Risk Assessment For Stone Works: Project Name
Risk Assessment For Stone Works: Project Name
REF:
RISK ASSESSMENT FOR STONE WORKS REV:
DATE:
RISK RISK
RESIDUAL RISK
CONSEQUENCES/ EVALUATION LEVEL ACCEP
S.N. ACTIVITY HAZARD CAUSES OF HAZARD IMPLEMENTED CONTROL MEASURES
IMPACT Y/N?
P S H/M/L P S H/M/L
1 Material Falling Unstable stacks; uneven Injuries to parts - Off-loading of materials with
delivery object from grounds; stacking marble of the body; the use of mobile plant (e.g.
or granite too high so that Damage to forklift); only competent
Loose person to operate machine,
they may collapse property (broken
materials riggers must be assisting the
marble)
operator at all times during
operation.
- Supervisor should have a
stacking program at all times
indicating direction and
height
- Floors/grounds used for
stacking must be kept level
and free from obstructions at
2 2 4 all times 2 2 4 y
- All stackers to be trained on
how to stack properly and
safely
Daily Safe Task
Instructions must be conducted by
the SRS prior to work
commencement on a daily basis
indicating all the associated
hazards and risks together with the
control measures identified under
the scope of work. Site operatives
must sign in the form as proof of
attendance and understanding of all
the items raised and discussed
2 Shifting -Untrained personnel - Injury 3 3 9 - Use only tested and certified 2 2 4 y
marble and - Falling performing task - Damage to lifting equipments and gears.
mortar Objects. Property - Use designed and certified
Defective equipments
- Failure unloading platforms.
of Lifting. - Engage experienced, trained
- and certified operator and
Page 1 of 7
PROJECT NAME
REF:
RISK ASSESSMENT FOR STONE WORKS REV:
DATE:
Page 2 of 7
PROJECT NAME
REF:
RISK ASSESSMENT FOR STONE WORKS REV:
DATE:
Page 3 of 7
PROJECT NAME
REF:
RISK ASSESSMENT FOR STONE WORKS REV:
DATE:
Persons in danger
Persons passing the site location/ truck routes, e.g. members of the public and persons in the Vehicles.
Page 4 of 7
PROJECT NAME
REF:
RISK ASSESSMENT FOR STONE WORKS REV:
DATE:
All personnel in the team are to be made aware of the safe systems of work.
Training and experience for personnel to use electrical equipments and vibratory equipments.
Emergency procedures
Site emergency procedures should make provision for the rescue of individuals from heights.
First-aid facilities should be available to cope with any significant injuries that may arise from the work.
Work should be monitored by Foreman and charge hand who are trained to ensure that any additional precautions or equipment required are
provided.
Page 5 of 7
PROJECT NAME
REF:
RISK ASSESSMENT FOR STONE WORKS REV:
DATE:
RISK MATRIX
Risk Rating (RR) – Severity x Likelihood
LIKELIHOOD
(PROBABILITY)
Likely
(P) Rare Unlikely Possible Almost certain
Could happen often (on
Remote possibility (once Could happen but rare Could happen occasionally Could happen frequently
average once a month or
every 3 years or more) (typically once in a year) (on average quarterly) (once a week or more)
more)
SEVERITY 1 2 3 5
4
(IMPACT)
(S)
Low Low Low Low Medium
Insignificant 1
1 2 3 4 5
Quick, easy controls should be implemented immediately and further action planned for when resources permit. Monitoring required
1-4
ensuring controls are maintained. Manage through routine procedures. Go for economic improvements where possible. Incident
Low
report must be completed.
Page 6 of 7
PROJECT NAME
REF:
RISK ASSESSMENT FOR STONE WORKS REV:
DATE:
Aim to reduce risks but costs of prevention may be limited. Undertake a risk assessment of the situation / task and implement the
appropriate actions. Actions should have a timescale and should be monitored. Where the risk involves work in progress undertake
5-12 a risk assessment as soon as possible to ensure the safety of the situation or task. Work should not start until the risk is
Medium reduced to an acceptable level. Considerable resources may have to be allocated. Contact your Manager and Risk Manager by
telephone about the actions that should be taken to reduce the risk/s. incident report must be completed. Incident must be added
to service risk register.
Do not commence the activity until a risk assessment has been completed to ensure the safety of the situation or task. If it is
15-25 not possible to reduce or eliminate the risk even with unlimited resources, work must remain prohibited. Inform your relevant
High Director, your Manager and the Risk Manager immediately by telephone. Incident report must be completed. Incident must be
added to service risk register.
Page 7 of 7