The Project On System Loss Reduction For Philippine Electric Cooperatives (Ecs)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 67

Republic of the Philippines

National Electrification Administration (NEA)

The Project on System Loss Reduction


for Philippine Electric Cooperatives
(ECs)

Project Completion Report

March 2013

Japan International Cooperation Agency


Tokyo Electric Power Company
IL
JR
13-031
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Contents

Chapter 1 Outline of the Project ............................................................................................................... 1-1


1.1. Outline .................................................................................................................................... 1-1
1.1.1. Title of the Project .................................................................................................................. 1-1
1.1.2. Project Term............................................................................................................................ 1-1
1.1.3. Counterpart ............................................................................................................................. 1-1
1.1.4. Targeted Groups ...................................................................................................................... 1-1
1.2. Purpose of Technical Assistance ............................................................................................. 1-1
1.3. Technical Assistance Team Structure ...................................................................................... 1-2
1.4. Project Design Matrix (PDM)................................................................................................. 1-2
Chapter 2 Background of Technical Assistance ........................................................................................ 2-1
2.1. Background of Technical Assistance ...................................................................................... 2-1
2.2. Current Situation of Electricity and Energy Sector ................................................................ 2-2
2.2.1. Institutional Arrangement and Sector Overview..................................................................... 2-2
2.2.2. Distribution Sector .................................................................................................................. 2-4
2.2.3. Current Method to Reduce System Losses ............................................................................. 2-5
Chapter 3 Basic Policy of Technical Assistance ....................................................................................... 3-1
3.1. Issues on technical loss reduction Projects ............................................................................. 3-1
3.2. Project Strategy and Approach ............................................................................................... 3-2
3.2.1. Basic Policy on Technical Aspect ........................................................................................... 3-2
3.2.2. Detailed Approach to solving Issues ....................................................................................... 3-3
3.3. Work Flow .............................................................................................................................. 3-6
3.4. Basic Policy of the Study Implementation.............................................................................. 3-7
Chapter 4 Inputs ........................................................................................................................................ 4-1
4.1. Inputs from Japanese Side ...................................................................................................... 4-1
4.1.1. Experts .................................................................................................................................... 4-1
4.1.2. Counterpart Training in Japan................................................................................................. 4-1
4.1.3. Equipment ............................................................................................................................... 4-1
4.1.4. Others...................................................................................................................................... 4-1
4.2. Inputs from Philippine Side .................................................................................................... 4-2
4.2.1. Counterparts............................................................................................................................ 4-2
4.2.2. Spaces and facilities for project activities ............................................................................... 4-2
Chapter 5 Project Activities ...................................................................................................................... 5-1
5.1. Outline of Project Activities ................................................................................................... 5-1
5.2. Detailed Activities .................................................................................................................. 5-1
5.2.1. Outcome of the Study ............................................................................................................. 5-1
5.2.2. Site Survey Implementation.................................................................................................... 5-1
5.2.3. Cooperation on a Variety of Reports and Conferences ........................................................... 5-3

i
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
5.2.4. Record of installation and training of SynerGEE software..................................................... 5-5
5.2.5. System Loss Reduction Manual ............................................................................................. 5-6
5.2.6. The pilot projects installing AMDT ...................................................................................... 5-19
5.2.7. Work preparation to support planning of full-scale F/S (confirmation and analysis of the
power distribution development plan) .................................................................................. 5-26
Chapter 6 Project Performance and Achievements ................................................................................... 6-1
6.1. System loss reduction manual................................................................................................. 6-1
6.2. Support system for quantitative evaluation of system loss ..................................................... 6-2
6.3. Support system for upgrading the present medium voltage .................................................... 6-3
6.4. Current Status of the Targeted ECs ......................................................................................... 6-4
6.5. Target Index Trends ................................................................................................................ 6-5
Chapter 7 Conclusion and Recommendations .......................................................................................... 7-1
7.1. The System Loss Reduction Manual ...................................................................................... 7-1
7.2. Utilization of Distribution Analysis Software......................................................................... 7-2
7.3. Upgrading Medium Voltage to 23kV ...................................................................................... 7-2
7.4. Application of Amorphous Transformers ............................................................................... 7-3
Chapter 8 Appendix .................................................................................................................................. 8-1

ii
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Figure and Table List

Figure 1-1 Technical Assistance Team Structure....................................................................................... 1-2


Figure 2-1 Institutional arrangement of electricity sector in the Philippines ............................................ 2-2
Figure 2-2 Organization of NEA ............................................................................................................... 2-3
Figure 2-3 Map of distribution utilities in the Philippines ........................................................................ 2-7
Figure 3-1 Flow of Overall Technical Assistance ..................................................................................... 3-6
Figure 5-1 Flow of system loss calculation ............................................................................................. 5-10
Figure 5-2 Dividing load by transformer ................................................................................................ 5-12
Figure 5-3 Amorphous transformers and its loss reduction .................................................................... 5-14
Figure 5-4 NEA data of technical and non-technical losses in 2010 ....................................................... 5-16
Figure 5-5 Format of the good practices for system loss reduction ........................................................ 5-18
Figure 5-6 Daily Curve of Overloaded Transformer (10kVA) ............................................................... 5-23
Figure 5-7 Cost Comparison both SiFe and AMDT) .............................................................................. 5-25
Figure 5-8 Image of ISELCO I ‘s candidate site ..................................................................................... 5-28
Figure 5-9 Outline of the MV line (ISELCO I) ....................................................................................... 5-29
Figure 6-1 Trend of the system loss rate in the seven targeted ECs .......................................................... 6-5
Figure 6-2 Trend of SAIFI in the seven targeted ECs ............................................................................... 6-6
Figure 6-3 Trend of the SAIDI in the seven targeted ECs ........................................................................ 6-6

Table 2-1 Amount of loan for EC .............................................................................................................. 2-4


Table 2-2 Ranking of ECs based on management in 2011 ........................................................................ 2-5
Table 4-1 Total dispatch Records of the project ........................................................................................ 4-1
Table 5-1 Record of installation of SynerGEE software ........................................................................... 5-5
Table 5-2 Record of training of SynerGEE software ................................................................................ 5-6
Table 5-3 Status of distribution system modeling using SynerGEE software ........................................... 5-6
Table 5-4 Contents of the System Loss Reduction Manual....................................................................... 5-7
Table 5-5 Number of installation AMDT ................................................................................................ 5-21
Table 5-6 Unit Price of both AMDT and SiFe DT .................................................................................. 5-21
Table 5-7 Result of AMDT Unit Test (3 EC) .......................................................................................... 5-22
Table 5-8 Comparison of core loss and copper loss of each DT capacity ............................................... 5-24
Table 5-9 candidate plans for evaluation ................................................................................................. 5-26
Table 5-10 Basic information of ISELCO I‘s candidate site ................................................................... 5-28
Table 5-11 Outline of each case (ISELCO I)........................................................................................... 5-29
Table 5-12 Evaluation result (ISELCO I) ................................................................................................ 5-30
Table 5-13 Candidate Sites ...................................................................................................................... 5-31
Table 6-1 Category of targeted EC and comments .................................................................................... 6-2
Table 6-2 Number of workshop participants ............................................................................................. 6-2
Table 6-3 Schedule of SynerGEE training ................................................................................................ 6-3
Table 6-4 “Objectively verifiable indicator” for the “Overall Goal” ........................................................ 6-7

iii
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Abbreviations

ADB Asian Development Bank


AMDT Amorphous Transformer
C/P Counterpart
CAPEX Capital Expenditures
DT Distribution Transformer
DOE Department of Energy
EC Electric Cooperative
ERC Energy Regulatory Commission
EU European Union
JETRO Japan External Trade Organization
JICA Japan International Cooperation Agency
kV Kilo Voltage
LV Low Voltage
MERALCO Manila Electric Company
MV Medium Voltage
NEA National Electrification Administration
NEDA National Economic Development Authority
NGO Non-Government Organization
PDP Philippines Development Plan
PSALM Power Sector Assets and Liabilities Management Corporation
TA Team Technical Assistance Team
TEPCO Tokyo Electric Power Company, Inc.

<Targeted ECs>
ISELCO I Isabela I Electric Cooperative, Inc.
PELCO II Pampanga II Electric Cooperative, Inc.
FLECO First Laguna Electric Cooperative, Inc.
CASURECO II Camarines Sur II Electric Cooperative, Inc.
CASURECO IV Camarines Sur IV Electric Cooperative, Inc.
SORECO I Sorsogon I Electric Cooperative, Inc.
LEYECO III Leyte III Electric Cooperative, Inc.

iv
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Chapter 1 Outline of the Project


1.1. Outline

1.1.1. Title of the Project


The Project on System Loss Reduction for Philippine Electric Cooperatives

1.1.2. Project Term


From March 2011 to March 2013

1.1.3. Counterpart
„ National Electrification Administration (NEA)

1.1.4. Targeted Groups


„ ISELCO I (Isabela I Electric Cooperative, Inc)
„ PELCO II (Pampanga II Electric Cooperative, Inc.)
„ FLECO (First Laguna Electric Cooperative, Inc.)
„ CASURECO II (Camarines Sur II Electric Cooperative, Inc.)
„ CASURECO IV (Camarines Sur IV Electric Cooperative, Inc.)
„ SORECO I (Sorsogon I Electric Cooperative, Inc.)
„ LEYCO III (Leyte III Electric Cooperative, Inc.)

The seven targeted ECs was selected in consideration of local balance from EC of medium
rank in five-step evaluation to which the performance improvement effect was accepted
among 119 EC. The seven targeted ECs are shown in Fig. 2-3.

1.2. Purpose of Technical Assistance


In order to develop the technical capacity and planning abilities of the National
Electrification Administration (hereinafter referred to as NEA) and Electric Cooperatives
(hereinafter referred to as ECs) to reduce distribution system losses, the Technical Assistance
Team (hereinafter referred to as the TA Team) will provide the necessary support to improve
the management and technology of NEA and selected ECs. Specifically, the TA Team will
conduct activities to achieve the following:
„ Preparations and practices in accordance with the System loss reduction manual are
implemented.(Output 1)
„ Establish a support system for the quantitative evaluation of system losses. (Output
2)
„ Establish a support system for upgrading the present medium voltage and technical
design standards. (Output 3)

1-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

1.3. Technical Assistance Team Structure


The TA Team members were slightly replaced over the course of the Project. By having
considering assignment, there was no trouble to the project implementation by change. Figure 1.1
shows the structure of TA Team for this operation.

Masaharu YOGO
Team Leader/
Power System Planning

Output2 Output3
Output1 Support system for Support system for
Management Manuals for quantitative evaluation of upgrading mid-voltage to
System Loss Reduction system loss 23kV and technical design
standards

Kenichi KUWAHARA Masaki KUROIWA / Toshiya MINEJIMA /


Distribution Management / Junichi OHISHI Masahiro MYOGA
Maintenance management method Power System Analysis Distribution Planning / System Loss
(Software) Reduction

Keiichi FUJITANI Teru MIYAZAKI /


Capacity Building/Coordinator Takayuki SHIBATA
Economic / Financial Analysis

Figure 1-1 Technical Assistance Team Structure

1.4. Project Design Matrix (PDM)


The Project Design Matrix (PDM) has been revised three times over the course of Project
execution as mentioned below. The narrative summary of the current PDM is as follows:

(1) Overall Goal


Losses of ECs' power distribution systems are reduced and the power supply capability is
enhanced in an efficient and economic fashion.

(2) Project Purpose


The engineering and planning capacity to reduce the distribution system losses by the
EC’s and NEA are enhanced.

(3) Output
1. Prepare the System Loss Reduction Manual and put it into practice.
2. Establish a support system for the quantitative evaluation of system losses.
3. Establish a support system for upgrading the mid-voltage to 23kV as well as the
technical design standards.

1-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(4) Activities
1 System Loss Reduction Manual is prepared and put into practice
1-1 Survey the best existing practices of the system loss reductions, including the non-
technical losses at the leading EC’s;
1-2 Prepare draft manuals for system loss reduction based on Japanese experience;
1-3 Case studies to solve the issue for application of manuals into selected EC’s are
conducted;
1-4 Finalizing manuals based on the above activities with NEA, including the
compilation of EC’s best non-technical practices;
1-5 Propose an appropriate mechanism to transfer the manual contents to other EC’s with
NEA;

2 Support system for a quantitative evaluation of system losses is established


2-1 Survey current usage of software for power flow analysis in the selected EC’s;
2-2 Propose appropriate methods for evaluating the system loss reduction for the
selected EC’s;
2-3 Develop appropriate methods based on 2-1, 2-2 for the selected EC’s;
2-4 Train NEA and EC staff in electric power transmission and distribution via the
methods established above;

3 Establish a support system to upgrade the present mid-voltage to 23kV and the technical
design standards
3-1 Survey the existing facilities, facility configuration and the distribution development
plan;
3-2 Discuss proper design standards and guidelines for a 23 kV distribution line in the
Philippines with NEA;
3-3 Preparation work for a full scale F/S;

The final PDM including the indicators/targets means of verification and important
assumptions are shown in Appendix 1.

1-3
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Chapter 2 Background of Technical Assistance


2.1. Background of Technical Assistance
The self-sufficiency rate of energy in the Philippines is low 1 compared with other Asian
countries, and the focus is on improving energy independence as one of the most important parts
of energy policy. A considerable amount of energy depends on oil and coal from foreign countries.
Therefore, recent skyrocketing oil prices are having adverse effects on the economic and
industrial activities of the Philippines.
Current energy policies assert the importance of energy efficiency to improve the self-sufficiency
of energy in the Philippines in the “Philippine Energy Plan 2012-2030”, and demand is expected
be reduced by 10 % by 2030.
The electric power sector accounts for a large proportion of energy demand in the Philippines,
and improvement of energy efficiency in the electricity sector can contribute to the
comprehensive reduction of energy demand.
The National Electrification Administration (hereinafter referred to as “NEA”), counterpart of the
project, is a governmental organization managing and supervising 119 Electric Cooperatives
(hereinafter referred to as “ECs”). Since its establishment in the 1970s, NEA has provided ECs
with technical and financial support. However, many ECs cannot conduct appropriate
maintenance and are short of investments.
According to the statistical data from NEA in 2010, the average of the system loss reductions
(distribution system) for ECs is 12.29%. These losses consist of technical losses, non-technical
losses and administrative losses. Mainly, the resistance of equipment such as power lines and
transformers causes technical losses in the distribution systems. On the other hand, non-technical
losses are defined as meter reading errors and energy thefts, and administrative losses are due to
energy consumed in substations and electric power companies.
The Electricity Regulatory Committee requests that each EC report technical losses and non-
technical losses respectively to grasp the electricity consumption patterns of each customer and
clarify the business management practices of each EC. However, many ECs are not able to grasp
system losses accurately because appropriate measures to evaluate losses have not been
established. Thus, many ECs have not yet taken measures to reduce system losses and improve
business management practices, which results in inefficiency of distribution losses.
In addition, the transmission and distribution loss rate of the Philippines in 2009 was 12.1%. On
the other hand, the loss rate of Asian nations is 4.8% in Japan, 4.9 in China, 5.6% in Thailand,
9.6% in Vietnam, 9.9% in Indonesia, 15.7% in Myanmar and 18.3% in Cambodia. The loss rate of
the Philippines needs to improve by the loss rate level of Thailand, Vietnam, and Indonesia that
are neighboring countries.

1
The energy self-sufficiency rates of Indonesia, Malaysia, and Vietnam are 174%, 134%, and 120%, respectively. On the
other hand, the energy self-sufficiency rates of China, Cambodia, Thailand, and the Philippines are 90%, 71%, 60%, and 60%,
respectively. (Energy Balances of OECD / non-OECD Countries 2009)

2-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
2.2. Current Situation of Electricity and Energy Sector

2.2.1. Institutional Arrangement and Sector Overview

(1) Outline
Since 1936, the generation and transmission business had been operated by the monopoly
National Power Corporation (hereinafter referred to as “NPC”), and the electricity
generated by owned power stations was supplied to distribution cooperatives.
Since the late 1980’s, an Independent Power Producer (hereinafter referred to as “IPP”) is
allowed to enter the market, and NPC began to sell the electricity from its own power
plants as well as that from IPP.
In June 2001, the Electric Power Industry Restructuring Act (hereinafter referred to as
“EPIRA”) was enacted; the transmission department of NPC became the National
Transmission Corporation (hereinafter referred to as “TRASNCO”) as a split-off. As a
result, the generation business is operated by NPC and IPP, while the transmission
business is run by TRANSCO. The assets of NPC have been sold, and the transmission
business license was knocked down by NGCP, which is joint business venture include
State Grid Corporation of China, in an open bid, and has been operated by NGCP.
Moreover, the Wholesale Electricity Spot Market (hereinafter referred to as “WESM”)
was founded in June 2006 and has been operated in the Luzon area.
The distribution businesses in the Philippines are owned by private distribution
cooperatives and public ECs. The distribution cooperatives exclusively supply electricity
via a cross trade transaction with NPC or IPP, or the new WESM market.

Generation Transmission Distribution

NPC WESM

MERALCO
Customers
EC

TRANSCO
NPP

Flow of tariffs and Intra-Area Wheeling Service

Flow of electricity

Figure 2-1 Institutional arrangement of electricity sector in the Philippines


(Source:PSALM、MERALCO)

2-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(2) Related Organizations of Electricity Sector

(a) Department of Energy(DOE)


The Department of Energy (hereinafter referred to as “DOE”) was founded in 1976, and
was entitled to supervise the development and usage of energy. After the enforcement of
EPIRA, the DOE is also in charge of the power development plan as well as energy
planning.

(b) National Electrification Administration(NEA)


The NEA was founded in 1969 to promote electrification in the Philippines. The NEA is
the counterpart of this project, and declares the electrification of all areas by 2020. Its
mission is to assist ECs financially, systematically, and technically in implementing
electrification and quality services.

Figure 2-2 Organization of NEA


(Source:NEA home page)

2-3
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
2.2.2. Distribution Sector

(1) Outline
There are 16 Private Investor-Owned Utilities (hereinafter referred to as “PIOU”)
including the Manila Electric Company (hereinafter referred to as “MERALCO”, 199 ECs,
and 8 Local Government Unit-Owned Utilities (hereinafter referred to as “LGUOU”). In
2008, the total number of customers was 4,570,647, and electricity sales were 26,800GWh.
The number of consumers in 2011 was 4,847,238 houses in MERALCO and 8,027,939
houses in 119 ECs. The sales electric energy in 2010 was 55,266GWh in the Philippines
whole country. The distribution utilities map of the Philippines, which made an extract
from the JICA expert report, is shown in Fig. 2-3. The private distribution utility area is
shown in red and the EC area is shown in yellow. There are 119 ECs in the Philippines in
2011 and there is no big change from this figure. Some EC, such as PELCOII, is due to be
privatized in the near future.

(2) Manila Electric Company (MERALCO)


MERALCO is the largest private distribution company in the Philippines, and Manila is
one of its franchise areas. Its electricity sales account for more than about 55 % of all
sales in 2010.

(3) Electric Cooperatives (ECs)


Private distribution companies operate the lucrative distribution lines in city areas, while
ECs are in charge of areas that are not profitable under the supervision of NEA. All
coverage areas of ECs account for approximately 90 % of all of the Philippines. In 2010,
about 90 % of all customers were classified under resident usage, and the system losses
were 11.9 %.
NEA has provided ECs with technical assistance and loans for the expansion of facilities,
and supported the ECs financially.
ECs are non-profit electricity utilities, and have promoted electrification as a national
policy. Thus, some ECs’ income statements are not stable. NEA evaluates the ECs in
terms of finance and technology, and divides the ECs into 6 levels to facilitate
improvements.
The amount of loan in the 2011 is 1,395,000,000 PHP, and the detail is shown below.

Table 2-1 A mount of loan for EC


 
Type of Loan Actual (M PHP) No. of ECs
  STCF* 464 (average per month) 19
Capital Projects 712 33
  Working Capital 219 12
TOTAL 1,395
*Short Term Credit Finance
(Source: NEA Annual Report 2011)

2-4
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Table 2-2 Ranking of ECs based on management in 2011


Rank Score Num. of ECs Ratio (%)
A+ (outstanding) 90~ 58 49
A (very satisfactory) 75 ~ 89 24 20
B (satisfactory) 65 ~ 74 10 9
C (fair) 55 ~ 64 4 3
D (poor) 30 ~ 54 4 3
E (no improvement) ~29 6 5
No evaluation 13 11
Total 119 100
(Source: NEA data)

2.2.3. Current Method to Reduce System Losses


In the Philippines, distribution loss is relatively high. The loss of the distribution system
owned by the ECs was 11.9 % in 2011. The system losses are limited to 12 % by the
government in 2011, and this regulation makes some ECs’ non-profitable.

(1) Examples of Loss Reduction by MERALCO


The system loss of the MERALCO facilities is 7.35 % in 2011 due to the installation and
improvement of distribution systems.
Methods to reduce losses implemented by MERALCO are shown below.

„ Technical loss reduction


Š Install substations and a capacitor bank
Š Use appropriate capacity distribution transformers
Š Adopt appropriate supply voltage
Š Manage distribution line capacity and load
Š Revise route of distribution systems
Š Upgrade supply voltage for the large load and basic tariff discount
Š Install generators in the distribution systems
Š Reduce operated transformers at off-peak times (ex. 1 bank operation)
Š Recommend peak-shifts and set special tariff price
Š Estimate technical losses using the analysis system

„ Non-technical loss reductions


Š Install a large number of meters at the upper part of poles and conduct meter
readings with cameras
Š Install meters in iron boxes
Š Removal of illegal branch lines
Š Prevent power thefts by excluding unauthorized residents

2-5
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(2) Examples of Loss Reduction by ECs
EC distribution systems are broadly extended, and system losses vary according to ECs.
Methods to reduce losses implemented by the ECs are shown below.

„ Technical loss reduction


Š Install a 5MVA substation to prevent the overload of a transformer, or reduce the
distribution current
Š Improve overload and heating
Š Replace distribution transformers
Š Improve the long single-phase lines (medium-voltage and low-voltage)
Š Install capacitors to the improve voltage and power factor
Š Deforestation around lines
Š Manage voltage using analysis software

„ Non-technical loss reduction


Š Secure 100 % bill collection
Š Prevent power theft
Š Install a large number of meters at the upper part of the poles
Š Replace, adjust, and repair defective meters

Load loss, which is generated from the conductor by flowing the current of a power line,
and no-load loss, which is generated with the distribution transformer, exists in a
technical loss. The most effect measure for technical loss reduction is as follows.
Š Install a substation to prevent the overload of a transformer, or reduce the
distribution current
Š Improve overload and heating
Š Improve the long single-phase lines
Š Replace distribution transformers
Š Install capacitors to the improve voltage and power factor
Moreover, the most effect measure for non-technical loss reduction is Install a large
number of meters at the upper part of the poles, which is the system currently widely held
to the electric power supply to the small colony in the Philippines including MERALCO.

2-6
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

ISELCO I

PELCO II

FLECO

CASURECO II CASURECO IV

SORECO I

LEYECO III

○: Targeted EC

Figure 2-3 Map of distribution utilities in the Philippines


(Source: JICA experts report “Demand and power development plan”)

2-7
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Chapter 3 Basic Policy of Technical Assistance


3.1. Issues on technical loss reduction Projects

(1) Technical Matters


„ Technical Losses
¾ Specific technical loss calculation methods are not established
¾ The load factor of pole transformers are low and iron losses might be high
¾ Customer loads, which are used to calculate technical losses by software, are
estimated based on meter readings. However, the calculated technical losses are
not accurate since these loads include non-technical losses.
¾ Need to unify the temperatures of the conductor resistance on technical loss
calculations.
„ Software (PowerSolve)
¾ As low voltage loss calculations are bundled, it does not identify the exact
location of the loss.
¾ Without a mapping function, it is not easy to know the measurements such as a
load allocation.
„ Non-Technical Losses
¾ Metering data are not validated by the system
„ Economics evaluation
¾ There is no economical index to compare both the facilities investment and loss
reduction effects.
¾ The investment plans are not determined from a long-term viewpoint.
¾ The proper timing for the facilities replacement are not understood

Among these matters, establishment of specific technical loss calculation methods, the
grasp of a loss generating part using the power distribution analysis software equipped
with the mapping function, and the analysis of the proposed measures serve as an
important subject especially. Moreover, as a cause of loss, the situation that the load
factor of pole transformers are low and iron losses might be high is not suitable. The
creation of guideline for the selection method of transformer capacity is important.
Moreover, it is required to enable it to conduct economic evaluation appropriately quickly
from the stage of planning of the draft of loss reduction.

(2) Financial Matters


„ As ECs spend their budget to first repair the facilities, capital investment for loss
reduction is not enough
„ Project selection and prioritization by ERC is as follows,

3-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

1. Power Quality with Safety and Capacity


2. Rural electrification
3. Reliability improvements
4. System loss reduction
Loss reduction projects are the least priority of the ECs to invest in.
„ Update the software fees for loss calculations are relatively expensive

The standard of project implementation of ERC which priority is given to safety or


electric supply reliability is appropriate. On the other hand, technical loss reduction
cannot be achieved depending on the minimum investment only for supply capability. The
TA team recommends the implementation of the project that considered loss reduction as
suitable grasp of the effect because the effect continues to a long period.

(3) Management Matters


„ Lack of engineers in charge of management of electrical power facilities
„ Lack of engineers in charge of using SynerGEE software
„ Lack of efficiency and purchasing power because each EC is too small to order
the equipment

3.2. Project Strategy and Approach

3.2.1. Basic Policy on Technical Aspect


The main tasks are set as follows to achieve this technical assistance’s target.

【Common Tasks】
„ Grasp the current situation and the issues on technical and organizational aspects
of NEA and selected the ECs
„ Examine the overall plan of NEA
„ Examine the existing facilities and plans of selected ECs

【Output 1】
„ Study the existing best practices of selected ECs on loss reduction
„ Manuals and checklist preparation for system loss reductions
„ Carry out studies utilizing manuals to solve problems of selected ECs
„ Manual completion based on the above activities including the integration of best
practices for the non-technical loss reduction of selected ECs through cooperation
with NEA
„ Recommend appropriate methods that supersede other manuals currently used
through cooperation with NEA

3-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

„ Create a system loss reduction manual

【Output 2】
„ Examine and suggest an appropriate method of evaluating system loss reduction
„ Examine the necessity of analytical software
„ Collect data for carrying out an electric power system analysis
„ Conduct a preliminary analysis of power distribution losses
„ Develop methods of evaluating system loss reduction
„ Create a system loss reduction manual which includes technical loss evaluation
„ Train staff of selected EC’s on technical loss evaluations

【Output 3】
„ Examine the standard design and guidelines for 23 kV or 34.5 kV power lines
„ Establish the standard design and guidelines for 23 kV or 34.5 kV power lines
„ Create a system loss reduction manual which includes the basic design and
technological standards for 23 kV or 34.5 kV distribution lines
„ Work preparation to support the planning of full-scale F/S (confirmation and
analysis of a power distribution development plan)

3.2.2. Detailed Approach to solving Issues


The SynerGEE basic and advance training implemented for the engineer’s capacity
development in using SynerGEE software. In addition, the implementation of AMDT pilot
projects and 23kV upgrading studies are recommended to aid in coming up with proper
measures in finding the best solution for technical problems. An abstract of the pilot project
is as follows.

(1) Purpose
„ To create useful and efficient manuals on system loss reduction. A numerical
analysis on the chosen distribution network owned by selected ECs would be
conducted. The results of the analysis should be fully reflected in the manual
wherein the method of finding the proper measure for system loss reduction and in
estimating the individual measures would be described.
„ To transfer the planning technique for network loss reduction to NEA Staff and
concerned ECs
„ To verify the effects of the AMDT after introducing AMDT in three ECs
„ To nominate the candidate sites for the planning and conduct of system loss
reduction projects in the future.

3-3
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

(2) Outputs
„ Manuals on the system loss reduction are released and utilized.
„ Distribution professionals belonging to the counterpart organizations are trained to
make plans for the loss reduction utilizing software.
„ Understand the effects of AMDT to reduce losses and its easy O&M
„ Information on candidate sites for the future project is shared particularly with
those concerned with JICA’s technical cooperation.

(3) Procedures
1). Estimation of economical value created by reducing the system losses, which would
be equivalent to the costs of the construction work that would be implemented to
diminish losses.
2). Grasping the costs of each measure for loss reduction such as expanding the LV
network or installing new DTs and so on.
3). Surveying the distribution network
„ Listing up the overloaded DTs by checking the DSL data or by detecting the load
currents of some DTs.
„ Showing the expectation of reduced non-load losses of DTs by replacing the
conventional DTs to AMDTs.
4). Draft manuals on distribution network loss reduction
„ The selection of proper facilities such as wires or DTs from the perspective of
reducing technical losses
„ Guidance in choosing between two alternatives, multiplying the number of wires or
installing big conductors
„ Showing sample cases like upgrading the system voltage is expected to be a better
choice.
„ A comparison between the two methods, by expanding the LV line or MV line,
which means that a new DT would be installed.
„ Connecting the two distribution MV feeders, the load of one feeder is much bigger
than the other. The loads of the two feeders shall be well balanced to reduce the
total losses of the two MV lines.
„ The relocation of some of the DTs that would diminish the losses from the LV
lines.
„ The suppression of the non-load losses from the DTs by replacing the existing
transformers to the AMDTs, whose iron-losses would be much less than that of the
conventional ones.

3-4
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

5). Simulations
„ The simulation models of some distribution system for SynerGEE would be
created. Power flow, network losses and the voltage profile of the simulated
distribution feeders shall be checked.
„ The proposed methods for loss reduction described in the draft manuals would be
studied in computer simulations. The effectiveness of the recommended measures
to improve the system losses of the listed DTs shall be confirmed via the
SynerGEE simulations.
„ Know-how on making plans to reduce the system losses by software aids shall be
transferred to the distribution technicians of the counterpart organizations.
„ To confirm the effects to introduce AMDT as the pilot project and to measure the loss
reduction by the ECs
6). Efficient methods shall be included in the planning manual on loss reduction.

3-5
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

3.3. Work Flow


The next figure shows the flow of the entire Technical Assistance.
FY 2010, FY 2011
FY 2012

Figure 3-1 Flow of Overall Technical Assistance

3-6
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

3.4. Basic Policy of the Study Implementation

(1) Technology Transfer and Personnel Training


In this Technical Assistance, the TA Team worked with NEA and selected ECs to grasp
and analyze the present situation in consideration of the organizational and technical
aspects. Since the tasks were primarily conducted on-site (in the Philippines), the
opportunity for the technology transfer and over-all human resource cultivation is deemed
important.
The TA Team members provided technical assistance to counterparts for capacity
enhancement in each field of specialization. Through one-on-one coaching, knowledge
and skills were imparted to counterparts and priority issue solving activities were carried
out. During the training, each expert explained the TA objectives, ways and methods of
evaluating results. Moreover, the counterparts were encouraged to execute their tasks
though OJT as much as possible.

(a) Management Manuals for System Loss Reduction are prepared and are
appropriately practiced
The TA Team will tackle priority issue solving activities with selected ECs and propose
workable countermeasures through introducing the Japanese best practices. In addition,
the management system, which can share the best practices in all ECs, was developed in
collaboration with NEA. Moreover, the trainers who can become a lecturer of priority
issue solving activities were developed through participating counterpart training in
Japan.

(b) Support system for quantitative evaluation of system loss is established


The TA Team developed the support system for quantitative evaluation of system loss
in collaboration with NEA. When it is judged because of investigation that system
analysis software needs to be introduced, the quantitative evaluation technique that
used system analysis software is practiced, and the trainers who can become a lecturer
was developed.

(c) Support system for upgrading the present mid-voltage to 23kV and technical
design standards are established
The TA Team developed required guideline through considering standard specification
in collaboration with a counterpart. Moreover, The TA Team will explain the necessary
requirements for F/S based on the developed guideline. In addition, while having an on-
site exploration of a power distribution development project area and explaining the
point of an on-site exploration, it teaches so that the power distribution route and
substation point investigation may be possible by a counterpart independent.

3-7
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

(2) Workshop
The Staff of NEA and around three participants from each selected EC participated in the
workshop during the 2 nd , 4 th , 5 th and 9 th field survey. The purpose of the workshops is to
share the best practices that would be introduced by the selected EC participants and to
explain the progress of the system loss reduction manual, the support system for the
quantitative evaluation of the system loss and support system to upgrade the present
medium voltage to 23 kV or 34.5 kV including technical design standards. In the
workshop, from the perspective of technology transfer, the counterpart staff made the
presentation as much as possible. The participants in this workshop shall in turn be
responsible to share the knowledge and skills acquired with their colleagues upon
returning to their respective ECs.

(3) Counterpart Training in Japan


Maximum cooperation should be carried out to implement practical training on system
loss reduction & efficient management technique among others to the counterpart training
members.
The contents, trainees, time schedule and others of the counterpart training in Japan
(FY2011 and FY2012) have been decided through mutual discussion among the TA Team,
counterparts and JICA during field surveys. The appropriate steps for a successful
technology transfer was planned as part of the counterpart training program to include
study tours at Tokyo Electric Power Company, Shikoku Electric Power Company, quality
control methods of the associated company and system loss reduction techniques.

Additionally, counterparts were able to understand the manufacturing process and


maintenance procedures at the factory visit such as AMDT, meters and electric poles, and
knowledge about quality control could be deepened. By touching an actual thing, since it
has experience that is strongly impressive, it is expectable to practice to have learned by
the counterpart training in Japan within each EC in future.

3-8
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Chapter 4 Inputs
4.1. Inputs from Japanese Side

4.1.1. Experts
This project involved the dispatch of expert project teams and team leaders from Japan. The
performance and achievement of the dispatch of these expert project leaders are outlined in
Appendices 2 & 3. The table 4-1 shows the total dispatch Records of the project.

Table 4-1 Total dispatch Records of the project

M/M M/M
Year Total
(Site Survey) (Domestic Surver)
2010 0.00 0.30 0.30
2011 11.58 5.48 17.06
2012 13.80 5.85 19.65
Total 25.38 11.63 37.01

4.1.2. Counterpart Training in Japan


Counterpart Training in Japan was held four times between FY2011 and FY2012. The C/P
training consisted of lectures and study tours for about two weeks. The subjects of the C/P
training were mainly on the “System loss reduction method”, “Data management” and
“Quality control”. In total, 20 NEA and EC staff members had the opportunity to attend the
series of the training in Japan.
The trainees’ lists of counterpart training in Japan can be found in Appendix 4.

4.1.3. Equipment
During the period of project implementation, SynerGEE software, which was given to 7 EC
one license which is the number of minimum respectively, indicated as required at the very
beginning of the project, and digital clip meters, which was given to 7 EC two sets which is
the necessary requirement respectively, and amorphous transformers for pilot project shown
to be necessary during the operation phase, were purchased. Appendix 5 lists all such
equipment. This equipment will be required in future management activities at the relevant
ECs; as such, the equipment has been gifted to them.

4.1.4. Others
JICA has shouldered local activity costs, such as travel expenses, pilot project costs,
workshops and others.

4-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
4.2. Inputs from Philippine Side

4.2.1. Counterparts
Counterpart organizations are as shown in Chapter 1.1.3. and Chapter 1.1.4.

4.2.2. Spaces and facilities for project activities


NEA offered the office space for the Japanese experts at NEA, and the utilization costs of
electricity and water in the project office.

4-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Chapter 5 Project Activities


5.1. Outline of Project Activities
The project whose implementation was started in March 2011 is intended to provide technical
assistance to enhance the capacity of NEA and related organizations. The site surveys were
implemented six times.
„ The 1 st site survey: From April 3, 2011to April 16, 2011
„ The 2 nd site survey: From July 17, 2011 to August 5, 2011
„ The 3 rd site survey: From October 13, 2011 to October 28, 2011
„ The 4 th site survey: From January 29, 2012 to February 17, 2012
„ The 5 th site survey: From May 22, 2012 to June 6, 2012
„ The 6 th site survey: From August 15, 2012 to August 31, 2012
„ The 7 th site survey: From November 13, 2012 to December 21, 2012
„ The 8 th site survey: From January 6, 2013 to January 19, 2013
„ The 9 th site survey: From February 18, 2013 to March 5, 2013
The details are shown in appendix 2 and 3.

5.2. Detailed Activities

5.2.1. Outcome of the Study


„ Preparation of the reports
¾ Preparation of Implementation Plan
¾ Progress Report (FY2011)
¾ Completion Report for FY2011
¾ Progress Report (FY2012)
¾ Project Completion Report
„ Study and prepare Technical Assistance
¾ System Loss Reduction Manual
(Include the “System Loss Quantitative Evaluation” and “Design Criteria and
Technical Standards for the Upgraded Distribution Line Voltages”)

5.2.2. Site Survey Implementation


„ Accomplished tasks during the first site survey
¾ Work plan explanation to the counterparts (held kick-off meeting)
¾ Data collection and information review
¾ Grasped issues and the situation concerning the institutional and technical
aspects of NEA and ECs
¾ Confirmed the overall plans/policies of NEA
¾ Confirmed software usage conditions for power flow analysis of selected ECs
¾ Examined existing facilities and plans of selected ECs
„ Accomplished tasks during the second site survey

5-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
¾ Conducted the first Joint Coordination Committee meeting
¾ Carried out a workshop specifically for sharing best practices in system loss
reduction.
¾ Introduced distribution planning methods in Japan
¾ Confirmed current best practices to advance the loss reduction by selected ECs
¾ Examined the appropriate methods of evaluating system loss reduction
¾ Examined the necessity of analysis software
¾ Acquisition and request of data for the power distribution system analysis
¾ Examined the existing facilities and plans of the selected ECs
„ Accomplished tasks during the third site survey
¾ Data collection and information review
¾ Confirmed the current best practices to advance the loss reduction by selected
ECs
¾ Examined the appropriate methods of evaluating the system loss reduction
¾ Preparation of case studies for the application of the manuals into the selected
ECs
¾ Acquisition and request of data for power distribution system analysis
¾ Examined existing facilities and plans of the selected ECs
¾ Examined proper design standards for a 23 kV distribution line
„ Accomplished tasks during the fourth site survey
¾ Conducted the second Joint Coordination Committee meeting
¾ Carried out a workshop specifically to share best practices in system loss
reductions.
¾ Confirmed current best practices to advance loss reductions via selected ECs
¾ Propose appropriate methods to evaluate system loss reduction
¾ Acquisition and request of data for the power distribution system analysis
¾ Request of power distribution line modeling for the power distribution system
analysis
¾ Preparation of case studies for the application of manuals into the selected ECs
„ Accomplished tasks during the fifth site survey
¾ Carried out a third workshop specifically for the presentation of power
distribution line modeling for power distribution system analysis
¾ Carried out SynerGEE training
¾ Confirmed current best practices to advance loss reduction by selected ECs
¾ Assistance for the power distribution line modeling for power distribution
system analysis
¾ Request of power distribution line modeling for power distribution system
analysis

5-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
¾ Preparation of the System Loss Reduction Manual including the “System Loss
Quantitative Evaluation” and “Design Criteria and Technical Standards for the
Upgraded Distribution Line Voltages”
„ Accomplished tasks during the sixth site survey
¾ Preparation of the System Loss Reduction Manual including the “System Loss
Quantitative Evaluation” and “Design Criteria and Technical Standards for
Upgraded Distribution Line Voltages”
¾ Discussion of contents of the System Loss Reduction Manual
¾ Confirmed the pilot project of the amorphous transformers
¾ Preparation of the Total Ownership Cost (TOC) calculator
„ Accomplished tasks during the seventh site survey
¾ Conducted the third Joint Coordination Committee meeting
¾ Discussion of the contents of the System Loss Reduction Manual
¾ Introduction and explanation of the System Loss Reduction Manual for ECs
¾ Confirmed the pilot project of amorphous transformers
¾ Evaluation of the pilot project of amorphous transformers
¾ Preparation of the Total Ownership Cost (TOC) calculator
¾ 23kV upgrading candidate sites survey
¾ Modeling of the distribution system for 23kV upgrading candidate sites
¾ Simulation of the distribution system for 23kV upgrading candidate sites
„ Accomplished tasks during the eighth site survey
¾ Finalized System Loss Reduction Manual
¾ Evaluation of the pilot project of amorphous transformers
¾ Modeling of the distribution system for 23kV upgrading candidate sites
¾ Simulation of the distribution system for 23kV upgrading candidate sites
¾ Evaluation of the distribution system for 23kV upgrading candidate sites
„ Accomplished tasks during the ninth site survey
¾ Carried out a fourth workshop specifically to introduce the System Loss
Reduction Manual to all ECs
¾ Submit the System Loss Reduction Manual to all ECs
¾ Submit the project completion report
Details are shown in Appendix 6, meeting minutes.

5.2.3. Cooperation on a Variety of Reports and Conferences


The TA Team explained the plan of the project and held discussion with NEA and related
organizations on how to proceed with the survey. The first Joint Coordination Committee
meeting was held on July 28. The second Joint Coordination Committee meeting was held on
February 7 and the third Joint Coordination Committee meeting was held on November 27,
and the first workshop was held on July 29, 2011, the second workshop was held on February

5-3
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
8, 2012, the third workshop was held on May 31, 2012 and the fourth workshop was held on
February 28, 2013. The workshop materials can be found in Appendix 7.
„ The first Joint Coordination Committee meeting
¾ The TA Team reported the status of the project, and discussed how to proceed
with related organizations.
„ The first workshop
¾ The TA Team explained the outline of the project and the method to reduce
system losses in Japan.
¾ Selected seven ECs and introduced their best practices to reduce system losses.
„ The second Joint Coordination Committee meeting
¾ The TA Team reported the status of the project, the contents of the system loss
reduction manual and discussed how to proceed with related organizations.
„ The second workshop
¾ The TA Team explained the contents of the system loss reduction manual, the
appropriate methods for evaluating the system loss reduction and the effects of
introducing AMDT.
¾ Selected seven ECs and introduced their best practices to reduce system losses
based on the sheet of “Good Practices for System Loss Reduction”.
„ The third workshop
¾ The TA Team explained the method of Loss Reduction for the Medium Voltage
Line, the sample analysis of the Loss Reduction for the M V Line using
SynerGEE, and propose an appropriate mechanism to transfer the loss reduction
method to all ECs and the incentive system.
¾ Selected seven ECs and introduced their sample analysis of the Loss Reduction
for the MV Line using SynerGEE.
„ The third Joint Coordination Committee meeting
¾ The TA Team explained the contents of the system loss reduction manual, the
appropriate methods for evaluating the system loss reduction and the effects to
introduce AMDT and 23kV upgrades.
¾ NEA and the TA Team agreed with the contents of the system loss reduction
manual.
¾ NEA and the TA Team confirmed the evaluation of the AMDT pilot project.
¾ NEA and the TA Team confirmed the 23kV upgraded sites.
„ The third workshop
¾ The TA Team explained the system loss reduction manual to all ECs.
¾ The TA Team reported the results of the AMDT pilot project.
¾ The TA Team reported the results of the 23kV upgraded sites simulation using
SynerGEE.

5-4
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
5.2.4. Record of installation and training of SynerGEE software

(1) Record of installation of SynerGEE software


Each EC uses the power system analysis software, PowerSolve and SynerGEE, in order to
conduct a quantitative evaluation of system losses. Each of the software can calculate
system loss. However, PowerSolve cannot visualize the source of loss outbreak in the LV
line loss calculation. On the other hand, SynerGEE has a function of mapping and can
display the source of loss outbreak by color according to the amount of loss. Because of
this, we can easily grasp the source of loss outbreak. And we can also visually form
countermeasures of loss reduction and confirm the effects. Moreover, by using switching
function, which is an optional function of SynerGEE, SynerGEE can make the
composition of the system of which system loss is the least. SynerGEE is a very powerful
tool for loss analysis. The results of the comparison confirmed that SynerGEE is more
useful than PowerSolve, therefore, the SynerGEE Electric Load Flow Core (SYNE) and
Middlelink Electricity that is the option software is installed. The record of the
installation of the SynerGEE software to each EC is shown in the following table.

Table 5-1 Record of installation of SynerGEE software


(License number)

SynerGEE
Electric Load Middlelink
EC Remark (The past use record)
Flow Core Electric (ML-E)
(SYNE)
ISRECO I 1 1 New installation
PELCO II 1 1 Used old version
FLECO 1 1 Used old version
CASURECO II 1 1 Under training
CASURECO IV 1 1 New installation
SORECO I 1 1 New installation
LEYECO III 1 1 New installation
NEA 1 1 Used old version

(2) Record of training of SynerGEE software


The record of training of SynerGEE software for each EC is shown in the following table.
Because of training, the engineers have reached to the level that can propose the system
loss reduction project used SynerGEE at the workshop.

5-5
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Table 5-2 Record of training of SynerGEE software


(Number)

Number of Number of
EC attendance of attendance of Total
basic trainig advance trainig

ISRECO I 11 11 22
PELCO II 11 11 22
FLECO 13 12 25
CASURECO II 10 9 19
CASURECO IV 6 5 11
SORECO I 10 11 21
LEYECO III 5 8 13
Total 66 67 133

(3) Status of medium voltage feeder modeling using SynerGEE software


The status of modeling the medium voltage feeder, which was not modeled before project
implementation, using SynerGEE software is shown in the following table. Modeling
means the state that has finished to input the data of a power distribution system and to
build a database, and can be performed the simulation.

Table 5-3 Status of distribution system modeling using SynerGEE software


(Feeder number)

Number of medium Number of medium


voltage feeder which voltage feeder which
Total Number of
EC has been completed to has been completed to
medium voltage feeder
model except for low model include low
voltage system voltage system
ISRECO I 1 1 16
PELCO II 1 1 22
FLECO 8 0 8
CASURECO II 0 0 11
CASURECO IV 0 0 4
SORECO I 0 0 5
LEYECO III 0 0 4

5.2.5. System Loss Reduction Manual


The content of the System Loss Reduction Manual, which includes the “System Loss
Quantitative Evaluation” and the “Design Criteria and Technical Standards for Upgraded
Distribution Line Voltages” shows the following:

5-6
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Table 5-4 Contents of the System Loss Reduction Manual

Contents
1 Introduction
1.1 Purpose of This Manual
1.2 Types of Distribution Technical Losses and Their Countermeasures
1.2.1 General
1.2.2 Countermeasures
1.2.3 Concept of Seeking an Appropriate Technical Loss Reduction
1.2.4 Example of Loss Occurrence of Conductors
1.3 Planning Procedures of Technical Loss Reduction
1.3.1 Medium Voltage (MV) Loss Reduction
1.3.2 Low Voltage (LV) Loss Reduction
1.4 Appropriate Methods for Manual Distribution
1.4.1 Method for Maximum Utilization of the Technical Loss Reduction
Manual
1.4.2 Renewal of the Technical Loss Reduction Manual
1.4.3 Award of Good Practices for System Loss Reduction
2 Economical Evaluation for Technical Loss Reduction
2.1 Introduction
2.2 Methodology of Calculating Cost Savings from Loss Reduction
2.2.1 Outline
2.2.2 Process of Estimating Cost Saving
2.3 Countermeasure Cost
2.4 Benefits / Costs Analysis
2.4.1 Net Present Value (NPV)
2.4.2 Internal Rate of Return (IRR)
2.4.3 Practical Method to Estimate Total Cost Savings
3 Methodology of O&M for Data Arrangement of Loss Analysis
3.1 Network Data
3.2 Load Data
4 Identifying Countermeasures against Technical Losses for Low Voltage system
4.1 Calculation Methodology of the Operating Status of the Low Voltage System
4.1.1 Methodology based on the DSL data
4.1.2 Methodology of Confirming Operating Status of the Low Voltage
System by Using SynerGEE
4.2 Countermeasure Options to Prevent Technical Losses Caused in the Low
Voltage System
4.2.1 Line Thickening
4.2.2 Capacity Changing ( Small Æ Big )
4.2.3 Capacity Changing ( Big Æ Small )
4.2.4 Load Dividing
4.2.5 Load Centering
4.3 General Commentary for Taking Countermeasures against Technical Loss
Reduction
4.3.1 Concept of the Low Voltage Technical Loss Reduction
4.3.2 Proper Installation of Pole Transformers
4.3.3 Proper Installation of Low Voltage Wire

5-7
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
4.3.4 Transformer Load Management
4.4 Recommended Size of the Transformer and the Electric Wire
4.4.1 Identifying the Proper Consumption in Low Voltage System
4.4.2 Permissible Overload of Transformer
4.4.3 Recommended Transformer Capacity
4.4.4 Low Voltage Wire Selection Method
4.5 Installation of amorphous transformer
4.5.1 Effects for Introducing Amorphous Transformers
4.5.2 Cost Evaluation of Amorphous Transformers
4.5.3 Cost Evaluation of Amorphous Transformer Using TOC Simulation
4.5.4 Measurement and Testing for Amorphous Transformer
5 Identifying Countermeasures against Technical Losses for Medium Voltage
System
5.1 Calculation Methodology of the Operating Status of the Medium Voltage
System
5.1.1 Upstream Approach Method
5.1.2 Downstream Approach Method
5.2 Options of Countermeasures against Technical Losses Caused in the Medium
Voltage System
5.2.1 Line Thickening
5.2.2 Parallel Circuit
5.2.3 Upgrading Voltage
5.2.4 Capacitor Placement/Replacement
5.2.5 Load Balancing
5.2.6 Switching Optimization
5.2.7 Phase Increasing
5.3 Criteria for Taking Countermeasures against Technical Loss Reduction in
Medium Voltage System
5.3.1 Conditions of Study
5.3.2 Criteria of Line Thickening and Parallel Circuit
5.3.3 Criteria of Phase Increasing
5.3.4 Criteria of Capacitor Placement/Replacement
5.3.5 Criteria of Switching Optimization
5.4 Appropriate Capacities of Conductor Sizes
5.5 Appropriate Voltage for Installation of the New Transformer of the
Distribution Substation
6 New Installation of Distribution Substation and Upgrading MV Network
6.1 MV network Expansion Measures
6.1.1 Outline
6.1.2 New Installation of Distribution Substation
6.1.3 Upgrading MV Network
6.1.4 Standard System Voltage for MV Network
6.2 General Commentary for New Installation of Distribution Substation
6.3 General Commentary for Upgrading MV Network
6.3.1 Distribution Substation
6.3.2 Temporary Ways for Upgrading Business
6.3.3 All-new Equipments Installation
6.3.4 Utilizing the Existing Poles
6.3.5 Re-connection of Distribution Transformers
6.3.6 Other Issues

5-8
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
6.4 General Commentary for Upgrading MV Network
6.4.1 Evaluation Stage
6.4.2 Decision making by Management
6.4.3 Stage I
6.4.4 Stage II
6.4.5 Final Stage
7 Using SynerGEE
7.1 Confirming the Operating Status of the Distribution System
7.1.1 Implementation of Load Flow by SynerGEE
7.1.2 Confirmation of Operating Status of Distribution Transformer
7.1.3 Confirmation of the Operating Status of a Low Voltage Line
7.2 Procedure of Load Allocation
7.3 Power Flow Analysis
7.4 Method of Capacitor Placement using SynerGEE
7.5 Method of Switching Optimization Using SynerGEE
7.6 Load Balancing Improvement Using SynerGEE
7.7 Phase Balancing Improvement Using SynerGEE
8 Non-Technical Loss Reduction Activities
8.1 Method of Non-Technical Loss Reduction
8.2 Good Practices for System Loss Reduction
8.2.1 Sorsogon I Electric Cooperative Inc. (SORECO I)
8.2.2 Pampanga II Electric Cooperative Inc. (PELCO II)
8.2.3 Camarines Sur IV Electric Cooperative Inc. (CASURECO IV)
8.2.4 Cebu I Electric Cooperative Inc. ( CEBECO I )
8.2.5 Bohol I Electric Cooperative Inc. ( BOHECO I )
8.2.6 Isabela I Electric Cooperative Inc. (ISELCO I)
8.2.7 First Laguna Electric Cooperative Inc. (FLECO)
8.3 Good Practices Sheet for System Loss Reduction Method of Non-Technical
Loss Reduction

The system loss reduction manual presents intelligibly the criteria or standard of the
procedure of planning of the measure against the loss reduction so that the engineers in
charge of loss reduction can carry out work smoothly.

(1) Economical Analysis for Technical Loss Reductions


There are many methods to reduce technical losses. A method to estimate loss reduction
benefits easily from simulation results is necessary to verify the candidates. Therefore, the
TA team proposed a simple method to estimate easily the loss reduction benefits and its
procedures are described in the manual. Specifically, cost benefits are calculated based on
the 1 kW loss reduction benefit during the peak time and the loss reduction (kW) using
the simulation. Related knowledge such as NPV and IRR is also explained.

5-9
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(2) Methodology of O&M for data arrangement of the loss analysis
The system losses are calculated by inputting the necessary information to the system
model. The following figure shows the flow of loss calculation. Therefore, it is
necessary to maintain the system model and properly input information in order to
calculate the system losses correctly. The outline of each data arrangement is described as
follows.

Input System Model Output


System Data
Feeder Current Network Data
System Loss
Load Data DT,MV,LV,SD
Energy Consumption

Figure 5-1 Flow of system loss calculation

¾ Network data
The system model is composed of such network data as the distribution transformer, the
distribution line and so on. This network needs to be updated constantly because of the
changing facilities such as the new customer connections and improvement work.
Therefore, it is necessary to properly renew the system model, in case the distribution
facilities undergo changes.
It is easy to renew the system model to suit the contents of the construction, because
SynerGEE has a mapping function. Also by using Middlelink, which is a function added
to SynerGEE, it is easy to partially add and change new facilities to the system model.
Therefore, the TA Team proposed the O&M methodology for the network data
arrangement by using these SynerGEE functions.

¾ System data, Load data


z System data
The system data are the current, voltage, power factor etc of each distribution feeder.
This data is recorded at the distribution substation in each EC. Given that this data is
necessary for system loss calculation, the TA Team described the necessity of managing
these data with a Microsoft Excel database.

z Load data
The load data is the energy consumption data of each customer. Given that this data is
necessary to calculate electricity rates, each EC acquires and is properly managing this
data properly. Furthermore, this data is easily available for the system loss calculation
by using Middlelink. The TA Team described this methodology.

5-10
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(3) Identifying countermeasures to prevent technical losses for the low
voltage system
(a) Methodology of calculation of the operating status of the low voltage system
It is necessary to properly grasp the operating status of each of the distribution facilities
in order to identify system loss countermeasures. In this part, we made a proposal on
how to grasp the operating status of the distribution transformer and the low voltage line
which is composed of the low voltage system. At that time, we described the
methodologies by using not only the PowerSolve data but also SynerGEE. Furthermore,
regarding the distribution transformer, we proposed a methodology to create the list
classified by the operating status of the distribution transformer.

(b) Countermeasure options to prevent technical losses caused in the low voltage
system
We proposed 5 items as countermeasure options to prevent technical losses caused in the
low voltage system. Furthermore, we described the contents, target facilities and
effects of the proposed items as follows;

¾ Thickening of the low voltage line


9 Change existing low voltage line to the upper size
9 Apply to the high-operated low voltage line
9 Reduce technical losses by lowering the operating ratio of the low voltage line
¾ Capacity changing of the distribution transformer small => large
9 Change the capacity of the transformer to a large size
9 Apply to high operated transformers
9 Reduce technical losses by lowering the load loss of transformer
¾ Capacity changing of the distribution transformer large => small
9 Change the capacity of the transformer to a small size
9 Apply to low operated transformers
9 Reduce technical losses by lowering the no load loss of the transformer
¾ Load dividing
9 Divide load by adding a new transformer
9 Apply to high operated transformers and the low voltage line
9 Reduce technical losses by lowering the load loss of the transformer and the
operating ratio of the low voltage line
¾ Load centering
9 Move transformers at the center of load
9 Apply to the high operated low voltage line
9 Reduce technical losses by lowering the operating ratio of the low voltage line

5-11
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Furthermore, we show the specific examples of these options, and describe the
confirmation of the effect of each countermeasure.

(c) Criteria for implementing countermeasures of the low voltage system


The position of the low voltage system is the end terminal of the electric power system
and its power flow counts high values, because its currency is flowing through the
various facilities such as generators, transmission lines and the high voltage/medium
voltage lines. This means that the loss reductions in the low voltage system are valuable
compared with that of the high voltage/medium voltage lines.

The losses consist of the resistance loss from the line and iron/copper losses from the
pole transformers. The criteria of the low voltage system operation to reduce losses are
as follows,

¾ Dividing system by installing the pole transformers


Although the low voltage line losses are one of the line’s resistance losses, this loss
reduction should be considered with the installation span of the pole transformers.

That is becouse the installation span are related to the cross section size of the
conductors.
This means it is very important to install pole transformers (new additions and
replacements) in consideration of the demand density in this area and its demand
increasing rate.
The loss reduction manual should instruct on the appropriate load dividing
measurement by installing new transformers

New TR
SS
Tr1 Tr2
R1 I R4 I1
I=I0-I1 2

R3

New consumer

Figure 5-2 Dividing load by transformer

¾ Strengthening or replacing low voltage feeders


The low voltage system losses are proportional to the square of the line current and to
the line resistance. It is not affected by the power factor and frequency. For this
reason, it is possible to reduce the system losses to thicken the cross section of the
conductors per the results of the analysis of the load density and the load dispersions in

5-12
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
the supply area. But the real onsite situation is not dependent on these methods. The
criteria of the low voltage line strengthening are not conducted using loss reduction
measures but with a voltage drop limitation.
The TA team discussed the countermeasures against the voltage drop regulation with
ECs and created the manual to include the apropriate contents in these subjects.

¾ Replacing / relocation of pole transformers


The apropriate location of the pole transformers are mentioned in the previous section,
to reduce the losses of the transformer itself (Iron/Cupper loss), it is important to
manage the transformers which are of the overload and old type and if the conditions
are not suitable, they should be replaced.
The transformers are the most important parts of the low voltage distribution facilities.
Therefore the criteria of replacements are closely related to the economical operation of
the distibution facilities. It is vital to be very careful during the decsion-making process
and conduct operations properly.
To create the new replacement rules, the TA team discussed this rule including the
quantitative evaluation with the NEA and ECs in consideration of the operational
limitations of the transformer that is mentioned in the next section

(d) Appropriate capacities of pole transformers and sizes of conductors


The appropriate capacity of the pole transformers shall be selectied to meet its real load.
However, in a real situation it is very difficult to monitor the realtime load in each
transformer and it is more practical to estimate the proper capacity from the customer
facility and the unequal rate of the load.
The TA team discussed this operational limit with NEA and the ECs and described the
calculation methods of the capacity in the manual.

Additionally, as the maximum peak load time of the residential load curve of the
Philippines is just a few hours, it is an economical way to accept the short time overload
operation to consider the temperature limitation of the core of the transformer.
The limitation of the tempratures should be carefully decided depending on its
specifications because the overload is closely related to the decrease of the lifetime of
the transformers.
In this study, the TA team held a discussion with the Philippine members on the tolerable
amount of temperature. As a result of the discussion, the TA team proposed the IEEE
index and the transformer size up methodology. They are described in the manual.

5-13
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(e) Installation of amorphous transformers
In recent years, non-load transformer losses expect to be dramatically reduced due to
technical innovation to introduce the amoulphas material to its iron care.
There are many past failures and it makes sense to be apprehensive of the quality of the
amoulphas transformers made in India, because there has been much trouble with them in
the past. But for the past three years Philec, transformer manufactures, has been
producing the amoulphas transformers and shipped them to MERALCO. MERALCO has
a plan to replace the existing silicon transformer to amoulphas in order.

In this study the TA team are considering the fact that Philec company are using the
Japanese amoulphas technology for their materials, and the TA Team gave a presentation
concerning these technologies at the workshop. As a result of the workshop presentations,
there are more reactions from the ECs than we expected and the TA team implemented
the amoulphas pilot project with ISELCO I , PELCO II and FELCO.
Consultation should be held with NEA on the contents of the manual such as on the
effects of there being no special tools and know-how for their maintenance. However it
is expected that there will be a lot of loss reductions with quantitative values.
Furthermore, the TA team tried to encourage the ECs to introduce amoulphas
transformers to reduce their losses.

[ 25kVA(Load 50%) ]
150 No-Load Loss
Load Loss
Amorphous 100

Core 50
Coil 0
SIT AMT

Figure 5-3 Amorphous transformers and its loss reduction

The TA Team described the effects of the verifications for AMDT and the result of the
simulations in the manual according to the pilot project of AMDT donated by JICA.

5-14
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(4) Identifying countermeasures to prevent technical losses for the Medium
voltage system
Generally, if the scale of demand becomes large, installation of 23kV and 35kV is more
efficient than installation of 13.2 kV, because the merit may become large rather than the
increment of cost. Therefore, the TA Team ran a simulation and proposed the loss
reduction project, which includes upgrading the voltage level from 13.2 kV to 23 kV.
The contents are the “Methodology of the Calculation of the Operating Status of the
Medium Voltage System”, “Options of countermeasures to prevent technical losses caused
in the medium voltage system”, “Criteria for implementing countermeasures of the
medium voltage system” and “Appropriate sizes of conductors”. Furthermore, the TA
team showed specific examples of these options, and described the confirmation of the
effects of each countermeasure.

(5) Adding Transformers to Substations / Installation of Substations /


Upgrading Voltage of Medium Voltage (MV) Feeders
By dividing the MV distribution line into two or three by installing a new substation is
effective for system loss reduction, because the total length of the MV network of the
divided line would be shortened and it means both the current and resistance of the wires
will decrease. Another practical measure is to upgrade the MV system voltage, which
would diminish the network current in accordance with the increased voltage. It is a
significant project for the power utilities to install a new substation or to upgrade the MV
network, which would take a long time and much money for completion. So the utilities
are required to conduct a comprehensive study on the loss-reduction projects.
Chapter 6 of the System Loss reduction manual outlines the general procedures to assess
each project proposed to decrease the system losses. The network expansion measures are
summarized in 6.1 Methodologies on installing the new substation and upgrading the MV
network voltage are spotlighted. In 6.2, the actual plan to install the new substation in
some EC was described and explained as a case study model. The items to be examined in
the secondary side of the substation and in the MV network were described, when the
project on upgrading the voltage is being planned, as the upgrading business affects both
the substations and the MV lines.

(6) Non-technical Loss Reduction


According to the NEA data of technical and non-technical losses in 2010, there is a
tendency that each categorized EC has the different measurements to reduce their losses
as shown in the Figure below.

¾ Step 1: In the poor performance EC, more than half of the system losses are
piliferages and these ECs focus on the measuremants to reduce non technical losses.

5-15
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
¾ Step 2: It is difficult to reduce non-technical losses to less than several percentages,
the ECs try to reduce the technical losses as the next measurements.

%
30
% 1) Reduce Non-Tech
25
Target ECs
20
15 2) Reduce Tech Non‐Tech Loss
15 11
Tech Loss
5
10
3
5 9 9 9
6
0
15%-20% 10%-14% Single Digit
D
21% & above C B A
SL Categories

Figure 5-4 NEA data of technical and non-technical losses in 2010

Most of the selected seven ECs in this project are categorized into the ECs of which
system losses are about 10-14%. They conduct the measurements to achieve a single digit
loss rate to reduce both technical and non-technical losses.

All these seven ECs gave presentations of their loss reduction measurements in the
workshop to share the good practices in other ECs, and many ECs already know the
proper measurements to reduce especially non-technical losses. Here are the concrete
measurements conducted in many ECs.

1) Measurements for distribution lines


¾ Periodical patrol to clean and trim the trees near the lines

2) Measurements for the service drop wire


¾ Pull-out of the service drop wire and remove the illegal wire

3) Measurements for the Metering System


¾ Install pole metering at the secondary line of the TR
¾ Clustering meters
¾ Meter Box Installation and its seal
¾ Defective / Inaccurate meter replacement
¾ Correction of the Meter Reading Error

5-16
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
In addition, the TA team made a presentation referring to the lessons of loss reduction in
Brazil. This information is very useful in Philippine, because the slum situation is very
similar in both countries. Moreover, electric meters are expected to be one of the most
effective measurement tools to reduce losses also in the Philippines.

In the second JCC on the 7th, February, both JICA and the Philippine side agreed that
the manual to reduce non-technical losses would be made mainly per the Philippine side,
and according to that agreement NEA described chapter 8, which is the non-technical
loss reduction part.

In addition, the TA Team gave the following format of the good practices for system loss
reduction. At the second and third workshop, each EC presented the good practices to
achieve system loss reduction. That provided a good opportunity to know the other EC
good practices to achieve system loss reduction. These good practices are part of the
System Loss Reduction Manual.
Moreover, the TA Team proposed the system for lateral spread of the good practices to
achieve system loss reduction in collaboration with NEA.

5-17
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Figure 5-5 Format of the g ood practices for system loss reduction

5-18
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
5.2.6. The pilot projects installing AMDT
The TA Team proposed three pilot projects which will install AMDT at ISELCO I, PELCO II
and FELCO. The details of the projects are described as follows.

(1) The background of the pilot project proposal


The TA team discussed the availabilities of the pilot project and agreed with ISELCO I,
PELCO II and FELCO to cooperate with the pilot project of the amorphous transformers
at 5th mission.

In the Philippines, the load rates of the pole transformers are relatively low, and it is
expected that the introduction of amorphous transformers to replace the aged SiFe
transformers will have a big effect in reducing the distribution losses. The TA team
proposed the pilot project to PELCO II that will supply power to the Pampanga area.
PELCO II shows the favorable interests in the amorphous transformers and they can check
the transformer performance using the testing facilities by themselves.
Moreover, the TA team proposed the same pilot project to ISELCO I and FELCO that
have the same kind of testing equipment for the transformers. They also show favorable
interests in the amorphous transformers and they can check the transformer performance
using the testing facilities by themselves too.
Additionally, the Japanese manufacturer HITACHI has a dominant market share of the
material core part of the AMDT. They positively supported this project to accept the
counterpart training in Japan. In this way, this pilot project will promote the introduction
of Japanese technology and products to the Philippines.

(2) The concrete procedures of the pilot project


(a) Test Methods
After the preparatory study by the TA team at the end of 2011, the comparison studies of
before and after the replacement of the amorphous transformers have difficulties in
measuring the exact value of losses, because it is too small for the reduction to measure
even if precise meters are used.
The TA team suggested examining the performances of the amorphous transformers by
PELCO II and letting them know the effects of the replacement via their testing results.

The proposed examinations of the amorphous transformers are as listed below,


¾ Non-load test
¾ Short circuit test
As a pilot project, the result of the examinations between the amorphous transformers and
silicon care transformers enable one to indicate the loss reductions and measure the effects of
the replacement of the amorphous transformers.

5-19
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
The vilification of the actual system simulation will be mentioned in Chapter 5.2.6 Section (3)-
(b)

Non-load test
The no-load loss and the no-load current shall be measured on one of the windings at rated
frequency and at a voltage corresponding to rated voltage. The remaining winding or
windings shall be left open-circuited.

A :電流計
A

Power
電源 V 一次側 V :電圧計
二次側
Source
W :電力計

Short circuit test


The short-circuit impedance and load losses shall be measured at rated frequency with a
designated level of sinusoidal voltage applied to the terminals of one winding, with the
terminals of the other winding short-circuited, and with possible other windings open-
circuited.

P 75 :load loss at 75 (W)


Pt :load loss at t (W)
t :temperature of winding at P t (degrees C)
I :primary current at P t (A)
Rt :winding resistant at t convert to primary side(Ω)


Power
電源 V 一次側 二次側 A
Source

5-20
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(b) Specification of AMDT
Phase: Single
Cooling System: Oil Immersed (OA)
Frequency: 60Hz
Primary Side: Double primary bushing with bushing connector
that can accommodate up to No.1/0 size of wire
Primary Voltage: 13200/7620 Volts
Secondary Side: Triple secondary bushing with bushing connector
that can accommodate up to No.4/0 size of wire
Secondary Voltage: 240/120 Volts
HV Winding BIL: 95/95
LV Winding BIL: 30/30
Primary Taps, KV: 2.5%, 2A2B
% Impedance @85 deg C: 1.75 - 2.25%

Table 5-5 Number of installation AMDT


(Unit)
Ratings 10KVA 15KVA 25KVA 37.5KVA 50KVA

Units to be procured per rating


2 units 2 units 2 units 2 units 1 units
(ISELCO I)

Units to be procured per rating


2 units 2 units 2 units 2 units 1 units
(PELCO II)

Units to be procured per rating


2 units 2 units 2 units 2 units 1 units
(FLECO)

(c) Cost Comparison between AMDT and SiFe DT


Philec Corp. has succeeded in the bid for AMDT whose core parts are made by Hitachi.
Their bidding price of FOB was about 10% higher than that of SiFe as it is described in
Table5-6.
After a factory test that was conducted by JICA Philippine and three ECs in November
2012, all the AMDT confirmed its effects and installed a model distribution feeder
decided beforehand.

Table 5-6 Unit Price of both AMDT and SiFe DT


Capacity 10 KVA 15 KVA 25 KVA 37.5 KVA 50 KVA
Unit Price of AMDT
56,196 60,118 86,442 108,635 122, 366
[PHP/Unit]
Unit Price of SiFe
48,716 59,999 77,741 94,828 110,796
DT[PHP/Unit]
Price Deference 115% 100% 111% 115% 110%

5-21
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(3) The Confirmation of the AMDT Effects
(a) The Result of Transformer Unit Test (Rated Condition)
The Transformer Unit Test in rated condition was conducted by EC to compare the core
and cupper loss between AMDT and SiFe.
Because of this test, it was confirmed that the losses by AMDT was about 20% lower than
that of SiFe at all the three ECs.

Table 5-7 Result of AMDT Unit Test (3 EC)


FLECO
Amoulphous Conventional SiFe Total
Core Copper Total Core Copper Total reduction
[KVA] [W] [%]
loss[W] loss[W] Loss[W] loss[W] loss[W] Loss[W]
10 10 126 136 37 135 172 ▲ 36 -21%
15 20 103 123 30 134 164 ▲ 41 -25%
25 20 207 227 80 227 307 ▲ 80 -26%
37.5 30 285 315 100 314 414 ▲ 99 -24%
50 50 426 476 130 468 598 ▲ 122 -20%
1,277 1,655 ▲ 378 -23%
ISELCO_1
Amoulphous Conventional SiFe Total
Core Copper Total Core Copper Total reduction
[KVA]
loss[W] loss[W] Loss[W] loss[W] loss[W] Loss[W] [W] [%]
10 12 174 186 45 180 225 ▲ 39 -17%
15 15.5 205.5 221 58 215 273 ▲ 52 -19%
25 20.5 311.5 332 82 295 377 ▲ 45 -12%
37.5 28 412 440 110 400 510 ▲ 70 -14%
50 43 543 586 140 490 630 ▲ 44 -7%
1,765 2,015 ▲ 250 -12%
PELCO_2
Amoulphous Conventional SiFe Total
Core Copper Total Core Copper Total reduction
[KVA]
loss[W] loss[W] Loss[W] loss[W] loss[W] Loss[W] [W] [%]
10 10 145 155 37 150 187 ▲ 32 -17%
15 14 167 181 40 174 214 ▲ 33 -15%
25 19 255 274 71 263 334 ▲ 60 -18%
37.5 29 339 368 93 353 446 ▲ 78 -17%
50 47 445 492 126 444 570 ▲ 78 -14%
1,470 1,751 ▲ 281 -16%

(b) Simulation of Loss Reduction on Actual Distribution Feeders


All the AMDT (nine units each: total 27), which are the most effective and easily
manageable model feeders, have already been installed to the three ECs.
9 PELCO2:Feeder No. 2, No.2 SS (9 units)
9 FLECO:Feeder No. 2 (4 units), Feeder No.4 – Kalayaan Lumban_SS (5 units)
9 ISELCO1:Feeder 1_Bliss/Villador, Mercedes SS (9 units)
It is very difficult to verify the effects numerically by measuring the actual current in the
model distribution feeders given that there are many transformers and customers where
the current fluctuates from time to time. Then, the TA Team simulated the effect of the
AMDT on the model feeders by using the model load curve shown in the table5-6. The
precondition of the operating year, discount rate and wholesale power rate are 30 years,
10% and 5 peso/kWh.

5-22
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
The transformers should be replaced or upsized when it is overloaded or when they exceed
their age limits. In this model case, the TA Team has verified economically which
transformers were the best to be replaced when existing 10kVA transformers were
overloaded.
The hourly load data of the existing 10kVA transformers are as in Figure 5-6. The TA
team simulated the core loss and copper loss from this load curve and described in the
table 5-8.

KW
16 Model Load Curve_DT
14

12

10

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
AM PM

Figure 5-6 Daily Curve of Overloaded Transformer (10kVA)

5-23
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Table 5-8 Comparison of core loss and copper loss of each DT capacity

10kVA DT 15kVA DT 25kVA DT 37.5kVA DT 50kVA DT


SiFe AMDT SiFe AMDT SiFe AMDT SiFe AMDT SiFe AMDT
CORE LOSS[W] 45 12 58 15 82 20 110 29 140 43
COPPER LOSS[W] 180 173 215 206 295 311 400 416 490 544
DEMAND LOSSES LOSSES LOSSES LOSSES LOSSES LOSSES LOSSES LOSSES LOSSES LOSSES
TIME
(kVA) (Wh) (Wh) (Wh) (Wh) (Wh) (Wh) (Wh) (Wh) (Wh) (Wh)
1:00 10.54 245.0 204.1 164.2 116.3 134.4 75.6 141.6 61.4 161.8 66.8
2:00 10.08 227.8 187.6 155.1 107.6 129.9 70.9 138.9 58.5 159.9 64.8
3:00 9.70 214.4 174.6 147.9 100.7 126.4 67.2 136.8 56.3 158.4 63.1
4:00 8.95 189.2 150.4 134.6 87.9 119.8 60.2 132.8 52.2 155.7 60.1
5:00 8.99 190.3 151.5 135.2 88.5 120.1 60.5 133.0 52.4 155.8 60.2
6:00 8.34 170.3 132.2 124.5 78.3 114.9 55.0 129.8 49.1 153.6 57.8
7:00 7.46 145.1 107.9 111.2 65.5 108.3 48.0 125.8 45.0 150.9 54.8
8:00 8.19 165.8 127.8 122.1 76.0 113.7 53.7 129.1 48.4 153.2 57.3
9:00 8.71 181.6 143.0 130.5 84.0 117.8 58.1 131.6 50.9 154.9 59.2
10:00 9.54 208.7 169.1 144.9 97.8 124.9 65.6 135.9 55.4 157.8 62.4
11:00 9.06 192.9 153.9 136.5 89.8 120.8 61.2 133.4 52.8 156.1 60.5
12:00 7.98 159.5 121.8 118.8 72.8 112.0 52.0 128.1 47.3 152.5 56.5
13:00 10.79 254.4 213.2 169.2 121.1 136.9 78.2 143.1 62.9 162.8 68.0
14:00 9.51 207.8 168.3 144.4 97.4 124.7 65.3 135.7 55.3 157.7 62.3
15:00 7.02 133.8 97.0 105.1 59.7 105.3 44.9 124.0 43.1 149.7 53.4
16:00 8.70 181.1 142.6 130.3 83.8 117.7 58.0 131.5 50.9 154.8 59.1
17:00 11.96 302.7 259.6 194.8 145.7 149.6 91.6 150.7 70.8 168.1 73.8
18:00 12.01 304.5 261.3 195.7 146.6 150.0 92.1 151.0 71.1 168.3 74.0
19:00 13.66 381.1 335.1 236.4 185.6 170.1 113.2 163.1 83.7 176.6 83.3
20:00 13.77 386.5 340.4 239.3 188.4 171.6 114.7 164.0 84.6 177.2 83.9
21:00 14.72 435.0 387.1 265.0 213.0 184.3 128.2 171.6 92.6 182.5 89.8
22:00 12.80 340.0 295.6 214.6 164.7 159.4 101.9 156.6 77.0 172.1 78.3
23:00 12.24 314.8 271.3 201.2 151.8 152.7 94.9 152.6 72.8 169.4 75.3
0:00 10.88 258.1 216.7 171.1 123.0 137.9 79.3 143.7 63.5 163.2 68.4
Average Load
DAILY ENERGY LOSS 5.79 4.81 3.89 2.75 3.20 1.79 3.38 1.46 3.87 1.59
MONTHLY LOSSES [ 173.72 144.37 116.78 82.38 96.10 53.71 101.53 43.75 116.19 47.79
ANNUAL LOSS [kWh] 2,085 1,732 1,401 989 1,153 644 1,218 525 1,394 574
ENERGY LOSS
[peso/year] 10,423 8,662 7,007 4,943 5,766 3,222 6,092 2,625 6,971 2,868
Energy
loss in 30 yrs 98,258 81,655 66,053 46,595 54,354 30,378 57,428 24,743 65,718 27,033
(Biding cost)
[peso] 48,716 56,196 59,999 60,118 77,741 86,442 94,828 108,635 110,796 122,366
Additional Cost
of AMDT 100% 115% 123% 123% 160% 177% 195% 223% 227% 251%
PW Total Cost
in 30 yrs [peso] 146,974 137,851 126,052 106,713 132,095 116,820 152,256 133,378 176,514 149,399
Advantage
of AMDT in 30 100% 94% 86% 73% 90% 79% 104% 91% 120% 102%

The core loss is constant depending on the load, but the copper loss is proportional to the
square of the load.
Actual Copper Loss [W] = Percent loading 2 * Rated Copper Loss [W]
Annual Energy Loss [W] = (Actual Copper Loss [W] + Core Loss [W]) × 8760[H]
The cost can be calculated by multiplying the wholesale cost at 5 pesos. The present value
cost after 30 years is as follows,
PW Cost of Energy Loss [PHP] = Annual Cost of Energy Loss*(((1+10%) 30 -1) / 10% /
(1+10%) 30 )

5-24
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
The results of the simulation, 15kVA AMDT is the most economical for the replacement.

Using the same precondition data above, as shown in the table **, AMDT is more
economical than SiFe after about 5 years in each capacity of the transformers. JICA
explained this result to not only three ECs but also all the ECs in the workshop and in the
manual.
JICA convinced them to understand the results of this pilot project that AMDT is more
economical than they previously expected.
Considering the fact that MERALCO is accelerating the introduction of AMDT to replace
all the aged transformers, NEA also strongly believes that AMDTs are effective and the
existing transformers should be replaced in the near future, and NEA will recommend
AMDT to EC as well.

180,000

50kVA
160,000

37.5kVA
140,000 10kVA
PW Total Cost [peso]

120,000 25kVA

15kVA
100,000

80,000 SiFi
AMDT
60,000

40,000
0 5 10 15 20 25 30
[years]

Figure 5-7 Cost Comparison both SiFe and AMDT)

5-25
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

5.2.7. Work preparation to support planning of full-scale F/S (confirmation and


analysis of the power distribution development plan)

For work preparation to support the planning of full-scale F/S for the upgrading of an MV
network, the TA team evaluated the feasibility of upgrading the MV network.

(1) Power Distribution Development Plans


„ CAPEX Data and Plans
¾ Each EC submits CAPEX to NEA/ERC for their future projects. The TA team
picked up several projects from CAPEX provided by NEA, which planned for a new
installation of a distribution substation or replacement of a transformer at a
distribution substation in from years 2012 to 2014 and the TA team evaluated the
plans.
¾ The targeted seven ECs had a few plans for the new installation of a distribution
substation or replacement of a transformer at a distribution substation. ISELCO1,
FLECO, CASURECO2, CASURECO4, and SORECO1 are examples of candidate
plans.
¾ Additionally from the TA team’s site visit, the TA team picked up a project from
PELCO2 for our evaluation.

(2) Candidate Plans


„ The Candidate Plans from CAPEX and information from NEA and ECs
¾ The next table shows some examples of our candidate plans for evaluation.

Table 5-9 candidate plans for evaluation


EC Substation Capacity Targeted Year
PELCO II Sta Maria,Mabalacat 10MVA 2013
FLECO Pagsanjan 10MVA 2012
ISELCO I R. Mercedez 10MVA 2012*
SORECO I Bulan 5MVA 2013
Bagacay 50MVA 2012
CASURECO II
Sibulan 5MVA 2013
CASURECO IV Caramoan 5MVA 2012
* Targeted Year for ISELCO I’s plan has been changed from 2012 to 2013 or later.

¾ Based on a feasibility of the project and our interview to the EC, ISELCO I’s plan
was selected for the detailed evaluation for upgrading project.

5-26
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

(3) Evaluation method


The evaluation is based on two components. One is initial cost (cost of facilities) and the
other is the cost of power losses.

„ Initial cost (cost of facilities)


¾ The initial cost is the construction costs or replacement costs of MV systems such
as the replacements of a transformer at a distribution substation, the replacement of
line wires, electric poles, and the replacement of DTs and the insulators if the system
voltage is upgraded. For the purpose of the evaluation, the initial cost for the 13.2kV
case is based on the original plan that was established by the ECs, but in some cases,
the TA team modified the plan. On the other hand, the cost for the 23kV system is
based on the installation plans established by the TA team.
„ Cost of power losses
¾ In 13.2kV cases, based on the new installation of the distribution substation or new
feeder, or from the application of a parallel circuit or line thickening, the large loss
reduction at the MV system could be achieved. In 23kV cases, based on the
upgrading of the system voltage, a large loss reduction at the MV system could also
be achieved.
¾ The effects of the loss reduction would continue until the facilities reach the end of
their life spans. For the evaluation of the upgrading of a system voltage of MV, the
evaluation period of the cost of power losses is 15years.
„ Total costs
¾ The total cost of the plan is obtained from the sum of the initial cost and cost of
power losses.
Total Costs = Initial cost + Cost of Power losses for 15years [PHP]
„ Limitation of the evaluation
¾ Since based on our project limitations, we could not conduct the measurements of
actual feeders such as the length or height of poles or the space of additional wires
and a detailed sketch of the distribution facilities such as the configuration of electric
poles nor calculate the actual loading of the distribution transformers on the poles.
Additionally we could not forecast the development of the area where the feeder
supplies electric power.
¾ For our evaluation, we use schematic simulation models and from these, we
extracted SynerGEE data for the computer simulations and the forecast for the load
increase rate and the plans of new supplies were based on information from EC.

5-27
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

(4) ISELCO I
„ Original Plan
¾ As shown in the next figure, four big loads were planned and will be supplied by
the MV feeder from the Mercedes substation. The loads are two big mills, Isabela
medical hospital, and a shopping mall. The expected demand of each load is around
0.4MW.
¾ Additionally, from ISELCO I’s estimation, the base load of the substation is
increasing annually at about 3.8%. The estimated demand for the substation in year
2014 is 4.992MW.
¾ The original plan by ISELCO I is to replace the transformer at the R. Mercedes
substation. The 5MVA transformer will be replaced by the 10MVA transformer.

Table 5-10 Basic information of ISELCO I‘s candidate site


Capacity of % Loading Increase # of
Substation # of DTs
Tr. [MVA] [%] rate [%] Faders
R. Mercedes 5 84.36 3.8 2 358

Figure 5-8 Image of ISELCO I ‘s candidate site

5-28
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
„ Evaluation models
¾ To evaluate, two evaluation models are set. Case 1 is the 13.2kV and case 2 is the
23kV model. ISELCO I provided us with the SynerGEE data of the whole R.
Mercedes substation and from the data, we created the SynerGEE data to evaluate
each case and get the results.
¾ The next table shows an outline of each case and the figure shows the outline of
the MV line.

Table 5-11 Outline of each case (ISELCO I)


System
Case Description
Voltage
Construct a new 13.2kV MV line 5.7km long and supply
new big loads from a newly installed 13.2kV MV line,
Case 1 13.2kV
fed from an additional 5MVA Tr. (69/13.2kV) at R.
Mercedes
Construct a new 23kV MV line for 5.7km and supply
Case 2 23kV new big loads from a newly installed 23kV MV line, fed
from an additional 5MVA Tr. (69/23kV) at R. Mercedes

*Dotted red line indicates the newly installed MV line from R.M. SS.

Figure 5-9 Outline of the MV line (ISELCO I)

„ Evaluation result
¾ The next table shows the results of the simulation. The initial cost for case 1 is
25.9 M PHP and for case 2 is 29.8M PHP. The cost of the losses for over 15years for
case 1 is 38.2 M PHP and for case 2 is 29.4 M PHP. Finally, the total cost for 15years
for case 1 is 64.1 M PHP and for case 2 is 59.2 M PHP.
¾ From this evaluation, we verified that case 1 costs more due to the losses. To apply
the 23kV system voltage, we could reduce the losses occurring in the MV system.
Even the initial cost for a 23kV is high, because of the loss reduction, the total cost
for 23kV is less expensive.

5-29
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
¾ As shown in this evaluation, the project for R. Mercedes should be conducted with
the 23kV system upgrading. This is only one example, but if the big new loads are
planned on the same feeder and there is space to construct a new feeder for 23kV, in
many cases, applying a 23kV system will be cost effective.

Table 5-12 Evaluation result ( ISELCO I )


Cost of Construction
Case Total Cost Result
Power Loss cost
Only Upgrade
Power Tr. 101,269,882 24,468,405 125,738,332 -

1 38,183,726 25,875,418 64,059,144

2 29,408,584 29,748,023 59,156,607 ◎

*Unit: PHP for 15 years

(5) Propose for Full-scale F/S


Through our evaluations, we find the feasibly of an upgrading project. Since the TA team
mainly evaluates the possible projects of the seven targeted ECs, NEA asked the many
ECs to submit the candidate site for an upgrading project and the possible sites for an
upgrading project were listed and provided for the TA team.

„ Candidate Sites for the Upgrading Project


¾ The next table shows the candidate sites for an upgrading project which were
provided by NEA to the TA team.
¾ Roughly speaking from our evaluation shown in this chapter, the typical feasible
site for an upgrading project is where an increase rate of the load at the site is high
and the percent loading of the transformer at the site is also high. The table listed in
descending order in terms of an increase rate and the percentage loading of a
transformer.

5-30
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Table 5-13 Candidate Sites

5-31
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

„ Further Feasibility Study Needs


¾ As shown in section (4), the effectiveness of an upgrading project changes with the
geographic structure of the feeder and the geographic location of customers that are
supplied by the feeder and so on. More importantly, detailed information for new
supplies for big customers is needed. i.e. location, demand, the distance from the
substation, the expected data for the new supply will be started and so on.
¾ The TA team strongly recommends conducting site surveys for the candidate sites.
Through the site surveys, information important for further evaluations should be
acquired. The typical example data which should be additionally acquired are;
z Upcoming new supplies; demand, expected demand curve, type of customers
(houses, commercial entities, industries or etc), location, distance from the
substation, expected date for new supply, and so on.
z Load forecasting for the area supplied by the candidate sites.
z Peripheral environment; Type of area (houses, farmlands, commercial entities,
industries, forests, or etc), Roads (Widths, space to erect new poles), River
(Widths), Space (Erect new poles), and any laws or rules that restrict
construction of the new feeder.
z DTs; Capacity, current load, load curve, load forecast, connected phase, and
age
z Pole; Size, height, design strength, space for additional lines, and age
z MV line; Geographic area supplied by the feeder, Phase (single, or three phase),
size, current, size and number of insulators, Circuits (Single or parallel) and
age
z Substation ; Number of Tr. and capacity of each Tr., %loading of each Tr., load
forecast for each Tr., age of Tr., number of feeders fed by each Tr., area of the
site used up and free space, possibility to acquire adjacent space to expand the
substation if needed
z Typical construction costs for the DT, MV line, Poles, and Substation
(including new installations, replacements, removals) for candidate sites
z Detailed information of any existing plans related to the candidate site

5-32
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Chapter 6 Project Performance and Achievements


6.1. System loss reduction manual

(1) Current Status of C/Ps and Other Target Groups


¾ The system loss reduction manual was created in collaboration with NEA and 7ECs.
¾ In preparation for the system loss reduction manual, The TA team introduced Japan's
latest technology in advance. Then, the system loss reduction technique was guided
through meetings with the counterparts, the field meetings with the 7EC engineers
and four workshops. Therefore, they have learned the necessary technical requirements
necessary for the system loss reduction planning.
¾ The good practices of the non-technical loss reductions was put together by NEA,
and was included in the system loss reduction manual. Moreover, the lateral spread
of the good practices was attempted through presentations at workshops from each
EC. As a result, the non-technical loss reduction projects modeled after the good
practices of the other ECs was proposed.
¾ In the workshops, the opportunity to carry out the presentation to NEA and the 7ECs
was prepared, and it strove for capability improvements considered on their own
leading to the system loss reductions. As a result, the problem-solving capability of
the counterparts and the administrator of the targeted ECs has improved, and have
reached a level where the can propose solutions on their own.
¾ The system loss reduction manual was distributed to all the ECs, and in the final
workshop, in the system loss reduction manual it was explained that many ECs
would strive to spread of manual. As a result, in all of the ECs, the countermeasures
of the system loss reduction using this manual is to be expected from now on.

(2) Achievement Indicators

(a) The category of the targeted ECs


The category of the targeted ECs in 2007, when the preliminary survey was conducted,
and the newest category of the targeted ECs is shown in the following table.
Although it is believed that the effects of the loss reduction using the system loss
reduction manual will show up several years later, in the 7ECs, the latest results have
exceeded the results in 2007, and the effects of the system loss reduction per this project
and the improvements in the capability of the data management is accepted.

6-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Table 6-1 Category of targeted EC and comments

EC 2007 2011 comment

Engineers tackled numbering of


ISELCO I C A
transformer for equipment
Young engineers tackled the modeling
PELCO II D B
for plan of loss reduction project.
NEA engineer tackled the management
FLECO D A
improvement.
Engineers understood the advantage of
CASURECO II C C
modeling.
Engineers understood the advantage of
CASURECO IV B B
modeling.
Engineers tackled non-technical loss
SORECO I E B
reduction.
Manager tackled non-technical loss
LEYECO III C A
reduction.

(Source: NEA data)

(b) Number of times of workshop holding


A workshop was held three times for the targeted 7ECs and one time for all the ECs. The
number of participants is shown in the following table. 350 people participated.

Table 6-2 Number of workshop participants


(Number)
JICA and
Title NEA ECs Other Total
JICA TA Team
1th Workshop 19 28 13 0 60
2nd Workshop 24 24 10 0 58
3rd Workshop 11 22 10 0 43
Final Workshop 30 109 10 40 189
Total 84 183 43 40 350

6.2. Support system for quantitative evaluation of system loss

(1) Current Status of C/Ps and Other Targeted Groups


¾ Per a request from the NEA that the system loss reduction manual should be packed
into one volume, the TA team held discussions with NEA and JICA. As a result of
the discussion, the support system for the quantitative evaluation of the system
losses was included in the system loss reduction manual. For this reason, the support
system for the quantitative evaluation of the system losses was created also in
collaboration with NEA and 7ECs.
¾ The quantitative evaluation techniques of the system losses were guided through the
meetings with the counterparts, the field meetings with 7EC engineers, four

6-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
workshops and AMDT pilot projects. Therefore, they have learned the necessary
technical requirements necessary to conduct a quantitative evaluation of the system
losses .
¾ For improvements in the capability of the quantitative evaluation of the system
losses and data management, power distribution system analysis software
(SynerGEE) was introduced, and software training was provided, and strove to
improve the capabilities of the NEA engineers and the 7ECs. As a result, it
reached a level where they are able to come up with a proposal on their own for a
system loss reduction project using SynerGEE.
¾ The quantitative evaluation of the system losses and data management and system
losses were put into practice through the AMDT pilot project. As a result, they
reached a level where they were able to conduct evaluations on their own of the test
results of the transformer and an evaluation of the loss reduction effects.

(2) Achievement Indicators

(a) Number of AMDT pilot projects


The pilot projects using AMDT were carried out in ISELCO I, PELCO II, and FELCO as
described in detail in Chapter 5.2.6.

(b) Number of SynerGEE Training Classes


The SynerGEE basic training and SynerGEE advanced training were carried out for NEA
and the seven targeted EC as follows. The number of trainees is shown in Table 5-2.

Table 6-3 Schedule of SynerGEE training


EC Basic trainig Advance trainig
ISELCO I January 31 to February 2, 2012 May 24 to May 25, 2012
PELCO II February 22 to February 24, 2012 May 29 to May 30, 2012
FLECO February 29 to March 2, 2012 June 18 to June 19, 2012
CASURECO II April 2 to April 4, 2012 June 5 to June 6, 2012
CASURECO IV April 2 to April 4, 2012 June 7 to June 8, 2012
SORECO I April 10 to April 12, 2012 June 21 to June 22, 2012
LEYECO III April 18 to April 20, 2012 June 14 to June 15, 2012

6.3. Support system for upgrading the present medium voltage

(1) Current Status of C/Ps and Other Targeted Groups


¾ Per the request from NEA that the system loss reduction manual should be packed
into one volume, the TA team held discussions with NEA and JICA. As a result of

6-3
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
the discussion, the support system to upgrade the present medium voltage was
included in the system loss reduction manual. For this reason, the support system to
upgrade the present medium voltage was created also in collaboration with NEA and
7ECs.
¾ The technique to upgrade the present medium voltage was guided through the
meetings with the counterparts, the field meetings with the 7EC engineers and four
workshops. Therefore, they have learned the necessary technical requirements
necessary for the upgrading of the present medium voltage .
¾ The model case of upgrading the medium voltage line was introduced to all ECs, and
the technical instructions on the criteria and the method of the upgrading was carried
out. As a result, it is expected that the system loss reduction project, which includes
the upgrading of the medium voltage line at some ECs will be proposed from now on.

(2) Achievement Indicators

(a) Number of Model Cases of Medium Voltage Line Upgrades


The TA Team carried out a model study to upgrade the medium voltage lines at ISELCO I
and PELCO II as described in detail in Chapter 5.2.7.

6.4. Current Status of the Targeted ECs

(1) ISELCO I
¾ They tackled the AMDT pilot project.
¾ 22 engineers participated in the SynerGEE software training.
¾ Two engineers participated in the Counterpart Training in Japan.

(2) PELCO II
¾ They tackled the AMDT pilot project.
¾ 22 engineers participated in the SynerGEE software training.
¾ Two engineers participated in the Counterpart Training in Japan.

(3) FLECO
¾ They tackled the AMDT pilot project.
¾ 25 engineers participated in the SynerGEE software training.
¾ Two engineers participated in the Counterpart Training in Japan.

(4) CASURECO II
¾ 19 engineers participated in the SynerGEE software training.
¾ Two engineers participated in the Counterpart Training in Japan.

6-4
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(5) CASURECO IV
¾ 11 engineers participated in the SynerGEE software training.
¾ One engineer participated in the Counterpart Training in Japan.

(6) SORECO I
¾ 21 engineers participated in the SynerGEE software training.
¾ Two engineers participated in the Counterpart Training in Japan.

(7) LEYECO III


¾ 13 engineers participated in the SynerGEE software training.
¾ One engineer participated in the Counterpart Training in Japan.

6.5. Target Index Trends


The trends of the system loss rate, SAIFI, and SAIDI, which are relevant to electric supply
reliability, in the seven targeted ECs are shown below.

%
26.00

24.00
ISRECO I
22.00
PELCO II
20.00 FLECO
18.00 CASURECO II
CASURECO IV
16.00
SORECO I
14.00 LEYECO III
12.00 All EC

10.00

8.00
Year
2004 2005 2006 2007 2008 2009 2010 2011

(Source: NEA data)

Figure 6-1 Trend of the system loss rate in the seven targeted ECs

6-5
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Time
60

50 ISRECO I
PELCO II

40 FLECO
CASURECO II
30 CASURECO IV
SORECO I
20 LEYECO III
All EC
10

0 Year
2004 2005 2006 2007 2008 2009 2010 2011

* They are those with the deficit data in part.


(Source: NEA data)

Figure 6-2 Trend of SAIFI in the seven targeted ECs

8,000Min.

7,000

6,000 ISRECO I
PELCO II
5,000
FLECO
4,000 CASURECO II
CASURECO IV
3,000
SORECO I
2,000 LEYECO III
All EC
1,000

0 Year
2004 2005 2006 2007 2008 2009 2010 2011

* They are those with the deficit data in part.


(Source: NEA data)

Figure 6-3 Trend of the SAIDI in the seven targeted ECs

The system loss rate in the seven targeted ECs has been decreasing and can expect more
of a decrease using the created system loss reduction manual from now on.
The achievement of an “Objectively verifiable indicator” for the “Overall Goal”, which
means overall system losses of 13.87% (yearend 2008) being reduced to a single digit
level by 2015, is also expected.
On the other hand, although all EC’s on average show an almost fixed tendency with
regards SAIFI and SAIDI, which are indexes relevant to electric supply reliability, in the

6-6
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
individual seven targeted ECs, the per-year fluctuation is large and reflects the specific
impact from typhoons etc. Therefore, future predictions are difficult.

Table 6-4 “Objectively verifiable indicator” for the “Overall Goal”

Before project Present Target


Indicator
2007 (2011) (2015)

Overall system
13.87% 11.87% less than 10%
losses

Three objectively verifiable indicators to the project target on PDM are as follows.
„ The selected EC can segregate non-technical loss and technical loss.
„ Power distribution system plan is made by EC’s own capacity.
„ Power system is analyzed, and its problems are resolved by EC’s.
Each targeted EC can introduce the proposal that contain the three above-mentioned
objectively verifiable indicators at the workshop through the AMDT pilot project,
SynerGEE training, and model case analysis of the 23kV up grading. This point is an
achievement of this project. It is thought that it is a cause of the improvement in a
category of the targeted EC as shown in Table 6-1.

6-7
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)

Chapter 7 Conclusion and Recommendations

The main purpose of this Project is to provide the necessary support to improve the skills
for the loss reduction planning and NEA and EC technology. The System Loss Reduction
Manual has been prepared and a support system for the quantitative evaluation of system
losses using the distribution analysis software was established. The voltage upgrading of
the medium voltage systems was preliminary studied and its technical guidelines were
recommended in the Manual. The pilot projects of the adoption of amorphous
transformers were executed to confirm its effects on loss reductions.

We expect that the outputs of this Project will be reflected into the policy and plans of the
distribution system loss reductions of EC and NEA.

7.1. The System Loss Reduction Manual


The purpose of this manual is to support NEA and the EC staff in the smooth
implementation of the power distribution loss reduction plans by summarizing their
procedures.

We have attempted to make this manual easier to use by showing the criteria or
indications to achieve technical loss reductions. The reason for this is that it is sometimes
very difficult for the staff to quantitatively understand the effectiveness of the technical
loss reductions due to their large number of options.

We put the utilization of the distribution analysis software with the distribution system
images to the conditions for loss analysis to have an adequate grasp of the distribution
losses. The methodologies of the required data arrangement are also described such as the
distribution facility data and load data. The methodologies of the identification of those
places where technical losses occur and obtaining a numerical understanding are
explained using this software.

The manuals describe the adoption of larger size conductors, a recommendation of the
selection of the appropriate transformer sizes, the criteria for the application of 23 kV, the
loss reduction effects of the amorphous transformers with small core losses and the
recommended cases for their applications and a summary of the activities for non-
technical loss reductions by NEA and ECs. This manual prepares the criteria
corresponding to the amount of the peak loads that can be grasped by the distribution
analysis software.

7-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
On the other hand, this manual also takes the role of a guide to show an adequate way of
thinking about the technical considerations of loss reduction. We recommend that ECs
understand its meaning and that NEA and the ECs establish an institutional promotion
system of the manual. The reason is to be able to implement its recommendations and
implement revisions in the case of a situation change such as an increase in the power
generation costs or the re-arrangement of the steps for the voltage upgrades owing to
urbanization.

Overall, it cannot be said that the power distribution system losses of the ECs have been
sufficiently reduced. There is still much room for improvement in the area of power
distribution losses.

We recommend that many loss reduction plans should be looked into that are able to yield
benefits far exceeding the costs for its measures by utilizing this Manual.

7.2. Utilization of Distribution Analysis Software


JICA provided the seven targeted ECs and NEA with the distribution system analysis
software “SynerGEE” that is equipped with the mapping functions in order to grasp the
distribution system losses adequately. The technical transfer was also provided through
the training courses including the methodology of inputting the distribution system data
and their operations.

We expect that each EC will achieve more of a loss reduction by utilizing this software
and the aforementioned Manual thorough the expansion of the data input to SynerGEE
under the support of NEA.

We recommend that the database be maintained and periodically revised such as the
geographical information, specification of facilities and the load data to promote the
making of the models of the actual distribution system for using the distribution analysis
software.

7.3. Upgrading Medium Voltage to 23kV


It can be found that in some cases the application of 23 kV is superior to 13.2 kV from an
economic perspective owing to its large effects on the loss reductions. The multiple
candidates for the 23 kV upgrades have been found based on the results of the
examination of NEA and some ECs.

7-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Thus, we recommend that detailed studies be implemented to evaluate the candidate sites
of the 23 kV upgrading regarding their feasibility and the costs and benefits brought about
by the loss reduction.

7.4. Application of Amorphous Transformers


The amorphous transformers were purchased and introduced as a pilot project to three of
the targeted ECs. The EC staff could measure the effects of the amorphous transformers
on the loss reductions using their own measurement equipment and confirm the factory
data. The superiority of the amorphous transformer could be confirmed with the
possibility of reducing the losses effectively by expanding its installations.

Thus, we recommend that the installation of amorphous transformers be promoted in all


the ECs with an adequate economic evaluation conducted.

7-3

You might also like