Part2 Overhead Network Grounding PDF
Part2 Overhead Network Grounding PDF
Part2 Overhead Network Grounding PDF
SDCS-03
CONSTRUCTION STANDARD
(PART-II)
OVERHEAD NETWORK
GROUNDING
Rev. 01
TABLE OF CONTENTS
1.0 General 3
Figures 10-18
Page 2 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
1.0 GENERAL:
1.1 Scope:
This Grounding Standard describes the technical requirements for grounding the
SEC overhead Distribution Network installations.
SEC Distribution System extends from the MV (33 kV, 13.8 kV) feeder outlets of
HV/MV Substations down to SEC Customer interface including KWH-Meters and
meter boxes.
1.2 Objective:
Page 3 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
These are 3-wire primary systems run on steel poles. MV neutral of power
transformers is grounded solidly or thru low resistance at HV /MV substations.
b) LV System
It is a 4-wire system and system neutral is multiply grounded at each pole and at
consumer location.
For MV lines, the metal work of all overhead line distribution equipment is always
grounded and bonded to continuous run ground wire. For LV lines, metal work
shall be bonded to the neutral and grounded at each pole.
Below mentioned grounding methods and materials shall be used for all system
configurations.
1.5.1 Grounding and Bonding Materials:
ACSR conductor Quail (67.44 mm2) shall be used as continuous running ground
wire for MV lines. 16 mm (5/8 inch) diameter and 1x2400 mm long or 2x1200 mm
copper weld ground rods with 70 mm2 (for MV Grounding) and 35 mm2 (for LV
grounding) bare copper conductor shall be used for grounding applications.
Materials are described in respective figures of this Construction Standard.
Page 4 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
Where it is very difficult to drive the standard ground rod in soil, Copper wire
buried horizontally to a depth of at least 500 mm is considered equivalent to
placing ground rods (6m of wire length equivalent to one rod). This length is in
addition to the connecting length of wire between ground rods and from pole to
ground rods. The ground wire should be so installed that as far as possible, it forms
a ground mat around the pole. Two ends of the wire must be connected to the pole
grounding terminals.
Before deciding to install ground wire in place of ground rods it should be
investigated if normal (non rocky) soil is available within a reasonable distance
(up to 50 meters) from the installation. If available the required number of ground
rods should be installed in the normal ground and connected to the pole grounding
terminals. The connecting ground wire from ground rods to the pole should form a
ground mat around the pole. Copper ground wire alone (in place of ground rods)
should be laid only if normal soil as described above is not available.
For increasing the effectiveness of grounding arrangement the adjacent grounding
rods should not be located closer than 4 meters. In case of difficult situation less
than four meters separation is acceptable. However the respective SEC
Construction Supervisor should satisfy himself that reduced separation is indeed
unavoidable.
In case 2400mm rods can not be used, single 1200mm ground rod can be used with
separation of 2m instead of 4 m.
To prevent overheating features of connections in the grounding systems, following
shall be observed:
Page 5 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
LV neutral ground and any grounds associated with MV equipment / system shall
always be kept bonded.
Soil resistivity can also be improved by adding the appropriate Low Resistivity
Materials (LRM) as described in SDCS-03 part 3.
All installations with Surge Arresters for protection of line equipment shall be
grounded through minimum four ground rods.
Maximum recommended ground resistance for different installations is as follows:
4.1 General:
Details of grounding arrangements for poles for overhead lines and the overhead
line equipment are given in respective figures as mentioned below.
4.2 Non plant poles with 33 kV & 13.8 kV, 3-Wire Circuits:
The circuit elements generally consist of the steel poles, pole top line metal work
consisting of cross arm and base metal work of insulators, which support
conductors energized to line voltage. Such poles do not support any "Equipment"
like cable riser, Transformer, Voltage Regulators etc.
Every fifth Pole of MV overhead line shall be grounded through single earth rod.
In case of less than five poles in a line, Tee-off and the Terminal Pole shall be
Page 6 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
Grounding arrangement for single and double pole mounted transformers is shown
in Fig. 2 to Fig. 5. The PMT body shall be grounded through four (4) earth rods and
70 mm2 bare copper conductor. Neutral of transformer is grounded by bonding
neutral bus bar inside LV cabinet with the body through a 70mm2 copper link. MV
& LV ground conductors shall be bonded to the continuous run ground wire.
A ground mat shall be provided under the LV cabinet.
4.4 Pole Mounted Equipment with Control Cabinets or Switch operating handle
The equipment such as Line Auto Reclosers, Line Sectionalizers and Load Break
Switches which have their operating handle or control cabinet near the ground level
shall be grounded as per Fig. 6 and Fig. 7 and bonded with continuous ground wire.
A ground mat shall be provided under the switch operating handle/ control cabinet
to establish an equipotential zone.
The grounding arrangement for power capacitor shall be as per Fig. 8. Grounding
shall be through four (4) ground rods and 70mm² bare copper conductor.
Grounding of cable riser shall be as per Figure 9. Grounding shall be through Four
(4) ground rods and 70 mm 2 bare copper conductor. Cable screens, armor and pole
top metal work shall be bonded to ground wire.
The pole top connection of guys, on all steel poles, already has a bond with ground
through metal work and continuous running ground wire.
Page 7 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
5.1 General:
These networks are designed for use in the places with short of space and where the
customers are located adjacent to MV overhead lines. The steel poles carry both
MV conductor on post insulators and LV Quadruplex conductor.
All metal work is bonded together, and to the continuously running ground wire In
case of less than five poles in a line, Tee-off and the Terminal Pole shall be
grounded. For the lines with five or more poles, the grounding shall be carried out
according to clause 4.0.
c- One rod shall be driven at the meter position for every 4 KWH meters
served directly from a pole which carry both MV and LV circuit.
d- Connection between the LV neutral conductor and the grounding conductors
shall be as shown in Overhead Construction Standards SDCS-01.
e- The grounding conductor shall be 35 mm².
Page 8 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
6.1 General:
It shall be essential for the customer to provide grounding at his interface. The
customer shall bring the grounding wire to the grounding terminals of the meter
box. The ground wire of the customer shall be connected to the ground terminal
inside the meter box. The ground terminal shall be short linked with the neutral.
Page 9 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
Page 10 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
Page 11 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
Page 12 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
Page 13 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
Page 14 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
Page 15 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
Page 16 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
Page 17 of 18
Saudi Electricity Company اﻟﺸﺮآﺔ اﻟﺴﻌﻮدﻳﺔ ﻟﻠﻜﻬﺮﺑﺎء
SDCS-03 Part II Rev.01
SEC DISTRIBUTION CONSTRUCTION STANDARD
DATE: 12 September 2007G
Page 18 of 18