PPP Feasibility Study Checklist: Project Name
PPP Feasibility Study Checklist: Project Name
PPP Feasibility Study Checklist: Project Name
Project Name
C4 Based on the analysis, does the sponsoring authority consider the project concept to
be practical?
C5 Has the Assessment of existing supply been prepared?
Is the project site or at least one of the project site options suitable from a technical
C6 and operational perspective?
C7 Has the technical scope of the project been defined?
C8 Is the engineering plan practical?
C9 Is the operations and maintenance plan practical?
C10 Have the major technical and operational risks to the project been identified?
C11 Does the project master plan prepared?
C14 Have the costruction cost estimates prepared?
C15 How much is the project total cost?
C16 Hav IT & Office Equipment plan prepared?
C17 How much start up cost does need the project?
D Financial Study
Have all major project cost components (capital, operations, maintenance) of the
D1 technical scope of the project been estimated?
Are the assumptions on major project cost components reasonable? Can they be
D2 justified based on a rationale?
D3 Has a market demand analysis been done? (Tariffs, Volume)
D9 Has an estimate of required financial support from the public sector been made?
D10 Have the major financial and commercial risks to the project been identified?
D11 Have the impact and management strategy of the financial and commercial risks to the
project been prepared?
Does the financial analysis demonstrate that the sponsoring authority will recover its
D12 investments along with a reasonable return under different scenarios?
Based on the analysis, does the sponsoring authority consider the project concept to
D13
be financially and economically viable?
D14 Has a strong rationale and recommendation been made by the sponsoring authority in
the preliminary assessment?
D15 Have the likely economic benefits generated by the project been identified?
D16 Has a sensitivity analysis been undertaken?
D17 Have the key financial and economic ratios been computed? (for example, NPV,
IRR,EIRR, ENPV etc.)
D18 Have financial projections been prepared?
D19 Has a financial analysis model been used to assess the financial viability of the project?
D20 Has the fiscal affordibility of the project is identified?
D21 Have the financial statements of the project is prepared?(for example, Balance sheet,
income statement...)
Have the producer suplus and consumer suplus analysis for infrastructure project is
D22 prepared?
E Legal Study
E1 Land Ownership and Construction
E2 Process for Getting Land
E3 Tax and tariff examption
F The Social, Economic and Environmental Study
Has a scoping environmental assessment been done? Were any serious issues raised?
Has an impact and management strategy been prepared to deal with the major social
and environmental issues?
F1 Has a scoping social impact assessment been done? Were any serious issues raised?
G Value For Money Study
G1 Has the project Value for Money Analysis been preapared?
H Risk Management
H1 Major Risks associated to the project
H2 Risk Sharing and allocation
H3 Risk Mitigation
I Base Case Assumptions
H2
J Conclusion Statement
I1