Example 1: Generation of A Bearing Graph For An Open End Diesel Hammer
Example 1: Generation of A Bearing Graph For An Open End Diesel Hammer
1.1 Situation
A 45 ton design-load pile is to be driven through a loose non-cohesive layer
into a dense, coarse sand with gravel. The contractor wants to use an HP
12x53 profile of 40 ft (12.2 m) length and a Delmag D-12 hammer. He uses a
standard 12 x 12 inch (305 x 305 mm) helmet with 2 inches (50.8 mm) of
Conbest.
1.2 Problem
Determine the relationship between blow count and both capacity and stress
maxima.
1.3 Approach
Since extensive static and dynamic testing will be performed at the site, a
safety factor of 2 is sufficient. A higher safety factor of maybe 2.5 or 3 may
otherwise be appropriate. Using a safety factor of 2, the pile has to be driven
to an ultimate capacity of 90 tons (180 kips) or 801 kN. A curve, called
Bearing Graph, can be constructed for the desired range if capacities of 60,
120, 180, 240, 300, 360, 420, 480, 540, and 600 kips (267, 534, 801, 1068,
1334, 1601, 1868, 2135, 2402, and 2669 kN) are analyzed.
Click on the Units Option if it shows SI when English units are desired or
vice versa.
Click File/New to open a blank Main Input Form and to start the input
wizard. The input wizard will automatically display the necessary input forms,
which include the Job Information, Select Hammer, Analysis Type, Pile Input,
Hammer Cushion, Soil Profile Input, Soil Parameter Input, and Ultimate
Capacity screens, unless the user selects Finish or Cancel. Enter the
following inputs in the corresponding screens if using the input wizard
(recommended) or proceed with the following commands if opting not to use
the input wizard.
mk:@MSITStore:C:\Program%20Files%20(x86)\PDI\GRLWEAP%202010\GRLWE... 25.11.2016
Example 1: Generation of a Bearing Graph for an OED Page 2 of 5
Move to the Pile material box and click on Steel for the pile material. This
will generate pile material defaults for elastic modulus and specific weight. In
the Pile Information box, enter the Length (40 ft or 12.2 m). Enter the
Penetration depth (say also 40 ft or 12.2 m even though that is not a very
practical situation since normally the pile is left out of the ground at least 2 ft
or 0.6 m at the end of driving). This penetration input is, however, only used
for the simple resistance distribution input and therefore not much demand is
placed on its accuracy. Enter the pile Section Area, Toe Area and
Perimeter with F3button (while the cursor is on one of the input fields).
Choose H pile and select HP 12x53. All these parameters will be automatically
filled.
(You may set the Coefficient of Restitution for the pile top spring (the helmet-
pile interface) to a value less than the normal default of 0.85 (e.g., 0.8 to
reflect the fact that the pile top surface may be rough cut). The Coefficient of
Restitution for the pile top spring is found under Options/Pile
Parameters/Additional Input and should not be confused with the
coefficient of restitution of the hammer cushion found on the Main Input
screen.
mk:@MSITStore:C:\Program%20Files%20(x86)\PDI\GRLWEAP%202010\GRLWE... 25.11.2016
Example 1: Generation of a Bearing Graph for an OED Page 3 of 5
system.
Move to Soil Parameters . These are average shaft values and individual
toe values for quake and damping.Shaft Quakesare almost always 0.1
inches or 2.5 mm.Toe Dampingis almost always 0.15 s/ft or 0.5 s/m. The
Toe Quake may increase with the size of piles but in our example of a 12
inch (305 mm) the toe quake rule of D/120 (actually only recommended for
very dense or hard soils, otherwise D/60 would be better) leads to the
standard quake of 0.1 inches or 2.5 mm. This is strictly applicable only for a
plugged H-Pile; however, for an unplugged H-Pile, the standard toe quake
recommendation is also 0.1 inches or 2.5 mm.Shaft Damping depends on
the soil type. For non-cohesive soils, the recommendation is 0.05 s/ft or 0.16
s/m.
This completes the input. However, you may now wonder whether more data
is required. To check whether or not all important data has been submitted,
click Options/Check Status. If the answer is "Input file appears to be
complete", you may move to saving the file and analyzing the data. If not,
then another message will indicate the missing information.
mk:@MSITStore:C:\Program%20Files%20(x86)\PDI\GRLWEAP%202010\GRLWE... 25.11.2016
Example 1: Generation of a Bearing Graph for an OED Page 4 of 5
1.6 Analyze
Click File/Analyze Input and a Window will open that gives some
information on the analysis progress. Once the analysis is finished, exit this
window by pressing any key to continue.
mk:@MSITStore:C:\Program%20Files%20(x86)\PDI\GRLWEAP%202010\GRLWE... 25.11.2016
Example 1: Generation of a Bearing Graph for an OED Page 5 of 5
are all acceptable values: a moderate blow count and a compressive stress
well below yield. Note, confirmation of the actual bearing capacity should be
done some time after pile installation by either static testing or dynamic
testing using a Pile Driving Analyzer® during restrike.
mk:@MSITStore:C:\Program%20Files%20(x86)\PDI\GRLWEAP%202010\GRLWE... 25.11.2016