EIS (Review Report)
EIS (Review Report)
EIS (Review Report)
SUPPLEMENTAL ENVIRONMENTAL
IMPACT STATEMENT
IN ACCORDANCE WITH
JICA GUIDELINES FOR ENVIRONMENTAL AND
SOCIAL CONSIDERATIONS
OCTOBER 2011
PHASE IV
(Improvement of Upper Marikina
River & Construction of MCGS)
CHAPTER 1 INTRODUCTION…………………………………………………… 1
1.1 Purpose of Review and Supplemental Study…………..……………………… 1
1.2 Scope of Work…………………………………………………………………. 1
1.3 General Description of the Project…………………………………………….. 1
i
4.4.10 Important Social Bounding and Places……………………………….. 41
4.4.11 Health…………………………………………………………………. 42
4.4.12 Religion and Indigenous Belief……………………………………….. 43
4.4.13 Heritage……………………………………………………………….. 43
4.4.14 Gender………………………………………………………………… 44
4.4.15 Ethnic Minority and Indigenous People (IP)…………………………. 44
4.4.16 Awareness of Phase III………………………………………………... 44
ANNEX
ii
ANNEX-3 : Scoping Matrix of EIS(1998)
ANNEX-4 : Public Hearings/Consultations
LIST OF TABLES
iii
LIST OF FIGURES
iv
ABBREVIATIONS
v
NAPC - National Anti-Poverty Commission
NCIP - National Commission of Indigenous People
NCR - National Capital Region
NEPC - National Environmental Protection Council
NGO - Non-Government Organization
NIPAS - National Integrated Protected Area
NO2 - Nitrogen Dioxide
NO3 - Nitrate
NPCC - National Pollution Control Commission
NTU - Nephelometric Turbidity Unit
PAF - Project Affected Families
PAP Project Affected People/Person
Pb - Lead
PD - Presidential Decree
PDR - Project Description Report
PEISS - Philippine Environmental Impact Statement System
PM10 - Particulate matter with diameter of not less than 10 microns
PMO-MFCP I - Project Management Office for Major Flood Control I
PMRIP - Pasig-Marikina River Channel Improvement Project
PO4 - Phosphate
PRRC - Pasig River Rehabilitation Commission
RA - Republic Act
SAPROF - Special Assistance for Project Formation, JBIC
SO2 - Sulfur Dioxide
TC - Total Coliform
TDS - Total Dissolved Solids
TOR - Terms of Reference
TSP - Total Suspended Particulates
TSS - Total Suspended Solids
UP - University of the Philippines
µg/NCM - Micro gram per normal cubic meter
µS/cm - microsiemens per centimeter
MEASUREMENT UNITS
(Length) (Time)
mm : millimeter(s) s, sec : second(s)
cm : centimeter(s) min : minute(s)
m : meter(s) h, hr : hour(s)
km : kilometer(s) d, dy : day(s)
y, yr : year(s)
(Area)
mm2 : square millimeter(s) (Volume)
cm2 : square centimeter(s) cm3 : cubic centimeter(s)
m2 : square meter(s) m3 : cubic meter(s)
km2 : square kilometer(s) l, ltr : liter(s)
ha : hectare(s) mcm : million cubic meter(s)
(Weight) (Speed/Velocity)
g, gr : gram(s) cm/s : centimeter per second
kg : kilogram(s) m/s : meter per second
ton : ton(s) km/h : kilometer per hour
vi
CHAPTER 1 INTRODUCTION
1.1 Purpose of Review and Supplemental Study
Environmental Impact Statement in June 1998 (hereafter “EIS(1998)”) and Environmental
Compliance Certificate (hereafter “ECC”) for the Pasig Marikina River Channel Improvement
Project (hereafter “the Project” or “PMRCIP”) are reviewed and supplemented to comply with
JICA Guidelines for Environmental and Social Considerations (revised in April 2010 and
hereafter “JICA Guidelines”) for the proposed implementation of Phase III of the PMRCIP.
1.2 Scope of Work
The EIS(1998) and ECC are reviewed and primary supplemental baseline study is performed in
the JICA Preparatory Study for the Phase III of the Project. The review and supplemental study
is conducted focusing on following:
(1) Validity of ECC,
(2) Compatibility of the EIS(1998) with current Philippines’ regulatory requirements,
(3) Compatibility of the EIS(1998) with JICA Guidelines,
(4) Validity of primarily appropriateness of the EIS(1998) for the Phase III, and
(5) Providing supplemental information in accordance with JICA Guidelines for
EIS(1998), if necessary, for implementation of Phase III:
Baseline status of environment and society of concerned area
Philippines’ legal and policy framework
Environmental impact assessment
Alternatives
Mitigation measures
Environmental monitoring plan
Financial arrangement
1
Drainage Project in Metro Manila”.
Based on the F/S, the “Pasig-Marikina River Channel Improvement Project” from river mouth
to Marikina Bridge (29.7 km long) is being proposed for the implementation in the following
four phases: Phase I (Detailed Design), Phase II (Channel Improvement of the Pasig River),
Phase III (Channel Improvement for the Lower Marikina River) and Phase IV (Channel
Improvement for the Upper Marikina River)
The Phase I of Detailed Design (D/D) was carried out from October 2000 to March 2002
through the Japanese ODA assistance. The Phase II has been requested for financing under the
26th JICA Yen Loan Package with STEP (Special Term Economic Partnership). The construction
of Phase II Project has commenced in July 2009 targeting the completion of the Project by June
2012.
Since the tremendous damages were brought to Metro Manila by Tropical Storm ‘Ondoy’ in
September 2009, it is urgently required to complete the whole scheme of the PMRCIP to protect
Metro Manila against the further flood disaster. Following the ongoing Phase II, it is proposed
to implement the Phase III which is the Lower Marikina River Channel Improvement Works in
total of 5.4 km upstream from the junction with the Pasig River. Also, heavily deteriorated bank
sections in the Pasig River due to the recent floods including ‘Ondoy’ is proposed to be included
in the Phase III Project. These sections are not covered by the ongoing Phase II. Construction
area of Phase III Project is administratively in the cities of Manila, Mandaluyong, Makati and
Pasig in Metro Manila.
Major works of the Phase III Project are summarized as follow:
(1) Construction of Revetments supported by Steel Sheet Piles and Reinforced Concrete
River Wall along the Pasig River (about 9.9 km long in total on both banks)
(2) Dredging of Lower Marikina River Channel (about 5.4 km long; 612,000 m3)
(3) Earth Dikes/Concrete River Walls along the Lower Marikina River (4 location; about
2.15 km long in total)
(4) Boundary Bank along Lower Marikina River (about 7.1 km in total)
(5) Bridge Pier Protection Work at 4 existing Bridges along Lower Marikina River (by
Stone Riprap)
The Pasig-Marikina River flows in the center of Metro Manila which is a capital of the Republic
of the Philippines. Both banks of the river channel are currently the urban area and occupied
with residential houses, factories, offices, roads, etc.
To increase the flow capacity of river channel for flood control, measures of widening,
deepening, heightening of river wall, short-cut of channel were alternatively studied. Among the
alternative measures, to avoid and minimize the social problem such as land acquisition and
resettlement, the adopted flood control measure is to rehabilitate/construct the river walls and
revetments on the existing river walls and to deepen the existing channel by dredging, without
land acquisition for widening the channel.
Moreover, to minimize the negative impacts during project construction, the access to the sites
and required works are planned to be basically done from the river channel using boats/barges.
2
CHAPTER 2 REVIEW OF ECC AND EIS(1998)
The following items which are thought to be important were not discussed in scoping
session of the EIS(1998):
i) Water-related diseases,
ii) Poor and indigenous peoples,
iii) Historical and religious sites,
iv) Gender and land use,
3
v) Loss of bond of community,
vi) Construction area safety,
vii) Conflict of interests,
viii) Inequity of wealth, and
ix) Accidents.
However, overall contents of the EIS(1998) were basically appropriated based on the JICA
Guidelines and the WB O.P.4.01. It is not necessary that the EIS(1998) be completely revised.
Features
16 Soil Erosion N/A N/A ○
17 Groundwater +/- N/A ○
18 Hydrological Situation N/A N/A ○
19 Coastal zone N/A N/A ○
20 Flora, Fauna and Biodiversity +/- N/A ○
21 Meteorology N/A N/A ○
4
22 Landscape Aesthetics: +/- N/A ○
23 Global Warming N/A N/A ○
24 Protected Area N/A N/A
25 Air Pollution +/- Yes ○ ※
26 Water Pollution +/- Yes ○ ※
27 Soil Contamination +/- N/A ○ ※
Pollution
5
and Mangahan Floodway). Through the scoping session, a scoping matrix was formed for
major concerns that were raised by the attendances.
As DAO 96-37 ordered, and as the DENR emphasized in the initial scoping meeting public
participation, obtaining full support from the public is very critical to carrying out the
Project successfully. However, names of Barangay captains and ordinary persons who live
in the areas where the Project takes place and might be relocated for the Project were not
listed on the attendance sheets.
Although two consultation meetings were held (which was the minimum number of
meetings required by the World Bank’s standard), none of them were about the EIS Final
Report.
(2) Scoping
Both the possible positive and negative significant environmental impacts were identified
through the scoping sessions. Agreed-upon items of concern with possible negative
impacts were (1) dredging activities, (2) construction of the river improvement works
along the banks (construction of revetments and river walls), (3) construction of the
MCGS, (4) operation of the MCGS, and (5) operation of the Rosario Weir.
(3) Information Disclosure
DAO 2003-30, Section 5.3 defines a public hearing as part of EIS review, i.e. information
disclosure. For those who did not participate in public hearings and scoping sessions,
DAO 97-24 assures the provision of “public access to all official data or information”.
However, the general public faces difficulty in accessing EIS Reports because DAO 97-24
Section 3.1.5 treats some of these reports as “Confidential” and forbids the their review.
There is weak evidence in the EIS(1998) regarding the social and environmental concern
were disclosed properly and adequately in accordance with JICA guidelines:
(1) An information dissemination meeting was held at the Bayview Hotel in Manila in
1998. Most of the people who attended the meeting were those of the government
agencies, LGUs, ADB, and SAPROF. No residents of areas affected by the project
were included.
(2) The EIS (1998) was written in English which is a official language of the Philippines.
Since most of the people living in the Project affected Area use either non-English
(52% Households in directly affected area use only Tagalog) or a mixture of some
English (48% use mixture of Tagalog or Filipino and non-standard English) with
native tongue, it is deemed to be not easily accessible to the information in the EIS.
6
The pollutants of most concern are BOD, Total Coliform, and Oil and Grease, which
are originated usually from daily-life living activities.
Pollution levels of the heavy metals in the river mostly equally distributed. Cadmium
and Chromium tend to exceed Class C water standard level.
(2) Social environment (Interview and Secondary Data)
Large numbers of Project Affected Peoples (PAPs) who are informal settlers and
needed to be relocated.
LGUs are not measuring up to their Land Use Plan (CLUP); uncontrolled land use is
still practiced. The land use plan is very incompatible and its execution is relaxed.
Pasig City, which is located along the lower Marikina River, is transitioning from a
manufacturing- and industry-oriented city to a commerce- and business-oriented city.
An insignificant amount of agricultural land and no fisheries exist in the project
affected area.
No PAPs depend their incomes and living on the river.
No socially, historically, culturally or religiously significant sites are located in the
project directly affected area.
No vulnerable indigenous people groups exist.
Most of residents in the project affected area along the Lower Marikina River are not
aware of Phase III Project.
Gender issues seem less likely to be caused by the construction work.
PAPs are less sick than the national average.
7
CHAPTER 3 CURRENT LEGAL FRAMEWORK FOR
ENVIRONMENTAL AND SOCIAL
CONSIDERATIONS IN THE
PHILIPPINES
3.1 Overall Legal Framework
In the Philippines, any private or public projects or activities which are envisaged to potentially
have a negative impact on the environment are subject to EIA by Philippine Environmental
Impact Statement System (PEISS). The EIA is the preliminary analysis of the potential
impacts of the project on the environment. Aware of the possible negative effects of the
implementation of industrial and other activities, the Philippine Government has instituted
measures to encourage the use of EIA as a planning and decision making tool.
PEISS is a set of laws, regulations, administrative orders and guidelines concerned with
Environmental Impact Assessment. The following are some of the most important of these laws
and guidelines:
Environmental Impact Statement System (EISS), Presidential Decree No. 1586 (1978):
An act establishing and centralizing the Environmental Impact Statement (EIS) System
under the National Environmental Protection Council (NEPC), which merged with the
National Pollution Control Commission (NPCC) in June 1987 to become the
Environmental Management Bureau (EMB).
Presidential Proclamation No. 2146 (1981) and No. 803 (1996): It proclaims
Environmentally Critical Projects (ECPs) to have significant impact on the quality of
environment and Environmentally Critical Areas (ECAs) as environmentally fragile
areas within the scope of the EIS System.
DAO 96-37 revised to become DAO 92-21: Devolved responsibility for EIS to the
EMB-Regional Office and further strengthened the PEISS. Placed emphasis on
promoting maximum public participation in EIA process to validate the social
acceptability of the Project.
DENR Administrative Order No. 30 Series of 2003 (DAO 03-30), Revised Procedural
Manual (2007): Provides for implementation of rules and regulations of Presidential
Decree No. 1586, establishing PEISS. Also, provided detailed definitions of technical
terms and detailed information regarding procedures, related laws and regulations.
3.2 Procedures
The procedures of EIA can be grouped into the following stages as shown in the following
diagram: (1) pre-study stage (screening and scoping), (2) EIA study stage and (3) post-study
stage (review, decision-making and monitoring).
8
Project
Pre-Study Stage
EIA Study Scoping
Change of
Public Involvement
Project Review and Evaluation of EIA
EIA Study Stage plan/ facilitated by DENR-EMB
Relocation
Legend:
Proponent driven
DENR-EMB driven
Proponent driven but the EIA process as
requirements are under the mandate of
other entities
Source: Revised Procedural Manual for DENR Administrative Order No. 30 Series of 2003 (DAO 03-30)(2007)
9
Table 3.1 Summary of Environmentally Critical Projects (ECPs)
Main Categories Sub Category
A. Golf Course Project Golf course projects/complex
B. Heavy Industries Iron and Steel Metals
Non-ferrous Metal Industries
Petroleum and Petrochemical Industries
Smelting Plants
C. Resource Extractive Fishery Projects (fishery-related dikes and fishpond development projects)
Industries Forestry Projects
Major mining and quarrying projects
D. Infrastructure Projects Major Dams
Major Reclamation Projects
Major Power Plants (Proc No. 2146 declared types: fossil-fueled, nuclear fueled,
hydroelectric or geothermal)
Source: Revised Procedural Manual for DENR Administrative Order No. 30 Series of 2003 (DAO 03-30)(2007)
10
The proposed Project belongs to the infrastructure category in the Table 3.1 (ECPs). However,
this Project is not included in the sub-category of Table 3.1. On the other hand, in Table 3.2 for
ECAs, this Project is included in Category F.
PROJECT
FINANCIAL AND HUMAN RESOURCE
PLANNING & POLICY RIVER BASIN PROJECT DESIGN & OPERATIONS & LEGISLATIVE ADMINISTRATIVE SPECIAL CONCERNS
LEGAL SERVICE MANAGEMENT DEVELOPMENT
STUDIES OFFICE CONTROL OFFICE PACKAGING SERVICE MANAGEMENT LIAISON OFFICE SERVICE OFFICE
SERVICE SERVICE
SERVICE
ECOSYSTEMS PROTECTED
FOREST LAND
RESEARCH AND AREAS AND
MANAGEMENT MANAGEMENT
DEVELOPMENT WILDLIFE
BUREAU BUREAU
BUREAU BUREAU
The DENR is the government entity which is designated to handle issues related to the
following five tasks as described in pertinent legislation:
Assure the availability and sustainability of the country's natural resources through
judicious use and systematic restoration or replacement, whenever possible;
Increase the productivity of natural resources in order to meet the demands for forest,
mineral, and land resources of a growing population;
Enhance the contribution of natural resources for achieving national economic and social
development;
Promote equitable access to natural resources by the different sectors of the population;
Conserve specific terrestrial and marine areas representative of the Philippine natural and
cultural heritage for present and future generations.
Under the framework of PEISS, the EMB is responsible for the issuance of decision making
documents such as Environmental Compliance Certificate (ECC), Certificate of Non-Coverage
(CNC) and Denial Letter. Also, the EMB Regional Offices in respective regions are primarily
responsible for the supervision of development projects and conducting consultation related to
such projects.
11
The following shows the organization chart of EBM:
Hazardous
Waste Cashier Section
Management EMB – Regional Offices
Section
The Pasig-Marikina River Channel Improvement Project which is not ECP but of ECA is
considered to be Group II. The Group II Project is required to submit the following documents
to the DENR-EMB:
Environmental Impact Statement (EIS),
Initial Environmental Examination Report (IEER),
Initial Environmental Examination Checklist (IEEC), and
12
Project Description Report (PDR).
All documents should be prepared by the project proponent and submitted to the EMB Central
Office or the Environmental Impact Assessment Division in respective EMB Regional Office.
The outcome of the EIA Process within PEISS administered by the DENR-EMB is the issuance
of decision documents. A decision document may either be an ECC, CNC or a Denial Letter,
described below. The PDR is important for some of the implementation of Group II and Group
III projects, which do not foresee adverse impact, to secure eventual issuance of a CNC.
(1) EIA Proponent
The proponent agency of this Project is the Department of Public Works and Highways
(DPWH). The DPWH has the responsibility for preparation and submission of the PEISS.
DPWH usually establishes a Project Management Office (PMO) prior to feasibility studies
and the PMO prepares the PEISS. Once the project execution starts, PMO has
responsibilities for implementation of environmental and social considerations such as land
acquisition and resettlement in cooperation with local government units. The Environmental
Social Services Office (ESSO), in the Development Planning Division of the DPWH, is
responsible for supporting and supervising preparation of PEISS.
(2) Environmental Compliance Certificate (ECC)
An ECC is issued as a certificate of Environmental Compliance Commitment, to which the
proponent conforms with after DENR-EMB explains the ECC conditions.
(3) Outline of Required Documents by PEISS
The following is the outline of the EIS according to Revised Procedural Manual of DENR
Administrative Order No. 30 Series of 2003:
13
4.1.4. Terrestrial Biology
4.2. The Water (Discuss only relevant modules)
4.2.1. Hydrology & Hydrogeology
4.2.2. Oceanography
4.2.3. Water Quality
4.2.4. Freshwater Biology
4.2.5. Marine Biology
4.3. The Air (Discuss only relevant modules)
4.3.1. Meteorology
4.3.2. Air Quality and Noise
4.4. The People
5. ENVIRONMENTAL RISK ASSESSMENT (WHEN APPLICABLE)
6. ENVIRONMENTAL MANAGEMENT PLAN
6.1. Impacts Management Plan
6.2. Social Development Framework
6.3. IEC Framework
6.4. Emergency Response Policy and Generic Guidelines
6.5. Abandonment /Decommissioning /Rehabilitation Policies and Generic Guidelines
6.6. Environmental Monitoring Plan
6.6.1. Self-Monitoring Plan
6.6.1. Multi-sectoral Monitoring Framework
6.6.1. Environmental Guarantee and Monitoring Fund Commitment
6.7. Institutional Plan for EMP Implementation
7. BIBLIOGRAPHY/REFERENCES
8. ANNEXES
8.1. Scoping Checklist
8.2. Original Sworn Accountability Statement of Proponent
8.3. Original Sworn Accountability Statement of Key EIS Consultants
8.4. Proof of Public Participation
8.5. Baseline Study Support Information
8.6. Impact Assessment and EMP Support Information
Source: Revised Procedural Manual for DENR Administrative Order No. 30 Series of 2003 (DAO 03-30)(2007)
14
(c) Participation of Indigenous Peoples for decision-making process
In 2006, NCIP Administrative Order No.1, namely, the Free and Prior Informed
Consent (FPIC) guidelines, was promulgated by the National Commission of
Indigenous People (NCIP). The objective of the guideline is to ensure genuine
participation of Indigenous Cultural Communities (ICC) and Indigenous Peoples (IPs)
in decision-making as well as to protect the rights of ICCs/IPs in the introduction and
implementation of activities that will impact upon their Ancestral Domains/Lands
(ADs/ALs).
Also, the guideline details the process for conducting Field Based Investigation (FBI)
and obtaining the Certification Precondition from the NCIP attesting that the
applicant has complied with the requirements for securing the affected ICC/IP’s
FCIP. It is required for the EIS (Environment Impact Statement)-based projects
which can affect the ADs to follow the FCIP procedures.
NCIP regional office is responsible for receiving applications for the issuance of
Certificate Precondition as well as implementing FBI and overseeing the process to
obtain the FPIC from the IPs/ICCs.
(5) Laws and Regulations Concerning Environmental Standards
(a) Environment Code (Presidential Decree No. 1152)
Known as the Philippine Environment Code, it launches a comprehensive program on
environmental protection and management. It also provides for air, water quality, land
use, natural resources and waste management for fisheries and aquatic resources;
wildlife; forestry and soil conservation; flood control and natural calamities; energy
development; conservation and utilization of surface and ground water and mineral
resources.
(b) Water Code (Presidential Decree No. 1067)
A decree instituting a water code which revises and consolidates the laws governing
the ownership, appropriation, utilization, exploitation, development, conservation and
protection of water resources.
(c) Clean Water Act (Republic Act 9275)
An Act which aims to protect the country’s water bodies from pollution from all
possible sources (industrial, commercial, agricultural and household activities). It
provides for a comprehensive and integrated strategy to prevent and minimize
pollution through a multi-sectoral and participatory approach involving all the
stakeholders.
(d) Clean Air Act of 1999 (Republic Act No. 8749)
An Act which lays down policies to prevent and control air pollution. The act sets
standards for exhaust emission from vehicles, manufacturing plants and so on. All
potential sources of air pollution must comply with the provisions of the Act. As
such, all emissions must be within the air quality standards set under the law. It also
imposes the appropriate punishments for violators of the law.
(e) Ecological Solid Waste Management Act (Republic Act No. 9003 in 2000)
An Act providing for an ecological solid waste management program, creating the
necessary institutional mechanisms and incentives, declaring certain acts prohibited,
providing penalties, and appropriating funds therefore, and for other purposes.
(f) Pollution Control Law (Presidential Decree No. 984)
An Act that serves as the foundation for managing industrial activities impacting air
and water quality. It empowers the DENR to impose ex-parte cease and desist orders
15
(CDO) on the grounds of immediate threat to life, public health, safety or welfare, or
to animal or plant life when wastes or discharges exceed the normal amounts.
(g) Forestry Reform Code (Presidential Decree No. 705)
The Forestry Reform Code of the Philippines recognizes that there is an urgent need
for proper classification, management and utilization of the lands of the public
domain to maximize their productivity to meet the demands of the increasing
population of the Philippines. It surmises that to achieve the above purpose, it is
necessary to reassess the multiple uses of forest lands and resources before allowing
any utilization to optimize the benefits that can be derived. It also emphasizes not
only the utilization, but even more so the protection, rehabilitation and development
of forest lands to ensure the continuity of their productive condition.
(h) National Integrated Protected Areas System (Republic Act No. 7586)
An Act that aims to protect and maintain the natural biological and physical
diversities of the environment, notably areas with biologically unique features to
sustain human life and development as well as plant and animal life. It establishes a
comprehensive system of integrated protected areas within the classification of
national parks as provided for in the Constitution to secure for the Filipino people of
present and future generations the perpetual existence of all native plants and animals.
It encompasses (1) outstandingly remarkable areas and biologically important public
lands that are habitations of rare and endangered species of plants and animals, (2)
bio-geographic zones and (3) related ecosystems, whether terrestrial, wetland or
marine.
(6) Laws and Regulations Concerning Solid Waste Management and Disposal
(a) Presidential Decrees (PD) No.825 (1975), PD No.856(1975), and PD No.1152
Presidential Decree (PD) No.825 (1975), PD No.856(1975), and PD No.1152 regulate
safe and responsible disposal of solid and liquid wastes, LGU’s responsibility on
waste management, and treatment methods.
(b) An Act to Control Toxic Substances and Hazardous and Nuclear Wastes,
Providing Penalties for Violations thereof , and for their Purposes, Republic Act
(RA) 6969 (1990)
(c) MMDA Regulation No.96-009 (August 22, 1996)
Prohibiting littering/dumping/throwing or garbage, rubbish or any kind of waste in
open or public places, and requiring all owners, lessees, occupants of residential,
commercial establishments, whether private or public to clean and maintain the
cleanliness of their frontage and immediate surroundings and providing penalties for
violation thereof.
(d) MMDA Regulation No.99-009 (August 22, 1999)
Amending MMDA Regulation No.96-009 in order to differentiate dumping from
littering to determine the appropriate imposable penalties thereof and address the
problem on how to immediately dispose the junk vehicles which have been causing
traffic congestion in many roads in the metropolis.
(e) DAO 36 Series of 2004 (DAO 04-36)
DAO 04-36 is a procedural manual of DAO 92-29, a comprehensive documentation
on the legal and technical requirements of hazardous waste management.
16
CHAPTER 4 SUPPLEMENTAL STUDY
4.1 Scope of Supplemental Study
Thirteen years have passed since the EIS(1998) was prepared. Hence the social and
environmental situations in location for the Phase III of the Project are naturally and socially
anticipated to change. Such changes might be or might be not affect appropriateness of the
environmental impacts and the Environmental Management Plan (EMP) developed in 1998.
In order to prepare the way for the next phase of the Project, the important social and
environmental criteria have to be identified and their integrity be confirmed according to JICA
Guidelines, which also refer to World Bank’s O.P. 4.01. Key points of the investigation are as
follows:
Focusing on areas directly impacted by construction works of Phase III, which may cause
some possible negative impacts.
Focusing on the current conditions of social and environmental criteria for which concern
should be given according to JICA Guidelines, and
Updating and adding some information that are used to measure social and environmental
impacts during the construction stage of Phase III.
4.2 Physical Environment
4.2.1 Area of Concern
Barangays that are facing directly to the Phase III area of the lower Marikina River are chosen
as a directly affected area by the Project. These Barangays are shown within the boundary line
in Figure 4.1.
17
For the Pasig River area, study and mitigation measures II has been undertaken under the
ongoing construction of Phase II by the DPWH, Consultant and Contractors. The compliance
with ECC for Phase II has been monitored and ensured by the established Multiparty
Monitoring Team (MMT).
The existing environmental sampling and monitoring locations, including air quality, noise and
vibration in the Phase II are shown in Figure 4.2 below:
Bamb
Napin Ilugin
18
Table 4.1 DENR National Ambient Air Quality Guideline for Criteria Pollutants
Short Term (a) Long Term (b)
Pollutant
g/Ncm ppm Ave. Time g/Ncm ppm Ave. Time
Suspended Particulate
Matter (e) -
230 (f) 24 hours 90 -- 1 year (c)
TSP
150 (g) 24 hours 60 -- 1 year (c)
PM -10
Sulfur Dioxide (S02)
180 0.07 24 hours 80 0.03 1 year
(e)
Nitrogen Dioxide
150 0.08 24 hours -- -- --
(N02)
Photochemical
140 0.07 1 hour -- -- --
Oxidants
60 0.03 8 hours -- -- --
As Ozone
35 mg/Ncm 30 1 hour -- -- --
Carbon Monoxide
10 mg/Ncm 9 8 hours -- -- --
Lead (d) 1.5 -- 3 mo. (d) 1.0 -- 1 year
(a) Maximum limits represented by (98%) values not to be exceeded more than once a year.
(b) Arithmetic Mean
(c) Annual Geometric Mean
(d) Evaluation of this guideline is carried out for 24- hours averaging time and averaged over three
moving calendar months.
(e) SO2 and Suspended Particulates are sampled once every 6-days when using the manual method
(f) With mass median diameter less than 25-50 m.
(g) With mass median less than 10 m.
N CR moni tori ng
700
s i tes
EDSA – NPO
600 East Ave.
Mandaluyong
500
Pasig
TPS (ug/NCM)
400 Pasay
Manila
300
Pha s eII s i tes
19
(2) Noise
According to 24-hour noise level monitoring of Phase II in nearby residential areas which are
the most affected, noise levels are not necessary highest during day time (7:00 am-17:00 pm)
when construction work takes place. This indicates that although construction contributes to
noise pollution to some degree, most of the noise is from non-construction related vehicles,
passing barges/ferries, and other day-to-day human activities. The following should be noted
with regard to noise pollution in affected residential areas:
(a) Piling activity causes most of the noise in the Project, around 97 dBA while it was 83
dBA before piling work started. Although the noise level increases, the piling lasts on
average for 10 minutes per piling work session, which is easily acceptable.
(b) Moreover, while it can be noted that Project construction may generate a considerable
level of noise, it is considered short-term and therefore minimal in magnitude.
(c) In addition, before starting of the Project construction, the nearby communities were
informed beforehand that such construction would be implemented. So far, no complaints
from the communities have been reported during Project construction.
100
Environmental
90
Standard * (Class
80 A**)
Noise level (dBA)
70
60
Date/Period of
50 Monitoring
40 Baseline Data***
30
20
Date/Period of
10 Monitoring Nov-
0 Dec 2009
21:00-5:00
21:00-5:00
21:00-5:00
21:00-5:00
5:00-7:00
7:00-17:00
17:00-21:00
5:00-7:00
7:00-17:00
17:00-21:00
5:00-7:00
7:00-17:00
17:00-21:00
5:00-7:00
7:00-17:00
17:00-21:00
Date/Period of
Monitoring June
Coast guard checking No. 361 Matienza Yanib Foundadtion Ojales Pharmacy - 8-10 and 28-30
point Street Nursery Coronado Street 2010
**Class A: a section or contiguous area which is primarily used for residential purposes.
20
Table 4.2 DENR Standards for Noise in General Areas (dBA)
CLASS
TIME
AA A B C D
Daytime (0700Hr-700Hr) 50 60 65 70 75
Evening (1700Hr-100Hr) 45 50 60 65 70
Nighttime
40 45 55 60 60
(2100Hr-500Hr)
Morning (0500Hr-700Hr) 45 50 60 65 70
Class AA – a section of contiguous area which requires quietness, such as areas within 100
meters from school sites, nursery schools, hospitals and special homes for the aged.
Class A – a section or contiguous area which is primarily used for residential purposes.
Class B – a section or contiguous area which is primarily a commercial area.
Class C – a section primarily zoned or used as light industrial area.
Class D – a section which is primarily reserved, zoned or used as a heavy industrial area
(3) Vibration
Vibration level caused by a Vibro-Hammer of Phase II ranges from 0.02 to 0.03 mm/sec within
3 meters of the equipment. This is less than 2.5mm/sec applied in Phase II Project which is the
limit that would affect properties. Hence the equipment least likely causes vibration hazardous
to the residents in the concerned area.
4.2.3 Water Resources
The Pasig-Marikina River originates at the Southern Sierra Madre Mountain, running thru the
Luzon Central Plain to Manila Bay. The Napindan River is one of seven major rivers supplying
freshwater to Manila Bay from Laguna Lake (Laguna de Bay) through the Pasig River.
Although the Pasig-Marikina River is classified as Class C, the water quality and their
environment were declared as “biologically not active” in the 1990’s.
4.2.4 Water Quality
Overall water quality is better upstream of Marikina River at Marikina Bridge sampling station.
BOD, COD, TSS, Nitrates, Phosphates, Total Coliform, and Cadmium show a similar trend:
they start with lower levels at Marikina Bridge, then increase toward Vargas Bridge of Lower
Marikina River after merging with highly concentrated water from Buayang Bao creek water.
The trend more or less remains steady from Guadalupe Ferry Station to Havana Bridge in the
Pasig River, and then, after joining the San Juan River, it decreases toward Manila Bay. The
reverse trend is observed for DO. Almost all parameters for all sampling locations do not satisfy
Class C water quality criteria. Oil, Grease and Heavy Metals (except cadmium) do not display a
clear trend.
(1) BOD and DO
The trend of Biological Oxygen Demand (BOD) loading has been rising from 1998 to
2008. Since 2002, BOD levels at most monitoring stations have been exceeding
7mg/L—the Class C river water standard. BOD is low at Marikina Bridge (upstream of the
Marikina River) and higher downstream of Havana Bridge—toward Manila Bay (the river
mouth of the Pasig-Marikina River).
The Dissolved Oxygen (DO) level trend is decreasing to below 5mg/L, which is below the
Class C river water standard. DO level at Marikina Bridge is generally best of all the
stations. DO tends to be high at Marikina Bridge, and it drops when moving downstream
of Havana Bridge, then increases again when moving toward Manila Bay.
21
(2) Nutrient Salts
Both Nitrate (NO3) and Phosphate (PO4) do not satisfy water quality criteria for Class C
level. Nitrate level fluctuates within the 5mg/L range below and above the Class-C level
of 10mg/L throughout the rivers. There is no distinguishing difference throughout the
Pasig-Marikina River. On the other hand, there is a higher concentration of phosphate
between the Guadalupe Bridge and Havana Bridge in the Pasig River and also in the flow
from the San Juan River.
(3) TSS and COD
Both Total Suspended Solids (TSS) and Chemical Oxygen Demand (COD) do not satisfy
water quality criteria for Class C. General trends of TSS and COD are low in Marikina
Bridge, increasing toward Guadalupe Bridge, and mostly leveling out until they finally taper
out toward Manila Bay. TSS level is mostly above Class C standard of 30mg/L.
(4) Oil and Grease; Total Conliform
Both Oil and Grease and Total Coliform (TC) do not satisfy River water quality for Class
C. The standard for Oil and Grease is 2mg/l and TC is 5,000 MPN/100ml. There is no
trend for Oil and Grease, these fluctuate between 1 and 5 mg/L, mostly above Class C
level (2mg/L). Total Coliform is mostly between 5000 and 1.36x1010 MPN/100ml, with a
trend increasing toward Guadalupe Bridge then tapering off toward Manila Bay.
(5) Heavy Metals
Chromium (Cr), lead (Pb), and mercury (Hg) do not have a clear trend, but are equally
dispersed throughout the Pasig-Marikina River. Cr is between diction limit to 0.5mg/L but
mostly greater than 0.05mg/L (Class-C std). Pb and Hg clear Class-C std levels of 0.05 and
0.0005mg/L respectively. Cd levels increase toward the Manila Bay, between 0.01 and
0.02mg/L, mostly around Class-C level of 0.01mg/L.
22
DO (1999-2008) BOD (1999-2008)
7 25
6
20
Class C
5
STD: 5mg/L
4 15
mg/L
mg/L
3
10
2
5
1 Class C
STD: 7mg/L
0 0
1998 2000 2002 2004 2006 2008 1998 2000 2002 2004 2006 2008
Year Year
0 0
. 0
1 9 9 8 1 9 9 9 2 0 0 0 2 0 0 1 2 0 0 2 2 0 0 3 2 0 0 4 2 0 0 5 2 0 0 6 2 0 0 7 2 0 0 8 2 0 0 9
River flow direction: Up-stream/Marikina River Pasig River toward Manila Bay
DO (2009-2010)
DO (2009 10) BODBOD
(2009-2010)
(2009 10)
10 150
mg/L
100
mg/L
50
0 0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 0 1 2 3 4 5 6 7 8 9 10 11 12 13
1 2 3 4 5 6 7 8 9 10 11 12
Legend
Guadalupe Ferry Station
Nagtahan Bridge
Guadalupe Viejo
Marikina Bridge
Sevilla Bridge
Jones Bridge
Manila Bay
23
NO3 (2009-2010) PO4 (2009-2010)
12
25
10
20
8
15
mg/L
mg/L
6
10
4
5
2
0 0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 0 1 2 3 4 5 6 7 8 9 10 11 12 13
150
600
mg/L
mg/L
100
300
50
0 0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 0 1 2 3 4 5 6 7 8 9 10 11 12 13
4
1.E+09
MPN/100ml
3
mg/L
1.E+06
2
1.E+03
1
0 1.E+00
0 1 2 3 4 5 6 7 8 9 10 11 12 13 0 1 2 3 4 5 6 7 8 9 10 11 12 13
1 2 3 4 5 6 7 8 9 10 11 12
Legend
Guadalupe Ferry Station
Nagtahan Bridge
Guadalupe Viejo
Marikina Bridge
Sevilla Bridge
Jones Bridge
Manila Bay
Figure 4.6 Water Quality(NO3, PO4, TSS, COD, Oil and Grease, Total Coliform)
24
Chromium (2009-2010) Lead (2009-2010)
0.5 0.4
0.4
0.3
0.3
mg/L
mg/L
0.2
0.2
0.1
0.1
0.0 0.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 0 1 2 3 4 5 6 7 8 9 10 11 12 13
0.02
mg/L
0.0005
0.01
0 0.00
0 1 2 3 4 5 6 7 8 9 10 11 12 13 0 1 2 3 4 5 6 7 8 9 10 11 12 13
1 2 3 4 5 6 7 8 9 10 11 12
Legend
Guadalupe Ferry Station
Nagtahan Bridge
Guadalupe Viejo
Marikina Bridge
Sevilla Bridge
Jones Bridge
Manila Bay
25
4.2.5 Watershed
The cities located along the Pasig-Marikina River belong to the Pasig-Marikina River Basin,
which is a sub-basin of the Laguna Lake Watershed, connecting with the existing Mangahan
Floodway. The cities’ political/administrative boundaries do not match with those of the
watershed. The following table shows area coverage of the Pasig-Marikina River Basin.
Table 4.3 Pasig-Marikina River Basin
City/Municipality Total administrative Area within the Marikina Administrative area
land area (km2) River Basin (km2) in the basin (%)
Marikina City 23.48 23.48 100
Pasig City 33.77 8.90 26.35
Quezon City 129.84 33.05 25.45
Mandaluyong City 11.3 0.51 4.51
San Jose Del Monte 115.77 11.08 9.57
Rodriguez 360.55 218.58 60.62
Antepolo 293.49 206.52 70.36
San Mateo 53.74 53.74 100
Source: Sewerage Master Plan and Feasibility Study for the Marikina River Basin, (2008) Manila Water
Company Inc.
26
4.2.7 Sediment
(1) Sediment Quality
The Pasig River Rehabilitation Commission (PRRC) and Phase I (in 2001 in the Detailed
Design) of this Project have been monitoring the Pasig-Marikina River sediment quality. Since
two different testing methods, TCLP and Elutriate Test, were used, data obtained from the
monitoring are discussed separately.
(a) Sediment Quality by TCLP
Table 4.4 Inorganic Chemicals in Sediments (mg/kg-dry weight)
Sampling Sampling Cadmium Chromium Copper Lead Mercury Nickel Zinc
Location Date (MDL1=0.9) (LOQ2=20) (LOQ=0.2),
(Bridge) (MDL=0.04)
Marikina 08/06/09 <MDL 42 101 12.5 <MDL 33.5 185
12/11/09 <MDL 35.5 99 19.85 0.055 32 195
Rosario 2001 0.55 (1.11*) 75.57 14.88 <0.003 99.45
(Lower
Marikina)
Marikina River
27
The placement of sampling stations runs from Marikina Bridge crossing upper Marikina
River, located in the 30 km upstream from the river mouth, to Vargas Bridge in the lower
Marikina River and toward Laguna Lake through the Napindan River. Bambang Bridge
and Ilugin Bridge are located in Napindan River, which connects to Laguna Lake. Their
locations are shown in Figure 4.8.
Vargas also shows high lead values after Bambang. However, these values are
less than the target value of the Netherlands, i.e. environmentally safe.
Levels of cadmium are at a safe level in the lower Marikina River according to
various reference values (with the exception of the target value employed by the
Netherlands).
Marikina Bridge
Rosario Bridge
Alfonso Bridge
Vargas Bridge
Ilugin Bridge
Napindan Gate Bambang Bridge
28
Netherlands, but this chromium level is not recommended for agricultural and
residential use in Canada.
Copper in the lower Marikina River is at an environmentally safe level according
to standard of Washington State but does not conform to the Target Value of the
Netherlands.
Lead in the lower Marikina River is at an environmentally safe level according to
all the reference values.
Mercury in the lower Marikina River is at an environmentally safe level
according to all the reference values.
Nickel and Zinc in the lower Marikina River are at an environmentally safe level according
to all the reference values, but not conformed with the Target Value of the Netherlands.
Chromium, copper, mercury, nickel, and zinc are highest in sediment samples taken at
Vargas Bridge in the lower Marikina River. However, these values are lower than reference
values such as natural sediment quality of State of Washington and mostly satisfy
environment values used by Canada and the Netherlands.
Hence, according to this method, TCLP, it can be said that disposal of dredged materials is
less likely to cause contamination of surfaces and groundwater via the leaching process if
sediment quality is equal to or less than reported levels.
TCLP (Toxicity Characteristic Leaching Procedure) is recommended by the DENR. TCLP
is sometimes conducted to determine the leaching potential of sediments under more severe
conditions to measure an effect of dredging action. Test Methods for Evaluating Solid
Waste (SW-846) Method 1311 (US EPA, 2009) are used.
Elutriate Test method was developed by the U.S. Army Corps of Engineers to simulate a
condition that occurs during a dredging operation. An amount of chemicals that is
absorbed to sediment and that may reabsorb into the water column under normal pH is
estimated. When dredging effects are a study objective, elutriate analysis should be
included in the test design.
29
4.2.8 Wastes
Social survey conducted in the JICA Preparatory Study shows that 84% of households answered
that their wastewater is going to collection pipes that are connected to a city sewer. However,
there are very few sewer collection systems; as of 2006 only 8% of people were served by
sewerage systems in Pasig City, while the percentages of people served in Quezon and Makati
cities were 20% and 25% respectively. Marikina city and Pateros municipality are not connected
to a sewer system at all. Also, during the field investigation in JICA study it was observed that
raw wastewater is discharged into the river from most of houses located on the river banks.
Social survey results show that 94% of households’ garbage is collected and disposed of by a
regular garbage collection system. About 5% burn their garbage and another 5 % discard
garbage into the river or open spaces intentionally. Safe and sanitarily solid waste disposal sites
do not exist in Pasig city. In Quezon city there is an open dumping site located in Payatas in
close vicinity to La Mesa dam, which is a source of drinking water to Metro Manila.
Cities encourage their citizens to separate recyclable and reusable materials from other garbage.
The garbage is collected by LGUs and private garbage collectors. Industrial hazardous and toxic
materials must be separated and safely disposed of by licensed contractors (DAO92-29,
DAO2004-36). Although there are many “recycle centers” that collect and process usable
“recyclable materials,” these are more like conventional “junk shops” and are not capable of
treating complex, highly toxic, and mixed hazardous wastes such as industrial wastes. As of
2002, only three (3) hazardous waste treatment facilities that are equipped with appropriate
technologies and skilled workers were identified. Hence, it can be said that some of the
wastewater from the Pasig and Quezon cities are still discharged into the river one way or
another and that this discharge is the major source of river water and sediment pollution.
4.2.9 Protected Area
Republic Act No, 7586, titled the National Integrated Protected Areas System (NIPAS) Act,
prescribes the following eight (8) categories of protected areas: (1) strict nature reserve, (2)
natural park, (3) natural monument, (4) wildlife sanctuary, (5) protected landscapes and
seascapes, (6) resource reserve, (7) natural biotic areas and (8) other categories established by
law, conventions or international agreements which the Philippine Government is a signatory.
Protected area nearest the Phase III site is Marikina Watershed Reservation (18,965.86 ha)
which is located about 20 km upstream from the project site, Lower Marikina River, in Antipolo
city and Montalban municipality in Rizal Province. Therefore, no adverse impact is predicted.
Candaba Swamp and Manila Bay have been nominated as Important Bird Areas by Bird Life
International. Candaba Swamp is located in the Pampanga River Basin about 60 km far (straight
distance) from the Pasig-Marikina River. Bird area of Manila Bay is located around Cavite area,
20 km far from Pasig River. Therefore, no adverse impact is predicted.
4.2.10 Recreational Area
The PRRC initiated the creation of Environmental Preservation Areas (EPAs) in order to
promote a cleaner Pasig River. The EPAs take the form of linear parks, walkways and
greenbelts on both sides of the Pasig River. So far, a total of 24.64 linear kilometers of parks
have been completed extending from the City of Manila to Taguig City.
30
Table 4.6 Environmental Preservation Areas
Protected Area and other Environmental Preservation Areas (EPAs)
Pineda Linear Park
Pasig Buting Linear Park
West Rembo Linear Park
Vergara Linear Park
Hulo Linear Park
Barangka Itaas Linear Park
Makati
Barangka Ibaba Linear Park
Barangka Ilaya Linear Park
Buayang Bato Linear Park
Tagig Napindan North Riparian Forest
Source:. www.prrc.com.ph (2011), PRRC
31
(4) Phytoplankton
The phytoplankton species that were collected on 20 September 2008 during Pasig (II)
environment monitoring session are of 3 different classes: Cyanophyceae, Chlorophyceae
and Bacillariophyceae.
Stephanodiscus sp. of Bacilliariophyceae dominates the phytoplankton
population with 83% of the total population in all of the sampling stations.
Pediastrum sp. belongs to Chlorophyceae. It occupies 8% of the total
phytoplankton population in all of the sampling stations.
The Melosira sp. of Bacilliariophyceae occupies 5% of the total phytoplankton
population in all of the sampling stations.
Oscillatoria sp. of Cyanophyceae and Cymbella sp. of Bacillariaphyceae
occupy 0.05% of the total phytoplankton population in sampling stations.
4.3.2 Fauna
(1) Wildlife
Table 4.8 National List of Threatened Fauna in and around Metro Manila Area
Taxonomy Scientific Name Common Name Conservation Distribution area
Status
Macaca fascicularis Philippine Monkey OTS
Throughout the
Cervus mariannus Philippine brown deer VU Philippines
Pteropus vampyrus Giant flying fox OTS
Mammals
Dugong dugon Dugong CR Manila, Taytay
Acerodon jubatus Golden-crowned fruit bat EN Manila, Quezon
Pteropus leucopterus White-winged fruit bat VU Quezon
Ptilinopus marchei Flame-breasted fruit dove VU Quezon
Ptilinopus merrilli Cream-bellied fruit dove VU Quezon
Birds Grus antigone Sarus crane CR Quezon
Sterna bernsteini Chinese crested tern CR Manila Bay (1905)
Hydrosaurus postulatus Philippine sailfin lizard OTS Quezon
Eretmochelys imbricata Hawksbill turtle CR Quezon
Crocodylus mindorensis Philippine crocodile CR Quezon
Reptile Varanus olivaceus Gray's monitor lizard VU Quezon, Manila
Varanus salvator. Northern
Malay monitor lizard VU
marmoratus Philippine
Note: Conservation Status: CR (Critically Endangered), EN (Endangered), VU(Vulnerable), OTS(Other
Threatened Species).
Source: 2004 Statistics on Philippines Protected Areas and Wildlife Resources, Protected Areas and Wildlife
Bureau (PAWB), DENR
32
highly-developed Metro Manila area, exclusively in and along the already highly-polluted
and disturbed Pasig-Marikina River.
(2) Nektons (fish)
Ancistrus temminckii, commonly known as “janitor fish,” was the only fish species caught
during the aquatic biota sampling. The Janitor Fish is an invasive specie, which was
brought for a research purpose from out of the country, and not a native of the
Pasig-Marikina River. The greatest number of janitor fish caught and observed was in
Guadalupe Bridge. None were caught at Lambingan Bridge.
(3) Zooplankton
Three groups of zooplankton were found in four sampling stations in the Pasig River. As in
most tropical freshwaters, results show that the zooplankton population is dominated by
Cladocerans, with 46% of the total population count of zooplankton in all of the
sampling stations. Diaphanosoma excisum is the species notably recorded as the most
abundant among the other Cladoceran species.
(4) Macrobenthos
Oligochaetes and dextral pond snails dominate the macrobenthic population,
occupying 48 % of the total collection in all sampling stations. Oligochaetes belong
to Phylum Annelida, which are known as well-segmented worms.
The river snail, which belongs to family Pleuroceridae, holds 19% of the total
number of collected macrobenthic organisms.
Shrimp are the least number in the macrobenthic community with 5% dominancy.
They are under the Subphylum Crustacea, that requires well-oxygenated water. This
explains its low dominance among the macro invertebrate species in four stations.
Corbicula manilensis, commonly known as “tulya,” was observed in Guadalupe
station since the station is near Laguna de Bay. Few individuals of Pomacea
canaliculata, or “golden kuhol,” were also obtained from all the four stations.
33
San Jose
Bagong Katipunan
Sta. Rosa
Makati West Rembo
4.4.2 Population
Pasig City, where most of Phase III of construction sites takes place, experienced about a 1.6
fold population growth between 1990 and 2007, from 397,309 to 627,445 in 17 years.
The populations and annual average growth rates from 1990 to 2007 in the Study Area are
shown in the below table.
The population densities of the Study Area from 1990 to 2007 are shown below table.
Populations in Barangays located along the Phase III construction segment of the Lower
Marikina River are listed in following table.
34
Table 4.13 Estimated Population in the Directly Affected Barangays
2000 2007
Quezon City (Total) 2,173,831 2,679,450
Bagumbayan 7,597 9,209
Ugong Norte 6,959 6,822
Pasig City (Total) 505,058 627,445
Ugong 19,034 22,266
Bagong Ilog 16,423 15,454
Pineda 16,655 15,013
Santolan 37,055 43,286
Manggahan 32,615 38,063
Rosario 48,998 50,690
Maybunga 24,529 35,627
Caniogan 23,553 21,769
Kapasigan 6,178 6,569
San Jose 1,575 2,347
Bagong Kapipuan 1,044 1,185
Santa Rosa 1,120 1,515
Buting 10,408 9,073
San Joaquin 10,694 12,498
Source: www.census.gov.ph, Demographic Statistic, National Statistic Office
Overall populations in Pasig City increased about 24% on average between 2000 and 2007. It
can be assumed that social, commercial and industrial activities in such areas have increased as
population grew, which in turn resulted in changing mutual influences of the cities and the river
since the EIA report was prepared in 1998.
Most of the lower Marikina River runs through Pasig City. Pasig City’s population increased
from 505,058 in 2000 to 627,445 in 2007. Maybunga, one of 14 major Barangays located along
the river, increased its population by 11,098 people by 2007, which is 45% growth when
measured from 2000. While Barangay Buting lost 1,335 people, its neighboring
Barangays—namely San Jose, Banong Kapipuan, and Santa Rosa—gained 1,308 people all
together from 2000 to 2007.
Barangays Santolan and Mangahan, located upstream from the Phase III section, each increased
their populations about 17%. This implies that about 2,500 households (1 household contains
4.66 people in Pasig City) have moved into the two Barangays between 2000 and 2007. Ugong,
another major Barangay located in the middle of the Marikina River, has increased its
population from 19,034 in 2000 to 22,266 in 2007. This indicates that about 700 new
households moved into Ugong since 2000.
Residents in the projected affected area originate from neighbouring cities as well as from other
islands, such as: Albay, Samar, Pangasinan, General Santos, Iloilo, Sorsogon, Cagayan,
Misamis Oriental, Negros Occidental, Bacolod, Zamboanga, Marinduque, Legaspi, Masbate,
Quezon, Bulacan, Surigao, Cebu, Oriental Mindoro, Pampanga, Mindanao.
Populations in Barangays that are located upper and lower streams of Lower Marikina River
section are listed in the table below.
35
Table 4.14 Estimated Population in the Upper and Lower Sections of Phase III
2000 2007
Makati City
Total 444,867 567,349
East Rembo 23,902 23,119
West Rembo 28,889 28,578
Cembo 25,815 26,589
Guadalupe Nuevo 22,493 23,359
Marikina City
Total 391,170 424,610
Industrial valley 13,366 14,050
Calumpang 14,552 15,589
Barangka 19,466 17,424
Tanong 9,477 9,360
Jesus de la Pena 9,796 8,553
Santa Elena 5,704 7,008
Conception Uno 76,736 40,277
Malanday 42,256 51,363
Nangka 32,273 41,837
Santo Nino 27,602 24,694
Conception Dos 23,845 27,809
Source: www.census.gov.ph, Demographic Statistic, National Statistic
Office
Barangays East Rembo, West Rembo, and Cembo in Makati City are located 2 km directly
downstream of the lower end of the lower Marikina River section. While Makati City’s
population increased about 83,000 people (approx. 17%) between 2000 and 2007, the
populations in the three concerned Barangays has increased less than 1%, and rests were
decreased.
Marikina City, which is located above the Mangahan Floodway, has increased about 19% in the
7 years following 2000. Santa Elena, Conception Uno, Malanday, and Nangka have changed
their population about 23%, -48%, 22%, and 30% respectively since 2000. Reduction of
population in Conception Uno, which is located in the upper edge of Marikina City, is the
greatest of all; 36,459 people—or about 7500 households (1 household is 4.86 people in
Mrikina City)—had moved out in a 7 year-period. Meanwhile, Barangays Malanday and
Nangka, which are located right next to Conception Uno, increased their populations about
9,100 and 9,600 respectively during the same time period. Between 2000 and 2007, Barangay
Parang also lost about 45% of its population (30,136 people), while its neighboring Barangays
Marikina Heights and Conception Dos gained about 10,000 people.
36
while. About 36% of the city was estimated to be residential area in 2008. The residential area
grew from southwest to northeast and west along major roads such as Quirino Highway,
Tandang Soro Avenue, and Commonwealth Avenue. Quezon City had been developed as a
residential area by both private developers and NHA. However, most of the development has
been done by private developers. The city has been lacking “firm control and direction,” which
has resulted in “unrelated subdivisions with inadequate and uncoordinated service and facilities
(Quezon City CLUP, 2000)” and a growing population of informal settlers. Most of the informal
settlements are located on Constitution Hill, along Commonwealth Avenue, at the northeast of
Quezon City of upper Marikina River, Bagong Silangan, UP Campus, Escopa, Matandang
Balara, Pasong Tamo, Sauyo, and Bahay Toro Barangays as well as along riverbanks, creek
sides, aqueducts, and transmission lines.
In Quezon City, commercial areas have been developing along major roads and around public
markets. Fairview, North Triangle Business Center, and the Eastwood Cyber Park in
Bagumbayan Barangay are growing areas. The west side of the city is a traditional industrial
area and is still expanding. Potential industrial growth is expected to continue to occur in the
Balintawak and Novalishes districts. Light industries are expected to grow in the area east of E.
Rodoriguez Jr. Avenue in Ugong Norte. Spread of industrial zones is westward bound as they
consolidate and become less hazardous to the environment.
4.4.4 Land Use
The Project area is located in the National Capital Region (NCR). While most of NCR consists
of buildup areas, about 50% of the NCR consists of residential area and about 9% consists of
commercial areas.
Phase III construction sites are located close to high schools, major highways, narrow and
congested residential streets, community/Barangay parks, churches, Barangay Halls,
hospitals/clinics, and a Barangay fire station.
37
Table 4.16 Significant Facilities and Industries Located along the Marikina River and
Major Roads Nearby
City Barangay Avenues/Road Major Industries Major Facilities
Pasig Portland Cement,
Evangelista Ave. Tamilee Industries, San. Tomas de Villanueva Church
Himmel Industreis
Santlan
E. Amang Rodriguez Selecta Warehouse, RFM, Aggragates, Mangahan
Ave. PAG-ASA Steel Business center, Park Center, Sta.
factory, Lucia Church
Manggahan E. Amang Rodriguez Litten Mills Inc.,
Ave. Universal Robina
Corp.,
Rosario Dr. Sixto Antonio Alfonso Specialist Hospital, Rosario
Ave. Market
Pasig Blvd. Ext. (C. Mariwasa Tiles Rosario Sport Complex, Rizal High
Raymundo/MRR Rd) school Rosario Annex,
Maybunga Dr. Sixto Antonio Hampton gardens, San Antonio
Ave. Abad parish
Pasig Blvd. Ext. (C. Lunar Steel, Negro St.Therese hospital
Raymundo/MRR Rd) Woodwork Inc.
Caniogan Dr. Sixto Antonio Riverfront residences, Arelland
Ave. University Andres Bonifacio High
School, Sta. Clare de Montefalco
Parish, Rizal High School
Pasig Blvd. Ext. (C. Defcon Ready Mix Crossings Supermarket, Iglesia Ni
Raymundo/MRR Rd) Plant, Kristo Church, Evergreen Pasig
Memorial park pantheon,
San Nicolas Caruncho Ave. Pasig City hall, Pasig public market,
Health canter, Sport Center, Sabater
hospital
Ugong Eulogio Redoriguez International piple Iglesia Ni Kristo Church, Astron
Jr. Ave. industries, Republic Bldg., Ovaltine, Toyota Ortigas,
cement, Armour Tendesitas, SM Supercenter Pasig,
products, PR Relience center, Mitsubishi motors,
Cement, Resine & Admiral Unnisphene,
Ajinomoto,
Bagong Ilog Eulogio Redoriguez Universal Robina Gren valley sport center, Hyundai
Jr. Ave. Corp(food)., Pasig, Resins Inc., Mary Immaculate
Chateau Verde Hospital
restaurant
Pasig Blvd Universal Robina Rizal Medical Center
Corp(food).
Pineda Wellington Flour
Mills
Quezon Bagumbayan Eulogio Redoriguez D&L Industries, Camp Atienza, Phoenix Sun
Jr. Ave. Universal Robina Business Park, 3D service center,
Inc., Concrete Mercury drug corp., Holy family
aggregates, Auto chapel, One Luna Lifestyle center,
mechanica IDS Logistics, Shopwise,
Robinson’s Inc., IBM HQ, Citi Bank
HQ
Ugong Norte Eulogio Redoriguez Builder’s depot, Olympic badminton club, Red
Jr. Ave. McKenzie Ribbon office, Super 8, Nissan
distribution galley Oltigas
Pasig City has been developed as an uncontrolled as industrial area during the 1960s and
1970s. More than 200 large scale industries have been established along the Pasig and
Marikina Rivers. Economic development through industrial activities has attracted more
people to immigrate to the city indiscriminately. This has led to problems such as
38
pollution, squatters, flooding, unplanned communities, and urban expansion. Some
industries that might cause environmental hazards coexist with residential areas.
As of 2000, major establishments in Pasig City were mostly manufacturing industries such
as garments, chemical products, electronics, steel products, and food. Major commercial
businesses in the city are those in the retail, banking, and service sectors. Major
commercial areas are Pasig Public Markets (about 600m to the Napindan Channel, Brgy.
San Nicolas), Ortigas Commercial Center (located at the boundary of Pasig City,
Mandaluyong City, and Quezon City). There are almost no agriculture, forestry or fishing
operations except for very small patches of vegetable gardens and back yard livestock
operations.
Most of Pasig City consists of moderately to highly populated residential areas, except for
some parks, cemeteries, and an about 16% share of small-scale agricultural and
open/vacant spaces which are located mostly within the Laguna Bay Basin. Commercial
areas make up about 7% of the city and are located in Ortigas Center, the Central Business
District of Pasig, which is in San Antonio Barangay, on the border to Mandaluyong City.
Pasig Public Markets are located in San Nicolas Barangay, near by Pasig City Hall, about
600m to Napindan channel.
The city’s land use plan is incoherent and its execution is relaxed. Hence, it has caused
encroachments and hazardous living conditions. Ownership of land is often unclear.
Boundaries of private land, as well as Barangays, is often not clear. Ownership of land is
often confused, with land claimed by more than one owner, untitled, and overlapped.
Squatters live in such gray zones, setback zones, river banks, or simply in any vacant
places.
Two main road routes in Pasig City are Rodoriguez-Dr.Sixto Antonio Avenue from north
to south and Ortigas Avenue from east to west; the former runs along, and the latter
crosses, the Marikina River, and together they provide access to surrounding cities.
Jeepneys are mainly used to get around the city.
4.4.5 Living and Livelihood
In order to predict the impact of construction work, an area-specific social survey was
conducted of current residents in the areas directly impacted by Phase III construction activities.
4.4.6 Basic Biodata for Area Directly Affected by Phase III Construction
Most household heads (67%) are female and most household heads are also married (66%).
Twenty-five percent of them have been in their current residences for 1 to 10 years, while 52
percent have been living in the same Barangay.
39
The vast majority (92%) of household heads are house/structure-owners, while rent-free
occupants and renters comprise 3 and 12 % respectively. Lowest rent payment is Php1,200,
while the highest is Php5,000 for those who rent dwelling units. 97 percent of structures
house only 1 household, with 55 percent of structures housing 4 to 6 persons/ members. 49
percent of house/structure-owner households are comprised of 4 to 6 persons as well. Household
size of all 3 rent-free occupants is 5 persons. Only 8 percent of all households have caregivers.
Most renters have a household size of 3 persons.
Sixty three (63) percent of the households have only 1 member employed, while 59 percent of
the households have 2 members contributing to income. Forty one (41) percent of households
income comes from salaries ranging from Php9,001 to 15,000. Thirty eight (38) percent of
households earn a total income from business ranging from Php5,001 to 10,000. Lowest income
from pensions is Php1,200 while the highest is 10,000. There is no income derived from
agriculture.
Table 4.18 Biodata of Households in the Area Directly Affected by Phase III
Basic Biodata of Households Survey result (2011)
Household head Female (63%)
Marital status of head of HH Married (66%)
Averaged number of families in one HH 1
Averaged number of HH members 5
Own their dwellings (home owners) 89%
Averaged monthly rent Php 2,850
Averaged monthly income (total) Php 15,708
Averaged monthly remittance (domestic) None (98%)
Averaged monthly remittance (OFW) None (96%)
Averaged monthly expenses (total) Php 14,615
Averaged monthly expense on food Php 7,378
Averaged monthly expense on recreation Php 375
The lowest and highest incomes derived from remittance/s domestically is Php1,000 and 3,000,
respectively, while from OFWs are Php5,000 and 37,000, respectively. 40 percent of other
sources of income, such as loans and gifts, range from Php5,001 to 10,000 per annum. 38
percent of the respondents earn a total or combined monthly income (both from employment/
salary and various sources) of Php9,001 to 15,000.
Seventy one (71) percent spend Php5,001 to 10,000 monthly for food. Food is the single biggest
cost item for almost all of the households. 55 percent spent Php150 to 500 last year on clothing.
Thirty eight (38) percent of the respondents spend monthly from Php150 to 500 on
transportation; 46 percent spend from Php300 to 1,000 on education; 33 percent spend from
Php100 to 500 on water bills; 52% spend from Php1,001 to 2,000 on power bills; 54 percent
spend from Php100 to 300 on telecommunications; 64 percent spend from Php501 to 1,000 on
cooking fuel; 60 percent spend a monthly average of Php50 and below on medicines/
hospital; 60 percent did not spend anything on recreation last year; remittance to relatives
outside household is from Php200 to 3,000 monthly; and, 88 and 58 percent does not spend
anything on gambling and cigarettes/ alcohol.
Thirty three (33) percent spend the highest total monthly expenses ranging from Php9,001 to
15,000. Thirty-six percent said that they have a saving at least Php1,000 or below per month.
About 35 percent of the households have a member who has graduated from college. 46 percent
have at least 4 years of schooling, while fifteen percent stopped schooling mostly for financial
reasons.
40
4.4.7 Living Conditions
Twenty nine (29) percent are living in houses that are 11 to 20 years old. Seventy seven (77) or
54 percents of households are living in single-detached houses and houses that are exclusively
devoted to residential use, respectively. Seventy nine (79) percent of houses are 1-story/ level
structures, and 59 percent of houses have a gross area of 51 to 100 square meters.
Forty two (42) percent of house structures are semi-concrete. 62 percent of them are made of
semi-concrete walling materials; 93 percent are made of galvanized iron roofing materials; and,
82 percent are made of concrete flooring materials. 90 percent of toilet facilities are water sealed
and connected to a septic tank, and 93 percent have piped water connections.
Ninety three (93) percent of households suffered flood damage/s since 1998, with 90 percent of
them being damaged in September 2009/ Typhoon Ondoy. 91 percent said that flooding came
from the river, 76% of damages were done mostly to household furniture. To protect
themselves, 55 percent stayed at home, with 32 percent moving to a higher place. A specific
coping mechanism identified at the community level by the respondents is that of moving to an
evacuation center but mere 2% .
4.4.8 River Dependency
None of the household livelihoods in the directly affected area are dependent upon the river;
incomes both derived from agriculture or fishing and dependent upon the river were reported.
None of the households is depending on their income to the rivers and river banks.
The residents in the directly affected area do not think that temporary inaccessibility to the river
during the period of construction and dredging will adversely affect their lives. Moreover, no
one sees the river as culturally and religiously important place.
4.4.9 Drinking Water
Pasig, Marikina, parts of Makati and Manila, and the southeast part of Quezon cities are located
in the East Concession area of Manila Water Company, Inc (MWCI). As of 2003, MWCI
achieved 85% coverage of water service, connected to 396,778 outlets. (Source: MWSS
Regulatory office 2003 annual report, 2003; most recent to download from MWSS website).
The supply of water is not constant in the East Concession area of MWCI; tap water rationing
takes place in many areas in Pasig City.
The primary supply of water for the people living in the directly affected area is derived via
piped water (92.5%), public tap water (0.9%), and water vendors (6.5%); none of their water
supply is derived from river water or well water. And although deep wells do exist, they are not
a reliable source of drinking water.
4.4.10 Important Social Bounding and Places
No households belong to a particular social group with deep connections to the river or nature
contained within the Phase III affected area. Moreover, there are no culturally or
anthropologically significant places in the affected area that have been passed down through the
generations.
There are major public facilities located within 20 minutes walking distance of the residences of
those living in the directly affected area. Barangay centers are accessible to everybody (100%)
within 20 minutes walking distance. there are schools, LGU offices, evacuation centers and
women’s centers located within 20 minutes walking distance of their residences for 95 to 99%
of the respondents.
41
Table 4.19 Public Places within 20 Minutes Walking Distance
Place % HH
Police station 50%
Church or other religious places 54%
Market place 56%
Fire station 64%
Hospital/ clinic 70%
School 95%
LGU office 98%
Evacuation center 99%
Women center 99%
Barangay center 100%
Multiple answers (N=107)
In case of an emergency, such as flood, 98% of those surveyed stated that they do not have a
specific community-based coping mechanism, while 5% stated they would go to an evacuation
center. In the case of flood occurrence, about 60% stated that they would choose to stay home;
35.5% would choose to “move to higher place”; and 6.5% would move to somebody else’s
house.
4.4.11 Health
(1) Waterborne Disease
Diarrhea combined with dehydration was the 7th leading cause of infant death in Quezon
City, 46 out of 1251 deaths for each 100,000 population in 1998. Pneumonia was the top
cause of morbidity in Quezon City for the same year, followed by diarrhea/acute gastro
enteritis; there were 25,880 and 14,564 cases respectively. The morbidity rate for Dengue
fever was 25 per 100,000 people.
From June to December 2010, 35% of HH in the directly affected area were infected with
water related illness, including Dengue 1.9%, Malaria 2.8%, and Diarrhoea 33%. This
trend of disease occurrence matches the national trend. On the other hand, 62% have not
experienced illness in past six months.
(2) HIV/AIDS
According to the Philippine Department of Heath (DOH), as of December 2010, five (5)
new cases of HIV/AIDS are reported each day. Based on this statistic, DOH predicts that
there will be about 46,000 HIV cases by 2015.
42
Number of HIV/AIDS Cases Reported
1600
1400 Death
1200 AIDS
Number of people
Asymptomatic
1000
800
600
400
200
0
84
86
88
90
92
94
96
98
00
02
04
06
08
10
19
19
19
19
19
19
19
19
20
20
20
20
20
20
Source: Philippine HIV and AIDS Registry (November 2010), Department of health, national
Epidemiology Center
43
Only Malacanan Palace and Fort Santiago are located on the banks of Pasig River. Others are
located at least 0.5 km away from the project site. No construction activities are planned near
these areas. Therefore, there is no adverse impact on these historical sites.
4.4.14 Gender
The Philippine government established the National Anti-Poverty Commission (NAPC), the
Department of Social Welfare and Development (DSWD), and National Commission for the
Role of Filipino Women (NCRFW) to support poor and women and to deal with gender
problems.
More than half (63%) of households are female-headed, 66% include married couples, and 12%
include separated persons. Most households have water available within the home, and
important social services are located within 20 minutes walking distance of households. No
obvious gender inequity was observed.
4.4.15 Ethnic Minority and Indigenous People
The National Commission of Indigenous People (IP) is a mandated agency for ethnic minority
and indigenous people. NCIP does not provide data regarding IPs living in NCR or
municipalities and cities located in the Phase III construction area.
According to the interview survey that was conducted, there is no ethnic group or indigenous
people in the project affected area.
Twenty four percent of household members identified themselves as belonging to some local
groups (native regional/provincial places) such as Bisaya; Ilongo, Bicolano, Pangasinense, etc.
44
About 67% have not been informed of the Project Phase III.
Out of 33% that have been informed, 9% were informed in 2008, the rest were informed
in 2009 or 2010.
Out of the 33% that have been informed, 57% were informed by neighbors, 37% were
informed by Barangay Captains, and only one person received the information from the
media.
Out of the 33% that have been informed, 71% were informed only once while 29% were
informed twice.
Meetings were the most common medium for receiving the information about the Project.
66% of all those informed were informed via meetings. On the other hand, 29% were
informed through “rumors”.
Although 67% of the interviewed HH have never been informed of the Project, 98% are
positively accepting and supportive to the Project.
45
CHAPTER 5 POSSIBLE IMPACTS WITHOUT MITIGATIONS
parks on dikes.
6 Poor, Indigenous and Livelihood of general low income people is not
Ethnic People dependent on resources from the rivers, such as
- D
fish and drinking water. Also, no Indigenous and
Ethnic People were identified.
7 Misdistribution of Benefits People in the project affected area do not think
and Damage - D construction work is a problem for their daily life
according the interview conducted.
8 Cultural heritage, No cultural heritage sites or spiritually important
historical and religious places are identified in the project affected areas.
- D
sites
10 Water Usage or Water There are no people that are dependent on river
Rights and Communal water for domestic consumption, irrigation, etc.
- D
Rights
46
14 Soil Erosion In the construction, no soil erosion which affects
- D on wide area due to earth excavation might
occur.
15 Groundwater No changes in volume, flow direction, lowering
- D
water level, etc., for groundwater are anticipated.
16 Hydrological Situation Revetments are planned to be constructed along
the existing river banks. Although the channel
will be deepened by the dredging, there is no
- D change in normal water level because dredged
section is within tidal affected area of Manila
Bay. No change in hydrological situation is
anticipated by the project.
17 Coastal Zone No damage to coastal zone is anticipated since
- D
site is far from coastal zone.
18 Flora, Fauna and Although construction works will damage some
Biodiversity terrestrial flora, these can be naturally revived in
- D
time. No endangered or concerned species are
identified in the construction affected area.
19 Meteorology Not affected or least likely affected by the
- D
construction work.
20 Landscape In the construction period, no obstruction to
- D
landscape views of river walk/parks is expected.
21 Global Warming Not affected or least likely affected by the
- D
construction work.
22 Air Pollution Exhaust and fumes from construction machinery
will add pollutants to the air, but the pollution
will be very light, temporary, and localized, and
it will not be as significant an issue as the
already heavily polluted air in Metro Manila
Area. As Phase II project monitoring results
D D
show that the machineries and vehicle used for
the construction works least likely aggregate
already existing air pollution. Dust will be
generated due to construction activities such as
transportation, spreading, and embankment of
soils, stones, etc.
23 Water Pollution In the project construction period, suspension of
sediments and release of sediment pollutants will
B B
occur as a result of excavation/dredging in the
river.
24 Soil Contamination Dredged materials contain some heavy metals.
However, all the values taken from sediment to
Pollution
47
29 Bottom Sediment Since the dredging works remove polluted
- D sediments of river, no pollution of bottom
sediments are predicted.
30 Accidents In the project construction period, construction
- B
related accidents might occur.
A: Significant impact, B: Slight impact, C: Unknown, D: Few impact. -:Not Applicable
*EIS1998)did not use JICA’s method to evaluate the impact using “A,B,C and D”. Evaluation results of
EIS(1998) were converted to JICA’s method.
48
CHAPTER 6 SUGGESTED MITIGATION MEASURES AND
ENVIRONMENTAL MANAGEMENT PLAN
49
6.2 Mitigation Measures for Negative Impact of Phase III
The following table shows the suggested mitigation measures for the possible negative impacts:
Geographical D
Natural
Features
14 Soil Erosion For small scale of erosion, excavation works should be
D done in accordance with the design of civil works for
stability.
15 Groundwater D Not necessary
50
16 Hydrological Not necessary
D
Situation
17 Coastal zone D Not necessary
18 Flora, Fauna and Not necessary
D
Biodiversity
19 Meteorology D Not necessary
20 Landscape D Not necessary
21 Global Warming D Not necessary
22 Air Pollution Air quality is monitored as the same as Phase II,
although it is considered to be “D”. Fumes and exhaust
from machinery and equipment used for Project can be
reduced or prevented by properly installed and
D maintained mufflers and filters. CO2 level is suppressed
by frequent and timely changing of machine/engine oil
and stopping excessive idling of engines. Hosing of
ground is done during earth work to prevent dust from
dispersing into the air. Measures such as watering,
cover-sheets will be taken.
23 Water Pollution Use technology that prevents sediments from
B suspending/re-dissolving to the river, such as prevention
sheet, watertight type eco-grab, etc.
24 Soil Contamination For dredged materials, cement will be added, which will
contain the hazardous substances within cement-mixed
B soils. Leaching from dredged materials at disposal site
should be monitored. As required based on monitoring,
more adequate mitigation measures should be taken,
such as use of sheets under disposal materials.
25 Waste Generated contaminated solid wastes/sediments are
taken care of according to Republic Act 6969.
Pollution
51
This EMP will be finalized during Pre-construction stage based on the detailed construction
design for Phase III.
(Increase in
Demand for
Housing and
Associated
Utilities, such as
water supply, toilet,
etc., of Outside
Construction
Crews)
5 Existing Social Adjusting mobilization and Ditto Not
Infrastructures and formation of vessels for construction Applicable
Services activities to avoid navigation route in
coordination with Philippine Coast
(Impairment of Guard.
River Navigation)
11 Sanitation 1) Prioritizing to employ local people Ditto Not
to reduce outside workers to Applicable
(Deterioration of immigrate and reside around
Sanitation Level construction site.
due to Workers 2) Provision of adequate portalets for Ditto P3 million
Presence at construction workers.
Contractor 3) Initiate training and information Ditto Not
Campsite as dissemination on proper waste Applicable
Construction segregation.
Workers)
12 Hazards/Risk: Seminars to be conducted for Construction Not
Infectious Diseases construction workers. Contractor in Applicable
such as HIV/AIDS accordance
with
Construction
52
Contractor’s
Environmental
Program
(CCEP)
14 Soil Erosion 1) Proper excavation/ dredging Ditto P80 million
scheme and construction techniques
should be applied.
2) Measures such as shoring, sand Ditto P200 million
bags, bracing supports, etc., are
installed to prevent sudden soil
erosion, as necessary.
3) Excavation work is to be avoided Ditto Not
during rainstorm. Applicable
20 Landscape Planting of trees/shrubs/ornamental DPWH, P1 million
plants or landscape activities. DENR, LGUs,
etc.
22 Air Pollution 1) Regularly/ Properly maintaining Construction Not
the engines of construction Contractor in Applicable
equipment/machinery. accordance
with
Construction
Contractor’s
Environmental
Program
(CCEP)
2) Watering to prevent dust Ditto P12 million
generation when necessary during
dry season.
Use of tarpaulins to cover loaded
materials such as soils during
transportation.
23 Water Pollution Preventing accidental discharge of Ditto P50 million
excavated/demolished soil/ materials
(Change in Quality during the civil works.
of River Water
such as Turbidity
Increase)
24 & Soil Contamination 1) Efficient handling of dredged Ditto P650 million
25 and Waste materials providing temporary
containment facility and apply the
(Disposal of measure to reduce high water
Excavated/ contents for transportation and
Dredged Materials) disposal.
2) Use Eco-tube method Ditto P97 million
26 Noise and 1) Adjusting working time to avoid Ditto Not
Vibration early morning and night and Applicable
holidays.
2) Regularly maintaining/ adjusting Ditto Not
the engine and muffler of Applicable
machinery/equipment to keep an
appropriate function.
3) Adopting less noise/ vibration Ditto Not
generation type of heavy equipment. Applicable
28 Offensive Odor Application of plastic sheet-cover, Ditto Included in
Eco-tube and cement/lime mix Item Nos. 24
method. and 25.
30 Accidents Use of billboards. Information, Ditto P1 million
education and campaign to the
residents and construction workers to
promote workplace safety awareness.
53
6.3.2 Compliance with ECC Conditions
The conditions described in the ECC shall be followed and fulfilled by the proponent (DPWH)
as stated. Compliance with ECC shall be monitored by the DPWH and a Multipartite
Monitoring Team (MMT) to be set up in the proposed Phase III Project. A contractor for
construction is also mandated to comply with the ECC conditions. For each ECC conditions, the
following actions are proposed to be taken:
2 All other permits from pertinent To be complied by DPWH in assistance with the
government agencies shall be secured services of the Consultant employed by DPWH.
before project implementation. Likewise,
the proponent should submit a
Memorandum of Agreement (MOA) with
Local Government Units (LGUs)
pertaining to the preparation of maps
identifying/showing the flood prone
barangays, profile of the poor which
include the families living in high risk
location along the Pasig-Marikina Rivers,
preparation of disaster management plan
including response to flooding and
greening and maintenance of project
amenities as well as with the Pasig River
Rehabilitation Project relative to the
resettlement plan for the affected families.
3 A detailed construction design and contract To be compiled upon the conclusion of Contract
documents shall be submitted to this Office between DPWH and Contractor, prior to the start of
one (1) month prior to the start of construction.
construction.
4 A Construction Contractor’s Environmental To be complied by the Construction Contractor in
Program (CCEP) shall be submitted to this accordance with the Conditions/Technical
Office for approval 30’days before the start Specification of the Contract between the
of construction which should contain Contractor and DPWH.
among others, definite mitigation measures
such as proper disposal of spoils and waste
materials, excess concrete and wash water
from transit mixers and others.
5 The project proponent shall conduct To be complied through the Project Consultant
orientation for resident engineers and employed by DPWH. Multi-media information
contractor who will undertake and education campaign is one of scope of services of
54
implement the project, to apprise them of Consultant.
the conditions/stipulations of the ECC and
the necessary measures that will mitigate
adverse environmental impacts, and submit
reports of such orientation to this Office,
copy furnished the Multipartite Monitoring
Team (MMT).
6 A multi-media information education To be complied through the Project Consultant
campaign shall be implemented by the employed by DPWH. Multi-media information
proponent covering the immediate areas as education campaign is one of scope of services of
well as adjacent and affected cities. The Consultant.
target public will include the local
government unit officials and residents
concerned, basic sectors which will include
NGOs and POs.
7 A billboard measuring 0.5 meters by 1.0 To be complied by the Contractor in accordance
meter bearing “ECC-98-NCR-QC301 with the Conditions/Technical Specification of the
issued pursuant to P.D. 1586” shall be Contract between the Contractor and DPWH.
displayed in a conspicuous location at the
project site for identification and guidance.
8 In case that the construction of the project To be complied by the Contractor in accordance
temporarily stopped due to financial reason with the Conditions/Technical Specification of the
or forced majeure, measures to project and Contract between the Contractor and DPWH.
safeguard the adjacent properties and the
general public should be strictly observed.
II. Operation Stage
9 All restoration works/grading of the To be complied by the Contractor in accordance
exposed grounds shall be immediately with the Conditions/Technical Specification of the
undertaken after construction all in Contract between the Contractor and DPWH.
accordance with the Technical
Specifications of the Contract.
10 Planting of trees/shrubs/ornamental plants To be complied by inclusion in the detailed design
or landscape activities shall be undertaken and conditions/technical specification of the
to contribute to the aesthetic value of the Contract with the Contractor.
area and to compensate for the lost
capability of the area to absorb carbon
dioxide.
III. Others
11 A separate Initial Environmental To be carried out by the consultant during the
Examination (IEE) or an Environmental detailed design, including coordination with
Impact Statement (EIS) shall be prepared concerned agencies, collection data/information,
and submitted to this Office for the site reconnaissance, data consolidation, etc.
designated/chosen disposal site.
12 The proponent shall set up/provide a Submitted on May 27, 1999.
Contractor’s All Risk Insurance (CARI)
and Quick Response Fund (QRF) to
compensate/ cover expenses for
indemnification of damages to life, health,
property and environment caused by the
project and further environmental
assessment. The QRF shall be established
and committed through a Memorandum of
Agreement (MOA) between and among the
proponent, the LGU concerned,
Non-governmental Organization’s (NGO)
and affected parties within sixty days (60)
after the issuance of the ECC.
13 The Department of Public Works and To be complied by DPWH. DPWH EU is
Highways (DPWH) Environmental Unit Environmental and Social Service Office. Project
(EU) together with the Project Management Office is PMO-Major Flood Control
55
Management Office and Technical Projects, Cluster I. Environmental monitoring is
Consultants shall supervise the contractors, one of scope of works of consultancy services of
implement the EMP and other measures the Consultant to be employed by DPWH.
that may be required by this Office during
construction and operation phases.
14 All the proposed environmental To be complied by DPWH.
management measures contained in the
submitted documents shall be effected.
15 Project implementation and maintenance To be complied by DPWH.
throughout its lifespan shall strictly
conform with the submitted documents,
any modification from the approved project
scope shall be covered by another ECC
application.
16 Should adverse impact occur as a result of To be complied by DPWH.
project operations, all the activities causing
the same shall be immediately stopped,
remedial measures shall be effected and all
damages to life and property will be
properly compensated to all aggrieved
parties.
17 The project proponent shall allocate funds To be complied by DPWH. (Environmental
or provide the financial requirements of the monitoring including preparation and operation for
Multipartite Monitoring Team (MMT) and MMT is one of scope of works of consultancy
shall allow the same to conduct services of the Consultant to be employed by
inspection/monitoring in the entire project DPWH.)
area without prior notice to oversee
compliance to ECC conditions and to
determine the residual impacts to the
environment.
18 Additional ECC condition(s) shall be To be complied.
imposed if findings to protect the
environment warrants.
19 Any false information contained in the To be complied.
submitted documents and non-disclosure of
vital information which led to the issuance
of the ECC shall render the same null and
void and a ground for filing of appropriate
legal charges.
20 This Certificate shall be posted in a To be complied.
conspicuous place in the Field Office for
easy reference and guidance.
21 The project proponent shall submit to this To be complied. (Environmental monitoring
Office a quarterly environmental including preparation of quarterly environmental
monitoring report based on the monitoring reports is one of scope of works of
submitted/approved environmental consultancy services of the Consultant to be
monitoring plan. employed by DPWH.)
22 In case the project proponent cannot To be complied.
comply with any of the conditions for
technical reasons, a written approval from
the DENR-NCR shall be secured first prior
to implementation.
56
Table 6.4 Environmental Permissions to be Possibly Required
Information on not only social and environmental concern but also structural detailed design
will be disclosed properly and adequately in accordance with JICA Guidelines.
Stakeholders can access the information such as EIS(1998) report, supplemental EIS, results of
detailed design, etc., at the following. Stakeholder may request the explanation with local
language (Tagalog).
There are also disclosed at Barangay Halls of one of the affected Barangays in each city, where
it takes about 20 minutes from the farthest affected communities by walk. Such disclosure shall
start as soon as the Supplemental EIS Report is completed and last until completion of the
57
project. Those shall be available at all times for perusal by project stakeholders such as local
residents during project’s life and copying is permitted. Disclosure of EIS Reports shall be
informed to public distribution of brochures.
Summary documents or brochures of EIS(1998) and Supplemental EIS written in Tagalog, will
be prepared and disclosed in the Philippines.
The JICA study survey in 2010 revealed that the residents are not familiar with the improvement
of Lower Marikina River of Phase III. This need can best be responded to with a campaign plan
for information dissemination.
The Information Education and Communication (IEC) Plan, to be effective, shall have the
following objectives:
Cost for IEC is to be included in the cost of Consulting Services for the Phase III as the same as
ongoing Phase II.
In the scope of consulting service for PMRCIP Phase II, the consultant has continuously been
conducting various information campaigns in the project area that belongs to Manila City,
Mandaluyong City, Makati City, and Pasig City. The campaigns are coordinated for various
target groups such as government officials, general public, and students. The contents of the
campaign cover many educational subjects such as importance of flood control, and necessity of
river bank management work.
58
Table 6.5 Record of Public Consultation
No. of PAFs to be
No. Date Time Target Group Venue No. of Participants* Relocated in the
Barangay / LGU
14:00
Tue. April West Rembo Residents: 4 (3)
1 – West Rembo, Makati 10
19,2011 Barangay Hall Officials: 10
17:00
Thu. Barangay 900
9:00 – Residents: 32 (16)
2 April Barangay 900, Manila Barangay Hall 26
10.40 Officials: 10
28,2011
Thu. 11:00 Barangay 896
Residents: 19 (8)
3 April – Barangay 896, Manila Barangay Hall 13
Officials: 9
28,2011 12:30
Thu. 13:30 Barangay 897
Residents: 5 (1)
4 April – Barangay 897, Manila Barangay Hall 7
Officials: 15
28,2011 15:00
Thu. Barangay 894
15:30 - Residents: 17 (11)
5 April Barangay 894, Manila Barangay Hall 2
17:00 Officials: 8
28,2011
Fri. April 9:15 – Ugong Basket Residents: 77 (44)
6 Ugong, Pasig -
29, 2011 10:30 Ball Court Officials: 3
10:40 Barangay Hall
Fri. April Residents: 43 (19)
7 – Caniogan, Pasig -
29, 2011 Officials: 3
12:00
13:30 Barangay Hall
Fri. April Residents: 18 (7)
8 – Maybunga, Pasig -
29, 2011 Officials: 3
15:05
11:30 Barangay Hall
Sat. April Residents: 54 (29)
9 – Bagong Ilog, Pasig
30, 2011 Officials: 2
12:10
14:50 Consultant
Fri. July
10 – Stakeholder Office of Phase 18 -
8, 2011
16:15 II
14:55 Consultant
Mon. July
11 – Stakeholder Office of Phase 11 -
11, 2011
16:00 II
Fri. July 14:35 - Barangay 894 Residents: 67(28)
12 PAFs in Manila 48
15, 2011 16:35 Barangay Hall Officials: 8
10:00
Wed. July West Rembo Residents: 20
13 – PAFs in Makati 10
20, 2011 Barangay Hall Officials: 8
11:45
Owners of Residents: 24(11)
10:00
Fri. Aug. improvements and crops
14 – Barangay Hall Officials: 2 -
12, 2011 in Brgy. Maybunga,
10:45
Pasig
Owners of Residents: 27(10)
11:00
Fri. Aug. improvements and crops Ugong Baseket Officials: 2
15 – -
12, 2011 in Barangay Ugong, Ball Court
12:15
Pasig
Owners of Residents: 12(9)
11:00
Sat. Aug. improvements and crops Officials: 2
16 – Barangay Hall -
20, 2011 in Brgy. Bagong Ilog,
11:45
Pasig
8:00 – Residents: 42(14)
Existing
10:30 Owners of
Sat. Aug. Promenade, Officials: 2
17 14:00 improvements and crops -
20, 2011 Barangay
– in Brgy. Rosario, Pasig
Rosario
15:30
*: Number in ( ) means number of female participants. Officials include Barangay office staff.
In the consultation meetings held as the above, contents of EIS(1998) and supplemental EIS
conducted in 2010/2011 in accordance with JICA Guidelines have been explained in Tagalog,
showing pictures and documents. There was no request for implementing additional
environmental study. No objection about implementation of the Project was heard during the
59
consultation meetings.
The Institutional Plan intends to delineate the roles and responsibilities of the key players who
will be directly involved in the implementation of the Project in general and the EMP in
particular.
It is reasonable to continue using the existing organizational structure and MMT of Phase II for
the proposed Phase III but it needs to be improved to meet additional/new demands required by
dredging activities in the lower Marikina River section.
The following is institutional relationship of ongoing Phase II:
60
To coordinate with the LGUs and the DENR on the environmental aspect of the
preconstruction and construction activities of the Project,
To monitor all activities relative to the ECC stipulations to ensure compliance of all
requirements,
To coordinate with the DENR on all environmental monitoring activities,
To actively participate in the periodic consultations with all concerned sectors on the
various environmental impact issues of the Project,
To maintain records on all matters concerning the environmental aspects of the Project,
To prepare a monthly environmental status report of the project during the construction
phase and consolidate these reports for a quarterly submittal to the DENR, and
To prepare an annual environmental status report of the project during the operation phase.
(2) Consultants
(3) Contractor
The Contractor shall be bound by the Contract Agreement with DPWH to implement the sound
environmental protection and safety measures in the execution of the Contract Works, and to
comply with all requirements of ECC conditions and EMP. To ensure this, the Contractor shall
have in its employ an Environmental Manager who should be an expert in environmental
engineering/management system.
(4) LGUs
The LGUs related with Phase III, Manila, Mandaluyong, Makati and Pasig cities, shall be aptly
represented in the MMT. It should coordinate closely with the DPWH, DENR MMDA and
concerned government agencies towards ensuring sound management of the Project and
impacted environment.
(5) MMT
The MMT is a multi-stakeholder body and shall be organized to monitor compliance with ECC
conditions, measures set out in the EMP and pertinent DENR rules and regulations. The MMT
shall also serve as an independent evaluator that will provide check, balance and objectivity to
the entire environmental monitoring process. The table below shows expected membership and
its roles:
61
Table 6.6 Suggested MMT Components
Components Roles
DENR-EMB-NCR MMT Chairperson
DPWH-PMO-MFCP I (proponent) MMT Vice Chairperson/ Secretariat
LGUs:
Manila City Member
Mandaluyong City Member
Makati City Member
Pasig City Member
Concerned Government Agencies:
MMDA Member
LLDA Member
PRRC Member
NSWMC Member
(Add or replace them with most appropriate government
agencies for Project Phase III)
Non-Governmental Organization (NGOs) Member
Necessary operation costs of EMP and MMT shall be borne by DPWH as cost for consulting
services of Phase III in the Project Cost.
62
CHAPTER 7 SUGGESTED ENVIRONMENTAL MONITORING
PLAN
7.1 General
The Environmental Monitoring Plan for the Phase III will cover the construction and operation
phases of the Project. This summarizes what important parameters will be monitored and where,
which methodologies will be used in monitoring, and how frequent will be for measurements.
The Monitoring Plan will basically cover the following:
a) Compliance monitoring for ECC, EIS(1998), Supplemental EIS, and EMP conditions,
b) Environmental quality monitoring, and
c) Socio-economic monitoring (employment, existing social infrastructures and services,
misdistribution of benefit and damage, sanitation, accident, resettlement, etc.).
In Phase III, the monitoring locations, frequencies and parameters chosen are the same as those
chosen for Phase II except that Phase III includes use of monitoring locations in the lower
Marikina River. An additional monitoring requirement for Phase III is that river water quality
and sediment toxicity must be monitored intensively during the course of dredging work.
The monitoring plan shall include the Construction Contractor’s Environmental Program
(CCEP) which is mandated for a contractor to submit to the proponent (DPWH).
63
7.2 Environmental Monitoring Plan
The following table shows suggested environmental monitoring plan based on this review
works:
Table 7.1 Suggested Environmental Monitoring Plan
Monitoring No. of Sampling Monitoring
Monitoring Method Parameter(s) Duration
Item / Location Frequency
Noise Measured by noise Decibels (dB) 4 points (Pasig Quarterly Pre-Construction
1
level method R.) and Construction
Stages
4 points (L.
Marikina R.)
Air Quality High volume sampling SO2, NO2, TSP (24 4 points (Pasig Quarterly Pre-Construction
2
method hours) R.) and Construction
Stages
4 points (L.
Marikina R.)
River Water Sampling, laboratory pH, Temperature, EC, 4 points (Pasig Semi Pre-Construction
3 Annually
Quality test and analysis Turbidity, DO, True R.) and Construction
(Complete) Color, Nitrate as Stages
Intensive
Nitrogen, Phosphate as 4 points (L sampling for
Phosphorous, TDS, TSS, Marikina R.) the first
Conductivity, Salinity, dredging
Chloride, Oil & work
Grease, Cr6+, Cu, Pb,
Total Hg, Cd, Total
Coliform, Surfactants,
Phenolic Substances,
Cyanide, Arsenic,
Organophosphates, BOD
River Water Sampling, laboratory BOD, TSS 4 points (Pasig One time Pre-Construction
4 every 2
Quality test and analysis R.) and Construction
months
Stages
4 points (L.
Marikina R.)
Generation Sampling, laboratory Total Mercury, Sampling shall be Monitoring Construction
5
of test and analysis Cadmium, Lead, done. frequency Stage
Excavated/ Hexavalent Number/Location will be
Dredged Chromium, Copper, of samplings will determined
Materials Arsenic, Cyanide, Zinc, be determined in in the
Organophosphates, the Detailed Detailed
PCB’s, Formaldehyde Construction Construction
Design. Design.
Disposal/Re Field inspection and Cd, Cr, Pb, Hg, As, CN, Sampling shall be Monitoring Construction
6
use of observation (Cu, Zn, PCB, done. frequency Stage
Excavated Groundwater sampling groundwater quality std Number/Location will be
/ Dredged as necessary as necessary) of samplings will determined
materials be determined in in the
the Detailed Detailed
Construction Construction
Design. Design.
Aquatic Identify species, -Density and diversity of 4 points (Pasig Once before Pre-Construction
7 construction,
biota (if number of species and phytoplankton and R.) and Construction
once during
necessary as abundance / density of zooplankton Stages
construction
a reference species per station. - Density and diversity of 4 points (L and once
data) macrobenthic organisms, Marikina R.) after
- Nekton (fish) construction
- Aquatic flora
64
7.3 Monitoring/Sampling Locations
Possible monitoring/sampling locations are suggested in Table 7.2 below and Figure 7.1.
(1) As for the Pasig River sections to be constructed in the Phase III, current
monitoring/sampling locations of Phase II are planed to be used.
(2) Natural environmental and pollution statuses during Phase III construction are
monitored at four (4) locations on water quality, noise, vibration, air pollution and
sediment/soil to be dredged. Sediments are also monitored to measure impact of
dredging and terrestrial construction activities. Samples of sediment/soil are taken at
the interface of the river and bank, center of the river, and during both rainy and dry
seasons around the four monitoring locations.
65
Lambingann
Pandacan Bridge Br.
Rosario Bridge
Jones Bridge Sta. Mesa
Alfonso Bridge
Rizal School
Sta. Ana
Vargas Bridge
Poblacion, Makati
Napindan
Guadalupe Bridge
66
7.4 Monitoring Parameters
The following standards and regulations shall be used for environmental status monitoring.
Water Quality: DAO No. 34 series of 1990;Water quality criteria for conventional
and other pollutants contributing to aesthetics and oxygen demand for fresh waters;
Class C River water
Air: DAO No. 14 series of 1993
Noise: the Environmental Quality Standards for Noise in General Areas specified in
Presidential Decree (PD) 984
Vibration: To be studied (there is no known standard for vibration in the Philippines).
Dredged/Excavated Materials: To be studied in the Detailed Construction Design and
confirmed by DENR and concerned agencies (no specific standard values for
sediment and dredged materials set in the Philippines)
Water Quality
1. Temperature 14. Arsenic (As)
2. pH 15. Cadmium (Cd)
3. Turbidity 16. Cyanide (CN)
4. Dissolved Oxygen (DO) 17. Hexavalent Chromium (Cr6+)
5. Electric Conductivity (EC) 18. Copper (Cu)
6. Salinity 19. Total Mercury (T-Hg)
7. Biochemical Oxygen Demand (BOD) 20. Chloride (Cl)
8. Nitrate as Nitrogen 21. Lead (Pb)
9. Phosphate as Phosphorous 22. Oil and Grease
10. Total Suspended Solids (TSS) 23. Surfactants
11. Total Dissolved Solids (TDS) 24. Organophosphates
12. Phenolic substances 25. Total coliform
13. True Color
Air
1.Sulfur dioxide (SO2) 3.Particulate Matters( PM10)
2. Nitrogen dioxide(NO2) 4. Total Suspended Particulates ( TSP)
Sediment/ Dredged Material(TCLP Test & Elutriate Test)
1. Total Mercury (Hg) 5. Arsenic (As)
2. Total Chromium (Cr), Hexavalent Cr (Cr6+) 6. Cyanide (CN)
3. Cadmium (Cd) 7.Organophosphates (“OP”)
4. Lead (Pb) 8. Zinc (Zn)
Flora and Fauna
1. Flora (terrestrial, aquatic, phytoplankton) 2. Fauna ( aquatic, zooplankton, macrobenthos )
67
CHAPTER 8 ENVIRONMENTAL STUDY ON DISPOSAL SITE
FOR DREDGING MATERIALS
8.1 Laws and Regulations related to Dredged Materials
There are no laws and regulations to directly control or regulate the dredged materials in the
Philippines.
(1) For the dredged materials which do not contain hazardous substances
Republic Act 9003 “Ecological Solid Wastes Management Act of 2000”: for the
management of no-hazardous or non-toxic waste, this law seeks to adopt a systematic,
comprehensive and ecological solid waste management program which shall;
Republic Act 6969 (1990) “Toxic Substances and Hazardous and Nuclear Wastes Control
Act” which is a law designed to respond to increasing problems associated with toxic
chemicals and hazardous and nuclear wastes. RA 6069 mandates control and management
of import, manufacture, process, distribution, use, transport, treatment, and disposal of toxic
substances and hazardous and nuclear wastes in the country. The Act seeks to protect public
health and the environment from unreasonable risks posed by these substances in the
Philippines.
DENR Administrative Order 36 (2004): Thereafter, the Procedural Manual of DAO 29, a
comprehensive documentation on the legal and technical requirements of hazardous waste
management, was issued in 2004.
68
DAO 35 1990 Revised Effluent Regulations of 1990, revising and amending the effluent
regulations of 1982.
DAO 26-A 1994 Philippine Standard for Drinking Water 1993 under the revision of Chapter
II, Section 9 of PD 856 (Code on Sanitation of the Philippines).
Source: 1. Phase I (Detailed Design in 2001); 2. Procedural manual Title III of DAO 92-29 “Hazardous Wastes
Management”, DAO36(2004); 3. DAO 90-35; 4. DAO 90-35 Table 1 Effluent Standards (maximum limits for the
protection of public health): Discharge limit from new/proposed industry to Inland water (Class C); 5. US EPA
The Pasig River Rehabilitation Commission (PRRC) and Phase I (Detailed Design in 2001) of
this Project have been monitoring. Since there are environmental quality criteria or guidelines
for contaminated soils and sediments in the Philippines, regulation values of some developed
countries are used for reference. According to these data, the concentrations of toxic substances
in the river sediments are within the acceptable levels of the reference guidelines of some
developed countries.
Table 4.4 Inorganic Chemicals in Sediments (mg/kg-dry weight)
Sampling Sampling Cadmium Chromium Copper Lead Mercury Nickel Zinc
Location Date (MDL1=0.9) (LOQ2=20) (LOQ=0.2),
(Bridge) (MDL=0.04)
Marikina
Marikina)
Vargas 08/06/09 <MDL 56.5 125.5 25 0.19 38 320
12/11/09 <MDL 36 113.5 26 0.15 36.5 239
River
(Lower
Marikina) 2001 0.89 (1.16*) 108.9 63.57 0.15 263.59
69
Napindan 08/06/09 <MDL 29 79 12 0.06 14.50 125
12/11/09 <MDL 28.35 102.5 17.5 0.050 27 202.5
2001 0.55 (0.96*) 97.79 37.87 0.17 289.29
Bambang 08/06/09 <MDL 33.5 91.5 45 0.089 19.5 250
12/11/09 <MDL 28 81 42.5 0.08 27 250
Ilugin 12/11/09 <MDL 16.2 59.5 21.5 12.5 205
Japan Solid 150 250 150 15
Pollution
Allowable value Agriculture 3 8 150 375 0.8 600
in Canada3 Residential 5 8 100 500 2 500
Commercial 20 500 1000 10 1500
Washington Sediment 5.1 260 390 450 0.41 140 410
State standard
UK Garden use 3 254 130 500 1 70 300
(ICRCL) Parks 15 10005 1306 2000 20 706 3006
The Netherlands Target 0.8 100 36 85 0.3 35 140
value7
Intervention8 20 800 500 600 10 500 3000
Method of Analysis: GC/MS (Scan Method, acquisition) determination after extraction with methanol in DCM and
hexane and cleanup in alumina column
*As Cr6+
1. MDL: Method Detection Limit; 2. LOQ: Limit of Quantitation; 3. Interim Canadian Environmental Quality Criteria for
Contaminated sites (in EIS, 1998); 4. As Hexavalent (Cr6+); 5. As Total Cr; 6. As long as plants grow; 7. Dutch’s final
environmental quality goal value; 8. The degree of soil quality that is required a clean-up work.
On the other hand, EIS(1998) Report stated that “A PRRP report on the “Preliminary
Assessment of the Water Quality of Laguna de Bay with and without Flushing of Pasig River”
prepared by the Water Quality Institute (1993) revealed that heavy metals were not found in
suspended and bed sediments in any significant concentrations. In addition, the study concluded
that the concentrations of the heavy metals, such as cadmium, chromium, copper, nickel, lead,
zinc, and mercury are low. These concentrations correspond to normal background values in
slightly polluted sediments.
70
8.4 Procedure of River Dredging Works
For the purpose of flood control, riverbed soil of 612,000 m3 in total are dredged. Part of
dredged materials, which are packed in geo-textile eco-tube, are planned to be used for the
embankment of Boundary Bank Works along the Lower Marikina River. The remaining
materials are transported to the designated disposal area for land reclamation, as follows:
(Unit: m3)
Volume of Generated Dredged Volume to be Used for Boundary Volume for Disposal for Land
Material Bank (in Eco-tube) at Site Reclamation
Dredging Riverbed
(with Eco-Grab /Protection Sheet for Turbidity Diffusion)
71
Lower Marikina River
Pasig River
Manila de Bay
Napindan River
Proposed Disposal Site
(Land Reclamation) Existing Lakeshore Dike
Laguna Lake
EL.12.5m
72
(1) Climate and Hydrology
Item Description
Climate The area lies within the Philippine region classified as having Type I Climate. It has two
pronounced seasons; dry season (November – April) and wet season (May – October).
Rainfall Maximum rainfall occurs from the months of June to October or during the prevalence of
the southwest monsoon rains. The mean annual rainfall within the Pasig-Marikina-Laguna
Lake Basin ranges from 1700 mm to 3200 mm.
Hydrology Laguna Lake with 900 km2 and 220 km shoreline is a shallow lake. Water levels of
Laguna Lake depend on the seasonal variation; from EL. 10.5 m in average annual
(Laguna
minimum and EL. 12.5 m in average annual maximum. Laguna Lake is a brackish water.
Lake)
Recent recorded high water level is about EL. 15.0 m at the time of Typhoon Ondoy in
September 2009.
Water Lake water quality is being monitored by the LLDA at various points within lake. Waters
Quality of Laguna Lake near the proposed area are within the standard for Class C fresh surface
(Laguna waters.
Lake)
Groundwater During dry season groundwater level is about 2 m below existing ground. During rainy
season, the low-laying area is submerged.
Item Description
Geology The area is located within the Quartenary Marikina Valley Alluvial Plain which is
between the hills of Guadalupe Formation and the Sierra Madre Range. The Guadalupe
Formation is a thick sequence of tuff, volcanic breccias, conglomerates, sandstone and
mudstone.
There are two prominent faults found in the area, namely, the Marikina Valley Fault and
the Binangonan Fault.
Topography The area is situated at the southern end of the Marikina Valley bounded by the
Guadalupe Formation Lowland on the west (EL. 2- to 200 m) and the Sierra Madre
Range (EL. 100 to 300 m) on the east. The Laguna Lake bounds the area to the south
and the Pasig-Marikina River lies to the north of the area. Generally, the terrain of the
area is described to be low-lying flat land.
Soil Soils of the coastal landscape type consists predominantly of fluid marine deposits of
sandy materials, mostly found in fresh water marshes. The soils in the broad and alluvial
plains are often subjected to seasonal flooding as evidently shown by the high clay
content that ranges from 40 to 70%.
The physico-chemical characteristics of the substrate in the terrestrial communities
in/around the area are; soil texture (C;lay-Clay-Loam), soil depth (0 – 200m), soil
drainage (poor) and pH (5.6 – 7.8).
Eighty-six % of the soils of Laguna Lake basin are volcanic in origin, the rest is
composed of alluvial and fluid marine deposits. The soil media within and around the
area is relatively homogenous specially in those localities occupying the low-lying areas
and is flat or plain.
Soil Erosion The area is in the area of no sheet erosion and no gullying.
73
(3) Land Use
Current land use in/around the proposed disposal site are:
a) Present land use of proposed disposal area is open area covered by natural grass.
b) Present land use around the disposal areas is open area, agricultural land and residential
area.
c) Near the disposal site, there are the existing flood control structures such as Lakeshore
road-dike and drainage pumping station along the Laguna lakeshore.
(4) Flora and Fauna
The area is generally homogenous in terms of non-productive grass vegetation in unused area.
There are no trees observed.
Domestic animals and birds are commonly found around the area. There are no endangered
species of either flora and fauna found in the area.
No Item Description
1 Air Pollution During construction, air pollution is predicted due to use of heavy
equipment. However, the magnitude of the rate of of emission of these
exhaust gases are relatively small and could be easily dispersed by
surrounding air since the area is described as an open space.
2 Noise and Vibration Due to the construction activities, noise and vibration by heavy
equipment such as dump trucks and bulldozers.
4 Traffic Condition After unloaded at Napindan River from barge, dredged materials are
hauled on the temporary road constructed in the open area. No
negative impact is predicted.
5 Flora and Fauna A loss of flora species due to reclamation can be easily restored.
Domestic animals and birds are commonly found around the area.
There are no endangered species of fauna existing in the area.
6 Soil Pollution/ In case the dredged materials contain hazardous substances, these will
Groundwater contaminate the original soil of disposal site.
7 Water Quality In case the dredged materials contain hazardous substances, when
existing drainage channel overflows due to flood, there is possibility
to effect on water quality around the disposal site.
74
8.8 Environment Management Plan for Disposal of Dredged Materials
The preliminary Environmental Management Plan including Mitigation Measures and
Monitoring Plan for treatment of dredged materials is tabulated below. In the next stage,
detailed construction design, applicable and proper mitigation measures will be studied and
proposed.
75
substances to prevent 1 point at
leaching of Drainage
contaminants into Canal.
adjacent surface.
Quarterly
during
Pre-construc
tion,
Construction
& Operation
phases.
No. Item 1st Month 2nd Month 3rd Month 4th Month 5th Month 6th Month
1 Understanding of
Project Features
2 Site
Reconnaissance/
Identification of
Potential Impacts
3 Secondary Data
Collection
4 Sediment Sampling
& Analysis
5 Surface Water,
Groundwater,
Biological Survey,
etc.
6 Study/Preparation
of Report
7 DENR Evaluation
76
CHAPTER 9 ENVIRONMENTAL EVALUATION IN THE
OPERATION PERIOD OF THE PHASE III
The possible positive and negative impacts and suggested each mitigation measure in the
operation period of the Phase III are forecasted and summarized in the table below.
Concerning the natural environment and pollution items, a few possible negative impacts might
be occurred by the Project. Therefore, it is not necessary to conduct any specific mitigation
measures and monitoring activities for the natural environment and pollution items in the
project operation period.
Table 9.1 Possible Impacts and Suggested Mitigation
Measures in the Operation Phase of Phase III
Impact Explanations and
Item
Positive Negative Suggested Mitigation Measures
Local Economy Positive: Losses of properties and lives are reduced considerably
such as and lives of people on the directly and indirectly affected areas
Employment and are stabilized which allows improvement of household economy.
Livelihood, etc
A -
Land Use and Positive: developed area will be protected from habitual floods
Utilization of and flood disaster be reduced.
Local Resources
A -
77
CHAPTER 10 CONCLUSION AND RECOMMENDATIONS
The EIS(1998) has concluded that the proposed project can be implemented in an
environmentally acceptable manner. The total benefits to be derived will overwhelmingly
outweigh the effects of the adverse impacts. Environmentally, the proposed project is
beneficial since it is actually a mitigating measure against the annual adverse impacts of a
natural hazard.
In addition to the EIS(1998), the Supplemental EIS Study has been conducted in the JICA
Preparatory Study to comply with the JICA Guideline for the proposed implementation of Phase
III. Through the supplemental study and evaluation, it is conformed that the Project can be
implemented in an acceptable manner.
Through this review/supplemental study, the following are recommended to be done before
commencement of the construction of Phase III:
b) ICP team uses local language in communicating with PAPs instead of solely
depending on a written report of EIS and RAP. Essence of the Project shall be
informed in this manner.
c) Update/ Measure and revise the concerned environmental data of baseline status of
natural and social environment are necessary before the Phase III construction work
starts.
78
CHAPTER 11 ENVIRONMENTAL CHECKLIST
Environmental checklists for the Project based on a JICA Environmental Checklist for River
Channel Improvement Project Form are shown as follows:
(b) Have EIA reports been Y EIA report was approved by the DENR-EBM of
* NB: In the approved by authorities of the Government of the Philippines. Then, ECC was
Philippines, host country’s government? issued in 1998. Validation of the ECC was
“EIA” system is confirmed in 2008.
called “EIS
(Environmental (c) Have EIA reports been Y EIA has been approved conditionally in the ECC.
Impact unconditionally approved? If No claim or penalty was imposed yet. MMT
Statement) conditions are imposed on the monitors the compliance with ECC conditions for
approval of EIA reports, are Phase II of the Project.
the conditions satisfied?
(d) In addition to the above Y All necessary documents have been submitted
approvals, have other and approved by the concerned agencies
required environmental including DENR and LLDA.
permits been obtained from
the appropriate regulatory
authorities of the host
country’s government?
(2) Explanation (a) Have contents of the Y Since the beginning of the Project, stakeholders
to the Public project and its potential impact have been informed and involved; Such
been adequately explained to stakeholders are: LGUs, PRRP, Star Craft Ferry
local stakeholders based on Corp., DENR-NCR office, EMB, MMDA, NGOs,
appropriate procedures, LLDA, etc. A public awareness meeting was held
including information on May 20, 1998 in Manila to disseminate
disclosure? information about the entire Project. All the
Has understanding of Local concerns were taken care of and/or considered
stakeholders been obtained? through the Scoping workshop.
Multi-party Monitoring Team (MMT) has been
holding quarterly meetings to explore, consider,
and address PAP concerns. Information Campaign
and Publicity (ICP) Team carries out periodic
activities in order to disseminate information
regarding the Project under the implementation of
Phase II since 2008.
Several public consultation meetings with
stakeholders have been held in 2011 for Phase III.
(b) Have comments from Y The most important public consultation was held
stakeholders (such as local on February 27, 1998 by DPWH at its central
residents) been reflected to office in order to work to formulate a Scoping
the project design? matrix which reflects stakeholders’ social and
environmental concerns regarding the project
design. Also, through frequent meetings hosted by
DPWH and mediated by Barangay captains,
Stakeholders’ comments reflected in the design as
much as possible through detailed design stage
and construction in Phase II.
(3) Examination Have alternative project plans Y An alternative (i.e. Zero-Option) plan was
of Alternatives been examined in light of considered in the EIS(1998). EIS(1998) concluded
79
social and environmental that the zero (no project) option would not help the
considerations? community to prevent flood damage. Also,
alternative plans in light of social and
environmental aspects were considered in the
feasibility study, to minimize land acquisition and
affected structure/families in the highly urbanized
project area.
2. Pollution (1) Water Is there a possibility that Y The project helps in controlling river water flow in a
Mitigation Quality changes in river flow flood event which itself does not change water
Measures downstream (mainly water quality. During the construction period, it might
level drawdown) due to the temporarily increase suspended solids by working
project will cause areas to not in and on the river bank and dredging. However,
comply with the country’s the adverse effects caused by construction
ambient water quality activities can be negligible when compared with
standards? existing water pollution levels and size of the
rivers. Also, in the event of large-scale dredging,
the project plans to use dredging techniques that
minimize suspension of sediments.
(2) Wastes In the event that large Y The soils generated in the Project are tested and
volumes of disposed of properly in accordance with
excavated/dredged materials regulations in the Philippines. They are
are generated, are the transported and used as fill-material for low land
excavated/dredged materials areas. EIS shall be conducted for the disposal
properly treated and disposed area in accordance with ECC conditions prior to
of in accordance with the start of construction.
country’s standards?
(3) Subsidence Is there a possibility that the N No effect or a negligible effect on groundwater and
excavation of waterways will subsidence will be caused by construction works,
cause groundwater level based on the examples of structural construction
drawdown or subsidence? Are in/around the sites.
adequate measures taken, if
necessary?
3. Natural (1) Protected Is the project site located in N According to “Statistics on Philippine Protected
Environment Areas protected areas designated by Areas and Wildlife Resources (2004)”, there is
the country’s laws or one protected area in NCR, “Quezon Memorial;
international treaties and Ninoy Aquino Parks and Wildlife Nature Center” in
conventions? Is there a Diliman, Quezon City, which is different from a
possibility that the project will protected area established for nature preservation
affect the protected areas? purposes. The Project will be unlikely to affect the
Parks since construction sites are well distanced
from it.
(2) Ecosystem (a) Does the project site N These are no primeval forests, tropical rain forests,
encompass primeval forests, or ecologically valuable habitats that were
tropical rain forests, recorded according to “2004 Statistics on
ecologically valuable habitats Philippines Protected Areas and Wildlife
(e.g., coral reefs, mangroves, Resources, Protected Areas and Wildlife Bureau
or tidal flats)? (PAWB), DENR”. Some mangrove areas exists
in Manila Bay, but it is unlikely that the project will
affect them. According to LLDA report, the
Pasig-Marikina River has been declared to be
“biologically inactive…” and “…no longer
classified as class C” for a long time. No rare
species have been found in quarterly monitoring of
the areas during Phase II.
80
disturbed Pasig-Marikina River.
(c) If significant ecological N/A N/A It is not anticipated that the project or its
impact is anticipated, are construction activities will have a significant
adequate protection measures ecological impact.
taken to reduce the impact on
the ecosystem?
(d) Is there a possibility that N The construction of river walls is on the edges of
hydrologic changes, such as river banks and has a very negligible effect on
reduction of river flow or downstream ecosystems, and flow is predicted in
seawater intrusion upriver will comparison with river size.
adversely affect downstream
aquatic organisms, animals,
vegetation, and ecosystems?
(e) Is there a possibility that N The Project does not change the river’s flow
changes in water flows due to pattern or volume of the river while the river banks
the project will adversely are reinforced and protected in normal
affect aquatic environments in circumstances.
the river? Are adequate
measures taken to reduce the
impacts on aquatic
environments, such as effects
on aquatic organisms?
(3) Hydrology Is there a possibility that N No possibility.
hydrologic changes due to the
project will adversely affect
surface water and
groundwater flows?
(4) Topography Is there a possibility that N No change in topography is anticipated. Disposal
and Geology excavation of rivers and sites for dredged materials taken from the
channels will cause a Pasig-Marikina River can raise disposal site
large-scale alteration of the elevation, but only on a very localized and
topographic features and negligible scale.
geologic structures in the
surrounding areas?
4. Social (1) (a) Is involuntary resettlement Y A census was conducted in November 2010. It
Environment Resettlement caused by project was found that there are 58 household to be
implementation? If affected by the construction activities of the Project
involuntary resettlement is along the Pasig River.
caused, are efforts made to In the process of planning and designing of the
minimize the impact of Project, efforts on structural components and
resettlement? construction methods are made to minimize the
number of households to be affected.
(f) Does the resettlement plan Y There are no indigenous peoples living in the
pay particular attention to project area.
vulnerable groups or persons, As a custom operation of resettlement, staff of
including women, children, the welfare department of the LGUs will attend the
elderly, people living below demolition work so that the rights of the vulnerable
81
the poverty line, ethnic people are not violated.
minorities, and indigenous Also, when the households are transported to the
peoples? resettlement sites, special arrangements will be
provided for the elderly and those with difficulty in
mobility.
(g) Are agreements with the Y During the public consultation meetings held twice
affected persons obtained so far, information was distributed orally, questions
prior to resettlement? were raised and answered, and PAFs showed
understandings about the resettlement plan.
Final agreements with the affected households are
to be obtained at the final stage of preparation of
the resettlement activity. The official documents
of agreement are obtained prior to resettlement.
(i) Have any plans been Y Internal Monitoring will be conducted by DPWH
developed to monitor the (ESSO, PMO and Consultant).
impact of resettlement? External Monitoring Team will be contracted by
DPWH.
Check lists for both Interior and External
Monitoring are included in the Resettlement Plan.
Cost for the external monitoring is to be included in
the Consulting Services.
(j) Is the grievance redress Y DPWH (PMO-MFCP I) will be the window for
mechanism established? receiving opinions, consultations and complaints.
Information about contact numbers and names
were shown on board during the public
consultation meetings in July 2011.
LIAC in each LGU will also work as the window.
PAFs may go to LGU staff (offices for social
welfare or urban poor affairs) for expressing
opinions, consultations and complaints.
All received opinions will be transfered to the LIAC
(Sub-Committee for Beneficiary, Selection, Awards
and Arbitration) for immediate action.
(2) Living and (a) Is there a possibility that Y There is a possibility that some informal settlers
Livelihood the project will adversely who are living on riverbanks and in right-of-way
affect the living conditions of areas will be relocated due to construction
inhabitants? Are adequate activities. They will be taken care of properly,
measures considered to according to the prepared RAP and JICA
reduce the impacts, if Guidelines.
necessary? Construction activities generate noise and exhaust
fumes via machine operation. Providing mufflers
and filters for the machineries maintains the
capacity to absorb and reduce noise levels and
exhaust fumes.
Barges and dredging boats used by the project
might hinder boats and ferry traffic. This hindrance
can be eased by consultation, IEC and
coordinating operation space, hours and dates.
Vehicles used for construction may block and
congest the streets. Barges can therefore be used
to ship construction materials and for construction
82
activities.
Dredged materials shall be covered or dried for
transportation to disposal area in such way that no
offensive odor or leak from dredged materials.
(b) Is there a possibility that N The Project regulates river water but does not use
the amount of water (e.g., it.
surface water, groundwater)
used by the project will
adversely the downstream
fisheries and other water
uses?
(c) Is there a possibility that N Cleaning of the river bank and constructing river
waterborne or water-related bank-protection will result in reduction of mosquito
diseases (e.g., breeding places and thus reduction of mosquito
schistosomiasis, malaria, infestation and related spread of disease.
filariasis) will be introduced? Moreover, suspended solids caused by excavation
will also help coagulate and settle floating viruses
and bacteria.
(3) Heritage Is there a possibility that the N There are no local archeological, historical,
project will damage the local cultural, or religious heritage sites reported on or
archeological, historical, around the Project site. Neither have such palaces
cultural, and religious heritage at small community levels been reported.
sites? Are adequate
measures taken to protect
these sites in accordance with
the country’s laws?
(4) Landscape Is there a possibility that the N River banks often serve as natural parks/river
project will adversely affect walks/water parks and serve amenity functions for
the local landscape? Are the local population. During construction activity,
necessary measures taken to some area will be adversely affected. But this is
deal with such adverse temporary and limited narrow area.
effects? Although vegetation might be lost temporarily due
to construction, it will grow back naturally in the
Philippines’ tropical climate.
(5) Ethnic (a) Does the project comply N/A N/A No ethnic group has been identified.
Minorities and with the country’s laws
Indigenous regarding rights of ethnic
Peoples minorities and indigenous
peoples?
(b) Is consideration given to N/A N/A Ditto
reducing impact on culture
and lifestyle of ethnic
minorities and indigenous
peoples?
(c) Is consideration given to N/A N/A Ditto
reducing impact on culture
and lifestyle of ethnic
minorities and indigenous
peoples?
(d) Will all of the rights of N/A N/A Ditto
ethnic minorities and
indigenous peoples in relation
to land and resources be
respected?
(6) Working (a) In the course of carrying N No, the Project is not violating national laws.
Conditions out the project, is the project
proponent violating any laws
or ordinances relating to
working conditions of the
country?
(b) Are tangible safety Y BOSH (Basic Occupational Safety and Health)
considerations in place for protocol and CCEP are followed in Phase II.
individuals involved in the Phase III is carried out in the same manner.
project, such as the Fences, warnings, notice-of-construction billboards
83
installation of safety and information campaigns are also provided.
equipment which prevents Proper environmental training is given to
industrial accidents, and construction workers by construction contractors.
management of hazardous Helmets and steel-toe shoes are worn by most
materials? construction workers. Occupational safety training
will be continuously and periodically provided and
appropriate safety measures will always be in
place.
(c) If construction activities Y Staff of IEC of the DPWH, MMT and Barangay
adversely affect the social captains are to handle complaints from residents
environment, are adequate affected by the construction, if any occur.
measures undertaken to Most construction workers are hired locally from
reduce the impact? the Barangay where construction takes place, with
the exception of a few skilled technicians and
engineers. In hiring local workers, gender equity
and appropriateness of assigning position are
considered. Hence, a damping effect of numbers
of workers and cash flooding into a Barangay will
84
not occur and disturbance of the social
environment will be minimized.
6. Note Note on Using If necessary, the impact on N/A N/A No county shares a border with Luzon island,
Environmental trans-boundary or global where the project takes place. The Philippines is
Checklist issues should be confirmed an island nation, and thus has no land borders.
(e.g., the project includes River improvement works for flood mitigation do
factors that may cause not cause global-scale climate change.
problems, such as
trans-boundary waste
treatment, acid rain,
destruction of the ozone layer,
or global warming).
85
ANNEX
A-1
ANNEX-1: ECC
A-2
A-3
A-4
A-5
A-6
ANNEX-2: Socio-Economic Survey in Project Affected Area
A-7
1. Survey Area
A-8
2. Survey Results
The road network enclosing the river line was used to determine the
A-9
main project affected area and to demarcate the project site from
which the sampling of respondents was obtained. Figure 2-1 presents
the project area.
Selection of household-respondents was through systematic random
sampling at estimated intervals sufficient to cover the stretch of the
barangay commencing from predetermined public landmarks until the
required number of samples on a certain spot has been satisfied.
A-10
61 to 70 years 2 1.9
71 to 80 years 3 2.8
TOTAL 107 100
Table Place of residence prior to current
3.1-5 Place of residence Frequency Percent
Same barangay 52 48.6
Another Barangay within LGU 31 29
Other LGU within Metro Manila 12 11.2
Outside Metro Manila 12 11.2
Total 107 100
Table Current tenurial status
3.1-6 Tenural status Frequency Percent
House structure owner 92 86
Rent-free occupant ( RFO) 3 2.8
Renter 12 11.2
TOTAL 107 100
Table Monthly rental of current dwelling
3.1-7 Amount Frequency Percent
Non-renters 95 88.8
1,200.00 1 0.9
1,500.00 1 0.9
2,000.00 2 1.9
2,500.00 1 0.9
3,000.00 4 3.7
4,000.00 2 1.9
5,000.00 1 0.9
TOTAL 107 100
Table Total number of HH in structure
3.1-8 Number of HH Frequency Percent
Structure with 1 HH 97 90.7
Structure with 2 HH 6 5.6
Structure with 3 HH 2 1.9
Structure with 4 HH 1 0.9
Structure with 6 HH 1 0.9
TOTAL 107 100
Table Range of total number of persons in structure
3.1-9 Number of persons Frequency Percent
Structures with 1 to 3 persons 29 27.1
Structures with 4 to 6 persons 59 55.1
Structures with 7 to 10 persons 17 15.9
Structures with 11 to 15 persons 2 1.9
A-11
Table Range of number of house/structure-owner (HO) and family
3.1-10 HH size Frequency Percent
House structure owner with 1 to 3 22 20.6
members
House structure owner with 4 to 6 52 48.6
members
House structure owner with 7 to 10 16 15
members
House structure owner with 11 to 15 2 1.9
members
Total 92 86
Non structure-owner 15 14
TOTAL 107 100
Table Total Number of persons living in the house/structure: Number
3.1-11 of rent-free occupants (RFO)
Rent-free occupants Frequency Percent
Non-RFO 104 97.2
Rent-free occupants with 5 HH 3 2.8
members
TOTAL 107 100
Table Total Number of Persons living in the house/structure:
3.1-12 Number of caregivers
Rent-free occupants Frequency Percent
HH with no caregivers 99 92.5
HH with 1 caregiver 5 4.7
HH with 2 caregivers 3 2.8
TOTAL 107 100
A-12
Table Specific ethnicity
3.1-15 Specific ethnicity Frequency Percent
Albayano 1 0.9
Bisaya 9 8.4
Pangasinense 2 1.9
Ilongo 7 6.5
Bicolano 7 6.5
Marinduqueno 1 0.9
Tagalog 1 0.9
Bulaqueño 1 0.9
Cebuano 1 0.9
Pampangueno 1 0.9
Not applicable 76 71
A-13
Not applicable 76 71
TOTAL 107 100
QUESTION:
A9. Ethnicity, Special Clan, Indigenous people: Does your household
member belong to a specific ethnic group or clan or “Indigenous
people”?
Table Religion
3.1-17 Religion Frequency Percent
Roman Catholic 100 93.5
Other Christian organization 2 1.9
Traditional/ indigenous belief 1 0.9
Iglesia ni Kristo 4 3.7
TOTAL 107 100
QUESTION:
A10. What is your religion?
Table River dependency
3.2-1 Dependency Frequency Percent
None 107 100
QUESTION:
B1.Do you depend on the Marikina river as a major resource to support
your family/ self?
Table Particular dependency
3.2-2 Particular dependency Frequency Percent
None 107 100
QUESTION:
B1.Do you depend on the Marikina river as a major resource to support
family/yourself?
Table Impact of river structure construction or closing
3.2-3 Impact Frequency Percent
None 106 99.1
Don't know 1 0.9
TOTAL 107 100
QUESTION:
B2. What do you lose if the Marikina river sides are closed for a year for
a construction, or forever?
Table Impact of dredging
3.2-4 Impact Frequency Percent
None 107 100
QUESTION:
B3. What do you lose if a large scale dredging activity takes place in the
Marikina river for many months?
Table Where solid waste is disposed
3.2-5 Activities Responses
Frequency Percent
A-14
Collected and disposed by waste 101 91
collectors
Discarded to the river 3 3
Discarded to open space 2 2
Burnt 5 5
TOTAL 111 100
QUESTION:
B4. Where do you dispose solid wastes
of?
Table Where wastewater is discharged
3.2-6 Activities Responses
Frequency Percent
Drained to pipes connected to city sewer 90 58
Drained to pipes directly connected to t 17 11
Discharged to open space/land 48 31
TOTAL 155 100
QUESTION:
B5. Where do you discharge wastewater
to?
Table Number of employed HH member
3.3-1 Household size Frequency Percent
HH with 1 member employed 67 62.6
HH with 2 members employed 23 21.5
HH with 3 members employed 3 2.8
HH with 6 members employed 1 0.9
HH with purely self-employed member/s 13 12.1
TOTAL 107 100
QUESTION:
C1. How many members of this household are currently working or
employed?
Table Number of HH members contributing to income
3.3-2 HH size Frequency Percent
HH with only 1 member contributing 20 18.7
HH with only 2 members contributing 63 58.9
HH with only 3 members contributing 22 20.6
HH with only 4 members contributing 1 0.9
HH with only 6 members contributing 1 0.9
Total 107 100
QUESTION:
C2. How many persons contribute to household
income?
Table Range of total income from salary
3.3-3 Frequency Percent
A-15
9,001 to 15,000 44 41.1
15,001 to 18,000 10 9.3
18,001 to 24,000 5 4.7
24,001 to 30,000 2 1.9
40,000 up 1 0.9
Total 94 87.9
Non-salary earners 13 12.1
TOTAL 107 100
QUESTION:
C3. What is the estimated total monthly income of your household for
the past month? (IN PESOS) – From regular employment.
A-16
0 107 100
QUESTION:
C3. What is the estimated total monthly income of your household for
the past month? (IN PESOS) – From agriculture.
Table Total monthly remittance from the Philippines
3.3-7 Amount Frequency Percent
1,000.00 2 1.9
3,000.00 4 3.7
3,500.00 1 0.9
Total 7 6.5
Those who are not receiving 100 93.5
TOTAL 107 100
QUESTION:
C3. What is the estimated total monthly income of your household for
the past month? (IN PESOS) – From remittances (from the Philippines).
Table Total monthly remittance from OFW/s
3.3-8 Amount Frequency Percent
5,000.00 1 0.9
15,000.00 2 1.9
37,000.00 1 0.9
Total 4 3.7
Those who are not receiving 103 96.3
TOTAL 107 100
QUESTION:
C3. What is the estimated total monthly income of your household for
the past month? (IN PESOS) – From remittances (OFW).
Table Range of total income from other sources (loans, gifts, etc.)
3.3-9 per annum
Amount Frequency Percent
5,000 and below 16 15
5,001 to 10,000 43 40.2
10,001 to 15,000 11 10.3
20,001 to 25,000 2 1.9
30,001 and above 1 0.9
Total 73 68.2
Those who are not earning from other 34 31.8
sources
TOTAL 107 100
QUESTION:
C3. What is the estimated total monthly income of your household for
the past month? (IN PESOS)
Table Range of total monthly income both from salary and various
3.3-10 sources (business, pension, remittances, etc
Amount Frequency Percent
3,000 to 9,000 14 13.1
A-17
9,001 to 15,000 41 38.3
15,001 to 18,000 29 27.1
18,001 to 24,000 16 15
24,001 to 30,000 3 2.8
30,001 to 40,000 2 1.9
40,001 up 2 1.9
TOTAL 107 100
QUESTION:
C3. What is the estimated total monthly income of your household for
the past month? (IN PESOS)
Table Range of total food expenses
3.3-11 Amount Frequency Percent
5,000 and below 21 19.6
5,001 to 10,000 76 71
10,001 to 15,000 9 8.4
20,001 to 25,000 1 0.9
TOTAL 107 100
QUESTION:
C4. In your estimate, how much does your household spend for the
following?
(in average in PESOS per month) –
Food.
Table Housing/ rental expenses
3.3-12 Amount Frequency Percent
Non renters 96 89.7
1,200.00 1 0.9
1,500.00 1 0.9
2,000.00 2 1.9
2,500.00 1 0.9
3,000.00 3 2.8
4,000.00 2 1.9
5,000.00 1 0.9
TOTAL 107 100
QUESTION:
C4. In your estimate, how much does your household spend for the
following?
(in average in PESOS per month) – Housing
(amortization/ rent).
Table Range of clothing expenses
3.3-13 Amount Frequency Percent
150 to 500 59 55.1
501 to 1,000 10 9.3
1,001 to 1,500 3 2.8
1,501 to 2,000 3 2.8
A-18
Total 75 70.1
Did not spend for clothing last year 32 29.9
A-19
25,001 to 3,000 1 0.9
TOTAL 107 100
QUESTION:
C4. In your estimate, how much does your household spend for the
following?
(in average in PESOS per month) –
Water.
Table Range of monthly power bills/ expenses
3.3-17 Amount Frequency Percent
100 to 1,000 28 26.2
1,001 to 2,000 56 52.3
2,001 to 3,000 15 14
3,001 to 4,000 3 2.8
4,001 to 5,000 5 4.7
TOTAL 107 100
QUESTION:
C4. In your estimate, how much does your household spend for the
following?
(in average in PESOS per month) –
Electricity.
Table Range of monthly telecommunication expenses
3.3-18 Amount Frequency Percent
100 to 300 58 54.2
301 to 600 26 24.3
601 to 900 14 13.1
901 to 1,200 4 3.7
Total 102 95.3
Those who are not spending on telecom 5 4.7
A-20
(in average in PESOS per month) – Fuel for cooking (LPG, kerosene,
charcoal, wood).
Table Range of average monthly medical expenses
3.3-20 Amount Frequency Percent
50 and below 64 59.8
51 to 100 33 30.8
101 to 150 4 3.7
151 to 200 3 2.8
201 and up 3 2.8
TOTAL 107 100
QUESTION:
C4. In your estimate, how much does your household spend for the
following?
(in average in PESOS per month) –
Medical bills.
Table Recreational expenses
3.3-21 Amount Frequency Percent
0 64 59.8
500 18 16.8
600 1 0.9
1,000.00 14 13.1
1,500.00 5 4.7
1,700.00 2 1.9
1,800.00 2 1.9
2,000.00 1 0.9
TOTAL 107 100
QUESTION:
C4. In your estimate, how much does your household spend for the
following?
(in average in PESOS per month) – Entertainment/
recreation.
Table Monthly remittance to relatives outside HH
3.3-22 Amount Frequency Percent
0 94 87.9
200 2 1.9
500 7 6.5
700 1 0.9
1,000.00 1 0.9
2,000.00 1 0.9
3,000.00 1 0.9
TOTAL 107 100
QUESTION:
C4. In your estimate, how much does your household spend for the
following?
A-21
(in average in PESOS per month) – Remittances to relatives outside
household.
Table Expenses for gambling
3.3-23 Amount Frequency Percent
Those not spending for gambling 94 87.9
200 6 5.6
300 2 1.9
500 4 3.7
1,000.00 1 0.9
TOTAL 107 100
QUESTION:
C4. In your estimate, how much does your household spend for the
following?
(in average in PESOS per month) –
Gambling.
Table Expenses for cigarette/ alcohol
3.3-24 Amount Frequency Percent
Those not spending for cigarette/ alcohol 62 57.9
500 6 5.6
800 2 1.9
1,000.00 37 34.6
TOTAL 107 100
QUESTION:
C4. In your estimate, how much does your household spend for the
following?
(in average in PESOS per month) –
Cigarette/ alcohol.
Table Range of total monthly expenses
3.3-25 Amount Frequency Percent
3,000 to 9,000 20 18.7
9,001 to 15,000 35 32.7
15,001 to 18,000 27 25.2
18,001 to 24,000 20 18.7
24,001 to 30,000 4 3.7
30,001 to 40,000 1 0.9
TOTAL 107 100
QUESTION:
C4. In your estimate, how much does your household spend for the
following?
(in average in PESOS per month).
Table Savings
3.3-26 Amount Frequency Percent
None 1 0.9
A-22
Php1,000-1,999 25 23.4
Php2,000-2,999 16 15
Php3,000-3,999 5 4.7
4,000 - 4,999 7 6.5
Php5,000-9,999 9 8.4
Php10,000 or over 5 4.7
TOTAL 107 100
QUESTION:
C5. On average, how much of your net income are you able to save in
a month?
Table Range of age of structure
3.4-1 Age of structure Frequency Percent
1 to 10 years 18 16.8
11 to 20 years 31 29
21 to 30 years 22 20.6
31 to 40 years 13 12.1
41 to 50 years 14 13.1
51 to 60 years 7 6.5
61 to 65 years 2 1.9
TOTAL 107 100
QUESTION:
D1. Age of Structure:
Table Type of structure
3.4-2 Structure type Frequency Percent
Single-detached 82 76.6
Duplex 24 22.4
Apartment/ condo/ townhouse/ rowhouse 1 0.9
TOTAL 107 100
QUESTION:
D2. Type of Structure.
Table Use of structure
3.4-3 Use of structure Frequency Percent
Residential 58 54.2
Residential-commercial 48 44.9
Residential-industrial 1 0.9
TOTAL 107 100
QUESTION:
D3. Use of Structure.
Table House storey/ level
3.4-4 Number of level/s Frequency Percent
Structures with 1 level 85 79.4
Structures with 2 levels 22 20.6
A-23
TOTAL 107 100
QUESTION:
D4. Structure Dimension.
Table Range of total gross floor area in square meter
3.4-5 Total gross area Frequency Percent
50 and below 30 28
51 to 100 63 58.9
101 to 150 9 8.4
151 to 200 4 3.7
301 to 360 1 0.9
TOTAL 107 100
QUESTION:
D4. Structure Dimension.
Table Type of house structure
3.4-6 Structure type Frequency Percent
Type II - Light (nipa, cogon,bamboo, 4 3.7
lightwood)
Semi-concrete 45 42.1
Type IV - Concrete 30 28
Type V - Mixed materials 28 26.2
TOTAL 107 100
QUESTION:
D5. Type of House/Structure (materials dominantly
used).
Table Type of wall materials
3.4-7 Main walling materials Frequency Percent
Type II - Light (nipa, cogon, bamboo, 11 10.3
etc.)
Semi-concrete 66 61.7
Type IV - Concrete 2 1.9
Type V - Mixed materials 28 26.2
TOTAL 107 100
QUESTION:
D6. Type of housing materials for walls.
Table Type of roofing materials
3.4-8 Main roofing materials Frequency Percent
Light (nipa, cogon, bamboo, lightwood) 4 3.7
Galvanized iron 99 92.5
Concrete/ cement 4 3.7
TOTAL 107 100
QUESTION:
D7. Type of housing materials for roof.
Table Type of flooring materials
3.4-9
A-24
Main flooring materials Frequency Percent
Soil 1 0.9
Gravel/ pebbles 1 0.9
Wood 12 11.2
Concrete 88 82.2
Mixed 5 4.7
TOTAL 107 100
QUESTION:
D8. Type of housing materials for floor.
Table Type of toilet facility
3.4-10 Toilet type Frequency Percent
Water sealed (flush or pour/ flush) 10 9.3
connected to sewerage
Water sealed (flush or pour flush) 96 89.7
connected to septic tank
Shared toilet 1 0.9
TOTAL 107 100
QUESTION:
D9. Type of toilet facility that household have/use. [PROBE OR
OBSERVE].
Table Primary source of water for domestic use
3.4-11 Water source Frequency Percent
Piped connection 99 92.5
Public/ street faucet 1 0.9
Water vendor 7 6.5
TOTAL 107 100
QUESTION:
D10. Primary source(s) of water for
domestic use.
Table Facility within 20 minutes walk
3.4-12 Facility Responses
Frequency Percent
Hospital/ clinic 75 8.90%
School 102 12.10%
Fire station 68 8.10%
Church or other religious places 58 6.90%
Market place 60 7.10%
LGU office 105 12.50%
Police station 54 6.40%
Evacuation center 106 12.60%
Barangay center 107 12.70%
Women center 106 12.60%
TOTAL 841 100.00%
QUESTION:
A-25
D11. Do you have following facilities within 20 min of walking distance in
between the river and nearest main avenue?
A-26
Secondary - unfinished 3 2.8
Secondary - graduated 15 14
Vocational - unfinished 1 0.9
Vocational - graduated 33 30.8
College - unfinished 18 16.8
College - graduated 37 34.6
TOTAL 107 100
QUESTION:
F.1 What is the highest educational achievement at your
household?
Table Number of years spent in schooling
3.6-2 Years of schooling Frequency Percent
1 4 3.7
2 16 15
3 38 35.5
4 49 45.8
TOTAL 107 100
QUESTION:
F.1 What is the highest educational achievement at your
household?
Table Member/s of the HH who stopped schooling
3.6-3 Schooling HH member/s Frequency Percent
Those who stopped 16 15
Those who did not stop 91 85
TOTAL 107 100
QUESTION:
F.2 Are there members of the HH of schooling age (6-17 yrs.old) who
stopped schooling during the past three (3) years?
Table Reason for stopping schoo
3.6-4 Reasons Frequency Percent
No money 15 14
Had to work 1 0.9
Not applicable 91 85
TOTAL 107 100
QUESTION:
F.3 Why did the member (s) stopped
going to school?
l
Table Language used in communication with non-HH member
3.6-5 Language used Frequency Percent
Tagalog only 56 52.3
Mix of Tagalog and English 51 47.7
TOTAL 107 100
QUESTION:
A-27
F.4 What language do you use to communicate to people outside of
your family members?
Table Illness in the HH in the last 6 months
3.7-1 Illness Frequency Percent
Did not suffer illness in the last 6 months 66 61.7
Malaria 3 2.8
Diarrhea 35 32.7
Dengue 2 1.9
Other infectious illness 1 0.9
QUESTION:
G.1 In the last 6 months have you and your family member had illness
stated below?
Table Those who were informed regarding the flood control project
3.8-1 Flood control project information Frequency Percent
Not informed 72 67.3
Informed 35 32.7
TOTAL 107 100
QUESTION:
H.1 Have you been informed about the flood control project which will
take place in your barangay?
Neighbor 20 18.7
Barangay chairman/ kagawad/ worker 13 12.1
Friend 1 0.9
Media 1 0.9
Not applicable (/not informed) 72 67.3
TOTAL 107 100
QUESTION:
H.1 Have you been informed about the flood control project which will
take place in your barangay?
Table Frequency of information
A-28
3.8-4 Frequency Frequency Percent
Once 25 23.4
Twice 10 9.3
Not applicable (/not informed) 72 67.3
TOTAL 107 100
QUESTION:
H.1 Have you been informed about the flood control project which will
take place in your barangay?
Table Media used in informing
3.8-5 Media used Frequency Percent
At meeting 23 21.5
Rumors 10 9.3
Neighbors 1 0.9
TV 1 0.9
Not applicable (/not informed) 72 67.3
TOTAL 107 100
QUESTION:
H.1 Have you been informed about the flood control project which will
take place in your barangay?
Table Approval rating of the project
3.8-6 Project approval Frequency Percent
Those who do not approve 2 1.9
Those who approve 105 98.1
TOTAL 107 100
QUESTION:
H.2 Do you agree to the project?
Table Flood damages since 1998
3.9-1 Flood damage experience Frequency Percent
Did not suffer 8 7.5
Did suffer 99 92.5
TOTAL 107 100
QUESTION:
I.1 Have you had flood damage since
1998?
Table Date/s of flooding
3.9-2 Activities Responses
N Percent
Sep-09 96 83.5
Nov-07 5 4.3
Jun-05 1 0.9
Jan-04 1 0.9
Nov-00 3 2.6
Apr-00 8 7
A-29
Dec-99 1 0.9
TOTAL 115 100
QUESTION:
I.1.4 When have you had flood?
Table Origin of floodwaters
3.9-3 Origin Responses
N Percent
River 99 90.8
Other than river 4 3.7
Can't specify 6 5.5
TOTAL 109 100
QUESTION:
I.1.5 Where did the water come from?
Table Flood loss
3.9-4 Activities Responses
N Percent
Cash 3 3.20%
Furniture 72 76.60%
House 18 19.10%
Family member 1 1.10%
TOTAL 94 100.00%
QUESTION:
I.1.6 What did your household lose for
the flood?
Table Coping mechanism of the HH/ family
3.9-5 Activities Responses
N Percent
Stayed at home 64 55.20%
Escaped to the shelter 5 4.30%
Moved to somebody's House 7 6.00%
Moved to higher place 38 32.80%
Other 2 1.70%
TOTAL 116 100.00%
QUESTION:
I.1.7 How did you cope with the flood?
Table Presence/ existence of coping mechanism of the community
3.9-6 on flood
Attribution Frequency Percent
Without coping mechanisms 105 98.1
With coping mechanisms 2 1.9
TOTAL 107 100
QUESTION:
I.1.8 Do you/ does your community have flood coping
mechanism now? How?
A-30
Table Specific coping mechanism of the community
3.9-7 Coping mechanism Frequency Percent
Moved to evacuation center 2 1.9
Not applicable 105 98.1
TOTAL 107 100
QUESTION:
I.1.8 Do you/ does your community have flood coping
mechanism now? How?
A-31
2-4 SUMMARY OF RESULTS
A-32
Lowest and highest income derived from remittance/s from
the Philippines is Php1,000 and 3,000, respectively (Table
3.3-7), while from OFWs are 5,000 and 37,000, respectively
(Table 3.3-8). Most or 40 percent of other sources of income
such as loans and gifts range from Php5,001 to 10,000 (Table
3.3-9) per annum. Most or 38 percent of the respondents
earn a total or combined monthly income (both from
employment/ salary and various sources) of Php9,001 to
15,000 (Table 3.3-10).
A-33
to facilities such as barangay hall/ center, school, LGU office,
evacuation center, etc. (Tale 3.4-12).
3.5 Community There is neither a special place passed down through
generation nor an organization related to Marikina River
(Tables 3.5-1 and 3.5-2). Most or 84 percent are not member
of any organization (Table 3.5-3). Majority of those who are
member of an organization belong to a homeowners
association (Table 3.5-4) and all do not consider any adverse
effect on them of the closure of Marikina River (Table 3.5-5).
3.6 Education Most or 35 percent of the households have a member who
has graduated from college (Table 3.6-1). Most also or 46
percent have at least 4 years of schooling (Table 3.6-2).
Fifteen percent stopped schooling (Table 3.6-3) mostly for
financial reasons (Table 3.6-4).
3.7 Health and Majority or 62 percent of the households did not have any
hygiene member who suffered from any illness for the past 6 months.
Those who were ill consisting of 33 percent were mostly due
to diarrhea (Table 3.7-1).
3.8 Awareness Only 33 percent of households were informed regarding the
flood control project (Table 3.8-1), most or 30 percent of them
on 2009 and 2010 (Table 3.8-2). Main source of information
are neighbors (Table 3.8-3) and most were informed only
once (Table 3.8-4) through (informal) meetings (Table 3.8-5).
A-34
2 Survey Sheet
A-35
CHECK LIST
LIST OF IHOUSEHOLDS
MAP
SURVEY SHEETS /QUESTIONNAIRES
YOUR ID
PENCILS (1 DZ)
ERASER
CLIPBOARD
CALCULATOR
WATCH
WATER PROOF BAG TO KEEP ALL SURVEY SHEETS IN
A-36
SOCIO‐ECONOMIC SURVEY OF HOUSEHOLDS
AFFECTED BY THE
PASIG‐MARIKINA RIVER CHANNEL IMPROVEMENT PROJECT
General Guidelines for Conducting the Interview
1. Choose a setting with little distraction. Avoid loud lights or noises,
ensure the interviewee is comfortable (you might ask them if they
are), etc. Often, they may feel more comfortable at their own places
of work or homes.
2. Explain the purpose of the interview.
3. Address terms of confidentiality. Explain who will get access to their
answers and how their answers will be analyzed. You might also need
to inform that “Rest assured that your answers will be kept
confidential and that your name will not be associated with your
responses in this interview.”
4. Explain the format of the interview. Explain the type of interview you
are conducting and its nature. If you want them to ask questions,
specify if they're to do so as they have them or wait until the end of
the interview.
5. Indicate how long the interview usually takes.
6. Tell them how to get in touch with you later if they want to.
7. Ask them if they have any questions before you both get started with
the interview.
8. Explain definition of HOUSE HOLD and make sure that answers are
given based on a household.
9. Please check in an appropriate box when applicable. Follow the
instructions given in each of the section. Do not leave any item blank.
Write NAP if the question does not apply.
10. During interview read ALL the choices of answers that the
interviewee can chose from before he/she give you answer.
Interviewer:
Name: Mr/Ms/________________________________________________
Respondent:
HH ID No. ______
Name: Mr/Ms/Mrs
Address:
City:
Barangay:
Telephone: _______________________________________
A-37
Instruction: Please appropriate box and do not leave any item blank. Write NAP if the
question does not apply.
SECTION A. BASIC HOUSEHOLD INFORMATION
NAME OF HOUSEHOLD HEAD (LAST NAME, FIRST NAME, MIDDLE NAME); USE PRINT
CAPITAL LETTER
A1. Relationship of Respondent to the HH Head:
[ ] 1 Household Head [ ] 2 Spouse of HH head [ ] 3 Child
of HH head
[ ] 4 Parent of HH head [ ] 5 Sibling
[ ] 6 Other Relative
[ ] 7 No relation (maid, friend, etc.)
A2. Sex of HH Head: [ ] 1 Male [ ] 2 Female
[ ] 3 Transgender
A3. Marital Status of HH Head: [ ] 1 Single [ ] 2 Married
[ ] 3 Separated
[ ] 4 Widow/er [ ] 5 Common Law Spouse [ ]
6 Cohabitation
A4. Number of years household has been residing in current address: _________ years
(Note if he/she moved here after 1998 survey)
A5. Place of residence prior to current place of residence:
1 Same barangay 2 Another barangay within LGU 3
Other LGU within Metro Manila
4 Outside Metro Manila 5 Others, ________________
A6. Current Tenurial status: 1 House/Structure Owner (HO) 2
Rent‐Free Occupant (RFO)
3 Renter, Monthly rent: ___________
[ 4 Other: ___________
A7. Total Number of households in the house/structure: ______
A8. Total Number of Persons living in the house/structure: _______
House/Structure Owner (HO) & family ______
Rent‐Free Occupants (RFO) ______
Caregivers ______
Renters _____
A9. Ethnicity, Special Clan, Indigenous people: Does your household member belong to a specific
ethnic group or clan or “Indigenous people”? 1 Yes 2 No,
If YES, what is it? Please specify here:
originated from:
A10. What is your religion? 1 Roman Catholic, 2 Other Christianity,
3 Islam
4 Traditional/Indigenous belief:
Specify , 5 Others:
Specify
A-38
SECTION B. RIVER AND LIFE
B1.Do you depend on the Marikina river as a major resource to support family/yourself?
[ ] 1 No, [ ] 2 Yes, If YES please answer the following: My
life is depending on:
[ ] 3 the fish and other aquatic creatures from the river, [ ] 4 Vegetables
and fruits cultivated on the river side, [ ] 5 Operating or using a boat, [ ]
6 Water, [ ] 7 Trades or other commercial activities that take place on the river, 8
Others, Specify: _____________________
B2. What do you lose if the Marikina river sides are closed for a year for a construction, or forever?
[ ] 1 Nothing, [ ] 2 Source of major income, [ ] 3
Time(need extra time to perform daily tasks), [ ] 4 Religious activity, [ ] 5
Important place for a cultural activity, [ ] 6 Recreational place,
[ ] 7 A connection to my family, relatives and friends, [ ] 8 Others, Specify:
_____________________ __
B3. What do you lose if a large scale dredging activity takes place in the Marikina river for many
months?
[ ] 1 Nothing, [ ] 2 Source of major income, [ ] 3
Mean of transportation,
[ ] 4 Others, Specify: _____________________ __
B4. Where do you dispose solid wastes of?
[ ] 1 Collected and disposed of by wastes collectors [ ] 2 Discard to the river
[ ] 3 Discard to open space/ land [ ] 4 Burn [ ]
5 Don’t know [ ] 6 Others, specify ___________________
B5. Where do you discharge wastewater to?
[ ] 1 Drain pipes that are connected to city sware [ ] 2 Drain pipes that are
directly connected to the river
[ ] 3 Discharge to open space/ land [ ] 4 Don’t know [ ] 5
Others, specify ___________________
A-39
SECTION C. HOUSEHOLD ECONOMIC PROFILE
C1. How many members of this household are currently working or employed? _______
A-40
SECTION D. HOUSING CONDITIONS AND BASIC SERVICES
D1. Age of D2. Type of Structure:
Structure: [ ] 1 Single‐Detached [ ] 2 Duplex
[ ] 3 Apartment/Condo/Townhouse/Row House
______ years [ ] 4 Commercial/Industrial building [ ] 5
Others, specify ___________________
D3. Use of Structure:
[ 1 Residential 2 Residential‐Commercial [ 3
Residential‐Institutional 4 Residential‐Industrial
5 Commercial 6 Institutional
[ ] 7 Industrial 8 Others ____________
D4. Structure Dimension D5. Type of House/Structure (Materials
Storeys/Floors Length and Gross Floor dominantly used)
(Encircle No. of *For observation and recording by the
Width Area = L x W (in
Storeys) interviewer
(in meters) sq. meters)
[ ] Type I Salvaged (plastic,
1 L =
tin, cardboard)
W=
2 L =
[ ] Type II Light (nipa, cogon,
W=
bamboo, light wood)
3 L =
W=
[ ] Type III Semi‐concrete
Total Gross Floor Area [ ] Type IV Concrete
[ ] Type V Mixed materials
D6. Type of housing materials for walls: [ ] 1 Salvaged (plastic, tin, cardboard)
*For observation and recording by [ ] 2 Light (nipa, cogon,
bamboo, light wood) [ 4 Semi‐concrete
the interviewer [ 3
Concrete (hollow blocks/bricks) [ 5 Mixed
D7. Type of housing materials for roof: [ ] 1 Salvaged (plastic, tin, cardboard)
[ ] 2 Light (nipa, cogon, bamboo) [ ] 3 Galvanized iron
*For observation and recording by [ ] 4 Concrete/Cement
[ ] 5 Others, specify _____________
the interviewer
D8. Type of housing materials for floor: [ ] 1 Soil
[ ] 2 Gravel/Pebbles [ ] 3 Wood
*For observation and recording by the interviewer
[ ] 4 Concrete [ ] 5 Mixed
A-41
D9. Type of toilet facility that household have/use: [PROBE OR OBSERVE]
[ ] 1 Water‐sealed (flush or pour/flush) connected to sewerage system
[ ] 2 Water‐sealed (flush or pour/flush) connected to septic tank [ ] 6
Non‐water sealed (open pit privy, overhang)
[ ] 3 Water‐sealed (flush or pour/flush) connected to pit
[ ] 7 Shared toilet
[ ] 4 Water‐sealed (flush or pour/flush) connected to drainage [ ]
8 Public toilet
[ ] 5 Non‐water sealed (ventilated improved pit, sanitary pit privy, [ ] 9
No toilet (wrap and throw, arinola,
closed pit)
bush, lake, creek, river)
D10. Primary source(s) of water for domestic use
[ ] 1 Piped connection [ ] 5
Rain
[ ] 2 Public/Street faucet [ ] 6
Water vendors (e.g, bottled water, container, peddlers)
[ ] 3 Deep or shallow well [ ] 7
Others; Specify: _______________________
[ ] 4 Pasig or Marikina River
D11. Do you have following facilities within 20 min of walking distance in between the river and
nearest main avenue?
[ ] 1 Hospital /Clinic [ ] 5
Market place [ ] 8 Evacuation centre
[ ] 2 School [ ]
6 LGU office [ ] 9 Barangay center
[ ] 3 Fire station [ ] 7
Police station [ ] 10 Women’s center
[ ] 4 Church or other religious places you and your family member attend
[ ] 11 Others (Specify if there is a significant places):
A-42
SECTION E. COMMUNITY
E1. .Do you have following special places that have been passed down for generations in your Barangay?
[ ] 1 Sacred place [ ] 2 Nature worshipping site, Animism [ ]
3 indigenous religious site
[ ] 4 traditional/heritage site [ ] 5 other, specify:
E2. Does your barangay have an association or group that closely related to Marikina River?
1 Yes 2 No, If YES please specify:
E3. Are you or any member of your household a member of an organization or association/s (in/out of
community):
1 Yes 2 No
If YES please specify:
E4. Type of organization:
1 Home Owners Association, 2 Cooperative, 3
Women’s group, 4 Savings group,
5 Religious organization, 6 Others ______________
E6. What do you lose if you are no longer a part of the organization that is given at E4 because of
inaccessibility to the Marikina River?
1 No effect at all, 2 social support, 3 privilege ,
4 income source,
5 mental and moral support, 6 Others ______________
SECTION F. EDUCATION
F1. What is the highest educational achievement at your household?
Chose “UF” for “unfinished”, “G” for “graduated” in below table.
Primary Secondary Vocational College(4yr) Master Doctor
No education UF G UF G UF G UF G UF G UF G
check
No. of years
F2. Are there members of the HH of schooling age (6‐17 yrs. old) who stopped schooling during the
past three (3) years?
1 Yes 2 No, If YES go to F3
F3. Why the member(s) stopped going to school?
1 No money [ ] 2 Had to work 3 school is too far
from home
[ ] 4 Others, pls. specify
F4. What language do you use to communicate to people out side of your family members?
1 Tagalog only, 2 English only, 3 Mix of Tagalog and English
4 Other: Specify
A-43
SECTION G. HEALTH and HYGIENE
G 1. In last 6 month have you and your family member had illness stated below?
[ ] 1 Malaria, [ ] 2 Diarrhoea, [ ] 3
Dengue, [ ] 4 HIV/AIDS, [ ] 5 Other STDs
[ ] 6 Other inflectional illness; Specify: ______________________
SECTION H. AWARENESS
H1. Have you been informed about the Flood control project which will take place in your Barangay?
[ ] 1 No, [ ] 2 Yes: If Yes, then ; When were you informed
first time? : __________ __________
Whom did you get informed by? : _______________________ How often?:
_____________________ __
How was the message emitted, type of media? (e.g. at meeting, by TV, by Ads, by radio):
_____________________
H2. Do you agree to the project?
[ ] 1 No, [ ] 2 Yes
SECTION I. Flood damage
I1. Have you had flood damages since 1998?
[ ] 1 No, [ ] 2 yes; If YES please answer the following
questions:
3. How many times?
4. When have you 5. Where did the 6. What did your 7. How did you cope
had flood? (year water come from? household lose for the with the flood? (If #4 is
/month) flood? (count only within chosen, pls specify)
where you live)
[ ] 1 River [ ] 1 Cash [ ] 1 Stay
[ ] 2 Other [ ] 2 Furniture at house
than River (e.g. pipe ) [ ] 3 House [ ] 2
[ ] 3 Can’t [ ] 4 Family Escaped to the shelter
specify member [ ] 3 Move to
[ ] 5 Other somebody’s house
[ ] 4 Moved
to higher place
[ ] 5 Other
[ ] 1 River [ ] 1 Cash [ ] 1 Stay
[ ] 2 Other [ ] 2 Furniture at house
than River (e.g. pipe ) [ ] 3 House [ ] 2
[ ] 3 Can’t [ ] 4 Family Escaped to the shelter
specify member [ ] 3 Move to
[ ] 5 Other somebody’s house
[ ] 4 Moved
to higher place
[ ] 5 Other
[ ] 1 River [ ] 1 Cash [ ] 1 Stay
[ ] 2 Other [ ] 2 Furniture at house
than River (e.g. pipe ) [ ] 3 House [ ] 2
[ ] 3 Can’t [ ] 4 Family Escaped to the shelter
specify member [ ] 3 Move to
[ ] 5 Other somebody’s house
A-44
[ ] 4 Moved
to higher place
[ ] 5 Other
[ ] 1 River [ ] 1 Cash [ ] 1 Stay
[ ] 2 Other [ ] 2 Furniture at house
than River (e.g. pipe ) [ ] 3 House [ ] 2
[ ] 3 Can’t [ ] 4 Family Escaped to the shelter
specify member [ ] 3 Move to
[ ] 5 Other somebody’s house
[ ] 4 Moved
to higher place
[ ] 5 Other
8. Do you /Does your community have flood coping mechanism now? How?
[ ] 1 No [ ] 2 Yes, If YES please specify:
End of Survey
A-45