Austroads Guide Bridge Technology Part5 AGBT05 09
Austroads Guide Bridge Technology Part5 AGBT05 09
Austroads Guide Bridge Technology Part5 AGBT05 09
http://www.onlinepublications.austroads.com.au/
Austroads
GUIDE TO BRIDGE TECHNOLOGY
Summary
Part 5 of the Guide to Bridge Technology – Structural Drafting sets out the principles involved in
the presentation of bridge structural drawings and is intended to give engineers and draft persons
at all levels a sound guide in drafting presentation and information.
The Guide covers a variety of principles used within bridge structural drafting practice including line
work, text and dimensions, scales, definitions, drawing order and numbering, use of abbreviations
and symbols, and concrete and reinforcement detailing.
Keywords
Sketches, detailed design drawings, fabrication drawings, dimensions, symbols, patterns, setting
out, cover sheet, general arrangement, footings, piles, concrete detailing, reinforcement detailing,
structural steel detailing, vertical alignment, horizontal alignment.
This work is copyright. Apart from any use as permitted under the Copyright Act 1968, no part may
be reproduced by any process without the prior written permission of Austroads.
ISBN 978-1-921551-39-0
Project Manager
Mark Bennett, RTA NSW
Prepared by
Matthew Thompson
This Guide is produced by Austroads as a general guide. Its application is discretionary. Road
authorities may vary their practice according to local circumstances and policies.
Austroads believes this publication to be correct at the time of printing and does not accept
responsibility for any consequences arising from the use of information herein. Readers should
rely on their own skill and judgement to apply information to particular issues.
Guide to Bridge Technology
Part 5: Structural Drafting
Sydney 2009
Austroads profile
Austroads’ purpose is to contribute to improved Australian and New Zealand transport outcomes
by:
providing expert advice to SCOT and ATC on road and road transport issues
facilitating collaboration between road agencies
promoting harmonisation, consistency and uniformity in road and related operations
undertaking strategic research on behalf of road agencies and communicating outcomes
promoting improved and consistent practice by road agencies.
Austroads membership
Austroads membership comprises the six state and two territory road transport and traffic
authorities, the Commonwealth Department of Infrastructure, Transport, Regional Development
and Local Government in Australia, the Australian Local Government Association, and NZ
Transport Agency. Austroads is governed by a council consisting of the chief executive officer (or
an alternative senior executive officer) of each of its eleven member organisations:
Roads and Traffic Authority New South Wales
Roads Corporation Victoria
Department of Transport and Main Roads Queensland
Main Roads Western Australia
Department for Transport, Energy and Infrastructure South Australia
Department of Infrastructure, Energy and Resources Tasmania
Department of Planning and Infrastructure Northern Territory
Department of Territory and Municipal Services Australian Capital Territory
Department of Infrastructure, Transport, Regional Development and Local Government
Australian Local Government Association
New Zealand Transport Agency.
The success of Austroads is derived from the collaboration of member organisations and others in
the road industry. It aims to be the Australasian leader in providing high quality information, advice
and fostering research in the road sector.
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
CONTENTS
1 SCOPE AND GENERAL................................................................................................ 1
1.1 Scope.............................................................................................................................. 1
1.2 Application ...................................................................................................................... 1
1.3 Guide Structure............................................................................................................... 1
1.4 Definitions ....................................................................................................................... 2
1.5 Types of Drawings ........................................................................................................ 10
1.5.1 Sketches ......................................................................................................... 10
1.5.2 Detailed Design Drawings .............................................................................. 10
1.5.3 Fabrication Drawings (Shop Drawing) ............................................................ 10
1.5.4 Works-as-Executed Drawings (As-Built Drawings or As-Constructed)........... 11
2 GENERAL APPLICATIONS ........................................................................................ 19
2.1 Line Work...................................................................................................................... 19
2.2 Text............................................................................................................................... 19
2.3 Dimensions ................................................................................................................... 19
2.3.1 Dimension Lines, Projection Lines and Leader Lines ..................................... 19
2.4 Order of Dimensioning.................................................................................................. 20
2.5 Scales ........................................................................................................................... 20
2.6 Drawing Order .............................................................................................................. 20
2.6.1 General ........................................................................................................... 20
2.6.2 Drawing Numbering ........................................................................................ 21
2.6.3 Title Blocks ..................................................................................................... 22
2.6.4 Titles and Sub-titles ........................................................................................ 22
2.7 Abbreviations ................................................................................................................ 23
2.7.1 Standard Abbreviations .................................................................................. 23
2.7.2 Acceptable Abbreviations ............................................................................... 23
2.7.3 Other Abbreviations ........................................................................................ 26
2.8 Symbols and Patterns................................................................................................... 26
2.8.1 Patterns .......................................................................................................... 26
2.8.2 Use of Symbols............................................................................................... 30
2.8.3 Welding........................................................................................................... 30
2.9 Notes and References .................................................................................................. 30
2.9.1 General Notes or Drawing Specific Notes ...................................................... 30
2.9.2 Particular Notes .............................................................................................. 31
2.10 Conventions.................................................................................................................. 31
2.10.1 Cross-referencing ........................................................................................... 31
2.10.2 Orientation of Views and Sections.................................................................. 32
2.11 Setting Out.................................................................................................................... 33
2.11.1 Chainage, Compass Bearing, Coordinates .................................................... 33
2.11.2 Survey Marks.................................................................................................. 34
2.11.3 Reduced Levels (Heights) .............................................................................. 34
3 PARTICULAR APPLICATIONS................................................................................... 35
3.1 Cover Sheet.................................................................................................................. 35
3.1.1 Information Shown.......................................................................................... 35
3.2 General Arrangement ................................................................................................... 40
3.2.1 General ........................................................................................................... 40
3.2.2 Plan View........................................................................................................ 40
3.2.3 Elevation ......................................................................................................... 41
Austroads 2009
— i—
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— ii —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
TABLES
Table 1.1: Definitions provided for guidance ..................................................................... 3
Table 2.1: Order of drawings ........................................................................................... 21
Table 2.2: Metric abbreviations........................................................................................ 23
Table 2.3: Acceptable abbreviations................................................................................ 24
Table 2.4: Coordinates .................................................................................................... 34
FIGURES
Figure 1.1: Bridge components........................................................................................... 9
Figure 1.2: RTA – Concept sketch.................................................................................... 12
Figure 1.3: DTEI – Concept design – general arrangement ............................................. 13
Figure 1.4: DTEI – Concept design – details .................................................................... 14
Figure 1.5: QDMR – Preliminary general arrangement .................................................... 15
Figure 1.6: RTA – Proposal sketch ................................................................................... 16
Figure 1.7: VicRoads – Concept general arrangement – Part 1 ....................................... 17
Figure 1.8: VicRoads – Concept general arrangement – Part 2 ....................................... 18
Figure 2.1: Scale bars....................................................................................................... 20
Figure 2.2: Sub-titles......................................................................................................... 23
Figure 2.3: Hatching and patterns – 1............................................................................... 27
Figure 2.4: Hatching and patterns – 2............................................................................... 28
Figure 2.5: Hatching and patterns – 3............................................................................... 29
Figure 2.6: Note leader convention................................................................................... 31
Figure 2.7: Cross-referencing ........................................................................................... 31
Figure 2.8: Compass bearing............................................................................................ 33
Figure 3.1: DTEI – Cover sheet ........................................................................................ 36
Figure 3.2: QDMR – Cover sheet ..................................................................................... 37
Figure 3.3: RTA – Cover sheet ......................................................................................... 38
Figure 3.4: VicRoads – Cover sheet ................................................................................. 39
Figure 3.5: Vertical alignment diagram ............................................................................. 43
Figure 3.6: Horizontal alignment diagram ......................................................................... 43
Figure 3.7: Skew diagrams ............................................................................................... 44
Figure 3.8: DTEI – General arrangement ......................................................................... 45
Figure 3.9: RTA – General arrangement .......................................................................... 46
Figure 3.10: VicRoads – General arrangement .................................................................. 47
Figure 3.11: QDMR – General arrangement – Sheet 1 ...................................................... 48
Figure 3.12: QDMR – General arrangement – Sheet 2 ...................................................... 49
Figure 3.13: Pile layout – bearing and offsets..................................................................... 51
Figure 3.14: Pile layout – pile coordinates .......................................................................... 52
Figure 3.15: Piles in a group ............................................................................................... 52
Austroads 2009
— iii —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— iv —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
The Guide is intended to cover the most common bridge information used, giving engineers and
drafting persons at all levels of experience, a sound guide in drafting presentation and information.
For more detailed information, the relevant state road authority should be contacted to ascertain
their requirements in the production of bridge structural drawings.
The Guide will cover a variety of areas within bridge structural drafting based on drafting principles
such as the following:
line work, text and dimensions
scales
definitions
drawing order and numbering
use of abbreviations and symbols
concrete and reinforcement detailing.
1.2 Application
The information contained in this Guide is intended for adoption by engineers and drafting persons
throughout the industry. The Guide is intended for a common practice basis and to promote a
consistency in application throughout the industry.
Part 2: Materials
The full range of bridge building materials is discussed in Part 2 including concrete, steel,
timber and non-metallic components. It also discusses the material characteristics including
the individual stress mechanisms.
Austroads 2009
— 1—
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
1.4 Definitions
Table 1.1 lists a number of definitions provided for guidance and shall be used in preference to
other terms. See Figure 1.1 for a diagrammatic view of a bridge structure showing bridge
components and definitions.
Austroads 2009
— 2—
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Term Definition
abutment An end support of a bridge or similar structure
alignment The geometric form of the centreline (or other reference line) of a carriageway in both the horizontal and
vertical directions
Horizontal – plan geometry of road/design
Vertical – elevation geometry of road/design
approaches A relatively short length of carriageway leading up to a bridge, including embankment, pavement and
safety barriers
approach slab A reinforced concrete slab supported on the abutment or deck and the approach fill
asphalt A mixture of bituminous binder and aggregate with or without a mineral filler, produced hot in a mixing
plant, which is delivered, spread and compacted while hot. (Used as a road surface)
Australian height datum A level datum, uniform throughout Australia, based on an origin determined from observations of mean
sea level at tide gauge stations, located at more than 30 points along the Australian coastline
back fill Fill placed in an excavation
back wall A narrow reinforced concrete wall, forming part of the abutment to prevent the earth fill reaching the
abutment sill and bearings (See curtain wall, fender wall, ballast wall)
ballast wall A narrow reinforced concrete wall, forming part of the abutment to prevent the earth fill reaching the
abutment sill and bearings (See curtain wall, fender wall, back wall)
bar mark A label given to a reinforcement bar for the purposes of identification
barrier An obstruction placed to prevent vehicle access to a particular area
base centreline The pegged centreline of the road alignment
batter 1. The uniform side slope of walls, banks, cuttings, etc. Usually expressed as a ratio of horizontal to
vertical e.g. 2 to 1, 1.5 to 1
2. The amount of such slope or rake, usually expressed as a ratio of horizontal to vertical, distinct from
grade
3. To form a uniform side slope to a wall, bank, or cutting
beam A load bearing member which supports the deck of a bridge (See girder)
bearing (structural) A device for transmitting horizontal and vertical forces of a bridge superstructure to the supporting
structure
bearing (surveying) The bearing of a straight line is the angle measured clockwise from grid north to the subject line and is
given in degrees, minutes and seconds.
The bearing of the Control Line shall always be given in the direction of increasing chainage along the
line
bench mark A defined mark of a permanent nature, the level of which, relative to some datum, has been determined
or assumed and to which the level of other points may be related
blinding (preliminary A layer of lean mass concrete placed on soil to provide a clean bed for reinforced concrete work
concrete)
bore (bore hole, drill hole) A hole produced in the ground by drilling or driving for geotechnical investigation
Austroads 2009
— 3—
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Term Definition
chainage The distance of a point along a control line, measured horizontally from a datum point
concrete A mixture of fine and coarse aggregate, water, cement and admixtures
construction joint A joint made during the placement of concrete or pavement base material to divide the work into parts
for convenience during construction or to provide for unavoidable interruption to placing
contours Lines on a map or plan joining all points of the same level
contraction joint A provision made in a structure or pavement to allow contraction of components, induced by
temperature change or other causes, to occur in a controlled manner (e.g. a groove in concrete)
contract level The level shown on the drawings representing the extent of the work in the piles and footings (e.g. toe of
a pile)
control line A line, generally at or near the centre line of a road, on which design is based and from which
measurements for setting out construction may be conveniently made
coordinates Distances measured in a certain way from fixed straight lines which intersect at the origin – used to
locate points. Systems include MGA and ISG (Section 2.7)
cover 1. The depth of material between the surface of the ground or pavement and the top of a culvert or pipe
2. The thickness of concrete between a reinforcing bar, tendon or duct, and the nearest surface of a
concrete member
3. The depth of material over the subgrade or any layer in the pavement structure
crossfall The slope, measured at right angles to the alignment, of the surface of any part of a carriageway (shown
as a percentage e.g. 3.0%)
cross beam Transverse beam, used to support longitudinal members, such as girders, planks, stringers, etc.
cross girder
cross head Part of a pier or abutment that supports the superstructure (See sill beam, headstock)
culvert One or more adjacent pipes or enclosed channels for conveying surface water or a stream below
formation level
curtain wall A narrow reinforced concrete wall, forming part of the abutment to prevent the earth fill reaching the
abutment sill and bearings (See back wall, ballast wall, fender wall)
cut The depth from the natural surface of the ground to the subgrade level
datum A defined horizontal or level plane to which the relative elevations of other points may be referred
deck The bridge floor directly carrying traffic loads
deck units Load bearing deck members which comprise the bridge deck
designed surface level A required level of the road as a basis for construction which is generally located on a control line, such
as a base centreline, a true centreline or other nominated line
design load The load distribution, or combination of loads, for which a structure is designed
design standard Identifies particular standards used in the design
diaphragm A transverse stiffening member between girder webs or inside a hollow pier (See end beam)
discharge The volumetric rate of waterflow
earthworks 1. All operations involved in loosening, removing, depositing, shaping and compacting soil or rock
2. The structure resulting from this operation
elevation A view through a vertical plan, viewed at a right angle to the object
end beam A transverse stiffening member between girder webs or inside a hollow pier (See definition of
diaphragm)
Austroads 2009
— 4—
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Term Definition
end of deck The back face of the curtain wall or back wall (if wall extends to the design surface level) or the end
of superstructure when the approach slab sits above the curtain. As shown below.
existing surface level The surface of the earth formation existing at the bridge site prior to construction
fender wall A narrow reinforced concrete wall, forming part of the abutment to prevent the earth fill reaching the
abutment sill and bearings (See back wall, ballast wall, curtain wall)
fill 1. The depth from the subgrade level to the natural surface
2. That portion of road where the formation is above the natural surface
3. The material placed in an embankment
footing The widening at the base of a structure (pier, abutment, etc.) to spread the load above to the
foundation material
formwork Temporary structure of timber, metal or other material comprising the moulds in which concrete is
formed to the desired shape
foundations The soil or rock upon which a structure rests
gabion A wire basket filled with stones used to retain earth or to control scour
girder A load bearing member which supports the deck of a bridge
Austroads 2009
— 5—
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Term Definition
gradient The longitudinal slope of a road or path, usually represented as the ratio of a one metre rise to the
horizontal distance (e.g. 1 : 50), or expressed as a percentage (e.g. 2%)
median A strip of road, not normally intended for use by traffic, which separates carriageways for traffic in
opposite directions. Usually formed by painted lines, kerbed and paved areas, grassed areas, etc.
mortar 1. A mixture of cement and/or lime and sand with water
2. A mixture of fine aggregate with an epoxy compound or other binder
obvert The highest portion of the internal surface of a drain or culvert
overlay The addition of pavement material to a bridge deck to provide a wearing surface
overpass A grade separation where the subject carriageway passes over an intersecting carriageway or railway
parapet A raised kerb with a profile and height sufficient to prevent vehicles leaving the carriageway, formed at
the edge of a carriageway, usually on a bridge or similar structure
pier 1. An intermediate support in a bridge having more than one span
2. Part of the substructure supporting the superstructure and transferring the loads to the foundations
pile A slender member driven, jetted, screwed, or formed in the ground to resist loads
pile cap A structural member designed to connect and distribute loads from the above structure to a group of
piles
plank A load bearing member which supports or forms part of the deck of a bridge
plinth 1. A low level barrier subjected to repeated flooding (also known as a castellated kerb)
2. A concrete member raised above the surrounding concrete
post-tensioning A method of prestressing in which tendons are tensioned after the concrete has hardened
prestressed concrete (PSC) Concrete in which effective internal stresses are introduced, usually by means of steel tendons
pretensioning A method of prestressing in which tendons are tensioned before the concrete is placed (e.g. Super T
Girders, Deck Units)
reduced level A level relative to an agreed datum (See height)
reinforced concrete Concrete strengthened within its mass by steel bars, or mesh
reinforcement Bars, or mesh, usually steel, embedded in concrete, masonry, or brickwork, for the purpose of resisting
particular stresses (e.g. tensile, temperature related, etc.)
reinforced soil wall (RSW) A method of constructing retaining walls in which fill is retained by vertical steel or concrete units
anchored by friction into the fill by means of galvanised steel strips
Austroads 2009
— 6—
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Term Definition
running surface That part of the pavement specifically designed to resist abrasion from traffic and to minimise the entry
of water (See wearing surface)
safety barrier A physical barrier separating roadside hazards or opposing traffic and the travelled way, designed to
resist penetration by an out-of-control vehicle and as far as practicable, to stop or redirect colliding
vehicles
safety screen A screen barrier usually placed behind a bridge safety barrier, designed to prevent objects being thrown
to the carriageway which is being spanned
screed The operation of forming a surface by use of screeds to impart a grade for directing waterflow in small
areas (e.g. landings)
setting out line A straight reference line between known fixed points from which a bridge/structure can be set out
sill beam Part of a pier or abutment that supports the superstructure (See headstock, cross head)
skew angle The angle between a line at right angles to the control line/setting out line and the pier or abutment
slope The inclination of a surface with respect to the horizontal and can be expressed as a ratio (e.g. 1:50), or
expressed as a percentage (e.g. 2%)
span length 1. End spans – the distance between the end of the superstructure and the centre of the nearest pier
2. Intermediate spans – the distance between the centres of piers
Note: for design purposes the span length is the length between centres of supports
strand A product consisting of two or more wires spun together in a helical form. Usually bundled together to
form a tendon
subgrade The trimmed or prepared portion of the formation on which the pavement is constructed. Generally
taken to relate to the upper line of the formation
substructure In a bridge, the piers and abutments (including wing walls) which support the superstructure
superelevation A slope on a curved pavement selected so as to enhance forces assisting a vehicle to maintain a
circular path
superstructure That part of a bridge which is supported by the piers and abutments
survey Work performed to record features which are described and presented on a plan
tangent point The point on a centreline where straight and curve meet tangentially
tendon A tension element usually made up of a number of steel strands or wires, used in concrete members, to
impart prestress
traffic barrier railing A railing usually fabricated from steel, consisting of one or more rails, with posts, positioned on a
reinforced concrete barrier/plinth designed to restrict the lateral movement of vehicles
truss A framed structure comprised of steel or timber which acts as a beam
underpass A grade separation where the subject carriageway passes under an intersecting carriageway or railway
waterway area The area of the cross-section of the stream at right angles to the direction of the flow, up to the assumed
flood level
wearing surface That part of the pavement specifically designed to resist abrasion from traffic and to minimise the entry
of water (see running surface)
widening The widening of an existing pavement or carriageway generally without alteration of level
width of carriageway The clear width, measured at right angles to the longitudinal centreline of the bridge or carriageway,
between the inner faces of the traffic barrier or kerb
Austroads 2009
— 7—
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Term Definition
wing wall The extension of an abutment wall as in a bridge, or of an end wall in a culvert, used for retaining the
side slopes of earth filling
works-as-executed plans A set of plans on which all variation to the original design, made during construction, are recorded for
(WAE) record purposes. Also referred to as ‘As built’ or ‘As constructed’ drawings
A comprehensive list of definitions can be found in: AS 1348 – Roads and Traffic Engineering –
Glossary of Terms (2002) or Austroads – Glossary of Austroads Terms (2008).
Austroads 2009
— 8—
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 9—
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
1.5.1 Sketches
Sketches come in a number of forms depending on their intended use and requirements.
Proposal sketch – This is a plan or set of plans produced to depict what is considered to be the
most appropriate design solution for the planned site. In some cases it may be deemed necessary
to produce a number of alternative design options in order to help the designer receive client
feedback prior to detailed design commencing. A proposal sketch shall contain the following
information:
plan view
elevation
typical cross-section
locality plan (if applicable)
site plan (if applicable)
horizontal alignment diagram (if applicable)
vertical alignment diagram (if applicable)
general notes (if applicable).
A proposal sketch should show all necessary dimensions, notes and components, particular to the
structure.
The Roads and Traffic Authority, New South Wales (RTA) classifies their proposal sketches into
two types:
Concept sketch (concept drawing) – a development sketch used to help the designer and
client choose the most appropriate structure type for the planned site. An example of a
concept sketch is shown in Figure 1.2.
Proposal sketch (preliminary general arrangement) – is a sketch of what is considered the
most appropriate design and structure type for the planned site. Examples of proposal
sketches are shown in Figure 1.3 to 1.8 inclusive.
A detail sketch can be a sketch or a set of sketches providing details for temporary works to be
carried out on a structure.
Austroads 2009
— 10 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 11 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 12 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 13 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 14 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 15 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 16 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 17 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 18 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
2 GENERAL APPLICATIONS
2.1 Line Work
Line work on drawings should generally be in accordance with Table 3.1 in AS 1100 Part 101.
Variations on the theme may be allowed according to the application.
2.2 Text
Though full size drawings are produced for the final design, the minimum text size used should
clearly be read on an A3 size set of plans, however font styles may vary and some examples of
font styles used are listed below:
Department for Transport, Energy and Infrastructure, South Australia (DTEI) use the
following text font:
— ISOCP (AutoCAD font) font style for all text
Department of Main Roads, Queensland (QDMR) uses the following text font:
— mr_romans (AutoCAD font) font style with a width factor of 0.8 for all text
The Roads and Traffic Authority, New South Wales (RTA) uses the following text fonts:
— International ISO (Microstation font) font style for general use and dimensions
— Arial font style for text in the title blocks
Roads Corporation, Victoria (VicRoads) use the following text font:
— StenceQ font from a Microstation resource file
Main Roads Western Australia (MRWA) use the following text font:
— ISOCP2 (Autocad font) front style with a width factor of 1.0 for all text.
2.3 Dimensions
Each dimension necessary for the complete definition of a particular element shall be clearly
shown on the drawing and shall be shown only once. The dimensioning of any element shall not
be such, that a dimension relating to that element shall need to be deduced from other dimensions,
nor, that the drawing must be scaled to determine a dimension.
In all cases, dimensions shown on drawings shall be in millimetres and they shall be shown in
accordance with AS 1100 Part 101.
Where practical, dimensions shall be placed using the aligned method with each dimension placed
parallel to its dimension line in order to be read from either the bottom or the right hand side of the
drawing.
Austroads 2009
— 19 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Projection lines for dimensions shall extend from a point no less than 2 mm (A1 drawing) from the
surface of the object to a point not less than 2 mm beyond the dimension line. Projection lines
shall, in the majority of cases, be unbroken.
Leader lines for notes shall commence from either the beginning or the end of a note with a short
(minimum length 3 mm) horizontal line before being angled to the point of reference. The
termination of the leader line shall be with an arrow to the outline of the element or a small fully
shaded circle (nominal 3.5 mm diameter – A1 drawing) within the area being noted.
2.5 Scales
Scale used on drawings will vary in accordance with the size and character of the feature being
detailed or the degree of detailing required.
The scales on all drawings should be drawn to a defined natural scale (A1 drawing) with the scale
to be such, as to be easily read on an A3 size drawing.
Distorted scales should only be used under special circumstances where clarity is the most
important feature.
Quoting a scale as a ratio e.g. 1:100, should not be used. Scales should be displayed as a scale
bar, either below the detail, in the general notes, or in the drawing title block.
Drawings shall not contain two scales which are similar, e.g. 1:20 shall not be used on the same
drawing as 1:25.
Austroads 2009
— 20 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
The above is only a representative list of drawings showing a generic order of drawings for a
simple bridge structure, this may vary according to the type of structure or the road authority’s
requirements.
This drawing numbering should be followed as a general rule; however numbering may vary
depending on which state the plans are prepared in, such as the following:
QDMR obtains drawing numbers in a block set aside for the particular project.
The RTA requires a numerical sequence starting with the Cover Sheet as number 1
(Section 3.1). Blocks of numbers and company reference numbers shall not be used in
identifying drawing numbers.
DPI Northern Territory obtain drawing numbers from their Plan Room.
DTEI SA require a numerical sequence starting with the Cover Sheet as number 1
(Section 3.1).
VicRoads require a numerical sequence starting with the Cover Sheet as number 1
(Section 3.1).
When producing a numbering system for a set of bridge construction plans, the relevant state
authority’s numbering system shall be used.
Austroads 2009
— 21 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Cover Sheets may or may not require title blocks. This will depend on the road authority.
The Roads and Traffic Authority also requires the road number and the Local Government Area
name.
The title block of each sheet shall also include a description of the details shown on that sheet, e.g.
piers concrete, piers reinforcement, piers profile.
Where more than one sheet is required to detail a part of a structure, it shall be considered to be a
sheet series and the sheet titles shall reflect the particular situation. Examples of sheet series titles
are:
DTEI SA uses the following labelling system:
— DECK 1
— DECK 2
— DECK 3
The RTA uses the following labelling system:
— DECK CONCRETE – SHEET A
— DECK CONCRETE – SHEET B
— DECK CONCRETE – SHEET C
QDMR uses the following labelling system:
— DECK – SHEET 1
— DECK – SHEET 2
— DECK – SHEET 3
VicRoads uses the following labelling system:
— OVERLAY – PART 1
— OVERLAY – PART 2
— OVERLAY – PART 3.
Sub-titles
A sheet generally comprises several views, sections, details, tables, etc., and each shall be given
an appropriate sub-title, e.g. plan, elevation. (Figure 2.2)
Austroads 2009
— 22 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Elevations, Section, Views and Details shall be identified and cross referenced in accordance with
AS/NZS 1100 Part 501 (2002). For the convention of cross-referencing refer to Section 2.10.1.
2.7 Abbreviations
2.7.1 Standard Abbreviations
A list of standard abbreviations for metric units is shown in Table 2.2. The arrangement of upper
and lower case letters for each abbreviation shall be strictly adhered to.
Austroads 2009
— 23 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 24 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 25 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Common hatching used in bridge and related structures should be related back to the relative road
authority.
Material representation
Material representation can be a useful tool when showing the differences between a number of
materials, e.g. mass concrete and reinforced concrete. Material representation can be displayed
by showing a material specific pattern over an area. When using patterns, consideration about
scale, congestion and possible confusion should be taken when drawings are read at an A3 size.
Common material specific patterns used in bridge and related structures should be related back to
the relevant road authority. (Figure 2.3 and Figure 2.5)
Austroads 2009
— 26 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 27 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 28 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 29 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
2.8.3 Welding
The necessary information concerning the location, type, size and length of welds in welded joints
and whether the welds are made in the shop or on site shall be given on the drawings with the use
of standard welding symbols.
All lettering shall be in upper case except where standard metric abbreviations dictate otherwise.
General Notes or Drawing Specific Notes shall be shown on either the structure component
drawing or on a designated notes sheet.
The practice of locating General Notes or Drawing Specific Notes will vary depending on the State
Authority.
The Roads and Traffic Authority, New South Wales (RTA) has the following requirements:
Each bridge/structure component drawing, or drawing set, shall contain clear and concise
general notes relating the required information needed to construct the component being
detailed in its entirety. At no such time should a designated notes sheet be created to
contain all notes for a complete set of bridge/structure plans.
Austroads 2009
— 30 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
For a component where more than one sheet is required to show adequate details for
construction, the general notes are not required to be produced on each subsequent sheet, a
note referring to the sheet containing these notes is adequate. e.g. ‘For other General Notes
relating to this sheet, see sheet No. X or sheet No. Y’.
2.10 Conventions
2.10.1 Cross-referencing
Where elevations, section, views and details are shown on a different sheet, cross-referencing
shall be carried out in accordance with AS/NZS 1100 Part 501. Where a series of sheets is
necessary to adequately detail an element, e.g. Abutments Concrete – Sheet A, Abutments
Concrete – Sheet B, etc., the same section number or detail letter shall not be used more than
once in the sheet series. Typical examples Figure 2.7.
Austroads 2009
— 31 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Sections
Sections shall be drawn as a view from a cutting plane located through an element previously
drawn as an elevation, plan, section or view.
Generally, only the details at the cutting plane of the section should be shown, however, details
beyond the cutting plane may be included (represented by dotted lines) provided that the included
details are not confusing to the main details being shown.
Sections, where possible, shall be drawn adjacent to the plan or elevation to which they relate.
Sections should be taken looking from the bottom of the drawing to the top.
Sections whether taken looking from right to left or left to right should be consistent in their
direction, sections taken looking in both directions on a drawing should be minimised.
If a series of cutting planes are used to define section details, any change in direction of the cutting
plane shall be shown by thick lines.
Views
Views shall be drawn representing what is seen from outside an element previously drawn as an
elevation, plan or section.
The designation of views shall be numerical with view numbers not replicating any section number
already used.
Details
Where the scale used to draw elements on drawings is too small to adequately show minute
details, the item requiring enlargement shall be enclosed in a circle, or other suitable shape and a
detail mark shall be placed in a convenient location.
Alternatively, a north point arrow can be shown to indicate the abutment direction in relation to the
bridge structure.
Austroads 2009
— 32 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
For structures which have a straight alignment, the setting out should be carried out using the
control line.
Chainages and offsets or, alternatively, coordinates may be used to locate the centre of elements
e.g. spread footings, piles; pier headstocks etc. Dimensions for each element shall be related to
the defined location and shall be normal to the element centreline.
Chainage
Chainages, given along the control line, shall be adopted from the road design and/or site survey
information provided.
Where possible and practical, chainages for the centrelines of piers, bearings etc., shall be given in
metres to the nearest 0.005 metre.
Compass bearing
The bearing of a line is the angle measured clockwise from grid north to the subject line and is
given in degrees, minutes and seconds.
The bearing of the control line shall always be given in the direction of increasing chainage along
the line. The bearing of a line is relative to the station from where it is taken. (Figure 2.8)
Austroads 2009
— 33 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Coordinates
The coordinate system adopted for a project may be an arbitrary local one, ISG (Integrated Survey
Grid), GDA (Geocentric Datum of Australia) or MGA (Map Grid of Australia).
The coordinates are normally quoted in metres to the nearest 0.001 metre. In recording GDA, ISG
and MGA coordinates, the Easting value is always placed before the Northing value.
A gap shall be placed between the third and fourth figures, and also between the sixth and seventh
figures from the decimal point to assist in the alignment of figures. (Figure 2.4)
The coordinates shall be obtained from a road design and/or from site survey information.
Places, such as the Department of Planning and Infrastructure, Northern Territory (DPI), may also
have datum conversions and corrections which must be applied to give correct datum for an area
of interest.
Each state should be consulted for their datum conversions and corrections.
Reduced levels shall be shown in metres on all drawings with the following order of accuracy being
used:
Design surface levels 0.001 metres
Contract levels (toe of piles) 0.1 metres
Existing surface levels 0.1 metres
Contours 1.0 or 0.5 metres (dependent upon slope of existing
surface)
Flood and water levels 0.1 metres
Austroads 2009
— 34 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
3 PARTICULAR APPLICATIONS
3.1 Cover Sheet
3.1.1 Information Shown
The first sheet of any set of bridge construction plans shall be the ‘Cover Sheet’. The cover sheet
shall be numbered ‘1’ in any set of bridge construction plans.
Note: Where bridge construction plans are an integral component of a set of road construction
plans the bridge construction plans do not require their own cover sheet.
Some examples of cover sheets are shown in Figure 3.1 to Figure 3.4 inclusive.
Austroads 2009
— 35 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 36 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 37 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 38 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 39 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
The General Arrangement gives the reader an overall view of what the bridge/structure will appear
like once construction has been completed and shall not contain any construction requirement
information or construction sequences. (Figure 3.12)
Depending on the complexity of the bridge/structure and the detail required, multiple sheets may
be used and titled in accordance with Section 2.6.3 Titles and Sub-titles.
Austroads 2009
— 40 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Contours
A contour is a line derived from the joining of points at the same height above a datum on an
existing surface.
Contours shall be drawn as uniform lines, except under a bridge/structure where the line shall then
be shown as dashed lines. The line thickness shall be shown so as not to distract from the
bridge/structure elements.
The level annotation of each contour shall be shown, at a minimum, once at the end of the contour;
however more level annotations may be shown on the same contour line for easier reading if
deemed necessary due to the complexity of the contour.
The contour intervals should be determined to suit the slope of the existing surface, however for
very steep grades the intervals shall not exceed 1.0 metre and for very flat grades the intervals
shall be no more than 0.25 metres.
3.2.3 Elevation
Elevations are important in showing the reader the location in height of the bridge/structure and the
level of the surrounding site, the locations of roads, waterways and other points of interest and
therefore should show adequate details. The elevation should be placed as a projection above or
below the plan, depending on the road authority method of projection.
Austroads 2009
— 41 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
the longitudinal grade (e.g. 0.5%), if the deck slope is uniform, or, if a vertical curve a
reduced level shall be shown
vertical and horizontal clearances for bridges over roadways and/or railway lines including an
approximate reduced level at the intersection point between the control line and the
centreline of the underlying road or railway line
form and extent of any embankments and any required embankment protection above or
below the existing surface level
contract levels of all footings or piles
bearing movements (e.g. fixed, free, sliding, etc.), and expansion joints
chainages, existing surface levels and design surface levels at the end of deck and at pier
centrelines on the control line in a datum block beneath the elevation
to/from showing the nearest major towns in both directions from the bridge/structure.
Austroads 2009
— 42 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
the position of the bridge/structure indicated by a filled shape and showing the chainage and
reduced level at each end of the bridge/structure.
Note: Depending on the complexity of the horizontal geometry, values such as chainage and
coordinate may be placed in a table.
Austroads 2009
— 43 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 44 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 45 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 46 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 47 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 48 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 49 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
These elements can also be combined such as piles and spread footings, which when designed
will form the base element to support the structure above.
Footing, spread footing and pile layout drawings shall be shown in a set of bridge construction
plans, showing the correct setting out, orientation and plan size of all elements. The layout will
also show the locations of any test piles (Figure 3.13).
Geotechnical information
Test bores for foundations are taken at nominated locations on bridge sites to establish the type
and strength of the foundation material. The information is shown by the drilling contractor in a
borehole log.
As a rule at least one borehole would be taken at each pier and abutment location; however this
process may vary from one site to the next.
If required or preferred, the locations of the boreholes may be shown on the plan view of a General
Arrangement drawing.
As part of a set of bridge construction plans, the borehole log shall be referred to as a reference,
either on the pile/footing drawings or on the Cover Sheet.
3.3.2 Piles
Various types of piles are used in bridge construction, such as:
Driven piles
Cast-in-place/drilled piles.
Driven piles
Driven piles are generally prefabricated members made from various types of material, such as,
steel (‘H’ piles, tubular piles), concrete (precast reinforced concrete, prestressed reinforced
concrete), and timber in some cases. Driven piles also come in various shapes, such as round,
square, octagonal, and shaped (e.g. ‘H’ pile).
A separate drawing for the fabricated members shall be added as part of the set of bridge
construction plans and shall contain all relevant information required for the fabrication of each
member.
Where piles are required to be spliced, the minimum depth below ground level to the splice shall
be clearly shown on the drawings.
Austroads 2009
— 50 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
All relevant information for the placement and location of the piles, such as reduced levels, rakes
and coordinates shall be clearly shown on the drawings.
All relevant information for the placement and location of the piles, such as reduced levels, rakes,
rock sockets and coordinates shall be clearly shown on the drawings.
Generally cast-in-place piles can come in various diameters, sometimes on the same bridge
construction site.
The layout should be shown on the pile detail sheet where possible and include all information
necessary for the positioning of the piles (Figure 3.13 and Figure 3.14).
Austroads 2009
— 51 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Piles in a group
The centre of the pile group shall be defined by a chainage and bearing to the control line together
with a dimension from the control line; or alternatively by a set of coordinates with the location of
each pile being dimensioned from the centre of the pile group parallel or normal to the centreline of
the piles (Figure 3.15).
Austroads 2009
— 52 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Raked piles
Where raked piles are used, a note shall be added to the drawing to indicate that the location
shown is at a nominated reduced level/height (usually the top of pile).
Raked piles shall also have the degree of rake shown together with an arrow to indicate the
direction of the rake in relation to the centreline of piles.
Where raked piles are in two or more rows beneath a pile cap, a dimension between the design
levels (usually the top of pile) of the pile centrelines shall be provided (Figure 3.13).
The layout shall indicate plan dimensions of the individual footings. The layout shall provide the
horizontal alignment data for the control line, such as chainage, bearing and coordinates, and
include all information necessary for the positioning of the footing from the intersection of the
control line and the centreline of the footing, such as the bearing of the footing centreline (Figure
3.16).
Austroads 2009
— 53 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
The layout does not necessarily need to be to scale, however it should be reasonably
proportioned. On curved bridges it may be advantageous to exaggerate the curvature in order that
dimensions may be shown more clearly.
Concrete detail drawings should show the physical dimensions and reduced levels of a concrete
structure. It is important that sufficient information is shown to enable formwork to be built and
erected and concrete quantities to be easily calculated.
Formed holes, cast-in metal work, construction joints and any necessary layers of mass concrete
shall be shown.
General notes
General notes applicable to concrete detail sheets will cover such information as concrete
exposure classification, concrete strength and any other applicable notes relating to the concrete
structure.
Formed holes are cast at the time of placing the concrete either by using some form of sacrificial
material, such as a polystyrene block, or by using some type of hollow pipe as a permanent
formwork. The location of the formed holes shall be sufficiently dimensioned to enable their correct
positioning inside the formwork.
Austroads 2009
— 54 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Cored holes are created in existing concrete by the use of coring drills and are used when large
diameter holes are required. The location of the cored holes shall be sufficiently dimensioned to
enable their correct positioning in the existing concrete structure.
Drilled holes are drilled in existing concrete and are deemed a small diameter hole. The location of
the drilled holes shall be sufficiently dimensioned to enable their correct positioning in the existing
concrete structure.
Cast-in items
Cast-in items (where applicable) shall be cross-referenced to the sheet where the respective
details are shown. The location of cast-in items shall be sufficiently dimensioned to enable their
correct positioning inside the concrete structure formwork.
3.4.3 Dimensioning
Dimensioning of concrete items shall be in accordance with Section 2.3 and Section 2.4 of this
Guide.
Dimensioning of concrete elements, whose details appear on a separate sheet, shall not be given,
e.g. the dimensions for the positioning of piles relative to the pile cap and its extremities shall not
be shown on the pile cap drawing.
Non-standard fillets i.e. greater than 20 x 20 mm, shall be shown in all instances and shall be
either called up or dimensioned.
Plan views shall be drawn as a horizontal view taken immediately above the element under
consideration.
Hidden details such as piles, columns and footings shall be shown as broken lines where
appropriate (Figure 3.17).
Austroads 2009
— 55 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
3.4.5 Elevation
Elevations shall be drawn as a view seen from a vertical plane immediately in front of the element
under consideration.
Hidden details, such as abutment wing walls and associated fillets shall be shown as broken lines
(Figure 3.18).
Austroads 2009
— 56 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
3.4.6 Section
Sections shall be drawn as a view from a cutting plane located through an element previously
drawn as an elevation, plan or view.
Generally, only the details at the cutting plane of the section should be shown, however, details
beyond the cutting plane may be included provided that the included details are not confusing to
the main details being shown.
Sections, where possible, shall be drawn adjacent to the plan or elevation to which they relate.
Where section details cannot be shown on the sheet of origin, they shall be cross-referenced in
accordance with Section 2.10 of this Guide.
If a series of cutting planes are used to define section details, any change in direction of the cutting
plane shall be shown by thick lines. (Figure 3.19 and Figure 3.20).
Austroads 2009
— 57 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Construction joints, where critical for design purposes e.g. continuous deck slabs, voided slabs and
continuity connections, shall be adequately located by dimensions on the drawings.
Construction joints may also be required in tall members (e.g. pier columns) to avoid height related
access and concrete compaction problems.
The aesthetic aspect of construction joints in highly visible members should be considered and
detailed if deemed necessary.
Austroads 2009
— 58 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
3.5.1 General
The elevations, plans, views and sections shall be drawn using the same principles as outlined in
Section 3.4 of this guide and will show the required reinforcement details.
In some cases concrete and reinforcement can be shown on the same drawing, even on the same
view, however, in more complex reinforced concrete elements, such as, abutments, it is preferable
to detail the concrete and reinforcement on separate drawings.
The full description of a bar, as above, will appear on a drawing only once. All subsequent
references to the bar shall require only the bar mark (e.g. A2). For a more detailed view see
Section 3.5.3 of this Guide.
Austroads 2009
— 59 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Where a grade other than D500N is required (e.g. D250N), the bar’s structural properties shall be
placed before the bar size (Figure 3.23).
Where the bar’s surface shape is required to be plain round, the letter before the bar size shall be
shown as an ‘R’ (Figure 3.24).
Bar size
The nominal bar diameter in the longitudinal direction is shown in millimetres.
Austroads 2009
— 60 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Bar spacing
The spacing of a bar or bars, along a limit line is expressed in millimetres (Figure 3.22).
In bridge decks where cross girders/diaphragms are used, the first bar marks used shall be in the
cross girders/diaphragms as these bars must be placed before the main slab reinforcement
(Figure 3.26).
Austroads 2009
— 61 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Where interference is of a minor nature only and is not critical, a suitable note shall be added to the
drawing, such as the following:
The spacing of vertical bars may be adjusted slightly where necessary to clear formed holes
and dowels.
Reinforcement may be displaced slightly where necessary to clear dowels, anchor bolts,
formed holes and recesses.
Austroads 2009
— 62 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Bar shapes
Bar shapes in general shall be taken from Table 3.1 (A) and Table 3.1(B) of AS 1100 Part 501.
In addition to the Australian Standard bar shapes, each road authority may have adopted bar
shapes that are commonly used in the detailing of a set of bridge construction plans. Each state
shall be consulted for their commonly used bar shapes.
Where the shape of a particular bar does not conform to the Australian Standard bar shapes or the
bar shapes used by the road authority, a ‘Z’ suffix shall be added to the bar shape code with the
first non-standard shape being ‘AZ’. Variations within a particular non-standard bar shape (e.g.
same general shape with different leg lengths), shall be identified by the use of the next available
numerical prefix (Figure 3.27).
Any subsequent non-standard bar shapes shall be labelled 'BZ', 'CZ' etc. and all non-standard
shapes shall be clearly defined on the ‘Bar shapes diagram’ sheet. Where non-standard bars
require fitment of bends and hooks, this and any other special feature shall be specified in the bar
shapes diagram.
In elevations, plans and views reinforcement is typically detailed using the following method:
Only one bar in a set of bars is drawn with the extents of that bar shown using limit lines.
The number and spacing of the bars over the extents is shown as a reinforcement label.
When showing bars in elevation, plan and view, bars should not be shown in section, only
under special circumstances should this rule not apply (Figure 3.25 and Figure 3.28 to
Figure 3.30).
Austroads 2009
— 63 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Figure 3.29: Elevation, plan and view – Detail principle (variable bars)
Austroads 2009
— 64 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 65 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
A bar shape shall not be shown next to an elevation, plan, view or section, the bar shall be detailed
in its final position, in relation to the concrete shape (Figure 3.31 to Figure 3.34).
Austroads 2009
— 66 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Austroads 2009
— 67 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Reinforcement laps
Reinforcing bars are manufactured to set lengths.
When the length required exceeds the bar length, two or more bars are lapped together to produce
the required length.
Laps need not be shown unless they are required in a specific location.
When lapped in a specific location the lapped reinforcement is typically detailed using the following
methods:
Austroads 2009
— 68 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Bundled bars
When two or more bars are placed together (e.g. fitments in a parapet, etc.), they shall be called
up as a bundle. Not all the bars in a bundle need to be shown, particularly when the number of
bars exceed the practical limit of showing the clear representation of the bundle.
In Figure 3.38 a number of bars are displayed in a slab, in both section and elevation. Figure 3.39
displays two simple alternative methods of detailing a bundle.
Austroads 2009
— 69 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
Cover to reinforcement
All reinforcement drawings shall contain a note giving the required cover from a concrete face to
the reinforcement, e.g. ‘Nominal cover to reinforcement nearest to the concrete surface shall be
40 mm, unless specified otherwise.’
When the cover is not as stated, the cover must be detailed (Figure 3.31).
For simple fabrication work, such as bridge girders that are made from rolled steel sections,
universal beams and built-up plate girders, shop drawings are not usually prepared.
Each item of fabricated steelwork shall be detailed in the form with which the item would be
released from the fabrication shop, with each and every part that would be attached in the
fabrication shop, shown as part of the total assembly.
Fabricated items that form part of the total assembly need not be detailed as separate items, nor
shall the quantity of those items be shown separately unless unduly complicated, and in such a
case, the quantity of those items is shown and detailed separately.
In the majority of cases, it is sufficient to detail a fabricated item in one or two views, with enlarged
details of the more complex portions as necessary.
Where items are to be bolted or welded together in the field, (e.g. where steel cross girders are to
be attached to the main girders), an assembly drawing showing all components in their final
position in the structure shall be provided.
Bolts, nuts and washers shall be described separately on drawings due to the different Australian
Standards they refer to.
Austroads 2009
— 70 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
In all cases where protective treatment of steelwork is required, a note shall be included in the
general notes on the drawing.
Where fabricated steel items have been hot-dip galvanised and the surface of the protective
coating has been disturbed or damaged for any reason, a note shall be included in the general
notes on the drawing for the treatment and repair of the damaged surface.
Austroads 2009
— 71 —
GUIDE TO BRIDGE TECHNOLOGY PART 5: STRUCTURAL DRAFTING
REFERENCES
Austroads 2008, Glossary of Austroads terms, 2nd edn., by K Sharp & P Milne, AP-C87/08 Austroads,
Sydney, NSW.
Department of Planning and Infrastructure, Northern Territory 2007, CADD manual, version 1.3 , DPI,
Darwin, NT.
Department for Transport, Energy and Infrastructure, South Australia 2008, ‘Structures group drafting
guidelines’ version 2, DTEI, Adelaide, SA.
Main Roads Western Australia, 2009, Drafting guidelines and practices manual, MRWA, Perth, WA.
Roads and Traffic Authority, New South Wales 2007, Structural drafting and detailing manual, RTA, Sydney,
NSW.
Queensland Department of Main Roads 2008, Bridge design drafting manual, QDMR, Brisbane, Qld.
VicRoads n.d, ‘A selection of bridge related project drawings’, VicRoads, Kew, Vic. (unpublished).
Standards Australia
AS 1100.401-1984, Technical drawing: engineering survey and engineering survey design drawing.
AS ISO 1302-2005, Geometrical product specifications (GPS): indication of surface texture in technical
product documentation.
Austroads 2009
— 72 —