Project Prefab Seminar
Project Prefab Seminar
Project Prefab Seminar
ON
CONTENTS PAGE
ACKNOWLEDGMENT.............................................................................................................................2
Abstract.......................................................................................................................................................3
CHAPTER ONE : INTRODUCTION.........................................................................................................4
1.1. BACKGROUND..................................................................................................................4
1.2. STATEMENT OF THE PROBLEM...................................................................................6
1.3. RESEARCH QUESTIONS..................................................................................................7
1.4. OBJECTIVES OF THE STUDY.........................................................................................7
1.4.1. GENERAL OBJECTIVE...........................................................................................................7
1.4.2. SPECIFIC OBJECTIVES..........................................................................................................7
1.5. SCOPE OF THE STUDY....................................................................................................8
1.6. LIMITATIONS....................................................................................................................8
1.7. NEED OF THE STUDY......................................................................................................8
1.8. METHOD OF THE STUDY................................................................................................8
CHAPTER TWO : LITRECTURE REVIEW.............................................................................................9
ACKNOWLEDGMENT
We would like to express my deepest appreciation to Prof. Dr.-Ing. Abebe Dinku for his
valuable advice, encouragements, constructive advice, and continuous guidance in the whole
process of this courses and helps us to make fruitful paper.
We would like to acknowledge those who had helped us during site visits and those respond our
interviews with patience and collaboration, in giving accurate data for us.
Besides writing of this Seminar paper, We would like to thank those friends who had given us
comments during every step of our work for the success of this paper completion.
Abstract
Construction is an important activity that has to be done very carefully. In present scenario
there is a large need for Industrial Development. So it has to be completed at some faster rate
without affecting the cost. But with the conventional construction the speed cannot be achieved.
So we opt for some other methods of construction. Prefabrication construction is one of the
method by which the total time of construction can be minimized. Prefabrication construction
has its own advantages such as it reduces the construction time; the erection is easy etc. but still
in countries like Ethiopia there is a hesitation to accept the prefabrication technology. So a
study is done comparing the conventional construction and Pre-Engineered Building
construction based on time and cost. So, various literatures are studied and the scheduling and
estimation is done separately for both the methods of construction and results are obtained
based on this comparison. Pre-Engineering Building is the recently trend for construction of
industrial building, residential building, malls, warehouse, etc. in Ethiopia. Now a days, a large
scope of PEB buildings with many advantages like light weight, short erection time period, easy
maintenance, weather proof, provision of future expansion and also good control over quality.
In this paper, a comparative study of Pre-Engineering Building (PEB) with Conventional one of
two area different area such as 3,000 m2 and 5,000m2 are analyzed.
From the study results, it can induce the relationship between the time and costs evaluation. The
overall construction period for the conventional building construction method was ------- days
while the PEB construction method was ------- days. As compared across the results for the
project construction costs, it shows that PEB construction method with ----------- ETB is more
cost effective with about 19% less than the conventional building method with total amount of
-----------ETB. The results reflect the significance on selection of the construction method,
namely the PEB construction method not only can shorter the construction periods but also
reduce the construction costs since it reduces greatly the expenses on the project direct costs
particularly the machineries costs.
Also a questionnaire is done to analyze the various risks in precast construction and the
analysis is done based on several factors that leads to injury. Further a checklist is also
prepared so that to ensure safety in precast construction by collecting data from precast office.
Key Words: PEB, Conventional, comparison, risks, checklist.
CHAPTER ONE : INTRODUCTION
1.1. BACKGROUND
Construction industry plays a vital role in any developing country. This is mainly because
developing countries are considerably dependent on the growth and development of their
physical infrastructures and because the linkage of the construction industry to both economic
and social sectors is very significant. A wide range of Industries and construction facilities are
required by our country, including Industrial parks, commercial property, manufacturing
facilities, schools, hospitals, complex transport infrastructure, and so on.
Technological improvement over the year has contributed immensely to the enhancement of
quality of life through various new products and services. One such revolution was the pre-
engineered buildings. Through its origin can be traced back to 1960’s its potential has been felt
only during the recent years. This was mainly due to the development in technology, which
helped in computerizing the design.
The prefab industry is the backbone for the development of new ideas in construction business of
any country; factory buildings, residential buildings and the industrial township are needed
practically by all the sectors, either to support the manufacturing or services of any industry.
In its steadfast development, the construction industry has discovered, invented and developed a
number of technologies, systems and products, one of them being the concept of Pre-engineered
Buildings (PEBs). As opposed to being on-site fabricated, PEBs are delivered as a complete
finished product to the site from a single supplier with a basic structural steel framework with
attached factory finished cladding and roofing components. The structure is erected on the site
by bolting the various building components together as per specifications.
Pre-Engineered Buildings (PEB) is the future for Ethiopia. Most of the Ethiopians business
community is just started to realize the benefits of PEB's. Where you have been building with
concrete for as long as anyone can remember, it is difficult to change. However Ethiopia's most
progressive companies are seeing the benefits of PEB‟s. The Pre-engineered Building is the
combination of pre-casted and pre-fabricated structures. These are generally ideal for offices,
houses, showrooms, shop fronts etc. Long span, Column free structures are the most essential in
any type of industrial structures and Pre Engineered Buildings (PEB) fulfill this requirement
along with reduced time and cost as compared to conventional structures. This methodology is
versatile not only due to its quality pre- designing and prefabrication, but also due to its light
weight and economical construction.
Industrial building is generally classified as braced and unbraced framed structures. In braced
buildings, the trusses rest on column with hinges and stability is provided by bracings in three
mutually perpendicular planes. The basic function of a bracing is to transfer horizontal loads
from frames i.e. loads like wind or earth quake or horizontal surge due to acceleration and
breaking of travelling cranes over gantry girders to the foundation. The longitudinal bracing
provides stability in longitudinal direction on each longitudinal end provides. The gabble bracing
provides stability in the lateral direction. The tie bracing at the bottom chord level transfers the
lateral loads (due to wind or earthquake) of truss to the end gabble bracings and similarly the
rafter bracing and the bracing system at bottom chords work. Whereas the purlin acts as the
lateral bracings to the compression chords of the roof trusses which increases the compression
chord’s design strength.
The unbraced frames such as portal frames are the most common type of frames used in
industrial building construction because of its simple design, economy, easy and fast erection.
This type of frames provides the large utility area with maximum column free space. In such
type of structures the inner columns are eliminated, requires considerably less Foundation and its
area, the valley gutters and the internal drainage too. The portal frame is a rigid jointed plane
made from hot rolled or cold rolled sections, supporting roofing and side cladding. It's typical
span ranges from 30-40 m and its bay spacing could be 4.5-10 m.
1.2. STATEMENT OF THE PROBLEM
Now days, in world construction sector using prefabricated elements for Industrial Shed
construction has been growing. According to David (2014) prefabricated construction is
preferred in Industrial sector for the reasons that benefits occur right across the value chain to
investor and manufacturer.
The development of Manufacturing industry is becoming a very critical and backbones for the
economic developments of the country. Even though it become critical sector currently there are
so many problems in Ethiopian Manufacturing industry construction industry. Some study states
that delays in construction of manufacturing industry projects are common in Ethiopia and the
project cost for the completion of the project is also high. The other thing is the quality problem
of the works is also under question especially to concrete structural elements
As time is one of the main factors in construction industry, time overrun affects the overall cost
of the project by additional overhead cost, change of material price because of additional time
and inflation. As construction method is playing an important role to eliminate those problems
and satisfying the growing demand of residence in the city. Adopting using PEB is one of the
best methods to minimize the quality problem which occurred by poor workmanship and low-
quality material, minimize the problems occurred by construction delay and to minimize cost of
construction.
1.6. LIMITATIONS
The study does not include the design aspect.
Pre Engineered metal buildings use the combination of built-up members, hot rolled, cold form
elements which make the basic steel frame work and other accessories canopy, fascia, clip, trim,
deck sheet for mezzanine floor, ridge vent, bracing, sag rod etc. Build up members are used for
primary members (Rafter and Column) as per optimum requirement with the help of bending
moment diagram, thus reducing wastage of material and self-weight of the structure, due to
reducing self-weight the reaction at support will be reduced and foundation will be light thus
structure become economical. Z & C sections are used as secondary members (Purlin and Girt).
All these components of PEB are fabricated in factories after designing and assemble on site for
erection. Now a days, PEB buildings have become very popular in India because these buildings
are most economical, low cost, short erection time period, light weight, seismic and wind
resistant, water proof & wall covering structure etc. one distinct advantage of PEB buildings
have become bolted is it can be dismantled and relocate. Three types of frames are used in PEB
structure, rigid frame, post end beam and semi rigid frame. Basically, main frame (Column &
Rafter) of PEB structure is rigid steel frame and combination taper column and taper rafter.
These taper sections are fabricated in plant using advanced technology wherein taper flange
welded to the taper web while end wall frame of PEB building may be designed as a main frame
or post end beam frame. While post end beam system framing consists of columns (Post) with
pinned ends and supporting beam known as end-wall. In post beam system consists bracing to
resisting lateral load to maintain longitudinal as well as lateral stability. Generally mezzanine
framing is connected to the main frame column and main
Primary built-up
Frames in the PEB industry often refer to primary built-up & hot rolled members.
Constant depth or tapered depth built-up members generally account for over 90% of
the weight of frames while hot rolled members generally account for the remaining 10%.
Figures
Secondary Members in the PEB industry refer mostly to longitudinal roof and wall members
that are roll formed from galvanized coils or press broken from narrow galvanized sheets. The
raw material of these members is stocked in five thicknesses: 1.5, 1.75, 2.2, 2.25 and 2.5mm.
The following building components are considered secondary members
Z” sections acting as longitudinal roof purlins and longitudinal wall girts that connect to
columns & rafters and support exterior roof and wall panels.
Eave struts located at the building eaves (corner of roof and wall sheeting along
sidewalls also providing bracing for frames and supporting roof and wall panels.
"C” sections used primarily in framed openings and as a transition member between
partial block walls and wall panels.
Mezzanine Deck (0.7mm thick) used to support concrete slabs in second level flooring.
Base angles, gable angles, and mezzanine edge angles.
Valley gutters (0.9mm thick) in Multi Gable Buildings.
Figures
Panels & Panel Accessories include single skin panels, sandwich panels, trims and flashing,
panels standard buyouts and building accessories. Although all roofs have panels, walls are often
partially or fully open for block wall, precast panels or access.
Single Skin Panels are trapezoidal ribbed sheets roll formed from thin mill finish or pre
painted aluzinc coated steel and aluminum coils and cut-to-length to meet the
requirements of a specific building.
Sandwich Panels have a polyurethane foam core sandwiched between two single skin
metal panels (or an exterior single skin metal panel and an interior aluminum faced
laminate). SUNTECH does not produce sandwich panels but has an exclusive
arrangement, with the largest producer of sandwich panels in the UAE, for the purchase
and resale of sandwich panels, to provide its Customers with a single source supply
responsibility. The engineering drawings for the sandwich panels are done by
SUNTECH so are the production of trims and the supply of all sandwich panels
accessories such as fasteners, bead mastic, purlin tape, etc.
Trims and Flashing include eave trim, eave gutters, downspouts, gable trim, curved
eave panels, flashing around building accessories, etc. which are produced from
preprinted aluzinc coated steel or aluminum sheets that are bent to the required shape
using roll formers, presses, or folding machines.
Figures
Building Accessories and special buyouts (SBO’s) include sliding doors, rollup doors,
personnel doors, fiberglass insulation, sandtrap louvers, windows, ridges ventilators.
Some are produced in-house. Some are purchased from suppliers and included in our
single source supply.
figures
Panel Standard Buyouts are items that are produced by others and stocked as finished
items by the PEB manufacturer. They include sheeting fasteners (carbon steel and
stainless steel), bead mastic, pop rivets, foam closures, skylights, etc. These are packed
by us for a specific building and shipped to the jobsite with the panels.
CONVENTIONAL CONCRETE HOLLOW BUILDINGS
4.4.1. CONVENTLONAL
4.4.2. MANUFACTURED
3.METHODS OF CONNECTION
Foundations
Columns to base Connection (Anchorage bolts)
Columns to Columns connection
Columns with beam connection
PREFAB MATERIALS AVAILABLE IN THE MARKETS:
Structural Insulated Panels: These are composite building material consisting of an insulating
layer of rigid polymer foam sandwiched between two layers of structural board. One of the main
advantages of SIPs is their insulating value, which depends on the thickness of the foam core.
The foam core forms a continuous energy barrier, and the smaller number of studs leaves less
opportunity for heat conduction. One of the biggest concerns about SIPs is their resistance to
insects. While the EPS foam core provides no nutrition to insects, it offers an easy way for them
to tunnel into the structure. Borate additives can be mixed into the foam during manufacture,
providing some amount of insect resistance.
Sandwich Panel:
These are used for insulation of roofing and walling in the building. It has one or both side metal
Galvalume sheet and PUF insulation in between. These have high thermal efficiency and
significant mechanical strength, which makes it possible to go for larger spans as well as large
partition walls.
FRP Corrugated Sheets:
Fibre-reinforced plastic (FRP) (also fibre-reinforced polymer) is a composite material made of a
polymer matrix reinforced with fibres. The fibres are usually glass, carbon, basalt or asbestos.
The polymer is usually an epoxy or a polyester thermosetting plastic. FRPs are commonly used
as roofing material as it is light weight, strong and resistive to deforming forces. They are usually
rust and termite proof. They have good impact resistance, possess fire retardant properties and
resistant to external weather conditions.
RESULTS AND DISCUSSION
S. No DESCRIPTION DURATION
1 Sub Structure-(Site cleaning, Earth work, Foundation, Basement,
Soil filling & Consolidation.)
2 Super Structure (Columns, Lintel & sunshade, Beams, Roof
slabs, Brick work, Plastering.)
3 Finishing Works–(Electrical, Plumbing Painting, Tiling, and
Installation of doors & Windows, Extra items.)
chart
Figures Comparison of total project duration for both prefab and conventional construction of
Industrial Building
The total project duration were calculated for both construction and shown in the Figure (5.2).
The figure represents the duration of the prefabrication construction is lower than the
conventional construction. The time duration of the project difference is 63 days between the
prefabrication and conventional construction. This contains very low time duration compared to
the conventional method for the individual double storey building.
Comparison of total project cost for both prefab and conventional construction of Industrial Shed
with area of 5,500m2
2. Cost Analysis
S. No DESCRIPTION Cost
1 Sub Structure -(Site cleaning, Earthwork, Foundation, Basement, 16,539,000
Soil filling & Consolidation.)
2 Super Structure – (Wall panels framing and Roofing slabs.) 46,041,000
3 Finishing Works–(Electrical, Plumbing Painting, Tiling, and 26,820,000
Windows, Extra items.)
Table 3: Total Cost for Prefabrication Construction
The cost of the prefab construction was calculated through the data collected from precast
company, which help to find the cost of the super structure of prefabrication construction. The
sub-structure and finishing work cost was the same as conventional construction because of same
method is used to construct in the prefab. The cost of the project is shown in three different
stages. The total cost of the double storey residential building for prefabrication construction is
73, 00,000.00 (Sixty nine lakes and nineteen thousand rupees only).
S. No DESCRIPTION Cost
1 Sub Structure-(Site cleaning, Earth work, Foundation, Basement,
Soil filling & Consolidation.)
2 Super Structure (Columns, Lintel & sunshade, Beams, Roof
slabs, Brick work, Plastering.)
3 Finishing Works–(Electrical, Plumbing Painting, Tiling, and
Installation of doors & Windows, Extra items.)
Table 4: Total Cost for Conventional Construction
The cost of the conventional construction was calculated through the data collected from
conventional construction company, which help to find the cost of the total project. The sub-
structure and finishing work cost was taken to the prefab construction from the conventional. So
there are no cost variations in both constructions for these stages. But the cost variation was in
the super-structure and which is low when compared to the prefab construction for double storey
residential building. Total cost of the double storey residential building for conventional
construction is 60, 19,000.00 (Sixty lakes and nineteen thousand rupees only).
Chart
Figure Comparison cost for prefab and conventional in three different stages
In this analysis, we had known about the cost of both prefab and conventional constructions. And
also the comparison cost for different stages as sub-structure, super-structure and finishing
works. The figure (5.3) shows the cost difference for the both prefab and conventional
construction in three different stages. As in the figure the sub-structure and finishing works has
the similar cost for both construction of double storey residential building, because of the sub-
structure and the finishing works was done by the traditional method. But the category of super-
structure has more variations, which the prefabrication construction is very high cost compare to
the conventional construction, because of the superstructure was done in two different methods
as prefab and conventional. The total project cost were calculated for both construction and
shown in the Figure (5.4). The figure represents the cost of the prefabrication construction is
higher than the conventional construction. The cost difference is 12, 91,000.00 rupees between
the prefabrication and conventional construction.
Chart
Figures: Comparison of total project cost for both prefab and conventional construction of
Comparison of total project duration for both prefab and conventional construction of Industrial
Shed with area of 3,000m2
1. Project Duration
S. No DESCRIPTION DURATION
1 Sub Structure -(Site cleaning, Earthwork, Foundation, Basement, 30 days
Soil filling & Consolidation.)
2 Super Structure – (Wall panels framing and Roofing slabs.) 74 days
3 Finishing Works–(Electrical, Plumbing Painting, Tiling, and 76 days
Windows, Extra items.)
Table 5: Total Duration for Prefabrication Construction
S. No DESCRIPTION DURATION
1 Sub Structure-(Site cleaning, Earth work, Foundation, Basement,
Soil filling & Consolidation.)
2 Super Structure (Columns, Lintel & sunshade, Beams, Roof
slabs, Brick work, Plastering.)
3 Finishing Works–(Electrical, Plumbing Painting, Tiling, and
Installation of doors & Windows, Extra items.)
Table 6: Total Duration for Conventional Construction
Comparison of total project cost for both prefab and conventional construction of Industrial Shed
with area of 3,000m2
2. Cost Analysis
S. No DESCRIPTION Cost
1 Sub Structure -(Site cleaning, Earthwork, Foundation, Basement, 13,782,500
Soil filling & Consolidation.)
2 Super Structure – (Wall panels framing and Roofing slabs.) 38,367,500
3 Finishing Works–(Electrical, Plumbing Painting, Tiling, and 22,350,000
Windows, Extra items.)
Table 7: Total Duration for Prefabrication Construction
S. No DESCRIPTION Cost
1 Sub Structure-(Site cleaning, Earth work, Foundation, Basement,
Soil filling & Consolidation.)
2 Super Structure (Columns, Lintel & sunshade, Beams, Roof
slabs, Brick work, Plastering.)
3 Finishing Works–(Electrical, Plumbing Painting, Tiling, and
Installation of doors & Windows, Extra items.)
Table 8: Total Duration for Conventional Construction
In this Study, we compare the cost and time taken for convention as well as prefabricated
construction show them through graphical representation and network diagram
Comparison Graphs of Cost and Time for Conventional and Prefabricated Structures
Cost for substructure is lesser in prefabricated structures. The cost for superstructure is almost
equal in both cases. Finishes shows a difference of about 6 lakhs lesser in prefabricated. The time
for the sub structure is almost equal in both prefab and conventional construction. The
superstructure in the conventional methods takes 241 days more than prefabricated structure,
which helps to reduce the total duration in prefabrication by large extent. Finishes in
conventional takes 114 more days than prefabricated structure.
CONCLUSION
The main goals of the work have been achieved. The total cost and total duration for the double
storey residential building have been determined for both prefab and conventional construction.
And also we had known about the advantages and disadvantages of both prefabrication and
conventional construction by the survey conducted in similar companies. The comparison
showed there is enormous cost difference between the methods, which the prefab is very high
when compared to conventional on this type of individual houses.
The prefab construction for individual double storey residential building cost is 13% more than
the conventional construction. This is main drawback for prefab construction which is not
economical to construct in this case. At the same time the prefab construction is easy to work and
reduces the project duration, is reduced by 63 days when compared to the conventional. It’s the
main advantages for prefab construction and also it helps when there is labour shortage. As a
result of survey we had known that the prefab construction have more advantages and
procurement in industrialized, heavy infrastructures. But in individual houses there are lot of
constraints and lack of knowledge its get struggling to implement in our country. At this stage
conventional construction is economical and comfortable when compared to the prefabrication
construction.
Even if the general theoretical idea of prefabrication technology is known by
professionals involved in real estate construction in Addis Ababa, majority of them
have no information about the existing prefabrication plant in Addis Ababa.
Majority, 72.5%, of the professionals involved in Addis Ababa real estate
construction are preferred using prefabrication construction method to conventional
method. But it is believed that there is no capability to use the technology in
construction industry of Ethiopia.
There is no sufficient supply of prefabrication elements in Addis Ababa, as a result
the attitudes towards use it for real estate construction is also limited. The study
shows that, currently there is no practice of using prefabricated concrete structural
elements in Addis Ababa real estate construction.
The major challenges to use prefabrication technology are: - shortage of supply of
prefabrication elements, lack of information about the existing potential, shortage of
skilled man power on the area, lack of consideration of the existing dimension during
design and low motivation of designers to adjust their work with it.
PEBs needs a huge initial investment
RECOMMENDATION
Based on the findings of the study and the discussions above a summary of some general
recommendations are offered to support the improvement of application of prefabrication
technology for real estate construction in Addis Ababa and to recommend some area for
further investigation. These are listed below:
Great effort should be done by government to distribute technical information for
professionals and other stakeholders to raise public information about the existing
potential of the technology.
Acceptance and preference of the technology by professionals is great potential to
apply a given technology, so that the government and other stakeholders should use
this resource as an input.
To minimize the shortage of supply of prefabricated elements in addition to
improving the existing plant, government should encourage the investors who have
potential to establish modern prefabricating plant in Addis Ababa.
The government should pay due attention to develop prefabrication construction as a
viable solution to improve the quality, speed, and economy of upcoming real estate
construction.
REFERENCE
1. A.Venkateswara B. Sarath Chandra ―Study on Prefabricated Concrete Beam and Column
Connections,‖ 2013, International Journal of Applied Sciences, Engineering and Management,
ISSN 2320 – 3439, V. 2, N. 02, pp. 41 – 45.
2. Alex Opoku, JulusAkotia,Vian Ahmed ―Research Methodology in the Built Environment,‖
2016.
3. Ali Rashidi and Rahinah Ibrahim, ―Industrialized Construction Chronology: The Disputes
and Success Factors for a Resilient Construction Industry in Malaysia‖ The Open Construction
and Building Technology Journal, 2017, v. 11, pp.286-300.
4. AlirezaBaghchesaraei and Omid Reza Baghchesaraei, ―Evaluation of Prefabrication
Technologies in Construction,‖ The Caspian Sea Journal, 2016, v.10 pp. 1578-7899
5. Anderson Mark and Anderson Peter‖Prefab prototypes: site- specific design for
offsite construction, 2007.
6. Baghchesaraei, A., Vatan, M., and Baghchesaraei, O.R. ―Using Prefabrication
Systems in Building Construction,‖ International Journal of Applied Engineering
Research, 2015, v. 10, n. 24, pp.44258-44262.
7. Bahamon Alejandro and Bill Bain, ―Prefab: adaptable, modular, dismountable,
light, mobile architecture,‖ 2002, LOFT and HBI. New York.
8. Cheung, S.-O. andSuen, H. C. H.; ―A Web-based construction project performance
monitoring stem‖ PPMS: Automation in Construction, 2004, v.13, pp.361–376.
9. Chia-Cheng Chen and Huiman X. BBarnhart ,―Assessing agreement with interclass
correlation coefficient and concordance correlation coefficient for data with
repeated measures,‖Elsevier, 2013, V.60, pp. 132-145.
10. Creswell, W.‖ Research design: qualitative, quantitative, and mixed methods
approaches,‖ London: Sage publications, 2009.
11. David Nomanr, ―Prefabrication and standardization potential in buildings,‖ Study
Report SR 312, 2014.
12. Denscombe, m. ―The good Research Guide‖ (3rd ed), Maidenhead, Uk: Open
University press,2007.
13. Graaskamp ―Fundamentals of real estate development,‖ 1981, Urban land institute,
University of Wisconsin-Madison, USA.
14. GutemaBulto, ―Prefabrication of Structural Elements: A Case Study,‖ Master‘s
Thesis,Addis Ababa University, Addis Ababa, Ethiopia, 1998.
15. Harvey M Bernstein ―Prefabrications & Modularization: Impact on the
construction industry,‖ Modular Building Institute Annual Conference, McGraw-
Hill Construction, Las Vegas, NV, 2011, pp. 1-60.
16. Kibirt Bayou Chane,‖ Precast Construction in Ethiopia - An In-Depth Look at the
PBPPE Precast Plant,‖ Master‘s Thesis,Addis Ababa University, Addis Ababa,
Ethiopia, 2017.
19. L. Jaillon and C.S. Poon,‖Advantages and Limitations of Precast Concrete
Construction in High- rise Buildings: Hong Kong Case Studies,‖ CIB World
Building Congress, CIB2007-011,2007, pp. 2504-2514.
20. Mikhailov, V. V.; Susnikov, A. A.; Development of Factory Production of
PrecastPrestressed Concrete in the U.S.S.R.; PCI Journal, 1995.
21. N.Dineshkumar and P.Kathirvel, ―Comparative Study on Prefabrication
Construction with Cast In-Situ Construction of Residential Buildings,‖ 2015,
IJISET - International Journal of Innovative Science, Engineering & Technology,
Vol. 2.
22. NegashZergaSema ―Modeling Hedonic Real Estate Price for Small Family Houses
in Addis Ababa,‖ 2010.
23. Polit, DF and Hungler, BP, Essentials of nursing research: Methods, appraisals and
utilisation, 4th edition, Philadelphia: Lippincott-Raven Publishers, 1997.
24. Richard, R. B., ―Individualizations and industrializationIn Adaptables
"Adaptability in Design and Construction" 2006.
25. RiduanYunus, (2012). Decision making Midlines forSustainable Construction
ofIndustrialized Building Systems. Queensland University of Technology School
of Urban Development.
26. Ryan E. Smith and ShilpaNarayanamurthy,‖ Prefabrication in Developing
Countries: a case study of India,‖ Graduate Researcher, University of Utah, 2002.
APPENDIX
Interview Questions
Section I: -Interview Questions to Industrial Parks Development Cooperation staff ,
Employer Representative and Contractor for Comparison of prefabricated PEB Industrial
Building than Conventional method.
1. What is the benefits of using prefabricated structural elements than Conventional method in
minimizing of quality problems?
2. What is the benefits of using prefabricated structural elements than Conventional method in
minimizing of work place hazard?
3. What is the Advantage of using prefabricated structural elements than Conventional method
takes shorter time?
4. Minimizing of material wastage
5. Minimizing of overhead cost
6. Low maintenance cost
7.It need less work place
8.Easy HR management
9.No false work needed
10.It need less supervision
What are shortcomings of using prefabricated structural elements?
1. Not easily transported
2. It may face connection problem
3. It is not flexible with design
4. It need more expensive machinery
Challenges to Use Prefabricated Concrete Structural Elements
1. Shortage of skilled man power on the area
2. Shortage of supply of prefabricated elements
3. Lack of information about the existing potential.
4. Lack of awareness about the technology
5. Lack willingness of professionals