Project Delivery Alternatives
Project Delivery Alternatives
Project
Delivery
Alternatives
Design and
Decommissioning RFP Preparation
Or repurposing Project Delivery
Permits
Commissioning
Construction
1
2015-‐02-‐01
3
Issues
Design-Bid-Build
Owner
(building project)
Engineering
Structural, Subcontractors
Mechanical, Electrical
2
2015-‐02-‐01
5
Design-Bid-Build
u Payment typically by fixed price or unit cost (for unseen conditions)
u Lowest bid award
u Prime Consultant reviews & certifies
u Typically adversarial relationships
u Long timeline – sequential activities
6
Divergent Project Objectives
Client Contractor
• Lowest Cost • Maximized Profit
• Maximum Quality • Acceptable Quality
• Earliest Completion • Most Cost Effective Schedule
• Flexibility to Make Changes • Capitalize on Changes
• Fix Costs and Hand-off Risk • Minimize Risk
• Control the Work • Control the Work
3
2015-‐02-‐01
7
Most Common Method
u When:
u No time constraints
u Buildings
u Client is willing to work with architect to meet design needs
8
Pros and Cons
u Pros:
u Design is complete and therefore the contractors know exactly
what they’re bidding on (in a perfect world)
u Owner knows what they’re getting and for how much money
u Cons:
u Contractor has no influence on the design
u Must bid on design even if they have ideas for improving
design or reducing costs
u Longest duration because activities are sequential
u Very adversarial between designers and contractors
4
2015-‐02-‐01
9
Note!
10
Fast Track
u Reduce over all project timeline by overlapping design and construction
u Incremental approach
u Defined scope of work
u Achieve by: Design
u Construction Management Bid
u Design-build Build
u P3
5
2015-‐02-‐01
Construction Management
Owner
Construction
Manager
11
12
Construction Management (CM)
6
2015-‐02-‐01
13
CM cont.
14
Pros and Cons
u Pros:
u Project delivered more quickly as construction can begin
before design is complete.
u The involvement of the CM in the design process helps to cut
costs and improve the constructability of the design.
u Cons:
u Tends to be a bit more expensive
u Greater errors occur because construction is pushing design.
Therefore construction rework should be expected.
u Owner holds potentially hundreds of contracts
u Don’t know final cost until last contract is tendered
7
2015-‐02-‐01
15
Design-Build
Owner
(building
project)
Design-build
firm-
Often the GC
16
Design-Build
8
2015-‐02-‐01
17
Advantages
18
Disadvantages
9
2015-‐02-‐01
19
Proposal Process
u The process must not only be fair, it must appear to be fair !
u Provide adequate time to prepare proposals
u Provide adequate base information
u Control evaluation process (security)
u Eliminate conflicts of interest
20
Honorarium
10
2015-‐02-‐01
21
Evaluation of Proposals
22
Negotiations and Award
u Ensure all stakeholders have reviewed the proposal and negotiate
refinements
11
2015-‐02-‐01
23
Advantages
Public
Owner
P3
consortium
24
12
2015-‐02-‐01
25
Alliancing
Alliancing
Project
Prime
Owner Engineers Financers
Contractor
26
13
2015-‐02-‐01
27
Alliancing
28
Lessons Learned for Success
14
2015-‐02-‐01
29
Lessons Learned - Failures
30
15
2015-‐02-‐01
31
Fixed Price or Lump Sum
32
Unit Price
16
2015-‐02-‐01
33
Cost Plus
u Actual cost of construction plus overheads plus a profit margin (generally
low).
u Used in emergencies. They will call the company with which they have the
best relationship.
u For example, when Suncor experienced a large fire in their coker, they were
losing $2M per day – they just wanted it fixed!
u Services of CM paid this way too
u The owner and contractor must agree in advance to the payment amounts
and schedule.
34
Partnering
17
2015-‐02-‐01
35
What is Partnering?
36
Partnering Workshop(s)
18
2015-‐02-‐01
37
Partnering Charter
38
Does Partnering Work?
19