Lean Construction: Unit 1: Variation in Production Systems
Lean Construction: Unit 1: Variation in Production Systems
Little's Law :First proved by John Little in 1961, Little's Law is often taught in
conjunction with queuing theory. The law says that the average number of
customers in a stab le system (over some time interval) is equal to their
average arrival rate, multiplied by their average time in the system. Little's Law
holds when WIP, throughput, and cycle time represent long-term averages of a
stable system and are measured in consistent units.
–
Session Summary
• Workflow is the progression of work within a trade or from one trade to
another
• To improve the total system performance, we must improve the
throughput of the system, not just improve individual pieces
• Reducing workflow variation:
– Makes project outcomes more predictable
– Simplifies coordination between trades
– Reveals new opportunities for improvement
• In a batch-and-queue system each production stage creates more than one
piece at a time, creating a queue.
• Batch-and-queue systems are a form of push systems.
– In a push system everything is “pushed” through at a predetermined
schedule.
• In continuous-flow systems each stage of production is done sequentially.
• Continuous-flow systems are a form of pull systems.
– In a pull system work releases based on downstream demand.
• Little's Law captures the dynamics of changing WIP levels in either system.
This law offers a long-term relationship between WIP, throughput, and
cycle time of a production system in steady state.
Process Design
(How to assemble)
Product Design
(What will be built)
Work-structuring
Supply Chain
(How to
buy/fabricate)
2-5
How Is LWS Different?
• Much of what we do now is workarounds
• First Run Studies
– A cross-functional team tries to establish a standard to meet or beat
execution of that operation
– Follows the Shewhart plan-do-check-act cycle
• LWS vs. Constructability
– Constructability is a reaction to design, LWS is an influence on design
• LWS vs. Work Breakdown Structure (WBS)
WBS:
– is the progressive breaking down of a project into its component
parts
– It assumes that optimizing the parts will optimize the whole
LWS :
– is concerned with the whole, not the individual parts
Operation
Install Studs
Inspections
Processing
Handling
Wait
Install Electrical
Process
Processing
Inspections
Handling
Wait
Hang Drywall
Inspections
Processing
Handling
Wait
2-10
2-11
2-12
Lean Workstructuring Participants
• Who should be doing this?
– General and specialty contractors
• Project manager
• Foreman
• Team leader
– Supplier
– Owner (contract permitting)
– Architect (contract permitting)
Products of LWS: Operation Level
• Rough cut operations designs
– Decision to cast-in-place vs. precast
• Detailed operations designs
– How to form, rebar, and pour basement walls
– First run studies are utilized:
• Sequencing
• Material availability
• Video taping
Other Products of LWS
• Project organizational/contractual structure
– Each “chunk” of work is designed so that it:
• Can be produced rapidly and for a low cost
• Supports optimizing at the project level
• Delivers value to the customer and producer
• Supply chain configurations
– Look at how the project is connected to the external production
systems — Will it support just in time delivery?
Session 1 Summary
The pull planning simulation in this session illustrated the contrast between the
concepts of push and pull.
A push plan: is typically produced by a single entity, with little to no involvement
of those executing the work. This method results in a plan full of assumptions
about means and methods that usually is not reflective of what activities really
will take place.
A pull plan : is produced by those who will actually execute the work via active
collaboration and coordination. The pull plan is developed by working backward
from a target completion date, with tasks defined and sequenced as completion
of
one task releases work to begin on a subsequent task.
Session 2 Summary
• Lean Work structuring is the process of determining who will do what,
when, and how.
– The most benefit occurs when those decisions are made during early
design stages.
• Constructability is a reactive process to established designs.
• Work Breakdown Structure is good for understanding a project but not for
planning its execution.
Session 3 Summary
• The Last Planner System (LPS) is a project planning and production control
system.
– It is based on a collaborative and commitment-based process that
addresses should-can-will-did planning.
• LPS is comprised of different levels of planning:
– Master schedule
– Phase schedule
– Make-ready plan
– Weekly work plan
– Daily huddles
• PPC is a measure of the production planning reliability of the entire site, not
only a particular trade.
Unit 3 Course Summary
• Pull planning allows each party to make its own construction commitments
rather than being told what they are.
• Assumptions and constraints come out in pull planning sessions, leading to
better understanding of the project.
• Lean Workstructuring develops and aligns the project’s process design with:
– Engineering design
– Supply chain capability
– Resource allocation strategies
– Assembly efforts
• Lean Workstructuring is production system design.
• The LPS uses pull planning and Lean Workstructuring to develop different
levels of detailed work plans.
– Master, phase, make-ready, and weekly work
• The LPS results in more reliable workflow and can be used in design and in
construction.
– Coordinates action between specialists who will execute the work
• Percent plan complete (PPC) is an important metric to measure the
reliability of the production planning system.
Session 2 Summary
• Many different ways to show the schedules – sticky notes, spreadsheets,
etc.;
• Collaborative process and dialogue among subcontractors is key;
• GC no longer dictates the schedule.
• Push plans:
– Are typically produced by a single entity with little to no involvement
of those executing the work
– Result in a plan full of assumptions about means and methods that
usually is not reflective of what really will take place
• Pull plans:
– Are produced by those who will execute the work
• The executors will engage in production system design by
virtue of being present and the clear need for coordination.
– Are developed by working backward from a target completion date,
with tasks defined and sequenced so that their completion releases
work to begin on a subsequent task