CHAINAGE - 313.715 KM: Geotechnical Investigation Report
CHAINAGE - 313.715 KM: Geotechnical Investigation Report
FOR
SUBMITTED TO:
CONTENTS
1.0 Introduction 2
2.0 Scope of work 2-3
3.0 Site Exploration 3-4
4.0 Laboratory Testing 4-10
5.0 Finding 10-11
6.0 Proposed Depth & Type of Foundation 12
8.0 Conclusion with Recommendation 13
9.0 Closure 14
ANNEXURE 1
Soil Profile, SPT Curves & Grain Size Curves 15-20
1
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
1.0 INTRODUCTION:
1.1 This report presented herein deals with the field and laboratory investigations carried
out by us to access the nature of sub-strata and to evaluate the soil parameters
required for design of Construction of four laning of Rohtak-Jind Section from
KM. 307+000 to km 347+800 of NH-71 (New NH-352) and connecting link from
Km 347+800 of NH-71 to km 355+600 of NH 71 and meeting at Km 9.400 of NH-
71A ( new NH-709) ( Balance work) in state of Haryana) on EPC mode.
1.4 This report is based upon the results of field and laboratory tests conducted on
selected soil samples collected from twenty two bore holes.
The scope of geotechnical investigation for this site includes making 150mm diabore
hole at specified locations up to 10.0m below existing ground surface in soil& rock
strata using rotary drilling method, as per IS:1892, 1979. Conducting standard
penetration tests in bore holes as per IS: 2131, 1981 in all types of soils, during boring
activity at 1.5m interval or at every change of strata whichever occurs earlier. The blow
counts for SPT Test shall be terminated when combined blow count exceeds 100
(called as refusal) for the last 300mm penetration of the sampler.
2.1 Collecting undisturbed & disturbed soil samples in soil strata at regular interval of
3.0m depth or at every change of strata whichever occurs earlier.
2.2Conducting following laboratory tests on representative soil samples.
a) Natural moisture content
b) Dry density/Bulk Density
c) Particle size analysis
2
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
d) Atterberg’s limits
e) Classification of soil
f) Specific gravity of soil
g) Triaxial shear test (CU & UU)
h) Direct shear test on cohesion less specimen
i) Consolidation test on clayey specimen
Rock Samples
a) Density Tests
b) Water Absorption and Porosity
c) Determination of Specific Gravity
d) Unconfined Compression Test
e) Carry out Point Load Index.
All the above laboratory tests were carried out as per relevant Indian Standards. All the soil
samples were identified and classified as per IS: 1498-1970.
2.3 Recording the depth of ground water table on its full stabilization in all the bore holes
in case of its occurrence.
2.4 Describing sub-soil strata and preparation of bore logs.
2.5 Preparing & submitting the geotechnical investigation report in triplicate after
summarizing the field and laboratory tests. The geotechnical report shall include, in
general, as follows:-
a) Identification of soil strata and presentation of the soil profile.
b) Bore log for soil.
c) Tabulation of all laboratory test result.
d) General description-methodology, discussion of test result.
3.0 SITE EXPLORATION:
3.1 The required equipments and team were mobilized to the site for carrying
out the required field work. The locationsof the bore holes and depths adopted were
3
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
given by the engineer – in – charge. The entire bore holes and tests were carried out in
the presence of the representative of site-in-charge. All locations are exhibited in site
plan.
3.2 For boring, power operated winch driven shell and auger method was adopted as per
IS: 1892-1979. Casings were used as per requirement to retain the bore holes in
position. The Bore holes were advanced up to 10.0m depth below existing ground
surface.
3.3 The standard penetration tests were conducted at 1.5m intervals during
the advancement of boreholes.
3.4 For conducting SPT, IS Code: 2131-1981 / was followed. After reaching the required
depth of test, the bottom of the bore hole was cleaned properly and spoon is properly
and centrally seated in position in the borehole. Standard split spoon sampler attached
to lower end of “A” drill rods was driven in the bore holes by means of standard
hammer of 63.5kg.falling freely from a height of 75 cm. The sampler was driven 45
cm. and the number of blows required for each 15 cm. penetration were recorded. The
number of blows for the first 15 cm penetration was considered as seating drive. The
number of blows for last 30 cm. penetration was designated as SPT ‘N’ value. SPT soil
samples obtained from standard split spoon sampler for all the above standard
penetration tests were collected in polythene bags, sealed, labeled and sent to the
laboratory for testing.
3.5 The undisturbed soil samples were collected in good quality thin walled sample tubes,
of min. dia of 100mm and length of 450mm with area ratio less than 15%. The UDS
tubes are gently pushed in soil using hydraulic push rig/gently hammering action. After
retrieval of UDS tube from the borehole, ends of the tube with sample were sealed with
freshly molten wax of minimum 20mm thick, properly labeled, marked an arrow
showing upward direction and dispatched to laboratory for testing. At site, sample
tubes were covered with wet gunny bags. When the UDS tubes were not penetrated
into the subsoil strata, it was clearly mentioned on the bore log sheet.
4
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
3.6 Natural moisture contents of soil samples from the boreholes at different depths were
measured in the laboratory and the values are indicated in laboratory test results in
Bore Log table.
5
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
and blows are imparted by turning the handle at the rate of 2 revolutions per second. The
numbers of blows are counted till the continuous contact of the bottom of the groove
occurs. Few quantity of soil from the close portion of the groove after the contact occurs,
are taken and its water content is determined by oven drying method.
The liquid limit (wL) is computed by the equation.
WL =wN(n/25)e
Where wN =water content (% corresponding to n blows)
e=0.092 for soils with wL<50
=0.12 for soils with wL>50
4.3 PLASTIC LIMIT
For this test sample is prepared in the same way as for liquid limit test. A ball is formed of
sub sample weighting about 5 gm. This ball is rolled between the fingers of one hand and
the glass plate with pressure sufficient to reduce the mass into a thread of about 3mm in 5 to
10 complete forward and back movements. When a diameter of 3mm is reached, soil is
again remolded into a ball. The process of rolling and remolding is repeated until the thread
a start just crumbing at a diameter of 3mm.The crumbled thread is immediately transferred
to an air tight container for determination of its moisture content by oven drying method.
This water content is termed as plastic limit. (wp)
4.4 PLASTICITY INDEX
The plasticity index Ip is given by
Ip=wL –wp
4.5 WATER CONTENT
For this test the soil sample of known quantity (wm) is taken in a container.
The container with this soil sample is placed in an oven for drying at 105-110ºc for 16-24
hours. After drying the dry sample is again weighed to determine the dry weight of sample
(wd)
The moisture content is computed by the following equation:
wN = (wm-wd)/wd
6
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
7
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
thickness of specimen is recorded. Shear displacement dial gauge is also set to read
zero.
The locking screw is now removed and two parts of the shear box are separated by
advancing the spacing screws. The specimen is sheared at constant rate of strain. The
readings of the proving ring dial gauge are noted down every 15 seconds for the first
one minute and then every 30 seconds thereafter. The reading of change in the thickness
dial gauge and shear displacement dial gauge are also recorded at the same time
interval. The test is continued until the specimen fails. The specimen is assumed to fail
when the proving ring dial gauge starts receding or at shear displacement of
approximately 15% of the length takes place.
The soil is removed from the box and test is repeated on the identical specimen under
increased normal load. For consolidated undrained test the specimen is prepared and set
in the apparatus as above and after submergence, the specimen is allowed to consolidate
fully under normal loads. The specimen is then sheared as in undrained test. At the end
of the test, the specimen is removed and its final water content is determined. The test is
repeated on other identical specimen in similar way under increasing normal loads. For
drained test, after completion of consolidation under a particular normal load, specimen
is sheared at a slow rate to allow the pore water pressure inside the specimen may be
drained out ie completely dissipated. Final water content of failed specimen is
determined. The test is repeated on other identical specimen after consolidation under
increasing normal loads.
4.9 TRIAXIAL SHEAR TEST
For this test Triaxial Shear Test apparatus with pore pressure measurement apparatus is
used. The porous disc or plain disc, depending on the test conditions is placed on the
pedestal of the triaxial cell. The specimen is placed centrally on the disc. A correct size
membrane is fitted inside the stretcher with ends of membrane folded over those of the
stretcher. Vacuum is applied to stretch the membrane to the inside surface of the
stretcher is carefully slipped around the specimen kept on the pedestal. The vacuum on
8
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
the membrane is released. Its bottom part is rolled down into the pedestal. Depending
on the type of test porous or plain disc is placed on the top of the specimen and then
pressure pad is placed. The top part of membrane is rolled on to the pressure pad. Now
the stretcher is removed and ends are sealed with ‘O’ rings. With the properly sealed
specimen placed centrally on the pedestal, the cell is assembled, keeping the loading
piston initially clear of the pressure pad of the Specimen. The assembly is placed in the
loading frame. For unconsolidated untrained test, the bottom drainage valve (BDV) and
top
drainage valve (TDV) of cell, is closed and air release valve (ARV) is opened. The cell
is filled with water through the cell water valve CWV. ARV is closed when water
begins to escape through it. The cell pressure is raised to the desired valve and kept
constant till the end of the test.
If initially unsaturated specimen is to be saturated before the test, the specimen is
mounted in the cell with porous disc. The specimen is saturated by back pressure
saturation method. When the cell pressure is applied, the load piston rises upward, the
loading machine is operated at the anticipated rate to bring the load piston slightly
above the pressured pad of the specimen and the load measuring dial gauge on proving
ring is set to zero. The piston is brought just in contact with pressure pad by hand
operation of the machine. The axial compression dial gauge is mounted and set to read
zero. The axial loading is started at constant rate of strain. Simultaneous readings on the
load and compression dial gauges are noted down. The test is continued until a
recession of the axial load is observed. After failure, the specimen is unloaded by
reversing the loading machine, cell pressure is reduced and cell water is drained out
after opening the ARV. The cell is dismantled and the specimen is taken out rubber
membrane is removed and weight of the failed sample and its water content is
determined. The test is repeated on two more identical specimens with increasing cell
pressure. For consolidated undrained test, first the specimen is saturated by back
pressure saturation. The saturated specimen is then consolidated fully under a cell
9
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
pressure. After consolidation is complete, the axial load is applied and the test is
conducted as for undrained test. The pore pressure developed during the undrained test
portion is measured by the pore pressure measuring system. After the completion of
test, pore pressure apparatus and mercury
control system is disconnected, cell is dismantled and sample is taken outside to
determine its weight and final water content. The test is repeated on three identical
specimen using increasing cell pressure for consolidation. For consolidated drained test,
the specimen is first allowed to consolidate under a confining pressure as in
consolidated undrained test. Then sample is failed under drained condition. After
consolidation is complete, the axial load is applied and the test is conducted as for
undrained test. The pore pressure developed during the undrained test portion is
measured by the pore pressure apparatus. After completion of test the pore pressure
apparatus. After completion of test the pore pressure apparatus and mercury control
system is disconnected, cell is dismantled and sample is taken outside to determine its
weight and final water content. The test is repeated on three identical specimens using
increasing cell pressure for consolidation.
10
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
4, 6.25, 9, 12.25, 16, 20.25, 25, 36, 49, 64 --------- ).After the final dial reading under
the first applied pressure, the specimen is consolidated further under successive higher
pressures. Readings of settlement dial gauge are noted down for each increment of
pressure as above. Having completed the consolidation of specimen under the
maximum pressure, ensuring that water in the trough fully surrounds the specimen,
applied pressure is reduced to zero and specimen is allowed to take up water and swell.
After 24 hours, final dial gauge reading corresponding to the end of test is noted down.
The consolidation cell is removed from the loading machine. The specimen is taken out,
cleared off the filter papers, transferred into the container and dried in an oven for
determining final water content and weight of soil solids.
The subsoil strata are medium dense to very dense up to the depth of exploration. The
detail description of subsoil strata encountered along with various laboratory test
results are presented in the respective bore logs given in soil profile is enclosed as
ANNEXURE- A. The subsoil profile depicting the distribution of the various subsoil
strata along with observed ‘N’ values with depth together with other test results are
given in soil profile is enclosed as ANNEXURE- A
Based upon the results of field investigations, laboratory test results, & further
discussions held with the client, the following type of foundations have been analyzed
hereinbelow : -
11
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
The settlement of cohesion less layers below the foundation level and up to the zone of
Influence are computed by using the chart of settlement Vs SPT ‘N’ given on page 17
of IS 8009, part-I.
12
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
The relevant soil parameters have been adopted from the bore log enclosed with the
report.
The values of settlement obtained as above are corrected applying the Fox’s depth
correction factor and rigidity factor.
13
REPORT ON GEOTECHNICAL INVESTIGATION
FOR
CHAINAGE – 313.715 KM
8.0 CLOSURE
We appreciate the opportunity to submit this Soil Investigation Report. The above
recommendations have been made on the basis of in situ tests and laboratory tests
conducted on the samples collected from the boreholes bored at the locations given by
the client. If during excavation, any unusual or abnormal features are noticed, these
may be brought to the attention of geotechnical consultant before proceeding with
construction work for further suggestions.
SAMI R PANDE Y
(DIR ECTOR)
14
KUNIKA GEOTECHNICAL SERVICES PVT LTD
BOREHOLE NO. A1 DATE STARTED : : 28/05/2020 Co - ordinates Structure SHEET 1
LOCATION : Chainage - 313.715 Km. DATE COMPLETED : : 28/05/2020 X Y MNB
REDUCED LEVEL OF B/HOLE : 100.00 m 632527.269 3231320.934
FIELD TEST RESULTS LABORATORY TEST RESULTS
CHARACTERISTICS PARAMETERS
NATURE OF SAMPLING
COMPRESSION INDEX
IN THE LABORATORY
N, VALUE ( Corrected )
N, VALUE ( Recorded )
PENETRATION (CM)
SPECIFIC GRAVITY
REPRESENTATION
(%)
(%)
NO. OF BLOWS
(%)
Angle of friction
REFERENCE
VOID RATIO
Cohesion, C,
SYMBOLIC
(Degrees)
GRAVEL
(t/sqm.)
SAND
L.W.L
( MM)
CLAY
SILT
Cc
e0
DS 1.00 1 0.00 - 1.00
100.0 1.0
SPT 1.50 1 1.50 - 1.95 9 30 9 9 Light Brown Clayey Silt of
2.0
Medium Plasticity
UDS 2.50 1 2.50 - 2.80 ( CI ) UUT 0.0 21.0 68.0 11.0 36.0 22.0 1.74 1.54 13.10 2.67 3.60 9.0 0.139 0.734
3.0
SPT 3.00 2 3.00 - 3.45 12 30 12 12
4.0
SPT 4.50 3 4.50 - 4.95 18 30 18 19 0.0 60.0 40.0 0.0 NON PLASTIC -- -- -- 2.63 -- -- -- --
7.50m
95.00 5.0
150
UDS 5.50 2 5.50 - 5.80 DST* 1.73 1.58 9.50 -- 0.00 28.9 -- --
6.0
SPT 6.00 4 6.00 - 6.45 25 30 25 24 Light Brown Silty Sand of
7.0
Non Plasticity
SPT 7.50 5 7.50 - 7.95 14 30 14 12 ( SM ) 0.0 65.0 35.0 0.0 NON PLASTIC -- -- -- 2.62 -- -- -- --
8.0
UDS/DS 8.50 3 8.50 - 8.80 DST* 1.80 1.58 14.10 -- 0.00 29.5 -- --
9.0
SPT 10.00 6 9.55 - 10.00 21 30 21 16
90.00 10.0
2. ABBREVATION USED : DS = DISTURBED SAMPLE UDS = UNDISTURBED SAMPLE UU = UNCONSOLIDATED UNDRAINED DST = DIRECT SHEAR TEST BORE LOG CHART AND DATA SHEET
15
KUNIKA GEOTECHNICAL SERVICES PVT LTD
BOREHOLE NO. A1
N - VALUE
0 20 40 60 80 100
0
3
DEPTH IN M
OBSERVED
CORRECTED
6
12
16
KUNIKA GEOTECHNICAL SERVICES PVT LTD
BOREHOLE NO. A1 DATE STARTED : : 28/05/2020 Co - ordinates Structure SHEET 1
LOCATION : Chainage - 313.715 Km. DATE COMPLETED : : 28/05/2020 X Y MNB
REDUCED LEVEL OF B/HOLE : 100.00 m 632520.200 3231340.577
FIELD TEST RESULTS LABORATORY TEST RESULTS
SHEAR STRENGTH CONSOLIDATION TEST
SPT TEST RESULTS GRAIN SIZE ANALYSIS
DEPTH OF SAMPLE BELOW
DESCRIPTION OF SOIL
NATURE OF SAMPLING
PENETRATION (CM)
SPECIFIC GRAVITY
REPRESENTATION
(%)
COMPRESSION
(%)
NO. OF BLOWS
(%)
Angle of friction
REFERENCE
VOID RATIO
Cohesion, C,
SYMBOLIC
INDEX Cc
(Degrees)
GRAVEL
(t/sqm.)
SAND
L.W.L
( MM)
CLAY
e0
SILT
DS 1.00 1 0.00 - 1.00
100.0 1.0
Light Brown Clayey Silt of
SPT 1.50 1 1.50 - 1.95 9 30 9 9
2.0 Medium Plasticity
UDS 2.50 1 2.50 - 2.80 UUT 0.0 18.0 70.0 12.0 36.0 22.0 1.77 1.55 14.10 2.68 3.60 8.0 0.138 0.729
3.0 ( CI )
SPT 3.00 2 3.00 - 3.45 12 30 12 12
4.0
SPT 4.50 3 4.50 - 4.95 18 30 18 19 0.0 62.0 38.0 0.0 NON PLASTIC -- -- -- 2.62 -- -- -- --
7.50m
95.00 5.0
150
UDS 5.50 2 5.50 - 5.80 DST* 1.71 1.57 8.90 -- 0.00 28.7 -- --
6.0
Light Brown Silty Sand of
SPT 6.00 4 6.00 - 6.45 25 30 25 24
7.0 Non Plasticity
(
SPT 7.50 5 7.50 - 7.95 14 30 14 12 0.0 69.0 31.0 0.0 NON PLASTIC -- -- -- 2.63 -- -- -- --
8.0 SM )
UDS/DS 8.50 3 8.50 - 8.80 DST* 1.83 1.59 14.80 -- 0.00 29.3 -- --
9.0
SPT 10.00 6 9.55 - 10.00 21 30 21 16
90.00 10.0
2. ABBREVATION USED : DS = DISTURBED SAMPLE UDS = UNDISTURBED SAMPLE UU = UNCONSOLIDATED UNDRAINED DST = DIRECT SHEAR TEST BORE LOG CHART AND DATA SHEET
17
KUNIKA GEOTECHNICAL SERVICES PVT LTD
BOREHOLE NO. A1
N - VALUE
0 20 40 60 80 100
0
3
DEPTH IN M
OBSERVED
CORRECTED
6
12
18
KUNIKA GEOTECHNICAL SERVICES PVT LTD.
110.00
100.00
90.00
80.00
70.00
Percentage passing
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.001 0.01 0.1 1 10
Particle size (mm)
Symbol Description of soil Depth (m) Gravel (%) Sand (%) Silt (%) Clay (%)
19
KUNIKA GEOTECHNICAL SERVICES PVT LTD.
110.00
100.00
90.00
80.00
70.00
Percentage passing
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.001 0.01 0.1 1 10
Particle size (mm)
Symbol Description of soil Depth (m) Gravel (%) Sand (%) Silt (%) Clay (%)
20
SAMPLE CALCULATION
= 34.15 t/m2
2. Local Shear Failure :-
Qns = [2/3 cNc.sc.dc.ic+ p (Nq-1).sq.dq.iq+0.5 yb. B.Ny.Sy.dy.iy.w’]/2.5
= 14.63 t/m2
Interpolate between General Shear Failure and Local Shear Failure
Intrepolation Factor - I = 0.08
Intrepolation = 16.19
The Net Safe Bearing Capacity = 16.19 t/m2
21
1.0 SETTLE MENT CRITERIA (IS:8009, Part - I)
a. Consolidation Settlement 0.0 - 5.5 meter) 5.50
Cc Po + ∆P
sc = -----------. H. log10. ------------- ……………. (II)
1 + eo Po
3
H = 5.50 Cc = 0.139 e0 = 0.734 Saturated density = 1.77 t/m
2
P0 = 10.18 ∆P = 8.505308 t/m
Consolidation settlement of this layer 1 = 0.116 m
Corrected settlement for raft foundation = 79.09 mm
Seat of Settlement = 48.33 mm
b. Settlement in sand (Layer ) 5.50 - 9.0 meter) 3.50
Corrected Average N value = 18
Applied pressure 1.62 kg/cm2
The settlement for cohesion less soil are computed from Chart N vs settlement given on page 17 of IS: 8009 (Part I –
Reaffirmed -1998)
Settlement at a load of 1.0 Kg /cm2 = 17.5 0.5 34.92773
Settlement at a load of 1.62 Kg /cm2 = 56.6
Fox's Depth Factor = 0.85
Rigidity Factor, dr = 0.80
Corrected settlement for raft foundation = 38.46 mm
Total Settlement of Foundation = 86.79
Tolerable Total Settlement : = 50
Hence for 50 mm permissible settlement, net API = 0.93 Kg /cm2
= 9.33 T/m2
RECOMMENDATION:
LEAST FROM ABOVE VALUES OF NET SBC OBTAINED FROM SHEAR FAILURE CRITERIA AND
SETTLEMENT FAILURE CRITERIA i.e. 9.33 T/m2 FOR 50 MM SETTLEMENT MAY BE ADOPTED FOR
DESIGN PURPOSES
22
SAMPLE CALCULATION
= 41.16 t/m2
2. Local Shear Failure :-
Qns = [2/3 cNc.sc.dc.ic+ p (Nq-1).sq.dq.iq+0.5 yb. B.Ny.Sy.dy.iy.w’]/2.5
= 17.71 t/m2
Interpolate between General Shear Failure and Local Shear Failure
Intrepolation Factor - I = 0.08
Intrepolation = 19.58
The Net Safe Bearing Capacity = 19.58 t/m2
23
1.0 SETTLE MENT CRITERIA (IS:8009, Part - I)
a. Consolidation Settlement 0.0 - 5.5 meter) 5.50
Cc Po + ∆P
sc = -----------. H. log10. ------------- ……………. (II)
1 + eo Po
3
H = 5.50 Cc = 0.139 e0 = 0.734 Saturated density = 1.77 t/m
2
P0 = 11.95 ∆P = 10.28509 t/m
Consolidation settlement of this layer 1 = 0.119 m
Corrected settlement for raft foundation = 78.01 mm
Seat of Settlement = 47.67 mm
b. Settlement in sand (Layer ) 5.50 - 9.0 meter) 3.50
Corrected Average N value = 18
Applied pressure 1.96 kg/cm2
The settlement for cohesion less soil are computed from Chart N vs settlement given on page 17 of IS: 8009 (Part I –
Reaffirmed -1998)
Settlement at a load of 1.0 Kg /cm2 = 17.5 0.5 34.92773
Settlement at a load of 1.96 Kg /cm2 = 68.4
Fox's Depth Factor = 0.82
Rigidity Factor, dr = 0.80
Corrected settlement for raft foundation = 44.87 mm
Total Settlement of Foundation = 92.54
Tolerable Total Settlement : = 50
Hence for 50 mm permissible settlement, net API = 1.06 Kg /cm2
= 10.58 T/m2
RECOMMENDATION:
LEAST FROM ABOVE VALUES OF NET SBC OBTAINED FROM SHEAR FAILURE CRITERIA AND
SETTLEMENT FAILURE CRITERIA i.e. 10.58 T/m2 FOR 50 MM SETTLEMENT MAY BE ADOPTED FOR
DESIGN PURPOSES
24
SAMPLE CALCULATION
= 34.15 t/m2
2. Local Shear Failure :-
Qns = [2/3 cNc.sc.dc.ic+ p (Nq-1).sq.dq.iq+0.5 yb. B.Ny.Sy.dy.iy.w’]/2.5
= 14.63 t/m2
Interpolate between General Shear Failure and Local Shear Failure
Intrepolation Factor - I = 0.11
Intrepolation = 16.68
The Net Safe Bearing Capacity = 16.68 t/m2
25
1.0 SETTLE MENT CRITERIA (IS:8009, Part - I)
a. Consolidation Settlement 0.0 - 5.5 meter) 5.50
Cc Po + ∆P
sc = -----------. H. log10. ------------- ……………. (II)
1 + eo Po
3
H = 5.50 Cc = 0.138 e0 = 0.729 Saturated density = 1.77 t/m
2
P0 = 10.18 ∆P = 8.761528 t/m
Consolidation settlement of this layer 1 = 0.118 m
Corrected settlement for raft foundation = 80.51 mm
Seat of Settlement = 49.20 mm
b. Settlement in sand (Layer ) 5.50 - 9.0 meter) 3.50
Corrected Average N value = 18
Applied pressure 1.67 kg/cm2
The settlement for cohesion less soil are computed from Chart N vs settlement given on page 17 of IS: 8009 (Part I –
Reaffirmed -1998)
Settlement at a load of 1.0 Kg /cm2 = 17.5 0.5 34.92773
Settlement at a load of 1.67 Kg /cm2 = 58.3
Fox's Depth Factor = 0.85
Rigidity Factor, dr = 0.80
Corrected settlement for raft foundation = 39.62 mm
Total Settlement of Foundation = 88.82
Tolerable Total Settlement : = 50
Hence for 50 mm permissible settlement, net API = 0.94 Kg /cm2
= 9.39 T/m2
RECOMMENDATION:
LEAST FROM ABOVE VALUES OF NET SBC OBTAINED FROM SHEAR FAILURE CRITERIA AND
SETTLEMENT FAILURE CRITERIA i.e. 9.39 T/m2 FOR 50 MM SETTLEMENT MAY BE ADOPTED FOR
DESIGN PURPOSES
26
SAMPLE CALCULATION
= 41.16 t/m2
2. Local Shear Failure :-
Qns = [2/3 cNc.sc.dc.ic+ p (Nq-1).sq.dq.iq+0.5 yb. B.Ny.Sy.dy.iy.w’]/2.5
= 17.71 t/m2
Interpolate between General Shear Failure and Local Shear Failure
Intrepolation Factor - I = 0.11
Intrepolation = 20.17
The Net Safe Bearing Capacity = 20.17 t/m2
27
1.0 SETTLE MENT CRITERIA (IS:8009, Part - I)
a. Consolidation Settlement 0.0 - 5.5 meter) 5.50
Cc Po + ∆P
sc = -----------. H. log10. ------------- ……………. (II)
1 + eo Po
3
H = 5.50 Cc = 0.138 e0 = 0.729 Saturated density = 1.77 t/m
2
P0 = 11.95 ∆P = 10.59301 t/m
Consolidation settlement of this layer 1 = 0.121 m
Corrected settlement for raft foundation = 79.39 mm
Seat of Settlement = 48.52 mm
b. Settlement in sand (Layer ) 5.50 - 9.0 meter) 3.50
Corrected Average N value = 18
Applied pressure 2.02 kg/cm2
The settlement for cohesion less soil are computed from Chart N vs settlement given on page 17 of IS: 8009 (Part I –
Reaffirmed -1998)
Settlement at a load of 1.0 Kg /cm2 = 17.5 0.5 34.92773
Settlement at a load of 2.02 Kg /cm2 = 70.4
Fox's Depth Factor = 0.82
Rigidity Factor, dr = 0.80
Corrected settlement for raft foundation = 46.21 mm
Total Settlement of Foundation = 94.73
Tolerable Total Settlement : = 50
Hence for 50 mm permissible settlement, net API = 1.06 Kg /cm2
= 10.65 T/m2
RECOMMENDATION:
LEAST FROM ABOVE VALUES OF NET SBC OBTAINED FROM SHEAR FAILURE CRITERIA AND
SETTLEMENT FAILURE CRITERIA i.e. 10.65 T/m2 FOR 50 MM SETTLEMENT MAY BE ADOPTED FOR
DESIGN PURPOSES
28