The Project On System Loss Reduction For Philippine Electric Cooperatives (Ecs)
The Project On System Loss Reduction For Philippine Electric Cooperatives (Ecs)
The Project On System Loss Reduction For Philippine Electric Cooperatives (Ecs)
March 2013
Contents
i
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
5.2.4. Record of installation and training of SynerGEE software..................................................... 5-5
5.2.5. System Loss Reduction Manual ............................................................................................. 5-6
5.2.6. The pilot projects installing AMDT ...................................................................................... 5-19
5.2.7. Work preparation to support planning of full-scale F/S (confirmation and analysis of the
power distribution development plan) .................................................................................. 5-26
Chapter 6 Project Performance and Achievements ................................................................................... 6-1
6.1. System loss reduction manual................................................................................................. 6-1
6.2. Support system for quantitative evaluation of system loss ..................................................... 6-2
6.3. Support system for upgrading the present medium voltage .................................................... 6-3
6.4. Current Status of the Targeted ECs ......................................................................................... 6-4
6.5. Target Index Trends ................................................................................................................ 6-5
Chapter 7 Conclusion and Recommendations .......................................................................................... 7-1
7.1. The System Loss Reduction Manual ...................................................................................... 7-1
7.2. Utilization of Distribution Analysis Software......................................................................... 7-2
7.3. Upgrading Medium Voltage to 23kV ...................................................................................... 7-2
7.4. Application of Amorphous Transformers ............................................................................... 7-3
Chapter 8 Appendix .................................................................................................................................. 8-1
ii
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Figure and Table List
iii
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Abbreviations
<Targeted ECs>
ISELCO I Isabela I Electric Cooperative, Inc.
PELCO II Pampanga II Electric Cooperative, Inc.
FLECO First Laguna Electric Cooperative, Inc.
CASURECO II Camarines Sur II Electric Cooperative, Inc.
CASURECO IV Camarines Sur IV Electric Cooperative, Inc.
SORECO I Sorsogon I Electric Cooperative, Inc.
LEYECO III Leyte III Electric Cooperative, Inc.
iv
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
1.1.3. Counterpart
National Electrification Administration (NEA)
The seven targeted ECs was selected in consideration of local balance from EC of medium
rank in five-step evaluation to which the performance improvement effect was accepted
among 119 EC. The seven targeted ECs are shown in Fig. 2-3.
1-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Masaharu YOGO
Team Leader/
Power System Planning
Output2 Output3
Output1 Support system for Support system for
Management Manuals for quantitative evaluation of upgrading mid-voltage to
System Loss Reduction system loss 23kV and technical design
standards
(3) Output
1. Prepare the System Loss Reduction Manual and put it into practice.
2. Establish a support system for the quantitative evaluation of system losses.
3. Establish a support system for upgrading the mid-voltage to 23kV as well as the
technical design standards.
1-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(4) Activities
1 System Loss Reduction Manual is prepared and put into practice
1-1 Survey the best existing practices of the system loss reductions, including the non-
technical losses at the leading EC’s;
1-2 Prepare draft manuals for system loss reduction based on Japanese experience;
1-3 Case studies to solve the issue for application of manuals into selected EC’s are
conducted;
1-4 Finalizing manuals based on the above activities with NEA, including the
compilation of EC’s best non-technical practices;
1-5 Propose an appropriate mechanism to transfer the manual contents to other EC’s with
NEA;
3 Establish a support system to upgrade the present mid-voltage to 23kV and the technical
design standards
3-1 Survey the existing facilities, facility configuration and the distribution development
plan;
3-2 Discuss proper design standards and guidelines for a 23 kV distribution line in the
Philippines with NEA;
3-3 Preparation work for a full scale F/S;
The final PDM including the indicators/targets means of verification and important
assumptions are shown in Appendix 1.
1-3
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
1
The energy self-sufficiency rates of Indonesia, Malaysia, and Vietnam are 174%, 134%, and 120%, respectively. On the
other hand, the energy self-sufficiency rates of China, Cambodia, Thailand, and the Philippines are 90%, 71%, 60%, and 60%,
respectively. (Energy Balances of OECD / non-OECD Countries 2009)
2-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
2.2. Current Situation of Electricity and Energy Sector
(1) Outline
Since 1936, the generation and transmission business had been operated by the monopoly
National Power Corporation (hereinafter referred to as “NPC”), and the electricity
generated by owned power stations was supplied to distribution cooperatives.
Since the late 1980’s, an Independent Power Producer (hereinafter referred to as “IPP”) is
allowed to enter the market, and NPC began to sell the electricity from its own power
plants as well as that from IPP.
In June 2001, the Electric Power Industry Restructuring Act (hereinafter referred to as
“EPIRA”) was enacted; the transmission department of NPC became the National
Transmission Corporation (hereinafter referred to as “TRASNCO”) as a split-off. As a
result, the generation business is operated by NPC and IPP, while the transmission
business is run by TRANSCO. The assets of NPC have been sold, and the transmission
business license was knocked down by NGCP, which is joint business venture include
State Grid Corporation of China, in an open bid, and has been operated by NGCP.
Moreover, the Wholesale Electricity Spot Market (hereinafter referred to as “WESM”)
was founded in June 2006 and has been operated in the Luzon area.
The distribution businesses in the Philippines are owned by private distribution
cooperatives and public ECs. The distribution cooperatives exclusively supply electricity
via a cross trade transaction with NPC or IPP, or the new WESM market.
NPC WESM
MERALCO
Customers
EC
TRANSCO
NPP
Flow of electricity
2-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(2) Related Organizations of Electricity Sector
2-3
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
2.2.2. Distribution Sector
(1) Outline
There are 16 Private Investor-Owned Utilities (hereinafter referred to as “PIOU”)
including the Manila Electric Company (hereinafter referred to as “MERALCO”, 199 ECs,
and 8 Local Government Unit-Owned Utilities (hereinafter referred to as “LGUOU”). In
2008, the total number of customers was 4,570,647, and electricity sales were 26,800GWh.
The number of consumers in 2011 was 4,847,238 houses in MERALCO and 8,027,939
houses in 119 ECs. The sales electric energy in 2010 was 55,266GWh in the Philippines
whole country. The distribution utilities map of the Philippines, which made an extract
from the JICA expert report, is shown in Fig. 2-3. The private distribution utility area is
shown in red and the EC area is shown in yellow. There are 119 ECs in the Philippines in
2011 and there is no big change from this figure. Some EC, such as PELCOII, is due to be
privatized in the near future.
2-4
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
2-5
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(2) Examples of Loss Reduction by ECs
EC distribution systems are broadly extended, and system losses vary according to ECs.
Methods to reduce losses implemented by the ECs are shown below.
Load loss, which is generated from the conductor by flowing the current of a power line,
and no-load loss, which is generated with the distribution transformer, exists in a
technical loss. The most effect measure for technical loss reduction is as follows.
Install a substation to prevent the overload of a transformer, or reduce the
distribution current
Improve overload and heating
Improve the long single-phase lines
Replace distribution transformers
Install capacitors to the improve voltage and power factor
Moreover, the most effect measure for non-technical loss reduction is Install a large
number of meters at the upper part of the poles, which is the system currently widely held
to the electric power supply to the small colony in the Philippines including MERALCO.
2-6
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
ISELCO I
PELCO II
FLECO
CASURECO II CASURECO IV
SORECO I
LEYECO III
○: Targeted EC
2-7
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Among these matters, establishment of specific technical loss calculation methods, the
grasp of a loss generating part using the power distribution analysis software equipped
with the mapping function, and the analysis of the proposed measures serve as an
important subject especially. Moreover, as a cause of loss, the situation that the load
factor of pole transformers are low and iron losses might be high is not suitable. The
creation of guideline for the selection method of transformer capacity is important.
Moreover, it is required to enable it to conduct economic evaluation appropriately quickly
from the stage of planning of the draft of loss reduction.
3-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
【Common Tasks】
Grasp the current situation and the issues on technical and organizational aspects
of NEA and selected the ECs
Examine the overall plan of NEA
Examine the existing facilities and plans of selected ECs
【Output 1】
Study the existing best practices of selected ECs on loss reduction
Manuals and checklist preparation for system loss reductions
Carry out studies utilizing manuals to solve problems of selected ECs
Manual completion based on the above activities including the integration of best
practices for the non-technical loss reduction of selected ECs through cooperation
with NEA
Recommend appropriate methods that supersede other manuals currently used
through cooperation with NEA
3-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
【Output 2】
Examine and suggest an appropriate method of evaluating system loss reduction
Examine the necessity of analytical software
Collect data for carrying out an electric power system analysis
Conduct a preliminary analysis of power distribution losses
Develop methods of evaluating system loss reduction
Create a system loss reduction manual which includes technical loss evaluation
Train staff of selected EC’s on technical loss evaluations
【Output 3】
Examine the standard design and guidelines for 23 kV or 34.5 kV power lines
Establish the standard design and guidelines for 23 kV or 34.5 kV power lines
Create a system loss reduction manual which includes the basic design and
technological standards for 23 kV or 34.5 kV distribution lines
Work preparation to support the planning of full-scale F/S (confirmation and
analysis of a power distribution development plan)
(1) Purpose
To create useful and efficient manuals on system loss reduction. A numerical
analysis on the chosen distribution network owned by selected ECs would be
conducted. The results of the analysis should be fully reflected in the manual
wherein the method of finding the proper measure for system loss reduction and in
estimating the individual measures would be described.
To transfer the planning technique for network loss reduction to NEA Staff and
concerned ECs
To verify the effects of the AMDT after introducing AMDT in three ECs
To nominate the candidate sites for the planning and conduct of system loss
reduction projects in the future.
3-3
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(2) Outputs
Manuals on the system loss reduction are released and utilized.
Distribution professionals belonging to the counterpart organizations are trained to
make plans for the loss reduction utilizing software.
Understand the effects of AMDT to reduce losses and its easy O&M
Information on candidate sites for the future project is shared particularly with
those concerned with JICA’s technical cooperation.
(3) Procedures
1). Estimation of economical value created by reducing the system losses, which would
be equivalent to the costs of the construction work that would be implemented to
diminish losses.
2). Grasping the costs of each measure for loss reduction such as expanding the LV
network or installing new DTs and so on.
3). Surveying the distribution network
Listing up the overloaded DTs by checking the DSL data or by detecting the load
currents of some DTs.
Showing the expectation of reduced non-load losses of DTs by replacing the
conventional DTs to AMDTs.
4). Draft manuals on distribution network loss reduction
The selection of proper facilities such as wires or DTs from the perspective of
reducing technical losses
Guidance in choosing between two alternatives, multiplying the number of wires or
installing big conductors
Showing sample cases like upgrading the system voltage is expected to be a better
choice.
A comparison between the two methods, by expanding the LV line or MV line,
which means that a new DT would be installed.
Connecting the two distribution MV feeders, the load of one feeder is much bigger
than the other. The loads of the two feeders shall be well balanced to reduce the
total losses of the two MV lines.
The relocation of some of the DTs that would diminish the losses from the LV
lines.
The suppression of the non-load losses from the DTs by replacing the existing
transformers to the AMDTs, whose iron-losses would be much less than that of the
conventional ones.
3-4
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
5). Simulations
The simulation models of some distribution system for SynerGEE would be
created. Power flow, network losses and the voltage profile of the simulated
distribution feeders shall be checked.
The proposed methods for loss reduction described in the draft manuals would be
studied in computer simulations. The effectiveness of the recommended measures
to improve the system losses of the listed DTs shall be confirmed via the
SynerGEE simulations.
Know-how on making plans to reduce the system losses by software aids shall be
transferred to the distribution technicians of the counterpart organizations.
To confirm the effects to introduce AMDT as the pilot project and to measure the loss
reduction by the ECs
6). Efficient methods shall be included in the planning manual on loss reduction.
3-5
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
3-6
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(a) Management Manuals for System Loss Reduction are prepared and are
appropriately practiced
The TA Team will tackle priority issue solving activities with selected ECs and propose
workable countermeasures through introducing the Japanese best practices. In addition,
the management system, which can share the best practices in all ECs, was developed in
collaboration with NEA. Moreover, the trainers who can become a lecturer of priority
issue solving activities were developed through participating counterpart training in
Japan.
(c) Support system for upgrading the present mid-voltage to 23kV and technical
design standards are established
The TA Team developed required guideline through considering standard specification
in collaboration with a counterpart. Moreover, The TA Team will explain the necessary
requirements for F/S based on the developed guideline. In addition, while having an on-
site exploration of a power distribution development project area and explaining the
point of an on-site exploration, it teaches so that the power distribution route and
substation point investigation may be possible by a counterpart independent.
3-7
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(2) Workshop
The Staff of NEA and around three participants from each selected EC participated in the
workshop during the 2 nd , 4 th , 5 th and 9 th field survey. The purpose of the workshops is to
share the best practices that would be introduced by the selected EC participants and to
explain the progress of the system loss reduction manual, the support system for the
quantitative evaluation of the system loss and support system to upgrade the present
medium voltage to 23 kV or 34.5 kV including technical design standards. In the
workshop, from the perspective of technology transfer, the counterpart staff made the
presentation as much as possible. The participants in this workshop shall in turn be
responsible to share the knowledge and skills acquired with their colleagues upon
returning to their respective ECs.
3-8
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Chapter 4 Inputs
4.1. Inputs from Japanese Side
4.1.1. Experts
This project involved the dispatch of expert project teams and team leaders from Japan. The
performance and achievement of the dispatch of these expert project leaders are outlined in
Appendices 2 & 3. The table 4-1 shows the total dispatch Records of the project.
M/M M/M
Year Total
(Site Survey) (Domestic Surver)
2010 0.00 0.30 0.30
2011 11.58 5.48 17.06
2012 13.80 5.85 19.65
Total 25.38 11.63 37.01
4.1.3. Equipment
During the period of project implementation, SynerGEE software, which was given to 7 EC
one license which is the number of minimum respectively, indicated as required at the very
beginning of the project, and digital clip meters, which was given to 7 EC two sets which is
the necessary requirement respectively, and amorphous transformers for pilot project shown
to be necessary during the operation phase, were purchased. Appendix 5 lists all such
equipment. This equipment will be required in future management activities at the relevant
ECs; as such, the equipment has been gifted to them.
4.1.4. Others
JICA has shouldered local activity costs, such as travel expenses, pilot project costs,
workshops and others.
4-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
4.2. Inputs from Philippine Side
4.2.1. Counterparts
Counterpart organizations are as shown in Chapter 1.1.3. and Chapter 1.1.4.
4-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
5-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
¾ Conducted the first Joint Coordination Committee meeting
¾ Carried out a workshop specifically for sharing best practices in system loss
reduction.
¾ Introduced distribution planning methods in Japan
¾ Confirmed current best practices to advance the loss reduction by selected ECs
¾ Examined the appropriate methods of evaluating system loss reduction
¾ Examined the necessity of analysis software
¾ Acquisition and request of data for the power distribution system analysis
¾ Examined the existing facilities and plans of the selected ECs
Accomplished tasks during the third site survey
¾ Data collection and information review
¾ Confirmed the current best practices to advance the loss reduction by selected
ECs
¾ Examined the appropriate methods of evaluating the system loss reduction
¾ Preparation of case studies for the application of the manuals into the selected
ECs
¾ Acquisition and request of data for power distribution system analysis
¾ Examined existing facilities and plans of the selected ECs
¾ Examined proper design standards for a 23 kV distribution line
Accomplished tasks during the fourth site survey
¾ Conducted the second Joint Coordination Committee meeting
¾ Carried out a workshop specifically to share best practices in system loss
reductions.
¾ Confirmed current best practices to advance loss reductions via selected ECs
¾ Propose appropriate methods to evaluate system loss reduction
¾ Acquisition and request of data for the power distribution system analysis
¾ Request of power distribution line modeling for the power distribution system
analysis
¾ Preparation of case studies for the application of manuals into the selected ECs
Accomplished tasks during the fifth site survey
¾ Carried out a third workshop specifically for the presentation of power
distribution line modeling for power distribution system analysis
¾ Carried out SynerGEE training
¾ Confirmed current best practices to advance loss reduction by selected ECs
¾ Assistance for the power distribution line modeling for power distribution
system analysis
¾ Request of power distribution line modeling for power distribution system
analysis
5-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
¾ Preparation of the System Loss Reduction Manual including the “System Loss
Quantitative Evaluation” and “Design Criteria and Technical Standards for the
Upgraded Distribution Line Voltages”
Accomplished tasks during the sixth site survey
¾ Preparation of the System Loss Reduction Manual including the “System Loss
Quantitative Evaluation” and “Design Criteria and Technical Standards for
Upgraded Distribution Line Voltages”
¾ Discussion of contents of the System Loss Reduction Manual
¾ Confirmed the pilot project of the amorphous transformers
¾ Preparation of the Total Ownership Cost (TOC) calculator
Accomplished tasks during the seventh site survey
¾ Conducted the third Joint Coordination Committee meeting
¾ Discussion of the contents of the System Loss Reduction Manual
¾ Introduction and explanation of the System Loss Reduction Manual for ECs
¾ Confirmed the pilot project of amorphous transformers
¾ Evaluation of the pilot project of amorphous transformers
¾ Preparation of the Total Ownership Cost (TOC) calculator
¾ 23kV upgrading candidate sites survey
¾ Modeling of the distribution system for 23kV upgrading candidate sites
¾ Simulation of the distribution system for 23kV upgrading candidate sites
Accomplished tasks during the eighth site survey
¾ Finalized System Loss Reduction Manual
¾ Evaluation of the pilot project of amorphous transformers
¾ Modeling of the distribution system for 23kV upgrading candidate sites
¾ Simulation of the distribution system for 23kV upgrading candidate sites
¾ Evaluation of the distribution system for 23kV upgrading candidate sites
Accomplished tasks during the ninth site survey
¾ Carried out a fourth workshop specifically to introduce the System Loss
Reduction Manual to all ECs
¾ Submit the System Loss Reduction Manual to all ECs
¾ Submit the project completion report
Details are shown in Appendix 6, meeting minutes.
5-3
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
8, 2012, the third workshop was held on May 31, 2012 and the fourth workshop was held on
February 28, 2013. The workshop materials can be found in Appendix 7.
The first Joint Coordination Committee meeting
¾ The TA Team reported the status of the project, and discussed how to proceed
with related organizations.
The first workshop
¾ The TA Team explained the outline of the project and the method to reduce
system losses in Japan.
¾ Selected seven ECs and introduced their best practices to reduce system losses.
The second Joint Coordination Committee meeting
¾ The TA Team reported the status of the project, the contents of the system loss
reduction manual and discussed how to proceed with related organizations.
The second workshop
¾ The TA Team explained the contents of the system loss reduction manual, the
appropriate methods for evaluating the system loss reduction and the effects of
introducing AMDT.
¾ Selected seven ECs and introduced their best practices to reduce system losses
based on the sheet of “Good Practices for System Loss Reduction”.
The third workshop
¾ The TA Team explained the method of Loss Reduction for the Medium Voltage
Line, the sample analysis of the Loss Reduction for the M V Line using
SynerGEE, and propose an appropriate mechanism to transfer the loss reduction
method to all ECs and the incentive system.
¾ Selected seven ECs and introduced their sample analysis of the Loss Reduction
for the MV Line using SynerGEE.
The third Joint Coordination Committee meeting
¾ The TA Team explained the contents of the system loss reduction manual, the
appropriate methods for evaluating the system loss reduction and the effects to
introduce AMDT and 23kV upgrades.
¾ NEA and the TA Team agreed with the contents of the system loss reduction
manual.
¾ NEA and the TA Team confirmed the evaluation of the AMDT pilot project.
¾ NEA and the TA Team confirmed the 23kV upgraded sites.
The third workshop
¾ The TA Team explained the system loss reduction manual to all ECs.
¾ The TA Team reported the results of the AMDT pilot project.
¾ The TA Team reported the results of the 23kV upgraded sites simulation using
SynerGEE.
5-4
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
5.2.4. Record of installation and training of SynerGEE software
SynerGEE
Electric Load Middlelink
EC Remark (The past use record)
Flow Core Electric (ML-E)
(SYNE)
ISRECO I 1 1 New installation
PELCO II 1 1 Used old version
FLECO 1 1 Used old version
CASURECO II 1 1 Under training
CASURECO IV 1 1 New installation
SORECO I 1 1 New installation
LEYECO III 1 1 New installation
NEA 1 1 Used old version
5-5
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Number of Number of
EC attendance of attendance of Total
basic trainig advance trainig
ISRECO I 11 11 22
PELCO II 11 11 22
FLECO 13 12 25
CASURECO II 10 9 19
CASURECO IV 6 5 11
SORECO I 10 11 21
LEYECO III 5 8 13
Total 66 67 133
5-6
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Contents
1 Introduction
1.1 Purpose of This Manual
1.2 Types of Distribution Technical Losses and Their Countermeasures
1.2.1 General
1.2.2 Countermeasures
1.2.3 Concept of Seeking an Appropriate Technical Loss Reduction
1.2.4 Example of Loss Occurrence of Conductors
1.3 Planning Procedures of Technical Loss Reduction
1.3.1 Medium Voltage (MV) Loss Reduction
1.3.2 Low Voltage (LV) Loss Reduction
1.4 Appropriate Methods for Manual Distribution
1.4.1 Method for Maximum Utilization of the Technical Loss Reduction
Manual
1.4.2 Renewal of the Technical Loss Reduction Manual
1.4.3 Award of Good Practices for System Loss Reduction
2 Economical Evaluation for Technical Loss Reduction
2.1 Introduction
2.2 Methodology of Calculating Cost Savings from Loss Reduction
2.2.1 Outline
2.2.2 Process of Estimating Cost Saving
2.3 Countermeasure Cost
2.4 Benefits / Costs Analysis
2.4.1 Net Present Value (NPV)
2.4.2 Internal Rate of Return (IRR)
2.4.3 Practical Method to Estimate Total Cost Savings
3 Methodology of O&M for Data Arrangement of Loss Analysis
3.1 Network Data
3.2 Load Data
4 Identifying Countermeasures against Technical Losses for Low Voltage system
4.1 Calculation Methodology of the Operating Status of the Low Voltage System
4.1.1 Methodology based on the DSL data
4.1.2 Methodology of Confirming Operating Status of the Low Voltage
System by Using SynerGEE
4.2 Countermeasure Options to Prevent Technical Losses Caused in the Low
Voltage System
4.2.1 Line Thickening
4.2.2 Capacity Changing ( Small Æ Big )
4.2.3 Capacity Changing ( Big Æ Small )
4.2.4 Load Dividing
4.2.5 Load Centering
4.3 General Commentary for Taking Countermeasures against Technical Loss
Reduction
4.3.1 Concept of the Low Voltage Technical Loss Reduction
4.3.2 Proper Installation of Pole Transformers
4.3.3 Proper Installation of Low Voltage Wire
5-7
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
4.3.4 Transformer Load Management
4.4 Recommended Size of the Transformer and the Electric Wire
4.4.1 Identifying the Proper Consumption in Low Voltage System
4.4.2 Permissible Overload of Transformer
4.4.3 Recommended Transformer Capacity
4.4.4 Low Voltage Wire Selection Method
4.5 Installation of amorphous transformer
4.5.1 Effects for Introducing Amorphous Transformers
4.5.2 Cost Evaluation of Amorphous Transformers
4.5.3 Cost Evaluation of Amorphous Transformer Using TOC Simulation
4.5.4 Measurement and Testing for Amorphous Transformer
5 Identifying Countermeasures against Technical Losses for Medium Voltage
System
5.1 Calculation Methodology of the Operating Status of the Medium Voltage
System
5.1.1 Upstream Approach Method
5.1.2 Downstream Approach Method
5.2 Options of Countermeasures against Technical Losses Caused in the Medium
Voltage System
5.2.1 Line Thickening
5.2.2 Parallel Circuit
5.2.3 Upgrading Voltage
5.2.4 Capacitor Placement/Replacement
5.2.5 Load Balancing
5.2.6 Switching Optimization
5.2.7 Phase Increasing
5.3 Criteria for Taking Countermeasures against Technical Loss Reduction in
Medium Voltage System
5.3.1 Conditions of Study
5.3.2 Criteria of Line Thickening and Parallel Circuit
5.3.3 Criteria of Phase Increasing
5.3.4 Criteria of Capacitor Placement/Replacement
5.3.5 Criteria of Switching Optimization
5.4 Appropriate Capacities of Conductor Sizes
5.5 Appropriate Voltage for Installation of the New Transformer of the
Distribution Substation
6 New Installation of Distribution Substation and Upgrading MV Network
6.1 MV network Expansion Measures
6.1.1 Outline
6.1.2 New Installation of Distribution Substation
6.1.3 Upgrading MV Network
6.1.4 Standard System Voltage for MV Network
6.2 General Commentary for New Installation of Distribution Substation
6.3 General Commentary for Upgrading MV Network
6.3.1 Distribution Substation
6.3.2 Temporary Ways for Upgrading Business
6.3.3 All-new Equipments Installation
6.3.4 Utilizing the Existing Poles
6.3.5 Re-connection of Distribution Transformers
6.3.6 Other Issues
5-8
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
6.4 General Commentary for Upgrading MV Network
6.4.1 Evaluation Stage
6.4.2 Decision making by Management
6.4.3 Stage I
6.4.4 Stage II
6.4.5 Final Stage
7 Using SynerGEE
7.1 Confirming the Operating Status of the Distribution System
7.1.1 Implementation of Load Flow by SynerGEE
7.1.2 Confirmation of Operating Status of Distribution Transformer
7.1.3 Confirmation of the Operating Status of a Low Voltage Line
7.2 Procedure of Load Allocation
7.3 Power Flow Analysis
7.4 Method of Capacitor Placement using SynerGEE
7.5 Method of Switching Optimization Using SynerGEE
7.6 Load Balancing Improvement Using SynerGEE
7.7 Phase Balancing Improvement Using SynerGEE
8 Non-Technical Loss Reduction Activities
8.1 Method of Non-Technical Loss Reduction
8.2 Good Practices for System Loss Reduction
8.2.1 Sorsogon I Electric Cooperative Inc. (SORECO I)
8.2.2 Pampanga II Electric Cooperative Inc. (PELCO II)
8.2.3 Camarines Sur IV Electric Cooperative Inc. (CASURECO IV)
8.2.4 Cebu I Electric Cooperative Inc. ( CEBECO I )
8.2.5 Bohol I Electric Cooperative Inc. ( BOHECO I )
8.2.6 Isabela I Electric Cooperative Inc. (ISELCO I)
8.2.7 First Laguna Electric Cooperative Inc. (FLECO)
8.3 Good Practices Sheet for System Loss Reduction Method of Non-Technical
Loss Reduction
The system loss reduction manual presents intelligibly the criteria or standard of the
procedure of planning of the measure against the loss reduction so that the engineers in
charge of loss reduction can carry out work smoothly.
5-9
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(2) Methodology of O&M for data arrangement of the loss analysis
The system losses are calculated by inputting the necessary information to the system
model. The following figure shows the flow of loss calculation. Therefore, it is
necessary to maintain the system model and properly input information in order to
calculate the system losses correctly. The outline of each data arrangement is described as
follows.
¾ Network data
The system model is composed of such network data as the distribution transformer, the
distribution line and so on. This network needs to be updated constantly because of the
changing facilities such as the new customer connections and improvement work.
Therefore, it is necessary to properly renew the system model, in case the distribution
facilities undergo changes.
It is easy to renew the system model to suit the contents of the construction, because
SynerGEE has a mapping function. Also by using Middlelink, which is a function added
to SynerGEE, it is easy to partially add and change new facilities to the system model.
Therefore, the TA Team proposed the O&M methodology for the network data
arrangement by using these SynerGEE functions.
z Load data
The load data is the energy consumption data of each customer. Given that this data is
necessary to calculate electricity rates, each EC acquires and is properly managing this
data properly. Furthermore, this data is easily available for the system loss calculation
by using Middlelink. The TA Team described this methodology.
5-10
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(3) Identifying countermeasures to prevent technical losses for the low
voltage system
(a) Methodology of calculation of the operating status of the low voltage system
It is necessary to properly grasp the operating status of each of the distribution facilities
in order to identify system loss countermeasures. In this part, we made a proposal on
how to grasp the operating status of the distribution transformer and the low voltage line
which is composed of the low voltage system. At that time, we described the
methodologies by using not only the PowerSolve data but also SynerGEE. Furthermore,
regarding the distribution transformer, we proposed a methodology to create the list
classified by the operating status of the distribution transformer.
(b) Countermeasure options to prevent technical losses caused in the low voltage
system
We proposed 5 items as countermeasure options to prevent technical losses caused in the
low voltage system. Furthermore, we described the contents, target facilities and
effects of the proposed items as follows;
5-11
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Furthermore, we show the specific examples of these options, and describe the
confirmation of the effect of each countermeasure.
The losses consist of the resistance loss from the line and iron/copper losses from the
pole transformers. The criteria of the low voltage system operation to reduce losses are
as follows,
That is becouse the installation span are related to the cross section size of the
conductors.
This means it is very important to install pole transformers (new additions and
replacements) in consideration of the demand density in this area and its demand
increasing rate.
The loss reduction manual should instruct on the appropriate load dividing
measurement by installing new transformers
New TR
SS
Tr1 Tr2
R1 I R4 I1
I=I0-I1 2
R3
New consumer
5-12
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
the supply area. But the real onsite situation is not dependent on these methods. The
criteria of the low voltage line strengthening are not conducted using loss reduction
measures but with a voltage drop limitation.
The TA team discussed the countermeasures against the voltage drop regulation with
ECs and created the manual to include the apropriate contents in these subjects.
Additionally, as the maximum peak load time of the residential load curve of the
Philippines is just a few hours, it is an economical way to accept the short time overload
operation to consider the temperature limitation of the core of the transformer.
The limitation of the tempratures should be carefully decided depending on its
specifications because the overload is closely related to the decrease of the lifetime of
the transformers.
In this study, the TA team held a discussion with the Philippine members on the tolerable
amount of temperature. As a result of the discussion, the TA team proposed the IEEE
index and the transformer size up methodology. They are described in the manual.
5-13
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(e) Installation of amorphous transformers
In recent years, non-load transformer losses expect to be dramatically reduced due to
technical innovation to introduce the amoulphas material to its iron care.
There are many past failures and it makes sense to be apprehensive of the quality of the
amoulphas transformers made in India, because there has been much trouble with them in
the past. But for the past three years Philec, transformer manufactures, has been
producing the amoulphas transformers and shipped them to MERALCO. MERALCO has
a plan to replace the existing silicon transformer to amoulphas in order.
In this study the TA team are considering the fact that Philec company are using the
Japanese amoulphas technology for their materials, and the TA Team gave a presentation
concerning these technologies at the workshop. As a result of the workshop presentations,
there are more reactions from the ECs than we expected and the TA team implemented
the amoulphas pilot project with ISELCO I , PELCO II and FELCO.
Consultation should be held with NEA on the contents of the manual such as on the
effects of there being no special tools and know-how for their maintenance. However it
is expected that there will be a lot of loss reductions with quantitative values.
Furthermore, the TA team tried to encourage the ECs to introduce amoulphas
transformers to reduce their losses.
[ 25kVA(Load 50%) ]
150 No-Load Loss
Load Loss
Amorphous 100
Core 50
Coil 0
SIT AMT
The TA Team described the effects of the verifications for AMDT and the result of the
simulations in the manual according to the pilot project of AMDT donated by JICA.
5-14
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(4) Identifying countermeasures to prevent technical losses for the Medium
voltage system
Generally, if the scale of demand becomes large, installation of 23kV and 35kV is more
efficient than installation of 13.2 kV, because the merit may become large rather than the
increment of cost. Therefore, the TA Team ran a simulation and proposed the loss
reduction project, which includes upgrading the voltage level from 13.2 kV to 23 kV.
The contents are the “Methodology of the Calculation of the Operating Status of the
Medium Voltage System”, “Options of countermeasures to prevent technical losses caused
in the medium voltage system”, “Criteria for implementing countermeasures of the
medium voltage system” and “Appropriate sizes of conductors”. Furthermore, the TA
team showed specific examples of these options, and described the confirmation of the
effects of each countermeasure.
¾ Step 1: In the poor performance EC, more than half of the system losses are
piliferages and these ECs focus on the measuremants to reduce non technical losses.
5-15
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
¾ Step 2: It is difficult to reduce non-technical losses to less than several percentages,
the ECs try to reduce the technical losses as the next measurements.
%
30
% 1) Reduce Non-Tech
25
Target ECs
20
15 2) Reduce Tech Non‐Tech Loss
15 11
Tech Loss
5
10
3
5 9 9 9
6
0
15%-20% 10%-14% Single Digit
D
21% & above C B A
SL Categories
Most of the selected seven ECs in this project are categorized into the ECs of which
system losses are about 10-14%. They conduct the measurements to achieve a single digit
loss rate to reduce both technical and non-technical losses.
All these seven ECs gave presentations of their loss reduction measurements in the
workshop to share the good practices in other ECs, and many ECs already know the
proper measurements to reduce especially non-technical losses. Here are the concrete
measurements conducted in many ECs.
5-16
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
In addition, the TA team made a presentation referring to the lessons of loss reduction in
Brazil. This information is very useful in Philippine, because the slum situation is very
similar in both countries. Moreover, electric meters are expected to be one of the most
effective measurement tools to reduce losses also in the Philippines.
In the second JCC on the 7th, February, both JICA and the Philippine side agreed that
the manual to reduce non-technical losses would be made mainly per the Philippine side,
and according to that agreement NEA described chapter 8, which is the non-technical
loss reduction part.
In addition, the TA Team gave the following format of the good practices for system loss
reduction. At the second and third workshop, each EC presented the good practices to
achieve system loss reduction. That provided a good opportunity to know the other EC
good practices to achieve system loss reduction. These good practices are part of the
System Loss Reduction Manual.
Moreover, the TA Team proposed the system for lateral spread of the good practices to
achieve system loss reduction in collaboration with NEA.
5-17
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Figure 5-5 Format of the g ood practices for system loss reduction
5-18
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
5.2.6. The pilot projects installing AMDT
The TA Team proposed three pilot projects which will install AMDT at ISELCO I, PELCO II
and FELCO. The details of the projects are described as follows.
In the Philippines, the load rates of the pole transformers are relatively low, and it is
expected that the introduction of amorphous transformers to replace the aged SiFe
transformers will have a big effect in reducing the distribution losses. The TA team
proposed the pilot project to PELCO II that will supply power to the Pampanga area.
PELCO II shows the favorable interests in the amorphous transformers and they can check
the transformer performance using the testing facilities by themselves.
Moreover, the TA team proposed the same pilot project to ISELCO I and FELCO that
have the same kind of testing equipment for the transformers. They also show favorable
interests in the amorphous transformers and they can check the transformer performance
using the testing facilities by themselves too.
Additionally, the Japanese manufacturer HITACHI has a dominant market share of the
material core part of the AMDT. They positively supported this project to accept the
counterpart training in Japan. In this way, this pilot project will promote the introduction
of Japanese technology and products to the Philippines.
5-19
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
The vilification of the actual system simulation will be mentioned in Chapter 5.2.6 Section (3)-
(b)
Non-load test
The no-load loss and the no-load current shall be measured on one of the windings at rated
frequency and at a voltage corresponding to rated voltage. The remaining winding or
windings shall be left open-circuited.
A :電流計
A
W
Power
電源 V 一次側 V :電圧計
二次側
Source
W :電力計
W
Power
電源 V 一次側 二次側 A
Source
5-20
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(b) Specification of AMDT
Phase: Single
Cooling System: Oil Immersed (OA)
Frequency: 60Hz
Primary Side: Double primary bushing with bushing connector
that can accommodate up to No.1/0 size of wire
Primary Voltage: 13200/7620 Volts
Secondary Side: Triple secondary bushing with bushing connector
that can accommodate up to No.4/0 size of wire
Secondary Voltage: 240/120 Volts
HV Winding BIL: 95/95
LV Winding BIL: 30/30
Primary Taps, KV: 2.5%, 2A2B
% Impedance @85 deg C: 1.75 - 2.25%
5-21
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(3) The Confirmation of the AMDT Effects
(a) The Result of Transformer Unit Test (Rated Condition)
The Transformer Unit Test in rated condition was conducted by EC to compare the core
and cupper loss between AMDT and SiFe.
Because of this test, it was confirmed that the losses by AMDT was about 20% lower than
that of SiFe at all the three ECs.
5-22
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
The transformers should be replaced or upsized when it is overloaded or when they exceed
their age limits. In this model case, the TA Team has verified economically which
transformers were the best to be replaced when existing 10kVA transformers were
overloaded.
The hourly load data of the existing 10kVA transformers are as in Figure 5-6. The TA
team simulated the core loss and copper loss from this load curve and described in the
table 5-8.
KW
16 Model Load Curve_DT
14
12
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
AM PM
5-23
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Table 5-8 Comparison of core loss and copper loss of each DT capacity
The core loss is constant depending on the load, but the copper loss is proportional to the
square of the load.
Actual Copper Loss [W] = Percent loading 2 * Rated Copper Loss [W]
Annual Energy Loss [W] = (Actual Copper Loss [W] + Core Loss [W]) × 8760[H]
The cost can be calculated by multiplying the wholesale cost at 5 pesos. The present value
cost after 30 years is as follows,
PW Cost of Energy Loss [PHP] = Annual Cost of Energy Loss*(((1+10%) 30 -1) / 10% /
(1+10%) 30 )
5-24
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
The results of the simulation, 15kVA AMDT is the most economical for the replacement.
Using the same precondition data above, as shown in the table **, AMDT is more
economical than SiFe after about 5 years in each capacity of the transformers. JICA
explained this result to not only three ECs but also all the ECs in the workshop and in the
manual.
JICA convinced them to understand the results of this pilot project that AMDT is more
economical than they previously expected.
Considering the fact that MERALCO is accelerating the introduction of AMDT to replace
all the aged transformers, NEA also strongly believes that AMDTs are effective and the
existing transformers should be replaced in the near future, and NEA will recommend
AMDT to EC as well.
180,000
50kVA
160,000
37.5kVA
140,000 10kVA
PW Total Cost [peso]
120,000 25kVA
15kVA
100,000
80,000 SiFi
AMDT
60,000
40,000
0 5 10 15 20 25 30
[years]
5-25
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
For work preparation to support the planning of full-scale F/S for the upgrading of an MV
network, the TA team evaluated the feasibility of upgrading the MV network.
¾ Based on a feasibility of the project and our interview to the EC, ISELCO I’s plan
was selected for the detailed evaluation for upgrading project.
5-26
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
5-27
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(4) ISELCO I
Original Plan
¾ As shown in the next figure, four big loads were planned and will be supplied by
the MV feeder from the Mercedes substation. The loads are two big mills, Isabela
medical hospital, and a shopping mall. The expected demand of each load is around
0.4MW.
¾ Additionally, from ISELCO I’s estimation, the base load of the substation is
increasing annually at about 3.8%. The estimated demand for the substation in year
2014 is 4.992MW.
¾ The original plan by ISELCO I is to replace the transformer at the R. Mercedes
substation. The 5MVA transformer will be replaced by the 10MVA transformer.
5-28
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Evaluation models
¾ To evaluate, two evaluation models are set. Case 1 is the 13.2kV and case 2 is the
23kV model. ISELCO I provided us with the SynerGEE data of the whole R.
Mercedes substation and from the data, we created the SynerGEE data to evaluate
each case and get the results.
¾ The next table shows an outline of each case and the figure shows the outline of
the MV line.
*Dotted red line indicates the newly installed MV line from R.M. SS.
Evaluation result
¾ The next table shows the results of the simulation. The initial cost for case 1 is
25.9 M PHP and for case 2 is 29.8M PHP. The cost of the losses for over 15years for
case 1 is 38.2 M PHP and for case 2 is 29.4 M PHP. Finally, the total cost for 15years
for case 1 is 64.1 M PHP and for case 2 is 59.2 M PHP.
¾ From this evaluation, we verified that case 1 costs more due to the losses. To apply
the 23kV system voltage, we could reduce the losses occurring in the MV system.
Even the initial cost for a 23kV is high, because of the loss reduction, the total cost
for 23kV is less expensive.
5-29
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
¾ As shown in this evaluation, the project for R. Mercedes should be conducted with
the 23kV system upgrading. This is only one example, but if the big new loads are
planned on the same feeder and there is space to construct a new feeder for 23kV, in
many cases, applying a 23kV system will be cost effective.
5-30
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
5-31
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
5-32
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
6-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Table 6-1 Category of targeted EC and comments
6-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
workshops and AMDT pilot projects. Therefore, they have learned the necessary
technical requirements necessary to conduct a quantitative evaluation of the system
losses .
¾ For improvements in the capability of the quantitative evaluation of the system
losses and data management, power distribution system analysis software
(SynerGEE) was introduced, and software training was provided, and strove to
improve the capabilities of the NEA engineers and the 7ECs. As a result, it
reached a level where they are able to come up with a proposal on their own for a
system loss reduction project using SynerGEE.
¾ The quantitative evaluation of the system losses and data management and system
losses were put into practice through the AMDT pilot project. As a result, they
reached a level where they were able to conduct evaluations on their own of the test
results of the transformer and an evaluation of the loss reduction effects.
6-3
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
the discussion, the support system to upgrade the present medium voltage was
included in the system loss reduction manual. For this reason, the support system to
upgrade the present medium voltage was created also in collaboration with NEA and
7ECs.
¾ The technique to upgrade the present medium voltage was guided through the
meetings with the counterparts, the field meetings with the 7EC engineers and four
workshops. Therefore, they have learned the necessary technical requirements
necessary for the upgrading of the present medium voltage .
¾ The model case of upgrading the medium voltage line was introduced to all ECs, and
the technical instructions on the criteria and the method of the upgrading was carried
out. As a result, it is expected that the system loss reduction project, which includes
the upgrading of the medium voltage line at some ECs will be proposed from now on.
(1) ISELCO I
¾ They tackled the AMDT pilot project.
¾ 22 engineers participated in the SynerGEE software training.
¾ Two engineers participated in the Counterpart Training in Japan.
(2) PELCO II
¾ They tackled the AMDT pilot project.
¾ 22 engineers participated in the SynerGEE software training.
¾ Two engineers participated in the Counterpart Training in Japan.
(3) FLECO
¾ They tackled the AMDT pilot project.
¾ 25 engineers participated in the SynerGEE software training.
¾ Two engineers participated in the Counterpart Training in Japan.
(4) CASURECO II
¾ 19 engineers participated in the SynerGEE software training.
¾ Two engineers participated in the Counterpart Training in Japan.
6-4
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
(5) CASURECO IV
¾ 11 engineers participated in the SynerGEE software training.
¾ One engineer participated in the Counterpart Training in Japan.
(6) SORECO I
¾ 21 engineers participated in the SynerGEE software training.
¾ Two engineers participated in the Counterpart Training in Japan.
%
26.00
24.00
ISRECO I
22.00
PELCO II
20.00 FLECO
18.00 CASURECO II
CASURECO IV
16.00
SORECO I
14.00 LEYECO III
12.00 All EC
10.00
8.00
Year
2004 2005 2006 2007 2008 2009 2010 2011
Figure 6-1 Trend of the system loss rate in the seven targeted ECs
6-5
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Time
60
50 ISRECO I
PELCO II
40 FLECO
CASURECO II
30 CASURECO IV
SORECO I
20 LEYECO III
All EC
10
0 Year
2004 2005 2006 2007 2008 2009 2010 2011
8,000Min.
7,000
6,000 ISRECO I
PELCO II
5,000
FLECO
4,000 CASURECO II
CASURECO IV
3,000
SORECO I
2,000 LEYECO III
All EC
1,000
0 Year
2004 2005 2006 2007 2008 2009 2010 2011
The system loss rate in the seven targeted ECs has been decreasing and can expect more
of a decrease using the created system loss reduction manual from now on.
The achievement of an “Objectively verifiable indicator” for the “Overall Goal”, which
means overall system losses of 13.87% (yearend 2008) being reduced to a single digit
level by 2015, is also expected.
On the other hand, although all EC’s on average show an almost fixed tendency with
regards SAIFI and SAIDI, which are indexes relevant to electric supply reliability, in the
6-6
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
individual seven targeted ECs, the per-year fluctuation is large and reflects the specific
impact from typhoons etc. Therefore, future predictions are difficult.
Overall system
13.87% 11.87% less than 10%
losses
Three objectively verifiable indicators to the project target on PDM are as follows.
The selected EC can segregate non-technical loss and technical loss.
Power distribution system plan is made by EC’s own capacity.
Power system is analyzed, and its problems are resolved by EC’s.
Each targeted EC can introduce the proposal that contain the three above-mentioned
objectively verifiable indicators at the workshop through the AMDT pilot project,
SynerGEE training, and model case analysis of the 23kV up grading. This point is an
achievement of this project. It is thought that it is a cause of the improvement in a
category of the targeted EC as shown in Table 6-1.
6-7
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
The main purpose of this Project is to provide the necessary support to improve the skills
for the loss reduction planning and NEA and EC technology. The System Loss Reduction
Manual has been prepared and a support system for the quantitative evaluation of system
losses using the distribution analysis software was established. The voltage upgrading of
the medium voltage systems was preliminary studied and its technical guidelines were
recommended in the Manual. The pilot projects of the adoption of amorphous
transformers were executed to confirm its effects on loss reductions.
We expect that the outputs of this Project will be reflected into the policy and plans of the
distribution system loss reductions of EC and NEA.
We have attempted to make this manual easier to use by showing the criteria or
indications to achieve technical loss reductions. The reason for this is that it is sometimes
very difficult for the staff to quantitatively understand the effectiveness of the technical
loss reductions due to their large number of options.
We put the utilization of the distribution analysis software with the distribution system
images to the conditions for loss analysis to have an adequate grasp of the distribution
losses. The methodologies of the required data arrangement are also described such as the
distribution facility data and load data. The methodologies of the identification of those
places where technical losses occur and obtaining a numerical understanding are
explained using this software.
The manuals describe the adoption of larger size conductors, a recommendation of the
selection of the appropriate transformer sizes, the criteria for the application of 23 kV, the
loss reduction effects of the amorphous transformers with small core losses and the
recommended cases for their applications and a summary of the activities for non-
technical loss reductions by NEA and ECs. This manual prepares the criteria
corresponding to the amount of the peak loads that can be grasped by the distribution
analysis software.
7-1
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
On the other hand, this manual also takes the role of a guide to show an adequate way of
thinking about the technical considerations of loss reduction. We recommend that ECs
understand its meaning and that NEA and the ECs establish an institutional promotion
system of the manual. The reason is to be able to implement its recommendations and
implement revisions in the case of a situation change such as an increase in the power
generation costs or the re-arrangement of the steps for the voltage upgrades owing to
urbanization.
Overall, it cannot be said that the power distribution system losses of the ECs have been
sufficiently reduced. There is still much room for improvement in the area of power
distribution losses.
We recommend that many loss reduction plans should be looked into that are able to yield
benefits far exceeding the costs for its measures by utilizing this Manual.
We expect that each EC will achieve more of a loss reduction by utilizing this software
and the aforementioned Manual thorough the expansion of the data input to SynerGEE
under the support of NEA.
We recommend that the database be maintained and periodically revised such as the
geographical information, specification of facilities and the load data to promote the
making of the models of the actual distribution system for using the distribution analysis
software.
7-2
The Project on System Loss Reduction for Philippine Electric Cooperatives (ECs)
Thus, we recommend that detailed studies be implemented to evaluate the candidate sites
of the 23 kV upgrading regarding their feasibility and the costs and benefits brought about
by the loss reduction.
7-3