0% found this document useful (0 votes)
60 views8 pages

Setting and Configuration REQ650

Uploaded by

m yaqin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views8 pages

Setting and Configuration REQ650

Uploaded by

m yaqin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

JAKARTA, 15 JULY 2020

SETTING AND CONFIGURATION REQ650


BREAKER FAILURE PROTECTION
ID PGGA POWER GRIDS

© Copyright 2020 ABB. All rights reserved. Document ID.: Rev.:


Operation Principle

July 15, 2020 Slide 2


Typical Feature

Ø 1 ph and/or 3 ph starting
Ø Re-trip (i.e in first time delay
Ø Back-up trip/Bus trip (i.e second time delay)
Ø Correctly trip only to associated CBs via disconnector replica available inside the busbar differential protection

July 15, 2020 Slide 3



CSPRBRF
Breaker Failure Protection Phase Segregated Activation and Output

Ø Breaker failure protection, phase segregated activation and output CSPRBRF ensure fast backup tripping of surrounding breakers in
case of own breaker fail to open.
Ø CSPRBRF can be current base, contact based, or adaptive combination between this two principles.
Ø CSPRBRF can be programmed to give single- or three- phase re-trip of own breaker
Ø The breaker failure protection is initiated from protection trip command, either from protection function within the IED or from
external protection device

July 15, 2020 Slide 4


RetripMode vs FunctionMode

Ø Depedencies between parameters retrip mode and the


function mode

July 15, 2020 Slide 5


Breaker Failure Time Setting

Ø Breaker failure protection act as backup of other protection


Ø The total fault clearance time shall less than given critical time

July 15, 2020 Slide 6


Setting Parameters

Ø IP>: Current level of breaker failure detection, set in % of Ibase


Ø T1: Time delay of retrip
Ø T2: Time delay of backup trip

July 15, 2020 Slide 7