Myths and Common Problems Discovered in Geotechnical Forensic Engineering
Myths and Common Problems Discovered in Geotechnical Forensic Engineering
Myths and Common Problems Discovered in Geotechnical Forensic Engineering
discovered in Geotechnical
Forensic Engineering
IEM Sarawak, 5 Sep 2014
IEM Sabah, 12 Sep 2014
Ir. Liew Shaw Shong
Content
• Introduction
¾ What is Forensic Engineering?.
• Frameworks
¾ Approaches for Forensic Engineering.
• Common Problems & Myths
¾ Issues related to Forensic Engineering.
• Case Studies
¾ Examples
• Conclusions
¾ Summary of messages to do quality Forensic
Engineering
Introduction
Frameworks
• Desktop study
• Data collection (collecting evidences)
¾ Incident scene inspection
¾ Interview with Eye-witness & Specimen collection
¾ Measurements & Monitoring Data
• Developing chronological events
• Examine cause-and-effect
• Developing model and failure analysis
¾ Fault Tree Analysis (FTA) – Deductive
¾ Failure Mode and Effects Analysis (FMEA) & Criticality
Analysis (CA) – Inductive
• Experiments & laboratory tests
Failure Analysis
Failure Analysis
Common Problems:
¾ Inaccessibility to the incident site
¾ Timing between incident occurrence and commission
of investigation (Destroy of Evidences)
¾ Incorporative altitudes of involving parties
¾ Release of critical information (information on design,
construction records, monitoring results, maintenance
and operation)
¾ Conflicting data and facts
¾ Representativeness of interpreted information
¾ Establishment of event sequences
Myths:
¾ Overly simple postulation of potential mechanisms
¾ Fundamentals of mechanics & kinematic movement
traces
¾ Matching of performance data
¾ Cherry picking of facts to favourably suit perceptive
failure scenarios
¾ Uniqueness of cause-and-effect relationship
¾ Soundness of evidences collected or implied
¾ Compliance of design codes, work statement &
material specifications
Case Studies
APEC Seminar on The State-of-the-Practice of Deep Excavation Works in Malaysia, Taiwan and Hong Kong on 21 May 2011
Cheung On Tak Lecture Theatre, TU201, Hong Kong Polytechnic University, Hung Hom
Causes of Failures
Lessons Learnt
Two-Storey Basement
Temporary Excavation with Berms & Raking Struts to
Lower Basement Slab
Distresses observed in the middle of Temp. Excavation
Ground Distress
CBP Wall tilted and Structurally damaged
Remedial Works
Summary of Findings & Lessons Learnt
PROJECT
Construction stage where
SITE
ground distresses observed
1A 1 2
Adjacent lot with
ground distresses RL59.0m
RL56.1m (Ground Floor)
RC WALL
RL54.6m
12m Long 950mm x 600mm CAPPING BEAM
FSP IIIA Sheet Pile 200mm THK. REINFORCED SKIN WALL
RL52.0m (BASEMENT 1)
10.5m
TEMPORARY RAKING STRUT
RL48.8m (BASEMENT 2) FLOOR SLAB
HORIZONTAL DRAIN
PILED
16m Long FOUNDATION
750mm DIA. CBP WALL
RL38.6m
CS1: Excessive Movement of CBP Wall
60
65.00
N
58
56
62.00 56.75
54 56.50
52
ADJACENT SITE PROJECT SITE
50
59.00
56.00
48 56.00
46
44
55.00 Proposed platform level (RL m)
Possible seasonal stream 55.00
600mm
400mm
200mm
-200mm
CS1: Excessive Movement of CBP Wall
Project site Adjacent site Adjacent site Project site
12°
BH2 BH3
PBH1
IBH2
ADJACENT SITE ABH1
PROJECT SITE SP2
IBH1
ABH2
ABH3
IBH3
Adjacent site Project site
Back Analysis
Finite Element analysis (PLAXIS) to simulate the construction sequences of
excavation & to investigate the probable causes of ground distresses & wall
movements. 917mm displacement (sheet pile wall)
Excavation in front of the wall → the retained earth platform displaced excessively in the
609mm displacement (CBP wall)
horizontal & vertical (settlement) directions with the temporary sheet pile wall moving
forward
Over-excavation of passive berm before installing raking struts → reduce lateral
resistance to sheet pile wall & subsequently mobilise structural strength of the CBP walls
beyond serviceability state condition & reaching ultimate limit state condition
Excessively displaced temporary sheet pile wall → induced additional lateral force &
flexural stress to the installed contiguous bored piles (CBP) walls unavoidably damaged the
CBP piles.
The results of FE analyses agree reasonably well with the measured wall
movements and ground deformations (e.g. tension cracks, settlement and
depression)
CS1: Excessive Movement of CBP Wall
Remedial Solution
Observations of investigator:
Although strutting subcontractor did
not design the strutting system for
one strut failure scenario, the
retaining wall system still managed
to distribute the loads from Strut F
vertically to soil and laterally to
Struts D & E and passive berm safely
but with large incremental
movement registered at
Inclinometer IIC4.
The water pipe burst incident on
Day 227 could have weaken the
strut corbel connection for Strut F
and stressed the CBP walls towards
its structural ultimate limit state.
Water pipe burst incident on Day 227 which caused the steel corbel for strut F being sheared off as reported.
Observations of investigator:
Although strutting subcontractor did
not design the strutting system for
one strut failure scenario, the
retaining wall system still managed
to distribute the loads from Strut F
vertically to soil and laterally to
Struts D & E and passive berm safely
but with large incremental
movement registered at
Inclinometer IIC4.
The water pipe burst incident on
Day 227 could have weaken the
strut corbel connection for Strut F
and stressed the CBP walls towards
its structural ultimate limit state.
CS2: Important Events Before Collapse
Strut F was reinstated. After installation of struts G and H, temporary passive berm along Gridlines G and H were
progressively removed.
The removal of temporary passive berm has caused incremental ground movement that led to another water pipe
burst incident on Day 248. This water pipe leakage had triggered CBP wall collapse tragedy on Day 248.
CS2: Video Clip on Wall Failure
Over-estimation
of cohesion for
subsoil at
shallower depth
Triangular
system
CS2: Causes of Wall Collapse
3) Improper lateral restraint bracing system and non-compliance on hole
cutting at steel corbel by strutting sub-contractor and no timely review of the
retaining wall and strutting designs.
VS
Piezometric
Level
Laboratory Test Results
Sandy material within failed mass.
CIU test :
a. cp’=2kPa, φp’=30o
b. c’ε(max)=1.9kPa, φ’ε(max) =28o
Back Analysis :
a. cm’=0kPa, φm’=30o
Findings
Possible causes of failure:
FOS against overall failure indicates the
slope is at the verge of failure for the water
level measured during investigation.
Rainfall leading to rise of groundwater is
the triggering cause to failure.
Conclusions
Main Contributory Factors for Slope Failure (Static) :
- Inherent weak strength & sensitive materials
- Adverse geological & hydro-geological features
- Morphological features
- Steep slope geometry
- Gravity force
- Weathering
- Inadequate design & lack of maintenance
Triggering Factors (Dynamic) :
- Rainfall/leaking utilities/rapid drawdown (soil saturation/ rise of
GWT)
- Human disturbance (excavation/surcharge/vegetation
removal/vibration)
- Earthquake/volcanic eruption/thunder
- Erosion
55
56
Site Layout Plan & RS Wall Sectional View
WELL
COMPACTED
GRANULAR FILL
TO WALL
SPECIALIST
SPECIFICATION
1 20m
Ch 6 5 4 3 2 1
0m
Ch
120m long RS Wall
displaced laterally
Monsoon Drain 57
Subsurface Conditions
RL29.0m
30m
RL28.5m
RL27.0m
RL20.18m
20m RL19.0m
RL18.6m
58
Installation of Piles (mid Oct 06)
Installation of Piles (mid Oct 06) Slab Casting (mid Oct 06)
Rainfall Record
60
Retention pond full of water
61
Site Observations
` Panels
` Wet panels & traces watermark
` Highest level of observed seeping water below 2m high L-shaped
RC wall
∴ Evidence of high water table behind the wall panel
` Pile Foundation
` Flexural plastic hinge pile damage at 1.75m to 2m below slab
soffit level
∴ Likely due to excessive lateral load on piles
62
1.5m
1.5m
Water
seepage 1.5m
sign
1.5m
RL 20.2m
Ch 0m
63
2m top RC panel
RL 27.0m
Water
seepage
1.5m sign
Precast RC
panel
Monsoon Drain
64
Damaged Foundation Piles
Raked pile
RL 18.6m
Raked pile
1.8m
Damaged
condition
65
Investigation Approach
66
RL29.0m
30m
RL28.5m
RL27.0m
RL20.18m
RL20.5m
RL17.1m
20m RL19.0m
RL18.6m
15m
0 10m 20m 30m 40m
67
RL20.18m
RL20.5m
RL17.1m
20m RL19.0m
RL18.6m
15m
0 10m 20m 30m 40m
68
RL29.0m
30m 1m Earth drain
RL28.5m
1m
RL27.0m
RL20.18m
RL20.5m
RL17.1m
20m RL19.0m
RL18.6m
15m
0 10m 20m 30m 40m
69
RL29.0m
30m 1m Earth drain
RL28.5m
1m
RL27.0m
RL20.18m
RL20.5m
RL17.1m
20m RL19.0m
RL18.6m
15m
0 10m 20m 30m 40m
70
30m
RL28.5m
20m RL19.0m
15m
0 10m 20m 30m 40m
71
RC wall
Accumulation of Water on
bowl ground
Infiltration
Perched
Water
Level
Seepage of water
Well Compacted
granular soil
RS Wall panel
72
70m
View from
Retained
Platform
73
RL20.18m
RL20.5m
RL17.1m
20m RL19.0m
RL18.6m
15m
0 10m 20m 30m 40m
74
Design Scenario A Results
GWT at Top of Monsoon Drain (RL20.18m)
!
OK
75
RL20.18m
RL22.0m
RL20.5m
1/3H
RL17.1m
20m RL19.0m
RL18.6m
15m
0 10m 20m 30m 40m
76
Design Scenario B Results
GWT at 1/3 of Retained Height (RL22.0m)
ile
alP
ividu
f Ind
ro
c to n
d Fa itio
L oa ond
t ed fe C
a
lcula Uns
Ca ≠
ck
Ba
w
Lo
77
RL20.18m
RL20.5m
RL17.1m
20m RL19.0m
RL18.6m
15m
78
Failure Scenario Results
GWT at Top RS Wall Panel (RL27.0m)
ion!
it
ond
e C
n saf
U
79
Failure Scenario :
80
Remedial Works
Ch 120.0m Ch 0.0m
82
Drainage control on Intact Wall
Drainage blanket (4.8m c/c)
Weepholes (6m
intervals)
83
Conclusions
• Main causation :
• Excessive lateral wall force due to high water table rise from prolonged intense
rainfall
• Foundation design under service condition is acceptable
• Attention shall be given to brittle behaviour of concrete piles taking lateral
load with rapid increase of wall pressure when rise of groundwater table
within the wall.
84
29 December 2006 - Johor was the worst hit. Heavy rain – the highest recorded in 100 years
– caused floods in Johor Baru and several major towns.
85
86
Site Conditions
` Embankment (maximum 5.4m high) with Piles & Ground
Improvements
` Ch3328 to Ch3375 (Top 10m soft Clay, Su = 10~15kPa)
` Distressed Abutment
` Abutment A @ Ch3266 (Top 15m soft Clay, Su = 13~18kPa)
` Abutment B @ Ch3328 (Top 9m soft Clay, Su = 7~12kPa)
Abutment A Pier P1 Pier P2 Abutment B Piled Embankment PVD + EVD Area
PA PA P3
P1
Filled Working Platform
P2
Upper Weak Soil
EVD PVD
88
Site Inspection Findings
89
90
Site Inspections Findings
91
92
Site Inspections Findings
93
94
PA : Active Earth Pressure
P1 : Action/Reaction Force between Piled Embankment Slab & Abutment
P2 : Ultimate Lateral Pile Group Capacity of Embankment Piles
FOS
P3 : Mobilised Thrust on Stability Soil Mass with Corresponding FOS
PA PA P3
P1
Filled Working Platform
P2
Upper Weak Soil
EVD PVD
M7 10 11 M9
M10 M12 PA + P1 F D
M8 Deck 1 12 Deck 2 13 14 Deck 3 M13 15 16 18 19 PVD Area
Piled Embankment
M13 M14 E C
B
M2 8 4 3 2 1
8 7 6 5 EVD Area
M6 M5 A
M1 M3 M4
Movement Direction Bearing Distortion
PA : Active Earth Pressure
P1 : Action/Reaction Force between Piled Embankment Slab & Abutment Clockwise Rotation
PA PA P3
P1
P2
96
Investigation Findings
97
Isolation Gap
98
Conclusions
99
Recommendations
100
G&P Geotechnics Sdn Bhd
Content
Too large pre-bored hole Too small pre-bored hole Compromised pre-bored
hole
(Adopted)
Void in Pre-bored Hole Annulus
9m deep prebored
P=L
P>L
L – Pre-bored Length
MLT Results
Pile Top Settlement
Pile Max. Jack-in Achieved
Maintained Pre-bored At Max.
Penetration Load at Maximum
Load Test Diameter At Working Test
below Piling Termination Test Load
(MLT) (mm) Load (mm) Load
Platform (m) (kN) (kN)
(mm)
2220
MLT 1 600 9.40 2160 14.0 46.00
(1.71xWL)
2220
MLT 2 500 9.30 2600 23.50 42.00
(1.71xWL)
2600
MLT 3 550 12.50 2860 5.80 21.80
(2.00xWL)
1406
MLT 4 550 9.50 2860 16.50 24.50
(1.50xWL)
1950
MLT 5 550 13.50 2860 8.50 13.00
(1.50xWL)
Jack-in Pile Termination Criteria
Boreholes Information
Piling
Platform
9m
End of
Pre-bored Pre-bored
SPT-N>50
Photos of Exposed Subsoils
2600 2600
2400 2400
2200 2200
2000 2000
MLT1
PILE TOP LOADING (kN)
1800 1800
1600 1600
1400 1400
1200 1200
1000 1000
Legend
800 800
MLT 1 - 9.4m
MLT 2 - 9.3m
600 600
MLT 3 - 12.5m
MLT 4 - 9.5m
400 400
MLT 5 - 13.5m
200 200
0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
PILE TOP SETTLEMENT (mm)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
2800 2800
2600 2600
2400 2400
2200 2200
2000 2000
MLT1
MLT2
PILE TOP LOADING (kN)
1800 1800
1600 1600
1400 1400
1200 1200
1000 1000
Legend
800 800
MLT 1 - 9.4m
MLT 2 - 9.3m
600 600
MLT 3 - 12.5m
MLT 4 - 9.5m
400 400
MLT 5 - 13.5m
200 200
0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
PILE TOP SETTLEMENT (mm)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
2800 2800
2600 2600
MLT3
2400 2400
2200 2200
2000 2000
MLT1
MLT2
PILE TOP LOADING (kN)
1800 1800
1600 1600
1400 1400
1200 1200
1000 1000
Legend
800 800
MLT 1 - 9.4m
MLT 2 - 9.3m
600 600
MLT 3 - 12.5m
MLT 4 - 9.5m
400 400
MLT 5 - 13.5m
200 200
0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
PILE TOP SETTLEMENT (mm)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
2800 2800
2600 2600
MLT3
2400 2400
2200 2200
2000 2000
MLT1
MLT2
PILE TOP LOADING (kN)
1800 1800
1600 1600
1400 1400
MLT4
1200 1200
1000 1000
Legend
800 800
MLT 1 - 9.4m
MLT 2 - 9.3m
600 600
MLT 3 - 12.5m
MLT 4 - 9.5m
400 400
MLT 5 - 13.5m
200 200
0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
PILE TOP SETTLEMENT (mm)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
2800 2800
2600 2600
MLT3
2400 2400
2200 2200
1800 1800
1600 1600
1400 1400
MLT4
1200 1200
1000 1000
Legend
800 800
MLT 1 - 9.4m
MLT 2 - 9.3m
600 600
MLT 3 - 12.5m
MLT 4 - 9.5m
400 400
MLT 5 - 13.5m
200 200
0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
PILE TOP SETTLEMENT (mm)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
2800 2800
2600 2600
MLT3 & MLT5:
2400 2400
2000
Penetration 2000
below pre-bored
PILE TOP LOADING (kN)
1800 1800
base performs
1600 better 1600
1400 1400
1200 1200
1000 1000
Legend
800 800
MLT 1 - 9.4m
MLT 2 - 9.3m
600 600
MLT 3 - 12.5m
MLT 4 - 9.5m
400 400
MLT 5 - 13.5m
200 200
0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
PILE TOP SETTLEMENT (mm)
Additional MLT Results
Additional MLT
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
2800 2800
2600 2600
2400 2400
2200 2200
2000 2000
MLT6
PILE TOP LOADING (kN)
1800 1800
1600 1600
1400 1400
1200 1200
1000 1000
Legend
800 800
MLT 6 - 9.5m
MLT 7 - 10.5m
600 600
MLT 8 - 11.0m
400 400
200 200
0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
PILE TOP SETTLEMENT (mm)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
2800 2800
2600 2600
2400 2400
2000 2000
MLT6
PILE TOP LOADING (kN)
1800 1800
1600 1600
1400 1400
1200 1200
1000 1000
Legend
800 800
MLT 6 - 9.5m
MLT 7 - 10.5m
600 600
MLT 8 - 11.0m
400 400
200 200
0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
PILE TOP SETTLEMENT (mm)
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
2800 2800
2600 2600
MLT8
2400 2400
2000 2000
MLT6
PILE TOP LOADING (kN)
1800 1800
1600 1600
1400 1400
1200 1200
1000 1000
Legend
800 800
MLT 6 - 9.5m
MLT 7 - 10.5m
600 600
MLT 8 - 11.0m
400 400
200 200
0 0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75
PILE TOP SETTLEMENT (mm)
Pile Top Settlement
Max. Jack-in Achieved
Pre-bored Pile Penetration
Load at Maximum At Max.
MLT Diameter below Piling At Working
Termination Test Load Test Load
(mm) Platform (m) Load (mm)
(kN) (kN) (mm)
2220
MLT 1 600 9.40 2160 14.0 46.00
(1.71xWL)
2220
MLT 2 500 9.30 2600 23.50 42.00
(1.71xWL)
2600
MLT 3 550 12.50 2860 5.80 21.80
(2.00xWL)
1406
MLT 4 550 9.50 2860 16.50 24.50
(1.50xWL)
1950
MLT 5 550 13.50 2860 8.50 13.00
(1.50xWL)
1950
MLT 6 550 9.50 2860 15.08 42.38
(1.50xWL)
2400
MLT 7 550 10.50 2860 11.29 41.93
(1.85xWL)
2600
MLT 8 550 11.00 2860 10.30 50.35
(2.00xWL)
Investigation Findings
Pre-bored
Penetration below
base of pre-bored
Analogy of Footing
Conclusions