3.facilities Layout
3.facilities Layout
4. Cellular layouts
(8 h
Cd =
/
48
Cd = = 4 minutes / Unit 12
Example 1- A briefcase manufacturing company assembles its stylish cases in six primary
work elements
Workas Element
mentioned below Precedence Time in Mins.
A Tan leather - 20
B Dye leather A 12
C Shape case B 7
D Mold hinges and fixture - 10
E Install hinges and fixtures C,D 15
F Assemble case E 18
20 12
7
a, b, c d, e, f
A B C
20 12
Station - 1 A, D A,D A(20) 20 - 7
E E E(15) 22 -
F F F(18) 40
total time 40 40 8
Total idle
time 96 - 82 System utilisation = 41/48 =
total time = = 14 minutes
40 + 42 = 82 85.41%
minutes
Example 2
Using the information given in the table,
a). Draw a precedence diagram
b). Compute the cycle time for an out-put of 400 units in 8 hours shift
c). Determine the minimum number of work stations required
d). Compute the resulting percentage of idle time and the efficiency
c d f g h
• Software Packages :
• IBM’s COMSOAL (Computer Method for Sequencing Operations for Assembly Lines)
• GE’s ASYBL (Assembly Line Configuration Program)
•
The average number of loads transported per month, between the five departments of a
wood furniture factory is given in the below table.
The current layout of the facility is shown schematically on the 2 X 3 grid. You are asked
to evaluate the current layout in terms of non adjacent loads, and if necessary provide a
new layout on 2 X 3 grid. Load Summary Chart
FROM/TO DEPARTMENT
1
Department 1 2 3 4 5
2
1 — 100 50
2 — 200 50
3 60 — 40 50
4 100 — 60
5 50 —
From to Composite Loads
1 1 Department 1 2 3 4 5
0
1 2 100
1 3 50+60 = 110
1 4 0
1 5 0
2 3 200 2 3 200 loads
2 4 50+100 = 150 2 4 150 loads
1 3 110 loads
3 4 40 1 2 100 loads
3 5 50+50 =100 4 5 60 loads
4 5 60 3 5 100 loads
3 4 40 loads
1 4 0 loads
1 5 0 loads
Department 1 2 3 4 5
2 3 200 loads
2 4 150 loads
1 3 110 loads 110
1 2 100 loads
4 5 60 loads Nonadjacent Loads 110+40=1
100 200
3 5 100 loads 1
3 4 40 loads 150
100
0
1 4 0 loads
60
1 5 0 loads
2 5 0 loads 40
Grid 1
Nonadjacent Loads: 0
1
Grid 2
Load Summary Chart
FROM/TO DEPARTMENT
1
Department 1 2 3 4 5
2
1 — 100 50
2 — 200 50
3 60 — 40 50
4 100 — 60
5 50 —
1
1 2 4
3 5 3
Block Diagramming: Example 2
Given the following load summary chart, design a layout on a 2 X 3 grid that will minimize
the non-adjacent loads
Load
Summ
ary
Chart
From / to 1 2 3 4 5
1 - 50 25
2 - 20 100
3 30 10 - - 75
4 40 -
5 60
Composite
Load
loads
Sum
mary
• 2 0
Chart • 3 80
From / to 1 2 3 4 5 • 4 0
1 - 50 25 •
25
5
2 - 20 100
3 30 10 - - 75 23 30
4 40 - 24 100
5 60 25 60
34 40
•
75
5
45 0
Example -3 (minimizing transport cost or distance)
Develop a process layout that will minimize the total distance travelled by patients at
a medical clinic, using the following information on projected department visit by
patient and distance between locations. Assume a distance of 35 meters between the
reception and each patient location. Use following format
Distance
between
Room A
locations
Room B
(meters)
Room C
Room D From / To A B C D E F
Room E A 40 80 100 120 160
Room F
B - 40 60 80 120
C Number - 20 40 80
of Trips
1. Cardiology D between - 20 40
2. Orthopedic E locations - 40
3. General F (Nos.) -
Medicine
From / To Receptio 1 2 3 4 5 6
4. Radiology lab n
5. Pediatrics
Dist
anc
e
bet
wee
n
loca
tion
s
(me
ters
Number
)of Trips
From / Abetween
B C D E F
To locations
(Nos.)
A - 40 80 100 120 160
From / To Receptio 1 2 3 4 5 6
B - 40 60 80 120
n
C
Reception - 20 - 50 20210 40
20 80
10 130
1D 10 - 0 - 40 20
110 40
80 50
E - 40
2 40 - 0 50 40 120
F -
3 10 - 10 250 10
Dist No. of Order of
anc Trips Assignmen
e Between t
bet 0 10
1–2 40
wee 7
n 1–3
110 3
loca 1–4 80
tion
5
1–5
s 50 6
(me 1–6
0 10
ters
Number 2–3
)of Trips 50 6
2–4
From / Abetween
B C D E F 40 7
2–5
To locations 120 2
2–6
A -(Nos.)40 80 100 120 160 10 9
3–4
From
B / To Receptio
- 1 40 2 3
60 4
80 5120 6 1
3–5 250
n
C - 20 40 80 1 9
Reception - 20 50 210 20 10 130 3–6
D - 20 40
4–5
040 7
1 10 - 0 40 110 80 50
E - 40 90 4
2 40 - 0 50 40 120 4–6
F -
5–6
20 8
No. of Order of
A/3 B/5 C/2 Trips Assignmen
OR A/3 B/5 C/1
Between t
1–2 0 10
D/2 E/6 F/4
D/1 E/4 F/6 1–3 40 7 (tied)
1–4 110 3
1–5 80 5
A/3 B/5 C/1
A B C 1–6 50 6 (tied)
2–3 0 10 (tied)
D/4 E/6 F/2
2–4 50 6 (tied)
D E F
2–5 40 7 (tied)
Departments 2–6 120 2
Room A 1. Cardiology 3–4 10 9 (tied)
Room B 2. Orthopedic
3–5 250 1
Room C 3. General Medicine
Room D 4. 2D Echo 3–6 10 9 (tied)
Room E 5. Pathology lab 4–5 40 7 (tied)
Room F 6. Radiology lab 4–6 90 4
5–6 20 8
Dist
A/3 B/5 C/1 ance
bet
wee
D/4 E/6 F/2 n
loca
tion
s
A B C (met
ers)
D E F From / To A /3 B/5 C//1 D/4 E/6 F/2
Distan
A/3
ce - 40 80 100 120 160
C1-C1= 0 betwe
B/5 - 40 60 80 120
en
C/1 - 20 40 80
1-2 = C1-F2 = 80 depar
1-3 =C1-A3 =80 D/4
tment - 20 40
1-4 =C1-D4= 20 s
E/6 - 40
1-5=C1-B5=40 F(mete
/2 -
rs)
2-3 = F2-A3 =160 From To 1 2 3 4 5 6
2-4 =F2-D4 =40 1 - - 80 80 20 40 40
Distan
ce
A/3 B/5 C/1 betwe
en
depar
D/4 E/6 F/2
tment
s
(mete
A B C rs)
From To 1 2 3 4 5 6
1 - - 80 80 20 40 40
D E F Number
2 - of Trips - 160 40 120 40
3 - between 100 40 120
locations
4 - 60 20
(Nos.)
5 - 80
From / To Receptio 1 2 3 4 5 6
6 - n
Reception - 20 50 210 20 10 130
1 10 - 0 40 110 80 50
2 40 - 0 50 40 120
Dist ber
anc of
e Trips
bet betw
wee een
n locat
dep ions
art (Nos
men .)
ts From Rece 1 2 3 4 5 6
(me / To p.
ters From To 1 2 3 4 5 6
) Recep - 20 50 210 20 10 130
1 . - 0 3200 2200 3200 2000
Fro To 1 2 3 4 5 6 2 1 - 0 0 40 2000
m 10 - 110 4800
80 4800
50
3 2 40 - 0 1000
50 10000
40 1200
120
1 - - 80 80 20 40 40
4 3 10 - 10 2400
250 1800
10
2 - - 160 40 120 40
5 4 0 - 40 1600
90
3 - 100 40 120
6 5 10 - 20
4 - 60 20
5 - distance traveled per day = 40,200
80 6 30 -
Total meters
6 -
Example 4
Relationship diagramming – (Muther's grid) Closeness rating
6. Pediatrics
7. Pathology lab H
8. ECG and 2D Echo lab G
9. Mortuary E F
10. Operation theater
(Muther's grid) Closeness rating A = Absolutely important
E = Essential
I = Important
1. Cardiology O = Ordinary importance / OK
U = Un-important
2. Orthopaedics X = undesirable
3. Gynaecology
4. General Medicine
5. Radiology
6. Paediatrics
7. Pathology
9. Mortuary
1-6 1-9
1-8 2-9
1-10 3-9
2-5 4-9
2-10 5-9
3-10 6-9
4-6 7-9
5-10 8-9
Rel Dept. Dept. Dept. Dept. Dept. Dept. Dept. Dept.8 Dept. Dept.10
6-8
. 1 2 3 4 5 6 7 9
A 6,8,10 5,10 10 6 10, 8 - - - - 9-10
E - - 7 7 - 7 - - 10 -
I - - 6,8 8 - 10 10 - - -
O 4,7 4,6,7 4 - - - - - - -
U 2,3,5 3,8 5 5,10 5,6,7 - 8 - - -
X 9 9 9 9 9 9 9 9 -
6
5
6 8
1 8 2 10
10 4 6
5 10
Rel. Dept. 1 Dept.2 Dept.3 Dept. 4 Dept.5 Dept. Dept. 7 Dept.8 Dept.9 Dept.10
6
2 10 8
4 5 7
Department 1 Draw a lay out for the given relationship
X diagram
Department 2 A
O U
Department 3 X O
U O E
Department 4 A E X
A A A A
Department 5 U I E
U O A
Department 6 A A
U A
Department 7 A
E
Department 8
(Muther's grid) Closeness rating
Link A Link X
Department 1
X 1-3 1-2
Department 2 A
O U 1-8 1-7
Department 3 X O
U 2-7 2-3
O E
Department 4 A E X 2-5
A A A A
Department 5 U I E 3-5
U O A
Department 6 A A 3-6
U A
Department 7 A 3-8
E 4-5
Department 8
4-8
5-7
5-8
Link A Link X
Department 1
X
Department 2 A 1-3 1-2
O U
Department 3 X O 1-8 1-7
U O E
Department 4 A E X 2-7 2-3
A A A A
Department 5 U I E 2-5
U O A
Department 6 A A 3-5
U A
Department 7 A 3-6
E
Department 8 3-8
Rel. Dept. 1 Dept.2 Dept.3 Dept. 4 Dept. 5 Dept. 6 Dept. 7 Dept. 8 4-5
4-8
A 3,8 7 5,6,8 5,8 7,8, 8 - -
5-7
E 6 6,8 - - - - 8 - 5-8
I - - 7 - - - - -
O 5 3,5, - 7 - - - -
U - - - - - - - -
X 2,7 3 - - - - - -
Department 1
X
Department 2 A
6 2
O U
Department 3 X O
U O E 3 8 7
Department 4 A E X
A A A A
Department 5 U I E
U O A 1 5 4
Department 6 A A
U A
Department 7 A
E
Department 8
Rel. Dept. 1 Dept.2 Dept.3 Dept. 4 Dept. 5 Dept. 6 Dept. 7 Dept. 8
➢ More open space should be provided in the east and the North side than in the West and
South side.
➢ The sloping of the floors should be towards East, North and Northeast sides and never
towards South, West.
➢ A Thicker walls should be constructed in the South and West Side of the building and
the thinner walls should be in the North and east sides.
➢ The staircase should be in the Southwest side.
➢ The underground water tank should be in Northeast side.
➢ The overhead water tank should be in the Southwest corner.
➢ Toilets must be placed in Northwest or Western corners but should never be constructed
in the Northeast and Southwest corners.
➢ Administrative office and other office blocks can be constructed in North, East.
➢ Staff quarters, Outhouse should be built in the Northwest corner.
➢
Layout - Vastu
➢ Basement should be constructed in the east, North or Northeast corner of the proposed
building.
➢ Heavy machinery should be placed in the Southwest, West & South zones.
➢ Northeast and centers of the building should be avoided for placing anything heavy.
➢ The heat zone or the burners, boilers, ovens, generators, furnace transformers, chimneys
should be in the Southeast corner.
➢ No garbage should be dumped in the Northeast corner of the building or at the site, north
or the east corner should always be kept free and clean.
➢ In R.C.C. framed structure, the number of columns or the beams should be even and not
odd.
➢ The beam should never run above the machines & the workers.
➢ The finished goods should be stored in the Northwest corner of the area.
➢ A pooja room or a temple should be in the northeast corner and should be kept neat and
clean.
Next Topic
Product and Service Design