Status of Civil Works
Status of Civil Works
Status of Civil Works
PHASE:01
As per the discussion with President (Perumbalam GP) & other CFLTC team members on 25/07/20, following
works are included in the first phase at GHSS Perumbalam. And the total cost of phase-1 comes to Rs. 278000/-
including GST. The estimate is prepared as per CPWD DAR-2016.
PHASE:02
Renovation of LP School is included in phase-2. Cost for Renovation comes to Rs. 100000/- including GST. But it
need approval from the concerned CFLTC team members.
**Note:
1. Missing works if any shall be included in Phase-2. But it need approval from concerned CFLTC
members.
2. Since the work is of emergency nature as well as there is no project & TS, Valuation certificate will be
issued only at the time of completion.
Assistant Engineer
LID & EW SECTION PERUMBALAM