This includes floor
coverings, deckheads, bulkheads, furniture, fixtures, windows, etc.
• Coat deckhead of Z-drive compartment and hold area with a sprayed-on anti-
condensate treatment
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 66 of 177
LNG PROJECT
• A sufficient number of sacrificial Aluminium anodes shall be fitted to the shell plate
around rudder propeller, nozzle, bilge keels, sea chests, etc to minimize galvanic
action. Aluminium anodes shall have the lifetime of thirty-six (36) months after delivery
and shall be secured with studs on pads and nuts.
• Determine quantity and distribution of anodes in consultation with supplier and
Purchaser’s Representative
• Continuously weld 12 mm doubler plates to hull in way of anodes
• Fit two (2) anodes in each sea chest
• Protection of Z-drive assembly is responsibility of manufacturer
390.3 Covers
• Provide NRV covers for rescue boat, radar, searchlights, and hawser
***
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 67 of 177
LNG PROJECT
401. GENERAL
• Equip vessel with two anchors and stud-link chain cable, sized in accordance
with minimum Class requirements
• The following equipment is listed for preliminary guidance only. Ensure final
equipment selection meets Class requirements
405.1.1 Anchor
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 68 of 177
LNG PROJECT
• At chain cable ends, provide shackles of hot-dip galvanized, bow type, forged,
quenched, and tempered, with alloy pins. Nominal size same as adjoining
cable. Secure shackle pin with stainless steel split pin
• Joining shackles, if required, to be patent type split links
• Fit heavy fabricated chain guide at top of hawse pipes and at lead to spurling
pipes
• Incorporate manual cable stoppers to Class requirements
• Provide warping head and fairlead on towing winch and hawser winch as
specified below for general line handling
• Integrate H-type double mooring bitts, fabricated from heavy wall pipe into
bulwarks P&S
• Cut away bulwarks in way of bitts, neatly cap ends, and grind all corners
smooth
• Angle bitts to match bulwark slope and sheer
• Fabricate crossbar from heavy wall pipe and pass through uprights
• Fit tops with heavy plate caps
• Terminate bollards on plate inserts in deck, with suitable stiffening under
410.1.2 Bollards
• Fit heavy duty double bitt type pipe bollards, 310 dia., on aft deck as shown on
Plans
• Weld securely to deck over heavy inserts
• Reinforce deck under
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 69 of 177
LNG PROJECT
• Fit stainless steel round bar (50 mm SR) oval pattern mooring rings into
bulwarks in locations shown; clear opening approx. 200 x 300 mm
• Fit 300 dia. cast steel roller buttons, if required, on foredeck to align load from
winch warping head to mooring pipes and bitts
• Provide fabricated steel stools as required for height adjustment
• Equip vessel with a heavy duty hawser winch on foredeck for ship assist and
escort operations
• Provide a towing winch on aft deck for conventional towing
415.1 Winches
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 70 of 177
LNG PROJECT
• Brake
- Towing Brake
- capacity (mid drum) - 138 tonnes
- features - self-energizing power and hand-wheel
operated
- proportional feathering control on power brake
• Dynamic Brake - proporsional dynamic brake, with adjustable
rating from 50 – 75 tonnes line pull to match
rated escort performance. Final selection of
brake performance base on escort analysis.
• Line pull/speed, first layer - 30 tonnes at 6 metres/minute
- 10 tonnes at 10 metres/minute
- 35 tonnes stall
• Provide a single aperture, wide "A" style staple to suit lead from both sides of
winch drum, with maximum width at base
• SWL = 165 tonnes at top of staple, leading 45° abaft beam
• Construct according to Design Drawing
• Provide support under deck as defined
• Finish all surfaces in contact with hawser in 10 mm, polished 316 stainless
steel cladding
• Ensure no snags or burns, etc., are anywhere in line contact area
• Provide a heavy duty "H" bitt aft of towing winch as shown, to prevent
transmission of transverse loads to winch and to provide spooling to winch
drum
• SWL = 55 tonnes at 90° to tug
• Construct according to Design Drawing
• Provide support under deck as defined
• Ensure no snags or burns, etc., are anywhere in line contact area
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 72 of 177
LNG PROJECT
• Provide a compact, low profile, radial arm davit for rescue boat with 6.0 metre
boom
• Install in full compliance with SOLAS regulations for operations under
maximum heel and trim, etc.
• Ensure davit is capable of manual and stored-power operation per SOLAS
• Davit operation equipment to be stored in a weathertight enclosure.
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 73 of 177
LNG PROJECT
• Supply one (1) towing hawser, Dyneema or equal, 165 tonne minimum
breaking strain, 200 metres finished length, with a 2 metre soft eye spliced into
both ends
• Provide open weave braided nylon protective cover for outer 6 metres of
hawser
• Provide a weatherproof cover for hawser on winch, with suitable fasteners (ref.
390.2)
• Provide 500 metres of 44 mm OD, steel wire rope, not less than 135 tonnes
breaking strain
• Provide a closed Spelter socket at one end
• Installation details, rubber composition, and durometer for all rubber fenders to
be approved by Purchaser’s Representative prior to ordering
• Paint all steelwork behind fenders according to Paint Schedule (ref. 380) before
final installation of fendering
• All small fittings such as pins, bolts, nuts, rods, washers, etc., of 316L stainless
steel
• Secure extruded fenders with stainless steel margin bars and stainless steel
bolts, double washers, and Nylok nuts at regular intervals, generally as detailed
on Drawing
• Ensure edges of steel next to rubber are well rounded
• Plug exposed ends of rubber fenders with solid rubber plugs
• Secure rubber plugs with adhesive
• The fenders shall be constructed from low friction extruded rubber material in
accordance with BS 2782 or approved equivalent.
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 74 of 177
LNG PROJECT
• Provide and fit extruded hollow "D" rubber fenders, 300 x 300, with minimum
125 "D" bore along main sheer, focsle sheer, and diagonals
• Fit "W" type extrusion, approx. 450 mm thick size around stern
• Fit a water-spray system to wet all external fender contact areas, supplied from
general services pump
• Use all galvanized steel pipe and bronze fittings
• Ensure nozzles are protected from impact
• System to be activated by pushbutton control in wheelhouse
***
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 75 of 177
LNG PROJECT
501.1 General
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 76 of 177
LNG PROJECT
• Prepare a solid body dynamic analysis of main engine mounting system and
connected shafting to verify there will be no critical speeds in operating range
• Include stiffness characteristics of misalignment couplings and demonstrate
that displacements expected at crankshaft and all piping connections (cooling,
fuel, air, exhaust) due to change in torque reaction forces between no load and
full load are within the capabilities of flexible connections, and that forces
transmitted to engine (particularly crankshaft and turbo charger) due to these
displacements are within the limits established by engine manufacturer
• Provide two (2) marine diesel engines complying with latest emission standards
and configured for air start and heat exchanger cooling. Provide engines
suitable for installation at a slight decline toward free end of not more than 5°:
- make/model - Niigata 6L28HX
- type - vertical, single acting, 4-valves, 4 cycles,
trunk piston type with turbocharger and
charged air cooler
- number of set - two (2)
- rated output - 1,618 kW x 750 rpm at clutch output and
shaft end
- number of cylinders - six (6), in-line
- fuel oil - marine diesel low sulphur oil or gas oil;
corresponding to the following standards:
- ISO 8217, F-DMX and F-DMA
- ASTM D975, Grade 1-D and Grade
2-D
- lubricating oil - corresponding to SAE No. 40
- fuel supply system - feed pump, engine driven
- lubricating system - forced lubrication (wet sump system)
- starting system - compressed air starting 3.0 MPa (30
kgf/cm2)
- cooling system - piston with lubricating oil (system oil)
- turbocharger, non-cooling type
- charged air cooler with seawater
- lubricating oil cooler with seawater
- freshwater cooler with seawater
- fuel injection valve, non-cooling type
- cylinder jacket and head with freshwater
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 77 of 177
LNG PROJECT
510.2.1 Starting
• Provide engine configured for air starting suitable for connection to ship's
compressed air system and including:
- automatic prelube with emergency bypass
- cranking controls
- controls for engine room and wheelhouse starting with manual palm valve
in solenoid valve bypass
- "Y" type strainer for incoming air
- flexible hoses for all connections to ship's piping
• Provide interlocks to prevent engine starting while clutch is engaged, and to
prevent starting from wheelhouse while on engine room control
• Provide a complete set of approved flexible hose connections suitably rated for
the intended duty and appropriate for a resiliently fixed engine
• All flexible connections to terminate in JIS standard pipe threads or flanges
• Fit engines with air cleaner with service indicator suitable for operation with
_ __ unfiltered engine room air with temperatures up to 45° C without de-rating
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 78 of 177
LNG PROJECT
• Supply a dry exhaust expander and flexible connector to ship's exhaust piping
capable of accommodating expected displacement of exhaust connection
between cold, no load condition; and hot, full load condition (see 760.1)
510.2.10 Mounting
• Install engine on resilient mounts, approved for purpose, and with not less than
10 mm of allowable excursion
• Verify performance of mounts by analysis before finalizing shaft line
components
• Refer to Section 502 for requirements for Dynamic Analysis of the engine
mounting system
• Epoxy/chock-fast will be used for mounting the engines
• Alignment to be confirmed within the manufacturers limits and tolerances
before the mounting of the engines is completed
• Supply, separately packaged, a complete set of special tools and spares for
main engines
• Apply preservative coatings and seals on all spares appropriate for long term
warehouse storage
• See also Section 0.17
520. CLUTCHES
• Provide local and remote (wheelhouse) controls for all clutches, complete with
engaged/ disengaged indication, and interlocks with engine starting (see
Section 530 and Part 900)
• Provide a remote mounted slipping clutch system in each shaft line, capable of:
a. transmitting full engine power to Z-Drives during Fi-Fi operations, with
approx. 600 kW driving front PTO, and
b. reducing propeller rpm from idle speed to approx zero rpm when engines
are at idle
• Fit two hydraulic activated, multiple disc, wet type dual modulation slipping
clutches, Niigata model HLP80Y, with PTO device for driving hydraulic steering
pump
521. COUPLINGS
• Provide torsional/misalignment couplings between main engines (resilient
mounted) and the slipping clutches (hard mounted), and the fire pump PTOs
(hard mounted)
• Ensure coupling characteristics satisfy the performance criteria defined in
Section 502
530. Z-DRIVES
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 82 of 177
LNG PROJECT
• Provide one (1) shipset of special tools, supplied by Z-drive manufacturer for
maintenance and overhaul, including all special wrenches and pullers for
complete disassembly of unit
• See also Section 0.17
• Provide foundations for all main and auxiliary machinery in accordance with
good shipbuilding practice. Align load bearing points of isolators with engine
girder webs or brackets
• Bolt Z-drives into stern structure of vessel
• Thoroughly paint Z-drives with anti-corrosive and anti-fouling paints as
specified in Section 380
• Carry out final alignment while afloat
• Install main engines and align drive system components to within precision
tolerances, notwithstanding presence of shaft flexible couplings
• After sea trials, recheck alignment; Shipyard to provide Owner with alignment
tool(s)
• If alignment has moved outside acceptable tolerances, realign as necessary
• Mount clutches, Fi-Fi pumps, and shaft bearings on solid steel (poured epoxy
chocks to be used after Purchaser’s approval)
• Mount main engines on resilient mounts
• Fit collision stops on all mounts, for all directions of travel
• Fit permanent jacking bolts on main engine mounts and shaft bearings for
vertical, lateral, and longitudinal adjustment
• Where poured epoxy chocks are fitted, provide parting compound between
selected mating surfaces to facilitate removal of components
• Provide sub-plates for main engine mounts if necessary in order to set mounts
on Chockfast
• Provide lube oil and coolant, complete with coolant treatment in accordance
with machinery manufacturer's requirements
• Ensure Purchaser’s Representative and equipment supplier's representative
are present at start-up of all propulsion machinery, and that equipment
supplier's approval to start equipment is obtained before commencing start-up
• All foundation holes to be drilled through and made smooth and not cut
• Installations according to manufacturers requirements.
***
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 84 of 177
LNG PROJECT
601. GENERAL
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 85 of 177
LNG PROJECT
• Perform a design check on the specified power capacity to reflect all final
equipment proposed for installation
• Conduct an electrical load analysis detailing all known electrical services for
vessel. Apply reasonable demand factors appropriate to the service taking into
account specific operating conditions for vessel. Allow a minimum margin of
15% spare capacity above calculated worst case load. Advise Purchaser’s
Naval Architect if the specified generator set lacks sufficient capacity and work
to resolve the discrepancy
• Provide distribution equipment spare capacity as follows:
- transformers - 10%
- distribution panels - minimum of two spare circuits fitted with 3 or
2 pole breakers as appropriate
- main panel board feeders - minimum of 15% spare Ampacity
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 86 of 177
LNG PROJECT
601.5 Documentation
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 87 of 177
LNG PROJECT
601.8 Grounding
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 88 of 177
LNG PROJECT
604. DC POWER
604.1 Batteries
• Provide dry fit marine type distribution service batteries or approved equal
• Provide sealed commercial batteries, or approved equal, for starting batteries,
and arrange to provide required voltage and cranking Amps
• Battery capacities to be determined by DC load analysis
• Select battery Ampere-hour discharge ratings closest above that required for
the services supplied
• Solder all battery terminal clamps to wire leads
• Provide marine type DC power supplies suitable for servicing DC load without
battery connected and for charging batteries as necessary, in self-ventilated
drip-proof enclosure suitable for bulkhead mounting
• Rate power supplies to supply the load demand under:
- emergency conditions - supply DC load and charge fully depleted
batteries within 10 hours
- normal conditions - supply DC load and continuously maintain
float output voltage on fully charged batteries
• Operating characteristics:
- input voltage - 220 volt, single phase, 50 Hz
- output voltage - 24 volt DC as required
- output regulation - ± 1% with ± 10% input voltage variation
- features - independent float and equalize charge
voltage adjustment with automatic switching
between float and
equalize voltage, operator controlled variable
equalize cycle time, adjustable equalize timer
suitable for batteries provided
_ __ - float and equalize mode indication
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 89 of 177
LNG PROJECT
One (1) set of charging and discharging board shall be installed in the
wheelhouse.
The charging and discharging board shall be of independent, self-supported
cubicle type, mode of finely enameled steel plate paneled on strong steel frames,
and equipped with insulated hand rails in front of the board
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 90 of 177
LNG PROJECT
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 91 of 177
LNG PROJECT
605.1.1.3 Alarms
• Fit engines with the alarm sensors specified in Section 915, pre-wired to
terminal boxes on engines, for connection to shipboard alarm system
605.1.2 Generators
Two (2) main generators are provided, each capable of supporting the full
electric load demand for the vessel.
605.1.2.1 Rating
605.1.2.3 Accessories
605.1.2.4 Windings
• As per 605.1.1.1
• As per 605.1.1.2
605.2.1.3 Alarms
• Fit engines with the alarm sensors specified in Section 915, pre-wired to
terminal boxes on engines, for connection to shipboard alarm system
605.2.2 Generator
605.2.2.1 Rating
605.2.2.2 Construction
• As per 605.1.2.2
605.2.2.3 Accessories
• As per 605.1.2.3
605.2.2.4 Windings
• As per 605.1.2.4
605.3 Controls
• Provide 3 phase, 380 volt, 3 pole, 4 wire, 80 Amps, heavy duty circuit breaking,
bulkhead mounted, MALE receptacle suitable for terminating shore power cable.
_ __ Circuit Breakers to be provided for protecting fixed installation in event of fault.
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 95 of 177
LNG PROJECT
• Rate genset starting batteries for dead ship start condition at 32° C
610.1 Construction
• Provide fully insulated electrical devices on doors and panels or bond devices
to door through the instrument body or fixing points. Cover connections to all
equipment which may be live when door is opened with suitable insulated
covers
• Bond doors and panels to switchboard structure using extra flexible copper
cable connection wires fitted with a cable lug and bolted to a stud permanently
affixed to door
• Provide a complete and continuous copper bus (minimum size 25 mm x 6 mm)
throughout assembly. Provide facilities to bond bus to hull. Permanently affix
bus to switchboard structure and use for bonding equipment and components
to ground
610.3 Nameplates
610.4 Bus
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 97 of 177
LNG PROJECT
• Provide generators that can be locally and remotely started and stopped.
Ensure there is no need for engine room attendance with regard to operation of
generators
• Provide controls at main switchboard and in wheelhouse to select operating
generator and cause its connection to switchboard. Control to enable one of
_ __ three operating conditions to be implemented, MAIN/OFF/STANDBY. When
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 98 of 177
LNG PROJECT
selected for MAIN, generator to start and connect to switchboard. In the event a
generator is already connected, this control will cause generator to be of same
voltage and phase sequence before being allowed to be connected in parallel.
In event of an electrical system blackout, controls will cause automatic start up
and connection to switchboard of selected generator for STANDBY operation
• Install a green light for each generator in wheelhouse to indicate which
generator is online. Connect green light to instrument dimmer circuit
• Provide controls for starting, stopping, and cranking engine generator sets.
Provide controls which:
- cease cranking once engine starts
- comply with engine manufacturer's requirements regarding cool down time
between cranking attempts
- incorporate over-crank alarm and activate shut-down after three (3)
unsuccessful cranking attempts
- enable "restart attempts" only after cranking controller is reset
• Provide engine starting and stopping controls at each engine and emergency
stop in the wheelhouse. Provide emergency starting controls mounted locally
at engine, connected to bypass all system shut-downs and interlocks
• Provide one (1) spare engine cranking controller
• Provide engine running indication in wheelhouse
• Provide separate primary voltage (380 volt) distribution section integral with
switchboard assembly, complete with:
- 3 pole moulded case circuit breakers, fitted with fixed thermal and
adjustable magnetic elements in each phase
- ground fault indicating lights complete with test facility
• Provide all required circuit breakers and devices to switch and control feeders
and motor starters
• Provide 220 volt, 3 phase, 3 wire, panelboard within switchboard to distribute
secondary voltage power. Distribute power to secondary 220 volt using 2 or 3
pole moulded case circuit breakers rated as required
• Fit 220 volt panelboards with:
- transformer secondary voltmeter and switch (to read each phase voltage)
- transformer secondary power available indicator
- Ammeter and switch (to read each phase Amps)
- ground fault indicating lamps complete with test facility
• Provide spare circuit breakers for single phase and three phase loads
respectively in accordance with Section 601
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 99 of 177
LNG PROJECT
• Lighting distribution board shall be of dead front wall mounting steel structural
type and be composed of 2-pole moulded case circuit breakers.
Navigation light indicator panel shall have audible and visible indications of the
failure of the navigation light.
610.10 Documentation
• Provide a copy of circuit breaker short-circuit rating data and circuit breaker trip
unit protection characteristics
• Distribute secondary power (220 volt services ) from a 220 volt, 3 phase, 3 wire
panel board fitted with 3 and 2 pole circuit breakers for outgoing three and
single phase loads
• Distribute primary power from main switchboard
• Provide panel boards with hinged doors complete with lockable catch. Use
flush mounted cabinets recessed into bulkhead linings in accommodation
areas, and drip-proof surface mounted units on bulkheads in machinery spaces
and other working areas
• Provide circuit directories inside cabinets. Identify all circuits with load power
and circuit breaker size
• Provide circuit breakers rated as required by the service. Calibrate engine
room circuit breakers for 50° C ambient.
• Provide each panel unit with a minimum of 2 spare circuits fitted with 3 and 2
pole circuit breakers as appropriate.
• Distribute single phase loads equally over the three phases
616. TRANSFORMERS
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 100 of 177
LNG PROJECT
618.1 Cables
• Use prefabricated block, stuffing tubes, or poured liquid cable transit sealing
systems at all watertight and fire-retarding bulkheads.
• Provide reinforcing collars with smooth edges for cables passing through
beams and girders
• Provide chaffing collars or sleeves for cables passing through minor bulkheads
• Install cables inside unless outside installation is necessary for specific exterior
mounted equipment. Provide corrosion protection on all cables located
outside. Provide mechanical protection for cables installed in areas likely to
take seas, or installed in working areas of deck
• Do not install bronze cable armour directly on aluminium structures
• Route cables as directly as possible on fore to aft running wire ways. Route
branch lines at right angles to main runs. Avoid high fire risk areas
• Avoid working areas with a high potential risk of damage. Provide additional
mechanical protection for cables whose installation is necessary in such areas
• Run cables point-to-point without splices or joints. Use connection and junction
boxes only when supplying equipment such as heat tracing cables and light
fixtures which are provided with their own power supply cables
• Install a maximum of two (2) power cables vertically in a bank (double banked).
Maintain approx. 25% free space on rack or tray. Protect cables from chaffing
on tray edges
• Conceal main wire ways running through accommodation areas behind
removable panels. Use surface mounted decorative cable mouldings to drop
down to light switches, receptacles, and other surface mounted fixtures
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 101 of 177
LNG PROJECT
• Install cables under engine room floor plates only where alternative routing is
not practical and after approval by the Purchaser. Use galvanized steel conduit
to protect such cables
• Install cables into bottom of equipment, as far as possible. Provide watertight
entry glands for top and side entries, and for all watertight and vapour-proof
equipment
• Terminate all cables inside equipment enclosures. Support cables and provide
cable strain relief at terminal connections
Group Service
1 (Indifferent) power and lighting cables
2 (Sensitive) Control and Communication cables
3 (Jamming) RF Cables, Echo Sounder and Speed Log Transducer
Group 1 2 3
1 0 cm 20 cm
10 cm
2 10 cm 10 cm
0 cm
3 20 cm 0 cm
10 cm
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 102 of 177
LNG PROJECT
• Use standard 220 volt receptacles in all spaces except those on open deck,
which will be watertight receptacles fitted with spring-closed covers
• Use GFI type receptacles in galley, bathrooms, and accommodation spaces
619. RECEPTACLES
620. MOTORS
• Provide single phase, 220 volt, double pole, manually operated, motor starters
for single phase motors. Rate manual control for twice rated motor current
• Illuminate vessel with marine type fluorescent and incandescent light fixtures
• Provide rough service or vibration service, "tough-skin" type incandescent
lamps, according to location. Provide spare lamps as per Section 155
• Provide watertight connection boxes in machinery compartments, etc. Use
knockout boxes behind linings only. Fit junction boxes with terminal strips.
Provide approved type switches, three-way where necessary, recessed or
surface mounted, and arrange near entrance doors
• Incorporate watertight toggle switches complete with PVC covers for light
switches for Z-drive compartment, deck lockers, and hull void
I
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 104 of 177
LNG PROJECT
b. Deckhouse:
• 2 x 20 Watt fluorescents:
- deck corridor (2)
- crew rooms (one each) (4)
- entry lobby (2)
- galley (4)
- mess room/lounge (4)
• 60 Watt recessed incandescents:
- lavatories, with timer (1)
- laundry (1)
c. Lower Deck:
• 2 x 20 Watt fluorescents:
- corridor (2)
- ECR (4)
- engineer's store (4)
- crew rooms (2 each)
- galley store (3)
- deck store (3)
- lavatory space (3)
d. Machinery Spaces:
• Heavy duty, 2 x 40 Watt fluorescent fixtures (12):
- engine room (minimum 8)
- Z-drive compartment (4)
• Surface mount, watertight standard
• Radio interference suppression standard K
• Opal polycarbonate (unbreakable) diffuser
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 105 of 177
LNG PROJECT
625.3.2 Floodlights
625.3.4 Searchlights
• Install two (2) remote controlled searchlights on wheelhouse top with internal
controls at convenient location for helmsman. Searchlights as follows:
- 1,000 Watt, tungsten Halogen bulb; 220/3/50 power supply
- remote "joystick" type control
• Mount searchlights to effectively illuminate an arc of at least 240°
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 106 of 177
LNG PROJECT
***
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 107 of 177
LNG PROJECT
• Piping diagrams are intended as diagrams only and should not be interpreted
as piping arrangements or layouts
• Prepare calculations to verify the design of each system including:
- piping pressure drop calculations and pump capacity evaluations for each
pumping system including NPSH calculations for bilge and fire system
- expansion tank capacity calculations for engine cooling systems
• Provide piping, valves, fittings, and associated equipment suitable for the
working pressure to which they may be subjected in service, and test to static
pressure 1.5 times working pressure for a minimum of 2 hours unless
otherwise specified
• Fit spring-loaded shutoff valves to all tanks containing hydrocarbons
• Provide all pumps or equipment with shut-off valves on suction and delivery
side to isolate them for maintenance
• Vent all system high points, drain all system low points
• Design system layout to accommodate expansion or dynamic forces
transmitted by piping systems to equipment connections or structural members
• Provide space for servicing, disassembly, and removal of equipment and
components as recommended by manufacturer or as indicated
• Provide takedown joints to facilitate removal of equipment and piping for
maintenance and repair of vessel
• All piping and fittings shall be in accordance with Japanese Industrial Standard
(JIS). Unless specified otherwise, the following standards shall be allied:
- pipe - JIS 3454 STPG or JIS 3455 STS seamless
- fittings - JIS B2311, JIS B2312, JIS B2313, JIS B2316
- flanges - JIS B2220
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 108 of 177
LNG PROJECT
• Use smooth bends of four times (4 x) diameter minimum radius or long radius
elbows to all bending parts
• Arrange piping to ensure that "pockets" are not generated in pipe work
• Use eccentric type reducers as required to eliminate pockets, and to facilitate
drainage
• Galvanising to be carried out after the pipe fabrication is fully completed. In
addition, during outfitting no welding to be carried out on galvanised pipes.
• Use smooth bends of four times (4 x) diameter minimum radius or long radius
elbows
• Arrange piping to ensure "pockets" are not generated in pipe work
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 109 of 177
LNG PROJECT
• Join high pressure systems using solid drawn tubing by JIC flareless type
compression fittings
• On low pressure services use "Victaulic" or equal serrated type couplings for
takedown connections, where approved
• Provide expansion bends wherever straight runs of piping extend between rigid
bulkheads
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 110 of 177
LNG PROJECT
• Provide hose clamps of T-bolt type, all-stainless steel. Screw type hose
clamps are not acceptable. Where clamps are used, complete pipe ends with
hose barbs to resist thrust forces in piping
• In cases where vibration or noise in pipes would transmit to hull structure in
way of pilot house or day room, provide vibration isolating mounts
701.4 Valves
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 111 of 177
LNG PROJECT
704. INSTALLATION
• Descale internal surfaces of fuel, oil, and hydraulic systems and do not
contaminate thereafter by welding
• Clean external surfaces of galvanized piping damaged by welding or otherwise
and coat with inorganic zinc
• Clean all lube oil, fuel oil, and hydraulic pipes including fittings after fabrication
or assembly, and before installation. In addition, clean all hydraulic piping by
pickling in hot acid or by sandblasting, after which wash and neutralize piping,
wash again, dry, and coat with oil compatible with end use, to satisfaction of
equipment vendor and manufacturers
• After installation of lube oil, fuel oil, and hydraulic oil piping as described above
is complete, clean each entire system by continuously circulating hot flushing
oil at minimum two times (2 x) design velocity through each system, using
temporary strainers and filters until a clean system is obtained. During
flushing, fit bypasses around each engine, gear, hydraulic device, and
regulating valve
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 112 of 177
LNG PROJECT
• Identify all piping with standard colours designating contents and arrows
showing directions of flow. Provide labels of self-adhering PVC tape, "Flo-
Code" or equal. Indicate name of fluid on pipe band. Colour coding to be as
follows where approved by Purchaser’s Representative, or JIS standard colour
coding:
• Provide all tanks with means to fill, vent, and sound as per this Section, and as
shown on individual System Diagrams
• Provide deck fills for integratal tanks as indicated on Piping System Diagrams
• Provide local fills for loose tanks as indicated on Piping System Diagrams
• Provide spill coamings around fill and vent terminations for all tanks that could
contain hydrocarbons. Fit coamings with drains to oily water tank with shut off
valve under deck, and normally open clean water drains to adjacent deck.
Grade bottom of spill containment area to drains with cement or similar
impermeable filler. Volume of containment to be no less than required by
regulations
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 113 of 177
LNG PROJECT
• Provide a means of indicating tank level over a range of at least 10% to 90%
• Where glasses are used, a spring-loaded shut-off valve must be installed
(hydrocarbon tanks only)
• All sight glasses to be of glass not plastic material
710.1 Tanks
710.3.1 System
• Provide a duplex positive displacement pump set capable of transferring fuel oil
between storage tanks and able to draw fuel oil from any storage tank and
_ __ discharge to day tanks working separately or in tandem
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 114 of 177
LNG PROJECT
• Provide duplex primary fuel water separator/filter complete with priming system
for main engines
• Provide simplex primary water separator/filter complete with priming system for
each gen-set using same filter elements as provided for main engines
• Isolate each set of filter/water separator units by valves and fit with a bypass
• Provide connections to all fuel filters via flexible hose
• Arrange all filters and water separators drains over drip trays for convenient
water and/or fuel oil drainage into a portable container
• Incorporate differential pressure alarms and water sensors on primary fuel
filters
• Provide main bilge pump capable of pumping out bilge water or supplying
water from sea chest to fire hydrants
• Pump to be as follows:
- type - vertical centrifugal, close coupled with
mechanical seal
- construction - all iron, 316 stainless steel shaft
- performance - to Class requirements for fire and bilge
service; minimum 80 m3/hour at approx. 3
bar
- power - 380/3/50
_ __ - Impeller - Ni Al Bronze
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 115 of 177
LNG PROJECT
• Fit a basket type strainer on each sea suction. Provide basket of 316 stainless
steel with an open area at least four times (4 x) area of the pump suction with
opening size maximum 90% of maximum particle size that pump can pass
• Provide remote operator on sea chest valve operable from fire control station
• Set monitors to maximize range of motion and fit limit stops to prevent
discharge waterjet damaging mast, electronics, or antennae
• Provide one sea chest for each pump, not to be used for any other service. Fit
each sea chest with hinged GRP grating, air vent pipe, and compressed air
blow-down connection
• Size sea chest openings to give a total area at least three times (3 x) suction
pipe area with individual openings less than pump maximum particle size
• Increase plate thickness in way of sea chests by a minimum 3 mm over
adjacent plating, and fit suitably sized anodes in each sea chest.
730.3 Pumps
• Provide two (2) monitors to Fi-Fi I standards, and fit adequate bracing to
counteract monitor reaction forces:
- type - Fire-Fighting 1 monitor, short barrel type
- performance:
- water - 1,200 m3/hour, 120 metre minimum throw
length, 45 metre minimum throw height
- foam - 300 m3/hour, 50 metre minimum throw height
- nozzle - locally or remotely operable fog/jet
_ __ - materials - stainless steel and bronze
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 117 of 177
LNG PROJECT
• Provide a foam system suitable for use with protein foam concentrate. Use
316 L, Schedule 40, stainless steel pipe for foam piping with stainless steel
valves
• Fit freshwater flushing connections to enable all piping in contact with foam
concentrate to be washed out
• Provide two (2) balanced in-line foam proportioners, one in each fire pump
discharge line:
- material - stainless steel body with bronze nozzle
- size - to suit prescribed foam and water rates
- accessories - nozzle adjustment to vary foam concentrate
between 1% and 6%
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 118 of 177
LNG PROJECT
• Provide two sets of oil dispersant system with two spray booms of an
approximately 4.5 meters long shall be installed.
• Provide with an oil dispersant capacity as specified in Part 0.0.2.2
• Provide suitable dispersant pump as per manufacturer recommendation
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 119 of 177
LNG PROJECT
735.1 General
The vessel shall be provided with plate cooler cooling system separated into and
independent port and starboard system for the main propulsion system and a
separate system for auxiliary system. Each cooling system to be able to draw
from independent sea chest with main line crossover between port and starboard
sea chest for back-up purposes.
• Install the following according to system Diagram, and according to final heat
balance analysis, to be reviewed and approved after selection of all final
components:
- main engine cooling circuit:
- provide each main engine with a separate cooling system complete
with plate type heat exchanger and engine-mounted jacket water
circulating pump
- provide standby cooling freshwater at 60 m3/hour x 3 bar; electric
motor driven
- gen-set engines circuit:
- provide each gen-set engine with an individual cooling circuit
complete with a plate type heat exchanger and engine-mounted
_ __ jacket water circulating pump
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 120 of 177
LNG PROJECT
• Provide black steel piping for all jacket water piping circuits
• Provide individual expansion tanks for all engine jacket water circuits, complete
with pressure caps as required to prevent pump cavitation
• Provide main engines with individual cooling fresh water circuits
• Provide Copper Nickel piping (90-10) for all raw water circuits
• Provide a compressed air system for main and auxiliary engine starting, whistle
operation, winch brake and abort systems, sea chest blow down, control air
(where fitted), and general utility air services
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 121 of 177
LNG PROJECT
740.1 Receivers
• Provide two (2) main air receivers, each sized in accordance with Class
requirements for minimum number of engine starts for a multi-engine
installation (approx. 0.20 m3; to verify with engine manufacturer)
• Fit receivers with flanged inlet and outlet connections, drain valve, relief valve,
and clean out handhole, all JIS certified
• Install air receivers on a slope to drain
• Provide inlet and outlet valves on air receivers of all bronze construction with
outside screw and yoke and bolted bonnet
• Arrange air tank bleeds to blow off below deck plates
740.2 Compressors
• Provide two (2) main air-cooled air compressors complete with automatic
start/stop. Fit compressors with an air intake filter and an automatic unloader
• Compressors to each provide approx. 30 m3/hour FAD at 30 bar
• Supply air treatment system complete with all necessary filters, water drain
separator, oilers, etc.
• Install all filters in duplex pairs
• Dry air is required for instrument and associated control, not starting air for
machinery.
• Fit a swing check valve, a strainer, and a water trap with a valved blow-down
connection between compressor and main receiver. Fit pressure reducing
valves as required
• Provide a starting system to enable main and auxiliary engine starting only
from engine room. Arrange engines for local starting in engine room using
either air starting solenoid valve or manual bypass valve at operator's
discretion
• Arrange service air outlets according to diagram, complete with valve and 7.5
metre recoil type air hose with controllable nozzle at each station
740.4.6 Whistle
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 122 of 177
LNG PROJECT
• Deliver air service to air horn from main air receiver, with independent water
separator and filters
• Provide a separate buffer tank or large bore piping on run to air horn to ensure
adequate air capacity to meet demands
• Locate solenoid valve for air horn in close proximity to air horn to avoid a
noticeable time delay when activating air horn
• Provide main and auxiliary engines with self-contained, wet sump type
lubrication systems
• Provide lube oil storage tanks in machinery spaces for main engine and
auxiliary engine lube oil(s)
• Provide a lube oil transfer pump and connect to main engine sumps with
approved flexible connections
• Charge all machinery with correct amount of lubricating oil or grease as
required by manufacturer
• Provide a 4 litre measure with flexible spout for each type of oil
• Connect Z-drive lubrication system to cooling system
• Provide independent (non-integral) storage tanks for lube oil(s) with capacities
as per Section 0.0.2.2
• Construct tanks as specified in Section 225
• Provide the following fittings:
- tank to be plumbed with 63 mm line to a ball type shut-off valve and a
quick-closing draw-off cock with catch tray and screen for holding 4 litre
measures
- sight-glass, see Section 705.3
- calibrated capacity gauge, adjacent to sight-glass, with markings at
intervals of 5 litres. Gauge to be polished brass flat bar, with stamped
figures
745.2 Lube Oil Transfer System
750.1 General
• Provide a separate system for collection and treatment of oily bilge water and
other sources of contaminated oil mixtures and waste oil
• Connect oily water transfer pump to perform the following functions:
- draw oily water from bilges in machinery spaces, discharging to oily water
tank
- pump oily water from oily water tank to a deck connection to discharge
ashore
• Machinery space suctions to be 10 metre wandering hose leads, stowed on
suitable reels:
- provide hoses in Z-drive compartment (1), and engine room (1)
• Provide an oily water separator to treat oily water from oily water tank and
discharge clean water overboard in accordance with Regulatory requirements,
and discharge contaminants to waste oil (sludge) tank
• Fit deck termination with MARPOL standard flange
• Pipe all oil save-alls, spill coamings, and drip trays to drain by gravity to oily
water tank per Class requirements. Fit check valves where necessary
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 124 of 177
LNG PROJECT
751.1 General
• Provide a waste oil tank to receive discharge from purifiers, oily water
separator, and tun dishes, etc. Fit discharge pump to draw from tank and
discharge to a MARPOL standard flange deck connection for discharge ashore
755.1 General
• Connect Z-Drive steering gear resupply tank to P&S steering system service
tanks, and provide P&S isolation valves
• Steering gear Z-Drive resupply tank:
- quantity - one (1)
- description - independent tank to Class requirements for
steering gear systems
- capacity - 250 litres
- instrumentation - sightglass
• Provide two (2) identical pumps, each with capacity to meet the demand of one
winch operating at full load
• Main pumps:
- electric motor driven - 380/3/50
- capacity - approx. 150 litres/minute
- power input - approx. 30 kW each
- controls - wheelhouse and local
• Provide local and remote (wheelhouse) start/stop control and "pump running"
status indication of all pumps
• Provide local operational controls
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 126 of 177
LNG PROJECT
• Provide quick-connect type fittings on both fore and aft decks to operate oil
recovery equipment
• Provide Seamless steel pipe lines flanged in sections for disconnection and
cleaning
• Provide drain lines to "used hydraulic oil tank" from each system. Provide drain
lines sufficient for entire system. Provide filling line from "used hydraulic oil
tank" as well as from "hydraulic oil storage tank" for unused oil with electric
driven filling pump
• Provide flanges on pipe lines with male and female recesses. Carefully clean,
acid treat, and thoroughly wash all hydraulic pipelines after welding. Prohibit
welding on-board and after installation
• Install exhaust systems for main and auxiliary engines in accordance with
Drawing and engine manufacturer's allowable back pressure requirements
• Arrange system to provide maximum isolation of machinery vibration and
exhaust noise from vessel structure
• Ensure all joints are readily accessible for maintenance
760.3 Silencers
• Insulate main and auxiliary engine exhaust systems with removable, high
temperature resistant fibreglass type blankets. Insulation:
- pipe runs, engine to silencer - 25 mm jackets
- flanges and flexible sections - 25 mm muffs, overlapping adjacent
jackets no less than 75 mm
- silencers - 25 mm jackets, to outlet flange. Weld tabs
to silencer as necessary to prevent blanket
sagging or slipping
760.5 Installation
• Pay particular attention to isolating exhaust piping and silencer from main
structure. Provide heat-resistant pads to avoid excessive heat transmission to
isolators or structure
• Take special care to ensure proper support of exhaust system. Do not impose
more than the maximum permissible load on turbocharger outlets
• Provide a condensate trap and drain at low point of each exhaust system
• Bends in exhaust pipe runs may be fabricated, but are to have smooth
transitions. Connect sections by plate flanges as necessary for removal of, or
access to machinery
• Tailpipe from each muffler to pass through a coaming fitted at top of each
stack. Install pipe with 15 mm clearance to structure. Fit a rain hat on each
tailpipe above diaphragm
• Equip vessel to perform oil spill response and oil recovery functions as defined
_ __ herein.
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 128 of 177
LNG PROJECT
• Equip aft peak tank for storage of recovered oil. Provide the following:
- bolted manholes (two) on deck for connection of fill lines and cleaning
access (P&S)
- portable vents (two) to replace normal tank vents when recovered oil
operations taking place, 150 dia., 2.5 metres high, aluminium construction
- connections (two) for use of portable steam generator for tank cleaning
• Coat tank for use as both a recovered oil tank (occasional) and as a water
ballast tank
Ballast system to be provided with spectacle blind flange to isolate the system
when the aft peak tank is being used for recovered oil.
• One (1) set per four ships for use on any one of the four (4) vessels of the
following equipment shall be provided to Owner approval, stored ashore for de-
ployment as required:
- oil skimmer - hydraulic driven, 30 m3/hour
- oil containment fence - 50 metres, inflatable
- outrigger boom
- absorbant pads - 100 pieces, to be stored in hold
***
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 129 of 177
LNG PROJECT
801. GENERAL
• Provide low noise level, centrifugal duct fans, Woods or equal, 12 mm SWG
• Provide fan(s) sized to deliver fresh air to all accommodation, common, and
controls spaces as follows:
- crew cabins - 1.0 m3/minute/cabin
- galley - 2.0 m3/minute
- mess/lounge space - 2.0 m3/minute
- wheelhouse - 2.0 m3/minute
- ECR - 2.0 m3/minute
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 130 of 177
LNG PROJECT
• Mount two (2) trainable, two-speed, guarded, oscillating fans, 220 volt AC, so
they can be used to demist windows and to promote cooling
• Conceal electrical cables and provide switches located on units
• Provide low noise level exhaust fans for multiple speed control galley range
hood and lavatory exhaust capable of continuous operation
810.3 Ductwork
810.4 Dampers
• Provide engine room air supply via intake plenum(s) complete with high
velocity moisture-eliminating supply air louvres. Hinge louvres for intake
plenum access
• Provide acoustical insulation on interior bulkheads and deckhead of intake air
plenum
• Provide relief air vents using removable louvres on exhaust casings
• Provide permanently fitted hinged fire closures for each supply air and relief air
opening
• Provide a weathertight closure on fan intake
• Provide stainless steel mesh bird-screen (12 mm square mesh) on intake and
relief air openings
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 131 of 177
LNG PROJECT
• Provide two (2) axial flow engine room supply fans with variable operating
speed, 900 mm dia., 650 m3/minute at 50 mm SWG each
• Provide a fan diameter cylindrical silencer for engine room intake fan
• Provide intake bell-mouth on silencer complete with weathertight/fire closure
• Setup for fan to shut down and fire damper to close automatically on actuation
of engine room fire extinguishing system
• Provide variable speed fan control in engine room
• Isolate fan from ship structure with suitable resilient mounts
811.3 Ductwork
• Provide ducts/deflectors from supply fan to direct sufficient fresh air to engine
air intakes to maintain a maximum temperature rise of 10º C above outside air
temperature
815. AIR-CONDITIONING
• Provide corrosion inhibitor equivalent to main engine jacket water for tempered
water system, compatible with system equipment
• Provide multiple heat pump units (minimum two) working in parallel to provide
required total capacity
• Provide an automatic programmable system for heat pump control complete
with individual space fan controls/thermostats
• Provide all accessories for a complete operating system and install in as per
manufacturer's requirements
825.2 Pumps
• Provide water pressure by a duplex piston pump set, 2.0 m3/hour at 3.5 bar,
complete with pressure switch and relief valve
• One set to operate as 100% backup to the other
825.3 Piping
• Provide copper piping with zone and fixture isolation valves as indicated on
Drawings
• Insulate all hot and cold water lines, with PVC-jacketed foam insulation
• Provide ultraviolet filter sets for disinfection rated for full flow of installed pump
• Fit a 150 litre capacity electric hot water tank, with dual "flip-flop" type 1,500
_ __ Watt heating elements at high/low level
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 133 of 177
LNG PROJECT
825.9 Fixtures
• Provide electric, heavy duty, marine, straight line type window wipers on all
forward facing windows and on aft centreline window. Wipers must sweep
largest possible area of window, have individual controls, and have a "park"
feature
• Ensure wipers have suitable tension to hold firmly against the glazing in spite of
rake of windows
• Provide a valved, freshwater hose bib at bridge deck level to facilitate use of a
hose for washdown
• Provide main deck corridor, galley, mess area, and all lavatories with
independent floor drains, leading directly overboard, through swing check
valves
• On lower deck fit floor drains in galley store, corridor, and lavatory each led to
grey water tank
***
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 135 of 177
LNG PROJECT
905.6 Autopilot
• Supply and install one (1) autopilot system, including 360° follow-up
modification, and control box. Unit to include compass as per 920.1.2 "Gyro
Compass". Interface autopilot with Z-drive system as recommended, and to Z-
drive supplier approval
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 136 of 177
LNG PROJECT
• Provide local and remote tachometers for each propulsion engine; analogue
tachometers in wheelhouse, mechanical in engine room
• Provide local controls for all equipment including safety lockouts to Regulatory
Authorities' requirements
• Provide remote control panels for Fi-Fi system (ref. 730) in wheelhouse
console
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 137 of 177
LNG PROJECT
910.4 Consoles
910.4.1 Construction
• Provide access to interior of all consoles with neatly finished access panels
secured by hinges and non-rattling latches
• Ensure equipment may be easily removed for maintenance, and that an
adequate source of cooling air is provided to permit correct operation of all
console-mounted equipment
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 138 of 177
LNG PROJECT
910.4.4 Fittings
• Provide separate P&S free standing consoles with sufficient space to walk
completely around at least one of the consoles, and for the operator to enter or
exit the control position from front or rear
• Arrange hawser winch controls on aft portion of starboard control console
within normal reach of Master but also within reach of a crew member standing
aft or outboard of console
• Arrange towing winch controls in stand-alone console at aft end of wheelhouse
• Arrange Fi-Fi controls complete with mimic panel on aft portion of port console
within normal reach of Master, but also within reach of a crew member standing
aft or outboard of console
• Arrange radar display unit(s) at forward end of consoles with access for viewing
by either Master or another crew member standing outboard of console
• Provide panels overhead at consoles for mounting radios and other
communication equipment
• Recess panels in ends and/or outboard sides for light switches and breaker
panels. Slope recessed panels minimum 15° in at top to facilitate viewing
labels and nameplates
• Protect switches to prevent accidental operation
• Arrange consoles so controls are within acceptable reach of the operator in
standing position
• Provide adequate adjustment in helm chair position to maintain reach of
primary controls within the acceptable zone according to ASTM ergonomic
standards. Take note of the ergonomic norms for Indonesian crew members
• Provide an integrated marine type LCD or TFT based, electronic alarm and
monitoring system "MAX2" from Techsol or equal, meeting all requirements of
Regulatory Authorities for Unmanned Machinery Space (UMS) notation,
covering:
- machinery functions
- high bilge level
- fire alarms
- general alarm
• System power for alarms as follows:
- primary power; 24 volt DC from system battery charger (rectifier) power
supply
- secondary power for auxiliary functions; 24 volt DC, from system battery
• Provide redundant PLCs and redundant computers (type approved, one of
each at wheelhouse and one of each at ECR)
• Use PLCs, I/Os and software. No proprietary hardware will be allowed
• Use of redundant communication cable between PLCs and distributed I/Os is
mandatory
• System to be capable to communicate with engine electronics
• System to be able to send alarms to a printer
• Fit vessel with audibly distinct alarm systems meeting all Class requirements
including:
1. Machinery functions.
2. High bilge level.
3. Fire.
4. General alarm.
• Provide arrangements so false alarms do not trigger during start-up and
shutdown of main engines, or on engaging or disengaging clutches
• Locate no less than five (5) fire alarm sensors in machinery space and ECR
including over each engine and over switchboard. Locate sensors also in Z-
drive compartment, accommodation areas, and paint locker. Type and number
of sensors to be specifically approved by Purchaser and Class.
• Provide fire alarm sensors of both temperature and rate-of-rise resetable type
• Provide general alarm activated by pushbutton in wheelhouse audible
throughout vessel (excluding forepeak and aft peak), including fore and aft
exterior decks. To avoid excessive sound levels from general alarm, mount
separate sirens in each space/deck area
920.1 Compass
• Provide a 6" binnacle compass with correcting spheres and brackets, also to
be used as steering compass. Provide compass with light and dimmer switch
• Refer also to 905.6
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 141 of 177
LNG PROJECT
920.2 Clocks
920.3.1 Barometer
920.3.2 Anemometer/Anemoscope
• One (1) required, with display for wind speed up to 60 metres/second and for
wind direction from 0°–360°
920.5 Radar
• Fit two (2) radar units, X-band, 64 nautical mile range capable, flat-screen type
display
920.7 GPS
• Provide one (1) dual trumpet air horn, in accordance with Class requirements
and Collision Regulations
• Provide a chromeplated brass bell, 200 mm dia., engraved with ship's name
and year of construction and mount on house front
• Supply and stow on-board two (2) NUC shapes, two (2) black balls, collapsible,
610 dia. (ref. 920.9)
• Provide rigging to display shapes in accordance with Collision Regulations
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 143 of 177
LNG PROJECT
• Install one (1) set of MF/HF radio-telephones with DSC, DSCWR, and NBDP in
wheelhouse:
- 250 Watt SSB transceiver unit (1)
- DSC and DSCWR (1)
- NBDP terminal (1)
- printer (1) (for GMDSS requirements)
- control unit (1)
- battery charger (1)
- whip antenna (1)
- receiving antenna for DSC receiver (1)
• Install two (2) sets of VHF radio-telephones with DSC and DSCWR in
wheelhouse:
- 25 Watt VHF transceiver unit (2)
- whip antenna for VHF and DSC (2)
- printer (1) (for GMDSS requirements)
- repeater at mess room (1), bulkhead mounted
930.3 INMARSAT
• Provide three (3) sets of portable, two-way VHF radio-telephones with battery
charger
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 144 of 177
LNG PROJECT
• One (1) Public Address System shall be provided with microphone in the bridge
and internal speakers:
- Master's cabin
- mess room
- Chief Engineer's cabin
- each crew cabin
• Wheelhouse commands to be heard at all stations. Replies to be heard only in
wheelhouse
• Arrange a Klaxon flashing light and pushbutton system between wheelhouse
and engine room for emergency communications, with unique alarm signal
• Include 1 x 100 Watt amplifier with BC radio and cassette tape/CD player
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 145 of 177
LNG PROJECT
• One (1) lamp reply type engine telegraph to transmit signals for standby, run,
stop and finish from the wheelhouse to the engine side in the engine room
shall be installed.
• Electric source to be 24V, alarm and light shall be provided in the engine room.
***
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ESCORT TUG SPECIFICATION FOR TANGGUH
Page 146 of 177
LNG PROJECT
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
ROBERT ALLAN LTD.
NAVAL ARCHITECTS Project 206-054
Rev. 4
Annex B
Painting Schedule
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7
_ __
__ RA|
I N D __|
||___
07-SE
P-200
7