Method Statement - Relocation of Water Meter
Method Statement - Relocation of Water Meter
METHOD STATEMENT
FOR THE RELOCATION OF WATER METER
FOR RC CONTRACT 560-S28 LAYDOWN
AT T113 X T186
Document No.:01-001-00
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
TABLE OF CONTENTS
1.0 PURPOSE 03
1.0 PURPOSE
The intent of this document is to provide a complete Method Statement for the use of materials, equipment,
tools and plants, It includes the manpower and construction methodology in compliance with RC requirements,
drawings and technical specification with safety measures and quality control.
The intended scope of work includes the relocation of existing Marafiq’s water meter.
List of Equipment
Water Meter
Permits to be attained
1. MaSa Water line Permit
2. Encroachment permit
3. Plant outage request permit
2.3. Materials
2.5.1 The existing water meter will be removed first with safe and sound.
2.5.2 Install the water meter at new location
2.5.3 Site Clean up
2.5.4 Remove all tools used, equipment and materials from the site upon completion of work.
2.5.5 Welfare facilities on site shall be provided as per RC requirement
2.5.6 Clean and repair damages caused by installation and construction activities use for temporary works.
2.5.7 Restore existing and permanent facilities used during construction to original or better condition.
Construction Manager – will be the one to plan and coordinate all the activities in the site and will be
responsible for coordinating with all other departments as well.
Safety Personnel – will be the one to establish all necessary warning signs and barricades establish
the high risk areas in coordination with the Construction Manager and constantly monitor the activity
in terms of safety to all the workers. Furthermore he will give advice on current and forecasted safety
issues and concern.
Site Engineer - will be the one to implement the instruction of the Construction Manager in the site,
he will also directly supervise constantly the manpower and equipment working in the area and
implement all safety regulation and precaution set by the safety personnel.
Quality Control Inspector – Will be the one to inspect and monitor the repaired area before
recommending to RC Engineer for inspection through RFI. (Request for inspection)
Safety Manager – Will be responsible for managing day to day activities and will identify hazards,
evaluate risks, advise safe and best practices for the safety of all personals.
Safety Officer – will report directly to safety manager, and will assist him to organise the site as per
RC approved procedures
Supervisor – will be the one to supervise and assign the works as per schedule.
Plumber — will be responsible for relocating the water meter and allied plumbing works
Site Engineer — 1
Supervisors — 1
Skilled Helpers — 1
Plumber — 1
Electrician — 1
Skips will be provided at site for garbage collection and will be disposed of properly.
Spill tray will be provided for the genset or compressor in order to avoid oil spill.
Spill kit will be kept at site
15.1 Personal Protective Equipment shall be considered only as a “last resort of defence” against
potential risks and hazards. Where so ever possible hazards and risk are to be addressed and
reduced by other means.
15.2 based upon the findings of 3.1.3 Section 1 and 11 above the contractor shall ensure that
adequate stock of Personal Protective Equipment are readily either available on site or issued to
personnel. PPE shall be considered as consumable items.
15.3 All PPE utilised shall be manufactured to a recognized international acceptable standards
All the manual workers that will be working in the site will be informed and reminded by conducting
morning tool box meeting in order to continuously remind them of the existing safety risk and it will
be handled by the designated site supervisor and sometimes with the presence of the safety
personnel.
The following are the safety procedure that will be implemented in case of accident.
In case of traffic accident or person hit by the equipment notify immediately the police and
emergency crew do not engage in moving the person who are injured.
Emergency contact numbers will be prominently posted on bulletin board.
Police — 999
Ambulance — 997
Industrial security — (03) 341 777
Fire brigade — 998
Waste water — (03) 341 0109
SCECO — (03) 341 7341
Potable water — (03) 341 6095