Construction Monitoring Modular Accomplishment Based On NTP NTP No: No of Units: 3
Construction Monitoring Modular Accomplishment Based On NTP NTP No: No of Units: 3
Construction Monitoring Modular Accomplishment Based On NTP NTP No: No of Units: 3
1.0 2.0
### AT 100% ACCOMPLISHMENT
MODULE
PAY ITEMS
NO. B04L01 B04L02 DUPLEX
DUPLEX DUPLEX
Module I SUB-STRUCTURE 9.69% 9.69% 9.69%
1.01 Layout, Batterboards & Excavation 0.54% 0.54% 0.54%
1.02 2000 psi RC Wall Footing 2.91% 2.91% 2.91%
1.03 Wooden Zucallo Forms,600x2400mm 0.59% 0.59% 0.59%
1.04 2000 psi Zucallo Wall 2.85% 2.85% 2.85%
1.05 Septic Vault,1200x2800x1600mm 2.79% 2.79% 2.79%
Module II SLAB-ON-FILL 5.91% 5.91% 5.91%
2.01 2000 psi Slab-on-Fill, 100mm 4.60% 4.60% 4.60%
2.02 PVC Pipes & Fittings 0.62% 0.62% 0.62%
2.03 Wires & Conduits 0.69% 0.69% 0.69%
Module III GROUND FLOOR RC WALL 10.33% 10.33% 10.33%
3.01 Wires & Conduits 0.74% 0.74% 0.74%
3.02 PVC Pipes & Fittings 0.67% 0.67% 0.67%
3.03 GF Wall Concreting 8.92% 8.92% 8.92%
Module IV SECOND FLOOR SUSPENDED SLAB 6.55% 6.55% 6.55%
4.01 2F Slab Concreting 6.55% 6.55% 6.55%
Module V SECOND FLOOR RC WALL 11.66% 11.66% 11.66%
5.01 Wires & Conduits 1.22% 1.22% 1.22%
5.02 2F Wall Concreting 10.44% 10.44% 10.44%
Module VIA STEEL FRAMING WORKS 11.26% 11.26% 11.26%
6.01 Roof Framing 4.08% 4.08% 4.08%
6.02 Stair Railings 0.79% 0.79% 0.79%
6.03 Aluminum Windows 6.40% 6.40% 6.40%
Module VIB ROOFING & ACCESSORIES 4.19% 4.19% 4.19%
6.04 Prepainted GI Roof and Accessories 2.93% 2.93% 2.93%
6.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25%
Module VIC MISCELLANEOUS CONCRETE 2.10% 2.10% 2.10%
6.06 RC Kitchen Counter 0.56% 0.56% 0.56%
6.07 Concrete Stair Case 1.35% 1.35% 1.35%
6.08 Concrete Pads, 100x300x1000mm 0.19% 0.19% 0.19%
Module VID MASONRY FINISHES 2.56% 11.12% 11.12%
6.09 Exterior Steel Doors & Jambs 2.56% 2.56% 2.56%
6.10 Wall & Concrete Finishes 7.31% 7.31%
6.11 Concrete Mouldings & Canopy 1.25% 1.25%
Module VII CARPENTRY 0.00% 6.32% 9.66%
7.01 Ceilings, Eaves & Vents 3.74% 3.74%
7.02 Dry Wall Partitions(Double-walled) 2.21% 2.21%
7.03 Interior PVC Doors & Jambs 2.28%
7.04 Cabinet Doors 300mmx650mm (Kitchen) 0.38%
7.05 Cabinet Doors 900mmx1500mm (Bedroom) 0.69%
7.06 Wires & Conduits 0.36% 0.36%
Module VIIIA FINISHING WORKS 2.85% 0.00% 5.68%
8.01 Tileworks 2.62%
8.02 1st Coat Painting 2.85% 2.85%
8.03 Lot Levelling 0.21%
Module VIIIB MOVE-IN WORKS 4.75% 0.10% 11.86%
8.04 Plumbing Fixtures 4.88%
8.05 Electrical Fixtures 1.74%
8.06 Final Coat Painting 4.65% 4.65%
8.07 Clean-up & Turnover 0.48%
8.08 Tapping To Main 0.10% 0.10% 0.10%
1.0 2.0
### AT 100% ACCOMPLISHMENT
MODULE
PAY ITEMS
NO. B04L01 B04L02 DUPLEX
DUPLEX DUPLEX
Module I SUB-STRUCTURE 9.69% 9.69% 9.69%
1.01 Layout, Batterboards & Excavation 0.54% 0.54% 0.54%
1.02 2000 psi RC Wall Footing 2.91% 2.91% 2.91%
1.03 Wooden Zucallo Forms,600x2400mm 0.59% 0.59% 0.59%
1.04 2000 psi Zucallo Wall 2.85% 2.85% 2.85%
1.05 Septic Vault,1200x2800x1600mm 2.79% 2.79% 2.79%
Module II SLAB-ON-FILL 5.91% 5.91% 5.91%
2.01 2000 psi Slab-on-Fill, 100mm 4.60% 4.60% 4.60%
2.02 PVC Pipes & Fittings 0.62% 0.62% 0.62%
2.03 Wires & Conduits 0.69% 0.69% 0.69%
Module III GROUND FLOOR RC WALL 10.33% 10.33% 10.33%
3.01 Wires & Conduits 0.74% 0.74% 0.74%
3.02 PVC Pipes & Fittings 0.67% 0.67% 0.67%
3.03 GF Wall Concreting 8.92% 8.92% 8.92%
Module IV SECOND FLOOR SUSPENDED SLAB 6.55% 6.55% 6.55%
4.01 2F Slab Concreting 6.55% 6.55% 6.55%
Module V SECOND FLOOR RC WALL 11.66% 11.66% 11.66%
5.01 Wires & Conduits 1.22% 1.22% 1.22%
5.02 2F Wall Concreting 10.44% 10.44% 10.44%
Module VIA STEEL FRAMING WORKS 11.26% 11.26% 11.26%
6.01 Roof Framing 4.08% 4.08% 4.08%
6.02 Stair Railings 0.79% 0.79% 0.79%
6.03 Aluminum Windows 6.40% 6.40% 6.40%
Module VIB ROOFING & ACCESSORIES 4.19% 4.19% 4.19%
6.04 Prepainted GI Roof and Accessories 2.93% 2.93% 2.93%
6.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25%
Module VIC MISCELLANEOUS CONCRETE 2.10% 2.10% 2.10%
6.06 RC Kitchen Counter 0.56% 0.56% 0.56%
6.07 Concrete Stair Case 1.35% 1.35% 1.35%
6.08 Concrete Pads, 100x300x1000mm 0.19% 0.19% 0.19%
Module VID MASONRY FINISHES 11.12% 11.12% 11.12%
6.09 Exterior Steel Doors & Jambs 2.56% 2.56% 2.56%
6.10 Wall & Concrete Finishes 7.31% 7.31% 7.31%
6.11 Concrete Mouldings & Canopy 1.25% 1.25% 1.25%
Module VII CARPENTRY 0.36% 9.66% 9.66%
7.01 Ceilings, Eaves & Vents 3.74% 3.74%
7.02 Dry Wall Partitions(Double-walled) 2.21% 2.21%
7.03 Interior PVC Doors & Jambs 2.28% 2.28%
7.04 Cabinet Doors 300mmx650mm (Kitchen) 0.38% 0.38%
7.05 Cabinet Doors 900mmx1500mm (Bedroom) 0.69% 0.69%
7.06 Wires & Conduits 0.36% 0.36% 0.36%
Module VIIIA FINISHING WORKS 2.85% 5.47% 5.68%
8.01 Tileworks 2.62% 2.62%
8.02 1st Coat Painting 2.85% 2.85% 2.85%
8.03 Lot Levelling 0.21%
Module VIIIB MOVE-IN WORKS 4.75% 6.49% 11.86%
8.04 Plumbing Fixtures 4.88%
8.05 Electrical Fixtures 1.74% 1.74%
8.06 Final Coat Painting 4.65% 4.65% 4.65%
8.07 Clean-up & Turnover 0.48%
8.08 Tapping To Main 0.10% 0.10% 0.10%
1.0 2.0
### AT 100% ACCOMPLISHMENT
MODULE
PAY ITEMS
NO. B04L01 B04L02 DUPLEX
DUPLEX DUPLEX
Module I SUB-STRUCTURE 9.69% 9.69% 9.69%
1.01 Layout, Batterboards & Excavation 0.54% 0.54% 0.54%
1.02 2000 psi RC Wall Footing 2.91% 2.91% 2.91%
1.03 Wooden Zucallo Forms,600x2400mm 0.59% 0.59% 0.59%
1.04 2000 psi Zucallo Wall 2.85% 2.85% 2.85%
1.05 Septic Vault,1200x2800x1600mm 2.79% 2.79% 2.79%
Module II SLAB-ON-FILL 5.91% 5.91% 5.91%
2.01 2000 psi Slab-on-Fill, 100mm 4.60% 4.60% 4.60%
2.02 PVC Pipes & Fittings 0.62% 0.62% 0.62%
2.03 Wires & Conduits 0.69% 0.69% 0.69%
Module III GROUND FLOOR RC WALL 10.33% 10.33% 10.33%
3.01 Wires & Conduits 0.74% 0.74% 0.74%
3.02 PVC Pipes & Fittings 0.67% 0.67% 0.67%
3.03 GF Wall Concreting 8.92% 8.92% 8.92%
Module IV SECOND FLOOR SUSPENDED SLAB 6.55% 6.55% 6.55%
4.01 2F Slab Concreting 6.55% 6.55% 6.55%
Module V SECOND FLOOR RC WALL 11.66% 11.66% 11.66%
5.01 Wires & Conduits 1.22% 1.22% 1.22%
5.02 2F Wall Concreting 10.44% 10.44% 10.44%
Module VIA STEEL FRAMING WORKS 11.26% 11.26% 11.26%
6.01 Roof Framing 4.08% 4.08% 4.08%
6.02 Stair Railings 0.79% 0.79% 0.79%
6.03 Aluminum Windows 6.40% 6.40% 6.40%
Module VIB ROOFING & ACCESSORIES 4.19% 4.19% 4.19%
6.04 Prepainted GI Roof and Accessories 2.93% 2.93% 2.93%
6.05 PVC Downspouts & Catchbasins 1.25% 1.25% 1.25%
Module VIC MISCELLANEOUS CONCRETE 2.10% 2.10% 2.10%
6.06 RC Kitchen Counter 0.56% 0.56% 0.56%
6.07 Concrete Stair Case 1.35% 1.35% 1.35%
6.08 Concrete Pads, 100x300x1000mm 0.19% 0.19% 0.19%
Module VID MASONRY FINISHES 11.12% 11.12% 11.12%
6.09 Exterior Steel Doors & Jambs 2.56% 2.56% 2.56%
6.10 Wall & Concrete Finishes 7.31% 7.31% 7.31%
6.11 Concrete Mouldings & Canopy 1.25% 1.25% 1.25%
Module VII CARPENTRY 0.36% 9.66% 9.66%
7.01 Ceilings, Eaves & Vents 3.74% 3.74%
7.02 Dry Wall Partitions(Double-walled) 2.21% 2.21%
7.03 Interior PVC Doors & Jambs 2.28% 2.28%
7.04 Cabinet Doors 300mmx650mm (Kitchen) 0.38% 0.38%
7.05 Cabinet Doors 900mmx1500mm (Bedroom) 0.69% 0.69%
7.06 Wires & Conduits 0.36% 0.36% 0.36%
Module VIIIA FINISHING WORKS 2.85% 5.47% 5.68%
8.01 Tileworks 2.62% 2.62%
8.02 1st Coat Painting 2.85% 2.85% 2.85%
8.03 Lot Levelling 0.21%
Module VIIIB MOVE-IN WORKS 4.75% 11.38% 11.86%
8.04 Plumbing Fixtures 4.88% 4.88%
8.05 Electrical Fixtures 1.74% 1.74%
8.06 Final Coat Painting 4.65% 4.65% 4.65%
8.07 Clean-up & Turnover 0.48%
8.08 Tapping To Main 0.10% 0.10% 0.10%
1.0 2.0
### AT 100% ACCOMPLISHMENT
MODULE
PAY ITEMS
NO. B04L01 B04L02 DUPLEX
DUPLEX DUPLEX
Module I SUB-STRUCTURE 9.69% 9.69% 9.69%
Module II SLAB-ON-FILL 5.91% 5.91% 5.91%
Module III GROUND FLOOR RC WALL 10.33% 10.33% 10.33%
Module IV SECOND FLOOR SUSPENDED SLAB 6.55% 6.55% 6.55%
Module V SECOND FLOOR RC WALL 11.66% 11.66% 11.66%
Module VIA STEEL FRAMING WORKS 11.26% 11.26% 11.26%
Module VIB ROOFING & ACCESSORIES 4.19% 4.19% 4.19%
Module VIC MISCELLANEOUS CONCRETE 2.10% 2.10% 2.10%
Module VID MASONRY FINISHES 11.12% 11.12% 11.12%
Module VII CARPENTRY 9.66% 9.66% 9.66%
7.01 Ceilings, Eaves & Vents 3.74% 3.74% 3.74%
7.02 Dry Wall Partitions(Double-walled) 2.21% 2.21% 2.21%
7.03 Interior PVC Doors & Jambs 2.28% 2.28% 2.28%
7.04 Cabinet Doors 300mmx650mm (Kitchen) 0.38% 0.38% 0.38%
7.05 Cabinet Doors 900mmx1500mm (Bedroom) 0.69% 0.69% 0.69%
7.06 Wires & Conduits 0.36% 0.36% 0.36%
Module VIIIA FINISHING WORKS 5.68% 5.68% 5.68%
8.01 Tileworks 2.62% 2.62% 2.62%
8.02 1st Coat Painting 2.85% 2.85% 2.85%
8.03 Lot Levelling 0.21% 0.21% 0.21%
Module VIIIB MOVE-IN WORKS 11.86% 11.86% 11.86%
8.04 Plumbing Fixtures 4.88% 4.88% 4.88%
8.05 Electrical Fixtures 1.74% 1.74% 1.74%
8.06 Final Coat Painting 4.65% 4.65% 4.65%
8.07 Clean-up & Turnover 0.48% 0.48% 0.48%
8.08 Tapping To Main 0.10% 0.10% 0.10%
TOTAL 100.00% 100.00% 100.00%