Project Planning (Part III) Lecture 7
Project Planning (Part III) Lecture 7
(Part III)
Lecture 7
Learning Outcome
At the end of this class, students will be able to:
• conduct the forward and backward of a network diagram in date
form.
The different relationships (date form)
• Finish-to-Start (FS)
Activity A Activity B
FS
Duration Duration
(3 days) (4 days)
(3 days) (4 days)
The different relationships (date form)
• Start-to-Start (SS)
Activity A Activity B
SS
Duration Duration
(2 days) (3 days)
(2 days) (3 days)
The different relationships (date form)
• Finish-to-Finish (FF)
Activity A Activity B
FF
Duration Duration
(1 days) (4 days)
(1 days) (4 days)
The different relationships (date form)
• Start-to-Finish (SF)
Activity A Activity B
SF
Duration Duration
(2 days) (2 days)
Activity A
SF5
Duration
(2 days) LF
6
Example
Perform the forward and backward pass for the following network (using date form), and determine
the TF and FF for each activity. Assume that the project begins on 1 September 2020, where everyday
is a working day, except for Sunday.
1
3
4 3 4
Exercise
A small renovation project has been planned as follows (as given in the table). Based on that, please provide
answers to the following questions:
i. When will the project end?
ii. What is the immediate effect to the project, if the subcontractor for Activity B could not complete the task
within the given time frame of 5 days?
iii. If contractor C delays the completion of the task by 2 days, will it have any effect on the following activities?