Design and Construction of Excavation Works For Klang Valley Mass Rapid Transit Underground Station at Cochrane, Kuala Lumpur, Malaysia
Design and Construction of Excavation Works For Klang Valley Mass Rapid Transit Underground Station at Cochrane, Kuala Lumpur, Malaysia
Design and Construction of Excavation Works For Klang Valley Mass Rapid Transit Underground Station at Cochrane, Kuala Lumpur, Malaysia
KOO Kuan-Seng
[email protected], G&P Geotechnics, Kuala Lumpur, Malaysia
ABSTRACT - Kuala Lumpur limestone formation exhibits karstic features with irregular bedrock profiles and
variable weathering condition. The Klang Valley Mass Rapid Transit project is the first Mass Rapid Transit
project in Malaysia. The Cochrane station is one of the underground stations with maximum excavation
depth of 32m below ground and it is located in Kuala Lumpur limestone formation. This station also serves as
launching shaft for the tunnel boring machine from both ends of the station. A cost effective earth retaining
system deemed suitable for the geological formation was adopted using secant pile wall supported by
temporary ground anchors. High ground water table is also a concern. Rock grouting was carried out to
prevent water ingress into excavation pit as well as excessive ground settlement and occurrences of
sinkholes surrounding the excavation area due to groundwater drawdown. Vertical rock excavation adjacent
to the secant pile wall involving rock slope strengthening works, surface protection, controlled blasting and
vibration control was successfully designed and implemented. This paper presents the design of the secant
pile wall together with vertical rock excavation to the final depth of the station in karstic limestone formation.
The unique experience (design and construction) gained from this project will be useful reference for similar
excavation works, especially in mature karstic limestone.
1. Introduction
result, the recommended reduction factor due to design engineers during construction have enabled
bending of strand at U-turn point is 0.65. Summary vertical rock excavation to be carried out safely and
of the anchor properties are shown in Table 3. without delay. This design scheme has resulted in
considerable time and cost saving compared to
Table 3. Ground anchor properties non-vertical excavation which will incur additional
Description Properties cost and also present challenges in terms of
Working loads (kN) 212; 424; 636; 848 additional land acquisition.
No. of strand 2; 4; 6; 8 With proper geotechnical input, costly failure and
Strand diameter 15.24mm delay associated with underground works in
Breaking load 260.7 kN limestone formation such as excessive groundwater
Factor of safety 1.6 lowering, occurrences of sinkholes, excessive
Strand U-turn radius 47.5mm ground settlement, etc. can be prevented. It is
Reduction factor 0.65 important to have continuous feedback from the
Drill hole diameter 175mm construction team to anticipate problems and such
Allowable bond stress 400 kPa (limestone) model of cooperation between the construction
Free length Varies (until bedrock) team and the geotechnical engineers has proven to
Bond length (m) 3; 3; 4.5; 6 be successful as the excavation works at Cochrane
station were completed successfully and within the
contract period.
4.2. Rock slope strengthening works
6. Conclusions
The rock excavation was carried out using
conventional pre-split blasting followed by bulk Secant pile wall supported by temporary ground
blasting with suitable delays to minimize the anchors and rock strengthening were successfully
impacts of blasting works. The blasting works were used for the underground station excavation works.
carried out in 2 to 3m benches. After blasting, The secant pile wall system together with grouting
geological mapping was carried out by qualified works prevented excessive groundwater lowering
geologist to collect field data on the exposed rock and excessive ground movement. Overall, the
face including details of discontinuities, rock face system performs satisfactorily and the excavation
weathering condition, etc. The field data is used for works were successfully completed within the
kinematic stereonet analysis using software (Rock contract period.
Pack III) to determine the probable mode of rock
slope failures. The probable failure mode was 7. Acknowledgement
further analysed using software RocPlane (planar
stability), Swedge (wedge stability) and RockPack II The Author would like to thank G&P Geotechnics
(toppling stability) to establish the factor of safety design team members and project team of MMC-
and determine suitable rock slope strengthening Gamuda KVMRT for various discussions on
works. overcoming challenges associated with limestone
formation. The support and sponsorship from the
4.3. Grouting works Institution of Engineers, Malaysia (IEM) to attend
the conference is also gratefully acknowledged.
Grouting techniques rely much on local
experiences. Grouting works is mainly carried out 8. References
for limestone to reduce the rate of groundwater
inflow into excavation and reduce pathways of BS8002:1994. British Standard Code of Practice for
water flow into excavation area. Rock fissure Earth Retaining Wall.
grouting was carried out along the perimeter of BS8081:1989. British Standard Code of Practice for
excavation area to form a curtain grouting as shown Ground Anchorages.
in Figure 7. Fissure grouting involves a single CIRIA C580. (2003). Enbedded retaining walls –
packer in ascending or descending stages in order guidance for economic design, London.
to inject grout suspension into existing pathways, Raju V. R. & Yee Y W (2006). Grouting in limestone
fissures, cavities and discontinuities within the rock for SMART tunnel project in Kuala Lumpur.
formation. Rock fissure grouting is also adopted for International Conference and Exhibition on
base grouting at larger grout hole spacing. If any Tunnelling and Trenchless Technology, 7-9
cavities are detected during drilling / grouting, March 2006, Subang, Selangor, Malaysia.
compaction grouting with cement mortar will be Tan S. M. (2005). Karstic Features of Kuala Lumpur
used as cavity treatment. Limestone. Bulletin of the Institution of Enginner
Malaysia, June 2005, 6 -11.
5. Achievement Tan Y. C. & Chow C.M. (2008). Design of retaining
wall and support systems for deep basement
Excavation works started in early 2012 and reached construction – a Malaysian experience. Seminar
the final excavation level in January 2013. Proper on "Deep Excavation and Retaining Walls", , 24
geotechnical input and continuous support from the March 2008, Petaling Jaya, Malaysia.