0% found this document useful (0 votes)
226 views7 pages

PRJ Pinto 5

This document contains a series of questions related to earned value management. It provides earned value tables for two projects, Project Makeready and an unnamed project, and asks questions about calculating values like estimated cost to completion, schedule and cost variances, and schedule performance index based on the data in the tables. It also contains questions about different rules that can be used to determine percentage of completion like the 0/100 rule.

Uploaded by

faheem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
226 views7 pages

PRJ Pinto 5

This document contains a series of questions related to earned value management. It provides earned value tables for two projects, Project Makeready and an unnamed project, and asks questions about calculating values like estimated cost to completion, schedule and cost variances, and schedule performance index based on the data in the tables. It also contains questions about different rules that can be used to determine percentage of completion like the 0/100 rule.

Uploaded by

faheem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

59) Use the earned value table to determine the estimated cost to completion given the indicated

state of the project.

%
Activity 5 10 15 20 25 30 35 Plan Complete
A 850 350 1,200 100%
B 400 125 525 100%
C 1,275 650 1,925 100%
D 2800 4,500 350 7,650 95%
E 680 400 1,080 75%
F 125 875 1,000 80%
G 300 1200 1,500 45%
Monthly Plan 850 750 1,400 3,450 5,180 1,175 2,075 14,880
Monthly Act 900 650 1,350 3,875 4,780 850 2,000
A) $15,966
B) $16,235
C) $18,164
D) $17,441
Answer: B
Diff: 2
Section: 13.3 Earned Value Management
LO: 13.3 Understand how Earned Value Management can assist project tracking and evaluation.
Classification: Concept
AACSB: Analytical Thinking
60) Use the earned value table for Project Makeready to determine the earned value at week 49.

%
Activity 7 14 21 28 35 42 49 Plan Complete
Install fixtures 325 250 575 100%
Refinish floors 550 85 635 100%
Replace doors 350 275 625 100%
Complete tiling 1,200 565 1,765 80%
Install back door 875 225 1,100 70%
Landscaping 200 350 550 25%
Monthly Plan 325 800 435 1,475 1,440 425 350 5,250
Monthly Act 550 550 550 1,100 1,650 550 1,100
A) $4,950
B) $6,050
C) $4,155
D) $5,250
Answer: C
Diff: 2
Section: 13.3 Earned Value Management
LO: 13.3 Understand how Earned Value Management can assist project tracking and evaluation.
Classification: Critical Thinking
AACSB: Analytical Thinking
61) What is the cost variance of Project Makeready based on the data in the earned value table
shown below?

%
Activity 7 14 21 28 35 42 49 Plan Complete
Install fixtures 325 250 575 100%
Refinish floors 550 85 635 100%
Replace doors 350 275 625 100%
Complete tiling 1,200 565 1,765 80%
Install back door 875 225 1,100 70%
Landscaping 200 350 550 25%
Monthly Plan 325 800 435 1,475 1,440 425 350 5,250
Monthly Act 550 550 550 1,100 1,650 550 1,100
A) -$1,896
B) -$1,096
C) -$800
D) -$406
Answer: A
Diff: 2
Section: 13.3 Earned Value Management
LO: 13.3 Understand how Earned Value Management can assist project tracking and evaluation.
Classification: Critical Thinking
AACSB: Analytical Thinking
62) Use the earned value table for Project Makeready to determine the schedule variance.

%
Activity 7 14 21 28 35 42 49 Plan Complete
Install fixtures 325 250 575 100%
Refinish floors 550 85 635 100%
Replace doors 350 275 625 100%
Complete tiling 1,200 565 1,765 80%
Install back door 875 225 1,100 70%
Landscaping 200 350 550 25%
Monthly Plan 325 800 435 1,475 1,440 425 350 5,250
Monthly Act 550 550 550 1,100 1,650 550 1,100
A) -$1,896
B) -$1,096
C) -$800
D) -$206
Answer: B
Diff: 2
Section: 13.3 Earned Value Management
LO: 13.3 Understand how Earned Value Management can assist project tracking and evaluation.
Classification: Critical Thinking
AACSB: Analytical Thinking
63) Use the earned value table for Project Makeready to calculate their schedule performance
index.

%
Activity 7 14 21 28 35 42 49 Plan Complete
Install fixtures 325 250 575 100%
Refinish floors 550 85 635 100%
Replace doors 350 275 625 100%
Complete tiling 1,200 565 1,765 80%
Install back door 875 225 1,100 70%
Landscaping 200 350 550 25%
Monthly Plan 325 800 435 1,475 1,440 425 350 5,250
Monthly Act 550 550 550 1,100 1,650 550 1,100
A) 1.46
B) 0.68
C) 0.79
D) 1.26
Answer: C
Diff: 2
Section: 13.3 Earned Value Management
LO: 13.3 Understand how Earned Value Management can assist project tracking and evaluation.
Classification: Critical Thinking
AACSB: Analytical Thinking
64) Use the earned value table for Project Makeready to calculate the estimated cost to
completion.

%
Activity 7 14 21 28 35 42 49 Plan Complete
Install fixtures 325 250 575 100%
Refinish floors 550 85 635 100%
Replace doors 350 275 625 100%
Complete tiling 1,200 565 1,765 80%
Install back door 875 225 1,100 70%
Landscaping 200 350 550 25%
Monthly Plan 325 800 435 1,475 1,440 425 350 5,250
Monthly Act 550 550 550 1,100 1,650 550 1,100
A) $4,285
B) $5,250
C) $6,050
D) $7,645
Answer: D
Diff: 2
Section: 13.3 Earned Value Management
LO: 13.3 Understand how Earned Value Management can assist project tracking and evaluation.
Classification: Critical Thinking
AACSB: Analytical Thinking

65) If an activity's progress is defined as 0% until the activity is complete, the project manager is
using:
A) The 50/50 rule.
B) The all or nothing rule.
C) The 0/100 rule.
D) The Do Not Pass Go rule.
Answer: C
Diff: 1
Section: 13.5 Issues in the Effective Use of Earned Value Management
LO: 13.3 Understand how Earned Value Management can assist project tracking and evaluation.
Classification: Concept
AACSB: Application of Knowledge
66) Once an activity is begun, it is assumed to be half done under the:
A) "Once begun, half done" rule.
B) Minimal effort rule.
C) Midway rule.
D) 50/50 rule.
Answer: D
Diff: 1
Section: 13.5 Issues in the Effective Use of Earned Value Management
LO: 13.3 Understand how Earned Value Management can assist project tracking and evaluation.
Classification: Concept
AACSB: Application of Knowledge

67) Each activity contained a series of milestones that represented a previously agreed-upon
amount of work. Once the low graffiti was erased, 35% of the activity had been completed and
once the mid-level graffiti was erased, 70% of the activity had been completed. This project
manager was clearly in the:
A) Percentage complete camp.
B) Micromanagement camp.
C) 35/70 camp.
D) 3K specifications camp.
Answer: A
Diff: 1
Section: 13.5 Issues in the Effective Use of Earned Value Management
LO: 13.3 Understand how Earned Value Management can assist project tracking and evaluation.
Classification: Critical Thinking
AACSB: Analytical Thinking

68) Very short work packages would be better managed by:


A) The percentage complete rule.
B) The 0/100 rule.
C) The caveat emptor rule.
D) The prior knowledge rule.
Answer: B
Diff: 2
Section: 13.5 Issues in the Effective Use of Earned Value Management
LO: 13.3 Understand how Earned Value Management can assist project tracking and evaluation.
Classification: Critical Thinking
AACSB: Analytical Thinking

You might also like