Scope of Works: TOTAL AMOUNT .
Scope of Works: TOTAL AMOUNT .
SUBJECT: Supply labor of man power & power tools for the construction of painting area, stock room,
over hauling and mezzanine second floor.
Ma’am/Sir;
We are pleased to submit here with our quotation for the above subject as follows;
SCOPE OF WORKS
Preliminary
Mobilization & Demobilization
Form & Scaffolding
1. Masonry Works
CHB Laying works.
Wall Plastering works.
C.R CHB Laying.
C.R Plastering works.
2. Interior Works
Ceiling works.
Partition of stock room area & Over hauling area.
Electrical works (Lay-out of electrical wiring additional outlets & Switches.)
Wood Mezzanine 2nd floor.
Metal Railing works.
Repair Door & Door knob.
3. Exterior Works
Metal Gate works
Metal Beam works ( G.I Galvanized Iron )
Welding works
General cleaning of plastic roof
TOTAL AMOUNT…………………………………………………………………………………………………………..Php.150,000.00
Excluded works: Supply of Materials, Excavation, Roofing works, Concrete works, Rebar works
& Painting works.
Materials Needed
We thank you for the opportunity to quote on your requirements and may we look forward to
serve your valuable order.