Lab Manual Electrical Power System Protection Systems PTUK
Lab Manual Electrical Power System Protection Systems PTUK
Prepared by:
2021
Palestine Technical University-Kadoorie
Faculty of Engineering and Technology | Electrical Engineering Department
Electrical Power Systems Protection Lab || Eng. TareQ FoQha
Abstract
The power systems protection laboratory is designed to directly apply theory learned in
lectures to devices that will be studied in the laboratory. Power system protection is concerned
with protecting electrical power systems from faults within the network by isolating the
faulted components so as to leave as much of the remaining the electrical network operational
as possible. Moreover, by properly protecting the system components from overloading, the
probability of fires and other catastrophic and expensive system failures can be minimized.
The creation of a Power System Protection Lab at Palestine Technical University gives
students the opportunity to gain some real world experience in protection. Moreover, a
laboratory of this type facilitates educational opportunities. It also provides numerous
additional benefits such as research.
Objectives
The Laboratory covers all phases for the Protection devices specific of this field.
All protection and control devices of the electrical machines are exactly equal to those
installed in the industrial units. So, the sequences of control maneuvers in the control
stations are exactly equal to those necessary in the industrial units.
List of Experiments
Chapter (2) Protection Relays For High And Low Voltage Networks 06-38
Appendices 94-103
Chapter 1
Introduction
Contents
Experiment (1) General Considerations on Protection Devices 02-05
Introduction:
This part of the manual describes the main protection devices employed on electrical lines or
central stations. The purpose is to obtain a set of easily consultable news referring to the
bibliography for the known notions.
For the static equipments, the term relay can be used when it carries out a specific elementary
logic function while the term relay device is applied to equipment including a total logic
function corresponding to the combination of more elementary logic functions.
Relay device performing a specific protection or automatism function as it results from the
qualification of the same device.
These are among plant engineering systems designed for a specific purpose, in which a
determinant part is played by the electrical relays which are sets with the purpose of
protection. A protection system includes the measurement transformers, the transmission
channels, the cables or conductors, the release circuits, etc. necessary to achieve the
purpose. The designer qualifies the protection system specifying the job it must perform and
describing in details the characteristics of the elements composing the same system.
Electrical Relay:
Equipment to be used to cause predetermined changes of state in its output electrical circuits
when particular power supply conditions occur across its input electrical circuits.
Relay Device:
Set of relays connected between them so that they fulfill the purpose the device is supposed to
perform and with which the manufacturer qualifies the same device. The terms relay and relay
device are usually applied equipments of electromechanical kind, while for those of static kind
it is sometimes difficult to find the border between the relay and relay device.
Electrical variable which passage across a specified value, which is associated to a given
accuracy, determines the relay operation; the characteristic variable characterizes the name of
the relay. In the relays with one input power supply variable the names of the characteristic
variable and the input power supply ones usually coincide; however there are exceptions: e.g.
those relays in which the characteristic variable is the frequency, that are generally powered
with a voltage.
Relay in which the output circuits state change depends on the passage of the characteristic
variable across a specific service value which is associated to a given accuracy. Besides the
characteristic variable, other elements characterize the relay and are included in its
denomination; in particular the indication determining if the accuracy refers to the operation
increasing or dropping the characteristic variable (maximum or minimum relay) and, in case,
the indication if it is a relay with specified intervention time.
Relay in which the output circuits stage change depends on the shift of the input circuits
conditions from those corresponding to the relay characteristic threshold line, shift at which a
given accuracy is associated to.
In an alternated current measurement relay with two input power supply circuits, central value
in the field of the angles composed by the representative vectors of the two input power supply
variables, for which the relay is invited to intervene; the value of the characteristic angle can
characterize the relay denomination. In the electromechanical relays, there is the maximum
relay operative torque in correspondence to the characteristic angle of the relay and the range
of the angles has a particular value.
Ranges of Intervention:
In a measurement relay with characteristic threshold line, the two ranges defined by the
threshold line set on the same relay; for the conditions corresponding to one of the two ranges,
the relay is forced to intervene in a direction, for the conditions corresponding to the other
range the relay is forced to intervene in the reverse direction (or not to intervene).
In a measurement relay with characteristic threshold line, it is the line for which the relay - in
conditions specified according to the indications reported at the regulation elements or
however defined by the manufacturer - is in still.
In a measurement relay with characteristic threshold line, the lines located on the two sides of
the theoretical line, delimiting the maximum and minimum values, within which the relay, in
specified conditions, could not intervene.
Measurement relay with characteristic variable in which the prescriptions related to the
accuracy refer to the achievement of the operation value of the same characteristic variable
when its values rise or drop.
Chapter 2
Protection Relays For High And Low Voltage Networks
Contents
Experiment (1) Overcurrent Relay (SR1) 07-11
Objectives:
1. Connection and study of a fixed time maximum current relay and of a 3- phase line
short-circuit one with different currents.
2. To measure the tripping time of maximum-current (over load and short-circuit) in a
three-phase network with different current values;
These are the most famous protection relays. Main purpose is the detection of the phase to
phase or phase to ground faults. In particular the relay 50N or 51N can be used also with
networks with insulated neutral under particular conditions.
Figure (1)
SI1 first level regulation range (overload).
SI2 second level regulation range (short-circuit)
Necessary Material:
1. AMT-3/EV: Variable three-phase power supply mod.
2. SR-1/EV: Overcurrent relay.
3. RC3-PT/EV: Three-phase rheostat 3 x 50.
4. Contactor with on-off control.
5. AZ-VIP: Digital instrument.
Experimental Procedures:
1. Connect the circuit as shown in figure 2.
Figure (2)
2. Connect the auxiliary power line of 230 Vac with the relay, without powering it.
3. Connect the relay between the variable power line and the load rheostat (Y-connection).
4. Suppose to adjust the device with the following design data:
Overload threshold = 0.5-A;
Tripping delay time = 5-s;
Short-circuit threshold = 1-A;
Tripping delay time = 0.1-s.
5. Normal Condition: Power the relay with the auxiliary supply voltage and check
whether which led will goes on in the frontal panel. Check the contacts of the
contactor.
6. Adjust the voltage of the variable power line and the load rheostat to obtain a current
lower than 0.5-A.
7. Overload Condition: Increase the test current over 0.5-A, record the load current and
the tripping time and check the operation of the relay.
8. This condition is kept stored in memory even after the current drops below the preset
value; therefore the device will be reset with the corresponding button, resetting
manually the device by pressing the RESET button.
9. Short Circuit Condition: Increase the test current over 1-A, record the load current
and the tripping time and check the operation of the relay.
10. This condition is kept stored in memory even after the current drops below the preset
value; therefore the device will be reset with the corresponding button, resetting
manually the device by pressing the RESET button.
Questions:
1. Suppose you have to protect a three–phase induction motor from an overload condition,
the nameplate of the motor is shown in figure 1.
(A) Sketch the connection needed to connect three-phase induction motor with:
(1) 3-phase supply
(2) Contactor
(3) SR1: Overcurrent relay
(B) Explain how to put the settings of the relay?
(C) Explain how to reset the relay after removing the cause of overload?
(D) Explain the operation of the relay in this case?
Hints:
1) Motors with a service factor (SF) of 1.15 or more, the settings of the overload relay
should be 125% of the full load current.
2) Motors with a service factor (SF) less than 1.15, the settings of the overload relay should
be 115% of the full load current.
Objectives:
1. Connection and study of a maximum and minimum voltage relay in a 3-phase network.
2. To measure the tripping time of maximum/minimum in a three-phase network with
different voltage values;
The purpose of the maximum and/or minimum voltage relays is to detect anomalous voltage
rising or dropping near the production or usage centers so to prevent damages of machines or
OFF parallel situations.
Figure (1)
Necessary Material:
1. AMT-3/EV: Variable three-phase power supply mod.
2. SR-3/EV: Max/min three phase voltage relay.
3. IL-2/EV: Variable inductive load mod.
4. Contactor with on-off control.
5. AZ-VIP: Digital instrument.
Experimental Procedures:
1. Connect the circuit as shown in figure 1.
Figure (1)
6. Overvoltage Condition: Increase the test voltage over 400 V, record the line voltage
and the tripping time and check the operation of the relay (with no load condition).
7. The relay has a hysteresis of 3% in respect to the set point, take back the voltage to the
nominal value (380 V) and record the reset value.
8. Undervoltage Condition: Drop the test voltage under 342 V, record the line voltage
and the tripping time and check the operation of the relay (with no load condition).
9. The relay has a hysteresis of 3% in respect to the set point, take back the voltage to the
nominal value (380 V) and record the reset value.
10. Undervoltage Condition: Set the system under load with the insertion of the inductive
load and measure the following:
Minimum Line Measured Reset
Inductive intervention
voltage voltage delay Value
Load delay
threshold % (V) (Sec) (V)
B 95% 5 sec
Questions:
1. Suppose you have to protect a three–phase induction motor from an undervoltage
condition, the nameplate of the motor is shown in figure 1.
(A) Sketch the connection needed to connect three-phase induction motor with:
(1) 3-phase power supply;
(2) Contactor;
(3) SR3: Max/Min voltage relay.
(B) Explain how to put the settings of the relay to protect the motor from
undervoltage condition; the voltage applied to the motor should be at least
95% of the nominal voltage?
(C) Explain how to reset the relay after removing the cause of undervoltage?
(D) Explain the operation of the relay in this case?
Objectives:
1. Connection and study of a maximum current directional relay for maximum current.
2. To measure the tripping time with inverse current flow.
It is a much extended family of equipment sharing the capacity to operate a control on the
power direction. The concept of direction in the alternated currents is not proper; we should
rather talk of angular relation between the voltages and the phase currents. However, by
convention, we have fixed to consider as positive a vector direction resulting from the
composition of a reference vector with another set within ± 90° from the first; as negative the
one resulting from the composition with a superior angle.
The diagram of figure 1 shows straight line “L” called inversion or limit or threshold. One of
the pros of directional relays is just the one to operate, near the inversion straight line, without
operation uncertainties. To fulfill their purpose, the directional relays carry out the
measurement comparing two variables in module and in phase: the voltage and the current.
Figure (1)
Generally, with the help of watt-meters, ammeters and voltmeters, the positive or negative
power directions are checked associating the open or closed state of the output relay.
The control of the power provided by the production central station or absorbed by the user is
a need appeared since the first electrical power distribution. This is due by the fact that the
power market is made of more producers and also by the control of the contractual conditions
(active, reactive power, absorbed power excess, etc.). It is more obvious that the simple
current control, actuated with the maximum or minimum current protections, in case of more
or less shifted loads does not show the actual degree of work or the involved power. As
function of the needs of the different users and producers, it is advisable to carry out
protections sensible to the power expressed in one of the three relations:
Apparent power: S = V I
Active power: P = V I cos φ
Reactive power: Q = V I sin φ
In fact, while the generators keep equally employed for the production of the components in
quadrature, the dissipation by Joule effect considers only the resistive component, so, in
different power factor conditions, there are different dissipations to equal active power, too.
The power relays must measure the two variables, V and I, so that it is possible to compare
the phase (analogously to the watt-meters).
The adjustment of the intervention threshold of the power directional relays is expressed by
the following equation: F = K Iiv cos φ
In the protection relays against inverse power it is necessary for the polar operating quadrants,
block and threshold, to be clearly defined to prevent operation uncertainties near the inversion
zone when the generator is used to produce reactive instead of active power. A characteristic
situation is represented in figure 2 where a small alternator is set in parallel on a considerable
network.
Figure (2)
18 | Page Electrical PS Protection Lab
Palestine Technical University-Kadoorie
Faculty of Engineering and Technology | Electrical Engineering Department
Electrical Power Systems Protection Lab || Eng. TareQ FoQha
In the example mentioned in the last figure 1 –during normal operation– the users coming
from the lines E and F absorb the current I1 + I2 as they are powered by the line as well as the
local generator. In case the national line would be missing, all charge of the sector would rest
on the local generator with logical intervention of the maximum current protections. All this is
regular but in case the point A is to be sectioned for electrical maintenance and with no-load
users D E F or those with weak absorptions, there is a danger situation and the distribution
societies force the generator separation although no actual power inversion occur. The solution
consists in adding a protection device against inverse power in point C provided with high
sensitivity. The completion of the circuit under test sees a further protection against the
inverse power in point D.
The intervention characteristics of a power inversion relay should be the as shown in figure 2.
The directional relays are a very large family of equipment sharing the capacity to control the
power direction. The concept of direction comes from the angular relations between phase
voltages and currents where, by convention, positive is considered the direction of a vector
resulting from the composition of a reference vector with another set within ± 90° from the
first; negative the one resulting from the composition with a superior angle. To fulfill their
purpose, the directional relays carry out the measurement comparing two variables in module
and phase: voltage and current. The adjustment of the intervention current threshold, the delay
time and the characteristic angle α (+/- 30°) enables to use the relay in different applications.
This protection relay senses the current direction, and consequently, operates the output
contacts.
According to the relay model, and the selected connection, the relay is able to:
Block the active power direction of a generator (Reverse Power Relay). Generators
prime movers (Diesel engines or turbines) are designed to develop mechanical power,
not to accept power. Mechanical power is directly related with the generated active
power. When in parallel, it is possible that a generator becomes a motor (“accepting”
power). Then this “motor” drags the prime mover, with eventual danger for the
Diesel or the turbine.
Use of the relay to block the reverse current and active power. The following figure shows the
voltages vectors in a 3-ph balanced system.
Vector V12 is the Reference vector in the second figure, with the following parameters:
The current I1R is the current active component of I1RL, and its direction coincides with the E1
vector.
I1R = I1RL * cos (φ + Ψ- α)
I1R is max when cos (φ + Ψ- α) = 1 → (φ + Ψ- α); φ = α - Ψ = -30°- (-30°)= 0.
Necessary Material:
1. AMT-3/EV: Variable three-phase power supply mod.
2. SR-10/EV: Maximum current directional relay.
3. RL-2/EV: Variable resistive load mod.
4. IL-2/EV: Variable inductive load mod.
5. AZ-VIP: Digital instrument.
Experimental Procedures:
1. Connect the circuit as shown in figure 1.
Figure (1)
2. Connect the terminals (Power Supply) to the 230-Vac auxiliary power supply line, but
do not connect the voltage. Connect the terminal PE to the protection conductor, too.
3. Connect the terminals (Voltage Input) respectively to L1 and L2 of the variable three-
phase power supply source. Connect a voltmeter to measure the relay input alternated
voltage (line voltage).
4. From the same three-phase power supply source mentioned above, by-pass the three-
phase load consisting in the RC rheostat (Y-connection load), the current I1 (also
called R1) must reach the terminals (Current Input).
5. Connect an ammeter to measure the relay input alternated current (load current). In
practice, it is sufficient to insert the load only on the conductor L1 – Neutral.
6. Suppose and adjust the device with the following design data:
- Dip-switch angle α = 30°;
- Delayed intervention dip-switch = ON;
- Inverse current threshold (Is) = 0,7 A (dip-switch a 2 + 4 ON);
- Intervention time (Ts) = 5 s (dip-switch t 0.1 + 0.8 + 4).
7. Some important considerations:
- SR-10/EV senses only one phase current (the L1 phase).
- If the load is balanced, the three currents L1-L2-L3 are equal, so sensing one of them
is enough.
- If the load is not balanced, the relay will trip ONLY if the L1 current is over the
limit.
8. As set, it is a directional relay that, with the current direction (In = 5A) to the input
(input in the higher terminal)
9. Check the correspondence of the output relay contacts (powered device not in alarm
state).
10. The relay reset is manual; it can be done only after the current goes back under the
threshold, with the pushbutton on the front panel or with the insertion of a jumper into
the RESET terminals.
2. To simulate the direct current invert the SR-10 current input terminals, Modify the load
to increase the current over 0.7 A, and up to 2 A.
(Dotted lines in the last design in figure 1).
Measured With
Calculated
AZ-VIP/EV
Comments
I1RL (A) PF I1R = I1RL * PF (A)
2. Now invert the SR-10 current input terminals, to simulate the direct current. Modify
the load to increase the current I1R over 0.7 A, and up to 2 A.
(Dotted lines in the last design).
Measured With
Calculated
AZ-VIP/EV
Comments
I1RL (A) PF I1R = I1RL * PF (A)
Objectives:
1. Use of the differential relay in a single phase network, control of the tripping current
and the tripping delay time. Simulation of a fault: current imbalance between wires.
2. Use of the differential relay in a 3-phase network, without neutral wire. Simulation of
a fault: current imbalance between wires.
3. Use of the differential relay in a 3-phase network, with neutral wire. Simulation of a
fault: current imbalance between wires.
4. Use of the differential relay in a 3-phase network, TN connection. Simulation of a fault
to ground, use of the Isolation Transformer SR21.
We start the study of Differential Protections with the classical example of the single-phase
ELCB (Earth Leakage Circuit Breaker), a device that become common even at home. It will
help to understand the principle of the differential currents and its technical solution. See Fig 1
Figure (1)
The heart of the device is a toroidal magnetic core that has 3 coils:
- Two coils are run by the two currents of the single-phase current. Both coils are exactly
equal, and due to the currents, both produce the same magnetic flux, but opposite
direction.
- The third coil, the differential coil, generates a voltage only when there is a resultant
magnetic flux in the toroid. This voltage, processed by the internal circuits of the ELCB,
provokes the opening of the breaker.
The ELCB equations are (all equations are vectorial type, not algebraic):
when there is no fault: |Ф1 + Ф2 | = 0
when there is a fault: |Ф1 + Ф2 | = ФR
as one of the currents is predominant, and therefore, one of the two fluxes is higher than the
other.
ELCBs are sensitive to different currents differences |I1 + I2 | = Idn, according to the protected
device. Then we have:
- Low sensitivity, Idn ≥ 1 A
- Medium sensitivity: 100 ≤ Idn ≤ 500 mA
- High sensitivity: Idn ≤ 30 mA
Figure (2)
Figure (3)
Figure (4)
Figure (5)
27 | Page Electrical PS Protection Lab
Palestine Technical University-Kadoorie
Faculty of Engineering and Technology | Electrical Engineering Department
Electrical Power Systems Protection Lab || Eng. TareQ FoQha
Fig. 6 shows the circuit, where the difference with the previous ones are the restraint coils, in
series with the secondary currents of the CTs. The purpose of the restraint coil is to prevent
undesired relay operation due to CTs errors. The operating relay current |i1 - i2| required for
tripping is a percentage of the average current through the restraint coils, given by:
| i1 - i2 | ≥ k | i1 + i2 | / 2
K is the proportion of the operating coil current to the restraint coil current.
The restraint coils collect the currents relative to the machines, increasing the currents through
the operating coil. By so doing, the error sensitivity of the CTs is lowered.
Figure (6)
CTR1 / CTR2 = a
Where:
- a = N1 /N2; transformer ratio; N1 = number of coils of the primary; N2 = number of
coils of the secondary.
- CTR1, CTR2: the current transformers ratio of primary and secondary.
Figure (7)
Necessary Material:
1. UAT/EV: Fixed three-phase power supply mod.
2. SR-14/EV: Differential relay.
3. RL-2/EV: Variable resistive load mod.
4. AZ-VIP: Digital instrument.
5. SR21: Isolation Transformer.
6. DMM: Digital Multimeter.
Fault Current Adjustment: Rotary fault current to earth tripping adjustment, 0.25 to 2.5 A.
The constant multiplier IΔnx0.1 – IΔnx1- IΔnx10 is selectable according to the position of the
dip switches, third and fourth lines.
Multiplier K = 0.1, both dip switches to the right.
Multiplier K = 1, upper switch to the left; lower switch to the right
Multiplier K = 10, upper switch to the right; lower switch to the left.
Dip Switches:
First line: AUTO – MAN Reset. When MAN is selected, the Reset is carried out with the
Reset pushbutton.
Second line: used for Time multiplier
Third / Fourth lines: used for Fault Current multiplier.
Fifth line: selectable N-FS.
FS: positive safety activated: the output relay is normally energized, therefore, in the event of
lack of power, the contacts move to the tripping condition.
N: positive safety deactivated: output contacts normally denergized.
Experimental Procedures:
Part I: SR-14 in a single phase line. Simulation of a fault: current imbalance between
wires.
Figure (1)
3. Give power to the relay (230 VAC). With the DMM (ohmmeter), check the continuity.
Check also the other set of output contacts.
Figure (2)
4. Normal Condition: Apply balance load (switch A) to the circuit with the switches
of RL-2A/EV (1);
5. Set RL-2A/EV (2) as indicated in Test 1 with various value of resistance, and
connect as the dotted line. This connection simulates a “controlled imbalance
load” (the imbalance current is controlled by RL-2A/EV (2)).
Relay operation
Test R-load
IΔ Tripping Time Notes
Test (1) A
Test (2) B
Part II: SR-14 in a Three phase line without neutral wire. Simulation of a fault: current
imbalance between wires.
Figure (3)
3. Give power to the relay (230 VAC). With the DMM (ohmmeter), check the continuity.
Check also the other set of output contacts.
4. Normal Condition: Apply a balance load (switch A) to the circuit with the switches of
RL-2A/EV (1);
Figure (4)
5. Set RL-2A/EV (2) as indicated in Test 1 with various value of resistance, and connect
as the dotted line. This connection simulates a “controlled imbalance load” (the
imbalance current is controlled by RL-2A/EV (2)).
Relay operation
Test R-load
IΔ Tripping Time Notes
Test (1) A
Test (2) B
Part III: SR-14 in a Three phase line with neutral wire. Simulation of a fault: current
imbalance between wires.
Figure (5)
3. Give power to the relay (230 VAC). With the DMM (ohmmeter), check the continuity.
Check also the other set of output contacts.
4. Normal Condition: Apply a balance load (switch A) to the circuit with the switches of
RL-2A/EV (1);
Figure (6)
5. Set RL-2A/EV (2) as indicated in Test 1 with various value of resistance, and connect
as the dotted line. This connection simulates a “controlled imbalance load” (the
imbalance current is controlled by RL-2A/EV (2)).
Relay operation
Test R-load
IΔ Tripping Time Notes
Test (1) A
Test (2) B
Part IV: SR-14 in a Three phase line with neutral wire. Simulation of a fault: current
imbalance between wires.
Figure (7)
3. Give power to the relay (230 VAC). With the DMM (ohmmeter), check the continuity.
Check also the other set of output contacts.
4. Normal Condition: Apply a balance load (switch A) to the circuit with the switches of
RL-2A/EV (1);
Figure (8)
5. Set RL-2A/EV (2) as indicated in Test 1 with various value of resistance, and connect
as the dotted line. This connection simulates a “controlled phase to ground fault” (the
imbalance current is controlled by RL-2A/EV (2)).
Relay operation
Test R-load
IΔ Tripping Time Notes
Test (1) A
Test (2) B
Chapter 3
Synchronous Generator Protection
Contents
Part (1) Relay for phase sequence, phase failure and voltage asymmetry.
Objectives:
Studying and applying a relay for:
- Asymmetry adjustment with rotary potentiometer from the 5 to the 15 % with intervention
after DELAY time and automatic reset when the unbalance drops under the 1% of the set
point.
- Adjustment of the intervention time with DELAY potentiometer from 0.1 to 10 s.
- Instant intervention for phase lack or wrong phase sequence.
- Intervention for line frequency variation over the 5%
The electrical and the operation diagram of this relay are shown in the following
figures:
Dip Switches:
Necessary Material:
1. GCB-3/EV: Control board for the generating set mod.
2. MSG-3/EV: Synchronous generator-motor unit mod.
3. RL-2/EV: Variable resistive load mod.
4. IL-2/EV: Variable inductive load mod.
Experimental Procedures:
Part I: Relay for phase sequence, phase failure and voltage asymmetry.
1. Insert three jumpers into the terminals set to power the relay for phase sequence, phase
lacking and voltage asymmetry as indicated in Figure 1.
2. Connect an ohmmeter to check the state of the output relay contact and complete the
wiring involving the step resistive load mod. RL-2/EV, be sure that all switches of the
steps of each phase are in position of excluded load (OFF) as shown in Figure 1.
Test 1: Disconnect one of the three phases and check the intervention of the output relay.
………………………………………………………………………………………………………………………………….….
……………………………………………………………………………………………………………………………….…….
Test 2: Displace one of the three phases with another one and check the intervention of the
output relay.
………………………………………………………………………………………………………………………………….….
……………………………………………………………………………………………………………………………….…….
Figure (1)
44 | Page Electrical PS Protection Lab
Palestine Technical University-Kadoorie
Faculty of Engineering and Technology | Electrical Engineering Department
Electrical Power Systems Protection Lab || Eng. TareQ FoQha
3. Set the synchronous generator under load with the insertion of the resistive load.
Test 3: Put unbalanced load and record the value of phase voltages and currents (using power
analyzer) and delay time (using chronometer), fill the following table.
1. Remove jumpers of the symmetry relay and insert four jumpers into the terminals set to
power the max/min three-phase voltage relay as indicated in Figure 2.
2. Connect an ohmmeter to check the state of the output relay contact and complete the
wiring of the GCB-3/EV panel as shown in Figure 2.
Figure (2)
Increase the voltage supplied by the synchronous generator by increasing the excitation current
and record the time between the “overvoltage” moment and the same output relay tripping one.
Reduce the voltage again to its rated value (400 V) and check the alarm suppression (the
maximum voltage output relays is reset). Consider that the relay has a hysteresis of 3% with
respect to the set point. Determine at which value of voltage will the relay reset?
Maximum
Line voltage Maximum voltage Measured delay Reset Value
voltage threshold
(V) intervention delay (Sec) (V)
%
105% 5 sec
110% 5 sec
Way 1: Decrease the voltage supplied by the synchronous generator by decreasing the excitation
current and record the time between the “undervoltage” moment and the same output relay
tripping one. Increase the voltage again to its rated value (400 V) and check the alarm suppression
(the minimum voltage output relays is reset). Consider that the relay has a hysteresis of 3% with
respect to the set point. Determine at which value of voltage will the relay reset?
Minimum
Line voltage Minimum voltage Measured delay Reset Value
voltage threshold
(V) intervention delay (Sec) (V)
%
95% 5 sec
90% 5 sec
Way 2: Complete the wiring including the step resistive load mod. RL-2/EV. Be sure that all
step switches of each phase are in position of load excluded (OFF). Set the synchronous
generator under load with the insertion of the resistive load (with different values of the
resistive load) and measure the following:
1. Remove jumpers of the max/min voltage relay and Insert two jumpers into the terminals
set to power the max/min frequency relay as indicated in Figure 3.
2. Connect an ohmmeter to check the state of the output relay contact and complete the
wiring of the GCB-3/EV panel as shown in Figure 3.
Figure (3)
Increase the test frequency using RPM potentiometer and record the time between the
overfrequency and the same output relay tripping one.
Decrease the test frequency using RPM potentiometer and record the time between the under
frequency and the same output relay tripping one.
1. Remove jumpers of the max/min frequency relay and connect the 3-Phase Overload and
the Short-Circuit relay with the proper terminals via six jumpers as indicated in
Figure 4.
2. Connect an ohmmeter to check the state of the output relay contact and complete the
wiring of the GCB-3/EV panel and complete the wiring including the step resistive load
mod. RL-2/EV to obtain the current regulation in the ammetric relay as shown in
Figure 4.
Figure (4)
3. Increase the test current by adding resistive load, measure the load current and record
the time between the “overcurrent” and the output relay tripping.
A 0.5 5 sec
C 0.6 5 sec
Questions:
1. Describe the effect of the following Abnormal operating conditions on the
synchrouns generator?
(a) Voltage Asymmetry;
(b) Over and under voltage;
(c) Over and under frequency;
(d) Over load.
(b) If the load attached on the synchronous generator is (B||C = 120Ω) and the
load current measured is 889mA, if the settings of the overload relay are:
overload current = 0.7A with intervention delay of 5 second.
1) Explain how to put the settings of the relay, and explain how to reset the
relay after removing the cause of overload?
2) Explain the operation of the relay after the load attached?
3. Based on the relay for phase sequence, phase failure and voltage asymmetry
experiment answer the following questions:
(a) Sketch the connection needed to connect synchrouns generator with:
1. Relay;
2. 4-pole contactor (on-off) (to switch off the load when phase sequence or
phase failure or voltage asymmetry occur);
3. Variable three-phase resistive load.
(b) If the load attached on the synchronous generator is (C,A,A) and the
settings of the relay are:
- Asymmetry = 10%;
- Delay = 10 Second;
- Reset delay = 0.1 Sec.
Chapter 4
Transmission Line Protection
Contents
Objectives:
1. Protection against overcurrent in a power transmission line using overcurrent relay
SR1/EV.
2. Protection against Single line to ground fault in a power transmission line with insulated
neutral conductor using differential relay SR14/EV.
Necessary Material:
1. SEL-1/EV: Simulator of electric lines mod.
2. P14A/EV: Three-phase transformer mod.
3. Contactor with On-Off control
4. AMT-3/EV: Variable three-phase power supply mod.
5. SR-1/EV: Overcurrent relay.
6. SR-14/EV: Differential relay.
7. IL-2/EV: Variable Inductive load mod.
8. RL-2K/EV: Variable Resistive load mod.
Experimental Procedures:
Part I: Protection against overcurrents in a power transmission line using overcurrent relay SR1.
1. Start this experiment considering the LINE 2 with the following constants: R= 8.9 Ω;
L = 36 mH C = 0.1 µF; Length = 25 km.
2. Connect the circuit as shown in Figure 1.
Figure (1)
B 0.5 5
A || B 0.6 5
Part II: Protection against single line to ground fault in a power transmission line with
insulated neutral conductor using differential relay SR14.
1. Start this experiment considering the LINE 2 with the following constants: R= 18 Ω;
L = 72 mH C = 0.2 µF (with Y connection); Length = 50 km.
2. Connect the circuit as shown in Figure 2.
Figure (2)
Objectives:
To configure the protection device SR16/EV with the use of the DIGSI software as:
1. Instantaneous [50] and delayed [51] maximum current relay to protect a no-load power
transmission line against phase-phase faults.
2. Instantaneous [50N] and delayed [51N] maximum homopolar current relay to protect a
no-load power transmission line against phase-ground faults.
3. Max ground directional current relay [67N], to protect a no-load power transmission
line against phase-ground faults.
4. Distance relay [21], protection against phase-ground and phase-phase fault in a no-load
power transmission line.
Necessary Material:
1. SEL-1/EV: Simulator of electric lines mod.
2. PC with DIGSI software installed.
3. SR16/EV: Distance relay mod.
4. SR20/EV: Power transmission line simulator mod.
5. SR21/EV: Isolation transformer mod.
6. UAT/EV: Fixed Power supply mod.
7. RC3-PT/EV: Rheostat mod.
57 | Page Electrical PS Protection Lab
Palestine Technical University-Kadoorie
Faculty of Engineering and Technology | Electrical Engineering Department
Electrical Power Systems Protection Lab || Eng. TareQ FoQha
Experimental Procedures:
Part I: Configuration of SR16 as maximum current relay [50], [51], [50N] and [51N]
Protections [50N] and [51N] are fed by the amperometric transformer I4 (inside SIPROTEC
7SA610 device). The transformer reproduces the short-circuit current to the secondary in case
of a phase-ground fault. During normal operation, the currents vectorial sum in the three phases
is 0; the magnetic flux produced by the currents is consequently 0. During a ground fault, the
vectorial sum of the three phase currents is different from 0. This means that the resultant
magnetic flux concatenates with the secondary coil of the current transformer, resulting in a
non-zero current. The protection senses the generated homopolar current and intervenes.
1. Perform the electrical connections following the electrical diagram of figures 1 and 2.
Figure (1)
Figure (2)
2. Set the Parameters of the protection device SR16/EV and power system data using
DIGSI software as follows:
(A) Power System Data 1:
1. Rated primary voltage [No. 203] = 1 kV
2. Rated secondary voltage [No. 204] = 100 V
3. CT Rated primary current [No. 205] = 10 A
4. CT Rated secondary current [No. 206] = 1 A
2. Back-Up O/C
(a) O/C TRIP I>> [No. 07221] Led (4) : L (latched)
(b) O/C TRIP I> [No. 07222] Led (5) : L (latched)
Figure (3)
4. Insert the data obtained with the measurements in the following table:
L2 – L3 75
L3 – L1 50
L1 – L2 25
1. Connect the T.M.C.B. between the phase and ground, as shown in figure 4.
2. Turn ON the switch to perform a phase-ground fault, respectively at 25, 50, 75 and 100 km.
3. Measure the fault current with SIGRA program.
Figure (4)
4. Insert the data obtained with the measurements in the following table:
L1 – E 100
L2 – E 75
L3 – E 50
L1 – E 25
Part II: Configuration of SR16 as maximum ground directional current relay [67N]
This protection also has the I4 homopolar amperometric transformer (inside the SIPROTEC
7SA610 device). The protection [67N], besides measuring the homopolar residual current in a
ground fault, measures the homopolar voltage V0. That’s why we use three voltmetric
transformers (n=1000/100) without open Delta connection of the secondaries, because
calculation of the homopolar voltage V0 is internally calculated. During a normal operation the
vectorial sum of the three voltages over the secondaries of the VT is zero. In case of a phase-
ground fault, the sum of the three voltages is different from zero. Once the homopolar current
vector I0, the homopolar voltage vector V0 and their phase shift φ are measured, the protection
will be able to estimate the real power, that is equal to P0= V0*I0*cos φ.
The power sign (positive or negative) allows the relay [67N] to determine the fault current
direction, and then to establish if the fault is upstream or downstream.
Due to this property the protection [67N] is called ground directional relay. Since the
protections are selective, the directional relay [67N] controls the breaker opening only in case
of a downstream ground fault.
1. Perform the electrical connections following the electrical diagram of figures 1 and 5.
Figure (5)
2. Set the Parameters of the protection device SR16/EV and power system data using DIGSI
software as follows:
(A) Setting Group A – Earth Fault Overcurrent:
(a) General :
1. Earth Fault Overcurrent function [No. 3103] = ON
(b) 3I0>>>:
1. Operating mode [No. 3110] = Forward
2. Pick up current [No. 3111: 3I0>>> Pickup] = 0.07A
3. Time delay [No. 3112: T 3I0>>Time delay] = 0 Sec (Instantaneous Intervention).
(c) Direction:
1. Polarization [No. 2611]: With U0 +IY or U2
2. ALPHA, Lower angle for forward direction [No. 3612A]= 338o
3. BETA, Upper angle for forward direction [No. 3613A]= 122o
4. Min. zero seq. voltage 3U0 for polarizing [No. 3164]= 0.5 V
Figure (6)
8. Insert the data obtained with the measurements in the following table:
L2 – E 75
L3 – E 50
L1 – E 25
The distance relay Siemens 7SA610 mounted on panel mod. SR16/EV presents a polygonal
intervention characteristic. This characteristic is defined by a parallelogram that intersects the R
and X axes. There are 6 intervention zones in total (the sixth is not shown in the figure). For
each zone it is possible to set up the intervention direction (it depends on the network type that
is considered, unidirectional as in our case, where the power flow has only one sense).
Distributed “smart grids” where the power flow can be bidirectional, can be Forward, Reverse
or Non –Directional. Figure 7 shows for example an intervention zone Z1 of Forward type,
while zone 3 is of Reverse type, and zone 5 of Non – Directional type.
Figure (7)
1. Perform the electrical connections following the electrical diagram of figures 1 and 8.
2. Set the Parameters of the protection device SR16/EV and power system data using
DIGSI software as follows:
(A) Setting Group A – distance protection – General settings:
1. Distance protection [No. 1201] = ON
2. Phase current threshold for dist. Meas. [No. 1202]= 0.1 A
3. Angle of inclination, distance characteristic [No. 1211]= 52o
1. Connect a 20 Ω resistor in series to the T.M.C.B between two phases as shown in Figure. 8.
2. Turn ON the switch to perform a phase-phase fault, respectively at 25, 50, 75 and 100 km.
3. Measure the fault current with SIGRA program.
Figure (8)
4. Insert the data obtained with the measurements in the following table:
L2 – L3 75
L1 – L3 50
L1 – L2 25
1. Connect a 20 Ω resistor in series to the T.M.C.B between the phase and ground as shown
in Figure 9.
2. Turn ON the switch to perform a phase-phase fault, respectively at 25, 50, 75 and 100 km.
3. Measure the fault current with SIGRA program.
Figure (9)
4. Insert the data obtained with the measurements in the following table:
L2 – E 75
L3 – E 50
L1 – E 25
For example, the resistance and reactance values for a phase-ground fault at 50 km are:
RG50km = 18,09 Ω XG50km = 14,75 Ω
From which it is possible to calculate the fault impedance:
ZG50km = 18,09 Ω + j 14,75 Ω
In module and phase:
ZG50km =23.34 Ω <39,2°
we will verify that it is within the distance relay characteristic, as we wanted to demonstrate
(see figure 10)
Figure (10)
69 | Page Electrical PS Protection Lab
Palestine Technical University-Kadoorie
Faculty of Engineering and Technology | Electrical Engineering Department
Electrical Power Systems Protection Lab || Eng. TareQ FoQha
Chapter 5
Distribution Systems Protection
Contents
Checking the Operation of the Protection Devices with
Experiment (1) 71-80
Differential Current
Objectives:
1. Checking the operation of a differential switch with operating differential rated current
Idn = 30 mA - type A (Q11).
2. Checking the operation of a differential switch with operating differential rated current
Idn = 30 mA - type AC (Q12).
3. Checking the operation of a differential selective switch [S] with operating differential
rated current Idn = 0.3 A - type A (Q2).
4. Checking the operation of a delayed differential switch with adjustable operating
differential rated current Idn and time t, type A.
Necessary Material:
1. PDG-R/EV: Neutral Point Connection panel mod.
2. Multimeter for a.c. voltages.
3. Ammeter tongs for alternating currents.
Experimental Procedures:
Part I: Checking the operation of a differential switch with operating differential rated
current Idn = 30 mA - type A (Q11).
Figure (1)
Differential switch with operating differential rated current Idn = 30 mA - type A (Q11).
Combination of two faults
Current (mA) Comments
Fault (1) Left (Ω) Fault (2) Right (Ω)
50k 50k
15k 50k
15k 15k
5k 0
5k 5k
8. Then turn the selector EQUIPMENT to the position =, the earth fault current crossing
the power-absorbing equipment will be of unidirectional pulsating type.
9. Repeat the test changing the value of the earth fault and make sure that the differential
protection of class A is immediately enabled, like in the case of the sinusoidal fault
(EQUIPMENT in the position ∼), then tabulate your results in table (2).
Differential switch with operating differential rated current Idn = 30 mA - type A (Q11).
Combination of two faults
Current (mA) Comments
Fault (1) Left (Ω) Fault (2) Right (Ω)
50k 50k
15k 50k
15k 15k
5k 0
5k 5k
Part II: Checking the operation of a differential switch with operating differential rated
current Idn = 30 mA - type AC (Q12).
Figure (2)
7. Change the combination of the two earth faults as shown in table (3) and measure the
fault current with describing the operation of the differential switch Q12.
Differential switch with operating differential rated current Idn = 30 mA - type AC (Q12).
50k 50k
15k 50k
15k 15k
5k 0
5k 5k
Table (3)
8. Then turn the selector EQUIPMENT to the position =, the earth fault current crossing
the power-absorbing equipment will be of unidirectional pulsating type.
9. Repeat the test changing the value of the earth fault and check how a differential
protection of class AC behaves with a unidirectional fault. then tabulate your results in
table (4).
Differential switch with operating differential rated current Idn = 30 mA - type AC (Q12).
50k 50k
15k 50k
15k 15k
5k 0
5k 5k
Table (4)
Part III: Checking the operation of a differential selective switch [S] with operating
differential rated current Idn = 0.3 A - type A (Q2).
Figure (3)
7. Change the combination of the two earth faults as shown in table (5) and measure the
fault current with describing the operation of the differential selective switch Q2.
15k 15k
5k 5k
1.5k 1.5k
0.5k 0
0.5k 0.5k
Table (5)
8. Then turn the selector EQUIPMENT to the position =, the earth fault current crossing
the power-absorbing equipment will be of unidirectional pulsating type.
9. Repeat the test changing the value of the earth fault and check how the differential
protection behaves with a unidirectional fault, then tabulate your results in the following
table.
15k 15k
5k 5k
1.5k 1.5k
0.5k 0
0.5k 0.5k
Table (6)
Part IV: Checking the operation of a delayed differential switch with adjustable
operating differential rated current Idn and time t, type A (RCCB coupled with the
switch Q1 via the CRC coil).
Figure (4)
7. Use the “combination” of two earth faults to obtain various current values and to check
the operation of the differential protections.
8. Change the combination of the two earth faults as shown in table (7) and measure the
fault current with describing the operation of the differential switch Q12.
Differential switch with operating differential rated current Idn = 30 mA - type AC (Q12).
15k 15k
5k 5k
1.5k 1.5k
0.5k 0
0.5k 0.5k
Table (7)
9. Then turn the selector EQUIPMENT to the position =, the earth fault current crossing
the power-absorbing equipment will be of unidirectional pulsating type.
10. Repeat the test changing the value of the earth fault and check how the differential
protection behaves with a unidirectional fault, then tabulate your result in the following
table.
Differential switch with operating differential rated current Idn = 30 mA - type AC (Q12).
15k 15k
5k 5k
1.5k 1.5k
0.5k 0
0.5k 0.5k
Table (8)
Notes:
Remember that an (adjustable) delayed differential relay must always be coupled with a power
device such as a magnetothermal switch, to provoke the opening of the controlled circuit. This
device consists of a current transformer and of an electronic control circuit. The current
transformer with through hole will detect any “difference” of the current of all the live leads of
the electric system; the electronic control circuit compares the current detected by the
transformer to the selected threshold and it enables the output relay after a possible adjusted
delay time.
The output relay of the differential switch will be connected with an enabling/disabling device
of the power switch. As explained above, the current transformer of the differential relay
could be installed indifferently after or before the power switch. The only expedient concerns
the direction of the live leads running through it; all these must have the same direction.
Objectives:
1. Verification of selectivity among devices against overcurrents
2. Verification of selectivity between differential devices connected in parallel (horizontal
selectivity)
3. Verification of selectivity among differential devices connected in series (vertical,
amperometric and time selectivity)
Figure (1)
A magnetic release, suitable for the protection against short circuits, offers two options:
1) The short-circuit current has a value of intensity that exceeds the releasing threshold of B,
but not that of A;
2) The current pulse allowed by B has not shape nor quantity suitable to provoke the release
of A, for instance, when the downstream switch is much faster than that upstream.
The limiting power and operate times between the switches having to become selective, must
be compared to their respective curves I²t. As shown in the fig. 1, selectivity is enabled up to
the intersection point between the horizontal tangent to the minimum value concerning the
switch A and the curve of the upper limit of the switch B (value Is).
A distribution system very often includes various protection devices against overcurrents and
against indirect contacts: these are not always of the same type; automatic magnetothermal
switches and fuses can coexist.
The selectivity among various protections of a circuit is the property that enables the
protections to operate only in the section of circuit where this is necessary, avoiding to
disconnect the other parts not suffering any trouble.
The fig. 2 compares the curves of a fuse (upstream) and of a magnetothermal switch
(downstream). There is selectivity when the prearc value I²t of the fuse is higher than the total
value I²t of the automatic magnetothermal switch, or during the whole interval when the
two operating curves do not meet.
Figure (2)
Figure (3)
83 | Page Electrical PS Protection Lab
Palestine Technical University-Kadoorie
Faculty of Engineering and Technology | Electrical Engineering Department
Electrical Power Systems Protection Lab || Eng. TareQ FoQha
Figure (4)
A second example available in the fig. 5 shows a lay-out with three levels of selectivity:
besides the two types of differential devices shown in the fig. 4, also another type of switch,
delayed with definite time, are used; this device is not mentioned in the standards CEI EN
61008-1 and CEI EN 61009-1, but it complies with the prescriptions of the Annex B of the
Standard CEI EN 60947-2 and it can ensure an automatic protection against indirect contacts.
Figure (5)
84 | Page Electrical PS Protection Lab
Palestine Technical University-Kadoorie
Faculty of Engineering and Technology | Electrical Engineering Department
Electrical Power Systems Protection Lab || Eng. TareQ FoQha
The device installed downstream is a device of general type with differential rated current of
30 mA; the device available in intermediate position is of S type with differential rated current
of 100 mA, and the device installed downstream is of delayed type with definite time and
differential rated current of 300 mA.
The selectivity between two differential devices connected in series (one of S type and the
other of general type) is reached when the ratio between the respective differential rated
currents is at least equal to 3.A system without any differential device at its origin becomes
selective when all the starting circuits are protected by differential devices, separately or in
group. As soon as a fault occurs, only the differential switch protecting the relevant circuit is
enabled.
- Differential relay with separate toroidal transformer: differential rated current Idn
adjustable from = 0,03 A to 5 A by five steps, class A, operate time adjustable from 20
ms to 5 s by five steps. This differential relay has an output contact without potential
that changes its state in alarm conditions, and it can be used to control the release
coil of an automatic magnetothermal switch;
- Quadripolar automatic differential switch, with rated current In = 25 A; differential
rated current Idn = 0.3 A; class A (suitable for sinewave and unidirectional fault
currents with d.c. offsets), selective “S” operation;
- Fuse holder of three fuses with breakable neutral conductor and fuses type of 1 and
2 A;
- Two-pole automatic magnetothermal differential switch, with rated current In =1 A,
curve C, differential rated current Idn = 0.03 A, class AC (suitable for sine-wave fault
currents), type of general “G” operation;
- Two-pole automatic magnetothermal differential switch, with rated current In =1 A,
curve C, differential rated current Idn = 0.03 A, class A, type of general “G” operation.
Necessary Material:
1. PDG-R/EV: Neutral Point Connection panel mod.
2. Multimeter for a.c. voltages.
3. Ammeter tongs for alternating currents.
Experimental Procedures:
Part I: Verification of selectivity among devices against overcurrents
Figure (1)
86 | Page Electrical PS Protection Lab
Palestine Technical University-Kadoorie
Faculty of Engineering and Technology | Electrical Engineering Department
Electrical Power Systems Protection Lab || Eng. TareQ FoQha
Figure (2)
The two power-absorbing apparatuses available on the right and on the left of the panel, are
protected separately by the two automatic magnetothermal switches Q11 and Q12 and they are
powered, downstream, by the automatic magnetothermal switch Q1. These circuits are selective
in horizontal way (Q11 with respect to Q12) and in vertical way (Q1 with respect to Q11 and
Q12).
Selectivity is the characteristic shown by an electric system (conduits and protection devices)
where a fault provokes the disconnection only of that part of circuit affected by the fault. This
fault could be an overcurrent (overload or short circuit) or an earth fault.
7. Simulate a short circuit across the output terminals of Q11 and Q12, on the panel, to
obtain an overcurrent and to study its effects on the protection devices.
8. Measure the short-circuit current with the ammeter tongs and tabulate your results in the
following table.
Short circuit
Figure (3)
Suppose that both the power-absorbing apparatuses available on the right and on the left of the
panel, are powered by the same circuit (for instance, by the distribution board of the floor), but
they are protected separately. These circuits are selective in horizontal way between each
other. Obvious “logistical” reasons require that the two terminal circuits protected by the two
automatic differential magnetothermal switches Q11 and Q12 are separate from each other in
case of fault.
Figure (4)
7. Simulate earth faults on the panel to obtain a current equal to or higher than the Idn of
the differential switch under examination.
8. Measure the fault current with the ammeter tongs then tabulate your results in the
following table:
Earth fault
Figure (5)
Suppose that the power-absorbing equipment available at the left of the panel is powered by a
line shunted by a zone distribution board; in its turn, this board is shunted by a main control
board which is powered by the substation switchboard. This sequence of protection devices
must be coordinated to ensure selectivity. This concept of selectivity is called vertical
selectivity. The fault of the terminal circuit is “seen”, for obvious “logistical” reasons, not only
by the downstream protection Q12, but also by the upstream protection device Q2 and by the
unit Q1-RCCB.
Figure (6)
7. Simulate earth faults on the panel to obtain a current equal to or higher than the Idn of
the differential switch under examination.
8. Measure the fault current with the ammeter tongs then tabulate your results in the
following table:
Earth fault
9. If the optimum coordination can be reached if an Idn of 1A and a time of 1-sec are set
in the differential RCCB, After checking that the system described is selective and
coordinated, try to change only the time from 1-sec to fast in the differential RCCB,
What happens if the clear earth fault is simulated in Q12 output?
Chapter 6
Appendices
Electrical Diagram
Electrical Diagram
Electrical Diagram