Underground FOC Guidelines
Underground FOC Guidelines
Protocol for
Underground
Installation
of FOC
For PLDT / SMART
Fiber Optic Cable
Network Projects
Network Planning
- Techstands
Network Build
- GMM ME
- NL ME
- SL ME
- VisMin ME
Network Operations
- FxATOp
Prepared by the following: Reviewed by the following:
1. Purpose------------------------------------------------------------- P. 3
2. Standards---------------------------------------------------------- P. 3-8
2.1 Trench Width and Depth------------------------------ P. 3
2.2 Manhole Interval----------------------------------------- P. 3-4
2.3 Electronic Marker---------------------------------------- P. 5
2.4 HDPE Conduit Specification------------------------- P. 5
2.5 Warning Tape--------------------------------------------- P. 5-6
2.6 Non-Metallic and Metallic----------------------------- P. 6-7
2.7 Cable Tag--------------------------------------------------- P. 7-8
2.8 Grounding of Armoured FOC----------------------- P. 8
3. Methodology------------------------------------------------------ P. 9-42
3.1 Staking------------------------------------------------------ P. 9-14
3.2 Ground Trenching--------------------------------------- P. 14-20
3.3 Bridge and Culvert Crossing------------------------ P. 21-22
3.4 Conduit Preparation and Installation------------ P. 22-25
3.5 Reinstatement-------------------------------------------- P. 25-28
3.6 FOC Preparation and Insertion--------------------- P. 28-39
3.7 FOC Testing and Acceptance----------------------- P. 39
3.8 As-Built Plan---------------------------------------------- P. 39-42
3.9 Safety Guidelines P. 43-46
Annexes------------------------------------------------------------ P. 47-69
1. PURPOSE
1.1 This document shall cover the standard underground installation of fiber
optic cable for the PLDT/SMART Fiber Optic Cable Network Projects.
2. STANDARDS
1.50m
SPLICE LOOP - 15m/15m MAINT. LOOP - 15m. MAINT. LOOP - 15m. MAINT. LOOP - 15m. SPLICE LOOP - 15m/15m
4200m.(FOC Length)
2.2.6 In case the manhole is along the side of the road and there is an
on-going sidewalk construction, the manhole cover should be level
to the proposed height of the sidewalk (subject for DPWH
verification).
Note: This should be done only if there is an on-going sidewalk
construction. In case wherein there is a provision of sidewalk
construction but cannot be implemented within the duration of the
on-going PLDT project, must proceed to item 2.2.4.
Proposed Pathway
2.4.1 Both SMART and PLDT shall use 50mm or 63mm diameter
(HDPE) High Density Polyethylene Conduit to cater future
expansion/provisioning
2.4.2 HDPE Conduit to be used shall be SDR 13.5 for Direct Buried and
SDR 11 for Trenchless Boring
2.6.1.1 Attenuation
@1310 nm 0.4db/km
@1550 nm 0.3db/km
1. Blue 7. Red
2. Orange 8. Black
3. Green 9. Yellow
4. Brown 10. Violet
5. Slate 11. Rose
6. White 12. Aqua
1. Blue 7. Red
2. Orange 8. Black
3. Green 9. Yellow
4. Brown 10. Violet
5. Slate 11. Rose
6. White 12. Aqua
Material HDPE
Thickness 2 mm
Tensile Strength 16.5 MPa (min.)
Ultimate Elongation 300%
2.6.7 The cable jacket shall have two (2) permanent red stripe markings
printed 180 degrees apart in order to differentiate it from copper
cables.
2.6.8 The outer jackets of the cables shall be continuous, free from holes,
splits, blisters, or inclusions. The same requirements hold for any
inner jackets within a given cable structure as well as for fiber
coatings.
Cable tag
Cable tag
2.8.2 The National Electrical Code (NEC) and the National Electrical
Safety Code (NESC) are each recognized as ANSI documents and
define the grounding and bonding frequency of the optical fiber
cable plant. The NEC recommends in Article 770 that non-current
carrying metallic members (armour shield, metallic central member,
and metallic strength member) of optical fiber cables be bonded
and grounded at the point of entrance into a building or residence.
Note that the NEC recommends that the grounding wire on the
outside plant cable at the building entrance should be bonded
together with all the building grounding electrodes (main grounding
busbar). This grounding scheme limits the potential difference
between the outside cable plant and the building wiring system.
2.8.4 The contractor shall utilize existing busbar. Otherwise, install new
grounding system using ground rod.
RROW LIMIT
CURB & GUTTER CURB & GUTTER
SIDEWALK SIDEWALK
C
L
10.0m 10.0m
RROW LIMIT
SIDEWALK SIDEWALK
UNDERGROUND RCPC
PLANTING STRIP
2m NOTE: MANHOLE SHOULD BE INSTALLED ON EITHER
0.50m
SIDE OF THE ROAD.
UNDERGROUND UTILITY PROPOSED PLDT MH
E
SID
IN
TA
UN
MO
GUARD RAIL
PAVEMENT PAVEMENT
CLIFF SIDE
PROPOSED PLDT MH
GUARD RAIL
PAVEMENT
R
AP
IP
R
R
IP
AP
R
RICEFIELD RICEFIELD
NOTE: IF WITH COMPETITOR FACILITY, INSTALL MANHOLE
AT OPPOSITE SIDE WITH THE APPROVAL OF DPWH.
CL
1.50m 3.35m 3.05m 3.05m 3.35m 1.50m
SHOULDER
GROUTED
REINFORCED
RIP-RAP
LINE CANAL
CL
1.50m 3.35m 3.05m 3.05m 3.35m 1.50m
SHOULDER SHOULDER
REINFORCED REINFORCED
LINE CANAL LINE CANAL
CL
1.50m 3.35m 3.05m 3.05m 3.35m 1.50m
SHOULDER SHOULDER
GROUTED GROUTED
RIP-RAP RIP-RAP
3.1.3 The installation of the underground plant facilities shall utilize the
following method when applicable. (discuss in item 3.2)
3.1.4 Fiber optic cables are inserted in a conduit which is laid in direct
contact with earth, protected mechanically from accidents, insect
attack and chemical effects of soil.
3.1.5.1 Width of road shoulders – the conduit and fiber optic cable
networks shall be installed in compliance with DPWH D.O.
26 Series of 2011 (“Policy on Diggings/Excavations by
Private and Public Utilities on National Roads”).
3.1.6 Secure permits from Local from Local and National Government
Agencies and/or Private Property before starting any excavations.
Comply with all ordinances and regulations before excavating on
private property, crossing streams or boring under streets or
railways.
3.1.8 The work should be organized that the trenching and/or plowing
together with the placements of cables and other accessories of the
buried plant shall be done concurrently. In this manner, interval
from start to completion of any section of the project is held to a
minimum.
3.1.9 When specifying reel lengths, provide allowance for cable loop at
splice points and fiber looping through the closures.
3.2.1.2 Lower down the “Chain Assembly with carbide tooth” and
start digging until desired depth is attained (e.g., 1500mm)
3.2.3.2 The drilling fluids used in the boring equipment shall not
have any effects on the physical and chemical properties
of the HDPE or PVC conduit and the outer jacket of the
fiber optic cable.
DRAINAGE DRAINAGE
INVERT INVERT
1.5m 1.5m
3.3.1.4 Nuts and bolts should be welded then painted with epoxy
primer.
3.3.2.1 First option, implement HDD method. All three (3) trial
drillings shall be witnessed by OPPM Project Inspector and
Operations Representative.
3.3.2.2 If HDD fails on the third trial, check the depth of the top
slab. If the depth is >1500mm, apply Cross-Over Open
trench.
Yellow
conduit Black conduit
3.5 REINSTATEMENT
3.5.1.1 Backfilling
Conduit Seal
Conduit Clamp
Venturi
Seal Disk
Connection of
Hydraulic Power
Source to the
Blowing Machine
Connection of
Hydraulic Hose
to the Blowing
Machine
Connecting Air
Compressor to the
Blowing Machine
3.7.1 Measure the cable loss (splice point to splice point starting from the
ODF before and after the laying of FOC. This will establish
attenuation per span for future reference.
3.7.2 Manufacturer of FOC must provide factory test result and FOC
specifications including Mode Field Diameter (MFD) as part of the
FOC cable reel.
3.8 AS-BUILT-PLAN
3.8.1 GPS reading and 3 point references shall be provided in the As-
Built Plan for all:
3.8.1.2 Manholes
3.8.3 For HDD methodology, bore logs and FOC route location (in
reference with road centerline) must be reflected as part of the As-
built plan. Bore log data should be every rod.
MUNICIPAL BOUNDARY
KM24+16.00 TBNHH003
TBNHH002 KM23 + 14.00 DPWH ROAD WIDENING D
C GPS REFERENCE TBNSH006 DPWH ROAD WIDENING KM25+50.00
KM22+138.00 BRIDGE BRIDGE
HH03
N 10°40`32.8" ATTACHMENT ATTACHMENT ADDITIONAL SP/SH
KM21+170.00 TBNSH005
E 122°22`30.7" SIBALOM BRIDGE BUYUAN BR PLDT-SMART
NANGA BR.
4.1.2 Coverage
4.1.9.3 Barricades shall be three (3) feet vertical height from the
ground, when no other more practical height specification
is available.
4.1.11 Tool Box Meeting or Gang Meeting refers to daily meeting among
workers and their respective supervisors for the purpose of
instruction, discussion and proper briefing on the planned work, the
assessment of past work, the possibility or actual occurrence of
accidents at the site, tips and suggestions on how to prevent
possible accidents and other related matters.
4.1.13 Recommendations