0% found this document useful (0 votes)
39 views10 pages

Project Planning (Part III) Lecture 7

This document provides information about project planning, specifically conducting forward and backward passes on a network diagram. It defines different relationship types used in network diagrams like finish-to-start, start-to-start, and finish-to-finish. Examples are given to demonstrate how to perform forward and backward passes to determine earliest and latest dates. An exercise is included with a sample project plan to answer questions about project end date, impact of delays, and effects on subsequent activities.

Uploaded by

amiruddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views10 pages

Project Planning (Part III) Lecture 7

This document provides information about project planning, specifically conducting forward and backward passes on a network diagram. It defines different relationship types used in network diagrams like finish-to-start, start-to-start, and finish-to-finish. Examples are given to demonstrate how to perform forward and backward passes to determine earliest and latest dates. An exercise is included with a sample project plan to answer questions about project end date, impact of delays, and effects on subsequent activities.

Uploaded by

amiruddin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Project Planning

(Part III)
Lecture 7
Learning Outcome
At the end of this class, students will be able to:
• conduct the forward and backward of a network diagram in date
form.
The different relationships (date form)
• Finish-to-Start (FS)

Activity A Activity B
FS
Duration Duration

(3 days) (4 days)

• Finish-to-Start with Lag (FS2)


Activity A Activity B
FS2
Duration Duration

(3 days) (4 days)
The different relationships (date form)
• Start-to-Start (SS)
Activity A Activity B
SS
Duration Duration

(2 days) (3 days)

• Start-to-Start with Lag (SS3)


Activity A Activity B
SS3
Duration Duration

(2 days) (3 days)
The different relationships (date form)
• Finish-to-Finish (FF)

Activity A Activity B
FF
Duration Duration

(1 days) (4 days)

• Finish-to-Finish with Lag (FF3)


Activity A Activity B
FF3
Duration Duration

(1 days) (4 days)
The different relationships (date form)
• Start-to-Finish (SF)

Activity A Activity B
SF
Duration Duration

(2 days) (2 days)

• Start-to-Finish with Lag (SF5)

Activity A
SF5
Duration

(2 days) LF
6
Example
Perform the forward and backward pass for the following network (using date form), and determine
the TF and FF for each activity. Assume that the project begins on 1 September 2020, where everyday
is a working day, except for Sunday.

1
3

4 3 4
Exercise
A small renovation project has been planned as follows (as given in the table). Based on that, please provide
answers to the following questions:
i. When will the project end?
ii. What is the immediate effect to the project, if the subcontractor for Activity B could not complete the task
within the given time frame of 5 days?
iii. If contractor C delays the completion of the task by 2 days, will it have any effect on the following activities?

Activity Duration Predecessor


A 4 -
B 5 A
C 6 A
D 7 A
E 1 B,C
F 3 C,D
G 7 E,F
Discussion
The End

You might also like